KR100644507B1 - Installation structure of boiler pipe using connecting rail of the bottom of construction - Google Patents

Installation structure of boiler pipe using connecting rail of the bottom of construction Download PDF

Info

Publication number
KR100644507B1
KR100644507B1 KR1020050093647A KR20050093647A KR100644507B1 KR 100644507 B1 KR100644507 B1 KR 100644507B1 KR 1020050093647 A KR1020050093647 A KR 1020050093647A KR 20050093647 A KR20050093647 A KR 20050093647A KR 100644507 B1 KR100644507 B1 KR 100644507B1
Authority
KR
South Korea
Prior art keywords
boiler pipe
boiler
wire mesh
house
binding
Prior art date
Application number
KR1020050093647A
Other languages
Korean (ko)
Inventor
양철웅
Original Assignee
(주)태원종합기술단건축사사무소
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by (주)태원종합기술단건축사사무소 filed Critical (주)태원종합기술단건축사사무소
Priority to KR1020050093647A priority Critical patent/KR100644507B1/en
Application granted granted Critical
Publication of KR100644507B1 publication Critical patent/KR100644507B1/en

Links

Images

Classifications

    • FMECHANICAL ENGINEERING; LIGHTING; HEATING; WEAPONS; BLASTING
    • F24HEATING; RANGES; VENTILATING
    • F24DDOMESTIC- OR SPACE-HEATING SYSTEMS, e.g. CENTRAL HEATING SYSTEMS; DOMESTIC HOT-WATER SUPPLY SYSTEMS; ELEMENTS OR COMPONENTS THEREFOR
    • F24D3/00Hot-water central heating systems
    • F24D3/12Tube and panel arrangements for ceiling, wall, or underfloor heating
    • F24D3/14Tube and panel arrangements for ceiling, wall, or underfloor heating incorporated in a ceiling, wall or floor
    • F24D3/141Tube mountings specially adapted therefor
    • F24D3/142Tube mountings specially adapted therefor integrated in prefab construction elements
    • EFIXED CONSTRUCTIONS
    • E04BUILDING
    • E04FFINISHING WORK ON BUILDINGS, e.g. STAIRS, FLOORS
    • E04F15/00Flooring
    • E04F15/12Flooring or floor layers made of masses in situ, e.g. seamless magnesite floors, terrazzo gypsum floors

Landscapes

  • Engineering & Computer Science (AREA)
  • Architecture (AREA)
  • Civil Engineering (AREA)
  • Structural Engineering (AREA)
  • Physics & Mathematics (AREA)
  • Thermal Sciences (AREA)
  • Chemical & Material Sciences (AREA)
  • Combustion & Propulsion (AREA)
  • Mechanical Engineering (AREA)
  • General Engineering & Computer Science (AREA)
  • Building Environments (AREA)

Abstract

An installation structure of a boiler pipe is provided to improve heat insulation properties of the bottom of a construction, by preventing the boiler pipe from being moved in sideways or twisted. A foam concrete(2) is placed on a concrete slab(1) by burying wire meshes(2a) in the foam concrete. A boiler pipe(3) is arranged on the foam concrete, and mortar material is placed onto the boiler pipe. A cement layer(4) is formed on the mortar material. A plurality of joint members(10) are welded onto the wire mesh, and the boiler pipe is connected to the joint members. The joint member includes a boiler pipe mounting portion and a support portion(12). The boiler pipe mounting portion has an open top for insertion of the boiler pipe, and an annular bottom. The support portion is extended from both upper sides of the boiler pipe mounting portion, extended vertically from the boiler pipe mounting portion, and extended horizontally from the vertical extension. The support portion is welded onto the wire mesh.

Description

주택내부 바닥의 결속 레일을 이용한 보일러 배관의 설치구조{Installation structure of boiler pipe using connecting rail of the bottom of construction} Installation structure of boiler pipe using connecting rail of the bottom of construction}

도1은 본 발명의 주택 내부 바닥에 보일러 배관이 설치된 것을 도시한 사시도,Figure 1 is a perspective view showing that the boiler pipe is installed on the inner floor of the house of the present invention,

도2는 본 발명의 주택 내부 바닥에 보일러 배관이 설치된 것을 도시한 단면도이다.Figure 2 is a cross-sectional view showing that the boiler pipe is installed on the inner floor of the house of the present invention.

<도면의 주요부분에 대한 부호의 간단한 설명><Brief description of symbols for the main parts of the drawings>

1 : 콘크리트 슬래브 2 : 기포 콘크리트1: concrete slab 2: bubble concrete

2a : 와이어 메쉬 3 : 보일러 배관2a: wire mesh 3: boiler piping

4 : 시멘트 미장층 10 : 결속구4: cement plaster layer 10: binding hole

11 : 보일러 배관 안착부 12 : 지지부11: boiler piping seating part 12: support part

본 발명은 주택내부 바닥의 결속 레일을 이용한 보일러 배관의 설치구조에 관한 것으로, 더욱 상세하게는, 주택내부 바닥의 기포 콘크리트 위에 격자형의 와이어 메쉬를 설치하고, 이 와이어 메쉬 위에 일정 간격으로 다수개 용접 결합된 결 속구에 보일러 배관을 결속하여 설치하도록 함으로써, 보일러 배관의 위치가 좌우로 이동하거나 비틀림이 발생되는 것이 현저히 줄어들어 주택내부 바닥의 보온 순환이 양호하도록 한 주택내부 바닥의 결속 레일을 이용한 보일러 배관의 설치구조에 관한 것이다.The present invention relates to an installation structure of a boiler pipe using a binding rail on the bottom of a house. More specifically, a lattice-shaped wire mesh is installed on the bubble concrete of the bottom of a house, and a plurality of wire meshes are arranged on the wire mesh at regular intervals. By installing and installing the boiler pipes at the joints welded to each other, the boiler pipes can be moved from side to side or torsional to reduce the occurrence of torsion. It relates to a pipe installation structure.

일반적으로, 건물의 시공시에 온돌에는 난방을 위한 온수 공급관, 즉, 보일러 배관을 바닥면에 설치하게 되는데, 종래 난방용 보일러 배관을 시공할시에는 바닥면으로부터 시멘트 몰탈층으로 덮은 다음 보일러 배관을 일정한 간격으로 배관하고 시멘트 미장층으로 방바닥을 형성하는 시공법이 적용되었다. 상기 보일러 배관은 일정 간격으로 배관하여 밴드로 그 위치를 고정시키고 몰탈을 타설하였으나, 보일러 배관이 비틀림이 발생하여 그 위치가 좌우로 이탈됨으로써, 보일러 배관이 일정 간격으로 배치되지 못하게 되어 주택내부 바닥면의 보온 순환이 미흡해지는 문제점이 있다.In general, during construction of a building, a hot water supply pipe for heating is installed on the floor, that is, a boiler pipe is installed on the floor. When constructing a conventional boiler pipe for heating, the floor is covered with a cement mortar layer from the floor and then the boiler pipe is fixed. The construction method of piping at intervals and forming a floor with cement plaster layer was applied. The boiler pipe was fixed at a predetermined interval by the pipe to fix the position and mortar, but the boiler pipe is twisted and the position is separated from side to side, the boiler pipe is not arranged at regular intervals so that the floor inside the house There is a problem that the thermal cycling is insufficient.

따라서, 상기한 바와 같은 문제점을 해결하기 위하여 본 발명의 목적은 주택내부 바닥의 기포 콘크리트 위에 격자형의 와이어 메쉬를 설치하고, 이 와이어 메쉬 위에 일정 간격으로 다수개 용접 결합된 결속구에 보일러 배관을 결속하여 설치하도록 함으로써, 보일러 배관의 위치가 좌우로 이동하거나 비틀림이 발생되는 것이 현저히 줄어들어 주택내부 바닥의 보온 순환이 양호하도록 한 주택내부 바닥의 결속 레일을 이용한 보일러 배관의 설치구조를 제공하는 데 있다. Therefore, in order to solve the above problems, an object of the present invention is to install a lattice-type wire mesh on the foam concrete of the bottom of the house, and the boiler pipe to a plurality of welded joints at regular intervals on the wire mesh. It is to provide the installation structure of the boiler pipe using the binding rail in the bottom of the house to ensure that the heat insulation circulation of the bottom of the house is good by reducing the displacement of the boiler pipe to the left and right or torsion caused by binding to install. .

상기 목적을 달성하기 위하여, 본 발명에 의한 주택내부 바닥의 결속 레일을 이용한 보일러 배관의 설치구조는, 콘크리트 슬래브 위에 와이어 메쉬가 격자형으로 매설하여 바닥 기포 콘크리트를 타설하고, 이 기포 콘크리트의 위에 보일러 배관을 설치하며 그 위에 몰탈로 덮은 다음 시멘트 미장층으로 마감하여 시공한 주택내부 바닥에 있어서, 상기 와이어 메쉬 상에 일정 간격으로 다수의 결속구를 용접 결합하고, 상기 결속구에 상기 보일러 배관을 결속하여서 구성하되; 상기 결속구는 상측을 통해 보일러 배관이 끼움 삽입되도록 상측이 개구되고 하측이 원형으로 된 보일러 배관 안착부와; 상기 안착부의 상측 양측에 일체로 연장되고 하측으로 수직하게 연장 형성되며, 수직으로 연장된 양측으로 수평하게 연장 형성되어 상기 와이어 메쉬 위에 용접 결합되는 지지부로 이루어진 것을 특징으로 한다. In order to achieve the above object, the installation structure of the boiler pipe using the binding rail of the bottom of the house interior according to the present invention, the wire mesh is buried in a lattice shape on the concrete slab, and the bottom foam concrete is poured, and the boiler on the foam concrete In the bottom of the house installed by installing the pipe and covered with a mortar on it and finished with a cement plastering layer, a plurality of fasteners are welded and bonded at regular intervals on the wire mesh, and the boiler pipe is fastened to the fasteners. To constitute; The binding port includes a boiler pipe seating portion of which the upper side is opened and the lower side is circular so that the boiler pipe is inserted through the upper side; It is characterized in that the support is formed integrally extending on both sides of the seating portion and vertically downwardly extending, and horizontally extending vertically on both sides of the seating portion to be welded onto the wire mesh.

이하, 본 발명을 첨부된 도면을 참조하여 설명하면 다음과 같다. Hereinafter, the present invention will be described with reference to the accompanying drawings.

도1은 본 발명의 주택 내부 바닥에 보일러 배관이 설치된 것을 도시한 사시도이고, 도2는 본 발명의 주택의 내부 바닥에 보일러 배관이 설치된 것을 도시한 단면도이다.1 is a perspective view showing that the boiler pipe is installed on the inner floor of the house of the present invention, Figure 2 is a cross-sectional view showing that the boiler pipe is installed on the inner floor of the house of the present invention.

도1 및 도2에 도시된 바와 같이, 본 발명에 의한 주택내부 바닥의 결속 레일을 이용한 보일러 배관의 설치구조는, 콘크리트 슬래브(1) 위에 와이어 메쉬(2a)가 격자형으로 매설하여 바닥 기포 콘크리트(2)를 타설하고, 이 기포 콘크리트(2)의 위에 보일러 배관(3)을 설치하며 그 위에 몰탈로 덮은 다음 시멘트 미장층(4)으로 마감하여 시공한 주택내부 바닥에 있어서, 상기 와이어 메쉬(2a) 상에 일정 간격으로 다수의 결속구(10)를 용접 결합하고, 상기 결속구(10)에 상기 보일러 배관(3)을 결속하여서 구성하되; 상기 결속구(10)는 상측을 통해 보일러 배관(3)이 끼움 삽입되도록 상측이 개구되고 하측이 원형으로 된 보일러 배관 안착부(11)와; 상기 안착부(11)의 상측 양측에 일체로 연장되고 하측으로 수직하게 연장 형성되며, 수직으로 연장된 양측으로 수평하게 연장 형성되어 상기 와이어 메쉬(2a) 위에 용접 결합되는 지지부(12)로 이루어져 있다. As shown in Fig. 1 and Fig. 2, in the installation structure of the boiler pipe using the binding rail of the bottom of the house according to the present invention, the wire mesh 2a is buried in a lattice shape on the concrete slab 1 so that the floor bubble concrete (2) is placed, the boiler pipe (3) is installed on top of the foam concrete (2), covered with mortar on it, and finished with a cement plastering layer (4) on the floor in the house interior, the wire mesh ( 2a) by welding a plurality of binding ports (10) at regular intervals, and configured to bind the boiler pipe (3) to the binding port (10); The binding port 10 has a boiler pipe seating portion 11 of which the upper side is opened and the lower side is circular so that the boiler pipe 3 is inserted through the upper side; The support part 12 is integrally formed on both upper sides of the seating part 11 and vertically extended downwardly, and horizontally extended on both sides of the seating part 11 and welded on the wire mesh 2a. .

이와 같이 구성된 본 발명의 보일러 배관을 설치하는 과정을 설명하면, 콘크리트 슬래브(1) 위에 바닥 기포 콘크리트(2)를 타설하고, 이 기포 콘크리트(2)의 위에 보일러 배관(3)을 설치하며 그 위에 몰탈로 덮은 다음 시멘트 미장층(4)으로 마감하여 시공한 주택내부 바닥을 시공함에 있어서, 상기 보일러 배관(3)을 설치하기 전에 먼저, 상기 기포 콘크리트(2)의 상면에 있는 와이어 메쉬(2a) 위에 일정한 간격을 두고, 결속구(10)의 지지부(12)를 용접 결합한다. 이와 같이 용접 결합된 결속구(10)의 보일러 배관 안착부(11)의 상측 개구를 통하여 보일러 배관(3)을 눌러 끼움 삽입한다. 상기 결속구(10)는 탄성력있는 재질로 와이어를 구부려 안착부(11)와 지지부(12)를 형성 구성함으로써, 상기 안착부(11)에 삽입된 보일러 배관(3)은 그 삽입된 상태가 이탈되지 않고, 견고하게 고정된다. 이러한 시공이 완료되면, 상기 보일러 배관(3) 위에 몰탈로 덮은 다음 시멘트 미장층(4)으로 마감하여 주택 내부 바닥의 시공을 완료하게 된다. Referring to the process of installing the boiler pipe of the present invention configured as described above, the bottom foam concrete (2) is poured on the concrete slab (1), and the boiler pipe (3) is installed on the foam concrete (2) and thereon In the construction of the inner floor of a house covered with mortar and then finished with a cement plaster layer (4), before installing the boiler pipe (3), first, the wire mesh (2a) on the upper surface of the foam concrete (2) At regular intervals above, the welding portion 12 of the binding port 10 is welded. Thus, the boiler pipe 3 is pressed and inserted through the upper opening of the boiler pipe seating part 11 of the binding hole 10 welded and coupled. The binding port 10 is formed by bending the wire with an elastic material to form the seating portion 11 and the support portion 12, the boiler pipe (3) inserted into the seating portion (11) is removed from the inserted state It is not firmly fixed. When the construction is complete, the boiler pipe 3 is covered with mortar and then finished with a cement plastering layer 4 to complete the construction of the interior floor of the house.

상기에서 설명한 바와 같이, 본 발명의 주택내부 바닥의 결속 레일을 이용한 보일러 배관의 설치구조에 의하면, 주택내부 바닥의 기포 콘크리트 위에 격자형의 와이어 메쉬를 설치하고, 이 와이어 메쉬 위에 일정 간격으로 다수개 용접 결합된 결속구에 보일러 배관을 결속하여 설치하도록 함으로써, 보일러 배관의 위치가 좌우로 이동하거나 비틀림이 발생되는 것이 현저히 줄어들어 주택내부 바닥의 보온 순환이 양호한 뛰어난 발명이다. As described above, according to the installation structure of the boiler pipe using the binding rail of the bottom of the house, according to the present invention, a lattice-type wire mesh is installed on the bubble concrete of the bottom of the house, By binding and installing the boiler pipe to the welded binding port, the position of the boiler pipe is shifted from side to side or torsion is remarkably reduced, which is an excellent invention of good thermal circulation of the inner floor of the house.

Claims (1)

콘크리트 슬래브(1) 위에 와이어 메쉬(2a)가 격자형으로 매설하여 바닥 기포 콘크리트(2)를 타설하고, 이 기포 콘크리트(2)의 위에 보일러 배관(3)을 설치하며 그 위에 몰탈로 덮은 다음 시멘트 미장층(4)으로 마감하여 시공한 주택내부 바닥에 있어서,A wire mesh (2a) is laid in a lattice on the concrete slab (1) to pour the floor foam concrete (2), a boiler pipe (3) is installed on the foam concrete (2) and covered with mortar on the cement On the floor inside the house finished with a plastering layer (4), 상기 와이어 메쉬(2a) 상에 일정 간격으로 다수의 결속구(10)를 용접 결합하고, 상기 결속구(10)에 상기 보일러 배관(3)을 결속하여서 구성하되;A plurality of binding holes 10 are welded to the wire mesh 2a at regular intervals, and the boiler pipe 3 is attached to the binding holes 10; 상기 결속구(10)는 상측을 통해 보일러 배관(3)이 끼움 삽입되도록 상측이 개구되고 하측이 원형으로 된 보일러 배관 안착부(11)와;The binding port 10 has a boiler pipe seating portion 11 of which the upper side is opened and the lower side is circular so that the boiler pipe 3 is inserted through the upper side; 상기 안착부(11)의 상측 양측에 일체로 연장되고 하측으로 수직하게 연장 형성되며, 수직으로 연장된 양측으로 수평하게 연장 형성되어 상기 와이어 메쉬(2a) 위에 용접 결합되는 지지부(12)로 이루어진 것을 특징으로 하는 주택내부 바닥의 결속 레일을 이용한 보일러 배관의 설치구조.The support part 12 is integrally formed on both sides of the seating part 11 and vertically extended downwardly, and is formed horizontally on both sides of the seating part 11 to be welded onto the wire mesh 2a. A boiler pipe installation structure using a binding rail on the bottom of a house.
KR1020050093647A 2005-10-05 2005-10-05 Installation structure of boiler pipe using connecting rail of the bottom of construction KR100644507B1 (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
KR1020050093647A KR100644507B1 (en) 2005-10-05 2005-10-05 Installation structure of boiler pipe using connecting rail of the bottom of construction

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
KR1020050093647A KR100644507B1 (en) 2005-10-05 2005-10-05 Installation structure of boiler pipe using connecting rail of the bottom of construction

Publications (1)

Publication Number Publication Date
KR100644507B1 true KR100644507B1 (en) 2006-11-10

Family

ID=37654255

Family Applications (1)

Application Number Title Priority Date Filing Date
KR1020050093647A KR100644507B1 (en) 2005-10-05 2005-10-05 Installation structure of boiler pipe using connecting rail of the bottom of construction

Country Status (1)

Country Link
KR (1) KR100644507B1 (en)

Cited By (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN102980202A (en) * 2012-12-19 2013-03-20 青岛海众环保锅炉股份有限公司 Heat-preservation coal water slurry boiler
KR102105347B1 (en) 2019-12-31 2020-04-28 최종주 Plumbing installation system
KR102105342B1 (en) 2019-12-31 2020-04-28 최종주 Plumbing installation system

Cited By (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN102980202A (en) * 2012-12-19 2013-03-20 青岛海众环保锅炉股份有限公司 Heat-preservation coal water slurry boiler
CN102980202B (en) * 2012-12-19 2015-04-15 青岛海众环保锅炉股份有限公司 Heat-preservation coal water slurry boiler
KR102105347B1 (en) 2019-12-31 2020-04-28 최종주 Plumbing installation system
KR102105342B1 (en) 2019-12-31 2020-04-28 최종주 Plumbing installation system

Similar Documents

Publication Publication Date Title
CN100396860C (en) Concrete building combined with heat insulating framework and its construction method
KR100644507B1 (en) Installation structure of boiler pipe using connecting rail of the bottom of construction
KR20090088978A (en) Piping work structure for heating system
KR102053584B1 (en) Prefabricated thermal conduction plate for ondol and construction method
KR20130023540A (en) Concrete composite wall construction method with soft gangform and form-tie
KR200195502Y1 (en) A heating panel
KR200248810Y1 (en) Heating Panel With Sound-Proof Function
KR100644508B1 (en) Installation structure of boiler pipe using connecting rail of the bottom of construction
KR102422253B1 (en) How to install sanitary plumbing in a building
KR102333183B1 (en) Wire-inserted binding fixture that is assembled at the boundary for pouring heating pipes
KR200351874Y1 (en) A fabricated hot-water heating system.
KR100592466B1 (en) Doubled-wall structure completed by prefabbing panels
CN212001754U (en) Assembled partition wall mounting structure
KR102264712B1 (en) module type bathroom and building method using the same
KR200465920Y1 (en) Waterproof Construction Structure For Bathroom
KR20090006267U (en) Double bottom system and Panel for the double bottom system
KR100311724B1 (en) A brick constructing method of an outer wall and the architecture thereof
JP3112429U (en) Heating piping structure for assembly type ondol
KR100605030B1 (en) Structure for union a plastering mortar of heating pipe for housing floor
CN111719740A (en) Decoration integrated assembly type wall body and installation method thereof
KR100394401B1 (en) Heating system using hot water and method of constructing a heating pipe for the system
KR100301524B1 (en) Insulation Boards for Heating Pipes_
JP4891047B2 (en) Construction structure of drain pipe
KR100642983B1 (en) Reclamation Type Trench and Execution Method for Under Ground Structure Using The Same
KR200294592Y1 (en) Fixing Device of Ondol Panel

Legal Events

Date Code Title Description
A201 Request for examination
E701 Decision to grant or registration of patent right
GRNT Written decision to grant
FPAY Annual fee payment

Payment date: 20121102

Year of fee payment: 7

FPAY Annual fee payment

Payment date: 20131104

Year of fee payment: 8

FPAY Annual fee payment

Payment date: 20141103

Year of fee payment: 9

LAPS Lapse due to unpaid annual fee