KR100918144B1 - Evacuation assistance device for elevator - Google Patents

Evacuation assistance device for elevator Download PDF

Info

Publication number
KR100918144B1
KR100918144B1 KR1020087019648A KR20087019648A KR100918144B1 KR 100918144 B1 KR100918144 B1 KR 100918144B1 KR 1020087019648 A KR1020087019648 A KR 1020087019648A KR 20087019648 A KR20087019648 A KR 20087019648A KR 100918144 B1 KR100918144 B1 KR 100918144B1
Authority
KR
South Korea
Prior art keywords
evacuation
elevator
evacuation operation
floor
time
Prior art date
Application number
KR1020087019648A
Other languages
Korean (ko)
Other versions
KR20080087156A (en
Inventor
시로 히키타
Original Assignee
미쓰비시덴키 가부시키가이샤
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by 미쓰비시덴키 가부시키가이샤 filed Critical 미쓰비시덴키 가부시키가이샤
Priority to KR1020087019648A priority Critical patent/KR100918144B1/en
Publication of KR20080087156A publication Critical patent/KR20080087156A/en
Application granted granted Critical
Publication of KR100918144B1 publication Critical patent/KR100918144B1/en

Links

Images

Classifications

    • BPERFORMING OPERATIONS; TRANSPORTING
    • B66HOISTING; LIFTING; HAULING
    • B66BELEVATORS; ESCALATORS OR MOVING WALKWAYS
    • B66B5/00Applications of checking, fault-correcting, or safety devices in elevators
    • B66B5/02Applications of checking, fault-correcting, or safety devices in elevators responsive to abnormal operating conditions
    • B66B5/021Applications of checking, fault-correcting, or safety devices in elevators responsive to abnormal operating conditions the abnormal operating conditions being independent of the system
    • B66B5/024Applications of checking, fault-correcting, or safety devices in elevators responsive to abnormal operating conditions the abnormal operating conditions being independent of the system where the abnormal operating condition is caused by an accident, e.g. fire
    • AHUMAN NECESSITIES
    • A62LIFE-SAVING; FIRE-FIGHTING
    • A62BDEVICES, APPARATUS OR METHODS FOR LIFE-SAVING
    • A62B5/00Other devices for rescuing from fire
    • BPERFORMING OPERATIONS; TRANSPORTING
    • B66HOISTING; LIFTING; HAULING
    • B66BELEVATORS; ESCALATORS OR MOVING WALKWAYS
    • B66B5/00Applications of checking, fault-correcting, or safety devices in elevators
    • B66B5/02Applications of checking, fault-correcting, or safety devices in elevators responsive to abnormal operating conditions
    • B66B5/027Applications of checking, fault-correcting, or safety devices in elevators responsive to abnormal operating conditions to permit passengers to leave an elevator car in case of failure, e.g. moving the car to a reference floor or unlocking the door

Landscapes

  • Health & Medical Sciences (AREA)
  • General Health & Medical Sciences (AREA)
  • Business, Economics & Management (AREA)
  • Emergency Management (AREA)
  • Maintenance And Inspection Apparatuses For Elevators (AREA)

Abstract

엘리베이터의 피난 지원 장치는 복수의 층을 서비스층으로 하는 엘리베이터의 운전을 긴급시에 관리하는 것에 의해, 건물내에 남겨진 재관자를 피난층에 피난시킨다. 또, 엘리베이터의 피난 지원 장치는 피난 운전 실시부, 피난 운전 시간 산출부 및 피난 운전 판정부를 갖고 있다. 피난 운전 실시부는 각 서비스층의 적어도 어느 하나를 구출층으로 설정하고, 재관자를 구출층으로부터 피난층으로 운반하기 위한 피난 운전을 엘리베이터에 대해 실시한다. 피난 운전 시간 산출부는 긴급의 정도를 나타내는 긴급도 정보를 받는 동시에, 긴급도 정보에 기초하여 피난 운전을 계속할 예정 시간을 피난 운전 시간으로서 산출한다. 피난 운전 판정부는 피난 운전 시간 산출부로부터의 정보에 기초하여 피난 운전의 계속 여부를 판정한다. 피난 운전 실시부는 피난 운전 판정부로부터의 정보에 기초하여 피난 운전을 제어한다.The evacuation support device of an elevator manages the operation of an elevator having a plurality of floors as a service floor in an emergency to evacuate an inspector left in the building to the evacuation floor. Moreover, the evacuation support apparatus of an elevator has an evacuation operation execution part, an evacuation operation time calculation part, and an evacuation operation determination part. The evacuation driving unit sets at least one of the service floors to the rescue floor, and performs an evacuation operation for the elevator for transporting the inspector from the rescue floor to the evacuation floor. The evacuation driving time calculation unit receives the emergency information indicating the degree of emergency, and calculates, as the evacuation driving time, the scheduled time to continue the evacuation driving based on the emergency information. The evacuation operation determination unit determines whether the evacuation operation is continued based on the information from the evacuation operation time calculation unit. The evacuation operation execution section controls the evacuation operation based on the information from the evacuation operation determination section.

Description

엘리베이터의 피난 지원 장치{EVACUATION ASSISTANCE DEVICE FOR ELEVATOR}Evacuation assistance device for elevators {EVACUATION ASSISTANCE DEVICE FOR ELEVATOR}

본 발명은 긴급시에 건물내에 남겨진 재관자를 피난시키기 위한 엘리베이터의 피난 지원 장치에 관한 것이다.The present invention relates to an evacuation assistance device for an elevator for evacuating an inspector who is left in a building in an emergency.

종래, 건물에 화재가 발생한 경우에, 재관자의 피난을 위하여 엘리베이터를 이용하는 피난 방법이 제안되고 있다(비특허 문헌 1 참조).Conventionally, an evacuation method using an elevator has been proposed for evacuation of inspectors when a fire breaks out in a building (see Non-Patent Document 1).

비특허 문헌 1 : 세키자와 아이 외 4명, 「고층 빌딩에 있어서 엘리베이터 피난의 가능성에 관한 연구(그 2)」, 2004년도 일본 화재 학회 연구 발표회 개요집, p.590-593Non-Patent Literature 1: Sekizawa Ai and four others, "Study on the possibility of elevator evacuation in high-rise buildings (Part 2)", 2004 Japan Fire Institute Research Presentation Summary Collection, p.590-593

그러나, 예를 들어 테러 발생의 예고를 받은 경우 등, 엘리베이터의 운전이 강제적으로 정지될 가능성이 급격하게 높아지고 있는 긴급시에는 엘리베이터의 피난 운전을 무제한으로 계속하면, 재관자의 운반 중에 엘리베이터의 운전이 이상 정지하게 될 가능성이 높아져서, 오히려 재관자의 피난이 곤란해질 우려가 있다.However, in case of an emergency where the possibility of forcibly stopping the elevator is forcibly increased, for example, when a notice of terrorism has occurred, if the evacuation operation of the elevator is continued indefinitely, the operation of the elevator is abnormal during transportation of the inspector. There is a possibility that the evacuation of residents will be difficult because the possibility of stopping will increase.

본 발명은 상기와 같은 과제를 해결하기 위해 이루어진 것이며, 엘리베이터의 피난 운전의 이상 정지의 방지를 도모할 수 있는 엘리베이터의 피난 지원 장치를 얻는 것을 목적으로 한다.This invention is made | formed in order to solve the above subjects, and an object of this invention is to obtain the evacuation support apparatus of the elevator which can aim at the prevention of the abnormal stop of the evacuation operation of an elevator.

본 발명에 의한 엘리베이터의 피난 지원 장치는, 복수의 층을 서비스층으로 하는 엘리베이터의 운전을 긴급시에 관리하는 것에 의해, 건물내에 남겨진 재관자를 피난층으로 피난시키는 엘리베이터의 피난 지원 장치로서, 각 서비스층의 적어도 어느 하나를 구출층으로 설정하고, 재관자를 구출층으로부터 피난층으로 운반하기 위한 피난 운전을 상기 엘리베이터에 대해 실시하는 피난 운전 실시부; 긴급의 정도를 나타내는 긴급도 정보를 받는 동시에, 긴급도 정보에 기초하여 피난 운전을 계속할 예정 시간을 피난 운전 시간으로서 산출하는 피난 운전 시간 산출부; 및 피난 운전 시간 산출부로부터의 정보에 기초하여 피난 운전의 계속 여부를 판정하는 피난 운전 판정부를 구비하고, 피난 운전 실시부는 피난 운전 판정부로부터의 정보에 기초하여 피난 운전을 제어한다.An elevator evacuation support apparatus according to the present invention is an elevator evacuation support apparatus for evacuating an inspector left in a building to an evacuation floor by managing the operation of an elevator having a plurality of floors as a service floor in an emergency. An evacuation operation execution unit for setting at least one of the floors to the rescue floor and performing an evacuation operation for the elevator for transporting the inspector from the rescue floor to the evacuation floor; An evacuation driving time calculating unit that receives the urgent information indicating the degree of urgency and calculates, as an evacuation driving time, a scheduled time for continuing the evacuation driving based on the urgent information; And an evacuation operation determination unit that determines whether to continue the evacuation operation based on the information from the evacuation operation time calculation unit, and the evacuation operation execution unit controls the evacuation operation based on the information from the evacuation operation determination unit.

도 1은 본 발명의 실시 형태 1에 의한 엘리베이터의 피난 지원 장치를 나타내는 블록도이다.BRIEF DESCRIPTION OF THE DRAWINGS It is a block diagram which shows the evacuation support apparatus of the elevator by Embodiment 1 of this invention.

도 2는 도 1의 피난 지원 장치의 처리 동작을 설명하기 위한 플로우차트이다.FIG. 2 is a flowchart for explaining a processing operation of the evacuation support device of FIG. 1.

이하, 본 발명의 바람직한 실시 형태에 대하여 도면을 참조하여 설명한다.EMBODIMENT OF THE INVENTION Hereinafter, preferred embodiment of this invention is described with reference to drawings.

실시 형태 1.Embodiment 1.

도 1은 본 발명의 실시 형태 1에 의한 엘리베이터의 피난 지원 장치를 나타내는 블록도이다. 도면에 있어서, 건물(도시하지 않음)에는 복수의 엘리베이터 그 룹(1)이 마련되어 있다. 각 엘리베이터 그룹(1)은 복수의 층을 서비스층으로 하는 복수의 엘리베이터(2)를 갖고 있다. 각 엘리베이터(2)는 각 서비스층 및 피난층에 정지 가능한 엘리베이터 칸(3)과, 엘리베이터 칸(3)의 이동을 제어하는 제어 장치(4)를 갖고 있다. 본 예에서는 피난층은 건물의 현관이 마련된 현관층으로 되어 있다.BRIEF DESCRIPTION OF THE DRAWINGS It is a block diagram which shows the evacuation support apparatus of the elevator by Embodiment 1 of this invention. In the figure, a plurality of elevator groups 1 are provided in a building (not shown). Each elevator group 1 has a plurality of elevators 2 having a plurality of floors as a service floor. Each elevator 2 has a car 3 which can be stopped on each service floor and an evacuation floor, and a control device 4 for controlling the movement of the car 3. In this example, the evacuation floor is the entrance floor where the entrance of the building is provided.

각 엘리베이터 그룹(1)에는 각 엘리베이터(2)의 운전을 일괄하여 관리하기 위한 그룹 관리 장치(5)가 마련되어 있다. 또, 각 서비스층 및 피난층에는 승강장 호출을 등록하기 위한 승강장 호출 버튼(6)이 각 엘리베이터(2)에 대해 마련되어 있다. 승강장 호출 버튼(6)의 조작에 의해 승강장 호출이 등록되면, 엘리베이터 그룹(1)내의 각 엘리베이터 칸(3) 중, 승강장 호출에 대응하는 엘리베이터 칸(3)이 그룹 관리 장치(5)에 의해 할당된다.Each elevator group 1 is provided with a group management apparatus 5 for collectively managing the operation of each elevator 2. In addition, a platform call button 6 for registering a platform call is provided for each elevator 2 in each service floor and the evacuation floor. When the boarding point call is registered by the operation of the boarding point call button 6, the car 3 corresponding to the boarding point call among the cars 3 in the elevator group 1 is assigned by the group management apparatus 5 do.

건물의 각 층에는 피난 유도에 관한 안내 방송을 건물 전체에 행하기 위한 비상 방송 장치(알림 장치; 7)가 마련되어 있다. 또, 건물에는 방재에 관한 설비 기기의 감시 및 제어를 집중적으로 행하기 위한 중앙 관리실(방재 센터)이 설치되어 있다. 중앙 관리실내에는 건물 전체의 방재 기기를 총괄 관리하는 방재 관리 장치(8)와, 예를 들어 테러 발생의 예고를 받은 경우 등의 긴급시에 각 그룹 관리 장치(5)를 총괄 관리하는 피난 지원 장치(9)가 마련되어 있다.Each floor of the building is provided with an emergency broadcast device (notification device) 7 for conducting announcements regarding evacuation guidance to the entire building. In addition, the building is provided with a central management room (disaster prevention center) for intensively monitoring and controlling facility equipment related to disaster prevention. In the central management room, a disaster prevention management device 8 that collectively manages disaster prevention equipment for the entire building, and an evacuation support device that collectively manages each group management device 5 in case of an emergency such as when a notice of terrorism occurs. (9) is provided.

피난 지원 장치(9)는 각 그룹 관리 장치(5)를 총괄 관리하는 것에 의해, 건물내에 남겨진 재관자를 피난층으로 운반하기 위한 피난 운전을 각 엘리베이터 그룹(1)에 대해 행한다. 피난 지원 장치(9)에는 중앙 관리실내에 마련된 외부 입력 장치(도시하지 않음)의 조작에 의해 피난 운전에 관한 조작 입력 정보가 입력되게 된다. 피난 운전은 피난 지원 장치(9)가 받은 조작 입력 정보에 기초하여 제어된다.The evacuation support device 9 collectively manages each group management device 5 to perform evacuation operation for each elevator group 1 for transporting the inspectors left in the building to the evacuation floor. The operation input information regarding evacuation operation is input to the evacuation support device 9 by the operation of an external input device (not shown) provided in the central management room. Evacuation operation is controlled based on the operation input information received by the evacuation support device 9.

외부 입력 장치로는 예를 들어 퍼스널 컴퓨터(PC) 등이 이용된다. 또, 조작 입력 정보에는 긴급의 정도를 나타내는 긴급도 정보(예를 들어 테러의 예고 내용에 의해 유도된 테러 발생의 예정 시각(한계 시각)의 정보 등)이 포함되어 있다. 또한, 외부 입력 장치는 피난 지원 장치(9)에 직접 장착되어도 된다.As the external input device, a personal computer (PC) or the like is used, for example. In addition, the operation input information includes emergency information indicating the degree of urgency (for example, information on a scheduled time (limit time) of terror occurrence induced by the contents of the notice of terrorism). In addition, the external input device may be directly attached to the evacuation support device 9.

피난 지원 장치(9)는 통신부(10), 피난 운전 실시부(11), 피난 운전 시간 산출부(12), 피난 운전 판정부(13) 및 알림 지령부(14)를 갖고 있다.The evacuation support device 9 includes a communication unit 10, an evacuation driving unit 11, an evacuation driving time calculating unit 12, an evacuation driving determining unit 13, and a notification command unit 14.

통신부(10)는 각 그룹 관리 장치(5), 방재 관리 장치(8) 및 외부 입력 장치 각각과 피난 지원 장치(9)의 정보 통신을 행한다.The communication unit 10 performs information communication between each of the group management apparatus 5, the disaster prevention management apparatus 8, and the external input apparatus and the evacuation support apparatus 9, respectively.

피난 운전 실시부(11)는 각 그룹 관리 장치(5)에 피난 운전의 지령을 출력하는 것에 의해, 각 엘리베이터(2)에 대한 피난 운전을 실시한다. 피난 운전은 각 서비스층의 적어도 어느 하나를 구출층으로 설정하고, 구출층과 피난층 사이에서 엘리베이터 칸(3)을 이동시키는 것에 의해 행해진다. 피난 운전시에 구출층의 승강장에서 승강장 호출 버튼(6)이 조작되었을 때에는 승강장 호출에 응답하는 엘리베이터 칸(3)이 당해 구출층으로 제어 장치(4)의 제어에 의해 이동된다. 구출층에 도착한 엘리베이터 칸(3)은 재관자가 승차한 후, 피난층으로 이동된다.The evacuation driving unit 11 outputs an instruction for evacuation operation to each group management device 5 to perform evacuation operation for each elevator 2. Evacuation operation is performed by setting at least one of each service floor to a rescue floor, and moving the cage | basket | car 3 between a rescue floor and an evacuation floor. When the landing call button 6 is operated at the landing of the rescue floor during the evacuation operation, the car 3 in response to the landing call is moved to the rescue floor by the control of the control device 4. The car 3, which has arrived at the rescue floor, is moved to the evacuation floor after the inspector boards.

본 예에서는 피난 운전 실시부(11)는 모든 서비스층을 구출층으로 설정한다. 이에 의해, 피난 운전시의 각 엘리베이터 칸(3)은 모든 서비스층 및 피난층에 착상 가능하게 된다. 즉, 각 엘리베이터의 피난 운전은 통상시의 제어에 의한 통상 운전과 동일한 운전으로 된다.In this example, the evacuation driving unit 11 sets all service layers as rescue floors. Thereby, each cage | basket | car 3 at the time of an evacuation operation becomes possible to land on all the service floors and evacuation floor. That is, the evacuation operation of each elevator is the same operation as the normal operation by normal control.

피난 운전 시간 산출부(12)는 외부 입력 장치로부터의 조작 입력 정보를 받는 동시에, 조작 입력 정보에 기초하여 피난 운전을 계속할 예정 시간을 피난 운전 시간으로 하여 각 엘리베이터(2)에 대해 산출한다.Evacuation operation time calculation part 12 receives operation input information from an external input device, and calculates for each elevator 2 the estimated time to continue evacuation operation based on operation input information as an evacuation operation time.

본 예에서는 피난 운전 시간의 산출은 테러 발생의 예정 시각의 정보에 기초하여 행해진다. 즉, 테러 발생의 예정 시각(한계 시각)보다 전에 피난 운전이 종료하도록 피난 운전 시간이 산출된다. 구체적으로, 각 엘리베이터(2)에 대한 피난 운전 시간의 산출은 이하와 같이 하여 행해진다.In this example, the evacuation driving time is calculated based on the information of the scheduled time of the terror occurrence. That is, evacuation driving time is calculated so that evacuation driving ends before the scheduled time (limit time) of the terror occurrence. Specifically, the calculation of the evacuation operation time for each elevator 2 is performed as follows.

우선, 각 엘리베이터(2)에 대해 각각의 주회(周回) 시간이 계산된다. 주회 시간이란, 엘리베이터 칸(3)이 피난층을 출발하고 나서, 각 구출층에 남겨진 재관자를 엘리베이터 칸(2)에 차례로 승차시키고, 피난층으로 돌아와서 재관자의 하차를 완료시킨 후, 피난층으로부터 재차 출발할 때까지의 1 사이클 시간이다.First, each turn time is calculated for each elevator 2. With time for car 3, the car 3 leaves the evacuation floor, and the passengers left on each rescue floor are taken to the car 2 in turn, and after returning to the evacuation floor and completing the disembarkation of the visitors, the evacuation floor is restarted from the evacuation floor. One cycle time to departure.

이 후, 각 엘리베이터(2)에 대해 주회 시간에 기초하여 여유 시간 T가 구해진다. 예를 들어 주회 시간이 5분 이내인 경우에는 여유 시간 T=5분으로 되고, 주회 시간이 5분보다 길고 10분 이내인 경우에는 여유 시간 T=10분으로 된다. 이 후, 각 엘리베이터(2)에 대해 피난 운전 시간이 여유 시간 T에 기초하여 산출된다. 본 예에서는 테러 발생의 예정 시각보다 여유 시간 T분만큼 빠른 시각에 피난 운전이 종료하도록, 각 엘리베이터(2)에 대해 피난 운전 시간이 산출된다. 또한, 예를 들어 T=15분 등의 일정값을 여유 시간 T분으로 하여 미리 설정해도 된다.Subsequently, the spare time T is calculated | required about each elevator 2 based on the winding time. For example, if the meeting time is less than 5 minutes, the spare time T = 5 minutes, and if the meeting time is longer than 5 minutes and less than 10 minutes, the spare time T = 10 minutes. After that, the evacuation operation time is calculated based on the allowable time T for each elevator 2. In this example, the evacuation operation time is calculated for each elevator 2 so that evacuation operation is terminated at an earlier time T minutes earlier than the scheduled time of the terror occurrence. Further, for example, a predetermined value such as T = 15 minutes may be set in advance as a spare time T minutes.

피난 운전 판정부(13)는 피난 운전 시간 산출부(12)로부터의 정보에 기초하여, 각 엘리베이터(2)에 대한 피난 운전의 계속 여부를 판정한다. 즉, 피난 운전 판정부(13)는 피난 운전을 개시하고 나서의 시간이 피난 운전 시간내일 때에 각 엘리베이터(2)에 대한 피난 운전의 계속이 가능하다는 판정(계속 가능 판정)을 하고, 피난 운전을 개시하고 나서의 시간이 피난 운전 시간을 경과하고 있을 때에 각 엘리베이터(2)에 대한 피난 운전의 계속이 불가능하다는 판정(계속 불가 판정)을 한다.The evacuation operation determination unit 13 determines whether the evacuation operation for each elevator 2 is continued on the basis of the information from the evacuation operation time calculation unit 12. That is, the evacuation operation determination unit 13 determines that the evacuation operation can be continued for each elevator 2 when the time since the evacuation operation is started is within the evacuation operation time (continuity determination), and the evacuation operation is performed. When the time since the start has passed the evacuation operation time, it is determined that the evacuation operation for each elevator 2 is impossible (continuity determination).

피난 운전 실시부(11)는 피난 운전 판정부(13)로부터의 정보에 기초하여, 각 엘리베이터(2)에 대한 피난 운전을 제어한다. 즉, 피난 운전 실시부(11)는 피난 운전 판정부(13)가 계속 가능 판정을 개시했을 때에, 각 엘리베이터(2)에 대한 피난 운전을 개시한다. 또, 피난 운전 실시부(11)는 피난 운전 판정부(13)가 계속 가능 판정을 행하고 있을 때에 각 엘리베이터(2)에 대한 피난 운전을 계속하고, 피난 운전 판정부(13)가 계속 불가 판정을 실시했을 때에 각 엘리베이터(2)에 대한 피난 운전을 종료한다.The evacuation operation execution unit 11 controls the evacuation operation for each elevator 2 based on the information from the evacuation operation determination unit 13. That is, the evacuation driving unit 11 starts the evacuation operation for each elevator 2 when the evacuation driving determination unit 13 starts the determination of the possibility of continuing. In addition, the evacuation operation execution unit 11 continues the evacuation operation for each elevator 2 when the evacuation operation determination unit 13 is continuously performing the determination, and the evacuation operation determination unit 13 determines that the evacuation operation determination unit 13 cannot continue. When performed, the evacuation operation for each elevator 2 is terminated.

알림 지령부(14)는 피난 운전 판정부(13)로부터의 정보에 기초하여 각 비상 방송 장치(7)를 제어한다. 즉, 알림 지령부(14)는 피난 운전 판정부(13)가 계속 가능 판정을 행하고 있을 때에 피난 알림 지령을 각 비상 방송 장치(7)로 출력하고, 피난 운전 판정부(13)가 계속 불가 판정을 행하고 있을 때에 종료 알림 지령을 각 비상 방송 장치(7)로 출력한다. 본 예에서는 알림 지령부(14)로부터 각 비상 방송 장치(7)로의 지령 전송은 방재 관리 장치(8)를 통하여 행해진다.The notification command unit 14 controls each emergency broadcast apparatus 7 based on the information from the evacuation driving determination unit 13. That is, the notification command unit 14 outputs the evacuation notification command to each emergency broadcasting device 7 when the evacuation driving determination unit 13 is capable of continuing, and the evacuation driving determination unit 13 determines that the evacuation driving determination unit 13 cannot continue. Outputs an end notification command to each emergency broadcast apparatus 7 during the operation. In this example, command transmission from the notification command unit 14 to each emergency broadcast apparatus 7 is performed through the disaster prevention management apparatus 8.

각 비상 방송 장치(7)는 피난 알림 지령을 받는 것에 의해, 각 엘리베이터(2)의 피난 운전에 의한 피난이 가능하다는 것을 건물내에 알린다. 또, 각 비상 방송 장치(7)는 종료 알림 지령을 받는 것에 의해, 각 엘리베이터(2)의 피난 운전이 종료한다는 것을 건물내에 알린다.Each emergency broadcast apparatus 7 informs the building that evacuation by the evacuation operation of each elevator 2 is possible by receiving an evacuation notification command. Moreover, each emergency broadcast apparatus 7 informs in a building that the evacuation operation of each elevator 2 is complete | finished by receiving the completion | finish notification command.

피난 지원 장치(9)는 연산 처리부(CPU), 기억부(ROM 및 RAM 등) 및 신호 입출력부를 갖는 컴퓨터에 의해 구성되어 있다. 통신부(10), 피난 운전 실시부(11), 피난 운전 시간 산출부(12), 피난 운전 판정부(13) 및 알림 지령부(14)의 기능은 피난 지원 장치(9)의 컴퓨터에 의해 실현된다.The evacuation support device 9 is configured by a computer having an arithmetic processing unit (CPU), a storage unit (ROM and RAM, etc.) and a signal input / output unit. The functions of the communication unit 10, the evacuation driving unit 11, the evacuation driving time calculating unit 12, the evacuation driving determining unit 13, and the notification command unit 14 are realized by a computer of the evacuation supporting apparatus 9. do.

즉, 컴퓨터의 기억부에는 통신부(10), 피난 운전 실시부(11), 피난 운전 시간 산출부(12), 피난 운전 판정부(13) 및 알림 지령부(14)의 기능을 실현하기 위한 프로그램이 격납되어 있다. 또, 각 구출층 등의 정보도 기억부에 격납된다. 연산 처리부는 기억부에 격납된 프로그램에 기초하여 피난 지원 장치(9)의 기능에 관한 연산 처리를 실행한다.That is, a program for realizing the functions of the communication unit 10, the evacuation operation execution unit 11, the evacuation operation time calculation unit 12, the evacuation operation determination unit 13, and the notification command unit 14 is stored in the storage unit of the computer. Is stored. In addition, information such as each rescue layer is also stored in the storage unit. The arithmetic processing unit executes arithmetic processing relating to the function of the evacuation support device 9 based on the program stored in the storage unit.

다음에, 동작에 대해 설명한다. 도 2는 도 1의 엘리베이터의 피난 지원 장치(9)의 처리 동작을 설명하기 위한 플로우차트이다. 도면에 나타내는 바와 같이, 예를 들어 테러 발생의 예고를 받은 경우에는 중앙 관리실의 감시원에 의해 외부 입력 장치가 조작되어, 테러 발생의 예정 시각인 한계 시각(긴급도 정보)을 포함한 조작 입력 정보가 외부 입력 장치로부터 피난 지원 장치(9)에 입력된다(S1).Next, the operation will be described. FIG. 2 is a flowchart for explaining the processing operation of the evacuation support device 9 of the elevator of FIG. As shown in the figure, for example, when a notice of terrorism is received, an external input device is operated by a watchman in the central management room, and operation input information including a limit time (urgent information), which is a scheduled time of terror occurrence, is external. It is input to the evacuation support apparatus 9 from an input apparatus (S1).

외부 입력 장치로부터의 조작 입력 정보가 피난 지원 장치(9)에 입력되면, 한계 시각에 기초하여 피난 운전 시간이 피난 운전 시간 산출부(12)에 의해 산출된 다(S2). 이 후, 각 엘리베이터(2)의 피난 운전이 피난 운전 실시부(11)의 제어에 의해 실시된다(S3).When operation input information from an external input device is input to the evacuation support device 9, the evacuation operation time is calculated by the evacuation operation time calculation unit 12 based on the limit time (S2). After that, the evacuation operation of each elevator 2 is performed by the control of the evacuation operation execution unit 11 (S3).

이 후, 피난 운전 시간이 경과했는지의 여부가 피난 운전 판정부(13)에 의해 판정된다(S4). 피난 운전 시간이 경과하고 있지 않은 경우에는 각 엘리베이터(2)의 피난 운전의 실시가 계속된다(S3). 이 경우에는 피난 알림 지령이 알림 지령부(14)로부터 각 비상 방송 장치(7)로 출력된다. 이에 의해, 각 엘리베이터(2)의 피난 운전에 의한 피난이 가능하다는 취지가 각 비상 방송 장치(7)에 의해 건물내에 알려진다.Thereafter, whether the evacuation operation time has elapsed is determined by the evacuation operation determination unit 13 (S4). If the evacuation operation time has not elapsed, the evacuation operation of each elevator 2 continues (S3). In this case, the evacuation notification command is output from the notification command unit 14 to each emergency broadcast apparatus 7. By this, it is known by the emergency broadcasting apparatus 7 in the building that the evacuation by the evacuation operation of each elevator 2 is possible.

한편, 피난 운전 시간이 경과한 경우에는 각 엘리베이터(2)의 피난 운전이 피난 운전 실시부(11)의 제어에 의해 종료된다. 이 때, 엘리베이터 칸(2)은 피난층으로 신속하게 이동되어 문열림 상태인 채로 정상 정지된다. 또, 이 때, 종료 알림 지령이 알림 지령부(14)로부터 각 비상 방송 장치(7)로 출력되어, 각 엘리베이터(2)의 피난 운전이 종료한다는 취지가 각 비상 방송 장치(7)에 의해 건물내에 알려진다(S5).On the other hand, when the evacuation operation time has elapsed, evacuation operation of each elevator 2 is terminated by the control of the evacuation operation execution unit 11. At this time, the cage | basket | car 2 is moved to an evacuation floor quickly, and is stopped normally with the door open. At this time, the termination notification command is output from the notification command unit 14 to each emergency broadcasting device 7 so that the evacuation operation of each elevator 2 is completed by the emergency broadcasting device 7. It is known in (S5).

이 후, 재관자가 건물내에 남아 있는 경우에 재관자는 각 비상 방송 장치(7)에 의해 유도되면서 예를 들어 계단 등에 의해 피난하게 된다.Subsequently, when the inmates remain in the building, the inmates are guided by each emergency broadcasting device 7 and evacuated by, for example, stairs.

이와 같은 엘리베이터의 피난 지원 장치에서는 예를 들어 테러 발생의 예정 시각 등, 긴급의 정도를 나타내는 긴급도 정보에 기초하여 피난 운전을 계속할 예정 시간이 피난 운전 시간으로서 산출되고, 산출된 피난 운전 시간에 기초하여 피난 운전의 계속 여부가 판정되므로, 긴급시에 재관자를 피난층에 효율적으로 운반 할 수 있는 동시에, 각 엘리베이터(2)의 운전이 이상 정지할 가능성이 극단적으로 높아지기 전에 각 엘리베이터(2)의 피난 운전을 종료시킬 수 있다. 따라서, 각 엘리베이터(2)의 피난 운전의 이상 정지의 방지를 도모할 수 있고, 예를 들어 재관자의 엘리베이터 칸(3)내에 갇히는 일이 발생하는 것을 방지할 수 있다.In such an evacuation assistance device of an elevator, the estimated time to continue evacuation operation is calculated as the evacuation operation time based on the emergency information indicating the degree of emergency, such as, for example, the scheduled time of the occurrence of terrorism, and is based on the calculated evacuation operation time. Therefore, it is determined whether the evacuation operation is continued, so that the evacuator can be efficiently transported to the evacuation floor in an emergency, and the evacuation of each elevator 2 before the operation of each elevator 2 abnormally increases. You can end the operation. Therefore, the abnormal stop of the evacuation operation of each elevator 2 can be prevented, for example, it can prevent that trapping in the cage | basket | car 3 of a reinspector arises.

또, 각 엘리베이터(2)의 피난 운전의 계속이 불가능하다는 판정이 피난 운전 판정부(13)에 의해 행해졌을 때에, 각 엘리베이터(2)의 피난 운전이 종료한다는 취지를 각 비상 방송 장치(7)가 건물내에 알리기 때문에, 각 엘리베이터(2)의 피난 운전의 종료를 재관자에게 인식시킬 수 있고, 피난 운전 종료후의 패닉 발생의 방지를 도모할 수 있다.In addition, when the evacuation operation determination unit 13 determines that the evacuation operation of each elevator 2 cannot be continued, the emergency broadcast apparatus 7 indicates that the evacuation operation of each elevator 2 ends. Since the inside of the building is notified, the end of the evacuation operation of each elevator 2 can be recognized by the inspector, and the panic occurrence after the evacuation operation can be prevented.

또한, 상기의 예에서는 엘리베이터(2)의 피난 운전은 모든 서비스층이 구출층으로 설정되어, 통상 운전과 동일한 운전으로 되어 있으나, 예를 들어 각 서비스층 중, 미리 설정된 소정의 서비스층만을 구출층으로 하고, 구출층과 피난층 사이에서 엘리베이터 칸(3)을 왕복 이동시키는 운전을 피난 운전으로 해도 된다. 이 경우, 피난 운전시의 엘리베이터 칸(3)은 구출층 및 피난층에만 정지되고, 구출층 및 피난층 이외의 각 층은 모두 통과한다. 또, 구출층과 다른 층에 있는 재관자는 엘리베이터(2)를 이용하기 위해서, 건물에 마련된 계단으로 구출층으로 이동하게 된다. 이와 같이 하면, 엘리베이터 칸(3)을 정지시키는 층을 줄일 수 있고, 건물내의 재관자를 피난층으로 운반할 때의 운반 효율의 향상을 도모할 수 있다.In the above example, in the evacuation operation of the elevator 2, all service floors are set to the rescue floor, and the same operation as the normal operation is performed, but for example, only a predetermined service floor preset among each service floor is the rescue floor. The operation of reciprocating the car 3 between the rescue floor and the evacuation floor may be an evacuation operation. In this case, the car 3 at the time of evacuation operation is stopped only in the rescue floor and the evacuation floor, and each floor other than the rescue floor and the evacuation floor passes. In addition, the inspector on the other floor of the rescue floor moves to the rescue floor by the stairs provided in the building in order to use the elevator 2. By doing in this way, the floor which stops the cage | basket | car 3 can be reduced, and the conveyance efficiency at the time of conveying the reinspector in a building to an evacuation floor can be aimed at.

또, 피난 운전의 운전 방식은 상기의 방법에 한정되지 않으며, 예를 들어 건물의 형상, 용도 또는 재관 인구 등에 따라 미리 설정해 두면 된다.In addition, the driving method of evacuation driving | operation is not limited to the said method, For example, what is necessary is just to set previously according to the shape of a building, a use, or the population of an attendant.

또, 상기의 예에서는 외부 입력 장치로부터의 조작 입력 정보에 포함되는 테러 발생의 예정 시각(한계 시각)의 정보가 긴급도 정보로서 피난 운전 시간 산출부(12)에 입력되어도 되지만, 방재 관리 장치(8)로부터의 정보가 긴급도 정보로서 피난 운전 시간 산출부(12)에 입력되어도 된다.In the above example, the information on the scheduled time (limit time) of the terror occurrence included in the operation input information from the external input device may be input to the evacuation driving time calculation unit 12 as the emergency information, but the disaster prevention management device ( The information from 8) may be input to the evacuation operation time calculation unit 12 as the emergency information.

예를 들어 건물에 화재가 발생한 경우, 건물의 각 층에 마련된 복수의 화재 감지기로부터의 정보에 기초하여, 방재 관리 장치(8)가 화재 발생의 유무 검출과 화재 발생층의 특정을 행하도록 하고, 방재 관리 장치(8)로부터의 정보에 기초하여 피난 운전 시간 산출부(12)가 피난 운전 시간을 산출하도록 해도 된다. 이 경우, 피난 운전 시간 산출부(12)는 방재 관리 장치(8)로부터의 정보에 기초하여 화재의 연소 속도를 구하고, 구한 연소 속도로부터 피난 운전 시간을 산출한다.For example, when a fire breaks out in a building, the disaster prevention management apparatus 8 detects the presence or absence of a fire occurrence and specifies the fire generation floor based on information from a plurality of fire detectors provided on each floor of the building, The evacuation operation time calculation unit 12 may calculate the evacuation operation time based on the information from the disaster prevention management apparatus 8. In this case, the evacuation operation time calculation unit 12 calculates the combustion speed of the fire based on the information from the disaster prevention management apparatus 8 and calculates the evacuation operation time from the obtained combustion speed.

이와 같이 해도, 각 엘리베이터(2)의 운전이 이상 정지할 가능성이 극단적으로 높아지기 전에 각 엘리베이터(2)의 피난 운전을 종료시킬 수 있다. 따라서, 각 엘리베이터(2)의 피난 운전의 이상 정지 방지를 도모할 수 있고, 예를 들어 재관자가 엘리베이터 칸(3)내에 갇히는 일이 발생하는 것을 방지할 수 있다.Even in this way, the evacuation operation of each elevator 2 can be terminated before the possibility that the operation of each elevator 2 stops abnormally becomes extremely high. Therefore, the abnormal stop of evacuation operation of each elevator 2 can be prevented, for example, it can prevent that a reinvestigator is trapped in the cage | basket | car 3, and generation | occurrence | production.

본 발명에 의하면, 엘리베이터의 피난 운전의 이상 정지의 방지를 도모할 수 있는 엘리베이터의 피난 지원 장치를 제공할 수 있다.According to the present invention, it is possible to provide an elevator evacuation support apparatus capable of preventing abnormal stop of evacuation operation of the elevator.

Claims (2)

복수의 층을 서비스층으로 하는 엘리베이터의 운전을 긴급시에 관리하는 것에 의해, 건물내에 남겨진 재관자를 피난층으로 피난시키는 엘리베이터의 피난 지원 장치로서,As an evacuation support device for an elevator that evacuates the inspectors left in the building to the evacuation floor by managing the operation of the elevator having a plurality of floors as a service floor in an emergency, 각 상기 서비스층의 적어도 어느 하나를 구출층으로 설정하고, 상기 재관자를 상기 구출층으로부터 상기 피난층으로 운반하기 위한 피난 운전을 상기 엘리베이터에 대해 실시하는 피난 운전 실시부,An evacuation operation enforcement unit which sets at least one of the service floors to the rescue floor and performs evacuation operation for the elevator for transporting the inspector from the rescue floor to the evacuation floor; 긴급의 정도를 나타내는 긴급도 정보를 받는 동시에, 상기 긴급도 정보에 기초하여 상기 피난 운전을 계속할 예정 시간을 피난 운전 시간으로서 산출하는 피난 운전 시간 산출부, 및An evacuation operation time calculating section that receives emergency information indicating the degree of urgency and calculates, as an evacuation operation time, a scheduled time for continuing the evacuation operation based on the emergency information; and 상기 피난 운전 시간 산출부로부터의 정보에 기초하여 상기 피난 운전의 계속 여부를 판정하는 피난 운전 판정부를 구비하고,An evacuation operation determination unit that determines whether to continue the evacuation operation based on the information from the evacuation operation time calculation unit; 상기 피난 운전 실시부는 상기 피난 운전 판정부로부터의 정보에 기초하여 상기 피난 운전을 제어하는 것을 특징으로 하는 엘리베이터의 피난 지원 장치.And the evacuation driving unit controls the evacuation operation based on the information from the evacuation driving determination unit. 청구항 1에 있어서,The method according to claim 1, 상기 건물에는 알림 장치가 마련되고 있고,The building is provided with a notification device, 상기 피난 운전의 계속이 불가능하다는 판정이 상기 피난 운전 판정부에 의해 행해졌을 때에, 종료 알림 지령을 상기 알림 장치에 출력하는 알림 지령부를 추 가로 구비하고,When the determination that the evacuation operation cannot be continued is made by the evacuation operation determination unit, a notification command unit for outputting an end notification command to the notification device is further provided, 상기 알림 장치는 상기 종료 알림 지령을 받는 것에 의해, 상기 피난 운전이 종료하는 것을 상기 건물내에 알리는 것을 특징으로 하는 엘리베이터의 피난 지원 장치.And the notification device notifies the inside of the building that the evacuation operation is terminated by receiving the termination notification command.
KR1020087019648A 2008-08-11 2006-07-06 Evacuation assistance device for elevator KR100918144B1 (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
KR1020087019648A KR100918144B1 (en) 2008-08-11 2006-07-06 Evacuation assistance device for elevator

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
KR1020087019648A KR100918144B1 (en) 2008-08-11 2006-07-06 Evacuation assistance device for elevator

Publications (2)

Publication Number Publication Date
KR20080087156A KR20080087156A (en) 2008-09-30
KR100918144B1 true KR100918144B1 (en) 2009-09-17

Family

ID=40026012

Family Applications (1)

Application Number Title Priority Date Filing Date
KR1020087019648A KR100918144B1 (en) 2008-08-11 2006-07-06 Evacuation assistance device for elevator

Country Status (1)

Country Link
KR (1) KR100918144B1 (en)

Families Citing this family (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
US11370639B2 (en) * 2017-09-20 2022-06-28 Jessica Williams Emergency elevator evacuation system

Citations (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
WO2004101418A1 (en) 2003-05-14 2004-11-25 Mitsubishi Denki Kabushiki Kaisha Fire control system of elevator

Patent Citations (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
WO2004101418A1 (en) 2003-05-14 2004-11-25 Mitsubishi Denki Kabushiki Kaisha Fire control system of elevator

Also Published As

Publication number Publication date
KR20080087156A (en) 2008-09-30

Similar Documents

Publication Publication Date Title
KR100938040B1 (en) Management device for evacuation, used for elevator
JP5095399B2 (en) Elevator evacuation support device
US7677363B2 (en) Evacuation assistance device for elevator
KR100973883B1 (en) Evacuation assistance device for elevator
KR101203357B1 (en) Refuge supporting device of elevator
KR100968311B1 (en) Device for managing elevator in evacuation
EP2610202A1 (en) Monitor control device for elevator
JPWO2009054065A1 (en) Evacuation support system for double deck elevator
CN101238058A (en) Management device for evacuation, used for elevator
KR100918144B1 (en) Evacuation assistance device for elevator
JP2008184301A (en) Elevator control system
CN108290710B (en) Elevator control device and elevator control method
KR102657840B1 (en) Elevator control system and elevator control method for evacuation
JP5637617B2 (en) Evacuation system for elevator
JP6288391B1 (en) Recovery support system
TW202203166A (en) Support system for elevator entrapment rescue, mobile terminal, and support program for elevator entrapment rescue

Legal Events

Date Code Title Description
A201 Request for examination
E701 Decision to grant or registration of patent right
GRNT Written decision to grant
FPAY Annual fee payment

Payment date: 20120821

Year of fee payment: 4

FPAY Annual fee payment

Payment date: 20130822

Year of fee payment: 5

FPAY Annual fee payment

Payment date: 20150820

Year of fee payment: 7

FPAY Annual fee payment

Payment date: 20160818

Year of fee payment: 8

FPAY Annual fee payment

Payment date: 20170823

Year of fee payment: 9

FPAY Annual fee payment

Payment date: 20180816

Year of fee payment: 10

FPAY Annual fee payment

Payment date: 20190819

Year of fee payment: 11