KR100670675B1 - Continuous construction method of multi span prestressed steel composite beam - Google Patents

Continuous construction method of multi span prestressed steel composite beam Download PDF

Info

Publication number
KR100670675B1
KR100670675B1 KR1020060024334A KR20060024334A KR100670675B1 KR 100670675 B1 KR100670675 B1 KR 100670675B1 KR 1020060024334 A KR1020060024334 A KR 1020060024334A KR 20060024334 A KR20060024334 A KR 20060024334A KR 100670675 B1 KR100670675 B1 KR 100670675B1
Authority
KR
South Korea
Prior art keywords
continuous
composite beam
concrete
lower flange
steel
Prior art date
Application number
KR1020060024334A
Other languages
Korean (ko)
Inventor
박은진
정재희
Original Assignee
박은진
정재희
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Family has litigation
First worldwide family litigation filed litigation Critical https://patents.darts-ip.com/?family=38014061&utm_source=***_patent&utm_medium=platform_link&utm_campaign=public_patent_search&patent=KR100670675(B1) "Global patent litigation dataset” by Darts-ip is licensed under a Creative Commons Attribution 4.0 International License.
Application filed by 박은진, 정재희 filed Critical 박은진
Priority to KR1020060024334A priority Critical patent/KR100670675B1/en
Application granted granted Critical
Publication of KR100670675B1 publication Critical patent/KR100670675B1/en

Links

Images

Classifications

    • EFIXED CONSTRUCTIONS
    • E01CONSTRUCTION OF ROADS, RAILWAYS, OR BRIDGES
    • E01DCONSTRUCTION OF BRIDGES, ELEVATED ROADWAYS OR VIADUCTS; ASSEMBLY OF BRIDGES
    • E01D2/00Bridges characterised by the cross-section of their bearing spanning structure
    • E01D2/02Bridges characterised by the cross-section of their bearing spanning structure of the I-girder type
    • EFIXED CONSTRUCTIONS
    • E01CONSTRUCTION OF ROADS, RAILWAYS, OR BRIDGES
    • E01DCONSTRUCTION OF BRIDGES, ELEVATED ROADWAYS OR VIADUCTS; ASSEMBLY OF BRIDGES
    • E01D21/00Methods or apparatus specially adapted for erecting or assembling bridges
    • EFIXED CONSTRUCTIONS
    • E01CONSTRUCTION OF ROADS, RAILWAYS, OR BRIDGES
    • E01DCONSTRUCTION OF BRIDGES, ELEVATED ROADWAYS OR VIADUCTS; ASSEMBLY OF BRIDGES
    • E01D2101/00Material constitution of bridges
    • E01D2101/20Concrete, stone or stone-like material
    • E01D2101/24Concrete
    • E01D2101/26Concrete reinforced
    • E01D2101/28Concrete reinforced prestressed
    • E01D2101/285Composite prestressed concrete-metal
    • EFIXED CONSTRUCTIONS
    • E01CONSTRUCTION OF ROADS, RAILWAYS, OR BRIDGES
    • E01DCONSTRUCTION OF BRIDGES, ELEVATED ROADWAYS OR VIADUCTS; ASSEMBLY OF BRIDGES
    • E01D22/00Methods or apparatus for repairing or strengthening existing bridges ; Methods or apparatus for dismantling bridges

Landscapes

  • Engineering & Computer Science (AREA)
  • Architecture (AREA)
  • Civil Engineering (AREA)
  • Structural Engineering (AREA)
  • Bridges Or Land Bridges (AREA)

Abstract

A continuous construction method of a multi-span prestressed composite beam is provided to maintain lower sectional height of the steel composite beam by drawing a method for continuously connecting lower flange concrete and maintaining a continued point to the same height with the other portions of a bridge after pouring bottom and web concrete. A continuous construction method of a multi-span prestressed composite beam comprises the steps of: arranging a vertical reinforcing member between a middle supporting board mounted at the lower side of an I-shape steel at a supporting center of a continuous point and upper and lower flanges of the I-shape steel; separating a tensile member settling board from the end of the I-shape steel, and forming a block-out continuous connecting unit on the I-shape steel by installing the tensile member settling board on a lower supporting board mounted on the lower side of the middle supporting board; assembling iron bar and tensile member around the lower flange of the I-shape steel and limiting preflex load; forming lower flange concrete and projecting vertical connecting iron bars toward the block-out continuous connecting unit; removing the preflex load to introduce pressing stress to the lower flange concrete; manufacturing composite steel beam by tensing and settling the tensile member on the tensile member settling board; installing the steel composite beam on a pier(B) or an abutment to install a bridge base on the prestressed composite beam; vertically and laterally connecting the steel composite beams by connecting iron bars including vertical connecting iron bars(152), vertical iron bars(151), and lateral connecting iron bars(153); pouring lower flange concrete and web/bottom concrete to the block-out connecting unit; and curing and shaping the continuous point unit.

Description

다경간 프리스트레스트 강합성빔의 연속시공방법{Continuous Construction Method of Multi Span Prestressed Steel Composite Beam}Continuous Construction Method of Multi Span Prestressed Steel Composite Beam

도 1a, 도 1b 및 도 1c는 종래의 프리스트레스트 프리플렉스 강합성빔을 이용한 다경간 프리스트레스트 프리플렉스 강합성빔의 시공방법을 도시한 것이다.1A, 1B and 1C illustrate a method of constructing a multi-span prestressed preflex composite beam using a conventional prestressed preflex composite beam.

도 2a는 본 발명의 다경간 프리스트레스트 강합성빔의 I형 강재를 도시한 것이다.Figure 2a shows the type I steel of the multi-span prestressed steel composite beam of the present invention.

도 2b는 본 발명의 다경간 프리스트레스트 강합성빔의 연속연결부로부터 돌출된 종방향 연결철근을 도시한 것이다.Figure 2b shows a longitudinal connecting reinforcing bar projecting from the continuous connection of the multi-span prestressed rigid composite beam of the present invention.

도 2c 및 도 2d는 본 발명의 다경간 프리스트레스트 강합성빔의 연결지점부의 처리상태를 도시한 것이다.2C and 2D show processing conditions of the connection point portion of the multi-span prestressed rigid composite beam of the present invention.

도 3a, 도 3b 및 도 3c는 본 발명의 다경간 프리스트레스트 강합성빔의 정착블록의 설치상태도를 도시한 것이다. Figures 3a, 3b and 3c is a diagram showing the installation of the fixing block of the multi-span prestressed rigid composite beam of the present invention.

<도면의 주요부분에 대한 부호의 설명><Description of the symbols for the main parts of the drawings>

100:연속연결부 110:하부지지판100: continuous connection 110: lower support plate

120:중간연결재 130:수직보강판120: intermediate connector 130: vertical reinforcing plate

140:긴장재정착판 150:연속연결부철근140: tension reset plate 150: continuous connecting rod

200:I형 강재 300:긴장재200: Type I steel 300: Tension material

400:정착블록400: fixing block

본 발명은 다경간 연속 프리스트레스트 강합성빔의 연결 및 연속시공방법에 관한 것이다. 더욱 구체적으로 다경간 프리스트레스트 강합성빔의 시공에 있어서, 복부 및 바닥판콘크리트 타설에 앞서 교각 위에 설치되는 연속지점부에서 프리스트레스트 강합성빔을 연속 결합시킬 수 있는 방법 및 상기 연속지점부 경계면의 하부플랜지콘크리트에서 발생하는 압축응력을 경감시킬 수 있는 다경간 프리스트레스트 강합성빔의 연속시공방법에 관한 것이다.The present invention relates to a method of connecting and continuous construction of a multi-span continuous prestressed rigid composite beam. More specifically, in the construction of multi-span prestressed composite beams, a method of continuously coupling the prestressed composite beams in a continuous point portion installed on the piers prior to placing the abdominal and bottom plate concrete, and the boundary of the continuous point portion interface The present invention relates to a continuous construction method of multi-span prestressed rigid composite beams that can reduce the compressive stress generated in the lower flange concrete.

프리스트레스트 강합성빔은 I형 강재와 I형 강재의 하부플랜지 주변에 콘크리트를 타설,양생시켜 I형 강재와 하부플랜지콘크리트가 합성된 강합성빔에 프리플렉션(Preflexion)과 PC 강연선을 포함하는 긴장재에 의해 또는 프리플렉션없이 긴장재만에 의해 하부플랜지콘크리트에 소요의 압축 프리스트레스를 도입시킨 강합성빔을 의미한다.Prestressed steel composite beam is a tension material including preflexion and PC strands in a steel composite beam composed of I-type steel and lower flange concrete by placing and curing concrete around I-type steel and lower flange of I-type steel. By a tension material only by means of or without pre-fraction means a rigid composite beam in which required compression prestress is introduced into the lower flange concrete.

종래의 프리스트레스트 프리플렉스 강합성빔(10)은 1차 프리스트레스(I형 강재에 프리플렉션 하중이 가해진 상태에서 I형 강재의 하부플랜지주변에 콘크리트를 타설, 양생한 후 프리플렉션 하중을 제거하여 I형 강재의 탄성복원력에 의하여 하부플랜지콘크리트에 도입되는 압축응력)가 도입된 상태에서, PC 강연선을 이용하여 2차 프리스트레스를 하부플랜지콘크리트에 도입하는 방식으로 제작되는 교량용 강 합성빔이다. Conventional prestressed preflex steel composite beam 10 is the first pre-stress (pre-loading the concrete in the lower flange of the I-type steel in the state that the pre-flection load is applied to the I-type steel, after curing and remove the pre-flection load I It is a steel composite beam for bridges manufactured by introducing secondary prestress into lower flange concrete using a PC stranded wire in the state where the compressive stress introduced into the lower flange concrete by the elastic restoring force of the shape steel is introduced.

즉, 도 1a 같이 하부플랜지 콘크리트(20)의 타설 전, 하부플랜지 콘크리트 내부에 형성된 하부플랜지, 복부 및 상부플랜지로 구성된 I형 강재(10)의 하부플랜지(13) 주위에 일정간격을 두고 미리 다수의 PC 강연선(30)을 분산 배치시키고, 하부플랜지 주변에 거푸집을 이용하여 콘크리트를 타설,양생시킨 후, 프리플렉션 하중을 제거(릴리즈)하여 하부플랜지콘크리트(20)에 1차 프리스트레스를 도입시킨 상태에서, 하부플랜지콘크리트(20)에 배치된 다수의 PC 강연선을 긴장하여 하부플랜지콘크리트(20) 단부에 정착시킴으로서, 2차 프리스트레스를 추가로 더 도입되도록 한다.That is, before placing the lower flange concrete 20, as shown in Figure 1a, a plurality of in advance around the lower flange 13 of the I-type steel (10) consisting of the lower flange, the abdomen and the upper flange formed inside the lower flange concrete PC strands 30 are distributed and placed around the lower flange using the formwork, concrete is poured, and then the pre-flection load is removed (release) to introduce the primary prestress to the lower flange concrete (20) In, by tensioning a plurality of PC strands disposed on the lower flange concrete 20 to the lower flange concrete 20, the secondary prestress is further introduced.

이에 종래 프리플렉스 강합성빔에서 확보되는 낮은 형고를 그대로 유지하면서 I형 강재 사용량을 절감하여 경제성을 충분히 확보할 수 있는 장점과 하부플랜지콘크리트의 인장균열 및 과도한 처짐 발생과 피로강도저하 등이 발생되지 않는 등 구조적 안전성이 높은 장점이 있다.Therefore, while maintaining the low mold height secured by the conventional preflex steel composite beam, it is possible to reduce the use of I-type steel to secure sufficient economic feasibility, and do not cause tensile cracking, excessive deflection and fatigue strength reduction of the lower flange concrete. It does not have the advantage of high structural safety.

이러한 프리스트레스트 프리플렉스 강합성빔(10)을 다경간 교량에 적용하는 경우, 도 1b와 같이 교대 또는 교각(40)위에 상기 강합성빔(10)을 연속되지 않는 단순구조계로 각 경간에 걸쳐 반복 설치하기도 하나, 이 때 각 경간의 경계인 지점부에는 신축이음장치(50)를 설치하여야 하는바, 이로 인하여 차량의 주행성이 저하될 뿐만 아니라 신축이음 장치의 지속적인 유지보수에 많은 노력과 비용이 소요되므로, 도 1c와 같이 2경간 또는 3경간에 걸쳐 바닥판(60)을 연속 시공하는 경우가 많았다.When the prestressed preflex rigid composite beam 10 is applied to a multi-span bridge, the rigid composite beam 10 is repeated over each span in a simple structure that is not continuous on the alternating or pier 40 as shown in FIG. 1B. In this case, the expansion joint device 50 should be installed at the point that is the boundary of each span. As a result, the driving performance of the vehicle is not only deteriorated, but a lot of effort and cost are required for the continuous maintenance of the expansion joint device. 1C, in many cases, the bottom plate 60 was continuously constructed over two or three spans.

즉, 도 1c와 같이 연속 시공하는 경우, 프리스트레스트 프리플렉스 강합성빔(10)을 교각 위에 설치한 후, 바닥판 및 복부콘크리트를 타설, 양생하는 시공과정의 특성상, 그리고 연속지점부에서 교각의 크기가 제한되므로 프리스트레스트 프리플렉스 강합성빔(10)이 10㎝ 내외의 이격거리를 가진 협소한 인접공간에서 연결시공 하여야 하는 특성상,That is, in the case of continuous construction as shown in FIG. 1c, the prestressed preflex steel composite beam 10 is installed on the piers, and the bottom plate and the abdominal concrete are cast and cured in the construction process, and in the continuous point of the piers Due to the limited size, the prestressed preflex rigid composite beam 10 should be connected in a narrow adjacent space with a separation distance of about 10 cm.

하부플랜지콘크리트의 연결이 실제 거의 불가능하여, 하부플래지콘크리트 연결이 이루어지지 않은 상태에서 하부플랜지콘크리트의 상면에서부터 복부와 바닥판 상면에 걸쳐서만 연속이 이루어짐으로써, 연속지점부(A)의 높이가 프리스트레스트 프리플렉스 강합성교의 다른 부분 높이보다 하부플랜지콘크리트 높이만큼 작아 복부 및 바닥판 콘크리트의 타설, 양생 후에 재하 되는 아스팔트, 방호벽, 보도, 난간 등의 합성후 고정하중 및 차량하중 등에 의해 연속지점부(A)에 발생하는 부모멘트에 대한 저항단면이 부족하게 되어 강합성빔의 높이를 높게 하여야 하는데, 이는 단면높이를 낮게 유지한다는 프리스트레스트 프리플렉스 강합성빔의 근본적인 장점을 상실할 수 있다는 문제점이 있었다.Since the connection of the lower flange concrete is almost impossible, the continuous operation is performed only from the upper surface of the lower flange concrete to the upper surface of the abdomen and the bottom plate in the state where the lower flange concrete is not connected, so that the height of the continuous branch portion A is increased. Continuous point part due to fixed load and vehicle load after composite of asphalt, barrier, sidewalk, railing, etc. There is a problem that the height of the composite beam should be increased due to the lack of the resistance section against the parent moment generated in A), which may cause the loss of the fundamental advantage of the prestressed preflex steel composite beam to keep the cross-sectional height low. .

본 발명은 상술한 문제점을 해결하기 위한 것으로써,The present invention is to solve the above problems,

본 발명의 목적은 프리스트레스트 강합성빔의 다경간 시공에 있어서 하부플랜지콘크리트 연결시공방안을 도출하여 바닥판 및 복부콘크리트 타설 후 연속지점부의 높이를 프리스트레스트 강합성교의 다른 부분 높이와 동일하게 유지시켜 강합성빔의 단면높이를 낮게 유지한다는 프리스트레스트 강합성빔의 근본적인 장점을 고수하는 것이다.The purpose of the present invention is to derive a plan for connecting lower flange concrete in multi-span construction of prestressed rigid composite beams, so that the height of the continuous point portion after the bottom plate and the abdominal concrete is placed equal to the height of other parts of the prestressed steel composite bridge Adhering to the fundamental advantage of prestressed composite beams is to keep the cross-sectional height of the composite beams low.

본 발명의 다른 목적은 프리스트레스트 강합성빔의 단부인 PC 강연선 정착부가 설치되는 하부플랜지콘크리트에서 PC 강연선 정착시 또는 바닥판 및 복부콘크리트 타설이후 합성단계에서 고정하중 및 차량하중에 의해 추가적으로 발생하는 압축응력 등에 의한 영향 고려 시, 하부플랜지콘크리트에서 허용압축응력을 초과할 때 프리스트레스트 강합성빔의 단면높이 증가없이 연속결합부의 하부플랜지콘크리트가 허용압축응력범위내에 있도록 하는 연속결합부 하부플랜지콘크리트 압축응력 저감 방안을 제시하여, 강합성빔의 단면높이를 낮게 유지한다는 프리스트레스트 강합성빔의 장점을 고수함과 동시에 경우에 따라서는 프리플렉션 및 릴리즈 등의 시공과정을 생략 가능할 수도 있도록 하여 시공성 및 경제성을 향상시키는 것이다. Another object of the present invention is to further compress the compression caused by the fixed load and the vehicle load in the lower flange concrete, which is the end of the prestressed steel composite beam is installed in the lower flange concrete is installed on the PC strand wire or in the synthesis step after the bottom plate and abdominal concrete is placed In consideration of the effects of stress, the lower flange concrete compressive stress of the continuous coupling part is such that the lower flange concrete of the continuous coupling part is within the allowable compressive stress range without increasing the cross-sectional height of the prestressed composite beam when the allowable compressive stress is exceeded in the lower flange concrete. By presenting a reduction plan, we adhere to the advantages of prestressed composite beams to keep the cross-sectional height of the composite beams low, and in some cases, the construction process such as preflection and release can be omitted. To improve.

이에 본 발명은 다경간으로 가설되는 프리스트레스트 강합성빔의 연속시공시 연속지점부가 설치되는 교각부에서 프리스트레스트 강합성빔을 연속으로 결합시키기 위한 연결시공방법에 관한 것과 Accordingly, the present invention relates to a connection construction method for continuously coupling a prestressed steel composite beam at a piers provided with continuous point portions during continuous construction of prestressed steel composite beams that are hypothesized by multi-span.

연속지점부 하부플랜지콘크리트 연결결합면에서의 압축력 저감방안에 관한 것으로서 연속지점부가 완전연속으로 결합됨으로써 구조적으로 더욱 안전하고 단면높이가 증대되어 효율성이 향상되어 경제성도 향상되는 다경간 프리스트레스트 강합성교를 건설하고자 함에 있으며, 경우에 따라서는 프리플렉션 및 릴리즈 과정을 생략함으로써 시공성 및 경제성을 향상시키고자 하였다.Multi-span prestressed steel composite bridge that is designed to reduce the compressive force at the joint surface of the lower flange of the continuous branch part. In this case, the construction process and economic feasibility were improved by omitting the preflection and release process.

이하 본 발명의 최적 실시예를 도 2 내지 도 3을 기준으로 살펴본다.Hereinafter, an exemplary embodiment of the present invention will be described with reference to FIGS. 2 to 3.

다경간 프리스트레스트 프리플렉스 강합성빔를 시공하기 위하여 연속지점부가 설치되는 교각 위에 설치하는 프리스트레스트 프리플렉스 강합성빔의 연속연결부(100) 구성은 In order to construct a multi-span prestressed preflex composite beam, the continuous connection part 100 of the prestressed preflex composite beam is installed on a pier where the continuous point portion is installed.

하부플랜지콘크리트(240) 하부에 설치하는 하부지지판(110);A lower support plate 110 installed below the lower flange concrete 240;

하부지지판과 I형 강재(또는 강형)의 하부플랜지(230) 사이에 설치되는 중간지지판(120); An intermediate support plate 120 installed between the lower support plate and the lower flange 230 of the I-type steel (or steel type);

I형 강재(200)의 상부플랜지(210)와 하부플랜지(230) 사이에 설치되는 수직보강재(130);,Vertical reinforcement 130 is installed between the upper flange 210 and the lower flange 230 of the I-type steel 200;

하부플랜지콘크리트에 2차프리스트레스를 도입하기 위한 PC강연선을 포함하는 긴장재(300)가 정착되는 긴장재정착판(140);A tension reset plate 140 in which a tension member 300 including a PC strand for introducing secondary prestress to the lower flange concrete is fixed;

프리스트레스트 강합성빔의 하부플랜지콘크리트에서 연장되어 나온 종방향 철근(151), 종방향 연결철근(152), 종방향으로 연결된 프리스트레스트 프리플렉스 강합성빔을 횡방향으로 연결시키는 횡방향 연결철근(153)을 포함하는 연속연결부철근(150);을 포함하여 구성된다.Longitudinal reinforcing bars 151 extending from the lower flange concrete of the prestressed rigid composite beam, longitudinal connecting reinforcing bars 152, and transverse connecting bars for connecting the prestressed preflex steel composite beams connected in the longitudinal direction ( It is configured to include; continuous connection part reinforcing bars 150 including 153.

본 발명은 우선적으로 I형 강재(200)를 제작하게 되는데 I형 강재 제작시 연속지점부(A)에 해당되는 양 단부 또는 일단부는 도 2a와 같이 I형 강재(200)에 하부지지판(110), 중간지지판(120), 수직보강재(130), 긴장재정착판(140)을 부착시켜 제작하게 된다.The present invention preferentially produces the I-type steel 200, both ends or one end corresponding to the continuous point portion (A) during the production of the I-type steel, the lower support plate 110 on the I-type steel 200 as shown in Figure 2a , The intermediate support plate 120, the vertical reinforcing material 130, the tension repositioning plate 140 is attached to make.

하부지지판(110)은 I형 강재의 단부 하부면에 위치되도록 하는 지지판으로써 그 하부면에는 교량받침(SHOE)이 설치되며, 소정의 크기를 가진 판재를 이용하여 설치하면 된다. 이때 하부지지판은 교량받침의 받침중심부에 지지되도록 하고, 이러한 받침중심부는 프리플렉션 하중 재하 시 역시 지점부로 기능하게 된다.The lower support plate 110 is a support plate to be positioned on the lower end surface of the I-type steel, the bridge support (SHOE) is installed on the lower surface, it may be installed using a plate having a predetermined size. At this time, the lower support plate is to be supported in the support center of the bridge support, and this support center will also function as a point when loading the preflection load.

중간지지판(120)은 하부플랜지콘크리트 콘크리트가 연통될 수 있도록 관통공이 형성된 판재를 양측면에 관통공이 형성되지 않은 판재를 중간부에 하부지지판(110)과 I형 강재(200)의 하부플랜지(230) 사이에 배치하여 고정되도록 설치한다.The intermediate support plate 120 is a plate having a through hole formed so that the lower flange concrete can communicate with the lower plate 230 and the lower flange 230 of the I-type steel 200 in the middle plate Place it in place to fix it.

수직보강재(130)는 상부플랜지(210)와 하부플랜지(230) 사이에 위치하도록 한 일종의 지점보강재 역할을 하는 것으로써 다양한 형상으로써 설치될 수 있다.The vertical reinforcing material 130 serves as a kind of point reinforcing material to be located between the upper flange 210 and the lower flange 230 may be installed in various shapes.

긴장재정착판(140)은 하부지지판(110) 위에 수직판 형태로 설치되도록 하며, 도 2a와 같이 개략 중앙부가 I형 강재의 하부플랜지(230)에 삽입되도록 설치하며, 긴장재(300)가 삽입 후, 긴장, 정착될 수 있도록 다수의 긴장홀이 형성된다.The tension reset plate 140 is installed on the lower support plate 110 in the form of a vertical plate, and is installed so that the central portion is inserted into the lower flange 230 of the roughly I-shaped steel as shown in Figure 2a, the tension member 300 after insertion Numerous tension holes are formed to allow for tension, tension and settlement.

이때 복부 및 바닥판 콘크리트(260,270) 타설시, 연속지점부가 타설 되고 나서, 연속지점부의 콘크리트 양생 후 콘크리트의 건조수축 등으로 인하여 프리스트레스트 강합성빔의 하부플랜지콘크리트와 연속지점부 콘크리트의 결합경계면에서 균열 등이 발생하지 않도록 긴장재 정착판(140)을 하부지지판(110) 위에 설치하며, 필요에 의해서는 추가적으로 하부지지판 또는 I형 강재, 긴장재정착판에 완전결합 작용을 이루도록 도 2a와 같이 전단연결재(160)를 설치한다.At this time, when placing the abdominal and bottom plate concrete (260,270), after the continuous point part is poured, the dry flange shrinkage of the concrete after the curing of the continuous part of the concrete at the joint boundary between the lower flange concrete and the continuous part concrete The tension member fixing plate 140 is installed on the lower support plate 110 so that cracks do not occur, and if necessary, the shear connecting member as shown in FIG. 2A to completely bond to the lower support plate or I-type steel and the tension reset plate. 160).

이러한 긴장재정착판(140)은 I형 강재(200)의 단부가 아닌 단부로부터 이격되어 중앙부쪽에 설치되도록 하여 연속지점부의 하부플랜지콘크리트 부위에 블록아웃된 연속연결부(100)가 형성되도록 한다.The tension repositioning plate 140 is spaced apart from the end of the I-shaped steel 200 to be installed on the center portion so that the continuous connection portion 100 is formed in the lower flange concrete portion of the continuous point portion.

즉 프리스트레스트 강합성빔이 교각 위에 설치될 때 교량받침의 받침중심점 위치에 중간지지판(120), 수직보강재(130)를 설치하고 긴장재정착판(140)은 프리스트레스트 강합성빔의 양단으로부터 안쪽(이격거리 D 만큼)에 설치하는데, That is, when the prestressed rigid composite beam is installed on the bridge piers, the intermediate support plate 120 and the vertical reinforcement 130 are installed at the support center point of the bridge support, and the tension restoring plate 140 is disposed from both ends of the prestressed rigid composite beam ( At the separation distance D)

이와 같이 하는 이유는 프리스트레스트 강합성빔에 전체하중 재하시의 반력을 받침중심점에서 원활하게 처리할 수 있도록 하고,The reason for doing this is to allow the prestressed composite beam to smoothly handle the reaction force under the full load load at the center of support.

프리플렉션 하중 재하시 긴장재 정착부가 아닌 받침중심점이 지점이 되도록 함으로써 프리플렉션 하중에 대한 팔길이를 길게 하여 프리플렉션 도입 효율을 높이고, By raising the arm length to the preflection load by increasing the length of the support center, not the tension fixing unit, during the preflection load, the preflection introduction efficiency is increased.

받침중심점과 프리플렉션 하중재하시의 지점이 일치함으로써 하중집중부에 대한 중복보강을 피하고자 함이다.This is to avoid overlapped reinforcement of the load focusing point by coinciding with the point of the bearing center and the preflection load.

또한 긴장재 정착판을 I형 강재의 양 단부로부터 이격시켜 빔의 중앙쪽에 위치시킴으로써 연속지점부에서 하부플랜지콘크리트가 연속결합시킬 수 있도록 하기 위한 공간(연속연결부)이 확보되도록 함과 더불어In addition, the tension fixing plate is spaced apart from both ends of the I-type steel to be located at the center of the beam, thereby ensuring a space (continuous connection) for continuous coupling of the lower flange concrete at the continuous point.

긴장재정착판을 중앙쪽으로 이동시킴으로 인하여 아스팔트, 난간, 연석 등 합성 후 고정하중 및 활하중 등에 의해 연속지점부에서 발생하는 최대부모멘트부를 피함으로써 연속연결부에서 발생하는 압축응력에 대한 저항효율을 높이고자 함이다.By moving the tension reset plate toward the center, it aims to improve the resistance efficiency against the compressive stress generated in the continuous connection part by avoiding the maximum part moment generated at the continuous point part by the fixed load and live load after synthesizing asphalt, handrail, curb, etc. to be.

위와 같이 I형 강재(200)의 제작 후 철근 및 긴장재(300)인 PC 강연선을 하부플랜지 주변에 조립하고 프리플렉션 하중을 재하하고, 하부플랜지 콘크리트를 타설, 양생한 후, 프리플렉션 하중을 제거하여 하부플랜지콘크리트(240)에 1차 프리스트레스를 도입하게 된다.  After the fabrication of the I-type steel 200, assembling the PC strands of the reinforcing bars and tension members 300 around the lower flange and loading the pre-flection load, and after pouring and curing the lower flange concrete, by removing the pre-flection load Primary prestress is introduced into the lower flange concrete 240.

이때 연속지점부(A)는 도 2b와 같이 종방향 연결을 위한 종방향 연결철근(151)을 미리 노출시켜 놓는다.In this case, the continuous point portion A exposes the longitudinal connecting rebar 151 for longitudinal connection in advance as shown in FIG. 2B.

또한 복부 및 바닥판 콘크리트 타설시 보호캡으로 보호된 PC강연선 정착구에 손상이 가지 않도록 PC 강연선 정착구 주위의 하부플랜지콘크리트는 테이퍼(T) 처리하여 PC 강연선 정착구(141)와 보호캡(142) 보다 길게 돌출시키고 PC 강연선 정착구와 보호캡은 홈(143)에 의하여 결합되도록 하여 완전 밀착이 이루어져 외부충격에 의해 분리되지 않도록 한다. In addition, the lower flange concrete around the PC strand anchorage is tapered (T) to prevent damage to the PC strand anchorage protected by the protective cap when placing the abdominal and bottom plate concrete.The longer length than the PC strand anchorage 141 and the protective cap 142 Protruding from the PC strand wire anchorage and the protective cap is to be coupled by the groove 143 is made in full contact so as not to be separated by an external shock.

긴장재(300)인 PC 강연선을 긴장,정착하여 제작된 프리스트레스트 프리플렉스 강합성빔을 도 2c와 같이 교각(B) 위 연속지점부(A)에 설치하는데, 이때 교량받침(C)은 연속지점부(A)에 설치되는 프리스트레스트 프리플렉스 강합성빔 각각에 설치하여 시공의 편의성을 도모하며, 프리스트레스트 프리플렉스 강합성빔에서 돌출된 종방향 연결용철근(152)과 종방향 연결철근(151)을 겹이음 방법으로 연결시켜 철근의 종방향 연결결합을 시키게 된다.The prestressed preflex composite beam manufactured by tensioning and fixing the PC strand, which is the tension member 300, is installed at the continuous point portion A on the bridge B as shown in FIG. 2C, wherein the bridge support C is the continuous point. It is installed on each of the prestressed preflex steel composite beams installed in the unit (A) to facilitate construction, and the longitudinal connecting reinforcing bars 152 and the longitudinal connecting bars 151 protruding from the prestressed preflex steel composite beams. ) Is connected by the joint method to make the longitudinal connection of the rebar.

또한 종방향으로 결합된 연속지점부(A)를 횡방향 철근(153)을 이용하여 횡방향으로도 연결결합시키고, 도 2d와 같이 복부 및 바닥판콘크리트 타설시 연속지점부 하부플랜지콘크리트(250)를 타설하고 양생하여 블록아웃된 연속연결부(100)에 의하여 양 하부플랜지콘크리트가 서로 일체화되어 연결되도록 하고, 연속지점부(A)가 형성되도록 함으로써 결국,연속지점부(A)의 높이가 프리스트레스트 프리플렉스 강합성교의 다른 부분 높이와 동일하게 형성되도록 하여 연속지점부에 있어 소요의 강성을 충분히 확보할 수 있도록 하고, 강합성빔을 횡방향 및 종방향으로 모두 일 체화되어 연결되도록 함으로써 실질적인 연속 방식으로 시공이 가능한 프리스트레스트 프리플렉스 강합성교의 시공이 가능하도록 한다.In addition, the longitudinally coupled continuous point portion (A) using the transverse reinforcing bars 153 is also coupled in the transverse direction, as shown in Figure 2d when the abdominal and bottom plate concrete pouring continuous flange portion lower flange 250 By placing and curing the two bottom flange concrete is connected to each other integrally connected by the block-out continuous connection portion 100, and by forming a continuous point portion (A), the height of the continuous point portion (A) is prestressed Substantial continuous method by forming the same height as other part of the preflex steel composite bridge so as to secure sufficient rigidity in the continuous point portion, and by connecting the composite composite beams in the transverse direction and the longitudinal direction. The construction of the prestressed preflex steel composite bridge, which can be constructed, is possible.

또한 연속지점부 하부플랜지콘크리트(250)의 긴장재정착판 및 연속연결부에서의 응력이 PC강연선 정착시 발생하는 압축응력 및 강합성빔과 복부콘크리트, 바닥판콘크리트의 합성 후 고정하중 및 활하중 등에 의해 발생하는 휨 부모멘트에 의해 수반되는 압축응력 등에 의해 허용치를 초과하는 경우 In addition, the stress in the tension reset plate and the continuous connection of the lower flange concrete 250 of the continuous point portion is caused by the compressive stress and rigid composite beam, the abdominal concrete, the bottom plate concrete, and the fixed load and the live load after the PC strand strand fixing In case of exceeding the allowable value due to compressive stress accompanied by bending parent moment

도 3a, 도 3b, 도 3c와 같이 프리스트레스트 강합성빔의 지점으로부터 지간(받침간거리)의 10% ~ 25% 정도 이격된 거리에 콘크리트 정착블럭(400)을 설치하여 콘크리트 정착블럭(400)에 긴장재(300)인 PC강연선의 일부를 분산시켜 인장, 정착시킴으로써 연속연결부의 압축응력에 대한 저항효율을 향상시켜, 프리스트레스트 강합성빔의 단면높이를 증가시키지 않아도 되도록 한다.3A, 3B, and 3C, the concrete fixing block 400 is installed on the concrete fixing block 400 by installing the concrete fixing block 400 at a distance spaced from about 10% to 25% of the space between the points of the prestressed steel composite beam. By dispersing, tensioning and fixing a part of the PC strand, which is the tension member 300, the resistance efficiency against the compressive stress of the continuous connection portion is improved, so that the cross-sectional height of the prestressed rigid composite beam is not increased.

도 3a 및 도 3b는 정착블록(400)을 강합성빔의 일단부 또는 양 단부로부터 지간의 10%~25%정도 이격된 거리의 복부에 형성되도록 한 후, 긴장재(300)인 PC강연선의 일부가 하부플랜지콘크리트 상부로 인출되어 상기 정착블록(400)에 긴장 후, 정착되도록 하는 방식으로서 2경간 연속 및 3경간 이상 연속시 외측경간에 적용하는 방식이며, 정착블럭(400)에 PC강연선의 일부가 긴장,정착되도록 하고, 나머지 PC강연선을 강합성빔의 긴장재 정착판에 긴장 후 정착되도록 한다.3A and 3B illustrate a part of the PC strand, which is a tension member 300, after the fixing block 400 is formed at one end of the steel composite beam or at an abdomen at a distance of 10% to 25% from the end to both ends. Is pulled out to the lower flange concrete to tension the fixing block 400, and then settled, which is a method applied to the outer span when two spans continuous and three or more spans continuous, and a part of the PC stranded wire in the fixing block 400 After the tension is settled and the remaining PC strands are tensioned to the tension member fixing plate of the composite beam.

3경간 이상 연속시 내측경간에서의 정착블럭(400)의 경우 강합성빔의 양 측 단부로부터 도 3c와 같이 지간의 10%~25%정도 이격된 복부에 설치되도록 하고, 정착블럭(400)에 PC 강연선의 일부가 긴장, 정착되도록 하고, 나머지 PC 강연선은 강 합성빔의 긴장재정착판(140)에 긴장 후 정착되도록 한다.In the case of the fixing block 400 in the inner span when more than three spans are continuous, the fixing block 400 is installed in the abdomen spaced from about 10% to 25% of the space from both end portions of the composite beam as shown in FIG. A part of the PC strand is to be tensioned and settled, and the remaining PC strand is to be settled after the tension on the tension reset plate 140 of the steel composite beam.

이때 정착블록(400)은 콘크리트로 형성시킬 수 있으나 달리 재질에 있어 한정되는 것은 아니며, 위와 같이 PC 강연선의 일부를 정착블록에 긴장, 정착시킴으로써 PC 강연선에 의하여 도입되는 압축응력이 연속연결부에 집중되지 않도록 하여 하부플랜지콘크리트의 허용압축응력을 초과하지 않도록 할 수 있게 된다.At this time, the fixing block 400 may be formed of concrete, but is not limited to other materials, and the compressive stress introduced by the PC steel strand is not concentrated in the continuous connection by tensioning and fixing a part of the PC strand in the fixing block as described above. By doing so, the allowable compressive stress of the lower flange concrete can not be exceeded.

정착블럭(400)을 설치하여 PC 강연선의 일부를 콘크리트 정착블럭에 인장, 정착하여 하부플랜지콘크리트에 압축력을 도입하는 경우 필요에 따라서는 I형 강재의 프리플렉션 및 릴리즈에 의해 하부플랜지 콘크리트에 압축력을 도입시키는 과정을 생략하고, PC 강연선 만에 의해 하부플랜지 콘크리트에 압축력을 도입시켜 프리스트레스트 강합성빔 제작시 시공성 향상을 도모할 수 있도록 한다.When the fixing block 400 is installed and a part of the PC strand is stretched and fixed to the concrete fixing block to introduce a compressive force to the lower flange concrete, if necessary, the compressive force is applied to the lower flange concrete by the preflection and release of the I-type steel. Omitting the introduction process, and compressing force is introduced into the lower flange concrete by PC strand only, so that the workability can be improved when manufacturing the prestressed steel composite beam.

이러한 의미에서 강합성빔은 프리스트레스트 강합성빔이라 하여 프리스트레스트 프리플렉스 강합성빔과 구별하여 지칭하며, 프리스트레스트 프리플렉스 강합성빔을 포함하는 광의의 의미이다.In this sense, the composite beam is referred to as a prestressed composite beam separately from the prestressed preflex composite beam, and is a broad meaning including a prestressed preflex composite beam.

본 발명에 의하여 다경간 프리스트레스트 강합성빔에서 프리스트레스트 강합성빔이 설치되는 연속지점부에서 신축이음장치를 사용치 않아 차량의 주행감을 향상시키고, 신축이음장치의 유지를 위한 지속적인 유지관리 비용을 절감할 수 있다. In accordance with the present invention, it is possible to improve the driving comfort of the vehicle by not using the expansion joint in the continuous point portion in which the prestressed composite beam is installed in the multi-span prestressed composite beam, and to maintain the maintenance cost for maintaining the expansion joint. Can be saved.

또한 프리스트레스트 강합성빔의 연속지점부 높이가 프리스트레스트 강합성빔의 단면높이와 같게 유지되면서 연속지점부가 완전 연속으로 결합됨으로써, 프리스트레스트 강합성빔의 단면높이를 크게 하지 않을 수 있어 프리스트레스트 강합성 빔의 최대장점인 낮은 단면높이의 유지라는 특성 효율을 극대화시켜 발휘할 수 있다.In addition, since the continuous point portion of the prestressed composite beam is kept at the same height as the cross-sectional height of the prestressed steel composite beam, the continuous point portions are completely continuous, so that the cross-sectional height of the prestressed steel composite beam can not be increased. This can be achieved by maximizing the characteristic efficiency of maintaining the low cross-sectional height, which is the greatest advantage of the composite beam.

또한 연속지점부의 단면높이가 종래 기술에 비해 커짐으로써 연속지점부에 발생하는 부모멘트에 대처하기 위한 연속지점부 바닥판에 사용되는 PC강연선 또는 철근사용을 줄일 수 있어 경제적이면서도, 연속결합 효과를 통하여 구조적 내구성이 향상된 효율적인 다경간 프리스트레스트 강합성교를 가설할 수 있다. In addition, the cross-sectional height of the continuous branch portion is larger than that of the prior art, thereby reducing the use of PC strands or reinforcing bars used in the bottom plate of the continuous branch portion to cope with the parental forces occurring in the continuous branch portion. Efficient multi-span prestressed steel composite bridge with improved structural durability can be hypothesized.

또한 PC강연선 정착부(긴장재 정착판)가 연속지점부의 최대 부모멘트 발생부를 벗어남으로써 프리스트레스트 강합성빔의 하부플랜지콘크리트에서 발생하는 압축력에 대한 저항효율성을 증대시킬 수 있다.In addition, since the PC strand fixing unit (tension member fixing plate) deviates from the maximum parental portion generating portion of the continuous point portion, it is possible to increase the resistance efficiency against the compressive force generated in the lower flange concrete of the prestressed rigid composite beam.

또한 경우에 따라서는 프리스트레스트 강합성빔의 지간내부측에 콘크리트 정착블럭을 설치하고 콘크리트 정착블럭에 PC강연선의 일부를 분산시켜 인장,정착함으로써 하부플랜지 콘크리트의 연속결합면에 발생하는 압축력을 경감시켜 연속결합면의 압축에 대한 저항 효율성을 향상시켜 하부플랜지 콘크리트에 발생하는 압축력으로 인해 단면높이를 증가시키는 일이 없도록 하며, 이와 같은 경우 필요에 의해서는 I형강재의 프리플렉션,릴리즈과정을 생략한채 PC강연선만에 의해 압축력을 하부플랜지 콘크리트에 도입시켜 시공성을 향상시킴과 동시에 경제성을 향상시킬 수 있다.In some cases, the concrete anchoring block is installed inside the span of the prestressed rigid composite beam, and a part of the PC strand is distributed and tensioned and fixed on the concrete anchoring block to reduce the compressive force generated in the continuous engagement surface of the lower flange concrete. It improves the resistance efficiency against the compression of the continuous mating surface so that the cross-sectional height is not increased due to the compressive force generated in the lower flange concrete.In this case, the pre-flection and release process of the I-shaped steel is omitted if necessary. Compression force is introduced into the lower flange concrete by PC strand only to improve the constructability and economical efficiency.

Claims (5)

다경간 프리스트레스트 프리플렉스 강합성빔을 시공함에 있어서,In constructing multi-span prestressed preflex composite beam, 연속지점부의 받침중심점 위치에 I형 강재의 하부에 부착되는 중간지지판, I형강재의 상부 및 하부플랜지 사이에 수직보강재를 배치하고, 긴장재정착판은 I형 강재의 단부로터 이격되어, 중간지지판 하면에 부착된 하부지지판 위에 설치되도록 함으로써 I형 강재에 블록아웃된 연속연결부를 형성시키고,The intermediate reinforcing plate attached to the lower part of the I-type steel at the supporting center point of the continuous point portion, a vertical reinforcing material is disposed between the upper and lower flanges of the I-type steel, and the tension reset plate is spaced apart from the end rotor of the I-type steel, By forming a block-out continuous connection to the I-shaped steel by being installed on the lower support plate attached to the 상기 I형 강재의 하부플랜지 주변에 철근 및 긴장재를 조립시킨 후, 프리플렉션 하중을 재하한 다음, 하부플랜지콘크리트를 형성시키되 블록아웃된 연속연결부측으로 종방향 연결철근이 돌출되도록 한 상태에서, 프리플렉션 하중을 제거하여 하부플랜지콘크리트에 압축응력이 도입되도록 한 후, 상기 긴장재를 긴장재정착판에 긴장, 정착시켜 강합성빔을 제작하고,After assembling the reinforcing bar and the tension member around the lower flange of the I-type steel, and after loading the pre-flection load, the lower flange concrete is formed, but in the state in which the longitudinal connecting bar protrudes toward the block-out continuous connection side, After the load is removed, the compressive stress is introduced to the lower flange concrete, and then the tension member is tensioned and fixed on the tension reset plate to produce a rigid composite beam. 강합성빔을 교각 또는 교대 위에 설치하되 교량받침을 프리스트레스트 프리플렉스 강합성빔 각각에 설치한 후, 연속연결부의 종방향 연결철근이 종방향 연결용 철근 및 횡방향 연결철근을 포함하는 연속연결부철근에 의하여 종방향 및 횡방향으로 서로 연결되도록 하고,After installing the composite beam on the piers or alternating bridges and installing the bridge bearings on each of the prestressed preflex steel composite beams, the longitudinal connecting rebars of the continuous connecting section include the continuous connecting bars including the longitudinal connecting bars and the transverse connecting bars. To be connected to each other in the longitudinal and transverse directions, 블록아웃된 연속연결부에 하부플랜지콘크리트 및 복부와 바닥판콘크리트를 타설, 양생하여 연속지점부가 형성되도록 하는 다경간 프리스트레스트 프리플렉스 강합성빔의 시공방법.A method for constructing a multi-span prestressed preflex rigid composite beam for placing a continuous flange portion, and curing the lower flange concrete, the abdomen and the bottom plate concrete to form a continuous point portion. 다경간 프리스트레스트 프리플렉스 강합성빔을 시공함에 있어서,In constructing multi-span prestressed preflex composite beam, 연속지점부의 받침중심점 위치에 I형 강재의 하부에 부착되는 중간지지판, I형강재의 상부 및 하부플랜지 사이에 수직보강재를 배치하고, 긴장재정착판은 I형 강재의 단부로터 이격되어, 중간지지판 하면에 부착된 하부지지판 위에 설치되도록 함으로써 I형 강재에 블록아웃된 연속연결부를 형성시키고,The intermediate reinforcing plate attached to the lower part of the I-type steel at the supporting center point of the continuous point portion, a vertical reinforcing material is disposed between the upper and lower flanges of the I-type steel, and the tension reset plate is spaced apart from the end rotor of the I-type steel, By forming a block-out continuous connection to the I-shaped steel by being installed on the lower support plate attached to the 상기 I형 강재의 하부플랜지 주변에 철근 및 긴장재를 조립시킨 후, 프리플렉션 하중을 재하한 다음, 하부플랜지콘크리트를 형성시키되 블록아웃된 연속연결부측으로 종방향 연결철근이 돌출되도록 한 상태에서, 프리플렉션 하중을 제거하여 하부플랜지콘크리트에 압축응력이 도입되도록 한 후, 긴장재의 일부를 긴장재정착판에 긴장, 정착하고, 긴장재의 일부는 하부플랜지콘크리트 상면으로 인출되어 강합성빔의 일 단부 또는 양 단부로부터 지간의 10%~25%정도 이격되어 설치된 콘크리트 블록을 포함하는 정착블록에 긴장 후, 정착시켜 강합성빔을 제작하고,After assembling the reinforcing bar and the tension member around the lower flange of the I-type steel, and after loading the pre-flection load, the lower flange concrete is formed, but in the state in which the longitudinal connecting bar protrudes toward the block-out continuous connection side, After the load is removed to introduce the compressive stress to the lower flange concrete, a part of the tension member is tensioned and fixed to the tension restoring plate, and a part of the tension member is drawn out to the upper surface of the lower flange concrete so as to be removed from one end or both ends of the rigid composite beam. After the tension is settled in the fixing block including the concrete block installed 10% ~ 25% spaced between the space, it is fixed to produce a steel composite beam, 강합성빔을 교각 또는 교대 위에 설치하되 교량받침을 프리스트레스트 프리플렉스 강합성빔 각각에 설치한 후, 연속연결부의 종방향 연결철근이 종방향 연결용 철근 및 횡방향 연결철근을 포함하는 연속연결부철근에 의하여 종방향 및 횡방향으로 서로 연결되도록 하고,After installing the composite beam on the piers or alternating bridges and installing the bridge bearings on each of the prestressed preflex steel composite beams, the longitudinal connecting rebars of the continuous connecting section include the continuous connecting bars including the longitudinal connecting bars and the transverse connecting bars. To be connected to each other in the longitudinal and transverse directions, 블록아웃된 연속연결부에 하부플랜지콘크리트 및 복부와 바닥판콘크리트를 타설, 양생하여 연속지점부가 형성되도록 하는 다경간 프리스트레스트 프리플렉스 강합성빔의 시공방법.A method for constructing a multi-span prestressed preflex rigid composite beam for placing a continuous flange portion, and curing the lower flange concrete, the abdomen and the bottom plate concrete to form a continuous point portion. 다경간 프리스트레스트 강합성빔을 시공함에 있어서,In constructing multi-span prestressed steel composite beams, 연속지점부의 받침중심점 위치에 I형 강재의 하부에 부착되는 중간지지판, I형강재의 상부 및 하부플랜지 사이에 수직보강재를 배치하고, 긴장재정착판은 I형 강재의 단부로터 이격되어, 중간지지판 하면에 부착된 하부지지판 위에 설치되도록 함으로써 I형 강재에 블록아웃된 연속연결부를 형성시키고,The intermediate reinforcing plate attached to the lower part of the I-type steel at the supporting center point of the continuous point portion, a vertical reinforcing material is disposed between the upper and lower flanges of the I-type steel, and the tension reset plate is spaced apart from the end rotor of the I-type steel, By forming a block-out continuous connection to the I-shaped steel by being installed on the lower support plate attached to the 상기 I형 강재의 하부플랜지 주변에 철근 및 긴장재를 조립시킨 후, 하부플랜지콘크리트를 형성시키되 블록아웃된 연속연결부측으로 종방향 연결철근이 돌출되도록 한 상태에서, 긴장재의 일부를 긴장재정착판에 긴장,정착하고, 긴장재의 일부는 하부플랜지콘크리트 상면으로 인출되어 강합성빔의 일 단부 또는 양 단부로부터 지간의 10%~25%정도 이격되어 설치된 콘크리트 블록을 포함하는 정착블록에 긴장 후, 정착시켜 강합성빔을 제작하고,After assembling the reinforcing bar and the tension member around the lower flange of the I-type steel, and forming the lower flange concrete, but the longitudinal connecting reinforcing bar protruding toward the block-out continuous connection side, a part of the tension member to the tension plate mounting plate, A part of the tension member is drawn out to the upper surface of the lower flange concrete and is tensioned after fixing to a fixing block including a concrete block installed from one or both ends of the steel composite beam by 10% to 25% of the space. Make a beam, 강합성빔을 교각 또는 교대 위에 설치하되 교량받침을 프리스트레스트 강합성빔 각각에 설치한 후, 연속연결부의 종방향 연결철근이 종방향 연결용 철근 및 횡방향 연결철근을 포함하는 연속연결부철근에 의하여 종방향 및 횡방향으로 서로 연결되도록 하고,After installing the composite beam on the piers or alternating bridges and installing the bridge bearings on each of the prestressed composite beams, the longitudinal connecting bars of the continuous connecting sections are connected by continuous connecting bars including longitudinal connecting bars and transverse connecting bars. To be connected to each other in the longitudinal and transverse directions, 블록아웃된 연속연결부에 하부플랜지콘크리트 및 복부와 바닥판콘크리트를 타설, 양생하여 연속지점부가 형성되도록 하는 다경간 프리스트레스트 강합성빔의 시공방법.A method for constructing a multi-span prestressed composite beam for placing a continuous flange portion by placing and curing a lower flange concrete, an abdomen and a bottom plate concrete on a block-out continuous connection. 제 1항 내지 제 3항중 어느 한 항에 있어서, 상기 긴장재정착판 주위의 하부 플랜지콘크리트 외곽부는 테이퍼 처리하여 긴장재정착구와 보호캡이 내측에 위치하도록 하고, 긴장재정착구의 외주면에 홈을 형성시켜 보호캡이 상기 홈에 삽입되어 설치되도록 하는 것을 특징으로 하는 다경간 프리스트레스트 강합성빔의 시공방법. According to any one of claims 1 to 3, wherein the lower flange concrete around the tension restoring plate is tapered so that the tension restraint and the protective cap is located on the inside, grooves are formed on the outer circumferential surface of the tension restraint to protect the cap The construction method of the multi-span prestressed steel composite beam, characterized in that the groove is inserted into the groove. 제 4항에 있어서, 적어도 상기 I형강재, 하부지지판, 긴장재 정착판 에 전단연결재가 더 설치되는 것을 특징으로 하는 다경간 프리스트레스트 강합성빔의 시공방법. 5. The method for constructing a multi-span prestressed steel composite beam according to claim 4, wherein a shear connector is further provided on at least the I-shaped steel, the lower support plate, and the tension fixing plate.
KR1020060024334A 2006-03-16 2006-03-16 Continuous construction method of multi span prestressed steel composite beam KR100670675B1 (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
KR1020060024334A KR100670675B1 (en) 2006-03-16 2006-03-16 Continuous construction method of multi span prestressed steel composite beam

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
KR1020060024334A KR100670675B1 (en) 2006-03-16 2006-03-16 Continuous construction method of multi span prestressed steel composite beam

Related Child Applications (1)

Application Number Title Priority Date Filing Date
KR2020060007176U Division KR200418183Y1 (en) 2006-03-17 2006-03-17 Joint Structure of Continuous Multi Span Prestressed Steel Composite Beam

Publications (1)

Publication Number Publication Date
KR100670675B1 true KR100670675B1 (en) 2007-01-19

Family

ID=38014061

Family Applications (1)

Application Number Title Priority Date Filing Date
KR1020060024334A KR100670675B1 (en) 2006-03-16 2006-03-16 Continuous construction method of multi span prestressed steel composite beam

Country Status (1)

Country Link
KR (1) KR100670675B1 (en)

Cited By (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
KR101200563B1 (en) * 2008-07-14 2012-11-13 한국건설기술연구원 A Steel Composite Bridge Having Steel Plates Connected by Using Concrete Cross Beams and Its Constructing Method
CN108018991A (en) * 2016-11-03 2018-05-11 重庆大学 A kind of Self-resetting viscoplasticity energy dissipating girder steel
CN108360742A (en) * 2018-04-05 2018-08-03 南京林业大学 A kind of prestressing with bond bamboo H-beam
WO2024045588A1 (en) * 2022-09-02 2024-03-07 中铁七局集团有限公司 Continuous-beam-support-method-based one-time cast-in-place construction method

Cited By (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
KR101200563B1 (en) * 2008-07-14 2012-11-13 한국건설기술연구원 A Steel Composite Bridge Having Steel Plates Connected by Using Concrete Cross Beams and Its Constructing Method
CN108018991A (en) * 2016-11-03 2018-05-11 重庆大学 A kind of Self-resetting viscoplasticity energy dissipating girder steel
CN108018991B (en) * 2016-11-03 2023-08-11 重庆大学 Self-resetting viscoelastic energy dissipation steel beam
CN108360742A (en) * 2018-04-05 2018-08-03 南京林业大学 A kind of prestressing with bond bamboo H-beam
WO2024045588A1 (en) * 2022-09-02 2024-03-07 中铁七局集团有限公司 Continuous-beam-support-method-based one-time cast-in-place construction method

Similar Documents

Publication Publication Date Title
KR100536489B1 (en) Manufacturing method for prestressed steel composite girder and prestressed steel composite girder thereby
KR100941066B1 (en) Prestressed-precast-segmental open spendral concrete arch bridge and its constructing method
KR101202416B1 (en) Structual member making method using preflex baem and psc beam and the bridge construction method threrewith
KR101275754B1 (en) Psc girder with shear block, psc girder making method with shear block and bridge construction method using psc girder with shear block
KR100885663B1 (en) A prestressed concrete composite girder using cross-beam and constructing method thereof
KR101222620B1 (en) Prestressed concrete girder and it&#39;s manufacture and construction method which used pretensioning steel plate
KR100982974B1 (en) Method for manufacturing multi-span continuous re-prestressed preflex composite bridge
KR101693256B1 (en) Construction method of prefabricated psc bridge
KR100988074B1 (en) Girder bridge connected to abutment and the construction method thereof
KR100974305B1 (en) Continuous beam bridge construction method using girder for multi-span
KR100670675B1 (en) Continuous construction method of multi span prestressed steel composite beam
KR200407182Y1 (en) Precasted concrete plate
KR100875248B1 (en) Steel composite prestressed concrete beam using prestressed steel member and manufacturing method of the same
KR101200563B1 (en) A Steel Composite Bridge Having Steel Plates Connected by Using Concrete Cross Beams and Its Constructing Method
KR20130077191A (en) Prestressed concrete girder with half-depth cantilever and construction method using the same
KR200418183Y1 (en) Joint Structure of Continuous Multi Span Prestressed Steel Composite Beam
JP5716117B1 (en) Hinge reinforcement method and reinforcement structure for existing girder bridge
KR100937252B1 (en) Prestressed steel composite beam and a manufacturing method thereof
KR200342287Y1 (en) A structure of prestressed preflex steel composite beam prestressed by each construction steps
KR100456471B1 (en) Open-type steel wire holding device and Metod for construction of continuous bridge using of prestressed concret beam having it
KR101374701B1 (en) Concrete beam construction method with anchorage apparatus for bi-pressing compression member
KR20060017949A (en) Field-fabricated prestressing steel-composed girder and construction method of continuous bridge using the girder
KR20070001410A (en) Mounting structure of steel cross-beam in multi-girder concrete bridge and its construction method
KR100712622B1 (en) Continuous Preflex Girder Structure Using Prestress in Parent Section Using Expanded Concrete and Its Construction Method
KR200419013Y1 (en) Temporary bridge consruction system using composite slab girder

Legal Events

Date Code Title Description
A201 Request for examination
E701 Decision to grant or registration of patent right
GRNT Written decision to grant
J204 Invalidation trial for patent
J121 Written withdrawal of request for trial
FPAY Annual fee payment

Payment date: 20140108

Year of fee payment: 8

J204 Invalidation trial for patent
FPAY Annual fee payment

Payment date: 20150107

Year of fee payment: 9

J301 Trial decision

Free format text: TRIAL DECISION FOR INVALIDATION REQUESTED 20140114

Effective date: 20150205

J2X1 Appeal (before the patent court)

Free format text: INVALIDATION

J302 Written judgement (patent court)

Free format text: JUDGMENT (PATENT COURT) FOR INVALIDATION REQUESTED 20150310

Effective date: 20150918

FPAY Annual fee payment

Payment date: 20160112

Year of fee payment: 10

FPAY Annual fee payment

Payment date: 20180201

Year of fee payment: 12

FPAY Annual fee payment

Payment date: 20190130

Year of fee payment: 13

FPAY Annual fee payment

Payment date: 20200201

Year of fee payment: 14