KR101066837B1 - Lifting and bearing apparatus preventing fracture on the pier or abutment of bridge - Google Patents

Lifting and bearing apparatus preventing fracture on the pier or abutment of bridge Download PDF

Info

Publication number
KR101066837B1
KR101066837B1 KR1020110013966A KR20110013966A KR101066837B1 KR 101066837 B1 KR101066837 B1 KR 101066837B1 KR 1020110013966 A KR1020110013966 A KR 1020110013966A KR 20110013966 A KR20110013966 A KR 20110013966A KR 101066837 B1 KR101066837 B1 KR 101066837B1
Authority
KR
South Korea
Prior art keywords
bridge
plate
horizontal
jack
support
Prior art date
Application number
KR1020110013966A
Other languages
Korean (ko)
Inventor
심규숙
Original Assignee
심규숙
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by 심규숙 filed Critical 심규숙
Priority to KR1020110013966A priority Critical patent/KR101066837B1/en
Application granted granted Critical
Publication of KR101066837B1 publication Critical patent/KR101066837B1/en

Links

Images

Classifications

    • EFIXED CONSTRUCTIONS
    • E01CONSTRUCTION OF ROADS, RAILWAYS, OR BRIDGES
    • E01DCONSTRUCTION OF BRIDGES, ELEVATED ROADWAYS OR VIADUCTS; ASSEMBLY OF BRIDGES
    • E01D22/00Methods or apparatus for repairing or strengthening existing bridges ; Methods or apparatus for dismantling bridges
    • EFIXED CONSTRUCTIONS
    • E01CONSTRUCTION OF ROADS, RAILWAYS, OR BRIDGES
    • E01DCONSTRUCTION OF BRIDGES, ELEVATED ROADWAYS OR VIADUCTS; ASSEMBLY OF BRIDGES
    • E01D19/00Structural or constructional details of bridges
    • E01D19/04Bearings; Hinges

Landscapes

  • Engineering & Computer Science (AREA)
  • Architecture (AREA)
  • Civil Engineering (AREA)
  • Structural Engineering (AREA)
  • Bridges Or Land Bridges (AREA)

Abstract

교량 상부구조의 종방향 및 횡방향 이동을 용이하게 제어하여 교량받침 기능을 가질 수 있으면서도 안정적으로 교량 상부구조를 인상할 수 있도록 한 교량용 인상장치에 관한 것으로서 상기 교량용 인상장치는 상기 브라켓부는 교량 하부구조(B1)의 상면에 접하여 서로 횡방향으로 이격되도록 설치되되 교량 하부구조의 상단 모서리부의 파괴전단면(C1)을 지나도록 연장되어 교량 하부구조(B1) 상면에 형성된 걸림홈(112)에 일단부 저면에 형성된 걸림구가 걸려지도록 설치된 양 수평지지판과 상기 양 수평지지판의 타단부 저면에 하방으로 연장되어 교량 하부구조의 측면부(C)에 앵커볼트로 고정되도록 설치된 수직지지판; 및 수직지지판 전면 상단에 횡방향으로 연장된 수평판 형태로서 중앙 상면에 인상잭을 수용하는 인상잭용 받침구가 형성된 수평고정판;이 포함된다.A bridge pulling apparatus for stably raising a bridge superstructure while having a bridge supporting function by easily controlling longitudinal and lateral movement of a bridge superstructure, wherein the bridge pulling apparatus includes: In contact with the upper surface of the lower structure (B1) is installed so as to be spaced apart from each other in the transverse direction extends to pass through the fracture shearing surface (C1) of the upper edge of the bridge substructure in the locking groove 112 formed on the upper surface of the bridge substructure (B1) Vertical support plates installed to be fixed to anchor bolts on the side portions (C) of the bridge substructure extending downwards on both horizontal support plates installed at one end of the lower surface and the bottoms of the other ends of the horizontal support plates; And a horizontal fixing plate having a support hole for an impression jack for receiving an impression jack on a central upper surface thereof in a horizontal plate shape extending in a transverse direction on a top surface of the vertical support plate.

Description

받침기능을 보유하고 탈락방지가 가능한 탈착식 교량용 인상장치{LIFTING AND BEARING APPARATUS PREVENTING FRACTURE ON THE PIER OR ABUTMENT OF BRIDGE}Lifting device for detachable bridges with supporting function and preventing falling off {LIFTING AND BEARING APPARATUS PREVENTING FRACTURE ON THE PIER OR ABUTMENT OF BRIDGE}

본 발명은 받침기능을 보유하고 탈락방지가 가능한 탈착식 교량용 인상장치 에 관한 것이다. 더욱 구체적으로 교량 상부구조의 종방향 및 횡방향 이동을 제한된 범위내에서 용이하게 제어하여 교량 상부구조의 인상 중 교량받침 기능을 가질 수 있으면서도 안정적으로 교량 상부구조의 인상상태를 유지 할 수 있도록 한 받침기능을 보유하고 탈락방지가 가능한 탈착식 교량용 인상장치에 관한 것이다.The present invention relates to a lifting device for a removable bridge having a supporting function and capable of preventing falling. More specifically, the longitudinal and lateral movements of the bridge superstructure can be easily controlled within a limited range to support the bridge support function during the pulling of the bridge superstructure while maintaining a stable state of the bridge superstructure. The present invention relates to a removable bridge pulling apparatus having a function and preventing fallout.

일반적으로, 교량(橋梁)은 지지할 시설의 종류와 사용되는 용도에 따라서, 그 종류와 모양이 다양한 구조물로 이루어지고, 그 역할은 교량이 받쳐주는 통로와 시설의 기능을 안전하게 유지하는 것으로서 충분한 강도와 내구성을 갖추어야 한다.In general, bridges consist of structures of various types and shapes, depending on the type of facility to be used and the purpose of use, and its role is sufficient strength to safely maintain the function of the bridge and the facilities that the bridge supports. And must be durable.

이와 같은 교량(1)은 도 1에 도시된 바와 같이, 교량 하부구조(14,16)로서 양측 교대(14)의 사이에 소정의 거리를 두고서 설치되는 다수의 교각(16)과 각 교대(14) 및 교각(16)의 상단에 걸쳐 연속적으로 설치되는 교량 상부구조(12,슬래브 또는/및 거더)로 구성된다.As shown in FIG. 1, the bridges 1 are bridge substructures 14 and 16, and a plurality of bridges 16 and each shift 14 provided with a predetermined distance between both side shifts 14 are provided. And a bridge superstructure 12 (slab or / and girder) that is installed continuously over the top of the bridge 16.

이때 상기 교각 또는 교대(이하 “교량 하부구조” 라 한다.)의 상부에 걸쳐 설치되는 슬래브는 설치 후 작용하는 신축에 따른 팽창 또는 수축을 할 수 있고 교량 상부구조의 하중을 교량 하부구조로 전달할 수 있도록 교각과 슬래브를 지지하는 거더(미도시) 사이에 고정단 교량받침(20a) 또는 가동단 교량받침(20b)이 설치된다.At this time, the slab installed over the upper part of the bridge or the shift (hereinafter referred to as "bridge substructure") can be expanded or contracted according to the expansion and contraction acting after installation and can transfer the load of the bridge superstructure to the bridge substructure. A fixed end bridge bearing 20a or a movable end bridge bearing 20b is installed between the bridge and the girder (not shown) to support the slab.

이와 같은 구성으로 구축된 교량(1)은 설치 후 시간이 경과됨에 따라 여러 가지 형태의 자연적 또는 인위적 요인으로 인하여 교량받침(20a)(20b)이 파손되는 경우가 허다하다.As the bridge 1 constructed in such a configuration, as the time passes after installation, the bridge supports 20a and 20b are often damaged due to various types of natural or artificial factors.

예를 들면, 슬래브의 조인트 부분에서의 누수 등으로 인한 교량받침(20a)(20b)의 부식, 파괴, 교량받침(20a)(20b)의 공용 장기화와 지속적인 외부환경에의 직접적인 노출에 따른 교량받침의 교체 필요성이 발생하게 된다.For example, corrosion of bridge supports 20a and 20b due to leakage at joints of slabs, bridge support due to common prolongation of bridge supports 20a and 20b, and direct exposure to the external environment. The need for replacement will occur.

또한 상기한 예 이외에도 지반의 부등침하 현상으로 인한 교량 하부구조의 안전성 저하와 이로 인한 교량 상부구조(12)의 위치변동, 충격하중으로 파손될 경우에도 교량받침(20a)(20b)의 교체가 필요하다.In addition, in addition to the above examples, the bridge support 20a, 20b is also required to be damaged even when the bridge undercarriage due to uneven subsidence of the ground is deteriorated, thereby causing a change in the position of the bridge superstructure 12 and an impact load. .

이러한 노후화나 손상이 발생한 기존교량받침의 교체시 별도의 인상잭(미 도시)을 사용하여 교량 상부구조(12)를 들어 올리고 보수하는 방법이 이용되고 있다.In the replacement of the existing bridge support in which such aging or damage occurs, a method of lifting and repairing the bridge superstructure 12 using a separate jack jack (not shown) is used.

그러나 이와 같은 종래의 인상장치는 유압잭인 인상잭을 이용하여 교량 상부구조(12)를 들어 올리고 작업을 하기는 하지만, 이러한 인상잭을 단순거치하여 이용하는 경우 인상잭의 기능저하 등에 의해 안정적인 교량 상부구조(12)의 위치고정이 쉽지 않고, 교량 상부구조(12)가 인상잭에 의해 장기간동안 인상되어진 상태에서 일측으로 기울어지는 편심 상태인 경우, 이를 안정되게 지지할 수 없어서 그 기능 이용에 한계가 있을 수밖에 없었다.However, although the conventional lifting device lifts and works the bridge upper structure 12 by using the lifting jack, which is a hydraulic jack, the bridge upper structure is stable due to the functional deterioration of the lifting jack when such a lifting jack is used simply. If the position of (12) is not easy to be fixed and the bridge superstructure 12 is eccentrically inclined to one side after being lifted for a long time by the lifting jack, it cannot be stably supported and there is a limit in using the function. There was no choice but to.

나아가, 인상잭이 설치되는 교량 상부구조의 하부 공간은 통상 매우 협소하기 때문에 교량 하부구조 측면부에 브라켓을 별도 설치하고 상기 브라켓에 유압잭인 인상잭을 설치하는 경우가 많은데, 이럴 경우 상기 브라켓을 교량 하부구조 측면에서 다수의 케미컬 앵커로 고정시키는 방식으로 설치하는 것이 일반적이다.Furthermore, since the lower space of the bridge superstructure on which the impression jack is installed is usually very narrow, a bracket is often separately installed on the side surface of the bridge substructure and an impression jack, which is a hydraulic jack, is installed on the bracket. In terms of construction, it is common to install in a manner of fixing with a plurality of chemical anchors.

하지만 교량 하부구조가 공용의 장기화, 극심한 환경에 지속적으로 노출되어 열화되는 경우가 많기 때문에 케미컬 앵커의 설치 갯수와 상관없이 교량 하부구조 상단 측면부 콘크리트 전단파괴와 이로 인한 브라켓의 탈락으로 인하여 심각한 안전사고 발생 우려가 많았다.However, since the bridge substructure is often deteriorated due to prolonged periods of public use and extreme exposure, severe safety accidents occur due to the concrete shear failure of the upper side of the bridge substructure regardless of the number of chemical anchors and the failure of the bracket. There was a lot of concern.

또한 유압잭인 인상잭을 이용하여 교량 상부구조를 인상할 때 유압잭인 인상잭과 교량 상부구조 접촉면에서 마찰저항이 매우 커서 교량 상부구조의 온도변화에 따른 변위(이동)를 충분히 대응하지 못하여 상기 인상잭의 전도가 발생하는 경우도 많이 발생한다는 문제점이 있었다.In addition, when raising the upper structure of the bridge by using the impression jack, which is a hydraulic jack, the frictional resistance is very high at the contact surface of the hydraulic jack and the upper structure of the bridge, so that the displacement jack cannot sufficiently cope with the displacement due to the temperature change of the bridge superstructure. There was a problem that occurs a lot of conduction occurs.

또한 종래 사용되는 교량보수용 인상잭은 유압펌프에서 유압을 가하여 압력에 의하여 구조물이 인상되는 방식을 채택하고 있으나, 인상 당시에 주어진 유압이 시간이 경과하면 차량 통행 등의 외압에 의하여 잭 내부의 압력이 유실되는 문제가 발생되어 당초에 계획된 높이를 유지할 수 없는 문제점이 있었다.In addition, the conventional jack for bridge repair is adopted to increase the structure by pressure by applying hydraulic pressure from the hydraulic pump.However, if the hydraulic pressure given at the time of pulling is elapsed, the pressure inside the jack is increased due to external pressure such as traffic. There was a problem that the loss of the original planned height was not maintained.

이에 본 발명은 교량 상부구조를 인상시키기 위한 인상잭을 교량 하부구조에 보다 안정적으로 설치할 수 있도록 하여 인상잭을 포함한 브라켓의 탈락을 효과적으로 방지할 수 있고, 온도 변화 등에 의한 교량 상부구조 변위(이동)에 보다 효과적으로 대응할 수 있도록 기존 교량받침과 동일한 기능을 수행함으로서 인상잭의 전도위험을 방지할 수 있어 안전성을 제고할 수 있는 받침기능을 보유하고 탈락방지가 가능한 탈착식 교량용 인상장치 제공을 해결하고자 하는 기술적 과제로 한다.Accordingly, the present invention can more effectively install the lifting jack for raising the bridge upper structure to the bridge substructure to effectively prevent the fall of the bracket including the lifting jack, the bridge upper structure displacement (movement) due to temperature changes, etc. It is possible to prevent the fall hazard of the impression jack by performing the same function as the existing bridge support so that it can respond more effectively to it.It has a support function that can improve safety and provides a removable bridge lifting device that can prevent falling. It is a technical problem.

상기 기술적 과제를 달성하기 위하여 본 발명은According to an aspect of the present invention,

첫째, 교량 상부구조 인상을 위한 브라켓부 설치시 교량 하부구조 측면에서의 케미컬 앵커에 의한 고정뿐만 아니라 교량 하부구조 상면에 예상되는 전단파괴 영역을 지난 위치에 추가적으로 브라켓부가 고정되도록 하여 교량 상부구조의 인상중 안전성을 확보 하였다.First, when installing the bracket part to raise the bridge superstructure, the bracket part is fixed at the position beyond the expected shear failure area on the upper surface of the bridge substructure as well as fixed by the chemical anchor on the side of the bridge substructure. Safety was secured.

둘째, 교량 상부구조의 인상중 온도변화에 의한 종방향 이동량은 슬라이딩판으로 제어하고, 상대적으로 이동량이 거의 발생하지 않는 횡방향 이동에 의한 변위는 경질고무판으로 흡수할 수 있도록 하였다.Second, the longitudinal movement amount by the temperature change during the pulling up of the bridge superstructure was controlled by the sliding plate, and the displacement caused by the lateral movement with relatively little movement amount was absorbed by the hard rubber plate.

이를 위하여 본 발명은To this end,

교량 하부구조의 측면에 설치된 브라켓부에 인상잭을 설치하고 상기 인상잭에 의하여 교량 상부구조를 인상시킨 상태에서 교량 상부구조의 종방향 및 횡방향 이동에 의한 변위를 흡수하는 교량받침 기능을 가진 교량용 인상장치에 있어서,Bridge having a bridge support function that absorbs displacement caused by the longitudinal and transverse movement of the bridge superstructure in the state in which the impression jack is installed in the bracket portion provided on the side of the bridge substructure and the bridge superstructure is raised by the impression jack In the impression device for

상기 브라켓부는 교량 하부구조(B1)의 상면에 접하여 서로 횡방향으로 이격되도록 설치되되 교량 하부구조의 상단 모서리부의 파괴전단면(C1)을 지나도록 연장되어 교량 하부구조(B1) 상면에 형성된 걸림홈에 일단부 저면에 형성된 걸림구가 걸려지도록 설치된 양 수평지지판;The bracket portion is installed to be in contact with the upper surface of the bridge substructure B1 laterally spaced apart from each other but extending to pass through the fracture shear surface (C1) of the upper edge portion of the bridge substructure to form a locking groove formed on the upper surface of the bridge substructure B1 Both horizontal support plates installed at one end thereof so as to catch the locking holes formed at the bottom thereof;

상기 양 수평지지판의 타단부 저면에 하방으로 연장되어 교량 하부구조의 측면부(C)에 앵커볼트로 고정되도록 설치된 수직지지판; 및 A vertical support plate extending downward on bottom surfaces of the other ends of the horizontal support plates and fixed to the side portions C of the bridge substructure to be fixed with anchor bolts; And

수직지지판 전면 상단에 횡방향으로 연장된 수평판 형태로서 중앙 상면에 인상잭을 수용하는 인상잭용 받침구가 형성된 수평고정판;을 포함하는 받침기능을 보유하고 탈락방지가 가능한 탈착식 교량용 인상장치를 제공한다.It provides a lifting device for removable bridges having a support function, including a horizontal fixing plate formed in the horizontal top plate extending in the transverse direction on the front top of the vertical support plate formed with a support jack for receiving jacks on the center upper surface; do.

또한 바람직하게는Also preferably

상기 브라켓부에는 교량받침부가 더 형성되도록 하되 상기 교량받침부는 상기 수평고정판의 볼트홀에 삽입 설치된 압축 앵커볼트;The bracket portion is to be further formed bridge support portion, the bridge support portion compression anchor bolt inserted into the bolt hole of the horizontal fixing plate;

상기 압축 앵커볼트가 교량 상부구조의 인상 중 편심하중 작용 등으로 상부하중을 지지할 경우 압축좌굴에 의한 파괴를 방지할 수 있도록 압축 앵커볼트와 일체화된 좌굴방지용 관;When the compression anchor bolt supports the upper load by the eccentric load action, etc. during the lifting of the bridge superstructure, the buckling prevention tube integrated with the compression anchor bolt to prevent breakage by compression buckling;

상기 압축 앵커볼트의 하부가 수평고정판의 볼트홀을 관통하여 수평고정판의 저면에 체결된 하부 체결너트;A lower fastening nut having a lower portion of the compression anchor bolt penetrated through a bolt hole of the horizontal fixing plate to a bottom surface of the horizontal fixing plate;

볼트홀을 관통하여 상방으로 연장된 상기 압축 앵커볼트의 상부에 체결되도록 하는 상부 체결너트;An upper fastening nut configured to be fastened to an upper portion of the compression anchor bolt extending upward through a bolt hole;

상기 상부 체결너트의 상단부에는 장착된 수평판 형태의 상부받침판:An upper support plate in the form of a horizontal plate mounted on the upper end of the upper fastening nut:

상기 상부받침판의 양 측방 상면에 교량 상부구조의 횡방향 변위를 제어하기 위하여 설치되는 것으로서 상부받침판 양 측방 상면에 볼트홀에 대응한 관통홀이 형성된 하부판과 상기 하부판 내측상면에 상방으로 연장된 수직상부판을 포함하여 구성된 횡방향변위 구속판; 및It is installed to control the lateral displacement of the bridge superstructure on both side upper surfaces of the upper support plate, the lower plate formed with through holes corresponding to the bolt holes on both upper surfaces of the upper support plate and a vertical upper portion extending upward on the inner upper surface of the lower plate. A transverse displacement restraint plate including a plate; And

상기 수평고정판의 볼트홀과 상기 관통홀을 관통하여 횡방향변위 구속판을 구성하는 하부판 상면에서 압축 앵커볼트가 체결되도록 하는 고정너트;를 포함하도록 하는 받침기능을 보유하고 탈락방지가 가능한 받침기능을 보유하고 탈락방지가 가능한 탈착식 교량용 인상장치를 제공한다.A fixing nut for fastening the compression anchor bolts on the upper surface of the lower plate constituting the transverse displacement restraint plate through the bolt hole and the through hole of the horizontal fixing plate; It provides a removable bridge pulling device that can be held and prevented from falling off.

또한 바람직하게는Also preferably

상기 수직 연장된 상부판의 내측면들에는 에폭시와 같은 접착제로 부착된 경질고무판; 및 상기 수평고정판의 저면과 인상잭의 상면에 설치된 황동판으로 제작된 슬라이딩판;을 더 포함하는 받침기능을 보유하고 탈락방지가 가능한 탈착식 교량용 인상장치를 제공한다.Hard rubber plates attached to the inner surfaces of the vertically extending top plate with an adhesive such as epoxy; And a sliding plate made of a brass plate installed on a bottom surface of the horizontal fixing plate and an upper surface of the impression jack.

본 발명에 의하여 인상잭을 수용하는 브라켓을 교량 하부구조에 설치함에 있어 교량 하부구조에 보다 안정적으로 고정시킬 수 있도록 하여 브라켓의 탈락에 의한 교량용 인상장치의 하자발생여지를 현저하게 줄일 수 있을 뿐만 아니라,In the present invention, when installing a bracket for receiving an impression jack on a bridge substructure, it is possible to more stably fix the bridge substructure to significantly reduce the occurrence of defects in the lifting device for a bridge due to the dropout of the bracket. not,

브라켓에 설치된 인상잭의 전도를 방지할 있도록 함으로서 보다 안정적인 교량 인상 및 교량받침 기능을 자체적으로 가질 수 있도록 하여 효율적인 교량 상부구조 인상에 의한 교량 보강이 가능하게 된다.By preventing the fall of the impression jack installed in the bracket to be able to have a more stable bridge lifting and bridge support itself, it becomes possible to reinforce the bridge by efficient bridge superstructure lifting.

본 발명의 범위는 상기 상세한 설명보다는 후술하는 특허청구범위에 의하여 나타내어지며, 특허청구범위의 의미 및 범위 그리고 그 균등 개념으로부터 도출되는 모든 변경 또는 변형된 형태가 본 발명의 범위에 포함되는 것으로 해석되어야 한다.The scope of the present invention is shown by the following claims rather than the above description, and all changes or modifications derived from the meaning and scope of the claims and their equivalents should be construed as being included in the scope of the present invention. do.

도 1은 종래 교량의 시공 종단면도,
도 2a, 도 2b 및 도 2c는 본 발명에 의한 교량용 인상장치의 일부 설치사시도, 조립사시도,
도 3a, 도 3b 및 도 3c는 본 발명에 의한 교량용 인상장치의 사시도, 설치사시도이다.
1 is a construction longitudinal cross-sectional view of a conventional bridge,
Figures 2a, 2b and 2c is a perspective view of the installation, assembly perspective view of the lifting device for a bridge according to the present invention,
3A, 3B and 3C are perspective and installation perspective views of the pulling apparatus for a bridge according to the present invention.

아래에서는 첨부한 도면을 참조하여 본 발명이 속하는 기술분야에서 통상의 지식을 가진 자가 용이하게 실시할 수 있도록 본 발명의 실시예를 상세히 설명한다. 그러나 본 발명은 여러 가지 상이한 형태로 구현될 수 있으며 여기에서 설명하는 실시예에 한정되지 않는다. 그리고 도면에서 본 발명을 명확하게 설명하기 위해서 설명과 관계없는 부분은 생략하였으며, 명세서 전체를 통하여 유사한 부분에 대해서는 유사한 도면 부호를 붙였다.DETAILED DESCRIPTION Hereinafter, exemplary embodiments of the present invention will be described in detail with reference to the accompanying drawings so that those skilled in the art may easily implement the present invention. The present invention may, however, be embodied in many different forms and should not be construed as limited to the embodiments set forth herein. In the drawings, parts irrelevant to the description are omitted in order to clearly describe the present invention, and like reference numerals designate like parts throughout the specification.

< 본 발명의 받침기능을 보유하고 탈락방지가 가능한 탈착식 교량용 인상장치(A) ><Removable bridge pulling apparatus (A) having a supporting function of the present invention and preventing falling off>

도 2a, 도 2b 및 도 2c는 본 발명에 의한 받침기능을 보유하고 탈락방지가 가능한 교량용 인상장치(A)의 일부 설치사시도 및 조립사시도들을 각각 도시한 것으로서 이를 기준으로 본 발명의 교량용 인상장치(A)를 구체적으로 살펴본다.2a, 2b and 2c has a support function according to the present invention Some installation perspective views and assembly perspective views of the bridge pulling apparatus (A) capable of preventing the dropout will be described in detail with reference to the bridge pulling apparatus (A) of the present invention.

먼저, 본 발명의 받침기능을 보유하고 탈락방지가 가능한 탈착식 교량용 인상장치(A)는 브라켓부(100), 인상잭(200) 및 교량받침부(300)으로 크게 구성된다.First, the detachable bridge pulling apparatus (A) having a supporting function of the present invention and preventing falling off is largely composed of a bracket part 100, an impression jack 200, and a bridge support part 300.

상기 브라켓부(100)는 도 2a와 같이 교량 하부구조(B1) 예컨대 종래 교량받침이 설치된 교각 또는 교대의 코핑부에 상기 인상잭(200)과 교량받침부(300)가 안정적으로 설치될 수 있도록 하는 지지장치의 기능을 가지게 되며,The bracket portion 100, as shown in Figure 2a so that the bridge jack (B1), for example, the lifting jack 200 and the bridge support portion 300 can be stably installed in the bridge or the coping portion of the bridge bridge is installed conventionally Will have the function of supporting devices,

상기 인상잭(200)은 도 2a와 같이 교량 상부구조로(B2, 거더 및 슬래브)를 인상시키기 위한 유압잭의 기능을 가지게 되며,The lifting jack 200 will have the function of a hydraulic jack for raising the bridge superstructure (B2, girder and slab) as shown in Figure 2a,

상기 교량받침부는 도 2a와 같이 인상잭(200)에 의하여 인상되면서 교량 상부구조(B2) 저면에 접하여 결국 교량 상부구조를 인상시킨 상태에서 종래 교량받침 기능을 가지는 것이라 할 수 있다.The bridge support portion may be said to have a conventional bridge support function in the state in which the bridge upper structure is in contact with the bottom surface of the bridge upper structure B2 while being raised by the lifting jack 200 as shown in FIG. 2A.

먼저, 상기 브라켓부(100)를 구체적으로 살펴본다.First, the bracket unit 100 will be described in detail.

상기 브라켓부(100)는 기본적으로 교량 상부구조(B2)의 하부와 교량 하부구조(B1)의 상부 공간이 매우 협소하여 인상작업을 위한 인상잭 설치가 불가능한 경우 인상잭(200)을 교량 하부구조(B1)의 측면부(C)에 설치할 수 있도록 설치되는 일종의 지지체의 역할을 하게 된다.When the bracket part 100 is basically a lower space of the bridge upper structure (B2) and the upper space of the bridge lower structure (B1) is very narrow, it is impossible to install the jack jack for lifting work The impression jack 200 serves as a kind of support installed to be installed on the side portion C of the bridge substructure B1.

이때, 상기 교량 하부구조(B1)의 측면부(C)에 있어 상단 모서리부(C1)는 외력에 매우 취약한 부분인데 실제 파괴전단면(C1)에 의한 콘크리트 단부탈락에 의하여 종래 브라켓을 케미컬 앵커로 고정시킴에 따른 하자 발생이 많이 발생한 바 있다.At this time, the upper edge portion (C1) in the side portion (C) of the bridge substructure (B1) is a very vulnerable to external forces, but the conventional bracket is fixed with a chemical anchor by dropping the concrete end by the actual fracture shear surface (C1) Many defects have occurred due to the application.

이에 본 발명은 기본적으로 브라켓을 교량 하부구조(B1)에 확실하게 고정시키기 위하여 교량 하부구조 측면에서의 케미컬앵커에 의한 고정외에 추가적으로 걸림구를 이용하되, 상기 걸림구가 파괴전단면(C1)내에 상기 걸림구(111)가 배치되지 않도록 하였다.Therefore, the present invention basically uses a fastener in addition to the fixing by the chemical anchor on the side of the bridge substructure in order to securely fix the bracket to the bridge substructure (B1), the catch is in the fracture front end surface (C1) The latch 111 is not arranged.

이에 본 발명의 브라켓부(100)는 교량 하부구조(B1)의 상단 모서리부(C1)를 감싸면서 교량 하부구조의 측면부(C)에 접하도록 설치되는 것으로서,The bracket portion 100 of the present invention is installed to be in contact with the side portion (C) of the bridge substructure while surrounding the upper edge portion (C1) of the bridge substructure (B1),

도 2a, 도 2b 및 도 2c와 같이, 교량 하부구조(B1)의 상면에 접하여 서로 횡방향으로 이격되도록 설치되되 교량 하부구조의 상단 모서리부의 파괴전단면(C1)을 지나도록 연장되어 교량 하부구조(B1) 상면에 형성된 걸림홈(112)에 일단부 저면에 형성된 걸림구(111)가 걸려지도록 설치된 양 수평지지판(110);As shown in Figure 2a, 2b and 2c, it is installed so as to be in contact with the upper surface of the bridge substructure (B1) laterally spaced apart from each other extending beyond the fracture shearing surface (C1) of the upper edge of the bridge substructure bridge substructure (B1) both horizontal support plates 110 installed so that the locking holes 111 formed at one end of the lower surface of the locking grooves 112 formed on the upper surface thereof are hooked;

상기 양 수평지지판(110)의 타단부 저면에 하방으로 연장되어 교량 하부구조의 측면부(C)에 앵커볼트(121)로 고정되도록 설치된 수직지지판(120);으로 구성된다.The vertical support plate 120 is extended to the bottom of the other end of the horizontal support plate 110, the vertical support plate 120 is installed to be fixed to the anchor bolt 121 in the side portion (C) of the bridge substructure.

이에 도 2a와 같이 상기 양 수평지지판(110)은 교량 하부구조의 상면에 있어 종래와 달리 케미컬 앵커에 의한 고정방식이 아니라 걸림구(111)에 의하여 걸려지도록 하되,Thus, as shown in Figure 2a the two horizontal support plate 110 is to be caught by the latch 111, rather than the fixing method by the chemical anchor in the upper surface of the bridge substructure,

상기 걸림구(111)는 교량 하부구조(B1)에 핸드 커팅기로 형성시킨 일장형 걸림홈(112)에 걸려지는 방식을 따르게 된다.The latch 111 is to follow the manner of being caught in the one-piece locking groove 112 formed in the bridge substructure (B1) as a hand cutter.

이때 중요한 점은 상기 걸림구(111)가 교량 하부구조의 상단 모서리에 형성된 파괴전단면(C1)을 피하여 종방향으로 연장되도록 형성시킨다는 점이다.At this time, the important point is that the latch 111 is formed to extend in the longitudinal direction avoiding the fracture shear surface (C1) formed in the upper edge of the bridge substructure.

즉, 작업공간이 협소한 곳에서 굳이 케미컬 앵커를 주 고정수단으로 사용하지 않지 않도록 함과 더불어 교량 하부구조(B1)의 열화에 따른 파괴전단면(C1)을 따라 상단 모서리가 파손된다 할지라도 양 수평지지판(110)을 교량 하부구조에 그대로 고정될 수 있도록 한 것이다.In other words, do not use the chemical anchor as the main fixing means in a small space, and even if the upper edge is damaged along the fracture shear surface (C1) due to deterioration of the bridge substructure (B1). The horizontal support plate 110 is to be fixed to the bridge substructure as it is.

또한 작업공간이 협소한 교량 상부구조와 하부구조 사이의 공간에서 종래 케미컬앵커를 설치하는 작업상의 어려움 등을 해결할 수 있게 됨을 알 수 있다.In addition, it can be seen that a work space can be solved such as the difficulty in installing a conventional chemical anchor in the space between the bridge upper and lower structures.

이에 교량 하부구조(B1)의 상면에 형성시킨 걸림홈(112)에 걸림구(111)가 걸려지도록 한 상태에서 걸림홈(112)에 미도시된 에폭시와 같은 충진재 주입 등을 통해 걸림구(111)가 확실하게 교량 하부구조(B1) 상면에 걸려져 하중을 지지할 수 있도록 해야 한다.Accordingly, in the state in which the catch 111 is caught in the catch groove 112 formed on the upper surface of the bridge substructure B1, the catch 111 is injected through the filler such as epoxy not shown in the catch groove 112. ) Must be securely hung on the upper surface of the bridge substructure B1 to support the load.

다음으로 상기 수직지지판(120)은 도 2b 및 도 2c와 같이 양 수평지지판(110)과 일체로 형성시킨 수직 판재 형태로 형성시키되 교량 하부구조(B1)의 측면부(C)에 다수의 앵커볼트(121)에 의하여 고정되도록 함으로서 필요한 지지능력을 확보할 수 있도록 하게 된다.Next, the vertical support plate 120 is formed in the form of a vertical plate formed integrally with both horizontal support plate 110, as shown in Figure 2b and 2c, but a plurality of side portion (C) of the bridge substructure (B1) It is to be secured by the anchor bolt 121 to ensure the necessary support capacity.

이러한 앵커볼트(121) 설치를 위하여 상기 수직지지판(120)에는 앵커홀을 다수 형성시키게 되며 이러한 앵커볼트(121)는 미도시된 가설동바리 등에 의한 작업공간이 확보된 상태에서 설치하게 되므로 작업성에는 문제가 없으며 역시 하방으로 연장되는 길이는 파괴전단면을 지나도록 형성시키고, 파괴전단면이 아닌 위치에 상기 앵커볼트(121)를 설치하게 된다.In order to install the anchor bolt 121, a plurality of anchor holes are formed in the vertical support plate 120. Such anchor bolts 121 are installed in a state where a work space is secured by a not shown temporary work bar. There is no problem, and the length extending downwards is formed to pass through the fracture shear surface, and the anchor bolt 121 is installed at a position other than the fracture shear surface.

이에 상기 양 수평지지판(110)과 수직지지판(120)은 서로 일체화된 상태에 있어서는 역 “ㄱ"자 형상으로 설치되어 교량 하부구조(B1)의 상단 모서리부를 감싸면서 교량 하부구조(B1)의 측면부에 접하도록 설치됨을 알 수 있다.Accordingly, the horizontal support plate 110 and the vertical support plate 120 are installed in an inverted “a” shape in a state in which they are integrated with each other, and the side portions of the bridge undercarriage B1 while surrounding the upper edges of the bridge undercarriage B1. You can see that it is installed to contact.

다음으로 도 2a 및 도 2b와 같이 인상잭(200)과 교량받침부(300)가 안착되도록 상기 수직지지판(120) 전면에는 횡방향으로 연장된 수평판 형태로서 상단에 수평고정판(130)이 형성되어 있음을 알 수 있으며, 상기 수평고정판(130)의 개략 중앙 상면에는 인상잭(200)을 수용하는 인상잭용 받침구(131)가 형성되어 있고, 상기 인상잭용 받침구(131) 주위에는 교량받침부(300)가 설치되는 볼트홀(132)이 다수 형성되어 있음을 알 수 있다.Next, as shown in FIGS. 2a and 2b, the horizontal fixing plate 130 is formed on the top of the vertical support plate 120 in the form of a horizontal plate extending in the horizontal direction so that the impression jack 200 and the bridge receiving part 300 are seated. It can be seen that, in the upper surface of the outline of the horizontal fixing plate 130, an impression jack support 131 for receiving the impression jack 200 is formed, the bridge support around the impression jack support 131 is formed It can be seen that a plurality of bolt holes 132 in which the unit 300 is installed are formed.

이때 상기 수평고정판(130)을 양 수평지지판(110)과 수직지지판(120)에 보다 확실하게 연결될 수 있도록 상기 수평고정판(130)의 양 측면부 상면에는 배면 일부가 수직지지판(120)에 전면에 접하면서 수평지지판 상면으로 연장되도록 설치된 상부 브라켓 연결판(140)이 설치되도록 하고,In this case, a portion of a rear surface of the horizontal fixing plate 130 is in contact with the front surface of the vertical support plate 120 so that the horizontal fixing plate 130 can be more reliably connected to both the horizontal supporting plate 110 and the vertical supporting plate 120. While the upper bracket connecting plate 140 is installed so as to extend to the upper surface of the horizontal support plate,

상기 수평고정판(130)의 양 측면부 저면에는 배면 일부가 수직지지판(120)에 전면에 접하면서 상면이 수평고정판(130) 저면에 접하도록 설치된 판재 형태의 하부 브라켓 보강판(150)이 설치되도록 함을 알 수 있다.The lower surface of the horizontal fixing plate 130 is installed so that the lower bracket reinforcement plate 150 of the plate shape is installed so that the upper surface is in contact with the bottom surface of the horizontal fixing plate 130 while the rear part is in contact with the front surface of the vertical support plate 120. It can be seen.

이러한 상부 브라켓 연결판(140)과 하부 브라켓 보강판(150)은 수평고정판(130)의 상면 및 저면에 횡방향으로 다수가 이격되어 설치되어 있음을 알 수 있다.It can be seen that the upper bracket connecting plate 140 and the lower bracket reinforcing plate 150 are spaced apart in the transverse direction on the upper and lower surfaces of the horizontal fixing plate 130.

상기 수평고정판(130)에 설치된 인상잭용 받침구(131)는 인상잭(200)의 하부가 삽입되도록 하여 인상잭(200)이 외력에 의하여 그 설치위치를 벗어나지 않도록 하는 원형 링 형태의 받침링 역할을 하게 된다.Impression jack support 131 is installed on the horizontal fixing plate 130 is a lower ring of the lifting jack 200 to be inserted so that the lifting jack 200 does not leave the installation position by the external force serves as a support ring of a circular ring shape. Will be

이에 상기 인상잭용 받침구(131)에는 인상잭(200)이 상방으로부터 하방으로 하강하면서 안착되도록 하게 된다.Accordingly, the impression jack 200 is seated in the support jack 131 is lowered from the upper side to the lower side.

이러한 인상잭용 받침구(131)에는 인상잭(200)에 설치된 유압라인을 연결할 수 있도록 전면 일부가 개방된 상태로 형성되도록 하게 된다.The impression jack support 131 is formed so that a part of the front surface is opened to connect the hydraulic line installed on the impression jack 200.

다음으로 인상잭(200)은 유압에 의하여 교량 상부구조(B2)를 인상시키기 위한 힘을 발생시키는 유압잭으로서 교량 인상용 유압잭을 이용하면 된다.Next, the lifting jack 200 may use a hydraulic jack for lifting a bridge as a hydraulic jack for generating a force for raising the bridge upper structure B2 by hydraulic pressure.

다음으로 상기 교량받침부(300)는 기본적으로 인상잭에 의하여 인상된 교량 상부구조의 인상상태를 유지하면서 교량받침의 기능을 가지도록 형성된다.Next, the bridge receiving portion 300 is basically formed to have a function of bridge bearing while maintaining the pulling state of the bridge superstructure raised by the lifting jack.

이에 앞서 살펴본 수평고정판(130)의 볼트홀(132)에는 압축 앵커볼트(310)가 삽입되도록 함을 알 수 있으며, 상기 압축 앵커볼트(310)에는 좌굴방지용 관(320)과 일체화 시켜 세팅된다.Thus, it can be seen that the compression anchor bolt 310 is inserted into the bolt hole 132 of the horizontal fixing plate 130 described above, and the compression anchor bolt 310 is integrated with the buckling preventing pipe 320 Is set.

상기 좌굴 방지용관(320)은 지지하는 하중의 크기와 압축 앵커볼트(310)의 길이에 따라 관 또는 체결너트로 일체화 시킨다. 확실한 하중지지기능을 발휘시키기 위하여는 관 내부에 나사선 형태의 홈을 형성시켜 압축 앵커볼트(310)와 일체화 시키면 된다.The buckling preventing pipe 320 is integrated into the tube or fastening nut according to the size of the load to support and the length of the compression anchor bolt 310. In order to exert a certain load-bearing function, a groove in the form of a screw thread may be formed inside the pipe and integrated with the compression anchor bolt 310.

또한 좌굴 방지용관(320)의 하부는 상기 교량받침부(300) 상면에 용접 고정되어 상부하중을 효과적으로 지지할 수 있게 된다.In addition, the lower portion of the buckling preventing pipe 320 is welded to the upper surface of the bridge receiving portion 300 to effectively support the upper load.

이에 압축 앵커볼트(310)의 하부가 수평고정판(130)의 볼트홀(132)을 관통하여 수평고정판(130)의 저면에 하부 체결너트(330)에 의하여 체결되도록 하되, 상기 볼트홀(132)을 관통하여 상방으로 연장되면서 수평고정판(130)의 상면에 설치된 좌굴방지용 관(320)과 일체화 시킨다. 이에 상부는 상부 체결너트(340)가 체결되도록 하게 된다.Accordingly, the lower portion of the compression anchor bolt 310 penetrates through the bolt hole 132 of the horizontal fixing plate 130 and is fastened to the bottom surface of the horizontal fixing plate 130 by the lower fastening nut 330. While penetrating through the upper portion is integrated with the buckling preventing pipe 320 installed on the upper surface of the horizontal fixing plate 130. In the upper portion, the upper fastening nut 340 is fastened.

이러한 압축 앵커볼트(310)에 체결된 상부 체결너트(340)의 상단부에는 수평판 형태의 상부받침판(350)이 장착된다.The upper support plate 350 in the form of a horizontal plate is mounted on the upper end of the upper fastening nut 340 fastened to the compression anchor bolt 310.

이에 상기 상부받침판(350)의 외측에는 압축 앵커볼트(310)가 관통될 수 있도록 볼트홀(351)이 형성되어 있음을 알 수 있다.Accordingly, it can be seen that the bolt hole 351 is formed at the outside of the upper support plate 350 so that the compression anchor bolt 310 can pass therethrough.

이때 상기 상부받침판(350)의 양 측방 상면에는 교량받침의 기능 중 교량 상부구조의 횡방향 변위를 제어하기 위한 횡방향변위 구속판(360)을 설치한다.At this time, the two sides of the upper support plate 350 is provided with a transverse displacement restraint plate 360 for controlling the lateral displacement of the bridge superstructure of the function of the bridge support.

이러한 횡방향변위 구속판(360)은 상부받침판(350) 상면에 서로 횡방향으로 이격되도록 설치하여 그 사이에 교량 상부구조(B2) 예컨대 주형의 하부가 삽입되어 지지되도록 하게 된다.The horizontal displacement restraint plate 360 is installed on the upper surface of the upper support plate 350 so as to be laterally spaced apart from each other so that the bridge upper structure B2, for example, the lower part of the mold is inserted therebetween.

이를 위해 상기 횡방향변위 구속판(360)은 상부받침판(350) 양 측방 상면에 볼트홀에 대응한 관통홀(363)이 형성된 하부판(361)과 상기 하부판 내측상면에 상방으로 연장된 수직상부판(362)을 포함하도록 형성시켜 전체적으로 역 “ㄴ"자 형태로 형성되도록 하게 된다.To this end, the lateral displacement restraint plate 360 includes a lower plate 361 having a through hole 363 corresponding to a bolt hole on both side surfaces of the upper support plate 350, and a vertical upper plate extending upwardly on the inner upper surface of the lower plate. (362) to form an inverted “b” shape as a whole.

이에 상기 압축 앵커볼트(310)는 수평고정판(130)의 볼트홀(132)과 상기 관통홀(363)을 관통하여 하부판(361) 상면에서 고정너트(370)에 의하여 최종 장착 완료되도록 하게 된다.Accordingly, the compression anchor bolt 310 passes through the bolt hole 132 and the through hole 363 of the horizontal fixing plate 130 to be finally mounted by the fixing nut 370 on the upper surface of the lower plate 361.

또한 상기 수직 연장된 수직상부판(362)의 내측면들에는 경질고무판(380)이 에폭시와 같은 접착제로 부착되도록 하게 된다.In addition, the hard rubber plate 380 is attached to the inner surfaces of the vertically extending vertical upper plate 362 with an adhesive such as epoxy.

또한 상기 수평고정판의 저면과 인상잭(200)의 상면에는 황동판으로 제작된 슬라이딩판(390)이 삽입되도록 함을 알 수 있다.In addition, it can be seen that the sliding plate 390 made of a brass plate is inserted into the bottom surface of the horizontal fixing plate and the upper surface of the impression jack 200.

상기 경질고무판(380)과 슬라이딩판(390)은 후술된다.The hard rubber plate 380 and the sliding plate 390 will be described later.

< 본 발명의 받침기능을 보유하고 탈락방지가 가능한 탈착식 교량용 인상장치(A)의 설치방법 ><Installation method of the removable bridge raising device (A) having the support function of the present invention and preventing the fall off>

먼저, 앞서 살펴본 받침기능을 보유하고 탈락방지가 가능한 탈착식 교량용 인상장치(A)에 있어 도 3a 내지 도 3c와 같이 걸림구(111)가 형성된 양 수평지지판(110), 앵커볼트(121)에 의하여 설치되는 수직지지판(120), 인상잭용 받침구(131)와 볼트홀(132)이 형성된 수평고정판(130) 및 상부 브라켓 연결판(140) 및 하부 브라켓 보강판(150)을 포함하여 구성된 브라켓부(100)를 교량 하부구조(B1)에 설치하게 된다.First, in the lifting device (A) of the removable bridge retaining the above-described support function and prevented from falling off, on both horizontal support plates 110 and the anchor bolts 121 formed with the latches 111 as shown in FIGS. 3A to 3C. Bracket consisting of a vertical support plate 120, a horizontal fixing plate 130 and the upper bracket connecting plate 140 and the lower bracket reinforcing plate 150 is formed, the vertical support plate 120, the impression jack support 131 and the bolt hole 132 is formed The part 100 is to be installed in the bridge substructure B1.

이는 먼저 종래 교량 하부구조(B1)에 설치된 교량 받침 주위의 교량 하부구조 상면에 있어 전단파괴면(C1) 부위를 피하여 상기 걸림구(111)가 걸려질 수 있도록 핸드커팅기를 이용하여 일자 형태의 걸림홈(112)를 도 2a와 같이 형성시키게 된다.This is first by using a hand-cutting machine to avoid the shear fracture surface (C1) in the upper surface of the bridge base structure around the bridge support installed in the conventional bridge substructure (B1) using the hand cutting machine The groove 112 is formed as shown in FIG. 2A.

이에 먼저 걸림홈(112)에 걸림구(111)가 걸려지도록 한 상태에서 걸림홈에 충진재를 주입하여 걸림구를 마감하게 된다.First, the filling hole is injected into the locking groove in the state where the locking hole 111 is caught in the locking groove 112 to close the locking hole.

이와 함께 상기 수직지지판(120)을 앵커볼트(121)에 의하여 교량 하부구조(B1) 측면부(C)에 고정되도록 설치하게 된다.Along with this, the vertical support plate 120 is installed to be fixed to the side surface portion C of the bridge substructure B1 by the anchor bolt 121.

다음으로는 상기 인상잭용 받침구(131)에 인상잭(200)을 삽입하여 세팅하게 되며, 이와 함께 상기 수평고정판(130)에 압축 앵커볼트(310)를 하부 체결너트(330)로 가체결시키게 된다.Next, the impression jack 200 is inserted into the impression jack support 131 to be set, and the compression anchor bolt 310 is temporarily fastened to the horizontal fixing plate 130 by the lower fastening nut 330. do.

이때, 좌굴 방지용관(320)을 압축 앵커볼트(310)과 일체화시켜 수평고정판(130)에 설치된 압축 앵커볼트(310)가 외력 저항시 좌굴되지 않도록 하면서, 압축 앵커볼트(310)에 상부 체결너트(340)로 가체결시키게 된다.At this time, the buckling prevention pipe 320 is integrated with the compression anchor bolt 310 to prevent the compression anchor bolt 310 installed in the horizontal fixing plate 130 is not buckled during the external force resistance, while the upper fastening nut to the compression anchor bolt 310 The pre-tightening to 340.

다음으로 상기 압축 앵커볼트(310)에 경질고무판(380)이 부착된 역 “ㄴ"자 형태의 횡방향변위 구속판(360)과 함께 상부받침판(350)을 삽입하여 상부받침판(350)이 상부 체결너트(340)에 의하여 지지되도록 하게 된다.Next, the upper support plate 350 is inserted into the upper support plate 350 by inserting the upper support plate 350 together with the transverse displacement restraint plate 360 of the inverted “b” shape to which the hard rubber plate 380 is attached to the compression anchor bolt 310. It is to be supported by the fastening nut 340.

이때 상기 역 “ㄴ"자 형태의 횡방향변위 구속판(360)은 교량 상부구조(B2)인 거더 저면을 감싸도록 배치하도록 하게 된다.In this case, the inverse “b” shaped lateral displacement restraining plate 360 is arranged to surround the bottom of the girder which is the bridge superstructure B2.

또한 인상잭(200) 상면과 수평고정판(130)의 저면에 슬라이딩판(390)을 설치한 후, 상기 인상잭(200)을 작동시켜 교량 상부구조(B2)인 거더 저면을 인상시키게 된다.In addition, after installing the sliding plate 390 on the upper surface of the lifting jack 200 and the bottom of the horizontal fixing plate 130, the lifting jack 200 is operated to raise the bottom of the girder that is the bridge upper structure (B2).

이러한 최종 교량 상부구조인 거더를 인상하게 되면 인상상태를 그대로 유지해야 기존 교량받침의 보수가 가능하게 된다. 이에 본 발명은 압축 앵커볼트(310)의 상부가 고정너트(370)에 의하여 횡방향변위 구속판(360)의 관통홀(363)이 형성된 하부판(361) 상면에 체결되도록 하여 상기 인상상태를 유지시키게 된다.When the girder, which is the upper structure of the final bridge, is raised, it is possible to repair the existing bridge support only by maintaining the raised state. In the present invention, the upper part of the compression anchor bolt 310 is fastened to the upper surface of the lower plate 361 formed with the through hole 363 of the transverse displacement restraining plate 360 by the fixing nut 370 to maintain the pulling state. Let's go.

이에 교량 상부구조가 인상된 상태에서 교량 상부구조에 온도 변화등에 의한 종방향 및 횡방향 이동이 발생하게 된다.Accordingly, in the state in which the bridge superstructure is pulled up, longitudinal and transverse movements occur in the bridge superstructure due to temperature change.

이러한 이동을 흡수하지 않으면 인상잭의 전도등과 같은 현상이 발생하게 된다.If this movement is not absorbed, a phenomenon such as conduction of the impression jack will occur.

이를 위해 본 발명은 먼저 교량 상부구조의 횡방향 이동의 경우는 그 이동량이 거의 발생하지 않기 때문에 횡방향변위 구속판(360)의 수직상부판(362) 내측면에 설치된 경질고무판(380)이 상기 이동에 의한 교량 상부구조의 횡향향 이동에 의한 변위를 흡수하도록 하게 된다.To this end, the present invention is in the case of the transverse movement of the bridge superstructure first Since the movement amount hardly occurs, the hard rubber plate 380 provided on the inner side of the vertical upper plate 362 of the transverse displacement restraining plate 360 absorbs the displacement caused by the transverse movement of the bridge superstructure due to the movement. do.

또한 교량 상부구조의 종방향 이동은 슬라이딩판(390)이 담당하도록 하여 결국 본 발명의 교량용 인상장치가 교량 상부구조의 종방향 및 횡방향 이동을 흡수할 수 있도록 하게 된다.In addition, the longitudinal movement of the bridge superstructure is responsible for the sliding plate 390, so that the bridge pulling apparatus of the present invention can absorb the longitudinal and transverse movement of the bridge superstructure.

이때, 횡방향변위 구속판(360)의 하부판(361)에 형성된 체결홀(363)은 종방향으로 타원형으로 형성될 수 있도록 하여 교량 상부구조의 종방향 이동에 압축 앵커볼트(310)가 여유롭게 대처할 수 있도록 함이 바람직하다.At this time, the fastening hole 363 formed in the lower plate 361 of the transverse displacement restraining plate 360 can be formed in an elliptical shape in the longitudinal direction so that the compression anchor bolt 310 can cope with the longitudinal movement of the bridge superstructure. It is desirable to be able to.

이에 도 3c와 같이 본 발명에 의한 탈락방지가 가능한 탈착식 교량용 인상장치(A)가 교량 하부구조(B1)에 설치되어, 교량 상부구조(B2)를 인상시키고 이 상태에서 교량받침의 기능을 가지도록 함을 알 수 있다.Accordingly, as shown in FIG. 3C, a detachable bridge pulling apparatus A capable of preventing dropping according to the present invention is installed in the bridge undercarriage B1 to raise the bridge superstructure B2 and have a function of supporting the bridge in this state. It can be seen that.

물론, 종방향으로 교량받침 기능을 가지도록 하기 위해서는 고정너트(370)에 의한 압축 앵커볼트(310)가 완전히 고정체결되지 않도록 하되 관통홀(363)은 종방향으로 타원형으로 형성되어 있으므로 압축 앵커볼트(310)이 종방향으로 다소 여유를 가지면서 설치되도록 하여 교량 상부구조의 종방향 이동을 제한적으로 흡수할 수 있도록 하게 된다.Of course, in order to have a bridge bearing function in the longitudinal direction so that the compression anchor bolt 310 by the fixing nut 370 is not completely fastened but the through hole 363 is formed in the longitudinal oval compression anchor bolt The 310 is installed to have some margin in the longitudinal direction so that the longitudinal movement of the bridge superstructure can be limitedly absorbed.

100: 브라켓부
110: 양 수평지지판
111: 걸림구
112: 걸림홈
120: 수직지지판
121: 앵커볼트
130: 수평고정판
131: 인상잭용 받침구
132: 볼트홀
200: 인상잭
300: 교량받침부
310: 압축 앵커볼트
320: 좌굴방지용 관
330: 하부 체결너트
340: 상부 체결너트
350: 상부 받침판
360: 횡방향변위 구속판
370: 고정너트
380: 경질고무판
390: 슬라이딩판
100: bracket portion
110: both horizontal support plate
111: latch
112: hanging groove
120: vertical support plate
121: anchor bolt
130: leveling plate
131: impression jack support
132: bolt hole
200: Impression Jack
300: bridge support
310: compression anchor bolt
320: buckling prevention tube
330: lower tightening nut
340: upper fastening nut
350: upper support plate
360: lateral displacement restraint plate
370: fixing nut
380: hard rubber plate
390: sliding plate

Claims (4)

교량 하부구조의 측면에 설치된 브라켓부에 인상잭을 설치하고 상기 인상잭에 의하여 교량 상부구조를 인상시킨 상태에서 교량 상부구조의 종방향 및 횡방향 이동에 의한 변위를 흡수하는 교량받침 기능을 가진 교량용 인상장치에 있어서,
상기 브라켓부는 교량 하부구조(B1)의 상면에 접하여 서로 횡방향으로 이격되도록 설치되되 교량 하부구조의 상단 모서리부의 파괴전단면(C1)을 지나도록 연장되어 교량 하부구조(B1) 상면에 형성된 걸림홈(112)에 일단부 저면에 형성된 걸림구(111)가 걸려지도록 설치된 양 수평지지판(110);
상기 양 수평지지판(110)의 타단부 저면에 하방으로 연장되어 교량 하부구조의 측면부(C)에 앵커볼트(121)로 고정되도록 설치된 수직지지판(120); 및
수직지지판 전면 상단에 횡방향으로 연장된 수평판 형태로서 중앙 상면에 인상잭(200)을 수용하는 인상잭용 받침구(131)가 형성된 수평고정판(130);을 포함하도록 형성시키는 것을 특징으로 하는 받침기능을 보유하고 탈락방지가 가능한 탈착식 교량용 인상장치.
Bridge having a bridge support function that absorbs displacement caused by the longitudinal and transverse movement of the bridge superstructure in the state in which the impression jack is installed in the bracket portion provided on the side of the bridge substructure and the bridge superstructure is raised by the impression jack In the impression device for
The bracket portion is installed to be in contact with the upper surface of the bridge substructure B1 laterally spaced apart from each other but extending to pass through the fracture shear surface (C1) of the upper edge portion of the bridge substructure to the engaging groove formed on the upper surface of the bridge substructure B1 Both horizontal support plate 110 is installed so as to hang the hook 111 formed on the bottom end of the end 112;
A vertical support plate 120 extending downward on bottom surfaces of the other ends of the horizontal support plates 110 so as to be fixed to the side bolts C of the bridge substructure by an anchor bolt 121; And
A horizontal fixing plate 130 having an impression jack support 131 for receiving the impression jack 200 on a central upper surface thereof as a horizontal plate extending in the horizontal direction at the top of the vertical support plate; Removable lifting device for bridges with function and preventing fallout.
제 1항에 있어서,
상기 브라켓부(100)에는 교량받침부(300)가 더 형성되도록 하되 상기 교량받침부는
상기 수평고정판(130)의 볼트홀(132)에 삽입 설치된 압축 앵커볼트(310);
상기 압축 앵커볼트(310)의 압축좌굴에 의한 파괴를 방지할 수 있도록 압축 앵커볼트와 일체화된 좌굴방지용 관(320);
상기 압축 앵커볼트(310)의 하부가 수평고정판(130)의 볼트홀(132)을 관통하여 수평고정판(130)의 저면에 체결된 하부 체결너트(330)
볼트홀(132)을 관통하여 상방으로 연장된 상기 압축 앵커볼트(310)의 상부에 체결되도록 하는 상부 체결너트(340);
상기 상부 체결너트(340)의 상단부에는 장착된 수평판 형태의 상부받침판(350):
상기 상부받침판(350)의 양 측방 상면에 교량 상부구조의 횡방향 변위를 제어하기 위하여 설치되는 것으로서 상부받침판 양 측방 상면에 볼트홀에 대응한 관통홀(363)이 형성된 하부판(361)과 상기 하부판 내측상면에 상방으로 연장된 수직상부판(362)을 포함하여 구성된 횡방향변위 구속판(360); 및
상기 수평고정판(130)의 볼트홀(132)과 상기 관통홀(363)을 관통하여 횡방향변위 구속판을 구성하는 하부판(361) 상면에서 압축 앵커볼트(310)가 체결되도록 하는 고정너트(370);를 포함하도록 하는 것을 특징으로 하는 받침기능을 보유하고 탈락방지가 가능한 탈착식 교량용 인상장치.
The method of claim 1,
The bridge portion 300 is to be further formed on the bracket portion 100, but the bridge portion
A compression anchor bolt 310 inserted into the bolt hole 132 of the horizontal fixing plate 130;
Buckling preventing pipe 320 is integrated with the compression anchor bolt to prevent breakage by compression buckling of the compression anchor bolt 310;
The lower fastening nut 330 of which the lower portion of the compression anchor bolt 310 is fastened to the bottom surface of the horizontal fixing plate 130 by passing through the bolt hole 132 of the horizontal fixing plate 130.
An upper fastening nut 340 to be fastened to an upper portion of the compression anchor bolt 310 extending upward through the bolt hole 132;
The upper support plate 350 of the horizontal plate type is mounted on the upper end of the upper fastening nut 340:
The lower plate 361 and the lower plate, which are installed on both side upper surfaces of the upper support plate 350 to control the lateral displacement of the bridge superstructure, are provided with through holes 363 corresponding to bolt holes on both upper surfaces of the upper support plate. A transverse displacement restricting plate 360 including a vertical upper plate 362 extending upward on an inner upper surface thereof; And
Fixing nut 370 for fastening the compression anchor bolt 310 on the upper surface of the lower plate 361 constituting the transverse displacement restraint plate through the bolt hole 132 and the through hole 363 of the horizontal fixing plate 130 Has a supporting function, characterized in that it comprises a; Demountable lifting device for detachable bridge that can prevent falling.
제 2항에 있어서,
상기 교량받침부(300)의 횡방향변위 구속판(360)을 구성하는 수직상부판(362)의 내측면들에는 접착제로 부착된 경질고무판(380); 및 상기 수평고정판의 저면과 인상잭(200)의 상면에 설치된 황동판으로 제작된 슬라이딩판(390);이 더 형성되도록 하는 것을 특징으로 하는 받침기능을 보유하고 탈락방지가 가능한 탈착식 교량용 인상장치.
The method of claim 2,
A hard rubber plate 380 attached to the inner surfaces of the vertical upper plate 362 constituting the transverse displacement restraint plate 360 of the bridge receiving part 300; And a sliding plate (390) made of a brass plate installed on a bottom surface of the horizontal fixing plate and an upper surface of the lifting jack (200).
삭제delete
KR1020110013966A 2011-02-17 2011-02-17 Lifting and bearing apparatus preventing fracture on the pier or abutment of bridge KR101066837B1 (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
KR1020110013966A KR101066837B1 (en) 2011-02-17 2011-02-17 Lifting and bearing apparatus preventing fracture on the pier or abutment of bridge

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
KR1020110013966A KR101066837B1 (en) 2011-02-17 2011-02-17 Lifting and bearing apparatus preventing fracture on the pier or abutment of bridge

Publications (1)

Publication Number Publication Date
KR101066837B1 true KR101066837B1 (en) 2011-09-26

Family

ID=44957721

Family Applications (1)

Application Number Title Priority Date Filing Date
KR1020110013966A KR101066837B1 (en) 2011-02-17 2011-02-17 Lifting and bearing apparatus preventing fracture on the pier or abutment of bridge

Country Status (1)

Country Link
KR (1) KR101066837B1 (en)

Cited By (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN103510463A (en) * 2013-09-27 2014-01-15 无锡圣丰建筑新材料有限公司 Horizontal rotation hinged support
KR101478159B1 (en) * 2014-04-22 2014-12-31 웅진엔지니어링(주) Method for lifting upper structure of bridge
KR101767845B1 (en) * 2016-10-24 2017-08-14 심규숙 Bridge bearing replacement method for preventing drop of upper structure
KR101971274B1 (en) * 2018-09-28 2019-04-22 윤형남 Bridge lifting apparatus and lifing method using it
KR20210041813A (en) 2019-10-08 2021-04-16 김의석 Girder Joint

Citations (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
KR200333818Y1 (en) 2003-08-22 2003-11-17 김해영 bearing for jacking up upper structure of bridge
KR20070078418A (en) * 2007-07-11 2007-07-31 (주)신행건설 Oil pressure demolition device for bridge bearing upper part demolition and method of construction
KR100837608B1 (en) 2006-08-21 2008-06-13 주식회사 신화 엠앤씨 J.K Bracket Method
KR20090102266A (en) * 2008-03-25 2009-09-30 서울메트로 A pulling plate of beam the bridge pier

Patent Citations (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
KR200333818Y1 (en) 2003-08-22 2003-11-17 김해영 bearing for jacking up upper structure of bridge
KR100837608B1 (en) 2006-08-21 2008-06-13 주식회사 신화 엠앤씨 J.K Bracket Method
KR20070078418A (en) * 2007-07-11 2007-07-31 (주)신행건설 Oil pressure demolition device for bridge bearing upper part demolition and method of construction
KR20090102266A (en) * 2008-03-25 2009-09-30 서울메트로 A pulling plate of beam the bridge pier

Cited By (6)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN103510463A (en) * 2013-09-27 2014-01-15 无锡圣丰建筑新材料有限公司 Horizontal rotation hinged support
CN103510463B (en) * 2013-09-27 2015-08-26 无锡圣丰建筑新材料有限公司 Horizontally rotate hinged-support
KR101478159B1 (en) * 2014-04-22 2014-12-31 웅진엔지니어링(주) Method for lifting upper structure of bridge
KR101767845B1 (en) * 2016-10-24 2017-08-14 심규숙 Bridge bearing replacement method for preventing drop of upper structure
KR101971274B1 (en) * 2018-09-28 2019-04-22 윤형남 Bridge lifting apparatus and lifing method using it
KR20210041813A (en) 2019-10-08 2021-04-16 김의석 Girder Joint

Similar Documents

Publication Publication Date Title
KR101066837B1 (en) Lifting and bearing apparatus preventing fracture on the pier or abutment of bridge
KR100948359B1 (en) The bridge upper structure lifting method for which bridge upper structure lifter which does the bridge shue function and this were used
KR101300073B1 (en) Lifting device for girder
KR101564721B1 (en) Construction method for replacing bridge bearing without damaging of lower structure
KR100707312B1 (en) Bridge jacking and repair method using safety system
KR100977280B1 (en) a pulling plate of beam the bridge pier
KR101026012B1 (en) Bridge deck dismantling method by means of united pulling jack and pier
CN104005338A (en) Three-directional temporary tower and girder consolidation structure of large-span cable-stayed bridge
CN106460403B (en) Armrest kit, armrest system and installation method
KR101004795B1 (en) Method for raising a bridge and the raising structure there of
KR102024665B1 (en) System For Lifting Bridge Upper Plate
KR100977061B1 (en) The bridge adjustable bearing for change off puilling up system laying pc-beam restitution system and the method
KR101704550B1 (en) lift method for upper structure of bridge by using computer and hydraulic jack including safety device
KR101971274B1 (en) Bridge lifting apparatus and lifing method using it
JP6567920B2 (en) Road bridge telescopic device and road bridge telescopic device construction method
KR100780888B1 (en) Bracket structure for replacing the old shoe with new one continuously and method lifting the bridge slab
KR101704552B1 (en) Hydraulic jack including safety device and lift method for upper structure of bridge by using hydraulic jack including safety device
CN203866711U (en) Large span cable-stayed bridge tower beam three-way temporary consolidation structure
KR101404818B1 (en) superstructure raise device of the bridge
KR102581845B1 (en) Computer controlled impression device using hydraulic jack with full automatic multi-safety device
KR101605011B1 (en) Repair and Reinforcement method of lower structure of bridge
KR101282333B1 (en) Cross-type supporting structure and method for super-structure of bridge
JP2012102468A (en) Movable scaffold for repairing bridge lower face and installation method for the same
KR20040076348A (en) Apparatus and method for pulling up and prevention of falling down of bridge beam
KR100474299B1 (en) A

Legal Events

Date Code Title Description
A201 Request for examination
A302 Request for accelerated examination
E902 Notification of reason for refusal
E701 Decision to grant or registration of patent right
GRNT Written decision to grant
FPAY Annual fee payment

Payment date: 20140813

Year of fee payment: 4

FPAY Annual fee payment

Payment date: 20150824

Year of fee payment: 5

FPAY Annual fee payment

Payment date: 20160826

Year of fee payment: 6

LAPS Lapse due to unpaid annual fee