KR101046941B1 - Rahmen bridge construction method without hunch - Google Patents

Rahmen bridge construction method without hunch Download PDF

Info

Publication number
KR101046941B1
KR101046941B1 KR1020110022534A KR20110022534A KR101046941B1 KR 101046941 B1 KR101046941 B1 KR 101046941B1 KR 1020110022534 A KR1020110022534 A KR 1020110022534A KR 20110022534 A KR20110022534 A KR 20110022534A KR 101046941 B1 KR101046941 B1 KR 101046941B1
Authority
KR
South Korea
Prior art keywords
girder
steel
wall portion
transverse
bending
Prior art date
Application number
KR1020110022534A
Other languages
Korean (ko)
Inventor
양난경
Original Assignee
주식회사 하이드로코리아
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by 주식회사 하이드로코리아 filed Critical 주식회사 하이드로코리아
Priority to KR1020110022534A priority Critical patent/KR101046941B1/en
Application granted granted Critical
Publication of KR101046941B1 publication Critical patent/KR101046941B1/en

Links

Images

Classifications

    • EFIXED CONSTRUCTIONS
    • E01CONSTRUCTION OF ROADS, RAILWAYS, OR BRIDGES
    • E01DCONSTRUCTION OF BRIDGES, ELEVATED ROADWAYS OR VIADUCTS; ASSEMBLY OF BRIDGES
    • E01D21/00Methods or apparatus specially adapted for erecting or assembling bridges
    • EFIXED CONSTRUCTIONS
    • E01CONSTRUCTION OF ROADS, RAILWAYS, OR BRIDGES
    • E01DCONSTRUCTION OF BRIDGES, ELEVATED ROADWAYS OR VIADUCTS; ASSEMBLY OF BRIDGES
    • E01D19/00Structural or constructional details of bridges
    • E01D19/12Grating or flooring for bridges; Fastening railway sleepers or tracks to bridges
    • E01D19/125Grating or flooring for bridges
    • EFIXED CONSTRUCTIONS
    • E01CONSTRUCTION OF ROADS, RAILWAYS, OR BRIDGES
    • E01DCONSTRUCTION OF BRIDGES, ELEVATED ROADWAYS OR VIADUCTS; ASSEMBLY OF BRIDGES
    • E01D2/00Bridges characterised by the cross-section of their bearing spanning structure
    • E01D2/02Bridges characterised by the cross-section of their bearing spanning structure of the I-girder type
    • EFIXED CONSTRUCTIONS
    • E01CONSTRUCTION OF ROADS, RAILWAYS, OR BRIDGES
    • E01DCONSTRUCTION OF BRIDGES, ELEVATED ROADWAYS OR VIADUCTS; ASSEMBLY OF BRIDGES
    • E01D2101/00Material constitution of bridges
    • E01D2101/20Concrete, stone or stone-like material
    • E01D2101/24Concrete
    • E01D2101/26Concrete reinforced
    • E01D2101/268Composite concrete-metal
    • EFIXED CONSTRUCTIONS
    • E01CONSTRUCTION OF ROADS, RAILWAYS, OR BRIDGES
    • E01DCONSTRUCTION OF BRIDGES, ELEVATED ROADWAYS OR VIADUCTS; ASSEMBLY OF BRIDGES
    • E01D2101/00Material constitution of bridges
    • E01D2101/30Metal
    • E01D2101/32Metal prestressed

Landscapes

  • Engineering & Computer Science (AREA)
  • Architecture (AREA)
  • Civil Engineering (AREA)
  • Structural Engineering (AREA)
  • Bridges Or Land Bridges (AREA)

Abstract

PURPOSE: A construction method of a rahmen bridge without a haunch unit is provided to improve the exterior of a rahmen bridge and to lighten the weight of the rahmen bridge because a haunch unit is not required. CONSTITUTION: A construction method of a rahmen bridge is as follows. Abutment parts(200) are installed on the ground. Girders(300) are longitudinally installed between the tops of the abutment parts to be horizontally separated from each other. Slab concrete is placed between the girders and the top of the girders so that a slab can be integrally formed in the abutment parts. Main reinforcing bars, longitudinally extended, are arranged between the girders.

Description

헌치부가 배제된 라멘교 시공방법{RAHMEN BRIDGE CONSTRUCTION METHOD WITHOUT HUNCH}RAHMEN BRIDGE CONSTRUCTION METHOD WITHOUT HUNCH}

본 발명은 헌치부가 배제된 라멘교 시공방법에 관한 것이다. 더욱 구체적으로 헌치부가 형성된 라멘교의 교량계획고의 한계를 극복할 수 있도록 하면서도 구조적으로 효율적이며 경제적인 라멘교 시공이 가능한 헌치부가 배제된 라멘교 시공방법에 관한 것이다.The present invention relates to a method for constructing a ramen bridge without a haunting portion. More specifically, the present invention relates to a method for constructing a ramen bridge, which can overcome the limitations of the bridge plan of a ramen bridge where a haunting bridge is formed, while eliminating the haunting bridge that is structurally efficient and economical.

도 1은 종래 라멘교(10)의 일예를 사시도로 도시한 것이다.Figure 1 shows an example of a conventional ramen bridge 10 in a perspective view.

상기 라멘교(10)는 크게 저판(13)과 저판 중앙 상부면에 수직방향으로 연장돌출 되도록 설치된 저판 벽체부(12) 및 상기 저판벽체부(12)의 양 단부 상부면에 일체로 형성된 슬래브(11)로 구성된다.The ramen bridge 10 has a slab formed integrally with the bottom plate 13 and the bottom plate wall 12 and installed at both ends of the bottom plate wall 12 so as to extend and extend in a vertical direction to the bottom plate 13 and the center top surface of the bottom plate. 11).

상기 저판(13)은 지반을 터파기 하여 거푸집을 이용 직육면체 형태의 철근콘크리트 구조물로 제작하며 역시 저판벽체부(12)도 거푸집을 이용하여 소정의 높이(H)를 가진 철근콘크리트 구조물로 제작하게 된다.The bottom plate 13 is made of a reinforced concrete structure of a rectangular parallelepiped form using the formwork to dig the ground, and also the bottom plate portion 12 is also made of a reinforced concrete structure having a predetermined height (H) using the formwork. .

나아가 상기 슬래브(11) 역시 저판벽체부(12) 사이에 동바리를 지반에 설치하고 동바리 위에 거푸집을 설치하여 역시 철근콘크리트 구조물로 시공하게 된다.Furthermore, the slab 11 is also installed between the bottom plate wall portion 12, the copper bar on the ground and the formwork is installed on the copper bar to be constructed as a reinforced concrete structure.

이러한 슬래브(11)는 A-A 절단면도와 같이 소정의 두께(t)를 가지게 되며 그 단면 형태는 종방향 및 횡방향으로 연장되어 종방향으로 소정의 길이(L) 및 두께(t)를 가지도록 사각단면형태로서 전체적으로는 장방형 부재로 형성되도록 함을 알 수 있다.The slab 11 has a predetermined thickness (t) as shown in the AA cross-sectional view and the cross-sectional shape is a rectangular cross section so as to have a predetermined length (L) and thickness (t) in the longitudinal direction and extend in the longitudinal and transverse directions. It can be seen that it is formed as a rectangular member as a whole as a form.

이때, 상기 슬래브용 거푸집의 경우 슬래브 단부 내측으로부터 하방 경사져 지점벽체부의 상단 연결부위로 연장되도록 헌치부(20)를 형성시키게 되는데 이는 상기 헌치부(20)에 휨 부모멘트(M-)가 발생하기 때문에 이에 대한 강성을 확보하기 위한 것이다.At this time, in the case of the slab formwork to form the haunche 20 to be inclined downward from the inner end of the slab to extend to the upper connection portion of the point wall portion, which is to cause the bending parent (M-) in the haunche 20 Therefore, to secure the rigidity for this.

이를 위해 상기 헌치부(20) 내부에는 하부주철근(21), 헌치철근(22), 배력철근(23)을 배근하는 것을 기본으로 하고 있다.To this end, the lower cast iron (21), the haunch reinforcing bar (22), the reinforcing bar (23) is based on the inside of the haunch unit 20.

이때, 상기 헌치부의 확장상세도를 도 1b를 기준으로 살펴보면 At this time, looking at the expanded detail of the haunting unit on the basis of Figure 1b

상기 헌치부는 최대 휨 부모멘트와 함께 최대 전단력이 작용하는 부분이므로 거더 높이와 바닥판의 두께를 합친 길이 이상으로 종방향으로 연장시켜 형성시키고 있다.Since the haunch portion is a portion in which the maximum shear force is acted together with the maximum bending parent moment, it is formed by extending in the longitudinal direction beyond the length of the combined height of the girder height and the bottom plate.

하지만 상기 헌치부가 슬래브와 저판벽체부(12)와의 결합부 사이에 형성되어 있어 하천설계기준에서 규정하고 있는 헌치부 하단에서부터 아래 수면까지 교량의 여유교가 정해지게 되므로 이러한 헌치부에 의하여 교량 여유고를 결정하다 보면 저판벽체부(12) 슬래브와 접속되는 기존 접속도로(미도시)와의 높이와 대비하여 교량 계확고가 높게 형성되는 경우 이를 맞춰주기 위한 토공작업이 요구되어 경제적인 라멘교 시공이 어렵다는 문제점이 있었다.However, since the haunting portion is formed between the slab and the bottom plate wall portion 12, the free bridge of the bridge is defined from the bottom of the haunting portion prescribed by the river design standard to the surface below, so that the free space of the bridge is determined by the haunting portion. When it is decided, it is difficult to economically construct the Ramen bridge because earthwork is required to match the height of the bridge system when it is formed high compared with the height of the existing connecting road (not shown) connected to the slab of the slab 12. There was this.

이에 상기 헌치부를 배제시킬 필요가 있지만 라멘교에 있어 상기 헌치부의 기능을 대체할 수 있는 마땅한 수단이 없다는 한계가 있었다.Therefore, it is necessary to exclude the hunt, but there was a limit in that there is no proper means to replace the function of the hunt for the ramen.

또한 이러한 라멘교(10)는 시공이 간편하고 비교적 짧은 지간(개략 10-15m)에서는 효율적이고 경제적인 교량이라 할 수 있으며 거더교에 설치되는 교량받침과 신축이음장치를 배제할 수 있어 단경간 소교량에서 많이 이용되고 있다.In addition, such a ramen bridge (10) can be said to be an efficient and economical bridge in a relatively short span (approximately 10-15m) and easy to construct, and can eliminate bridge bearings and expansion joints installed on the girder bridge. It is used a lot.

이와 같이 교량받침과 신축이음장치를 배제시킨 라멘교는 사용재료 및 가설방법에 의해 크게 두가지 형식으로 구분되는데 As such, the ramen bridge that excludes the bridge bearings and expansion joints is divided into two types according to the materials used and the construction method.

첫째 철근콘크리트 라멘교는 가설시 전면동바리를 사용하여 가설하는 형식,First, reinforced concrete ramen bridge is hypothesized by using a front ridge for construction.

둘째 철근콘크리트 교대부와 교각부를 시공한 후 강재거더를 상부로 거치한 후 슬래브와 합성시킨 강합성 라멘교 형식으로 구분된다.Second, after constructing reinforced concrete alternating part and piling part, steel girder is mounted to upper part and then it is classified into steel composite ramen bridge type which is composited with slab.

이러한 구분에 의한 라멘교에 있어 개정된 하천설계기준에서 하천내 12.5M 이내에는 교각을 설치하지 못하도록 규정하고 있어 하천폭 18~25M 규모의 소하천에서는 기존 철근콘크리트 라멘교가 경간장의 한계가 15~17M로 상기 하천설계기준을 만족시키지 못하게 되었고 이에 강재거더를 이용하여 경간장의 한계를 극복한 강합성 라멘교가 개발이 되어 왔다.According to the revised river design standard in the Ramen Bridge, it is forbidden to install a pier within 12.5M in the river.In small rivers with a width of 18 ~ 25M, the existing reinforced concrete ramen bridge has a limit of 15 ~ 17M. Since the river design criteria were not satisfied, a steel ramen bridge was developed to overcome the limitations of span length using steel girder.

그러나 종래 개발된 강합성 라멘교들 또한 강재거더 거치후 벽체와 일체화 과정에서 강재거더를 철근을 감싸는 방식으로 헌치를 구성하고 있어 상기 강합성 라멘교 또한 교량계획고의 낮추는 데에는 한계가 나타나게 되었다.However, the conventionally developed steel ramen bridges also constitute a hunt by wrapping steel girders in the process of integrating with the wall after the steel girders are mounted, so that the steel composite ramen bridges also have a limit in reducing the bridge plan.

이에 본 발명은 종래 라멘교에 있어서 헌치부를 배제하는 수단을 갖추어 교량 계획고에 따른 능동적인 대처가 가능하도록 하고,Accordingly, the present invention is equipped with a means for excluding the haunch in the conventional ramen bridge to enable active response according to the bridge plan,

종래 라멘교의 철근콘크리트 슬래브의 경간장에 대한 한계를 극복할 수 있으면서도 구조적으로 효율적이며 경제적인 라멘교 시공방법 제공을 그 해결하고자 하는 기술적 과제로 한다.The technical problem to be solved to provide a structurally efficient and economical method for constructing a ramen bridge while overcoming the limitations on the span length of the reinforced concrete slab of the conventional ramen bridge.

상기 해결과제를 위하여 본 발명은The present invention for the above problem

교대부를 지반에 설치하고, 상기 교대부 상면 사이에 종방향으로 연장되도록 하면서 횡방향으로 다수가 이격되도록 설치된 거더를 상기 교대부에 강결시키고, 상기 거더가 매립되도록 하면서 거더 횡방향 사이 공간 및 상부에 슬래브콘크리트를 타설하여 상기 교대부와 슬래브가 서로 일체로 형성되도록 하는 단계를 포함하는 라멘교 시공방법에 있어서,The alternating part is installed on the ground, and the girders installed so as to be longitudinally spaced apart between the upper part of the alternating part are tightened to the alternating part, and the girder is embedded in the space between the girder transverse direction and the upper part. In the ramen bridge construction method comprising the step of placing the slab concrete so that the alternating portion and the slab are formed integrally with each other,

상기 교대부와 거더의 강결부위에 형성되는 헌치부를 제거하기 위하여 각 거더의 횡방향 사이 공간에 종방향으로 연장되는 주철근을 배치하되, 상기 주철근은 거더 하부 복부로부터 거더 중앙쪽으로 연장되면서 상방경사지게 종방향으로 배치되도록 하여 거더에 상기 주철근에 의한 종방향 절곡 주철근이 배치되도록 하고,In order to remove the haunch formed in the rigid portion of the alternating portion and the girder, a longitudinally extending main reinforcing bar is disposed in the transverse space of each girder, wherein the main reinforcing bar extends from the lower abdomen to the center of the girder and vertically inclined upwardly. To be arranged in the direction so that the longitudinal bending of the reinforcing steel bars by the cast steel bars,

상기 각 거더의 양 단부를 횡방향으로 관통하여 종방향 하면 절곡 주철근과 결속되도록 횡방향 배력철근을 배치하고,The transverse reinforcing bars are disposed so as to be coupled to the bent main bars when they penetrate both ends of each girder in the transverse direction and run in the longitudinal direction.

상기 슬래브콘크리트 타설에 의하여 종방향 절곡 주철근과 횡방향 배력철근이 매립되도록 형성시키는 헌치부가 배제된 라멘교 시공방법을 제공한다.Provided is a method for constructing a ramen bridge in which a haunting portion for forming a longitudinal bending reinforcing bar and a transverse reinforcing bar is embedded by the slab concrete pouring.

이에 본 발명은 종래 라멘교에 형성된 헌치부를 배제하되 헌치부를 대체할 수 있도록 거더의 양 단부에 직접 종방향 절곡 주철근과 횡방향 배력철근을 배치하되 이러한 철근들은 종래 헌치부의 형상과 유사하게 형성시키고, 이러한 철근들이 슬래브콘크리트에 매립되도록 한 것이다.Accordingly, the present invention excludes the haunch formed in the conventional ramen bridge, but the longitudinally retracted cast iron bars and transverse reinforcement bars are disposed directly at both ends of the girder so as to replace the haunch portion, but the reinforcing bars are similar to the shape of the conventional haunch portion. And the reinforcing bars are embedded in the slab concrete.

또한 바람직하게는Also preferably

상기 거더는 상부플랜지, 복부 및 하부플랜지를 포함하여 구성되는 강재거더 또는 PSC 거더로서,The girder is a steel girder or a PSC girder including an upper flange, an abdomen and a lower flange,

강재거더인 거더에는 횡방향 배력철근이 관통될 수 있도록 복부에 횡방향 관통홀을 형성시키고,In the girder, which is a steel girder, a transverse through-hole is formed in the abdomen so that the transverse reinforcing bars can be penetrated,

PSC거더인 거더에는 PSC 거더 제작시 미리 횡방향 배력철근이 PSC 거더의 복부에 횡방향으로 설치되도록 하는 헌치부가 배제된 라멘교 시공방법을 제공한다.The girder, which is a PSC girder, is provided with a method of constructing a ramen bridge that eliminates haunting so that transverse reinforcing bars are installed laterally on the abdomen of the PSC girder when the PSC girder is manufactured.

또한 바람직하게는Also preferably

상기 종방향 절곡 주철근은The longitudinal bending cast steel

거더의 복부 하부로부터 거더 중앙쪽으로 연장되는 수평철근부;Horizontal reinforcing portions extending from the lower abdomen of the girder toward the center of the girder;

상기 수평철근부로부터 상방으로 절곡되어 연장되는 절곡철근부;를 포함하며, 상기 수평철근부와 절곡철근부의 경계는 라멘교의 헌치부 종방향 연장길이보다 커지도록 하는 헌치부가 배제된 라멘교 시공방법을 제공한다.And a bending reinforcing part extending upwardly from the horizontal reinforcing part, wherein the boundary between the horizontal reinforcing part and the bending reinforcing part is greater than the longitudinal extension length of the haunch part of the ramen bridge. To provide.

또한 바람직하게는Also preferably

상기 강재거더를 벽체부 상면에 강결시키는 단계는Hardening the steel girder on the upper surface of the wall portion

상기 벽체부 상면 내측에, 벽체부 상면보다 상방으로 돌출연장된 돌출지지턱이 형성되도록 하고,Inside the upper wall of the wall portion, a projection supporting jaw protruding upward from the upper wall portion is formed,

상기 벽체부 상면과 돌출지지턱 상면에 걸쳐 강재거더가 연장배치되도록 하고,Steel girders are arranged to extend over the upper surface of the wall portion and the upper surface of the protruding support jaw,

상기 교대 상면 외측에서 돌출지지턱을 지점부로 하여 강재거더의 양 단부를 하방으로 눌러지도록 하여 상기 강재거더의 양 단부가 벽체부에 강결되도록 하는 단계를 포함하도록 하는 헌치부가 배제된 라멘교 시공방법을 제공한다.Ramen bridge construction method excluding the haunchi portion including the step of pressing the both ends of the steel girder downward with the protruding support jaw as a point portion from the outside of the upper surface of the alternating upper surface To provide.

또한 바람직하게는Also preferably

상기 강재거더의 양 단부를 하방으로 눌러지도록 하여 상기 강재거더의 양 단부가 벽체부에 강결되도록 하는 단계는Pressing both ends of the steel girder downward so that both ends of the steel girder is rigid to the wall portion

상기 강재거더의 상부플랜지 및 하부플랜지에 형성된 관통공에는 벽체부 내부로부터 상방으로 연장되어 벽체부 상면을 거쳐 상기 관통공에 삽입된 강봉을 포함하는 강봉을 포함하는 단부긴장재가 설치되도록 하고,The through-holes formed in the upper flange and the lower flange of the steel girder to be installed upwards from the inside of the wall portion is provided an end tensioning material including a steel rod including a steel rod inserted into the through hole through the upper wall portion,

상기 단부긴장재를 상방으로 인장시킨 후 단부긴장재의 상단이 강재거더 상부플랜지 상면에 정착되도록 하는 헌치부가 배제된 라멘교 시공방법을 제공한다.After tensioning the end tensioner upwards, there is provided a ramen bridge construction method in which a haunting portion is removed so that an upper end of the end tensioner is fixed to the upper surface of the steel girder upper flange.

본 발명에 의해 헌치부가 배제되어 교량 계획고 문제 때문에 라멘교를 시공하기 어려운 현장에서도 이를 쉽게 해결할 수 있고 미관도 우수해질 뿐 아니라 라멘교의 장점을 그대로 살리면서도 경량화가 가능하여 보다 효율적이고 경제적인 라멘교 시공이 가능하게 된다.The present invention can be easily solved even in the field where it is difficult to construct a ramen bridge due to the bridge design problem, and the aesthetics are also excellent, and the weight can be reduced while maintaining the advantages of the ramen bridge. Teaching is possible.

본 발명의 범위는 상기 상세한 설명보다는 후술하는 특허청구범위에 의하여 나타내어지며, 특허청구범위의 의미 및 범위 그리고 그 균등 개념으로부터 도출되는 모든 변경 또는 변형된 형태가 본 발명의 범위에 포함되는 것으로 해석되어야 한다.The scope of the present invention is shown by the following claims rather than the above description, and all changes or modifications derived from the meaning and scope of the claims and their equivalents should be construed as being included in the scope of the present invention. do.

도 1a는 종래 철근콘크리트 라멘교의 사사도,
도 1b는 종래 철근콘크리트 라멘교의 헌치부 구성도,
도 2a는 종래 강합성 라멘교의 헌치부 구성도
도 2b 및 도 2c는 본 발명에 의한 헌치부 부분 발췌사시도,
도 3a, 도 3b, 도 3c 및 도 3d는 본 발명에 의한 라멘교 시공순서도,
도 4는 본 발명의 거더를 도시한 것이다.
Figure 1a is a perspective view of a conventional reinforced concrete ramen bridge,
Figure 1b is a configuration of the haunting portion of the conventional reinforced concrete ramen bridge,
Figure 2a is a configuration of the haunting portion of the conventional steel composite ramen bridge
Figure 2b and Figure 2c is a perspective view of the portion of the haunting portion according to the present invention,
3a, 3b, 3c and 3d is a ramen bridge construction sequence according to the present invention,
4 illustrates the girder of the present invention.

아래에서는 첨부한 도면을 참조하여 본 발명이 속하는 기술분야에서 통상의 지식을 가진 자가 용이하게 실시할 수 있도록 본 발명의 실시예를 상세히 설명한다. 그러나 본 발명은 여러 가지 상이한 형태로 구현될 수 있으며 여기에서 설명하는 실시예에 한정되지 않는다. 그리고 도면에서 본 발명을 명확하게 설명하기 위해서 설명과 관계없는 부분은 생략하였으며, 명세서 전체를 통하여 유사한 부분에 대해서는 유사한 도면 부호를 붙였다.DETAILED DESCRIPTION Hereinafter, exemplary embodiments of the present invention will be described in detail with reference to the accompanying drawings so that those skilled in the art may easily implement the present invention. The present invention may, however, be embodied in many different forms and should not be construed as limited to the embodiments set forth herein. In the drawings, parts irrelevant to the description are omitted in order to clearly describe the present invention, and like reference numerals designate like parts throughout the specification.

< 헌치부가 배제된 라멘교 ><Ramen Church excluded from Hunchi>

본 발명의 라멘교는Ramen bridge of the present invention

예컨대 도 3d와 같이 교대부(200)를 지반에 설치하고, 상기 교대부 상면 사이에 종방향으로 연장되도록 하면서 횡방향으로 다수가 이격되도록 설치된 거더(300)를 상기 교대부에 강결시키고, 상기 거더(300)가 매립되도록 하면서 거더 횡방향 사이 공간 및 상부에 슬래브콘크리트를 타설하여 상기 교대부(200)와 슬래브(300)가 서로 일체로 형성되도록 하는 단계를 포함하는 라멘교 시공방법에 의하여 시공된다.For example, as shown in FIG. 3d, the alternating unit 200 is installed on the ground, and the girders 300 installed so as to be spaced apart in the lateral direction while extending in the longitudinal direction between the upper portions of the alternating parts are tightened to the alternating unit, and the girder It is constructed by the ramen bridge construction method comprising the step of placing the slab concrete in the space between the girder transverse direction and the upper portion while allowing the 300 to be buried to form the alternating portion 200 and the slab 300 integrally with each other. .

도 2a는 라멘교(100) 있어 있어서, 배제되는 헌치부(H)를 점선으로 표시한 것인데 상기 헌치부(H)의 내부에는 종방향으로 연장되는 주철근과 횡방향으로 연장되는 배력철근이 배근되어 있음을 알 수 있다.Figure 2a is a ramen bridge 100, which shows the haunting portion (H) to be removed in a dotted line, the reinforcing bars extending in the longitudinal direction and the reinforcing bars extending in the transverse direction are placed inside the haunch (H) It can be seen that.

이는 헌치부를 보강하기 위한 철근들이라 할 수 있는데 본 발명은 이러한 헌치부를 배제하므로 이러한 철근을 역시 배제시킬 수 있어 라멘교 시공성이 증진될 수 있게 됨을 알 수 있으며 사용되는 거푸집 형상도 최적화시킬 수 있다.This can be referred to as reinforcing bars for reinforcing the haunting part. The present invention excludes such a haunting part, so that the reinforcing bar can also be excluded, so that the workability of the ramen bridge can be improved, and the form shape used can be optimized. .

단지, 상기 헌치부에 발생하는 휨 부모멘트를 제어하기 위하여 본 발명은 종방향 절곡 주철근(510)과 횡방향 배력철근(520)을 거더(300)에 직접 설치하게 된다.However, the present invention is to install the longitudinal bending main reinforcing bars 510 and the transverse reinforcing bars 520 directly to the girder 300 in order to control the bending parent generated in the haunch.

이에 상기 본 발명의 종방향 절곡 주철근(510)은 종래 헌치부에 배근되는 주철근에 대응되고, 본 발명의 횡방향 배력철근(520)은 종래 헌치부에 배근되는 배력철근에 대응되며 이러한 철근들(510,520)은 거더(300)에 직접 관통하여 설치하게 된다.The longitudinal bending reinforcing bar 510 of the present invention corresponds to the main reinforcing bar reinforcement in the conventional haunche, the transverse reinforcing bar 520 of the present invention corresponds to the reinforcing bar reinforcement in the conventional haunche and such reinforcement ( 510 and 520 are installed through the girder 300 directly.

도 2b 및 도 2c는 이러한 철근들(510,520)의 설치방법과 관련하여 강재거더(310) 또는 PSC 거더(330)를 기준으로 살펴본 것이다.2B and 2C illustrate the steel girder 310 or the PSC girder 330 in relation to the installation method of the rebars 510 and 520.

먼저 도 2b는 상기 종방향 절곡 주철근(510)과 횡방향 배력철근(520)을 강재거더(310)에 적용한 예를 도시한 것인데,First, FIG. 2B illustrates an example in which the longitudinal bending main reinforcing bars 510 and the transverse reinforcing bars 520 are applied to the steel girder 310.

먼저, 상기 종방향 절곡 주철근(510)를 강재 거더의 횡방향 사이 공간에 종방향으로 연장되도록 하되 상기 종방향 절곡 주철근(510)은 강재 거더 하부 복부로부터 거더 중앙쪽으로 연장되면서 상방경사지게 종방향으로 배치되도록 설치하게 된다.First, the longitudinal bending cast iron 510 is extended in the longitudinal direction in the transverse space of the steel girder, but the longitudinal bending cast steel 510 extends toward the center of the girder from the lower abdomen of the steel girder and disposed in the longitudinal direction Install it if possible.

이에 상기 종방향 절곡 주철근(510)은The longitudinal bending cast steel 510 is

강재 거더(300)의 복부 하부로부터 거더 중앙쪽으로 연장되는 수평철근부(511); 및 상기 수평철근부로부터 상방으로 절곡되어 연장되는 절곡철근부(512);를 포함하도록 형성시키고 있음을 알 수 있으며,A horizontal rebar portion 511 extending from the lower abdomen of the steel girder 300 toward the center of the girder; It can be seen that it is formed to include; and a bending reinforcing bar portion 512 is bent upwardly extending from the horizontal rebar portion;

상기 수평철근부(511)의 연장길이는 강재거더의 높이와 슬래브의 두께를 합친 길이 이상으로 형성되도록 함이 바람직하다.The extension length of the horizontal reinforcing bar 511 is preferably formed to be equal to or more than the combined length of the height of the steel girder and the thickness of the slab.

나아가 상기 횡방향 배력철근(520)은 강재 거더의 양 단부를 횡방향으로 관통하도록 설치하는데 상기 종방향 절곡 주철근(510)과 결속될 수 있도록 배치시키게 된다.Furthermore, the transverse reinforcement bar 520 is installed to penetrate both ends of the steel girders in the transverse direction, so that the transverse reinforcing bars 520 can be engaged with the longitudinally bending main reinforcing bars 510.

이에 강재 거더(310)의 복부에는 횡방향 배력철근(520)이 관통될 수 있도록 철근관통홀(319)을 형성시키게되며, In the abdomen of the steel girder 310 to form a rebar through hole 319 so that the transverse reinforcement bar 520 can pass through,

상기 철근관통홀(319)은 종방향 절곡 주철근(510)의 배치형태에 대등하여 즉 수평철근부(511)와 수평철근부로부터 상방으로 절곡되어 연장되는 절곡철근부(512)의 배치 형태에 대응하여 역시 수평 철근관통홀(319a)과 경사 철근관통홀(319b)로 형성되어 결국 수평으로 연장 형성되다가 상방으로 절곡 연장되도록 형성시키게 된다.The rebar through hole 319 corresponds to the arrangement form of the longitudinal bending main reinforcing bars 510, that is, the arrangement form of the bending reinforcing bar portions 512 that are bent upward from the horizontal reinforcing bars 511 and the horizontal reinforcing bars 510. The horizontal rebar through hole 319a and the inclined rebar through hole 319b are also formed to extend horizontally and then bent upwardly.

이에 상기 횡방향 배력철근(520)은 먼저 설치된 종방향 절곡 주철근(510)과 가는 철선등(미도시)으로 서로 결속시켜 최종 강재 거더(310)에 횡방향 배력철근(520)과 종방향 절곡 주철근(510)을 설치하게 된다.Accordingly, the transverse reinforcing bars 520 are first bound to each other by the longitudinally bending main reinforcing bars 510 and thin wire lamps (not shown), so that the transverse reinforcing bars 520 and the longitudinal bending main bars in the final steel girders 310. 510 will be installed.

이때 횡방향 배력철근(520)을 먼저 설치하고 종방향 절곡 주철근(510)을 설치해도 상관은 없다.At this time, the transverse reinforcement bar 520 may be installed first, and the longitudinal bending main reinforcing bar 510 may be installed.

이에 이러한 횡방향 배력철근(520)과 종방향 절곡 주철근(510)의 설치가 완료되면 슬래브콘크리트를 타설하여 이러한 횡방향 배력철근(520)과 종방향 절곡 주철근(510)이 매립되도록 함으로써 본 발명의 라멘교에 있어서는 헌치부가 배제될 수 있도록 함을 알 수 있다.Thus, when the installation of the transverse reinforcing bar 520 and the longitudinal bending cast steel 510 is completed, the slab concrete is poured so that the transverse reinforcing bar 520 and the longitudinal bending cast steel 510 are buried. It can be seen that in Ramenism, the hunt can be excluded.

본 발명의 라멘교에 있어 슬래브와 교대부의 강결부위에 발생하는 휨 부모멘트에 대한 저항메커니즘은 다음과 같다.In the ramen bridge of the present invention, the resistance mechanism of the bending parental force generated in the hardened portion of the slab and the alternating portion is as follows.

먼저, 슬래브에 작용하는 여러 하중은 강재 거더에 전달되고 이러한 강재 거더와 강결된 교각부에도 상기 하중이 전달된다.First, the various loads acting on the slab are transmitted to the steel girders, and the loads are also transmitted to the steel girders and the pier to be rigid.

이에 상기 강재 거더에 작용하는 하중은 강재 거더에 설치된 횡방향 배력철근(520)에 직접 전달되고, 상기 횡방향 배력철근(520)과 결속된 종방향 절곡 주철근(510)에도 역시 직접 전달된다.Accordingly, the load acting on the steel girder is directly transmitted to the transverse reinforcing bar 520 installed in the steel girder, and is also directly transmitted to the longitudinal bending main reinforcing bar 510 bound to the transverse reinforcing bar 520.

이에 하중은 종방향 절곡 주철근(510)을 통해 주변의 콘크리트에 하중을 전달하게 됨을 알 수 있으며, 이러한 하중이 강도가 큰 철근들로부터 콘크리트로 분산 전달되면서 상기 하중에 대한 휨 부모멘트가 효과적으로 상쇄되게 된다.Therefore, it can be seen that the load transfers the load to the surrounding concrete through the longitudinal bending cast reinforcing bars 510. As the load is distributed and transmitted from the reinforcing bars to the concrete, the bending parent moment for the load is effectively canceled. do.

이는 종래 라멘교에 있어 헌치부가 헌치부 콘크리트에 먼저 휨 부모멘트가 전달되도록 하고 상기 헌치부 콘크리트에 배근된 철근들이 휨 부모멘트를 최종 부담하도록 하는 것과는 달리This is different from the conventional ramen bridge, in which the posterior portion of the haunch portion is first delivered to the concrete of the haunch, and the reinforcing bars reinforced to the concrete of the haunch portion ultimately bear the bending momentum.

본 발명은 거더에 직접 설치된 강도가 큰 철근들이 휨 부모멘트를 먼저 상당부분 부담하도록 하고 최종 상기 철근들 주변의 슬래브콘크리트가 휨 부모멘트를 부담하도록 함을 알 수 있다.The present invention can be seen that the high-strength reinforcing bars directly installed on the girder bear a large portion of the bending parent moment first, and the slab concrete around the last reinforcing bars bear the bending parent moment.

이에 본 발명의 종방향 절곡 주철근(510)과 횡방향 배력철근(520)은 그 형성위치 및 배치형태에 의하여 종래 헌치부의 역할을 대체할 수 있게됨을 알 수 있다.Accordingly, it can be seen that the longitudinal bending main reinforcing bar 510 and the transverse reinforcing bar 520 can replace the role of the conventional haunting unit by the formation position and the arrangement form.

도 2c는 도 2b와 대비하여 강재 거더(310)가 아닌 PSC 거더(330)에 앞서 살펴본 종방향 절곡 주철근(510)과 횡방향 배력철근(520)을 설치하는 예라 할 수 있다.FIG. 2C may be an example of installing the longitudinally bent main reinforcing bars 510 and the transverse reinforcing bars 520 described above in relation to the PSC girder 330 instead of the steel girder 310 in comparison with FIG. 2B.

상기 PSC 거더(330)는 철근콘크리트로 제작하게 되므로 강재 거더와 같이 철근관통홀(319)을 형성시키기가 용이하지 않을 수 있다.Since the PSC girder 330 is made of reinforced concrete, it may not be easy to form the reinforcing through hole 319 such as steel girder.

이에 철근관통홀(319)를 형성시키지 않고 PSC 거더(330) 제작시 미리 상기 횡방향 배력철근(520)이 PSC 거더 단부에 횡방향으로 돌출되도록 미리 형성시키게 된다.Accordingly, when the PSC girder 330 is manufactured without forming the rebar through hole 319, the transverse reinforcement 520 is formed in advance so as to protrude in the lateral direction at the end of the PSC girder.

이에 횡방향 배력철근(520)이 미리 형성된 PSC 거더(330)에 상기 종방향 절곡 주철근(510)을 설치하여 서로 결속시키는 방식을 따르게 된다.Accordingly, the longitudinally bending main reinforcing bars 510 are installed in the PSC girder 330 in which the transverse reinforcing bars 520 are formed in advance.

물론 상기 횡방향 배력철근(520)의 형성위치 및 배치형태는 강재 거더의 경우와 동일하고, 종방향 절곡 주철근(510)의 형성위치 및 배치형태 역시 강재 거더의 경우와 동일하다.Of course, the formation position and arrangement of the transverse reinforcement bar 520 is the same as the case of the steel girder, and the formation position and arrangement of the longitudinal bending main reinforcement 510 is also the same as the case of the steel girder.

물론 종래 헌치부를 대체하는 기능 및 작용도 강재 거더의 경우와 동일하다.Of course, the function and action of replacing the conventional haunbu is the same as the case of steel girders.

결국, 본 발명의 라멘교는 종방향 절곡 주철근(510)과 횡방향 배력철근(520)을 거더에 위치시키고(형성위치) 및 거더의 단부 하부에서 수평으로 연장되다가 종방향으로 상방절곡되도록 하는 배치(배치형태)를 통하여 종래 라멘교의 헌치부를 배제시킬 수 있음을 알 수 있다.As a result, the ramen bridge of the present invention is arranged so that the longitudinal bending reinforcing bar 510 and the transverse reinforcing bar 520 are located in the girder (formation position) and extend horizontally below the end of the girder and then bend upward in the longitudinal direction. It can be seen that the arrangement can eliminate the haunting portion of the conventional ramen bridge.

< 본 발명의 헌치부가 배제된 라멘교 시공방법><Ramen construction method without the haunting part of the present invention>

이러한 본 발명의 라멘교는 크게, 교대부(200), 거더(300) 및 슬래브(400)로 크게 구성되며 이는 시공순서를 고려하여 설명하기로 한다.The ramen bridge of the present invention is largely composed of an alternating portion 200, a girder 300 and a slab 400, which will be described in consideration of the construction order.

먼저, 도 3a와 같이 후술되는 교대부(200)를 시공하기 위한 위치의 지반(G)에 린콘트리트(120)를 형성시켜 후술되는 교대부(200)의 시공이 용이하도록 하게 되며 이에 린콘트리트(120)는 교대부 저면의 면적을 고려하여 형성시키되 도 2a에는 직사각형 형태로 도시됨을 알 수 있다.First, by forming a lean concrete 120 in the ground (G) of the position for the construction of the alternating portion 200 to be described later, as shown in Figure 3a to facilitate the construction of the alternating portion 200 to be described later lean concrete ( 120 is formed in consideration of the area of the lower surface of the alternate portion, it can be seen that it is shown in a rectangular shape in Figure 2a.

다음으로는 상기 린콘트리트(120)와 일체화되도록 교대부(200)를 시공하게 되며 이는 미도시된 거푸집을 이용하여 철근콘크리트체로 형성시키게 된다.Next, the alternating portion 200 is constructed to be integrated with the lean concrete 120, which is formed of reinforced concrete using a mold not shown.

이러한 교대부(200)는 벽체부(210)로서 전체적으로 사각박스체 형태로 형성되도록 하는데 린콘트리트(120) 상부에 형성되도록 하게 되며 상면에는 내부에 배근된 철근(211)이 상방으로 연장되도록 하고,The alternating portion 200 is to be formed in a rectangular box shape as a wall portion 210 as a whole to be formed on the upper surface of the lin concrete 120 and the upper reinforcement 211 is arranged in the upper surface to extend upwards,

강봉을 포함하는 단부긴장재(212)가 벽체부(210) 상면으로부터 상방으로 연장 돌출되도록 형성시키게 된다.End tension member 212 including a steel bar is formed to protrude upward from the upper surface of the wall portion (210).

상기 단부긴장재(212)는 후술되는 거더(300)를 벽체부(210)에 강결시키기 위한 것으로써 벽체부(210) 내측에 하단이 고정구(214)에 의하여 고정되도록 미리 설치한다.The end tensioning material 212 is installed in advance to fix the girder 300 to be described later to the wall portion 210 so that the lower end is fixed by the fastener 214 inside the wall portion 210.

또한 상기 벽체부(210) 상면(A)의 경우 그 상면 내측으로는 돌출지지턱(213)이 형성되도록 한다.In addition, in the case of the upper surface A of the wall portion 210, the protruding support jaw 213 is formed inside the upper surface.

이러한 돌출지지턱(213)은 벽체부(210) 상면보다는 다소 높게 형성된 단턱이되며, 이러한 돌출지지턱(213)에 후술되는 거더(300)가 지지되도록 하게되며, 거더(300)에 있어서는 일종의 지점부로서 역할을 하게 된다.The protruding support jaw 213 is a step formed somewhat higher than the upper surface of the wall portion 210, such that the girder 300 to be described later is supported on the protruding support jaw 213, a kind of point in the girder 300 It will act as wealth.

이에 상기 돌출지지턱(213)의 형성 위치를 교대 상면의 내측이라고 지칭하고, 상기 돌출지지턱(213)을 기준으로 그 좌측을 교대 상면의 외측이라고 지칭하기로 한다.Accordingly, the position at which the protruding support jaw 213 is formed is referred to as the inner side of the alternating upper surface, and the left side of the protruding support jaw 213 is referred to as the outer side of the alternating upper surface.

상기 돌출지지턱(213)의 기능에 대하여는 후술된다.The function of the protrusion supporting jaw 213 will be described later.

다음으로는 도 3b와 같이 거더(300)를 제작하여 상기 교대부(200)를 구성하는 벽체부(210)에 강결시키게 된다.Next, as shown in FIG. 3b, the girder 300 is manufactured to be firmly attached to the wall portion 210 constituting the shift portion 200.

먼저, 상기 거더(300)는 도 4와 같이 I형 강재거더를 이용하게 되는데, 이러한 강재거더(310)는 상부플랜지(311), 복부(312) 및 하부플랜지(313)으로 형성되어 있음을 알 수 있으며 연장길이는 라멘교의 경간장을 고려하여 상기 거더(300)가 벽체부(210) 상면에 지지될 수 있을 정도로 형성시키게 된다.First, the girder 300 is to use the I-shaped steel girder as shown in Figure 4, this steel girder 310 is found that the upper flange 311, the abdomen 312 and the lower flange 313 is formed. The length of the girder 300 may be formed to be supported on the upper surface of the wall portion 210 in consideration of the span length of the ramen bridge.

또한 앞서 살펴본 종방향 절곡 주철근(510) 및 횡방향 배력철근(520)에 간섭되지 않은 부위에 단부마감판(314)이 형성되도록 하여 비틀림 및 좌굴에 유리하도록 하고, 상부플랜지와 하부플랜지 상하 사이에는 수직판 형태의 수직 스티프너(315)를 다수 길이방향으로 이격시켜 단부 보강이 가능하도록 하는 것이 바람직하다.In addition, the end finishing plate 314 is formed in a portion which is not interfered with the longitudinally bending main reinforcing bar 510 and the transverse reinforcing bar 520 described above to be advantageous for torsion and buckling, and between the upper and lower flanges. The vertical stiffener 315 in the form of a vertical plate is preferably spaced apart in the longitudinal direction to enable end reinforcement.

이때 상기 수직 스티프너중 어느 하나에는 연결판(316)이 일체로 형성되도록 하고, 강재거더(310) 복부 사이에 강재 가로보(320)의 양 단부가 볼트 및 너트에 의하여 연결되도록 함으로써 강재거더(310)가 횡방향으로 구속되도록 함이 바람직하다.At this time, any one of the vertical stiffener is connected to the plate 316 is integrally formed, and the steel girder 310 by connecting both ends of the steel cross beam 320 between the abdomen of the steel girder 310 by bolts and nuts 310 It is desirable to allow the to restrain transversely.

이에 상기 연결판(316)과 가로보(320)의 복부에는 볼트홀이 각각 다수 형성시키게 된다.Accordingly, a plurality of bolt holes are formed in the abdomen of the connecting plate 316 and the cross beam 320, respectively.

또한, 후술되는 단부긴장재(212)가 상부플랜지와 하부플랜지를 관통할 수 있도록 상기 상부플랜지와 하부플랜지에는 플랜지 관통홀(317)이 각각 형성되도록 한다.In addition, a flange through hole 317 is formed in each of the upper flange and the lower flange so that the end tension member 212 to be described later may pass through the upper flange and the lower flange.

또한, 강재거더(310)의 양 단부는 그 배치상 라멘교의 우각부에 위치하게 되므로 하중이 집중된다. 이에 하중 집중에 의한 보강을 위하여 각각의 거더 단부들을 관통하여 형성되는 횡방향 철근조립체(318)에 의하여 단부가 보강되도록 함이 바람직하다.In addition, since both ends of the steel girder 310 is located in the right angle of the ramen bridge in the arrangement, the load is concentrated. The end is reinforced by the transverse reinforcing bar assembly 318 formed through the respective girder ends for reinforcement by load concentration.

이러한 횡방향 철근조립체(318)는 횡방향으로 연장되어 강재거더의 단부 들을 관통하는 주철근(318a)과 상기 주철근을 외곽으로 감싸는 스터럽철근(318b)을 포함시켜 제작하게 된다.The transverse reinforcing bar assembly 318 is manufactured by including a main reinforcing bar 318a extending in the transverse direction and penetrating the ends of the steel girder and a stirrup reinforcing bar 318b surrounding the main bar.

이에 상기 횡방향 철근조립체(318)는 내측에 가로보(320)를 감싸면서 강재거더의 단부를 횡방향으로 관통하도록 설치시키고 있음을 알 수 있다.Accordingly, it can be seen that the transverse rebar assembly 318 is installed to penetrate the end of the steel girder in the transverse direction while wrapping the cross beam 320 inside.

역시 앞서 살펴본 앞서 살펴본 종방향 절곡 주철근(510) 및 횡방향 배력철근(520)에 간섭되지 않도록 상기 가로보, 횡방향 철근조립체를 설치하게 된다.In addition, the horizontal beam, the horizontal reinforcing bar assembly is installed so as not to interfere with the above-described longitudinally bending main reinforcing bars 510 and the transverse reinforcing bar 520.

이에 강재거더(310)로 제작된 거더(300)를 앞서 살펴본 교대부(200)의 벽체부(210)에 강결시키게 된다.Accordingly, the girder 300 made of the steel girder 310 is hardened to the wall portion 210 of the shift portion 200 described above.

즉, 강재거더(310)의 양 단부가 벽체부(210) 상면에 강결되도록 하게 되는데 이는 벽체부 상면에 형성된 단부긴장재(212)와 돌출지지턱(213)을 이용하게 된다.That is, both ends of the steel girder 310 is to be rigid on the upper surface of the wall portion 210, which uses the end tensioning material 212 and the protruding support jaw 213 formed on the upper surface of the wall portion.

구체적으로 살펴보면, 도 3c와 같이 상기 강재거더(310)의 양 단부는 벽체부(210) 상면 외측까지 연장되도록 하여, 상기 양 단부로부터 중앙쪽으로 이격된 위치에서 벽체부 상면 내측에 형성된 돌출지지턱(213)에 지지되도록 설치하게 된다.Specifically, as shown in FIG. 3c, both ends of the steel girder 310 extend to the outer side of the upper surface of the wall portion 210, and protruding support jaw formed on the inner side of the upper surface of the wall at a position spaced from the both ends toward the center ( 213) to be supported.

이와 같이 돌출지지턱(213)에 지지되도록 설치된 강재거더(310)는 앞서 살펴본 단부긴장재(212)인 강봉이 그 양 단부를 관통하도록 하게 되는데, 이를 위하여 강재거더의 양 단부는 상기 강봉이 관통될 수 있도록 플랜지 관통홀(317)을 형성시키고 있음은 살펴본 바와 같다.As described above, the steel girder 310 installed to be supported by the protruding support jaw 213 allows the steel bar, which is the end tensioning material 212, to pass through both ends thereof. For this purpose, both ends of the steel girder may be penetrated by the steel bar. The flange through hole 317 is formed to be as described above.

이로서, 강재거더(310)는 벽체부(210)의 돌출지지턱(213)에 지지되면서 단부긴장재(212)인 강봉에 의하여 관통되어 초기 세팅되도록 하게 됨을 알 수 있다.As a result, the steel girder 310 is supported by the protruding support jaw 213 of the wall portion 210 to be penetrated by the steel rod which is the end tensioning material 212 to be initially set.

이러한 상태에서는 벽체부(210)의 돌출지지턱(213)에 강재거더(310) 양 단부가 단순 지지되도록 설치하는 것이 되어 상기 돌출지지턱을 기준으로 파일캡핑부의 외측으로는 휨 부모멘트(-M)이 발생하게 되고, 교대의 내측부터 중앙까지는 휨 정모멘트(+M)이 발생하게 됨을 알 수 있다.In this state, both ends of the steel girder 310 are simply installed on the protruding support jaw 213 of the wall portion 210 so that the bending cap is extended to the outside of the pile capping part based on the protruding support jaw (-M). ) Is generated, and the bending constant moment (+ M) is generated from the inner side to the center of the shift.

이때, 상기 휨 정모멘트(+M)는 강재거더(310)의 자중에 의하여 발생하게 되는데 그 크기가 상대적으로 휨 부모멘트(-M)보다는 크기 때문에 이를 구조적으로 줄일 수 있다면, 그 만큼 강재거더의 단면을 보다 효율적이고 경제적으로 제작할 수 있고, 동일한 단면 및 형고라면 보다 장지간의 라멘교 시공이 가능하게 된다.At this time, the bending positive moment (+ M) is caused by the weight of the steel girder 310, if the size is relatively larger than the bending parent moment (-M) if it can be structurally reduced, as much as that of the steel girder The cross section can be produced more efficiently and economically, and if the same cross section and the height of the cross section can be used, the ramen bridge construction can be made longer.

이를 위하여 본 발명에서는 벽체부(210)의 돌출지지턱(213)을 기준으로 강재거더(310)의 양 단부를 하방으로 눌러내리는 공종을 도입하게 된다.To this end, the present invention introduces a ball mill that pushes down both ends of the steel girder 310 based on the protruding support jaw 213 of the wall portion 210.

이러한 공종은 단부긴장재(212)가 위치한 곳에서 행하게 되며, 구체적으로는 단부긴장재(212)인 강봉을 인장한 후, 강재거더(310)의 상면에 정착시킴으로서 가능하게 된다.This work is performed where the end tensioning material 212 is located, specifically, by tensioning the steel bar that is the end tensioning material 212, it is possible to settle on the upper surface of the steel girder 310.

이에 강재거더(310)의 양 단부에는 강재거더(310)에 발생된 휨 부모멘트(-M)는 감소시키면서, 휨 정모멘트(+M)는 감소되도록 하는 효과를 가질 수 있게 된다.Accordingly, both ends of the steel girder 310 may have an effect of reducing the bending parent moment (-M) generated in the steel girder 310 and reducing the bending positive moment (+ M).

상기 단부긴장재(212)인 강봉의 인장은 강봉의 상단에 인상유압잭을 설치하여 상방으로 긴장후, 상기 긴장된 상태가 유지되도록 긴장된 강재를 강재거더(310) 상부플랜지(311) 상면에 너트로 고정시킴으로서 가능할 수 있을 것이다.The tension of the steel bar, which is the end tensioning material 212, by installing an impression hydraulic jack on the upper end of the steel bar and tensioning upwards, by fixing the tensioned steel to a steel girder 310 upper flange 311 with a nut to maintain the tensioned state with a nut. It may be possible.

이와 같은 단부긴장재인 강봉을 인장후 정착하게 되면, 돌출지지턱 사이에 위치한 강재거더는 위로 만곡되는 형태로 일종의 솟음(캠버, 휨 모멘트 발생)이 발생하게 되는데, 이러한 솟음 처리에 의하여 강재거더의 자중에 의한 휨 모멘트를 상기 솟음에 의하여 상쇄시키는 효과를 가질 수 있게 되며, 이는 결국 강재거더의 자중에 의하여 발생하는 휨 정모멘트(+M)를 감소시키는 역할을 하게 됨을 알 수 있으며,When the steel bar, which is an end tensioning material, is fixed after being tensioned, the steel girder located between the protruding support jaws generates a kind of rise (camber, bending moment) in the form of bending upward. It is possible to have an effect of canceling the bending moment by the rise by the rise, it can be seen that it serves to reduce the bending constant moment (+ M) caused by the weight of the steel girder eventually,

상기 단부긴장재인 강봉을 인장후 정착할 때 돌출지지턱을 기준으로 교대 외측에서는 강재거더의 양 단부가 하방으로 눌려지게 되어 강재거더 설치에 의한 상기 휨 부모멘트(-M)가 상쇄되어 라멘교에 있어 벽체부(210)에 강재거더의 경간중앙부에서의 휨 정부모멘트 감소가 가능하게 된다.Both ends of the steel girder are pressed downward from the outer side of the shift when the steel bar serving as the end tensioning member is tensioned and fixed, and the bending parent moment (-M) due to the installation of the steel girder is offset to the ramen bridge. There is a wall portion 210, it is possible to reduce the bending moment in the middle section of the steel girder.

이에 본 발명에 의한 거더로서 강재거더의 양 단부가 벽체부 상면에 강결되도록 하되 이를 벽체부 상면에 형성된 단부긴장재(212)와 돌출지지턱(213)을 이용하는 경우 경간부를 장경간화 할 수 있어 종래 RC 슬래브에 의한 라멘교와 대비하여 경간장에 대한 한계를 극복할 수 있으며, 후술되는 바와 같이 슬래브에 강재거더를 매입시키는 방식으로 슬래브를 시공하게 되므로 경량화가 가능하여 경제성이 확보될 수 있다.Therefore, as the girder according to the present invention, both ends of the steel girder are stiffened on the upper surface of the wall portion, but when the end tension member 212 and the protruding support jaw 213 formed on the upper surface of the wall portion can be used, the span can be made longer. In contrast to the ramen bridge by RC slab can overcome the limitations for the span length, and as described below, the slab is constructed by embedding steel girder in the slab, so that the weight can be reduced and economical efficiency can be secured.

이에 본 발명은 상기 강재거더(310)의 양 단부를 하방으로 눌러지도록 하여 상기 강재거더의 양 단부가 벽체부(210)에 강결되도록 하게 됨을 알 수 있다.Thus, the present invention can be seen that both ends of the steel girder is pressed down to both ends of the steel girder 310 to the wall portion 210.

다음으로는 도 3d와 같이 슬래브(400)를 형성시키게 되는데 이러한 슬래브는 미도시된 거푸집을 이용하여 슬래브콘크리트를 타설함으로서 이루어지게 되어 최종 헌치부가 배제된 라멘교 시공이 완성됨을 알 수 있다.Next, as shown in FIG. 3d, the slab 400 is formed, and the slab is formed by placing slab concrete using a formwork not shown, thereby completing the construction of the ramen bridge, which excludes the final haunting portion.

120: 린콘크리트 200: 교대부
210: 벽체부 212: 단부긴장재
213: 돌출지지턱
300: 거더 310: 강재 거더
311: 상부플랜지 312: 복부
313: 하부플랜지 314: 단부마감판
315: 수직 스티프너 316: 연결판
317: 플랜지 관통홀 318: 횡방향 철근조립체
319: 철근관통홀 320: (강재)가로보
330: PSC 거더 400: 슬래브
510: 종방향 절곡 주철근 520: 횡방향 배력 철근
120: lean concrete 200: shift
210: wall portion 212: end tensioning material
213: protruding support jaw
300: girders 310: steel girders
311: upper flange 312: abdomen
313: lower flange 314: end finish plate
315: vertical stiffener 316: connecting plate
317: flanged through hole 318: transverse reinforcing bar assembly
319: steel reinforcing hole 320: steel
330: PSC girder 400: slab
510: longitudinal bending of the reinforcing bar 520: transverse lifting bar

Claims (5)

교대부(200)를 지반에 설치하고, 상기 교대부(200) 상면 사이에 종방향으로 연장되도록 하면서 횡방향으로 다수가 이격되도록 설치된 거더(300)를 상기 교대부(200)에 강결시키고, 상기 거더(300)가 매립되도록 하면서 거더(300) 횡방향 사이 공간 및 상부에 슬래브콘크리트를 타설하여 상기 교대부(200)와 슬래브(400)가 서로 일체로 형성되도록 하는 단계를 포함하는 라멘교 시공방법에 있어서,
상기 교대부(200)와 거더(300)의 강결부위에 형성되는 헌치부를 제거하기 위하여 각 거더(300)의 횡방향 사이 공간에 종방향으로 연장되는 주철근을 배치하되, 상기 주철근은 거더(300) 하부 복부(312)로부터 거더(300) 중앙쪽으로 연장되면서 상방경사지게 종방향으로 배치되도록 하여 거더(300)에 상기 주철근에 의한 종방향 절곡 주철근(510)이 배치되도록 하고,
상기 각 거더(300)의 양 단부를 횡방향으로 관통하여 종방향 절곡 주철근(510)과 결속되도록 횡방향 배력철근(520)을 배치하고,
상기 슬래브콘크리트 타설에 의하여 종방향 절곡 주철근(510)과 횡방향 배력철근(520)이 매립되도록 형성시키는 것을 특징으로 하는 헌치부가 배제된 라멘교 시공방법.
The alternating portion 200 is installed on the ground, and the girders 300 installed so as to be spaced apart in the lateral direction while extending in the longitudinal direction between the upper portions of the alternating portion 200 are rigidly fastened to the alternating portion 200, and Ramen bridge construction method comprising the step of placing the slab concrete in the space between the girder 300 and the transverse direction while the girder 300 is embedded to form the alternating portion 200 and the slab 400 integrally with each other To
In order to remove the haunch formed in the rigid portion of the alternating portion 200 and the girder 300, the main reinforcing bars extending in the longitudinal direction are disposed in the transverse space of each girder 300, the main reinforcing bar girder 300 ) Longitudinally bent cast iron reinforcement 510 by the main reinforcement is arranged on the girder 300 by being disposed in the longitudinal direction to extend upward from the lower abdomen 312 toward the center of the girder 300,
The transverse reinforcing bars 520 are disposed to penetrate both ends of the girder 300 in the transverse direction and to be coupled with the longitudinally bending main reinforcing bars 510.
Ramen bridge construction method excluding the haunchi portion characterized in that the longitudinal bending of the reinforcing steel reinforcement (510) and the transverse reinforcement bar (520) is embedded by the slab concrete casting.
제 1항에 있어서,
상기 거더(300)는 상부플랜지, 복부 및 하부플랜지를 포함하여 구성되는 강재거더(310) 또는 PSC 거더(330)로,
강재거더(310)인 거더에는 횡방향 배력철근(520)이 관통될 수 있도록 복부(312)에 철근관통홀(319)을 형성시키고,
PSC 거더(330)인 거더에는 PSC 거더(330) 제작시 미리 횡방향 배력철근(520)이 PSC 거더(330)의 복부에 횡방향으로 설치되도록 하는 것을 특징으로 하는 헌치부가 배제된 라멘교 시공방법.
The method of claim 1,
The girder 300 is a steel girder 310 or PSC girder 330 including an upper flange, an abdomen and a lower flange,
In the girder, which is a steel girder 310, a rebar through hole 319 is formed in the abdomen 312 so that the transverse reinforcement bar 520 can pass therethrough.
In the girder, which is the PSC girder 330, when the PSC girder 330 is manufactured, a transverse reinforcing bar 520 is installed in the lateral direction of the abdomen of the PSC girder 330 in advance. Way.
제 1항에 있어서, 상기 종방향 절곡 주철근(510)은
거더(300)의 복부 하부로부터 거더(300) 중앙쪽으로 연장되는 수평철근부(511);
상기 수평철근부로부터 상방으로 절곡되어 연장되는 절곡철근부(512);를 포함하며, 상기 수평철근부(511)와 절곡철근부(512)의 경계는 라멘교의 헌치부 종방향 연장길이보다 커지도록 형성시키는 것을 특징으로 하는 헌치부가 배제된 라멘교 시공방법.
The method of claim 1, wherein the longitudinal bending cast steel 510 is
Horizontal reinforcing bar portion 511 extending from the lower abdomen of the girder 300 toward the center of the girder 300;
And a bending reinforcing part 512 that is bent upwards from the horizontal reinforcing part. The boundary between the horizontal reinforcing part 511 and the bending reinforcing part 512 is greater than the longitudinal extension of the haunch part of the Ramen bridge. Ramen bridge construction method excluding the haunchi characterized by forming.
제 3항에 있어서,
상기 강재거더(310)를 벽체부(210) 상면에 강결시키는 단계는
상기 벽체부(210) 상면 내측에, 벽체부 상면(A)보다 상방으로 돌출연장된 돌출지지턱(213)이 형성되도록 하고,
상기 벽체부 상면(A)과 돌출지지턱(213) 상면에 걸쳐 강재거더(310)가 연장배치되도록 하고,
상기 교대부(200) 상면 외측에서 돌출지지턱(213)을 지점부로 하여 강재거더(310)의 양 단부를 하방으로 눌러지도록 하여 상기 강재거더(310)의 양 단부가 벽체부(210)에 강결되도록 하는 단계를 포함하도록 하는 것을 특징으로 하는 헌치부가 배제된 라멘교 시공방법.
The method of claim 3,
The step of hardening the steel girder 310 on the upper surface of the wall portion 210
On the inside of the upper surface of the wall portion 210, a protruding support jaw 213 protruding upward from the upper surface A of the wall portion is formed,
The steel girder 310 is extended and disposed over the upper surface A of the wall portion and the upper surface of the protruding support jaw 213,
Both ends of the steel girder 310 are firmly formed on the wall portion 210 by pressing both ends of the steel girder 310 downward with the protruding support jaw 213 as the point portion from the outer side of the upper surface of the shift portion 200. Ramen bridge construction method excluding the haunchi, characterized in that it comprises a step to make.
제 4항에 있어서,
상기 강재거더(310)의 양 단부를 하방으로 눌러지도록 하여 상기 강재거더(310)의 양 단부가 벽체부(210)에 강결되도록 하는 단계는
상기 강재거더(310)의 상부플랜지(311) 및 하부플랜지(313)에 형성된 플랜지 관통홀(317)에는 벽체부(210) 내부로부터 상방으로 연장되어 벽체부(210) 상면을 거쳐 상기 플랜지 관통홀(317)에 삽입된 강봉을 포함하는 단부긴장재(212)가 설치되도록 하고,
상기 단부긴장재(212)를 상방으로 인장시킨 후 단부긴장재(212)의 상단이 강재거더(310) 상부플랜지(311) 상면에 정착되도록 하는 단계를 포함하는 것을 특징으로 하는 헌치부가 배제된 라멘교 시공방법.
The method of claim 4, wherein
Pressing both ends of the steel girder 310 to be pressed downward so that both ends of the steel girder 310 is rigid to the wall portion 210
The flange through hole 317 formed in the upper flange 311 and the lower flange 313 of the steel girder 310 extends upwardly from the inside of the wall portion 210 and passes through the upper surface of the wall portion 210 to pass through the flange. End tension member 212 including a steel rod inserted into the 317 is to be installed,
Ramen bridge excluded from the haunchi characterized in that it comprises the step of tensioning the end tensioner 212 upward and the upper end of the end tensioner 212 is fixed to the upper surface of the steel girder 310, the upper flange 311 Construction method.
KR1020110022534A 2011-03-14 2011-03-14 Rahmen bridge construction method without hunch KR101046941B1 (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
KR1020110022534A KR101046941B1 (en) 2011-03-14 2011-03-14 Rahmen bridge construction method without hunch

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
KR1020110022534A KR101046941B1 (en) 2011-03-14 2011-03-14 Rahmen bridge construction method without hunch

Publications (1)

Publication Number Publication Date
KR101046941B1 true KR101046941B1 (en) 2011-07-07

Family

ID=44923207

Family Applications (1)

Application Number Title Priority Date Filing Date
KR1020110022534A KR101046941B1 (en) 2011-03-14 2011-03-14 Rahmen bridge construction method without hunch

Country Status (1)

Country Link
KR (1) KR101046941B1 (en)

Cited By (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
KR101533379B1 (en) * 2014-12-23 2015-07-09 주식회사 하이드로코리아 Girder for rahmem structure using side wall with vertical tendon and the construction method therefor
KR101655330B1 (en) * 2015-08-11 2016-09-08 주식회사 하이드로코리아 Rahmem structure using composite steel beam and the construction method therefor
KR102067254B1 (en) * 2019-08-09 2020-01-16 주식회사 미강이엔씨 Negative moment reinforcement structure using girder and cross beam and method for constructing this same

Citations (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
KR20090075484A (en) * 2008-01-04 2009-07-08 권은태 Preflex composite girder bridge coupled width composite girder and method thereof
KR100929557B1 (en) 2009-05-29 2009-12-03 태우디엔씨 주식회사 Beam constructing structure for charge type steel box and i-beam girder of bridge
KR100951097B1 (en) 2009-03-13 2010-04-07 (주)한국건설공법 Slab and subgrade external wall structure and method for constructing underground slab and subgrade external wall, bracket
KR101011252B1 (en) 2010-11-24 2011-01-26 김석희 Rigid-frame bridge frame for reinforcing negative moment part and rigid-frame bridge having it

Patent Citations (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
KR20090075484A (en) * 2008-01-04 2009-07-08 권은태 Preflex composite girder bridge coupled width composite girder and method thereof
KR100951097B1 (en) 2009-03-13 2010-04-07 (주)한국건설공법 Slab and subgrade external wall structure and method for constructing underground slab and subgrade external wall, bracket
KR100929557B1 (en) 2009-05-29 2009-12-03 태우디엔씨 주식회사 Beam constructing structure for charge type steel box and i-beam girder of bridge
KR101011252B1 (en) 2010-11-24 2011-01-26 김석희 Rigid-frame bridge frame for reinforcing negative moment part and rigid-frame bridge having it

Cited By (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
KR101533379B1 (en) * 2014-12-23 2015-07-09 주식회사 하이드로코리아 Girder for rahmem structure using side wall with vertical tendon and the construction method therefor
KR101655330B1 (en) * 2015-08-11 2016-09-08 주식회사 하이드로코리아 Rahmem structure using composite steel beam and the construction method therefor
KR102067254B1 (en) * 2019-08-09 2020-01-16 주식회사 미강이엔씨 Negative moment reinforcement structure using girder and cross beam and method for constructing this same

Similar Documents

Publication Publication Date Title
KR100889273B1 (en) Construction method for rhamen bridge
KR101178876B1 (en) Prestressed composit rahmen bridge construdtion method
KR100808057B1 (en) Composite beam and construction method using the same
KR100742206B1 (en) Steel-concrete composite rahmen bridge and construction method thereof
KR101275754B1 (en) Psc girder with shear block, psc girder making method with shear block and bridge construction method using psc girder with shear block
KR100543969B1 (en) Composite rigid-frame bridge installing prestressed compound beam to the contral point of the slab of rigid-frame bridge and connecting the beam to the steel member installed in the upper of pole, and construction method thereof
KR101389285B1 (en) Pc girder shift of the chest wall with a block end integrated method
KR101135634B1 (en) Rahmen bridge construction method using hinge joint in support parts and rigid joint in rahmen conner parts
KR100728106B1 (en) Cantilever construction structure of slab for bridge and the method thereof
KR101004617B1 (en) Steel slab pannel and composited bridge construction method using temporary steel reinforcing rib and concrete reinforcing rib
KR101263370B1 (en) Precast end-block with girder connection member and bridge construction method using ths same
KR101046941B1 (en) Rahmen bridge construction method without hunch
KR101582599B1 (en) Bridge construction method for forming continuous point part of pier using copping for connecting girder
KR101243777B1 (en) Rahmen bridge using composite structure of corrugated steel web and concrete member and constructing method thereof
KR20090072224A (en) Manufacturing method for steel and concrete composite girder
KR200397213Y1 (en) Mounting structure of Steel Cross-beam in Multi-girder concrete bridge and its construction method
KR101601675B1 (en) The construction method of multicomposite Rahmen bridge
KR20140125754A (en) Bridge construction method for forming continuous point part of pier using copping for connecting girder
KR100920140B1 (en) Preflex composite girder bridge coupled width composite girder and method thereof
KR101286112B1 (en) Composite girder with steel pipe and rahmen bridge construction method using the same
KR101232329B1 (en) Integral bridge and construction method using arched and concrete-filled tube
KR101080943B1 (en) Rahmen bridge construction method using counterfort without abutment parts
KR101286116B1 (en) Composite girder with steel pipe and bridge construction method using the same
KR20070001410A (en) Mounting structure of steel cross-beam in multi-girder concrete bridge and its construction method
KR101384087B1 (en) Rahmen bridge construction method using support tendon apparatus and construction method therewith

Legal Events

Date Code Title Description
A201 Request for examination
A302 Request for accelerated examination
E701 Decision to grant or registration of patent right
GRNT Written decision to grant
FPAY Annual fee payment

Payment date: 20140630

Year of fee payment: 4

FPAY Annual fee payment

Payment date: 20150624

Year of fee payment: 5

FPAY Annual fee payment

Payment date: 20160623

Year of fee payment: 6

FPAY Annual fee payment

Payment date: 20170627

Year of fee payment: 7

FPAY Annual fee payment

Payment date: 20180802

Year of fee payment: 8