KR100628485B1 - Multi-drilling and infusion apparatus for reinforcing a tenderness ground - Google Patents

Multi-drilling and infusion apparatus for reinforcing a tenderness ground Download PDF

Info

Publication number
KR100628485B1
KR100628485B1 KR1020040017353A KR20040017353A KR100628485B1 KR 100628485 B1 KR100628485 B1 KR 100628485B1 KR 1020040017353 A KR1020040017353 A KR 1020040017353A KR 20040017353 A KR20040017353 A KR 20040017353A KR 100628485 B1 KR100628485 B1 KR 100628485B1
Authority
KR
South Korea
Prior art keywords
casing
shovel
drilling
coupled
panel
Prior art date
Application number
KR1020040017353A
Other languages
Korean (ko)
Other versions
KR20040034630A (en
Inventor
강익희
Original Assignee
강익희
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by 강익희 filed Critical 강익희
Priority to KR1020040017353A priority Critical patent/KR100628485B1/en
Publication of KR20040034630A publication Critical patent/KR20040034630A/en
Application granted granted Critical
Publication of KR100628485B1 publication Critical patent/KR100628485B1/en

Links

Images

Classifications

    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D3/00Improving or preserving soil or rock, e.g. preserving permafrost soil
    • E02D3/12Consolidating by placing solidifying or pore-filling substances in the soil
    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D5/00Bulkheads, piles, or other structural elements specially adapted to foundation engineering
    • E02D5/74Means for anchoring structural elements or bulkheads
    • E02D5/80Ground anchors
    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D2300/00Materials
    • E02D2300/0004Synthetics
    • E02D2300/0018Cement used as binder
    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D2600/00Miscellaneous

Landscapes

  • Engineering & Computer Science (AREA)
  • Structural Engineering (AREA)
  • Life Sciences & Earth Sciences (AREA)
  • General Life Sciences & Earth Sciences (AREA)
  • Mining & Mineral Resources (AREA)
  • Paleontology (AREA)
  • Civil Engineering (AREA)
  • General Engineering & Computer Science (AREA)
  • Agronomy & Crop Science (AREA)
  • Environmental & Geological Engineering (AREA)
  • Soil Sciences (AREA)
  • Consolidation Of Soil By Introduction Of Solidifying Substances Into Soil (AREA)

Abstract

본 발명은 다기능 연약지반 보강 시공장치에 관한 것으로, 연약지반에 대한 케이싱과 로드에 의한 천공, 시멘트 밀크 고압분사, 마이크로 파일 삽입 및 케이싱 인발, 별도의 주입관에 의한 시멘트 밀크 추가충전 등의 과정이 단일의 장치에서 이루어질 수 있도록 천공장치와 로타리장치를 이동패널 상에 이웃하게 구비하고, 그 이동패널이 지지패널의 상면에 형성된 레일을 따라 슬라이드 가능하게 구성함으로써 복수개의 장치를 이용하여 각각 수행되어져 왔던 위 공정을 하나의 장치로서 신속하고 용이하게 수행할 수 있도록 한 것으로, 이는 타격력 및 회전력을 부여하는 탑 해머와; 그 탑 해머의 전단에 체결되어 회전되면서 에어와 물을 전단에 공급하는 슈벨과; 슈벨의 외부에 결합 된 슈벨 케이스와; 슈벨 전단 외주연에 그 일단이 체결되는 어댑터와; 어댑터의 타단에 체결되는 케이싱과; 케이싱의 내부에 위치되고 그 내부 일단이 슈벨의 전단 내주연과 체결되는 로드로 구성된 천공장치와, 시멘트 밀크를 제트압으로 공급하기 위한 로타리장치에 있어서, 상기 천공장치와 그 전단에 로드 고정장치(=척)가 구성된 로타리장치를 각각 병렬로 그 상면에 안착하여 상기 천공장치의 케이싱과 수직되게 구성된 이동패널과; 상기 이동패널의 하부에 구성되며, 그 상면에 상기 이동패널이 슬라이딩되는 레일이 구비되어져 있으며, 내부 바닥면에 결합되고, 그 축이 상기 이동패널에 결합되어 슬라이딩을 위한 유출 압력을 제공하는 유압실린더가 구비된 지지패널로 구성된 것을 특징으로 한다.The present invention relates to a multifunctional soft ground reinforcement construction device, the process of drilling by casing and rod for soft ground, cement milk high-pressure injection, micro pile insertion and casing drawing, additional filling of cement milk by a separate injection pipe A perforation device and a rotary device are provided adjacent to the moving panel so as to be made in a single device, and the moving panel is configured to be slidable along a rail formed on the upper surface of the support panel. The above process can be performed quickly and easily as a single device, which includes: a tower hammer for imparting a hitting force and a rotating force; A shovel which is coupled to the front end of the tower hammer and rotates to supply air and water to the front end; A shovel case coupled to the outside of the shovel; An adapter whose one end is fastened to the outer periphery of the shvel shear; A casing fastened to the other end of the adapter; A perforation device consisting of a rod positioned inside the casing and having one end thereof engaged with a shear inner circumference of the shovel, and a rotary device for supplying cement milk at a jet pressure, wherein the perforation device and a rod fixing device at the front end thereof ( A movable panel configured to be mounted on the upper surface of the rotary device, each of which is configured to be chucks, in parallel with the casing of the drilling device; A hydraulic cylinder is provided in the lower portion of the moving panel, the upper surface is provided with a rail for sliding the moving panel, coupled to the inner bottom surface, the shaft is coupled to the moving panel to provide an outflow pressure for sliding. Characterized in that consisting of a supporting panel provided.

본 발명을 적용하면, 각각 복수개의 장치를 단일의 장치에 구성함으로서, 각 공정에 따라 신속하게 슬라이딩 되어 작업위치에 위치되게 함으로써 천공작업과, 시멘트 밀크의 고압분사 작업이 신속하게 이루어지게 되어 몇 개의 장치 이동에 따른 시공시간을 감소시키고, 천공장치나 고압분사 장치 등의 별도 비용을 효과적으로 감소한 효과가 있다.According to the present invention, by constructing a plurality of devices in a single device, the drilling operation and the high-pressure spraying work of cement milk can be made quickly by positioning the work position by sliding quickly according to each process. The construction time according to the movement of the device is reduced, and the separate cost of the punching device or the high-pressure jetting device is effectively reduced.

Description

다기능 연약지반 보강 시공장치{MULTI-DRILLING AND INFUSION APPARATUS FOR REINFORCING A TENDERNESS GROUND}MULTI-DRILLING AND INFUSION APPARATUS FOR REINFORCING A TENDERNESS GROUND}

도 1은 본 발명의 일실시예에 따른 다기능 연약지반 보강 시공장치에 포함된 천공장치를 도시한 사시도,1 is a perspective view showing a cloth mill included in the multifunctional soft ground reinforcement construction apparatus according to an embodiment of the present invention,

도 2는 본 발명의 일실시예에 따른 다기능 연약지반 보강 시공장치를 도시한 평단면도,Figure 2 is a plan sectional view showing a multifunctional soft ground reinforcement at the factory according to an embodiment of the present invention,

도 3은 본 발명의 일실시예에 따른 다기능 연약지반 보강 시공장치를 도시한 정단면도,Figure 3 is a front sectional view showing a multifunctional soft ground reinforcement at the factory according to an embodiment of the present invention,

도 4a∼4e는 본 발명의 일실시예에 따른 다기능 연약지반 보강 시공장치를 통한 공정을 도시한 측단면도이다.Figures 4a to 4e is a side cross-sectional view showing a process through a multi-functional soft ground reinforcement factory according to an embodiment of the present invention.

삭제delete

*도면의 주요부분에 대한 부호의 설명** Description of the symbols for the main parts of the drawings *

2:천공장치, 4:탑 해머,2: drilling device, 4: tower hammer,

14:슈벨, 24:케이싱,14: Schubel, 24: Casing,

26:로드, 30:로타리장치,26: rod, 30: rotary device,

32:로드 고정장치(=척), 40:지지패널,32: rod fixing device (= chuck), 40: support panel,

42:레일, 44:이동패널,42: rail, 44: moving panel,

46:유압실린더.46: Hydraulic cylinder.

본 발명은 다기능 연약지반 보강 시공장치에 관한 것으로, 보다 상세하게는 연약지반에 대한 케이싱과 로드에 의한 천공, 시멘트 밀크 고압분사, 마이크로 파일 삽입 및 케이싱 인발, 별도의 주입관에 의한 시멘트 밀크 추가충전 등의 과정이 단일의 장치에서 이루어질 수 있도록 천공장치와 로타리장치를 이동패널 상에 이웃하게 구비하고, 그 이동패널이 지지패널의 상면에 형성된 레일을 따라 슬라이드 가능하게 구성함으로써 복수개의 장치를 이용하여 각각 수행되어져 왔던 위 공정을 하나의 장치로서 신속하고 용이하게 수행할 수 있게 한 다기능 연약지반 보강 시공장치에 관한 것이다.
주지된 바와 같이, 토목공사시 연약지반 및 불량 지반을 보강할 경우에는 유압 드릴이나 각종 천공기의 로드(Rod), 및 비트(Bit)를 이용하여 그 연약지반에 천공홀을 형성하고, 그 천공홀에 앙카체를 삽입하고, 그 앙카체와 함께 삽입한 별도의 주입파이프를 이용하여 시멘트 밀크를 주입한 후, 앙카체를 인장하는 어스앙카공법과; 천공후 고압분사장치로 시멘트 밀크를 고압분사하여 원주형의 기둥을 지중에 형성하는 Z-그라우팅(Z-Grouting) 방법이 일반적이었다.
The present invention relates to a multifunctional soft ground reinforcement construction device, and more particularly, perforation by casing and rod for soft ground, cement milk high pressure spray, micro pile insertion and casing drawing, additional filling of cement milk by separate injection pipe The perforation device and the rotary device are provided adjacent to the moving panel so that the process can be performed in a single device, and the moving panel is configured to be slidable along the rail formed on the upper surface of the support panel. The present invention relates to a multifunctional soft ground reinforcement construction device which enables the above process, which has been performed each, to be performed quickly and easily as a single device.
As is well known, when reinforcing the soft ground and the poor ground during civil works, a drill hole is formed in the soft ground by using a rod and a bit of a hydraulic drill or various drilling machines, and the drill hole An earth anchor method for inserting an anchor into the container, injecting cement milk using a separate injection pipe inserted with the anchor, and tensioning the anchor body; The Z-Grouting method of forming a columnar column in the ground by high-pressure spraying cement milk with a high-pressure spraying device after drilling was common.

삭제delete

이때 Z-그라우팅(Z-Grouting) 작업은 대개 암반 및 토질이 안정화되어져 있는 곳에서는 행해지지 않으며, 연약지반이나 지층의 복합성으로 인한 불량지역에서 주로 그러한 불량지질을 안정화시키기 위한 방법으로 사용되어지고 있는 것으로, 전체 공정은 천공장치에 의한 천공 및 인발작업과 고압 분사장치에 의한 고압 분사작업으로 대별되고, 천공작업은 지반천공 -> 스라임 배출 -> 케이싱 일부 인발하는 것으로 단일의 천공장치에 의해 수행한다.At this time, Z-Grouting is not usually performed where rock and soil are stabilized, and is mainly used as a method for stabilizing such poor lipids in poor areas due to the complexity of soft ground or strata. The whole process is roughly divided into the drilling and drawing work by the drilling device and the high pressure spraying by the high pressure injection device, and the drilling work is performed by a single drilling device by ground drilling-> lime discharge-> drawing part of the casing. do.

또한, 고압분사작업은 연약지반의 천공이 완료된 상태에서 케이싱의 일부만을 그 연약지반의 상부로 인발시킨 상태에서, 천공장치를 위치이동시키고, 시멘트 밀크를 고압분사하기 위한 별도의 주입장치(일명, Z-Grouting 장비)를 해당 천공위치로 이동시켜 에어 및 시멘트 밀크를 로드의 내부에 형성된 안내로를 통해 연약지반의 천공홀로 고압분사시켜 원주형 기둥을 지중에 형성시킨다.In addition, the high-pressure spraying operation is a separate injection device for the high-pressure spraying cement milk to move the position of the mill factory in the state of drawing only a part of the casing to the upper part of the soft ground in the completion of the drilling of the soft ground (aka, Z-Grouting equipment) is moved to the corresponding drilling position, and high-pressure spraying air and cement milk into the drilling hole of the soft ground through the guideway formed inside the rod to form a columnar column in the ground.

추가로 마이크로 파일이나 앙카체를 삽입하는 경우(마이크로 파일공법)에는 Z-Grouting(고압분사)완료후, 다시 천공장치를 해당 위치로 이동시켜 일부 인발된 케이싱을 다시 천공심도의 종단부까지 삽입시키고, 마이크로 파일이나 앙카체를 그 케이싱의 내부로 삽입한다. 이때, 케이싱의 원할한 삽입을 위해 슈벨(Swivel)을 통해 시멘트 밀크를 투입하며 삽입한다.In addition, in case of inserting micro pile or anchor (micro pile method), after Z-Grouting (high pressure injection) is completed, move the fabric mill back to the relevant position and insert some drawn casing back to the end of drilling depth. Insert a microfile or anchor into the casing. At this time, insert the cement milk through the Swivel for a smooth insertion of the casing.

그리고, 삽입된 마이크로 파일이나 앙카체를 제외한 케이싱을 완전히 외부로 인발하고, 해당 천공홀과 마이크로 파일이나 앙카체의 사이에는 시멘트 밀크를 주입하여 충전시키면 천공 및 시멘트 밀크의 분사, 앙카체 삽입공정이 완료되어 연약지반을 보강할 수 있게 된다. Then, the casing except for the inserted micro pile or anchor is completely drawn out, and the cement milk is injected and filled between the perforation hole and the micro pile or anchor, and the injection and drilling of the cement milk is performed. It is completed to reinforce the soft ground.

하지만, 이러한 연약지반 보강 시공과정은 천공장치와 분사장치가 각각 번갈아가면서 작업을 수행해야 하므로 그 시공시간이 장시간 소요된다는 문제점이 있어 그 시공비용도 증가 될 뿐더러, 작업 공정이 매우 복잡하다는 단점이 있었다.
또한, 연약지반 보강공정에 투입된 장비의 수가 많아지게 되므로 장치 임대비용이 증가 된다는 단점이 있었다.
However, the soft ground reinforcement construction process has a problem that the construction time takes a long time because the drilling device and the injection device are to be alternately performed, the construction cost is increased, and the work process is very complicated. .
In addition, since the number of equipment put into the soft ground reinforcement process increases, the device rental cost was increased.

본 발명은 상기한 종래 기술의 사정을 감안하여 이루어진 것으로, 연약지반에 대한 케이싱과 로드에 의한 천공, 시멘트 밀크 고압분사, 마이크로 파일 삽입 및 케이싱 인발, 별도의 주입관에 의한 시멘트 밀크 추가충전 등의 과정이 단일의 장치에서 이루어질 수 있도록 천공장치와 로타리장치를 이동패널 상에 이웃하게 구비하고, 그 이동패널이 지지패널의 상면에 형성된 레일을 따라 슬라이드 가능하게 구성함으로써 복수개의 장치를 이용하여 각각 수행되어져 왔던 위 공정을 하나의 장치로서 신속하고 용이하게 수행할 수 있게 한 다기능 연약지반 보강 시공장치를 제공하는데 그 목적이 있다.The present invention has been made in view of the above-described circumstances of the prior art, such as perforation by casing and rod on the soft ground, cement milk high-pressure injection, micro-pile insertion and casing drawing, additional filling of cement milk by a separate injection tube, etc. A perforation device and a rotary device are provided adjacent to the moving panel so that the process can be performed in a single device, and the moving panel is configured to be slidable along a rail formed on the upper surface of the support panel. The purpose of the present invention is to provide a multifunctional soft ground reinforcement factory that can perform the above process as a single device quickly and easily.

상기한 목적을 달성하기 위해, 본 발명의 바람직한 실시예에 따르면 타격력 및 회전력을 부여하는 탑 해머와; 그 탑 해머의 전단에 체결되어 회전되면서 에어와 물을 전단에 공급하는 슈벨과; 슈벨의 외부에 결합된 슈벨 케이스와; 슈벨 전단 외주연에 그 일단이 체결되는 어댑터와; 어댑터의 타단에 체결되는 케이싱과; 케이싱의 내부에 위치되고 그 내부 일단이 슈벨의 전단 내주연과 체결되는 로드로 구성된 천공장치와, 시멘트 밀크를 제트압으로 공급하기 위한 로타리장치에 있어서, 상기 천공장치와 그 전단에 로드 고정장치(=척)가 구성된 로타리장치를 각각 병렬로 그 상면에 안착하여 상기 천공장치의 케이싱과 수직되게 구성된 이동패널과; 상기 이동패널의 하부에 구성되며, 그 상면에 상기 이동패널이 슬라이딩되는 레일이 구비되어져 있으며, 내부 바닥면에 결합되고, 그 축이 상기 이동패널에 결합되어 슬 라이딩을 위한 유출 압력을 제공하는 유압실린더가 구비된 지지패널로 구성된 것을 특징으로 하는 다기능 연약지반 보강 시공장치가 제공된다.In order to achieve the above object, according to a preferred embodiment of the present invention; A shovel which is coupled to the front end of the tower hammer and rotates to supply air and water to the front end; A shovel case coupled to the outside of the shovel; An adapter whose one end is fastened to the outer periphery of the shvel shear; A casing fastened to the other end of the adapter; A perforation device consisting of a rod positioned inside the casing and having one end thereof engaged with a shear inner circumference of the shovel, and a rotary device for supplying cement milk at a jet pressure, wherein the perforation device and a rod fixing device at the front end thereof ( A movable panel configured to be mounted on the upper surface of the rotary device, each of which is configured to be chucks, in parallel with the casing of the drilling device; Is configured in the lower portion of the movable panel, the upper surface is provided with a rail for sliding the movable panel, coupled to the inner bottom surface, the shaft is coupled to the movable panel to provide an outflow pressure for sliding Provided is a multifunctional soft ground reinforcement construction device comprising a support panel provided with a cylinder.

삭제delete

이하, 본 발명에 대해 도면을 참조하여 상세하게 설명한다.EMBODIMENT OF THE INVENTION Hereinafter, this invention is demonstrated in detail with reference to drawings.

도 1은 본 발명의 일실시예에 따른 다기능 연약지반 보강 시공장치에 포함된 천공장치를 도시한 사시도이며, 도 2는 본 발명의 일실시예에 따른 다기능 연약지 반 보강 시공장치를 도시한 평단면도이고, 도 3은 본 발명의 일실시예에 따른 다기능 연약지반 보강 시공장치를 도시한 정단면도이다.1 is a perspective view showing a fabric mill included in the multifunctional soft ground reinforcement construction apparatus according to an embodiment of the present invention, Figure 2 is a flat showing a multifunctional soft ground semi reinforcement municipal plant according to an embodiment of the present invention Figure 3 is a cross-sectional view showing a multifunctional soft ground reinforcement at the factory according to an embodiment of the present invention.

이를 참조하면, 본 발명의 일실시예에 따른 다기능 연약지반 보강 시공장치(1)는 천공장치(2)와 로타리 장치(30)로 이루어지며, 그 천공장치(2)와 로타리 장치(30)는 이웃하게 위치되어져 있으며, 각각 슬라이딩되어 천공위치에 대해 천공장치(2) 및 로타리장치(30)의 축이 위치될 수 있게 구성되어져 있다.Referring to this, the multifunctional soft ground reinforcement construction device 1 according to an embodiment of the present invention is made of a drilling device 2 and a rotary device 30, the drilling device 2 and the rotary device 30 is It is located adjacent to each other, it is configured so that the axis of the drilling device 2 and the rotary device 30 can be positioned with respect to the drilling position, respectively.

개략적으로 도 1을 참조하여 본 발명에 적용되는 공지의 천공장치(2)에 대해 기술하면, 천공장치(2)는 그 후단에 지지체(4)가 구성되어져 있으며, 그 지지체(4)에는 드래프트(6)와 탑 해머(8)가 구성되어져 있다. 탑 해머(8)는 그 내부에 연결된 축을 유압으로 회전시키면서 타격되어져 전단부의 구성물을 연약지반에 투입시키기 위한 것이다. Referring to FIG. 1, a punching device 2 known in the present invention will be described. In the punching device 2, a support 4 is formed at a rear end thereof, and the support 4 has a draft ( 6) and the tower hammer 8 are comprised. The tower hammer 8 is blown while hydraulically rotating the shaft connected therein so as to inject the components of the front end portion into the soft ground.

또한, 그 탑 해머(8)의 전단에는 샹크(12)가 결합되어져 있으며, 그 샹크(12)의 전단에는 슈벨(Swivel: 18)이 나사결합되어져 있다. 슈벨(Swivel: 18)은 천공장치(2)나 로타리장치(30)에 각각 구비되어져 있는 바, 그 기능은 회전력에 의해 회전하면서 공기나 시멘트 밀크를 로드를 통해 연약지반으로 주입하기 위한 연결 매개체이다. 슈벨(18)의 외부에는 슈벨 케이스(14)가 결합되어져 있으며, 슈벨(18)의 전단 외주연 및 내주연에는 각각 나사가 각설되어져 있다.In addition, a shank 12 is coupled to the front end of the top hammer 8, and a Swivel 18 is screwed to the front end of the shank 12. Swivel (18) is provided in each of the drilling device (2) or rotary device (30), the function is a connection medium for injecting air or cement milk into the soft ground through the rod while rotating by the rotational force . The outer side of the shovel 18 is coupled to the shovel case 14, and screws are angled on the front outer periphery and the inner periphery of the shovel 18, respectively.

외주연의 나사에는 어댑터(20)가 체결되고, 그 어댑터(20)의 타측 내주연에는 케이싱(24)이 길이방향으로 체결되게 된다. 그 케이싱(24)과 어댑터(20)의 내부에는 내부에 안내로(미도시)가 형성된 로드(26)가 개재되고, 그 로드(26)의 내측 종단은 상기 슈벨(18)의 내주연에 각설된 나사에 체결되게 된다.The adapter 20 is fastened to the screw of the outer circumference, and the casing 24 is fastened in the longitudinal direction to the other inner circumference of the adapter 20. The casing 24 and the adapter 20 are interposed therein with a rod 26 formed therein with a guide path (not shown), and the inner end of the rod 26 is angled to the inner circumference of the shovel 18. To the threaded screw.

따라서, 상기 탑 해머(8)의 타격력 및 회전력에 의해 상기 슈벨(18)이 회전되면서 타격되면 그 전단에 체결된 로드(26) 및 케이싱(24)이 연약지반에 대해서 타격되고 회전되면서 연약지반의 내부로 삽입되게 된다.Accordingly, when the shovel 18 is rotated and hit by the striking force and the rotational force of the top hammer 8, the rod 26 and the casing 24 fastened to the front end of the top hammer 8 are hit against and rotated against the soft ground. It will be inserted inside.

또한, 연약지반의 일정깊이로 상기 로드(26) 및 케이싱(24)을 삽입한 상태에서는 그 로드(26)를 통해 고압의 압축공기 및 물을 상기 슈벨(18)을 통해서 주입하게 되고, 그 전단에 체결된 로드(26)를 통해 내부 연약지반의 천공이 용이하게 에어와 물을 주입하여 토사나 암석을 파쇄하면서 천공한다. 이때, 배출홀(22)을 통해 파쇄된 토사나 암석은 외부로 배출된다.In addition, in the state where the rod 26 and the casing 24 are inserted at a predetermined depth of the soft ground, compressed air and water of high pressure are injected through the shoe bell 18 through the rod 26, and the front end thereof. Through the rod 26 fastened to the inner soft ground to easily inject air and water to drill while crushing the soil and rock. At this time, the soil or rock crushed through the discharge hole 22 is discharged to the outside.

천공이 완료되면 시멘트 밀크를 고압분사(일명, Z-Grouting)해야 하는 바, 본 발명의 일실시예에 따른 다기능 연약지반 보강 시공장치(1)는 도 2에 도시된 바와 같이 시멘트 밀크를 고압분사하기 위한 로타리 장치(30)를 그 천공장치(2)와 함께 단일의 장치에 구성한다.When the drilling is completed, the high-pressure spraying cement milk (aka, Z-Grouting) bar, multifunctional soft ground reinforcement construction device 1 according to an embodiment of the present invention is a high-pressure spraying cement milk as shown in FIG. And the rotary device 30 together with the perforation device 2 in a single device.

즉, 본 발명의 일실시예에 따른 다기능 연약지반 보강 시공장치(1)는 연약지반에 대한 케이싱(24)과 로드(26)의 삽입공정, 시멘트 밀크 고압분사공정, 마이크로 파일이나 앙카체 삽입공정 및 케이싱 인발공정, 여백에 별도의 주입관(도 4e참조)(72)을 통해 시멘트 밀크 추가 충전공정 등의 공정이 단일의 장치에서 이루어질 수 있도록 천공장치(2)와 로타리장치(30)를 이동패널(44) 상에 이웃하게 구비하고, 그 이동패널(44)이 지지패널(40)의 상면에 형성된 레일(42)을 따라 슬라이드 가능하게 구성함으로써 종래 복수개의 장치로 구성되었던 것을 단일의 장치에 구성함으로써 신속하고 용이하게 시공할 수 있도록 한 것이다.That is, the multifunctional soft ground reinforcement construction device 1 according to the embodiment of the present invention is a step of inserting the casing 24 and the rod 26 into the soft ground, a cement milk high pressure spraying step, a micro pile or an anchor inserting step. And the drilling device 2 and the rotary device 30 to move the casing drawing process, a separate filling tube (see FIG. 4E) 72 to the margin, and to perform a process such as additional filling of cement milk in a single device. It is provided adjacent to the panel 44, the movable panel 44 is slidably configured along the rail 42 formed on the upper surface of the support panel 40 in a single device that was conventionally composed of a plurality of devices By constructing, it is possible to construct quickly and easily.

보다 상세하게는, 본 발명의 일실시예에 따른 다기능 연약지반 보강 시공장치(1)는 상기 천공장치(2)와 그 전단에 로드 고정장치(=척)가 구성된 로타리장치(30)를 각각 병렬로 이동패널(44)의 상면에 구성한다. 이때, 상기 이동패널(44)은 천공장치(2)에 형성된 케이싱(24)과 수직으로 위치되게 형성되어져 있다.In more detail, the multifunctional soft ground reinforcement construction apparatus 1 according to the embodiment of the present invention parallels the perforation apparatus 2 and the rotary apparatus 30 in which a rod fixing device (= chuck) is formed at the front end thereof. The upper surface of the furnace movement panel 44 is configured. At this time, the movable panel 44 is formed to be perpendicular to the casing 24 formed in the drilling device (2).

또한, 상기 이동패널(44)은 지지패널(40)의 하부에 구성되는 바, 그 지지패널(40)의 상면에는 레일(42)이 구성되고, 그 레일(42)의 상면에 이동패널(44)이 안착되게 구성된다. 또한, 상기 지지패널(40)의 상면에는 복수개의 유압실린더(46)가 구성되어져 있으며, 그 유압실린더(46)의 유압로드는 상기 이동패널(44)의 하면에 결합되어져 있다. In addition, the movable panel 44 is formed in the lower portion of the support panel 40, the rail 42 is formed on the upper surface of the support panel 40, the movable panel 44 on the upper surface of the rail 42 ) Is configured to be seated. In addition, a plurality of hydraulic cylinders 46 are formed on the upper surface of the support panel 40, and the hydraulic rods of the hydraulic cylinders 46 are coupled to the lower surface of the moving panel 44.

따라서, 천공 작업시에는 상기 천공장치(2)가 케이싱(24)과 로드(26)에 결합되어져 작업을 수행하고, 시멘트 밀크 고압분사 작업시에는 상기 천공장치(2)의 슈벨(18)을 로드(26)와 케이싱(24)으로부터 분리시키고, 상기 유압실린더(46)를 구동시켜 상기 이동패널(44)을 일정거리 이동시켜 상기 케이싱(24)과 상기 로드(26)를 로타리장치(30)의 전단에 구비된 로드 고정장치(32)에 결합함으로써 시멘트 밀크가 고압분사될 수 있게 된다. 또한, 시멘트 밀크의 고압분사 작업후 케이싱(24)을 연약지반의 주입심도에 삽입하거나 마이크로 파일이나 앙카체를 삽입하는 공정시에는 다시 상기 유압실린더(46)를 구동시켜 상기 이동패널(44)을 일정거리 이동시켜 천공장치(2)의 슈벨(18)에 케이싱(24)이 결합되도록 한다. 이를 통해, 각각 별도로 구성된 복수개의 장치를 반복하여 해당 연약지반의 천공위치로 옮겨 작업해야 하는 불편을 효과적으로 제거하여 신속한 시공이 이루어질 수 있게 된다.Therefore, in the drilling operation, the drilling device 2 is coupled to the casing 24 and the rod 26 to perform the work, and in the cement milk high-pressure spraying operation, the shovel 18 of the drilling device 2 is loaded. Separate from the 26 and the casing 24, the hydraulic cylinder 46 is driven to move the movable panel 44 by a certain distance to move the casing 24 and the rod 26 of the rotary device 30 By coupling to the rod fixing device 32 provided at the front end it is possible to spray high-pressure cement milk. In addition, in the process of inserting the casing 24 into the injection depth of the soft ground or inserting the micro pile or anchor after the high-pressure injection of cement milk, the hydraulic cylinder 46 is again driven to drive the movable panel 44. A certain distance is moved so that the casing 24 is coupled to the shoe bell 18 of the drilling device (2). Through this, it is possible to achieve a rapid construction by effectively removing the inconvenience to move to a perforated position of the soft ground by repeating a plurality of devices each configured separately.

도 4a∼4e는 본 발명의 일실시예에 따른 다기능 연약지반 보강 시공장치를 통한 작업순서를 설명하기 위한 도면이다.Figures 4a to 4e is a view for explaining the work order through the multi-functional soft ground reinforcement factory according to an embodiment of the present invention.

먼저, 상기 천공장치(2)의 탑 해머(8) 전단에는 샹크(12)를 결합시키고, 그 샹크(12)의 전단에 슈벨(Swivel: 18)을 체결하고, 슈벨(18)의 외주연의 나사에 어댑터(20)를 체결하고, 그 어댑터(20)의 타측 내주연에 케이싱(24)을 체결하며, 그 어댑터(20)의 내부에 구비된 로드(26)를 상기 슈벨(18)의 내주연에 각설된 나사에 체결한다.First, the shank 12 is coupled to the front end of the top hammer 8 of the punching device 2, and the swivel 18 is fastened to the front end of the shank 12. The adapter 20 is fastened to the screw, the casing 24 is fastened to the inner circumference of the other side of the adapter 20, and the rod 26 provided inside the adapter 20 is connected to the inside of the shovel 18. Tighten to the screws laid on the periphery.

그리고, 연약지반에 대해 상기 케이싱(24)과 로드(26)를 위치시키고, 상기 탑 해머(8)의 타격력 및 회전력에 의해 상기 슈벨(18)이 회전되면서 타격되면 그 전단에 체결된 로드(26) 및 케이싱(24)이 연약지반에 대해서 타격되고 회전되면서 연약지반의 내부로 삽입되게 된다.
이때, 부가적으로 상기 슈벨(18)에 에어와 물을 공급함으로써 천공작업과 슬라임 배출이 용이하게 이루어질 수 있도록 한다.
In addition, the casing 24 and the rod 26 are positioned with respect to the soft ground, and the rod 26 is fastened to the front end when the shovel 18 is hit while being rotated by the striking force and the rotational force of the top hammer 8. ) And the casing 24 are inserted into the soft ground while being hit and rotated against the soft ground.
At this time, by additionally supplying air and water to the shovel 18 to facilitate the drilling and slime discharge.

또한, 연약지반의 일정깊이로 상기 로드(26) 및 케이싱(24)을 삽입한 상태에서는 그 로드(26)를 통해 고압의 압축공기 및 물을 상기 슈벨(18)을 통해서 주입하고, 흙이 흙배출공(22)을 통해 외부로 배출되게 한다. 그러면, 연약지반(50)의 내부가 도 4a에 도시된 바와 같이 천공된다.In addition, when the rod 26 and the casing 24 are inserted at a predetermined depth of the soft ground, compressed air and water of high pressure are injected through the shovel 18 through the rod 26, and the soil is soiled. It is to be discharged to the outside through the discharge hole (22). Then, the interior of the soft ground 50 is drilled as shown in Figure 4a.

천공이 완료되면, 상기 케이싱(24)의 일부를 외부로 인출하고, 상기 천공장치(2)의 슈벨(18)을 로드(26)와 케이싱(24)으로부터 분리시키고, 상기 유압실린더(46)를 구동시켜 상기 이동패널(44)을 일정거리 이동시켜 상기 케이싱(24)과 상기 로드(26)를 로타리장치(30)의 전단에 구비된 로드 고정장치(32)에 결합하고, 시멘트 밀크(60)를 상기 로드(26)를 통해 고압분사시켜 원주형 기둥 을 지중에 형성시킨다.When the drilling is completed, a part of the casing 24 is taken out, and the shoe bell 18 of the drilling apparatus 2 is separated from the rod 26 and the casing 24, and the hydraulic cylinder 46 is removed. Drive the movable panel 44 by a certain distance to couple the casing 24 and the rod 26 to the rod fixing device 32 provided at the front end of the rotary device 30, cement milk 60 The high pressure spray through the rod 26 to form a columnar column in the ground.

시멘트 밀크의 고압분사가 완료되면, 상기 로드(26)를 완전히 외부로 인발하고, 다시 상기 유압실린더(46)를 구동시켜 상기 이동패널(44)을 일정거리 이동시켜 천공장치(2)의 슈벨(18)에 케이싱(24)이 결합시킨다. 그리고, 케이싱(24)을 천공심도의 끝까지 삽입한다.When the high-pressure injection of the cement milk is completed, the rod 26 is completely drawn out, and the hydraulic cylinder 46 is driven again to move the movable panel 44 by a certain distance so that the shovel of the drilling device 2 18, the casing 24 is coupled. Then, the casing 24 is inserted to the end of the drilling depth.

케이싱(24)의 삽입이 완료되면, 그 케이싱(24)의 내부에 마이크로 파일(70)이나 앙카체(미도시)를 삽입하고 케이싱(24)의 선단까지 내려가게 한다. 마이크로 파일(70)이나 앙카체가 완전히 케이싱(24)의 선단까지 내려가면 상기 케이싱(24)을 외부로 인발하여 회수한다.When the insertion of the casing 24 is completed, the micro pile 70 or an anchor (not shown) is inserted into the casing 24 to descend to the tip of the casing 24. When the micro pile 70 or the anchor is completely lowered to the front end of the casing 24, the casing 24 is drawn out and collected.

그리고, 상기 마이크로 파일(70)이나 앙카체와 함께 묶어서 삽입한 별도의 주입튜브(미도시)를 통해 시멘트 밀크를 상기 마이크로 파일(70)이나 앙카체와 천공홀의 사이에 주입하여 천공홀 내부를 충전시킨다.Then, cement milk is injected between the micro pile 70 or the anchor body and the drilling hole through a separate injection tube (not shown) inserted and bundled with the micro pile 70 or the anchor body to fill the inside of the drilling hole. Let's do it.

따라서, 천공 작업시에는 상기 천공장치(2)가 케이싱(24)과 로드(26)에 결합되어져 작업을 수행하고, 시멘트 밀크 고압분사 작업시에는 상기 천공장치(2)의 슈벨(18)을 로드(26)와 케이싱(24)으로부터 분리시키고, 상기 유압실린더(46)를 구동시켜 상기 이동패널(44)을 일정거리 이동시켜 상기 케이싱(24)과 상기 로드(26)를 로타리장치(30)의 전단에 구비된 로드 고정장치(32)에 결합함으로써 시멘트 밀크가 고압분사될 수 있게 된다.
또한, 시멘트 밀크의 고압분사 작업후 케이싱(24)을 연약지반의 주입심도에 삽입하거나 마이크로 파일이나 앙커체를 삽입하는 공정시에는 다시 상기 유압실린더(46)를 구동시켜 상기 이동패널(44)을 일정거리 이동시켜 천공장치(2)의 슈벨(18)에 케이싱(24)이 결합되도록 한다. 이를 통해, 각각 별도로 구성된 복수개의 장치를 반복하여 해당 연약지반의 천공위치로 옮겨 작업해야 하는 불편을 효과적으로 제거하여 신속한 시공이 이루어질 수 있게 된다.
Therefore, in the drilling operation, the drilling device 2 is coupled to the casing 24 and the rod 26 to perform the work, and in the cement milk high-pressure spraying operation, the shovel 18 of the drilling device 2 is loaded. Separate from the 26 and the casing 24, the hydraulic cylinder 46 is driven to move the movable panel 44 by a certain distance to move the casing 24 and the rod 26 of the rotary device 30 By coupling to the rod fixing device 32 provided at the front end it is possible to spray high-pressure cement milk.
In addition, in the process of inserting the casing 24 into the injection depth of the soft ground or inserting the micro pile or the anchor body after the high-pressure injection of cement milk, the hydraulic cylinder 46 is driven again to drive the movable panel 44. A certain distance is moved so that the casing 24 is coupled to the shoe bell 18 of the drilling device (2). Through this, it is possible to achieve a rapid construction by effectively removing the inconvenience to work by repeatedly moving a plurality of devices each configured separately to the drilling position of the soft ground.

한편, 본 발명의 실시예에 따른 다기능 연약지반 보강 시공장치는 단지 상기한 실시예에 한정되는 것이 아니라 그 기술적 요지를 이탈하지 않는 범위내에서 다양한 변경이 가능하다.On the other hand, the multi-functional soft ground reinforcement factory factory according to an embodiment of the present invention is not limited to the above embodiments, but various modifications can be made without departing from the technical gist of the invention.

상기한 바와 같이, 본 발명에 따른 다기능 연약지반 보강 시공장치는 종래 복수개의 장치를 통하여 운용되어져 왔던 것을 단일의 장치에 구성함으로서, 각각의 공정에 따라 해당 장치가 신속하게 슬라이딩되어 작업위치에 위치되게 함으로써 천공작업과, 시멘트 밀크의 고압분사 작업이 신속하게 이루어지게 되므로 몇 개의 장치 이동에 따른 시공시간을 감소시키고, 천공장치나 고압분사 장치 등의 별도 비용을 효과적으로 감소시킬 수 있는 효과를 제공하게 된다.As described above, the multi-functional soft ground reinforcement factory according to the present invention is configured by a single device that has been operated through a plurality of devices in the prior art, so that the device is quickly slid according to each process to be located in the working position As a result, the drilling work and the high-pressure spraying work of cement milk are performed quickly, thus reducing the construction time due to the movement of several devices and effectively reducing the separate costs of the drilling device and the high-pressure spraying device. .

Claims (2)

타격력 및 회전력을 부여하는 탑 해머와; 그 탑 해머의 전단에 체결되어 회전되면서 에어와 물을 전단에 공급하는 슈벨과; 슈벨의 외부에 결합된 슈벨 케이스와; 슈벨 전단 외주연에 그 일단이 체결되는 어댑터와; 어댑터의 타단에 체결되는 케이싱과; 케이싱의 내부에 위치되고 그 내부 일단이 슈벨의 전단 내주연과 체결되는 로드로 구성된 천공장치와, 시멘트 밀크를 제트압으로 공급하기 위한 로타리장치에 있어서, A tower hammer for imparting hitting force and rotational force; A shovel which is coupled to the front end of the tower hammer and rotates to supply air and water to the front end; A shovel case coupled to the outside of the shovel; An adapter whose one end is fastened to the outer periphery of the shvel shear; A casing fastened to the other end of the adapter; In the perforation device consisting of a rod which is located inside the casing and one end thereof is engaged with the shear inner circumference of the shovel, and a rotary device for supplying cement milk at jet pressure, 상기 천공장치와 그 전단에 로드 고정장치(=척)가 구성된 로타리장치를 각각 병렬로 그 상면에 안착하여 상기 천공장치의 케이싱과 수직되게 구성된 이동패널과; 상기 이동패널의 하부에 구성되며, 그 상면에 상기 이동패널이 슬라이딩되는 레일이 구비되어져 있으며, 내부 바닥면에 결합되고, 그 축이 상기 이동패널에 결합되어 슬라이딩을 위한 유출 압력을 제공하는 유압실린더가 구비된 지지패널로 구성된 것을 특징으로 하는 다기능 연약지반 보강 시공장치.A moving panel configured to be mounted perpendicularly to the casing of the drilling device by mounting the drilling device and a rotary device having a rod fixing device (= chuck) at the front end thereof in parallel on the upper surface thereof; A hydraulic cylinder is provided in the lower portion of the moving panel, the upper surface is provided with a rail for sliding the moving panel, coupled to the inner bottom surface, the shaft is coupled to the moving panel to provide an outflow pressure for sliding. Multifunctional soft ground reinforcement construction device characterized in that consisting of a support panel provided. 삭제delete
KR1020040017353A 2004-03-15 2004-03-15 Multi-drilling and infusion apparatus for reinforcing a tenderness ground KR100628485B1 (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
KR1020040017353A KR100628485B1 (en) 2004-03-15 2004-03-15 Multi-drilling and infusion apparatus for reinforcing a tenderness ground

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
KR1020040017353A KR100628485B1 (en) 2004-03-15 2004-03-15 Multi-drilling and infusion apparatus for reinforcing a tenderness ground

Publications (2)

Publication Number Publication Date
KR20040034630A KR20040034630A (en) 2004-04-28
KR100628485B1 true KR100628485B1 (en) 2006-09-26

Family

ID=37333715

Family Applications (1)

Application Number Title Priority Date Filing Date
KR1020040017353A KR100628485B1 (en) 2004-03-15 2004-03-15 Multi-drilling and infusion apparatus for reinforcing a tenderness ground

Country Status (1)

Country Link
KR (1) KR100628485B1 (en)

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
KR102319224B1 (en) 2021-03-31 2021-10-29 새암개발 주식회사 Ground restoration method for the subsidence section of the railway

Families Citing this family (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
KR100974527B1 (en) * 2007-04-27 2010-08-10 김태정 A drilling device which have a dust removing function

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
KR102319224B1 (en) 2021-03-31 2021-10-29 새암개발 주식회사 Ground restoration method for the subsidence section of the railway

Also Published As

Publication number Publication date
KR20040034630A (en) 2004-04-28

Similar Documents

Publication Publication Date Title
JP4282022B2 (en) Drain pipe burial method and structures, etc. to prevent tilting, sinking or floating
US6109836A (en) Soil consolidation apparatus, tool and method
CN111140239B (en) Tunnel inverted arch non-explosive excavation method
KR100949606B1 (en) Hole-boring and hammering-vibration working method and device for integrated construction with sheet-pile fixed to outside of hole-boring auger casing
CN110529047A (en) A kind of self-advancing type pipe canopy drilling tool excavated for tunnel soft rock
US20080127528A1 (en) Earth auger head and excavation method
KR100628485B1 (en) Multi-drilling and infusion apparatus for reinforcing a tenderness ground
CN109026095A (en) Bolthole construction technology
CN112942477B (en) Rapid crushing tool for steel pipe pile encountering boulder and construction method
KR20120034432A (en) Grouting apparatus for direct-boring and grouting method using that
JP2009287326A (en) Pulling out method of existing pile
JP2014077286A (en) Pipe implantation device and pipe implantation method
KR20130027763A (en) Hammer bit structure for air circulation
KR100804751B1 (en) A self supported type ground drilling machine and its drilling method
KR20180045950A (en) Reforcement system and reforcement method thereof
JPH11172667A (en) High-pressure injection ground-improvement method
JP3528986B2 (en) Fore pile construction method
JP5700985B2 (en) Rock bolt forming method and drilling device
JP6719638B1 (en) Ground improvement device using top drive type boring machine
JP4781195B2 (en) Driving method for driving material and driving material for preceding excavation
JP2004332247A (en) Chemical grouting method for reinforcing natural ground and its rock drill
JP5250729B2 (en) Underground consolidated body construction method and underground solid body creation device for creating a solid body using the method
EP0437262B2 (en) Method for preventive consolidation of the soil for underground minings
KR102225882B1 (en) Double casing and compaction grouting method using the same
KR20030069922A (en) Method for grouting and drilling nail and anchor

Legal Events

Date Code Title Description
A201 Request for examination
E902 Notification of reason for refusal
E701 Decision to grant or registration of patent right
GRNT Written decision to grant
FPAY Annual fee payment

Payment date: 20120917

Year of fee payment: 7

FPAY Annual fee payment

Payment date: 20130917

Year of fee payment: 8

FPAY Annual fee payment

Payment date: 20141015

Year of fee payment: 9

FPAY Annual fee payment

Payment date: 20150917

Year of fee payment: 10

FPAY Annual fee payment

Payment date: 20161017

Year of fee payment: 11

FPAY Annual fee payment

Payment date: 20171017

Year of fee payment: 12

LAPS Lapse due to unpaid annual fee