KR100995815B1 - Shortcrete retaining wall construction method - Google Patents

Shortcrete retaining wall construction method Download PDF

Info

Publication number
KR100995815B1
KR100995815B1 KR1020100080692A KR20100080692A KR100995815B1 KR 100995815 B1 KR100995815 B1 KR 100995815B1 KR 1020100080692 A KR1020100080692 A KR 1020100080692A KR 20100080692 A KR20100080692 A KR 20100080692A KR 100995815 B1 KR100995815 B1 KR 100995815B1
Authority
KR
South Korea
Prior art keywords
shotcrete
connecting rod
reinforcement
wire mesh
retaining wall
Prior art date
Application number
KR1020100080692A
Other languages
Korean (ko)
Inventor
김재선
Original Assignee
(주)대한지오이엔씨
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by (주)대한지오이엔씨 filed Critical (주)대한지오이엔씨
Priority to KR1020100080692A priority Critical patent/KR100995815B1/en
Application granted granted Critical
Publication of KR100995815B1 publication Critical patent/KR100995815B1/en

Links

Images

Classifications

    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D29/00Independent underground or underwater structures; Retaining walls
    • E02D29/02Retaining or protecting walls
    • E02D29/0225Retaining or protecting walls comprising retention means in the backfill
    • E02D29/0233Retaining or protecting walls comprising retention means in the backfill the retention means being anchors
    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D29/00Independent underground or underwater structures; Retaining walls
    • E02D29/02Retaining or protecting walls
    • E02D29/0258Retaining or protecting walls characterised by constructional features
    • E02D29/0275Retaining or protecting walls characterised by constructional features cast in situ
    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D2300/00Materials
    • E02D2300/0084Geogrids

Landscapes

  • Engineering & Computer Science (AREA)
  • Environmental & Geological Engineering (AREA)
  • Life Sciences & Earth Sciences (AREA)
  • General Life Sciences & Earth Sciences (AREA)
  • Mining & Mineral Resources (AREA)
  • Paleontology (AREA)
  • Civil Engineering (AREA)
  • General Engineering & Computer Science (AREA)
  • Structural Engineering (AREA)
  • Bulkheads Adapted To Foundation Construction (AREA)

Abstract

PURPOSE: A construction method of a reinforcement-integrated shotcrete retaining wall is provided to integrate a shotcrete wall and reinforced ground without installation of a form. CONSTITUTION: A construction method of a reinforcement-integrated shotcrete retaining wall is as follows. A ground reinforcement bore(100) is drilled. A first anchor plate(310) is fixed on the head of the ground reinforcement bore. A connection rod(400) is installed in the first anchor plate to be projected to the front. First shotcrete(510) is poured so that a first wire net(210) is buried and the connection rod is projected to the front. A second wire net(220) is installed in front of the first shotcrete by being fastened to the projected connection rod, and a second anchor plate(320) is fixed to the connection rod in the front of the second wire net. Second shotcrete(520) is poured so that the second wire net and the second anchor plate are buried and the connection rod is projected to the front. A reinforcing bar(240) located between the second wire net and the second anchor plate is fastened to the connection rod and arranged.

Description

보강 일체형 숏크리트 옹벽의 구축방법{Shortcrete retaining wall construction method}Shortcrete retaining wall construction method

본 발명은, 네일, 어스앵커, 락볼트 중 어느 하나에 의한 지반보강공으로 보강된 지반 표면에 일체형 옹벽을 시공하는 방법에 관한 것으로, 더욱 상세하게는 보강된 지반에 숏크리트를 반복 시공하여 보강된 지반과 숏크리트에 의한 벽체가 일체 거동할 수 있도록 구현한 숏크리트 옹벽의 구축방법에 관한 것이다.The present invention relates to a method for constructing an integrated retaining wall on a ground surface reinforced by ground reinforcement by any one of nail, earth anchor, and rock bolt, and more particularly, ground reinforced by repeating shotcrete on reinforced ground. The present invention relates to a method for constructing a shotcrete retaining wall, which is implemented so that a wall formed by and shotcrete can be integrated.

도로, 철도 및 주택단지조성 등에서 용지의 효율적인 이용을 위해서는 대규모 지반 절취가 불가피한데, 이 경우 지반 붕괴를 막기 위해 옹벽을 적절하게 구축해야 한다.Large-scale ground cutting is inevitable for the efficient use of land in roads, railways and housing complexes. In this case, retaining walls must be properly constructed to prevent ground collapse.

도 1은 종래의 옹벽을 보여주는 도면으로, 이들 옹벽은 주로 터파기한 후 기초에서부터 옹벽 구체를 구축하고 이어 옹벽 배후를 뒷채움 하는 방식으로 시공한다. 그러한 이러한 시공방법은 전반적으로 터파기와 뒷채움 공정 진행에 따라 작업량이 많아지고 공기가 길어지는 문제가 있다. 이러한 문제를 해결하기 위해 제안된 것으로 도 2와 같은 보강 일체형 옹벽이 있다.1 is a view showing a conventional retaining wall, these retaining walls are constructed in such a way as to build a retaining wall sphere from the foundation and then backfill the retaining wall mainly after dig. Such a construction method generally has a problem that the work load increases and the air lengthens as the trench and backfill process progress. Proposed to solve this problem is a reinforced integral retaining wall as shown in FIG.

도 2는 특허 제0698758호에 따른 보강 일체형 옹벽은 네일링 공법으로 지반을 보강한 후 보강된 지반면에 일체로 철근콘크리트 벽체를 구축하는 방식으로 시공한다. 이렇게 시공된 옹벽은 보강된 지반과 철근콘크리트 벽체가 일체 거동하기 때문에 기초 없이도 구조적 안정성이 보장된다.Figure 2 is a reinforced integral retaining wall according to the patent 0698758 is constructed by reinforcing the ground by the nailing method to build a reinforced concrete wall integrally to the reinforced ground surface. The retaining wall constructed in this way ensures structural stability without foundation because the reinforced ground and reinforced concrete walls behave in one piece.

한편, 도 2에 따른 보강 일체형 옹벽에서 철근콘크리트 벽체는 도 2(b)에서와 같이 돌출된 네일 두부에 벽체철근을 걸친 후 콘크리트를 타설하는 방법으로 시공했다. 그러나 이러한 방법은 콘크리트 타설을 위해 벽체거푸집을 설치해야 하는 불편이 있었다.On the other hand, the reinforced concrete wall in the reinforcement-integrated retaining wall according to Figure 2 was constructed by placing the concrete after the wall reinforcement on the protruding nail head as shown in Figure 2 (b). However, this method was inconvenient to install wall formwork for concrete pouring.

본 발명은 상기한 종래 보강 일체형 옹벽 시공에서 벽체거푸집 설치에 관한 문제를 개선하고자 개발된 것으로서, 벽체거푸집을 설치하지 않고도 보강 일체형 옹벽을 구축할 수 방법을 제공하고자 한다.The present invention was developed to improve the problems related to the wall formwork installation in the conventional reinforcement integrated retaining wall construction, and to provide a method of constructing a reinforcement integrated retaining wall without installing the wall formwork.

상기한 기술적 과제를 해결하기 위해 본 발명은 네일, 어스앵커, 락볼트 중 어느 하나에 의한 지반보강공으로 보강된 지반 표면에 일체형 옹벽을 시공하는 방법에 관한 것으로, 더욱 상세하게는 보강된 지반에 숏크리트를 반복 시공하여 보강된 지반과 숏크리트에 의한 벽체가 일체 거동할 수 있도록 구현한 숏크리트 옹벽의 구축방법을 제공한다.In order to solve the above technical problem, the present invention relates to a method for constructing an integrated retaining wall on a ground surface reinforced by ground reinforcement by any one of nail, earth anchor, and rock bolt, and more specifically, shotcrete on reinforced ground. It provides a construction method of shotcrete retaining wall implemented so that the wall by the reinforced ground and the shotcrete by the repeated construction can be integrated.

본 발명에 따르면, 보강된 지반과 철근콘크리트 벽체가 일체 거동하는 보강 일체형 옹벽을 철망과 숏크리트의 반복 시공으로 구축하기 때문에 벽체 거푸집 설치과정을 생략할 수 있으며, 이에 따라 공사비를 절감하고 공사기간을 단축하면서 보강 일체형 옹벽을 시공할 수 있다.According to the present invention, since the reinforcement-integrated retaining wall in which the reinforced ground and the reinforced concrete wall are integrally constructed is constructed by repetitive construction of the wire mesh and the shotcrete, the wall formwork installation process can be omitted, thereby reducing the construction cost and shortening the construction period. Reinforcing integral retaining wall can be constructed.

도 1은 종래의 다양한 옹벽을 도시한다.
도 2는 종래의 보강 일체형 옹벽을 도시한다.
도 3은 본 발명에 따라 완성된 보강 일체형 숏크리트 옹벽의 단면도이다.
도 4와 도 5는 도 3의 보강 일체형 숏크리트 옹벽에서 'A' 부분에 대한 확대도이다.
도 6은 도 3의 보강 일체형 숏크리트 옹벽에서 보강철근의 배근상태를 보여주는 도면이다.
Figure 1 shows a variety of conventional retaining walls.
2 shows a conventional reinforced integral retaining wall.
3 is a cross-sectional view of a reinforced integral shotcrete retaining wall completed in accordance with the present invention.
4 and 5 are enlarged views of portion 'A' in the reinforced integral shotcrete retaining wall of FIG.
FIG. 6 is a view showing a reinforcement state of reinforcing bars in the reinforcing integrated shotcrete retaining wall of FIG. 3.

이하 첨부한 도면 및 바람직한 실시예에 따라 본 발명을 설명한다.Hereinafter, the present invention will be described according to the accompanying drawings and preferred embodiments.

도 3은 본 발명에 따라 완성된 보강 일체형 숏크리트 옹벽의 단면도이고, 도 4와 도 5는 도 3의 보강 일체형 숏크리트 옹벽에서 'A' 부분에 대한 확대도이며, 도 6은 도 3의 보강 일체형 숏크리트 옹벽에서 보강철근의 배근상태를 보여준다.3 is a cross-sectional view of the reinforced integral shotcrete retaining wall completed according to the present invention, Figures 4 and 5 is an enlarged view of the 'A' portion of the reinforced integral shotcrete retaining wall of Figure 3, Figure 6 is a reinforced integral shotcrete of Figure 3 It shows the reinforcement condition of the rebar in the retaining wall.

이들 도면을 참고하여 본 발명에 따른 보강 일체형 숏크리트 옹벽의 구축방법을 단계적으로 살펴본다.With reference to these drawings will be described step by step how to build a reinforced integral shotcrete retaining wall according to the present invention.

(1)제1단계- 지반보강공 시공(1) Stage 1-Ground reinforcement construction

지반보강공(100)을 시공한다. 지반보강공(100)은 머리가 지반 표면으로 돌출하도록 지반에 정착 시공하며, 통상 지반보강공법에 따라 네일, 어스앵커, 락볼트 등으로 시공하면 된다. 도 3 이하에서는 네일(110)을 지반에 관입 설치한 후 그라우트(120)하여 시공한 지반보강공(100)을 확인할 수 있다. 도 3에서와 같이 지반보강공(100) 시공과 함께 수평배수재를 시공할 수 있음은 물론이며, 수평배수재는 통상의 방법으로 시공하면 된다.Ground reinforcement (100) to construct. Ground reinforcement (100) is fixed to the ground so that the head protrudes to the surface of the ground, it may be installed by nail, earth anchor, rock bolt, etc. according to the ground reinforcement method. 3 or less after the nail 110 is inserted into the ground can be confirmed by the ground reinforcing hole 100 constructed by the grout (120). As shown in FIG. 3, the horizontal drainage material may be constructed together with the ground reinforcing hole 100 construction, and the horizontal drainage material may be constructed in a conventional manner.

(2)제2,3단계- 1차 숏크리트 시공(2) 2nd and 3rd stages-1st shotcrete construction

1차 숏크리트를 지반 표면에 제1철망(210)을 포설하는 제2단계;A second step of installing the first wire mesh on the ground surface of the first shotcrete;

지반보강공(100)의 머리에 제1지압판(310)을 고정 설치하고 제1지압판(310)에 소정 길이의 연결봉(400)이 전방으로 돌출하게 장치하는 한편, 제1철망(210)이 묻히면서 연결봉(400)이 전방으로 돌출하게 1차 숏크리트(510)를 뿜칠하는 제3단계;When the first pressure plate 310 is fixedly installed on the head of the ground reinforcing hole 100 and the connecting rod 400 having a predetermined length protrudes forward on the first pressure plate 310, the first wire mesh 210 is buried. A third step of spraying the first shotcrete 510 such that the connecting rod 400 protrudes forward;

(3)제4,5단계- 2차 숏크리트 시공(3) 4th and 5th stages-2nd shotcrete construction

1차 숏크리트(510) 뿜칠면 전방으로 제2철망(220)을 포설하되 돌출된 연결봉(400)에 결속시키면서 포설하고, 제2철망(220) 전방으로 연결봉(400)에 제2지압판(320)을 고정 설치하는 제4단계;The first shotcrete 510 is installed while the second wire mesh 220 is installed in front of the sprayed surface while binding to the protruding connecting rod 400, and the second pressure plate 320 is connected to the connecting rod 400 in front of the second wire mesh 220. A fourth step of fixing the installation;

제2철망(220)과 제2지압판(320)이 묻히면서 연결봉(400)이 전방으로 돌출하게 2차 숏크리트(520)를 뿜칠하는 제5단계;A fifth step of spraying the second shotcrete 520 so that the connecting rod 400 protrudes forward while the second wire mesh 220 and the second pressure plate 320 are buried;

상기 제4단계는, 제2철망(220)과 제2지압판(320) 사이에 위치하는 보강철근(240)을 연결봉(400)에 결속시키면서 배근하는 과정을 더 포함하면서 진행하는 것을 특징으로 하는 보강 일체형 숏크리트 옹벽 구축방법.The fourth step, reinforcing, characterized in that further comprising the step of reinforcement while binding the reinforcing bar 240 located between the second wire mesh 220 and the second pressure plate 320 to the connecting rod 400 Integrated shotcrete retaining wall construction method.

상기 제3단계는, 연결봉(400)을 4본으로 마련하여 상하좌우 십자형으로 배치하면서 진행하며,In the third step, the connecting rod 400 is provided in four pieces and proceeds while being arranged in up, down, left and right crosses,

상기 제4단계와 제6단계는, 제2지압판(230)과 제3지압판(330)을 십자형의 판재로 마련하여 연결봉(400)에 고정 설치하면서 진행하는 것을 특징으로 하는 보강 일체형 숏크리트 옹벽 구축방법.In the fourth and sixth steps, the method of constructing an integrated shotcrete retaining wall is characterized in that the second acupressure plate 230 and the third acupressure plate 330 are made of cross-shaped plate and fixed and installed on the connecting rod 400. .

상기 제4단계는, 제2철망(220)과 제2지압판(320) 사이에 위치하는 보강철근(240)을 배근하되, 상하방향으로 배치된 2본의 연결봉에 결속시키면서 2본의 보강철근(241)을 수평 배근하고, 좌우방향으로 배치된 2본의 연결봉에 결속시키면서 2본의 보강철근(242)을 수직 배근하고, 상하좌우방향으로 배치된 4본의 연결볼트에 결속시키면서 4본의 보강철근(243)을 경사 배근하는 과정을 더 포함하면서 진행하는 것을 특징으로 하는 보강 일체형 숏크리트 옹벽 구축방법.The fourth step is to reinforce the reinforcing reinforcing bar 240 located between the second wire mesh 220 and the second pressure plate 320, while binding to the two connecting rods arranged in the up and down direction of the two reinforcing bars ( 241) is horizontally reinforcement, while the two reinforcing bars 242 are vertically reinforcement while binding to two connecting rods arranged in the left and right directions, and the four reinforcement while binding to the four connecting bolts arranged in the up, down, left and right directions Reinforced one shotcrete retaining wall construction method characterized in that the progress further comprising the step of reinforcing the rebar (243).

(4)제6,7단계- 3차 숏크리트 시공(4) 6th and 7th stages-3rd shotcrete construction

2차 숏크리트(520) 뿜칠면 전방으로 제3철망(230)을 포설하되 돌출된 연결봉(400) 말단에 결속시키면서 포설하고, 제3철망(230) 전방으로 연결봉(400) 말단에 제3지압판(330)을 고정 설치하는 제6단계;The second shotcrete 520 is installed while binding the third wire mesh 230 to the front of the spouting surface while binding to the end of the protruding connecting rod 400, and the third pressure plate at the end of the connecting rod 400 toward the third wire mesh 230 ( A sixth step of fixing 330;

제3철망(230), 제3지압판(330), 연결봉(400)이 묻히도록 3차 숏크리트(530)를 뿜칠하는 제7단계;A seventh step of spraying the third shotcrete 530 so that the third wire mesh 230, the third pressure plate 330, and the connecting rod 400 are buried;

(5)제8단계- 마감(5) The eighth step-deadline

3차 숏크리트(530) 뿜칠면에 마감재(540)를 시공하는 제8단계;An eighth step of constructing the finishing material 540 on the third shotcrete 530 sprayed surface;

이상에서 본 발명은 구체적인 실시예를 참조하여 상세히 설명되었으나, 실시예는 본 발명을 예시하기 위한 것일 뿐이므로, 본 발명의 기술적 사상을 벗어나지 않는 범위 내에서 치환, 부가 및 변형된 실시 형태들 역시 아래에 첨부한 특허청구범위에 의하여 정하여지는 본 발명의 보호범위에 속한다고 할 것이다.The present invention has been described in detail above with reference to specific embodiments, but the embodiments are only for illustrating the present invention, and thus the embodiments substituted, added, and modified within the scope without departing from the spirit of the present invention are also described below. It will be said to belong to the protection scope of the present invention as defined by the claims appended hereto.

100: 지반보강공
110: 네일
120: 그라우트
130: 너트
210, 220, 230: 철망
240, 241, 242, 243: 보강철근
310, 320, 330: 지압판
400: 연결봉
510, 520, 530: 숏크리트
540: 마감재
100: ground reinforcement
110: nail
120: grout
130: nut
210, 220, 230: wire mesh
240, 241, 242, 243: rebar
310, 320, 330:
400: connecting rod
510, 520, 530: Shotcrete
540: Finishing material

Claims (5)

네일, 어스앵커, 락볼트 중 어느 하나에 의한 지반보강공으로 보강된 지반 표면에 일체형으로 옹벽을 시공하는 방법으로서,
머리가 지반 표면으로 돌출하도록 지반보강공(100)을 지반에 정착 시공하는 제1단계;
지반 표면에 제1철망(210)을 포설하는 제2단계;
지반보강공(100)의 머리에 제1지압판(310)을 고정 설치하고 제1지압판(310)에 소정 길이의 연결봉(400)이 전방으로 돌출하게 장치하는 한편, 제1철망(210)이 묻히면서 연결봉(400)이 전방으로 돌출하게 1차 숏크리트(510)를 뿜칠하는 제3단계;
1차 숏크리트(510) 뿜칠면 전방으로 제2철망(220)을 포설하되 돌출된 연결봉(400)에 결속시키면서 포설하고, 제2철망(220) 전방으로 연결봉(400)에 제2지압판(320)을 고정 설치하는 제4단계;
제2철망(220)과 제2지압판(320)이 묻히면서 연결봉(400)이 전방으로 돌출하게 2차 숏크리트(520)를 뿜칠하는 제5단계;
2차 숏크리트(520) 뿜칠면 전방으로 제3철망(230)을 포설하되 돌출된 연결봉(400) 말단에 결속시키면서 포설하고, 제3철망(230) 전방으로 연결봉(400) 말단에 제3지압판(330)을 고정 설치하는 제6단계;
제3철망(230), 제3지압판(330), 연결봉(400)이 묻히도록 3차 숏크리트(530)를 뿜칠하는 제7단계;
로 이루어지는 것을 특징으로 하는 보강 일체형 숏크리트 옹벽의 구축방법.
As a method of constructing the retaining wall integrally on the ground surface reinforced with ground reinforcement by any one of nail, earth anchor, rock bolt,
A first step of fixing the ground reinforcement hole 100 to the ground so that the head protrudes to the ground surface;
A second step of installing the first wire mesh 210 on the ground surface;
When the first pressure plate 310 is fixedly installed on the head of the ground reinforcing hole 100 and the connecting rod 400 having a predetermined length protrudes forward on the first pressure plate 310, the first wire mesh 210 is buried. A third step of spraying the first shotcrete 510 such that the connecting rod 400 protrudes forward;
The first shotcrete 510 is installed while the second wire mesh 220 is installed in front of the sprayed surface while binding to the protruding connecting rod 400, and the second pressure plate 320 is connected to the connecting rod 400 in front of the second wire mesh 220. A fourth step of fixedly installing the first substrate;
A fifth step of spraying the second shotcrete 520 so that the connecting rod 400 protrudes forward while the second wire mesh 220 and the second pressure plate 320 are buried;
The second shotcrete 520 is installed while binding the third wire mesh 230 to the front of the spouting surface while binding to the end of the protruding connecting rod 400, and the third pressure plate at the end of the connecting rod 400 toward the third wire mesh 230 ( 330);
A seventh step of spraying the third shotcrete 530 so that the third wire mesh 230, the third pressure plate 330, and the connecting rod 400 are buried;
Reinforced integrated shotcrete retaining wall construction method comprising a.
제1항에서,
상기 제7단계 후에,
3차 숏크리트(530) 뿜칠면에 마감재(540)를 시공하는 제8단계;
가 더 포함하여 이루어지는 것을 특징으로 하는 보강 일체형 숏크리트 옹벽의 구축방법.
In claim 1,
After the seventh step,
An eighth step of constructing the finishing material 540 on the third shotcrete 530 sprayed surface;
Method for constructing a reinforced integral shotcrete retaining wall, characterized in that further comprises.
제1항 또는 제2항에서,
상기 제4단계는, 제2철망(220)과 제2지압판(320) 사이에 위치하는 보강철근(240)을 연결봉(400)에 결속시키면서 배근하는 과정을 더 포함하면서 진행하는 것을 특징으로 하는 보강 일체형 숏크리트 옹벽의 구축방법.
The method of claim 1 or 2,
The fourth step, reinforcement characterized in that it further includes a process of reinforcement while binding the reinforcing bar 240 located between the second wire mesh 220 and the second pressure plate 320 to the connecting rod 400 Construction Method of Integrated Shotcrete Retaining Wall.
제1항 또는 제2항에서,
상기 제3단계는, 연결봉(400)을 4본으로 마련하여 상하좌우 십자형으로 배치하면서 진행하며,
상기 제4단계와 제6단계는, 제2지압판(230)과 제3지압판(330)을 십자형의 판재로 마련하여 연결봉(400)에 고정 설치하면서 진행하는 것을 특징으로 하는 보강 일체형 숏크리트 옹벽의 구축방법.
The method of claim 1 or 2,
In the third step, the connecting rod 400 is provided in four pieces and proceeds while being arranged in up, down, left and right crosses,
In the fourth and sixth steps, the second acupressure plate 230 and the third acupressure plate 330 are made of cross-shaped plate material, and the fixed bar shotcrete retaining wall is constructed to proceed while being fixed to the connecting rod 400. Way.
제4항에서,
상기 제4단계는, 제2철망(220)과 제2지압판(320) 사이에 위치하는 보강철근(240)을 배근하되, 상하방향으로 배치된 2본의 연결봉에 결속시키면서 2본의 보강철근(241)을 수평 배근하고, 좌우방향으로 배치된 2본의 연결봉에 결속시키면서 2본의 보강철근(242)을 수직 배근하고, 상하좌우방향으로 배치된 4본의 연결볼트에 결속시키면서 4본의 보강철근(243)을 경사 배근하는 과정을 더 포함하면서 진행하는 것을 특징으로 하는 보강 일체형 숏크리트 옹벽의 구축방법.
In claim 4,
The fourth step is to reinforce the reinforcing reinforcing bar 240 located between the second wire mesh 220 and the second pressure plate 320, while binding to the two connecting rods arranged in the up and down direction of the two reinforcing bars ( 241) is horizontally reinforcement, while the two reinforcing bars 242 are vertically reinforcement while binding to two connecting rods arranged in the left and right directions, and the four reinforcement while binding to the four connecting bolts arranged in the up, down, left and right directions A method of constructing an integrated reinforcement shotcrete retaining wall, characterized in that the process proceeds further comprising the step of reinforcing the reinforcing bars (243).
KR1020100080692A 2010-08-20 2010-08-20 Shortcrete retaining wall construction method KR100995815B1 (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
KR1020100080692A KR100995815B1 (en) 2010-08-20 2010-08-20 Shortcrete retaining wall construction method

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
KR1020100080692A KR100995815B1 (en) 2010-08-20 2010-08-20 Shortcrete retaining wall construction method

Publications (1)

Publication Number Publication Date
KR100995815B1 true KR100995815B1 (en) 2010-11-22

Family

ID=43409967

Family Applications (1)

Application Number Title Priority Date Filing Date
KR1020100080692A KR100995815B1 (en) 2010-08-20 2010-08-20 Shortcrete retaining wall construction method

Country Status (1)

Country Link
KR (1) KR100995815B1 (en)

Cited By (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
KR101244808B1 (en) 2012-06-29 2013-03-18 (주)대한지오이엔씨 Echo nail diaphragm wall that use reinforcement diaphragm wall
KR101674865B1 (en) 2016-05-30 2016-11-22 정쌍영 Shotcrete retaining wall and construction method thereof
CN108005104A (en) * 2017-10-27 2018-05-08 西安科技大学 A kind of combined type retaining wall structure and its construction method
KR102056345B1 (en) * 2017-07-11 2019-12-16 한국철도기술연구원 Slope face adjusting constructor of embanking roadbed for railway track, and construction method for the same

Citations (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
KR100842372B1 (en) 2007-03-09 2008-06-30 극동엔지니어링(주) Pretension soil nail method of top-down

Patent Citations (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
KR100842372B1 (en) 2007-03-09 2008-06-30 극동엔지니어링(주) Pretension soil nail method of top-down

Cited By (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
KR101244808B1 (en) 2012-06-29 2013-03-18 (주)대한지오이엔씨 Echo nail diaphragm wall that use reinforcement diaphragm wall
KR101674865B1 (en) 2016-05-30 2016-11-22 정쌍영 Shotcrete retaining wall and construction method thereof
KR102056345B1 (en) * 2017-07-11 2019-12-16 한국철도기술연구원 Slope face adjusting constructor of embanking roadbed for railway track, and construction method for the same
CN108005104A (en) * 2017-10-27 2018-05-08 西安科技大学 A kind of combined type retaining wall structure and its construction method

Similar Documents

Publication Publication Date Title
KR100771904B1 (en) Earth Reinforcement System by Using Bamboo Reinforcement
KR100930829B1 (en) Pannel have rockbolt coupler
CN101122132A (en) Demountable composite material face plate brad supporting system
CN103132690B (en) Basement exterior wall unilateral template and method for supporting template thereof
KR20140013497A (en) Method for constructing block type reinforced retaining wall in cut site
KR100995815B1 (en) Shortcrete retaining wall construction method
CN204662494U (en) A kind of Road Retaining Walls ruggedized construction
KR101211469B1 (en) Retaining wall structure having prefabricated block and method for constructing retaining wall using the same
KR100689078B1 (en) A method for construction an artificial wall
KR102255389B1 (en) Three-dimensional artificial rock landscape retaining wall structure with natural rock shape using porous metal plates
KR20080034424A (en) A constructing method of underground structure with supporting beam for steel pipe
JP2000352296A (en) Method o constructing passage just under underground structure
KR101314764B1 (en) Retaining wall using corrugated steel plate and construction method thereof
KR100444838B1 (en) A fiber reinforced earth retaining wall, a constructing method thereof, and a composite underground wall structure using thereof
KR100862387B1 (en) Tensional kit for top-down constructing of acupressure lasting anchor and top-down constructing method of acupressure lasting anchor using this
KR200407437Y1 (en) Construction establishment method and the structure for underground tunnel formation
KR101032408B1 (en) Method of reinforced earth retaining wall for cutting face through reinforcing execution and concrete block
KR20190142546A (en) Construction method of subsurface structure using outer shell suspension
KR20080059951A (en) Underground outer wall construction method using temporary retaining wall and connecting member strengthening shearing force therefor
KR102505365B1 (en) Support for tunnel shotcrete drop prevention
JP6099261B2 (en) Building construction method and structure
CN102433882A (en) Construction method for forming foundation pit support through combining concrete pile wall and jet grouting anchor piles and anchor bar structural piece
KR100473880B1 (en) A method for construction an artificial wall using a soil nail and the artificial wall constructed threrby
JP2011157719A (en) Earth retaining method
KR101524302B1 (en) Construction method for underground structure without temporary structure

Legal Events

Date Code Title Description
A201 Request for examination
A302 Request for accelerated examination
E701 Decision to grant or registration of patent right
GRNT Written decision to grant
FPAY Annual fee payment

Payment date: 20131118

Year of fee payment: 4

LAPS Lapse due to unpaid annual fee