JPS6114300B2 - - Google Patents

Info

Publication number
JPS6114300B2
JPS6114300B2 JP149881A JP149881A JPS6114300B2 JP S6114300 B2 JPS6114300 B2 JP S6114300B2 JP 149881 A JP149881 A JP 149881A JP 149881 A JP149881 A JP 149881A JP S6114300 B2 JPS6114300 B2 JP S6114300B2
Authority
JP
Japan
Prior art keywords
unit
steel
traveling
reaction
rail
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Expired
Application number
JP149881A
Other languages
Japanese (ja)
Other versions
JPS57116847A (en
Inventor
Masao Myaguchi
Yoshihiro Ishikawa
Hirohisa Kondo
Masahito Hirai
Yasuo Kaihara
Tokuo Yamamoto
Tsutomu Fumoto
Junro Aida
Toshio Araki
Yasuo Sugibayashi
Yukitaka Furukawa
Kazuyoshi Matsuda
Kozo Yamamoto
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Takenaka Komuten Co Ltd
Original Assignee
Takenaka Komuten Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Takenaka Komuten Co Ltd filed Critical Takenaka Komuten Co Ltd
Priority to JP149881A priority Critical patent/JPS57116847A/en
Publication of JPS57116847A publication Critical patent/JPS57116847A/en
Publication of JPS6114300B2 publication Critical patent/JPS6114300B2/ja
Granted legal-status Critical Current

Links

Landscapes

  • Conveying And Assembling Of Building Elements In Situ (AREA)

Description

【発明の詳細な説明】 本発明は、例えば体育館等大空間の鉄骨造屋根
を架構するのに適用される鉄骨トラス・トラベリ
ング工法に関する。
DETAILED DESCRIPTION OF THE INVENTION The present invention relates to a steel truss traveling construction method that is applied to constructing a steel roof of a large space such as a gymnasium.

従来、上述鉄骨造屋根を架構する為の工法とし
ては、大型クレーンを建物内部に入場させ、屋根
下全面に大掛りな仮設支保工と、作業足場を組立
て、該作業足場上で鉄骨組立を行なう工法と、予
め鉄骨を地組し、これを吊り上げ、又は押し上げ
て架構するところのリフトアツプ・ブツシユアツ
プ工法が知られている。
Conventionally, the construction method for constructing the above-mentioned steel roof is to bring a large crane into the building, erect large-scale temporary support and work scaffolding under the roof, and then assemble the steel frame on the work scaffold. The lift-up and push-up construction methods are known, in which steel frames are assembled in advance on the ground and then hoisted or pushed up to construct the frame.

しかし、前者によると、クレーン及び足場除去
后はコンクリート打ちが不可欠となるからアリー
ナ床にダメ工事ができると共に、大空間を足場組
みすることは経費が膨大となるだけではなく、そ
の組立、解体に要する労力、時間も膨大なものと
なり、為に、工期が著しく長びき、かつ、コスト
高となる欠点がある。
However, according to the former, concrete pouring is essential after the crane and scaffolding is removed, which can damage the arena floor, and erecting scaffolding in a large space not only incurs enormous costs, but also involves the assembly and dismantling of the scaffolding. The amount of labor and time required is enormous, resulting in an extremely long construction period and high costs.

又、後者によると、トラスが非立体である場
合、又体育館のようにギヤラリーが迫り出した建
物である場合、更に躯体が鉄骨の柱ではなくRC
柱である場合では、アリーナ床上での鉄骨地組が
困難であり、又、鉄骨支持の反力点を確保し難い
点で、当該工法は採用し得ない場合もある。
Also, according to the latter, if the truss is not three-dimensional, or if it is a building with a protruding gear rally like a gymnasium, the frame is not made of steel columns but RC.
In the case of columns, it is difficult to assemble the steel frame on the arena floor, and it is also difficult to secure a reaction force point for supporting the steel frame, so this construction method may not be possible.

又、従来上述工法の難点に鑑みてなされたもの
として、大空間の鉄骨造屋根を架構する体育館等
では、建物周囲の敷地が十分利用できる場合がほ
とんどであること、従来工法に比べて1個所で組
立てて送り出すところのベルトコンベアー方式の
流れ作業は精度、安全性共に高いこと、本設の鉄
骨トラスの原設計を僅かな変更だけで施工可能で
あること、仮設費が少なくてすむこと等の観点か
ら、これらの利用を活用し得る鉄骨トラス・トラ
ベリング工法は本願人において開発され、すでに
特許出願されている。
In addition, this was done in view of the drawbacks of the conventional construction methods mentioned above.In most cases, such as gymnasiums with large steel roofs, the grounds around the building can be fully utilized; The belt conveyor assembly process for assembly and delivery is highly accurate and safe, the construction can be completed with only slight changes to the original design of the steel truss, and temporary construction costs are low. From this perspective, the applicant has developed a steel truss traveling construction method that can take advantage of these uses, and a patent application has already been filed.

即ち、かゝる工法は、建物外部からのクレーン
の能力範囲である大空間の片側を鉄骨組立ゾーン
とし、屋根鉄骨トラスの1ユニツトを組立て、こ
れに牽引用のセンターホール型ジヤツキ及びロー
ラを取付け、予め桁方向の梁上に設置したレール
に乗せて1ユニツト巾だけスライドさせ、その
后、空いた鉄骨組立ゾーンで次の1ユニツトを組
立てて上記ユニツトに継ぎ足し、順次スライド、
ユニツト組立て継ぎ足しを行つて大空間鉄骨造屋
根を架構するものであるから、前述の従来工法に
比較して仮設足場の縮少、工費の節減、定位置同
一作業の繰返しによる安全性及び施工精度の向
上、工期短縮等を計り得る点で十分に効果的であ
るといえる。
In other words, this method involves setting one side of a large space within the capacity of a crane from outside the building as a steel frame assembly zone, assembling one unit of the roof steel frame truss, and attaching a center hole type jack and roller for traction to this unit. , put it on the rail installed in advance on the beam in the direction of the girder and slide it by one unit width, then assemble the next unit in the empty steel frame assembly zone and add it to the above unit, slide it in order,
Since a large space steel roof is constructed by assembling and adding units, compared to the conventional construction method mentioned above, it reduces the need for temporary scaffolding, reduces construction costs, and improves safety and construction accuracy by repeating work in the same position. It can be said that it is sufficiently effective in terms of improvement and shortening of construction period.

しかし、かゝる工法においても、ユニツト移動
用装置にクライミングジヤツキを使用する為、そ
の固定方法及びロツドの架設と、その反力補強工
事のコスト上の問題点と、上記ユニツトは下部に
車輪を取り付けてレール上を“機関車スタイル”
で移動させる為、牽引し終えた点で、全ユニツト
を同時にジヤツキアツプし、レールと車輪を除去
した後、下降して固定する必要があり、ユニツト
の定着作業が煩雑となる問題点がある。
However, even in such a construction method, since a climbing jack is used as a device for moving the unit, there are problems with the fixing method, the erection of the rod, and the cost of reinforcing the reaction force. Attach the “locomotive style” on the rails.
In order to move the units, it is necessary to jack up all the units at the same time after towing, remove the rails and wheels, and then lower and fix them, which poses the problem of complicating the work of fixing the units.

そこで本発明は上述鉄骨トラス・トラベリング
工法の問題点に鑑みて検討の結果、建物外部から
のクレーンの能力範囲である大空間の片側を鉄骨
組立ゾーンとし、屋根鉄骨トラスの1ユニツトを
載置し、このユニツトに複動ジヤツキに治具を備
えたトラベリング牽引装置及び円筒形移動用シユ
ーを取付け、予め桁方向の梁上に並設した走行レ
ール及び反力レールの内、該反力レールに反力を
とり、上記走行レールに係嵌して2ユニツト巾だ
けスライドさせ、次に空いた空間に第2のユニツ
トを載置させ、両ユニツトを鉄骨部材で連結し
て、合計3ユニツトを組立て、再び2ユニツト巾
をスライドさせて、以下順次同じ方法で進め、鉄
骨トラスを架設し、然る后上記移動用シユーを走
行レールに回転可能に、かつ軸方向の移動を阻止
して固定するようにしたことを要旨とするもの
で、スライド終了后、そのまゝ固定できて、かつ
ピン支承することができ、もつて、更に工費の節
減、安全性及び施工精度の向上、工期短縮を計り
得ることを目的とするものである。
Therefore, as a result of studies in view of the above-mentioned problems with the steel truss traveling construction method, the present invention has been developed by setting one side of a large space within the capacity range of a crane from outside the building as a steel frame assembly zone, and placing one unit of the roof steel truss. A traveling traction device with a jig and a cylindrical moving shoe are attached to this unit, and a traveling rail and a reaction rail are installed in parallel on the beam in the girder direction. Using force, engage the above-mentioned traveling rail and slide it by two unit widths, then place the second unit in the empty space, connect both units with a steel member, and assemble a total of three units. Slide the 2 unit width again and proceed in the same manner sequentially to erect the steel truss, and then fix the moving shoe to the traveling rail so that it can rotate and prevent axial movement. The main idea is that after the slide is completed, it can be fixed as it is and can be supported by a pin, which can further reduce construction costs, improve safety and construction accuracy, and shorten construction time. The purpose is to

以下、本発明工法を、一実施例を示した図面に
基いて施工順に詳述する。
Hereinafter, the construction method of the present invention will be explained in detail in the construction order based on drawings showing one embodiment.

先ず本発明工法で架構される大空間の鉄骨造屋
根Aは第1図のブロツク割図で示すようにX方向
へ1スパンづつ12ブロツクに仮分けし、1ブロツ
クを1ユニツトとして組立てられ、これを第2図
のスライドフローチヤート○イ〜○ヘの順にスライド
し、鉄骨造屋根Aを架構する。
First, the steel frame roof A of a large space to be constructed using the construction method of the present invention is temporarily divided into 12 blocks of 1 span each in the X direction as shown in the block diagram in Figure 1, and each block is assembled as one unit. 2 in the order of slide flowchart ○I to ○ to construct the steel roof A.

即ち、第3図ないし第5図に示したように、予
め施工された鉄筋コンクリート造の躯体Bの一側
妻側上端部に地組みした鉄骨トラスのユニツト1
を載置可能に、かつトラス組立可能に躯体Bの一
側部におけるギヤラリー2の足場3を組立て、該
足場3上に、地組した1ユニツト1及び鉄骨部材
4……を躯体B外側に設置したクレーン(図示省
略)により吊り上げて載置し、更に載置したユニ
ツト1,1相互を鉄骨部材4……で連結する。
That is, as shown in FIGS. 3 to 5, a steel truss unit 1 is assembled into the ground at the upper end of one gable side of the reinforced concrete frame B, which has been constructed in advance.
A scaffold 3 for the gear rally 2 is assembled on one side of the frame B so that the equipment can be placed thereon and a truss can be assembled, and on the scaffold 3, the assembled unit 1 and the steel frame members 4... are installed on the outside of the frame B. The units 1, 1 placed thereon are then lifted up and placed by a crane (not shown), and the placed units 1, 1 are connected to each other by steel members 4...

この際、上記ユニツト1の吊り上げ載置に先だ
つて、梁5,5の桁方向へ第6図,第7図に示し
たように溝形鋼からなる走行レール6と、該走行
レール6の左右両側に、長さ方向へ定間隔に多数
の反力ピン7……を突設してあるL形鋼等の反力
レール8,8が並設される。こゝで、上記走行レ
ール6及び反力レール8は、第7図に示したよう
に、梁5がH鋼からなる時は、当該梁5上に溶接
により、又梁5が第12図に示したように鉄骨コ
ンクリート造の時は、当該梁5の上面へ施工時に
植設した沓アンカーボルト9により敷設固定した
沓ベースプレート10上へ固定して敷設される。
At this time, prior to lifting and placing the unit 1, as shown in FIGS. 6 and 7, the running rail 6 made of channel steel and the right and left On both sides, reaction rails 8, 8 made of L-shaped steel or the like are arranged in parallel, each having a large number of reaction pins 7 protruding from each other at regular intervals in the length direction. Here, as shown in FIG. 7, when the beam 5 is made of H steel, the traveling rail 6 and the reaction rail 8 are welded onto the beam 5, or the beam 5 is made of H steel as shown in FIG. As shown, in the case of steel frame concrete construction, the foot is fixed on the foot base plate 10 which is laid and fixed by foot anchor bolts 9 planted on the upper surface of the beam 5 at the time of construction.

又、上記ユニツト1は、第8図〜に明示し
たように6つの部分b1〜b6に分け、X2トラスの第
1部分、X3トラスの第1部分、第1部分の継ぎ
材11、X2、X3のサブトラス12の第1部分、
上下弦フレーム材13等で形成される。又、X2
トラスの第2部分b2、X3トラスの第2部分以下
上記同様にして第3〜第6部分まで組合せて1ユ
ニツト1のトラスは形成される。
The unit 1 is divided into six parts b 1 to b 6 as clearly shown in FIGS. , the first part of the subtruss 12 of X 2 , X 3 ,
It is formed of upper and lower chord frame materials 13 and the like. Also, X 2
Second part of truss b 2 , X 3 The second part of truss and the third to sixth parts are combined in the same manner as described above to form one unit 1 of truss.

上記ユニツト1は地上にて予め組合せ形成され
るもので、該ユニツト1の下端には第7図に示し
たように円筒形の移動用シユー14……を取付け
た后、クレーンにより躯体Bの妻側上端部に吊り
上げて載置し、予め梁5上に敷設しておいた走行
レール6に係嵌する。
The unit 1 is assembled in advance on the ground, and after attaching a cylindrical moving shoe 14 to the lower end of the unit 1 as shown in FIG. It is lifted up and placed on the upper end of the side, and is engaged with the traveling rail 6 that has been laid on the beam 5 in advance.

こゝで、上記移動用シユー14は、上記走行レ
ール6内にスライド自在に係嵌可能な直径を有す
る円筒形の鋼棒14aと、該鋼棒14aの少なく
とも外周の下半分以上に第12図が示した如くテ
フロン等の滑り材14bを貼着して形成されてお
り、上述ユニツト1の巾方向に向けて溶着固定さ
れる。
Here, the moving shoe 14 includes a cylindrical steel rod 14a having a diameter that can be slidably fitted into the traveling rail 6, and a cylindrical steel rod 14a having a diameter that can be slidably fitted into the traveling rail 6, and a portion of at least the lower half of the outer circumference of the steel rod 14a as shown in FIG. As shown, it is formed by pasting a sliding material 14b such as Teflon, and is welded and fixed in the width direction of the unit 1 described above.

かくして、上記ユニツト1は、クレーンにより
躯体Bの一側妻側上端部に載置して、上記移動用
シユー14を梁5上の走行レール6に係嵌すれ
ば、当該走行レール6の長さ方向へ横移動自在に
なる訳である。
Thus, when the unit 1 is placed on the upper end of one end of the frame B by a crane and the moving shoe 14 is engaged with the running rail 6 on the beam 5, the length of the running rail 6 is fixed. This means that it can move laterally in any direction.

又、移動用シユー14は、ユニツト1の少なく
とも長さ方向の両端部における巾方向前後両端に
合計4個は固定しておく必要がある。
Further, a total of four moving shoes 14 must be fixed to at least both longitudinal ends of the unit 1 and both front and rear ends in the width direction.

上述のように移動用シユー14……を走行レー
ル6に係嵌したならば、ユニツト1の長さ方向に
おける両端の巾方向両前部に、トラベリング牽引
装置15,15を夫々連結する。
Once the moving shoes 14 are engaged with the traveling rails 6 as described above, the traveling traction devices 15, 15 are connected to both front portions of the unit 1 in the width direction at both ends thereof in the length direction.

こゝに用いられる上記トラベリング牽引装置1
5は、複動ジヤツキ15aと、これの出力軸15
b先端に枢着される治具15cとから形成されて
いる。即ち、上記治具15cは、第7図に明示し
た如く、左右2枚の側板15c′,15c′を継ぎ材
15c″で連結一体化し、上記両側板15c′,15
c′の先端から後方へ傾斜下降する傾斜面15c
と、上記反力ピン7との係合部15c〓とを備え
て形成されていて、上記走行レール6を含む、左
右の反力レール8,8上にスライド自在に跨設し
て上記係合部15c〓は反力ピン7を係合し、出
力軸15bを後退動作することで、上記反力ピン
7に反力をとつて、ユニツト1をスライドし、又
上記出力軸15bを前進させることで治具15c
は前進することにより反力ピン7との係合は外れ
ると共に、順位の反力ピン7と上記傾斜面15c
が突き当つて、当該治具15cは、出力軸15
bと枢着ピン15dを支点として上方へ回動し、
上記反力ピン7を乗り越え、次に出力軸15bが
後退動作に切り換えられる時、係合部15c〓と
反力ピン7が係合し、以下上述と同様にしてユニ
ツト1をスライドするようになつている。
The above traveling traction device 1 used here
5 is a double acting jack 15a and its output shaft 15
b and a jig 15c pivotally attached to the tip. That is, as clearly shown in FIG. 7, the jig 15c has two left and right side plates 15c', 15c' connected together with a joint material 15c'', and the two side plates 15c', 15c'
Inclined surface 15c that slopes downward from the tip of c' to the rear.
and an engaging portion 15c for engaging the reaction force pin 7. The portion 15c engages the reaction pin 7 and moves the output shaft 15b backward, thereby applying a reaction force to the reaction pin 7 to slide the unit 1 and move the output shaft 15b forward. jig 15c
By moving forward, the engagement with the reaction force pin 7 is disengaged, and the reaction force pin 7 of the order and the above-mentioned inclined surface 15c are disengaged.
When the jig 15c hits the output shaft 15, the jig 15c
b and pivot pin 15d as supporting points,
When the output shaft 15b is switched over the reaction pin 7 and then switched to the backward movement, the engaging portion 15c and the reaction pin 7 engage, and the unit 1 is then slid in the same manner as described above. ing.

つまり、このトラベリング牽引装置15は、し
やくとり虫方式に出力軸15bが複動し、上記反
力レール8,8の反力ピン7に反力をとつてユニ
ツト1をスライド動作する。
That is, in this traveling traction device 15, the output shaft 15b double-moves in a slow-moving manner, and the unit 1 is slid by applying a reaction force to the reaction pins 7 of the reaction rails 8, 8.

次に、作業手順を第9図に基いて説明する。 Next, the working procedure will be explained based on FIG. 9.

尚こゝで、上述ユニツト1の符号は、以下に説
明する施工順位で1a,1b,1c……とする。
Here, the above-mentioned units 1 are designated as 1a, 1b, 1c, . . . in the construction order explained below.

先ず、上述のように地組みした第1のユニツト
1aを妻側上端部に載置し、走行レール6に移動
用シユー14……を係嵌し、前部にトラベリング
牽引装置15を連結して反力ピン7に治具15c
を係合させる。そして、トラベリング牽引装置1
5により第1のユニツト1aを、同図○イから○ロに
示したように2ユニツト巾だけスライドする。
First, the first unit 1a assembled on the ground as described above is placed on the upper end of the gable side, the moving shoe 14 is engaged with the traveling rail 6, and the traveling traction device 15 is connected to the front part. Jig 15c on reaction pin 7
engage. And traveling traction device 1
5, slide the first unit 1a by two unit widths as shown from ○A to ○B in the same figure.

次に、空いた空間の妻側上端部に第2のユニツ
ト1cを載置する。この状態では同図○ロに示した
ように、第1,第2の両ユニツト1a,1c間
に、1ユニツト巾の空間が形成されるので、上記
第1,第2の両ユニツト1a,1cを足場3で鉄
骨部材4により連結して、1ユニツト1bを形成
し、合計3ユニツトを組立てる。そして、上記ト
ラベリング牽引装置15により、上記3ユニツ
ト、つまり1a,1b,1cを同図○ハに示すよう
に2ユニツト巾だけスライドする。
Next, the second unit 1c is placed on the upper end of the empty space on the gable side. In this state, as shown in the same figure, a space of one unit width is formed between the first and second units 1a and 1c. are connected by a steel frame member 4 on a scaffold 3 to form one unit 1b, and a total of three units are assembled. Then, the traveling traction device 15 slides the three units, ie, 1a, 1b, and 1c, by a width of two units as shown in ○C in the figure.

更に、空いた空間の妻側上端部に第3のユニツ
ト1eを載置し、該ユニツト1eと、上記第2の
ユニツト1cを鉄骨部材4により連結してユニツ
ト1dを形成して、合5ユニツトを組立てる。
Furthermore, a third unit 1e is placed on the upper end of the empty space on the gable side, and this unit 1e and the second unit 1c are connected by a steel member 4 to form a unit 1d, making a total of 5 units. Assemble.

そして、更に2ユニツト巾だけスライドし、以
下上述と同様の順番に連結し、スライドさせて、
同○ニ,○ホに示したようにユニツトを1a〜1ま
でを組立てる。
Then, slide it further by 2 units width, connect and slide it in the same order as above,
Assemble the units 1a to 1 as shown in ○D and ○E.

このようにしてユニツトの組立てを終了したな
らば、各ユニツト1a〜1の移動用シユー14
……を、第10図ないし第12図に示したよう
に、内側面を弧面16aに形成してある鉄板1
6,16を梁5上に溶着して断面方向よりはさみ
込むようにして回転可能に固定すると共に、側面
方向、つまり、移動シユー14の長さ方向には、
第11図に示したように、走行レール6内に鉄板
17,17を溶着時に固定して移動用シユー14
を前後方向へ移動しないように固定する。
After completing the assembly of the units in this way, the moving shoes 14 of each unit 1a to 1 are assembled.
..., as shown in FIGS. 10 to 12, an iron plate 1 whose inner surface is formed into an arc surface 16a.
6 and 16 are welded onto the beam 5 and are rotatably fixed by sandwiching them from the cross-sectional direction, and in the lateral direction, that is, the length direction of the moving shoe 14,
As shown in FIG. 11, the iron plates 17, 17 are fixed in the traveling rail 6 at the time of welding, and the moving shoe 14 is fixed.
Fix it so that it does not move forward or backward.

こゝで、上記移動用シユー14を回転可動に支
持するので、大規模構造物の柱脚としてのピン支
承となつて、構造物としての力学的特性を満足さ
せることができる。
Since the movable shoe 14 is rotatably supported, it can serve as a pin support as a column base of a large-scale structure and satisfy the mechanical characteristics of the structure.

又、上述のように固定した後、梁5上に第13
図が示すようにコンクリート、又はモルタル18
を打設して走行レール6を両側から埋設させ、躯
体Bとの連結強度を高めるようにするとよい。
Also, after fixing as described above, the 13th
Concrete or mortar 18 as shown in the diagram
It is preferable that the running rails 6 be buried from both sides by pouring them to increase the connection strength with the frame B.

更に、上記移動用シユー14の円滑なスライド
及び固定後の円滑な回転を考慮して、上記走行レ
ール6の底面にも第12図,第13図に示したよ
うに、テフロン等の滑り材18を敷設するように
するとよい。
Furthermore, in consideration of smooth sliding of the moving shoe 14 and smooth rotation after fixation, a sliding material 18 such as Teflon is also provided on the bottom surface of the traveling rail 6, as shown in FIGS. 12 and 13. It is recommended that you install the

その后は、第1図,第2図○ヘ第9図○ホに示すX
に通りの妻壁、続いて軒下壁のコンクリート打ち
を施工して、大空間の鉄骨造屋根Aは架構され
る。
After that, the
The gable wall of the street and then the wall under the eaves will be concreted, and the steel frame roof A of the large space will be constructed.

このようにして鉄骨屋根完了后は、従来と同様
な工法により屋根材を施工する。
After the steel roof is completed in this way, the roofing material is constructed using the same construction method as before.

以上説明したように本発明に係る鉄骨トラス・
トラベリング工法によれば、大空間の鉄骨造屋根
Aを架構するに際し、地組みして、移動用シユー
14……を取付けたユニツト1……をクレーン等
で吊り上げて躯体一側の妻側上端部に載置し、こ
れを予め桁方向の梁5,5上に敷設した走行レー
ル6,6に移動用シユー14……を係嵌し、上記
走行レール6と共に梁5,5上に並設した反力ピ
ン7付き反力レール8に反力をとつて、ユニツト
1前部に連結したトラベリング牽引装置15によ
りスライドされ、これと、次に載置したユニツト
を妻側のみに組立てた足場3上で鉄骨部材4……
で連結してユニツトを組立てし、順次2ユニツト
巾だけスライドさせながら、上記と同様に連結し
て鉄骨屋根Aを架構するものであるから、従来例
に比べて仮設支保工、足場を大巾に節減すること
ができ、かつアリーナ床にクレーン及び足場あと
のダメ工事を残すこともないから大巾に工費節減
と工期短縮を計ることができることは勿論のこ
と、特に本発明による時は、構造物の柱脚として
の支承ピンを移動用シユー14としているので、
車輪が不要となり、従つて、ユニツトスライド
後、車輪及びレールの除去作業を省略できて、ス
ライド完了時点で架構全ユニツトをアツプ・ダウ
ンさせる必要なく、そのまゝの位置で固定できる
ので定着作業が容易となり、又、移動用シユー1
4は円筒形であるので、走行レール6との接触面
積が少なく滑動に有利であるから安全性及び移動
精度(施工精度)を従来のこの種工法に比べて格
段に向上でき、更に反力をとる為のロツド及び反
力補強工事が不用となるので、移動架構の省力化
とコストダウンを計り得る等特筆すべき利点があ
る。
As explained above, the steel truss according to the present invention
According to the traveling construction method, when constructing a steel frame roof A in a large space, the unit 1 with the mobile shoe 14 attached is assembled on the ground and lifted up with a crane or the like, and the upper end of the gable side of one side of the frame is lifted. This was placed on the traveling rails 6, 6 that had been laid in advance on the beams 5, 5 in the girder direction, and the moving shoes 14 were engaged with them, and they were placed in parallel on the beams 5, 5 together with the traveling rails 6. The reaction force is absorbed by the reaction rail 8 with the reaction pin 7, and the unit 1 is slid by the traveling traction device 15 connected to the front part of the unit 1, and this and the next unit placed thereon are assembled on the scaffold 3 only on the gable side. Steel frame member 4...
Since the units are assembled by connecting them with each other, and the steel roof A is constructed by connecting them in the same way as above by sliding two unit widths one after another, the temporary shoring and scaffolding can be made wider than in the conventional example. In addition, since there is no need to leave unsatisfactory construction work behind the crane and scaffolding on the arena floor, it goes without saying that it is possible to significantly reduce construction costs and shorten the construction period. Especially when using the present invention, it is possible to Since the support pin as the column base is used as the moving shoe 14,
Wheels are no longer required, so the work of removing wheels and rails after sliding the unit can be omitted, and once sliding is complete, all units in the frame can be fixed in the same position without the need to raise or lower them, thereby reducing fixing work. It is easy to use, and it also makes it easier to move the shoe 1.
4 has a cylindrical shape, so the contact area with the running rail 6 is small and it is advantageous for sliding, so safety and movement accuracy (construction accuracy) can be significantly improved compared to conventional construction methods of this type, and the reaction force can be further reduced. Since there is no need for rods and reaction force reinforcement work, there are notable advantages such as the ability to save labor and reduce costs for the moving frame.

従つて、本発明工法によれば、鉄骨造屋根を経
済的、かつ高精度に架構することができる。
Therefore, according to the construction method of the present invention, a steel frame roof can be constructed economically and with high precision.

【図面の簡単な説明】[Brief explanation of the drawing]

第1図は本発明工法に係る鉄骨造屋根のブロツ
ク割図、第2図○イ〜○ヘは同工法における各ユニツ
トのスライドフローチヤート、第3図は同工法の
ユニツト連結用足場を示す正面図、第4図は同足
場の平面図、第5図は同工法の足場と鉄骨トラス
ユニツトのスライド及び連結状態を示す側面図、
第6図は同工法のユニツトスライド状態を示す側
面図、第7図は同工法に係る走行レール、反力レ
ール及びトラベリング牽引装置を示す斜視図、第
8図ないしは同工法の鉄骨トラスユニツトの
組立部材順位を順番に示した一例の線図、第9図
○イ〜○ホは同工法の鉄骨トラス各ユニツトの移動要
領図、第10図,第11図は同工法に係る移動用
シユーの固定状態を夫々示した正面図と側面図、
第12図は同工法の移動用シユーの固定部を示し
た拡大正面図、第13図は同工法の移動用シユー
の回転状態と、走行レールの補強状態を夫々示し
た横断正面図である。 A……鉄骨造屋根、B……躯体、1,1a〜1
……鉄骨トラスの1ユニツト、3……足場、4
……鉄骨部材、5……梁、6……走行レール、7
……反力ピン、8……反力レール、14……移動
用シユー、15……トラベリング牽引装置、15
a……複動ジヤツキ、15c……治具。
Figure 1 is a block diagram of a steel roof constructed using the construction method of the present invention, Figure 2 ○A to ○ are slide flowcharts of each unit in the construction method, and Figure 3 is a front view showing the scaffolding for connecting units in the construction method. Figure 4 is a plan view of the same scaffolding, and Figure 5 is a side view showing the sliding and connected state of the scaffolding and steel truss unit of the same construction method.
Figure 6 is a side view showing the sliding state of the unit in the same method, Figure 7 is a perspective view showing the traveling rail, reaction rail, and traveling traction device in the same method, and Figure 8 or assembly of the steel truss unit in the same method. An example of a line diagram showing the order of components in order, Figure 9 ○I to ○H are movement procedure diagrams for each unit of the steel truss using the same construction method, and Figures 10 and 11 are fixing of the movable shoes according to the same construction method. Front view and side view showing each condition,
FIG. 12 is an enlarged front view showing the fixed part of the movable shoe of the same method, and FIG. 13 is a cross-sectional front view showing the rotating state of the movable shoe of the same method and the reinforced state of the running rail. A...Steel frame roof, B...Structure, 1, 1a~1
...1 unit of steel truss, 3...Scaffolding, 4
... Steel frame member, 5 ... Beam, 6 ... Traveling rail, 7
... Reaction force pin, 8 ... Reaction force rail, 14 ... Moving shoe, 15 ... Traveling traction device, 15
a...Double acting jack, 15c...Jig.

Claims (1)

【特許請求の範囲】[Claims] 1 大空間の鉄骨造屋根を架構するに際し、予め
施工した躯体の桁方向の梁上に溝形鋼等からなる
走行レールと、複数個の反力ピンを定間隔に突設
した反力レールとを並設しておき、予め地組した
鉄骨トラスの1ユニツトを躯体一側の妻側上端部
に載置し、このユニツトには、上記走行レールに
係嵌する円筒形の移動用シユーと、複動ジヤツキ
に上記反力ピンと係脱自在な治具を備えたトラベ
リング牽引装置を取付け、このトラベリング牽引
装置により上記反力レールに反力をとつて1ユニ
ツトを2ユニツト巾だけスライドさせ、次に空い
た妻側上端部に第2のユニツトを載置させ、両ユ
ニツト鉄骨部材で連結して合計3ユニツトを組立
て、その后これらを2ユニツト巾だけスライドさ
せ、以下ユニツト載置と、前置ユニツトとの鉄骨
部材による連結と、2ユニツト巾のスライドを順
番に繰返して鉄骨トラスを架設し、然る后、上記
移動用シユーを走行レールに回転可能に、かつ軸
方向の移動を阻止して固定することを特徴とする
鉄骨トラス・トラベリング工法。
1. When constructing a steel frame roof in a large space, a traveling rail made of channel steel, etc. is placed on the girder direction beam of the frame that has been constructed in advance, and a reaction rail with a plurality of reaction pins protruding at regular intervals is used. are placed side by side, and one unit of steel truss assembled in advance is placed on the upper end of the gable side of one side of the frame, and this unit includes a cylindrical moving shoe that engages with the traveling rail, A traveling traction device equipped with a jig that can be freely engaged and detached from the reaction pin is attached to the double-acting jack, and the traveling traction device applies a reaction force to the reaction rail to slide one unit by the width of two units, and then Place the second unit on the empty upper end of the gable side and connect both units with a steel frame member to assemble a total of 3 units.After that, slide these by 2 unit widths, and then proceed with placing the unit and installing the front unit. A steel frame truss is constructed by repeating the connection with the steel frame member and the slide of two unit width in order, and then fixes the above-mentioned movable shoe to the running rail so that it can rotate and prevent axial movement. A steel truss traveling construction method that is characterized by:
JP149881A 1981-01-08 1981-01-08 Iron truss traveling engineering method Granted JPS57116847A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
JP149881A JPS57116847A (en) 1981-01-08 1981-01-08 Iron truss traveling engineering method

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
JP149881A JPS57116847A (en) 1981-01-08 1981-01-08 Iron truss traveling engineering method

Publications (2)

Publication Number Publication Date
JPS57116847A JPS57116847A (en) 1982-07-21
JPS6114300B2 true JPS6114300B2 (en) 1986-04-18

Family

ID=11503119

Family Applications (1)

Application Number Title Priority Date Filing Date
JP149881A Granted JPS57116847A (en) 1981-01-08 1981-01-08 Iron truss traveling engineering method

Country Status (1)

Country Link
JP (1) JPS57116847A (en)

Families Citing this family (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPS60173267A (en) * 1984-02-16 1985-09-06 鹿島建設株式会社 Scaffold free building construction method of large enclosure
JPS61277772A (en) * 1985-05-31 1986-12-08 株式会社竹中工務店 Traveling construction method
JPH061009B2 (en) * 1985-08-10 1994-01-05 清水建設株式会社 How to build a roof for a structure
JPH07207761A (en) * 1994-01-10 1995-08-08 Kajima Corp Roof truss construction method
JP5574335B2 (en) * 2010-11-24 2014-08-20 清水建設株式会社 Seismic reinforcement method for roof

Also Published As

Publication number Publication date
JPS57116847A (en) 1982-07-21

Similar Documents

Publication Publication Date Title
CN106760529B (en) Roof steel truss sliding assembly construction platform and installation method
CN115977407B (en) Prestressed large-span truss string slipping construction system and construction method thereof
US3863771A (en) Gantry cranes
JP2000144640A (en) Arch rib constructing device for concrete arch bridge
JPS6114300B2 (en)
JPS61290164A (en) Method and apparatus for supporting beam and slab
US4282696A (en) Method for fabricating and erecting unitary structural elements
JPH0455118Y2 (en)
JPS6142041B2 (en)
US4455270A (en) Construction process including slab sliding support and comprising simultaneous wall erection
JP3252675B2 (en) All-weather temporary roof
CN217325065U (en) Bridge erecting machine
JP7152383B2 (en) Structural column base structure and column base fixing method
JPS6114302B2 (en)
US3527553A (en) Apparatus for the construction of elevated ways
JPS6237439A (en) Traveling method
JP3179710B2 (en) Structural slide erection method and its work system
JPS6031983B2 (en) Sliding bearing of steel truss
JP3318133B2 (en) How to build artificial ground
JP2761526B2 (en) How to build structures
JPH0352811Y2 (en)
JPH0347375A (en) Space truss erection method and push-up device
SU617516A1 (en) Method of constructing hollow structures and structure erected by this method
CN117145268A (en) Jig frame supporting system for steel structure sliding and steel structure construction method
JPS6124505B2 (en)