KR100648419B1 - Support construction of electric pole - Google Patents

Support construction of electric pole Download PDF

Info

Publication number
KR100648419B1
KR100648419B1 KR1020060080239A KR20060080239A KR100648419B1 KR 100648419 B1 KR100648419 B1 KR 100648419B1 KR 1020060080239 A KR1020060080239 A KR 1020060080239A KR 20060080239 A KR20060080239 A KR 20060080239A KR 100648419 B1 KR100648419 B1 KR 100648419B1
Authority
KR
South Korea
Prior art keywords
pole
electric pole
foundation
nut
packing
Prior art date
Application number
KR1020060080239A
Other languages
Korean (ko)
Inventor
이영희
Original Assignee
(주) 희림종합건축사사무소
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by (주) 희림종합건축사사무소 filed Critical (주) 희림종합건축사사무소
Priority to KR1020060080239A priority Critical patent/KR100648419B1/en
Application granted granted Critical
Publication of KR100648419B1 publication Critical patent/KR100648419B1/en

Links

Images

Classifications

    • EFIXED CONSTRUCTIONS
    • E04BUILDING
    • E04HBUILDINGS OR LIKE STRUCTURES FOR PARTICULAR PURPOSES; SWIMMING OR SPLASH BATHS OR POOLS; MASTS; FENCING; TENTS OR CANOPIES, IN GENERAL
    • E04H12/00Towers; Masts or poles; Chimney stacks; Water-towers; Methods of erecting such structures
    • E04H12/22Sockets or holders for poles or posts
    • E04H12/2253Mounting poles or posts to the holder
    • E04H12/2269Mounting poles or posts to the holder in a socket
    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D27/00Foundations as substructures
    • E02D27/32Foundations for special purposes
    • E02D27/42Foundations for poles, masts or chimneys

Landscapes

  • Engineering & Computer Science (AREA)
  • Architecture (AREA)
  • Civil Engineering (AREA)
  • Structural Engineering (AREA)
  • Life Sciences & Earth Sciences (AREA)
  • General Life Sciences & Earth Sciences (AREA)
  • Mining & Mineral Resources (AREA)
  • Paleontology (AREA)
  • General Engineering & Computer Science (AREA)
  • Foundations (AREA)

Abstract

A supporting structure of an electric pole is provided to protect the foundation of an electric pole by placing a metal foundation into a laying groove instead of a concrete foundation and installing a primary packing, a press-fit ring, a nut body and a secondary packing on the outer circumference of an electric pole installed to the center of the foundation and to make construction easy by installing each member in the fabricated type. A supporting structure of an electric pole contains: a foundation(30) having circular ring shaped subsidence prevention supports projected to the bottom of a cylindrical body(31) at a certain distance, a nut formed on the top of the cylindrical body, an end projection formed on the cylindrical body to diminish in diameter toward the inner center and an insertion hole to insert a buried wire to the subsidence prevention support; a primary packing(40) formed elliptically with rubber and inserted to the inner bottom of a press-fit ring to be fixed to the outside of an electric pole(20); a press-fit ring(50) having many press-fit projections projected to the top of a circular ring and opened to make a nut body tightened on the nut of the foundation; a nut body(60) made with metal, tightened on the nut of the foundation and provided with a circular ring and an end projection; and a secondary packing(70) formed on the end projection of the nut body to be adhered closely to the outside of the electric pole.

Description

전주 지지 구조물{SUPPORT CONSTRUCTION OF ELECTRIC POLE}Jeonju support structure {SUPPORT CONSTRUCTION OF ELECTRIC POLE}

도 1은 종래 전주를 개략적으로 나타내는 도면,1 is a view schematically showing a conventional electric pole,

도 2는 본 발명 전주 지지 구조물의 분해 사시도,2 is an exploded perspective view of the present invention pole supporting structure,

도 3은 본 발명 전주 지지 구조물의 결합 사시도,3 is a perspective view of the combination of the present invention pole support structure,

도 4는 본 발명 전주 지지 구조물의 단면도,4 is a cross-sectional view of the present invention pole support structure,

도 5는 본 발명 전주 지지 구조물의 사용상태도.5 is a state diagram used in the present invention pole supporting structure.

<도면의 주요부분에 대한 부호의 설명><Description of the symbols for the main parts of the drawings>

20: 전주 30: 하단 기초20: pole 30: bottom foundation

40: 패킹 1 50: 압입링40: packing 1 50: press-fit ring

60: 너트체 70: 패킹 260: nut 70: packing 2

80: 원형봉체 90: 보도80: round rod 90: sidewalk

본 발명은 전주 지지 구조물에 관한 것으로, 특히 너트체 결합시 경사면에 의해 압입링을 압입함과 아울러 다시 압입돌기에 의해 전주를 압입할 수 있도록 설치되어 전주를 견고하게 지지할 수 있도록 구성된 전주 지지 구조물에 관한 것이 다.The present invention relates to a pole supporting structure, and in particular, a pole supporting structure, which is installed to press the indentation ring by the inclined surface when the nut body is coupled and to press the pole again by the indentation protrusion, and is configured to firmly support the pole. It's about

일반적으로 원거리로 전력을 송전하기 위하여 발전소로부터 변전소, 또는 변전소로부터 수용가까지 해당 규격의 전력선이 연결되고, 이러한 전력선은 지상에 설치된 철탑이나 전주 등을 이용하게 된다.In general, in order to transmit power over a long distance, power lines of a corresponding standard are connected from a power plant to a substation or a substation to a consumer, and these power lines use a steel tower or a pole installed on the ground.

그러나 지상에 설치되는 철탑이나 전주의 경우에는 위치 확보의 문제가 있고, 더욱이 철탑이나 전주에 가설되는 고압의 전력선 등도 미관 문제와 위험성의 노출 등의 문제가 있다.However, in the case of steel towers or poles installed on the ground, there is a problem of securing a position, and in addition, high-voltage power lines installed on the towers and poles also have problems such as aesthetic problems and exposure to danger.

하지만, 도 1과 같은 구조를 가지는 전주(12)의 시공이 용이하여 현재도 많이 시공되고 있는 실정이다.However, since the construction of the electric pole 12 having the structure as shown in FIG. 1 is easy, many constructions are still under construction.

즉, 보도(10)에는 일정 깊이로 터파기를 실시한 연후에, 그 터파기된 위치에 콘크리트를 타설하여 콘크리트 기초(11)를 형성함과 아울러 그 콘크리트 기초(11)의 중심에 전주(12)를 입설하게 된다.That is, after the trench 10 has been excavated to a predetermined depth, concrete is placed at the excavated position to form the concrete foundation 11, and the electric pole 12 is placed at the center of the concrete foundation 11. Will be put in place.

전주(12)에는 상부에 지지대(13)에 애자가 설치되어 전선(14)이 연장설치된다.In the pole 12, the insulator is installed on the support 13 in the upper portion, the wire 14 is extended.

상술한 구성을 가지는 전주(12)는 구조상 콘크리트 기초(11)와 전주(12)가 견고하게 수직방향으로 입설(入設)이 가능하지만, 차량이 주행중에 주행선을 이탈하여 보도(10) 측으로 넘어와 전주(12)와 추돌될 때 충격력에 의해 전주(12)가 전도될 위험성이 있다 할 것이다.The electric pole 12 having the above-described configuration can be erected in the vertical direction with the concrete foundation 11 and the electric pole 12 firmly in structure, but the vehicle is driven off the driving line while traveling to the sidewalk 10 side. When the collision with the pole 12 and the impact of the electric pole 12 will be overturned by the impact force.

본 발명은 상술한 내용을 감안하여, 본 발명은, 콘크리트 기초를 대신하여 금속으로 제작된 하단 기초가 터파기된 매설홈에 안착되고 하단 기초의 중앙에 삽입밀착설치된 전주의 외주에 패킹 1, 압입링, 너트체 및 패킹 2가 설치되어 전주의 하단을 보호함과 아울러 입설이 가능하도록 설치되며, 각 부재가 조립식으로 설치가능하여 시공이 용이로운 구조를 가지는 전주 지지 구조물을 제공함을 그 목적으로 한다.In view of the above, the present invention, the present invention, the lower base made of metal in place of the concrete foundation is seated in the burrow grooves are dug and the packing 1, press-fit in the outer periphery of the pole installed in close contact with the center of the lower foundation The purpose of the present invention is to provide a pole supporting structure having a structure in which a ring, a nut body, and a packing 2 are installed to protect the lower end of the pole and can be placed in a standing position, and each member can be prefabricated to facilitate construction. .

이하, 첨부된 도면을 참조하여 본 발명의 구성을 설명한다.Hereinafter, the configuration of the present invention with reference to the accompanying drawings.

도 2는 본 발명 전주 지지 구조물의 분해 사시도, 도 3은 본 발명 전주 지지 구조물의 결합 사시도, 도 4는 본 발명 전주 지지 구조물의 단면도, 도 5는 본 발명 전주 지지 구조물의 사용상태도이다.Figure 2 is an exploded perspective view of the present invention pole support structure, Figure 3 is a perspective view of the combination of the present invention pole support structure, Figure 4 is a cross-sectional view of the present invention pole support structure, Figure 5 is a state of use of the present invention pole support structure.

보도(20)에는 터파기를 실시하여 매설홈이 형성되고 매설홈에는 하단 기초(30)가 안착되어 되메우기 작업이 실시된다.In the sidewalk 20, a burrow is formed by digging, and the bottom base 30 is seated in the burial groove, and the backfilling operation is performed.

하단 기초(30)는, 원통 몸체(31)의 하단에 거리가 이격되도록 2개의 원형링 형태로 침하방지 지지부(32)가 돌출되고, 원통 몸체(31)의 상단에 나사가 형성된 너트부(35)가 형성되며, 원통 몸체(31)의 상면에 내측 중앙을 향해 지름이 축소되는 단턱(34)이 형성된다.The lower base 30, the anti-settling support portion 32 protrudes in the form of two circular rings so that the distance from the lower end of the cylindrical body 31, the nut portion 35 is formed on the upper end of the cylindrical body 31 ) Is formed, and a step 34 is formed on the upper surface of the cylindrical body 31 to reduce the diameter toward the inner center.

즉, 하단 기초(30)는 내측에 전주(20)가 삽입되어 밀착설치되는 한편, 하단 기초(30)와 전주(20)가 밀착된 내측에는 원형 단면을 가지는 원형봉체(80)이 삽입설치되어 전주(20)의 하단을 지지시키게 된다.That is, the lower base 30 is installed in close contact with the electric pole 20 is inserted into the inner side, while the lower base 30 and the circular rod body 80 having a circular cross section is inserted into the inner side in which the electric pole 20 is in close contact. The lower end of the pole 20 is to be supported.

또한, 하단 기초(30)에는 침하방지 지지부(32)에 매설선을 삽입할 수 있는 삽입공(33)이 형성된다.In addition, the lower base 30 is formed with an insertion hole 33 into which the buried wire can be inserted into the anti-sedimentation support part 32.

즉, 하단 기초(30)의 침하방지 지지부(32)의 삽입공(33)에는 미리 파이프(도면상 미도시)를 삽입설치하여 하단 기초(30)가 매설될 때 파이프를 삽입하여 매설하여 낙뢰에 대한 전주(20)의 파손을 방지할 수 있게 된다.That is, a pipe (not shown in the drawing) is inserted into the insertion hole 33 of the settlement prevention support part 32 of the lower foundation 30 in advance by inserting and embedding the pipe when the lower foundation 30 is buried to prevent lightning. It is possible to prevent the breakage of the electric pole 20 for.

이때 전주(20)와 하단 기초(30)가 밀착되는 단턱(34)에는 패킹 1(40)과 압입링(50)이 도 4와 같이 밀착된다.At this time, the packing 1 (40) and the press-fit ring (50) are in close contact with the step (34) in which the electric pole (20) and the lower base (30) are in close contact.

패킹 1(40)은 타원형 형태이고 고무 재질로 제작된 원형링으로, 패킹 1(40)은 압입링(50)의 하단 내측에 삽입되어 전주(20)의 외측에 고정된다.Packing 1 (40) is an oval shape and a circular ring made of rubber material, packing 1 (40) is inserted into the lower end of the press-in ring 50 is fixed to the outside of the electric pole (20).

즉, 패킹 1(40)은 압입링(50)의 하단 내측에 밀착되어 전주(20)의 외측에 고정되게 된다.That is, the packing 1 (40) is in close contact with the bottom inner side of the press-in ring 50 is fixed to the outside of the electric pole (20).

압입링(50)은 원형링(51)의 상면에 압입돌기(52)가 다수개 돌출되고 각각의 압입돌기(52)의 사이가 절개되어 형성된 부재로, 압입링(50)은 각각의 압입돌기(52)의 상부 외측이 경사지도록 형성된다.The indentation ring 50 is a member formed by a plurality of indentation protrusions 52 protruding from the upper surface of the circular ring 51 and the indentation between the indentation protrusions 52, the indentation ring 50 is each indentation protrusion The upper outer side of the 52 is formed to be inclined.

즉, 압입링(50)은 상부에 너트체(60)가 하단 기초(30)의 너트부(35)에 체결되는 경우 압입돌기(52)가 유동하여 긴밀한 결합이 가능하도록 압입돌기(52)의 사이가 절개되게 된다.That is, when the nut body 60 is fastened to the nut part 35 of the lower base 30 on the upper part of the press-fit ring 50, the press-in protrusion 52 flows so that the press-in protrusion 52 may be tightly coupled. The incision is made.

너트체(60)는 금속으로 제작되어 하단 기초(30)의 너트부(35)에 체결되는 부재로, 너트체(60)는 상면에 원형링(62)이 용접되어 고정되고, 너트체(60)의 중앙 관통홀의 외측으로 원형링(62)이 용접되어 단턱(64)이 형성되게 된다.The nut body 60 is a member made of metal and fastened to the nut part 35 of the lower base 30. The nut body 60 is fixed by welding a circular ring 62 on the upper surface thereof. Circular ring 62 is welded to the outside of the center through-hole of the) to form a step (64).

즉, 너트체(60)는 하단 기초(30)의 너트부(35)에 체결되어 하단 기초(30)의 상단 단턱(34)에 삽입설치되는 패킹 1(40)과 압입링(50)을 압착하여 전주(20)에 견고한 지지를 이루도록 설치된다.That is, the nut body 60 is fastened to the nut part 35 of the lower base 30 to compress the packing 1 40 and the press-fit ring 50 which are inserted into the upper end step 34 of the lower base 30. It is installed to achieve a solid support to the pole 20.

너트체(60)의 단턱(64)에는 패킹 2(70)가 형성되어 전주(20)의 외측에 밀착설치되게 되는 한편, 패킹 2(70)는 패킹 1(40)과 틀리게 평판이 연장되어 원형을 이루도록 형성된다.Packing 2 (70) is formed on the stepped portion (64) of the nut body (60) to be installed in close contact with the outer side of the electric pole (20), while packing 2 (70) has a circular plate extending differently from the packing 1 (40) It is formed to achieve.

상술한 전주 지지 구조물에 대한 시공 순서를 설명한다.The construction procedure for the above-described pole support structure will be described.

먼저, 보도(90)에는 기초 터파기를 실시한다.First, the sidewalk 90 is subjected to foundation trenching.

즉, 보도(90)에는 전주(20)가 설치될 위치에 터파기 작업을 실시하여 매설홈을 형성한 뒤 바닥면에 대한 다짐작업을 실시하게 된다.That is, the sidewalk 90 is formed in the burrow operation to the location where the electric pole 20 is to be installed to form a buried groove and then compaction work for the bottom surface.

다음으로, 보도(90)의 매설홈에 하단 기초(30)를 매설한 뒤 되메우기 작업을 실시한다.Next, the bottom foundation 30 is embedded in the embedding groove of the sidewalk 90, and then the backfilling operation is performed.

즉, 하단 기초(30)를 정위치를 가지도록 안착시킨 뒤 되메우기 작업을 하고 다짐작업을 실시하게 되고, 하단 기초(30)의 침하방지 지지부(32)의 삽입공(33)에 파이프를 삽입하여 함께 매설가능하다.That is, the lower base 30 is seated to have a correct position and then backfilled and compacted, and a pipe is inserted into the insertion hole 33 of the anti-sedimentation support part 32 of the lower base 30. Can be buried together.

다음으로, 하단 기초(30)에는 원통 몸체(31)의 내측 삽입홈에 전주(20)를 삽입하여 수직하게 입설한다.Next, the lower base 30 is inserted vertically by inserting the electric pole 20 into the inner insertion groove of the cylindrical body 31.

즉, 하단 기초(30)는 전주(20)의 하단이 삽입되어 밀착설치되는 바, 이때 크레인과 같은 중장비를 이용하여 전주(20)를 설치시 전주(20)에는 하단 중앙에 미리 원형봉체(80)를 삽입고정시킨 뒤 하단 기초(30)의 하단 중앙에 형성된 중앙홀을 원형봉체(80)가 관통하여 지중에 매설되게 설치하게 된다.That is, the lower base 30 is inserted into the lower end of the pole 20 is in close contact with the installation, at this time when installing the pole 20 using a heavy equipment such as a crane in the pole 20 in advance in the center of the lower round rod (80) After inserting and fixing the circular rod body 80 penetrates the central hole formed in the center of the lower end of the lower base 30 is embedded in the ground.

이때, 전주(20)에는 미리 패킹 1(40), 압입링(50), 너트체(60) 및 패킹 2(70)를 하단에 위치시킨 뒤 하단 기초(30)에 전주(20)를 삽입밀착하게 된다.At this time, packing 1 (40), press-fit ring (50), nut body (60) and packing 2 (70) are placed in the lower end of the electric pole 20, and then the electric pole 20 is inserted into the lower base 30. Done.

부연하자면, 하단 기초(30)와 밀착입설된 전주(20)는 크레인으로 유동이 없도록 고정하게 된다.In other words, the lower base 30 and the electric pole 20 in close contact is fixed so that there is no flow to the crane.

다음으로, 하단 기초(30)의 단턱(34)에 패킹 1(40)과 압입링(50)을 위치시킨 뒤 너트체(60)를 회전시켜 압입링(50)을 전주(20)와 밀착함과 아울러, 너트체(60)를 하단 기초(30)에 고정한다.Next, the packing 1 40 and the press-fit ring 50 are positioned on the step 34 of the lower base 30, and then the nut body 60 is rotated to closely contact the press-fit ring 50 with the pole 20. In addition, the nut body 60 is fixed to the lower base 30.

즉, 하단 기초(30)와 너트체(60)의 체결에 따라 패킹 1(40)과 압입링(50)이 견고하게 밀착되게 되고, 너트체(60)의 단턱(64)에 패킹 2(70)를 위치시켜 전주(20)와 밀착시켜 마감하게 된다.That is, the packing 1 40 and the press-fit ring 50 are firmly adhered to each other by fastening the lower base 30 and the nut body 60, and the packing 2 70 on the step 64 of the nut body 60. ) To close the finish and close to the pole (20).

실제로 도 4에서는 하단 기초(30)가 높이가 낮은 형태로 그려져 있지만 하단 기초(30)의 원통 몸체(31)의 높이를 가령 1.5M정도로 형성하여 전주(20)를 지지할 수 있도록 구성할 수 있음은 당연하다 할 것이다.Actually in Figure 4, but the lower base 30 is drawn in the form of a low height can be configured to support the electric pole 20 by forming the height of the cylindrical body 31 of the lower base 30, for example about 1.5M Will be taken for granted.

또한, 하단 기초(30)를 콘크리트로 기성제작하여 사용하는 경우에는 원통 몸체(31)의 상단 너트부(35)를 금속링에 나사를 형성하여 원통 몸체(31)의 상단에 금속링을 밀착하여 사용할 수도 있다.In addition, when the bottom base 30 is made of concrete, the upper nut part 35 of the cylindrical body 31 may be screwed to the metal ring to closely adhere the metal ring to the upper end of the cylindrical body 31. Can also be used.

뿐만 아니라, 전주(20)에는 내측 중앙홀에 원형봉체(80)를 삽입하여 기성제제작할 수 있음은 물론, 원형봉체(80)의 설치로 인해 전주(20)가 지중에 더욱 견고하게 입설될 수 있다.In addition, the electric pole 20 may be manufactured by inserting the circular rod 80 into the inner central hole, and of course, due to the installation of the circular rod 80, the electric pole 20 may be more firmly embedded in the ground. have.

상술한 본 발명의 구성에 의한 효과를 설명한다.The effect by the structure of this invention mentioned above is demonstrated.

본 발명에 따르면, 콘크리트 기초를 대신하여 금속으로 제작된 하단 기초가 터파기된 매설홈에 안착되고 하단 기초의 중앙에 삽입밀착설치된 전주의 외주에 패킹 1, 압입링, 너트체 및 패킹 2가 설치되어 전주의 하단을 보호함과 아울러 입설이 가능하도록 설치되며, 각 부재가 조립식으로 설치가능하여 시공이 용이로운 구조를 가지는 전주 지지 구조물을 제공하는 효과를 얻을 수 있다.According to the present invention, the packing 1, the press-fit ring, the nut body and the packing 2 are installed on the outer periphery of the pole pole which is made of metal instead of the concrete foundation is seated in the burial recessed groove and inserted close installed in the center of the bottom foundation It is installed so as to protect the bottom of the pole and can be set up, and each member can be installed in a prefabricated manner to obtain the effect of providing a pole supporting structure having a structure that is easy to construct.

Claims (2)

콘크리트로 기성(旣成) 제작되어 수직하게 보도에 입설되는 전주에 있어서, In Jeonju, which is made of concrete and is placed on the sidewalk vertically, 전주의 하단을 지지할 수 있도록 보도의 터파기를 실시한 매설홈에 매설되는 한편, In order to support the lower end of the pole, it is buried in the burial groove where the sidewalks were excavated. 원통 몸체(31)의 하단에 다수개의 침하방지 지지부(32)가 돌출되고, 원통 몸체(31)의 상단에 너트부(35)가 형성되며, 원통 몸체(31)의 상면 내측에 단턱(34)이 형성되고 중앙이 관통되어 형성된 하단 기초(30); A plurality of anti-sedimentation support parts 32 protrude from the lower end of the cylindrical body 31, a nut part 35 is formed at the upper end of the cylindrical body 31, and the stepped portion 34 is formed inside the upper surface of the cylindrical body 31. Is formed and the bottom base 30 is formed through the center; 전주(20)와 하단 기초(30)가 밀착되는 단턱(34)에 패킹 1(40)이 삽입되어 우수의 유입을 방지시키는 한편, 고무 재질로 제작된 원형링으로, 패킹 1(40)이 하단 내측에 밀착되어 전주(20)의 외측에 고정되고, 원형링(51)의 상면에 압입돌기(52)가 다수개 돌출되며, 각각의 압입돌기(52)의 사이가 절개되어 형성된 압입링(50); Packing 1 (40) is inserted into the step (34) in close contact with the electric pole 20 and the lower base 30 to prevent the inflow of rainwater, while the circular ring made of rubber material, the packing 1 (40) is the bottom It is in close contact with the inside is fixed to the outside of the electric pole 20, a plurality of indentation protrusions 52 protrude on the upper surface of the circular ring 51, the indentation ring 50 formed by cutting between the respective indentation protrusions 52 ); 하단 기초(30)의 너트부(35)에 체결되는 경우 압입돌기(52)를 압입하여 전주(20)의 외주연에 밀착되는 한편, 상면에 원형링(62)이 용접되어 고정되고, 중앙 관통홀의 외측으로 단턱(64)이 형성된 너트체(60); 및 When it is fastened to the nut part 35 of the lower base 30, the indentation protrusion 52 is pressed into close contact with the outer periphery of the electric pole 20, while the circular ring 62 is welded and fixed to the upper surface, and penetrates the center. A nut body 60 having a step 64 formed outside of the hole; And 너트체(60)의 단턱(64)에 안착되어 전주(20)의 외측에 밀착설치되는 한편, 평판이 연장되어 원형을 이루도록 형성된 패킹 2(70);을 포함하여 구성됨을 특징으로 하는 전주 지지 구조물.And a packing 2 70 seated on the stepped portion 64 of the nut body 60 to be in close contact with the outer side of the pole 20, and formed to extend in a circle to form a flat plate. . 제1항에 있어서,The method of claim 1, 하단 기초(30)와 전주(20)가 밀착된 내측에는 원형 단면을 가지는 원형봉체(80)이 삽입설치되어 전주(20)의 하단을 지지시키는 것을 특징으로 하는 전주 지지 구조물.An inner pole support structure, characterized in that the lower base (30) and the inner pole 20 is in close contact with the circular rod body 80 having a circular cross-section is inserted to support the lower end of the pole pole (20).
KR1020060080239A 2006-08-24 2006-08-24 Support construction of electric pole KR100648419B1 (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
KR1020060080239A KR100648419B1 (en) 2006-08-24 2006-08-24 Support construction of electric pole

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
KR1020060080239A KR100648419B1 (en) 2006-08-24 2006-08-24 Support construction of electric pole

Publications (1)

Publication Number Publication Date
KR100648419B1 true KR100648419B1 (en) 2006-11-24

Family

ID=37713137

Family Applications (1)

Application Number Title Priority Date Filing Date
KR1020060080239A KR100648419B1 (en) 2006-08-24 2006-08-24 Support construction of electric pole

Country Status (1)

Country Link
KR (1) KR100648419B1 (en)

Cited By (9)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
KR100796254B1 (en) 2007-12-06 2008-01-21 이유박 Prospect construction of electric pole
KR100891926B1 (en) 2008-10-30 2009-04-08 (주)원엔지니어링 Prospect construction of electric pole
KR100905889B1 (en) 2008-04-18 2009-07-03 박지운 Foundation structure for installing poles
KR100915799B1 (en) 2009-05-22 2009-09-07 제이엔케이기술단(주) Fixing equipment of electric pole for supply of electric power
KR100969410B1 (en) 2009-06-15 2010-07-14 박지운 Street lighting pole and foundation structure for installing poles
KR100997855B1 (en) * 2008-10-07 2010-12-01 박지운 Foundation structure for installing poles
KR101077971B1 (en) 2009-03-10 2011-10-28 (주)흥일엔지니어링 Elementary Block for Supporting of Steel Pipe
CN108612266A (en) * 2018-06-22 2018-10-02 中冶建工集团有限公司 A kind of roof lightning protection mounting structure
CN109681019A (en) * 2018-11-08 2019-04-26 广东耀龙金属科技有限公司 A kind of flagpole being easily installed

Cited By (11)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
KR100796254B1 (en) 2007-12-06 2008-01-21 이유박 Prospect construction of electric pole
KR100905889B1 (en) 2008-04-18 2009-07-03 박지운 Foundation structure for installing poles
KR100997855B1 (en) * 2008-10-07 2010-12-01 박지운 Foundation structure for installing poles
KR100891926B1 (en) 2008-10-30 2009-04-08 (주)원엔지니어링 Prospect construction of electric pole
KR101077971B1 (en) 2009-03-10 2011-10-28 (주)흥일엔지니어링 Elementary Block for Supporting of Steel Pipe
KR100915799B1 (en) 2009-05-22 2009-09-07 제이엔케이기술단(주) Fixing equipment of electric pole for supply of electric power
KR100969410B1 (en) 2009-06-15 2010-07-14 박지운 Street lighting pole and foundation structure for installing poles
CN108612266A (en) * 2018-06-22 2018-10-02 中冶建工集团有限公司 A kind of roof lightning protection mounting structure
CN108612266B (en) * 2018-06-22 2024-06-04 中冶建工集团有限公司 Roof lightning protection ground connection mounting structure
CN109681019A (en) * 2018-11-08 2019-04-26 广东耀龙金属科技有限公司 A kind of flagpole being easily installed
CN109681019B (en) * 2018-11-08 2020-05-29 广东耀龙金属科技有限公司 Flagpole convenient to installation

Similar Documents

Publication Publication Date Title
KR100648419B1 (en) Support construction of electric pole
US11976432B2 (en) Foundation for wind turbine towers
KR100588445B1 (en) Method for installation of environment friendly electric utility pole
US3988870A (en) Lamp post base
KR101358985B1 (en) Pillar settling structure and construction method of the same with improved stability and workability
CN106661856A (en) Transmission tower foundation using micropile
KR100982819B1 (en) A prefabricated drain-road
EP2800835B1 (en) Foundation equipment for a pole in particular for a lighting pole
KR20080108879A (en) Reinforcing method of bearing power for soft ground and reinforcing apparatus used in the same method
JP2021093853A (en) Edge stone
KR20100033750A (en) A fixing structure of electric and construction method thereof
KR20080002652U (en) Iron Pole Base
KR200267682Y1 (en) a support telegraph pole
KR200275363Y1 (en) The mold establishment necessit do not exist assembly road water pipe
KR100600516B1 (en) Waterproof-sealed manhole
CN110641306A (en) Electric vehicle charging device base shell
KR101337279B1 (en) Construction type manhole
CN215978723U (en) Telegraph pole mounting base
KR101028002B1 (en) Device for connecting body in wind turbine
KR20130142443A (en) Foundation construction of bus stop using concrete block and method for constructionn the same
JP6966133B1 (en) Pillar method
KR100873183B1 (en) Post
KR101390514B1 (en) Manhole for buoyancy prevention
KR101437282B1 (en) Connecting member for power-transmission tower
KR102236919B1 (en) Concrete foundation apparatus for supporting Solar cell equipped

Legal Events

Date Code Title Description
A201 Request for examination
N231 Notification of change of applicant
A302 Request for accelerated examination
N231 Notification of change of applicant
E701 Decision to grant or registration of patent right
GRNT Written decision to grant
FPAY Annual fee payment

Payment date: 20121113

Year of fee payment: 7

FPAY Annual fee payment

Payment date: 20131108

Year of fee payment: 8

FPAY Annual fee payment

Payment date: 20141110

Year of fee payment: 9

FPAY Annual fee payment

Payment date: 20151022

Year of fee payment: 10

FPAY Annual fee payment

Payment date: 20161104

Year of fee payment: 11

FPAY Annual fee payment

Payment date: 20171213

Year of fee payment: 12

FPAY Annual fee payment

Payment date: 20181106

Year of fee payment: 13

FPAY Annual fee payment

Payment date: 20191104

Year of fee payment: 14