JPS6058370A - Composite structure storage tank and construction method thereof - Google Patents

Composite structure storage tank and construction method thereof

Info

Publication number
JPS6058370A
JPS6058370A JP58160283A JP16028383A JPS6058370A JP S6058370 A JPS6058370 A JP S6058370A JP 58160283 A JP58160283 A JP 58160283A JP 16028383 A JP16028383 A JP 16028383A JP S6058370 A JPS6058370 A JP S6058370A
Authority
JP
Japan
Prior art keywords
wall
concrete
steel plate
storage tank
plate
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
JP58160283A
Other languages
Japanese (ja)
Inventor
松村 弘道
佐々木 昌克
俊一 小原
出口 瑩治
木内 貞毅
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
JFE Engineering Corp
Original Assignee
Nippon Kokan Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Nippon Kokan Ltd filed Critical Nippon Kokan Ltd
Priority to JP58160283A priority Critical patent/JPS6058370A/en
Publication of JPS6058370A publication Critical patent/JPS6058370A/en
Pending legal-status Critical Current

Links

Abstract

(57)【要約】本公報は電子出願前の出願データであるた
め要約のデータは記録されません。
(57) [Summary] This bulletin contains application data before electronic filing, so abstract data is not recorded.

Description

【発明の詳細な説明】 種の構造材とにより構築さ扛る佇合構造貯槽及びその構
築方法に関する。
DETAILED DESCRIPTION OF THE INVENTION The present invention relates to a storage tank with an enclosed structure constructed from various structural materials and a method for constructing the same.

従来、貯槽の構造として薄銅板による鋼製構造と鉄筋コ
ンクリート構造のものかあり、両者にはそれぞれ次のよ
うな長所.短所がある。即ち前者は気密性、防水性に優
れているが、座屈、断熱、防錆の而で問題があシ、他方
後者は、座屈、断熱、防錆の面では優扛ているが、気密
性、防水性に劣るという問題がある。そこでこのような
問題が改善さnた貯槽として銅板鉄筋コンクリート構造
の貯槽が知られている。この構造形式は、鋼板を貯槽の
内側に配し、その外側に鉄筋コンクリートを配し、上記
鋼板を構造材として用いるものであり、上記両得造形式
の長所を併せ持っている。L7か]−5この種では鋼板
とコンクIJ’−1−の一体性に問題があシ、靭性が劣
るという蔚点かあり、加えて、第1図に示すように複数
の主ビン(X)及びこれら主ビン間の副ビン(Y)を備
えた群サイロを構築しようとした場合(図中01は鋼板
、OGハコンクリート)、副ビン(Y)は、ホッパー取
付部と屋根数句部で鋼板が不連続にならざるを得す、副
ビン(Y)の気密性を十分に保てないという問題がある
Conventionally, storage tanks have two structures: steel structures made of thin copper plates and reinforced concrete structures, and each has the following advantages. There are disadvantages. In other words, the former has excellent airtightness and waterproofness, but has problems with buckling, heat insulation, and rust prevention, while the latter has excellent buckling, heat insulation, and rust prevention, but has problems with airtightness. There is a problem that it is inferior in durability and waterproofness. Therefore, a storage tank having a copper plate reinforced concrete structure is known as a storage tank that has solved this problem. This structural type uses steel plates as structural materials by placing steel plates on the inside of the storage tank and reinforced concrete on the outside, and has the advantages of both of the above-mentioned construction types. L7]-5 In this type, there is a problem with the integrity of the steel plate and the concrete IJ'-1-, and the toughness is poor. ) and sub-bins (Y) between these main bins (01 in the figure is steel plate, OG is concrete), the sub-bins (Y) are located between the hopper mounting part and the roof section. There is a problem that the steel plate has to be discontinuous and the airtightness of the sub-bin (Y) cannot be maintained sufficiently.

また、この種の貯槽の構築方式として次のような工法が
採用されている。その1つとして特公昭52 1970
2号公報に示されるものがあり、この方式はまず第1段
のり11製の環状内壁を製作してその外側にシアコネク
タを溶接し、更にこのシアコネクタを介して鉄筋を配筋
する。次いで上記環状内壁の内側を支保工で補強し、外
側には筒状フオームタイにより所定の間隔を保って外型
枠を設け、内壁と外型枠間にコンクリートを打込み第1
貯槽壁を形成する。次に同様にして第2段の貯槽を形成
するが、この場合は前記(筒状フオームタイにより第1
段貯槽壁に形成された孔を利用して支保工及び外型枠を
数句けてコンクリートを杓込む。このような作業を繰返
して所定高さの貯槽を構造するもので・ちる。1に他の
構築方法として、鉄筋コンクリート貯JHl17のM4
築に通常用いらするTj1謂スリスリップフオーム工法
用したものがある。さらに他の方法として、貯槽全体を
部品化し、上尾生産のプレキャスト板を現場で建方し、
接合部を溶接、モルタル詰めして貯4・EHを完成さぜ
る方式も開発されておシ、’f7’に築方式としでは鋼
4jJ製貯槽のそ汎に近いものとなっている。しかしな
がら以上の構築方式のうち、まず第1のものは、スリッ
プフオーム工法ではないlニめ外側に仮設足場を全面的
に設ける必要がらり、また通常鉄筋コンクリート貯イ・
j!Iで必要とさ扛る種類の工事に加えて鋼板の建方及
び溶接やシアジベルの取付などの作業が必要なことから
、現場での作業が繁雑化し、工事効率が悪いという問題
がある。捷た5主ビン及びその主ビン間に副ビンを備え
た群サイロをイ1η築する場合、同一レベルの高さの工
事を総て同時に施工していく必要があり、このため一度
に多くの人手及びクレーン等の設備を必要とする他、鉄
筋工、コンクリート工、桧械方オペレータ宿の多極多数
の技能]二を必要とし、工事が錯綜してし捷う等の難点
がある。また第2の構築方式では、スリップフオーム工
法をオU用しているため銅板を組立てる際ヨークを交す
必要から、銅板を小片に構成しこnを溶接しており、こ
のため銅板組み立てに要するニー11費が非常に大きく
なるという問題がある。
In addition, the following methods are used to construct this type of storage tank. One of them is the special public service in 1970.
There is a method disclosed in Japanese Patent No. 2, in which a first-stage annular inner wall made of glue 11 is manufactured, a shear connector is welded to the outside of the annular inner wall, and reinforcing bars are further arranged through the shear connector. Next, the inside of the annular inner wall is reinforced with shoring, an outer form is provided at a predetermined interval using cylindrical form ties on the outside, and concrete is poured between the inner wall and the outer form.
Form the storage tank wall. Next, a second stage storage tank is formed in the same manner, but in this case, the first
Using the holes formed in the tiered storage tank wall, the shoring and outer formwork are opened several times and concrete is poured in. This process is repeated to construct a storage tank of a predetermined height. 1. As another construction method, reinforced concrete storage JHL17 M4
There is one that uses the Tj1 so-called slip-slip form construction method, which is commonly used for construction. Another method is to make the entire storage tank into parts and erect the precast boards manufactured by Ageo on site.
A method of completing the storage tank 4/EH by welding the joints and filling with mortar has also been developed, and the 'f7' construction method is similar to that of steel 4JJ storage tanks. However, among the above construction methods, the first method is not the slip form construction method, and requires provision of temporary scaffolding on the entire outside.
j! In addition to the types of construction work required under I, work such as erecting and welding steel plates and installing shear belts is required, which makes on-site work complicated and has the problem of poor construction efficiency. When constructing a group of silos with 5 main bins and sub-bins between the main bins, it is necessary to construct all the works at the same height at the same time. In addition to requiring manpower and equipment such as cranes, it also requires multiple skills such as reinforcing bar work, concrete work, and mechanical operator accommodation, and has the disadvantage that the construction work is complicated and difficult to complete. In addition, in the second construction method, since the slip form construction method is used, it is necessary to intersect the yoke when assembling the copper plate, so the copper plate is constructed into small pieces and the pieces are welded. There is a problem that the knee 11 cost becomes very large.

また群サイロを第1・構築する場合には、上記第10栴
築法と同様の難点を有している。さらに第3の構築方式
では、運搬のために部品寸法を大きくできないため、部
品数も多く、したがってまた溶接工数が非常に多くなる
という問題がある。また各部品は鉄筋を四辺の銅板枠な
どに1本ずつ溶接等で接合するという構造とする必要が
あるため、溶接工数と6i *3」、!が非常に多くな
り、生産コストか上かるなどの問題がある。さらに、運
搬距離によっては運搬コストが大幅に上がる等の問題も
ある。
In addition, when constructing a group of silos in the first place, it has the same difficulties as the above-mentioned 10th construction method. Furthermore, in the third construction method, the size of the parts cannot be increased for transportation, so there is a problem that the number of parts is large, and therefore the number of welding steps is also extremely large. In addition, each part must have a structure in which reinforcing bars are joined one by one to the copper plate frame on each side by welding, etc., so the number of welding man-hours and 6i *3'',! There are many problems, such as increasing production costs. Furthermore, there is also the problem that the transportation cost increases significantly depending on the transportation distance.

本発明はこのような従来の腹合11″じf貯槽及びその
4’Fjl>方法の問題点に鑑み発明さ11.たもので
、槽自体の靭性にW tL、しかも群”す゛イロに適用
した場合でも副ビンの気m伯を適切に得ることができる
朴′)造の板金(イ”jj造貯柁1及びその構築に好適
な方法を提供せんとするもC)である。
The present invention was devised in view of the problems of the conventional 11" storage tank and its method, and it is applicable to the toughness of the tank itself, as well as to the group 11. Even in the case of the construction, we would like to provide a suitable method for constructing a sheet metal plate (1) and its construction, which can properly obtain the capacity of the secondary bottle.

このため本発明は、片面にシ′フ′コネクタを有シ且つ
互いのシアコネクタか向き合うようにして配設さfした
内壁針(板及び外壁銅板と、画調板間に打設されたコン
クリートと力・らなる壁構造を有することをそのジ、゛
ソ本的q4で改とする。またこのような構造の貯4・凸
を4’l’l ’;’!−j−るため、貯槽を高さ方向
で数段に分けて(lo・γ築するに当り、各段毎に、片
面にシアコネクタを有する内壁鋼板及び外壁銅板を互い
のシアコネクタが向き合うように配設し、内壁鋼板内側
に配設された作業用足場により内壁鋼板の内側への変形
を防止(一つつ、両鋼板間にコンクリートを打設するよ
うにしたことを他の基本的特徴とする。また他の借集方
法として、片面にシアコネクタを有する内壁鋼板及び外
壁鋼板を互いのシアコネクタが向き合うようにして配設
し7て鋼′a!!槽を構築し、該鋼製槽を密閉して内圧
をかけつつ内壁鋼板及び外壁鋼板間にコンクリートを打
設するようにしたことを他の基本的特徴とする。
For this reason, the present invention has a shear connector on one side, and the inner wall needles are arranged so that the shear connectors face each other. The fact that it has a wall structure with a force of When building a storage tank by dividing it into several stages in the height direction (lo and gamma), for each stage, an inner wall steel plate with a shear connector on one side and an outer wall copper plate are arranged so that the shear connectors face each other, and the inner wall The work scaffold placed inside the steel plate prevents the inner wall steel plate from deforming inward (one basic feature is that concrete is placed between both steel plates). As a collection method, an inner wall steel plate and an outer wall steel plate each having a shear connector on one side are arranged so that the shear connectors face each other to construct a steel tank, and the steel tank is sealed to reduce the internal pressure. Another basic feature is that concrete is poured between the inner wall steel plates and the outer wall steel plates.

以下本発明を実施例を図面に示すものについて説明する
The present invention will be described below with reference to embodiments shown in the drawings.

第2図は本発明による複合構造貯枯の壁枯造の断面を示
すもので、(1)は内壁鋼板、(2)は外壁銅板、(3
)はこれら画鋲板間に打設されたコンクリートである。
Figure 2 shows a cross section of a composite storage wall structure according to the present invention, in which (1) is a steel plate for the inner wall, (2) is a copper plate for the outer wall, and (3)
) is the concrete poured between these thumbtack boards.

両餉板の互いに向き合う面にはシアコネクタ(4)が設
けられている。
A shear connector (4) is provided on the opposing surfaces of both plates.

本発明では、コンク1,1− トは鉄筋なしで打設され
、こtしによっても強い靭性が443らハるようになっ
ている。
In the present invention, the concrete 1,1- is cast without reinforcing bars, and is made to have strong toughness even through hardening.

寸た第3図は第2図に示すような本発明の貯槽構造を群
サイロに適用したもので、(X)は主ビン、(Y)はこ
扛ら主ビン(X)間にそれらの外壁を利用して形成さ;
jl、る副ビンである。
Fig. 3 shows the storage tank structure of the present invention as shown in Fig. 2 applied to a group silo. Formed using the outer wall;
jl is a sub-bin.

各主ビン(X)を構成する外壁鋼板(2)の外側高さ方
向には、隣接する主ビン間で対向するようにして各2条
のフィン(5)が設けら71 、主ビン間で対向したフ
ィン(5)を継鋼板(6)で酷き、これによって形成さ
扛た継鋼板間の隙間に二ゴンク!j −) (7)が打
設さ肛ており、こ牡が副ビン(Y)の壁の一部を形成し
ている。
In the outer height direction of the outer wall steel plate (2) constituting each main bin (X), two fins (5) are provided 71 so as to face each other between adjacent main bins. The opposing fins (5) are severely damaged by the joint steel plates (6), and two gonks are created in the gap between the joint steel plates formed by this! j −) (7) is poured into the hole, and the hole forms part of the wall of the sub-bottle (Y).

第4図は以上の如き複合構造貯槽の−’−4?Ii築法
を示すもので、貯槽を高さ方向で数段に分けて114築
するようにし、鋼板の建方]工事とコンクリート工事を
各段毎に行うようにしグこものである。
Figure 4 shows -'-4? of the above-mentioned composite structure storage tank. This refers to the Ii construction method, in which the storage tank is built in several stages in the height direction, and the steel plate construction and concrete work are performed for each stage.

即ち、適当外高さhの内壁#4板(1)及び外4γ伸板
(2)(本実施例では鋼板リング)をそれぞれクレーン
吊り等により下層の各銅板」二部に積み」二げ、溶接し
て固定した後、画調板間にコンクIJ −) (3)を
打設して一層分の施工を行い、コンクリート硬化後火の
層のハエに進む。
That is, the inner wall #4 plate (1) and the outer #4 gamma plate (2) (steel plate ring in this example) each having an appropriate outer height h are hung by a crane or the like, and each of the lower copper plates is stacked in two parts. After welding and fixing, concrete IJ-) (3) is poured between the drawing boards to construct one layer, and after the concrete hardens, proceed to the fire layer.

そして、以上の工程を各層毎に繰り返すことにより貯槽
を完成させる。このような構築の過程において本発明で
は、コンクリート打設時における内壁銅板(1)の内側
−・の変形(はらみ出し)を特別な支保工を用いること
)く作業用足場(8)を第1」用して防止するようにし
ている。
The storage tank is then completed by repeating the above steps for each layer. In the process of construction, the present invention uses special shoring to prevent deformation (protrusion) of the inner side of the inner wall copper plate (1) during concrete pouring. ” to prevent this.

内壁銅板(1)の内側上7i+Sには足場支持用のブラ
ケット(9)が設けら九、作業用足場(8)は施工層よ
り下方の層(打設コンクリートが硬化(〜ている)の内
壁体1板に設けら7したブラケット(9)に支持されて
いる。作業用足場(8)は、前記ブラケット(9)の結
合部よυ上方に足場部(81)を有し、作業渚が施工層
へのコンクリートの打設とさらに次の層の銅板の溶接が
行えるように在っている。作業用足場(8)は施工層の
内壁鉄板を全周に亘って又は少なくとも周方同数箇所で
内fll11から支持すべき支持部(u’41示せず)
を有しており、こノ尤により、コンクリ−1・打設時に
おける内壁鉄板の内側へのはらみ出しを適切に防止する
ものである。例えば、第3図に示さ41″Lるものでは
、円形状の作業用足場(8)の周方向数銭所に前記支持
部(82)をフイ」している。
A bracket (9) for supporting the scaffold is provided on the inner side top 7i+S of the inner wall copper plate (1). The work scaffold (8) has a scaffold part (81) above the joint part of the bracket (9), and the work beach is It is located so that concrete can be placed on the construction layer and the copper plates of the next layer can be welded.The work scaffold (8) is placed around the entire circumference of the inner wall steel plate of the construction layer, or at least at the same number of places around the circumference. The support part that should be supported from inner full11 (u'41 not shown)
This feature appropriately prevents the inner wall steel plate from protruding inward during concrete 1 pouring. For example, in the case of 41"L shown in FIG. 3, the support portion (82) is fitted at several points in the circumferential direction of the circular work scaffold (8).

作業用足場(8)が第4図に示すように=1ンクリート
が硬化した層(xOa)のブラケツ+−(9a)に支持
された状態で、その足場部(81)土の人間により上部
の層(xob)のコンクリ−1・杓設作業及びさらにそ
の土部の層(10c)の′11.1板浴接作業が行われ
る。そしてこれらのイ′[業の光子(及びコンクリート
01化)後クレーン吊ν等により作業用足場(8)を上
方に移動させてこ才1を層(1ob)のブラケツ) (
9b)に支持せしめ、次の層の施工を行う。
As shown in Fig. 4, the working scaffold (8) is supported by the brackets +- (9a) of the layer (xOa) in which =1 concrete is hardened, and the upper portion of the scaffold (81) is Concrete 1 and ladle work for the layer (xob) and '11.1 board bathing work for the soil layer (10c) are carried out. Then, after these photons (and concrete 01 conversion), the work scaffold (8) is moved upward by a crane, etc., and the bracket of the layer (1ob))
9b) and apply the next layer.

なお、第3しjに示すような副ビン用の施工を行う場合
には、外壁鋼板(2〕を足場サポートに[1,た作業用
足場(8′)を配設し、各層毎の継鋼板(6)の溶接と
コンクリートの打設を行うものである。
In addition, when performing construction for a secondary bin as shown in 3.j., a working scaffold (8') is installed using the outer wall steel plate (2) as a scaffold support, and the joints for each layer are This is for welding steel plates (6) and placing concrete.

第5図は他の杓築払を示すもので、缶j板の建方工4T
とコンクリート打設工事とをそれぞn分離独立し、て行
うものであり、しかも上記わ1築法と同様内壁鋼板の支
保工等を要することなくコンクリート打言゛)を行える
ようにしまたものである。
Figure 5 shows another type of ladle construction.
This method performs the concrete pouring work separately and independently, and, like the construction method 1 above, it is possible to perform the concrete pouring work without the need for supporting the inner wall steel plate. be.

この構箔法では寸ず、第5図の(A)で示すように、内
壁釘板(])及び外壁剣、1れ(2)を積み上げて溶接
し、に宅1肥ff’i 01>全体を構築する。銅製栢
01)b下部1(ポツパー(図示せず)を有1/、土部
にし1.バ釈0つが取イ;]けら扛る。
In this construction method, as shown in Figure 5 (A), the inner wall nail plate () and the outer wall nail plate (2) are piled up and welded, and the nail plate (2) for the outer wall is stacked and welded. Build the whole thing. Copper shell 01) b Lower part 1 (with a popper (not shown) 1/, place it on the soil part 1. Remove 0 pieces;] Scrape off the shell.

鍋数J檜00の1lj部([′ド旦ζ欽1:、:(Iン
内部〕を曾1閉し、Iu’l rll (B)に示され
るようK、エアコンプレツサク5′(し1示せず〕によ
り打設さnる生コンクリートの側圧に対抗できる圧力の
内圧Pをかける。このような状態で内壁釦iな(1)と
外壁砲板(,2)との間にコンクリ−1−(3)を打設
するものでちり、ff1tl記内圧Pによか同壁化板(
1)が内側にはらみ出すことが適切に防止さl′とる。
Close the 1lj part of the pot number J hinoki 00 (['DO Danζkin 1:, :(inside)], and as shown in Iu'l rll (B), K, air compressor 5' ( 1 not shown] to apply an internal pressure P that can counter the lateral pressure of the fresh concrete being poured.In this state, the concrete is placed between the inner wall button (1) and the outer wall plate (, 2). -1-(3) is used to pour dust, and the same wall plate (
1) is properly prevented from protruding inward.

以上のようにして工事が完成したならば、槽内の空気を
抜き、(C)に示すような状態で構築が完了する。なお
、α3は仮設梁でaり、この仮設梁θ→は、 !’=i
 &! f27 QJIの4M築後ハユ釈0シ2土に取
付りら!15、槽内に空気圧をかけた場合、屋根θ′1
5が外方にi・、;!:らシ・出ずのを抑える極能を果
すとともに、上部からコンクリート打設をイーjう場合
、その足朽として使うこと〃;てきる。
Once the construction is completed as described above, the air inside the tank is removed and the construction is completed in the state shown in (C). Note that α3 is a temporary beam, and this temporary beam θ→ is ! '=i
&! f27 After QJI's 4M construction, it was installed on 0 and 2 soil! 15. When air pressure is applied inside the tank, the roof θ′1
5 is outward i・,;! : It has the ultimate ability to suppress rips and spills, and can also be used as a footwall when pouring concrete from above.

なお、コンクリート(3)は、槽」一部からの他、下部
から圧入することによりわ設することができる。tfC
,第3図に示す副ビン用の1J7=工を行う温合には、
継鏑板(6)を下から土プでη”(付けた後、コンクリ
ート(3)の打設、を行う0以上のようにして得ら扛る
本発明の複合構造貯槽は、対向したmlにシアご1ネク
ク(4)を有する内壁銅板(1〕及び外り電調&(2)
と、その間に打設されるコンクリ−1・(5)と力・ら
なる壁訂・)造を有するため、画調板による優nた気密
性が得らnるとともに、鋼板とコンクリートとの一体性
が高く、靭性に侵ノtた構造とすることができる。即ち
、コンクリートがシアコネクタを有する鋼板に胡み込′
まれる構造であるため、コンクリートのゴ々大荷重時で
も鋼板の拘束効果によシコンクリートが三軸応力状態と
なり、鉄筋なしで侵れた靭性が得られる。lた、このよ
うな利点に加え、群サイロを構築する場合、第3図のよ
うに内外壁鋼板(1)及び(2)が主ビン(X) 、副
ビン(Y)のエアタイト材及び構造材として使用できる
ので経済的であり、またコンクリートが座屈防止材或い
は圧縮材となるので、鋼板厚を従来のものに較べ極端に
薄くすることができる。
In addition, the concrete (3) can be placed by press-fitting from a part of the tank or from the bottom. tfC
, 1J7 for the secondary bottle shown in Figure 3.
The composite structure storage tank of the present invention, which is obtained by applying the joint plate (6) from below with soil, and then placing the concrete (3), Inner wall copper plate (1) with one side connection (4) and external electrical control panel (2)
Because the concrete is poured between the steel plate and the concrete wall, it is possible to obtain excellent airtightness due to the drawing board, and also to ensure that the steel plate and concrete do not overlap. It has high integrity and can have a structure with excellent toughness. In other words, the concrete penetrates into the steel plate with the shear connector.
Because of its structure, even when the concrete is subjected to heavy loads, the concrete becomes triaxially stressed due to the restraint effect of the steel plates, and toughness that can be achieved without reinforcing bars can be obtained. In addition to these advantages, when constructing a group silo, as shown in Figure 3, the inner and outer wall steel plates (1) and (2) are used for the airtight material and structure of the main bin (X) and sub-bin (Y). It is economical because it can be used as a material, and since concrete acts as an anti-buckling material or a compression material, the thickness of the steel plate can be made extremely thinner than conventional ones.

また、本発明の414築法によlしば、内外壁鋼板(1
)及び(2)が型枠代シとなシ、しかもコンクリート打
設による側圧が外壁鋼*、(2)にあっては鋼板そのも
ののフープテンションにより、また、内壁鉤板(1)に
あってはフープテンションと前記作業用足場(8)又は
槽内圧Pによりそ註ぞ牡支持されるため、支保工や端角
f’9することなく側圧による鋼板のはらみ出し3i:
適切に防止することができる。′また、ビ」外壁の画調
板ともに、言わば自己完結形で約9合いしかも膜応力だ
けが作用するので変形が少なく、このため鋼板用のフオ
ームタイ4tも不要となる。さらに、!洋すイロを仔す
るに°〕−るような場合、各ビン毎にそれぞJL別個に
本17.公して独立して完成せしめることが口1tiヒ
であり、このため従来法に較べ一時に必要な入・j・、
工・jf機材等を大幅に減少せしめることができる。
In addition, according to the 414 construction method of the present invention, the inner and outer wall steel plates (1
) and (2) are the formwork allowances, and the lateral pressure due to concrete pouring is due to the outer wall steel *, and (2) is due to the hoop tension of the steel plate itself, and the inner wall hook plate (1) is is supported by the hoop tension and the working scaffold (8) or the tank internal pressure P, so the steel plate protrudes due to lateral pressure 3i without shoring or edge angle f'9:
Can be appropriately prevented. 'Furthermore, both the drawing boards on the outside wall of the vinyl are self-contained, with approximately 9 joints, and only membrane stress acts on them, so there is little deformation, so there is no need for 4 tons of form ties for steel plates. moreover,! If you want to raise a Western-style baby, please prepare a separate JL book 17. for each bottle. It is important to complete the work publicly and independently, and for this reason, compared to the conventional method, it is necessary to complete the work at one time.
It is possible to significantly reduce the number of engineering/jf equipment, etc.

また特に、第4図に示すような不発ゆjの第2の荷染法
によ、fLば、次のような利点が?j+らnる。前述し
たように、従来の複合gI造貯槽の構築は、1つの貯槽
につ@鋼板の建方工事とコンクリート工事等の多村の王
、lj)が回11.″iないし交互に行わnるため、工
■1管理が繁雑化して工事効率が非常に悪いという問題
があった。これに対して本発明法によれば、まず鋼板(
鋼製槽)の建方を行い、次いでコンクリート打設工事が
行わnるため工事管理が容易となり、且つ施工時の実働
効率も大幅に改善されるものである。
In particular, the second unexploded dyeing method shown in Figure 4 has the following advantages: j+ra nru. As mentioned above, the construction of a conventional composite GI storage tank requires a lot of work such as steel plate erection work and concrete work, etc. for one storage tank. Since the work is carried out alternately, there is a problem that the work management becomes complicated and the work efficiency is very poor.In contrast, according to the method of the present invention, the steel plate (
Since the steel tank is erected and then the concrete is poured, construction management becomes easier and the actual efficiency during construction is greatly improved.

また上記槽内圧Pによる効果として、屋根θ′3とホッ
パーに圧力が作用することによシ鋼製槽αυには軸方向
に引張力が作用するので、槽自体はそれが薄鋼板であっ
ても座屈することなく施工時の荷重に十分耐えることが
できる。また、貯槽は完成後気密試験が行わ扛るが、本
発明では施工時における上記内圧Pの付与にこの試験を
兼用せしめることができる。
In addition, as an effect of the tank internal pressure P, a tensile force acts on the steel tank αυ in the axial direction due to the pressure acting on the roof θ'3 and the hopper, so the tank itself is made of thin steel plate. It can fully withstand the load during construction without buckling. Further, although the storage tank is subjected to an airtightness test after completion, in the present invention, this test can also be used to apply the above-mentioned internal pressure P during construction.

さらに本発明法では、完成後槽内の空気を抜くことによ
シ鋼板の引張応力が解放されるので、硬化したコンクリ
ートに圧縮応力がブレストレスとして作用し、これKよ
りコンクリートの亀裂防止が図られる。
Furthermore, in the method of the present invention, the tensile stress in the steel plate is released by removing the air from the tank after completion, so compressive stress acts on the hardened concrete as breath stress, which helps prevent cracks in the concrete. It will be done.

なお、本発明では複合構造として鋼板とコンクリート(
又は鉄筋コンクリート)をその対象としているが、鋼板
の代シに合成樹脂板、コンクリートの代シに発泡ポリウ
レタン19各種の材料が複合した構造に応用することも
できる。
In addition, in the present invention, steel plates and concrete (
Although the present invention is intended for use in steel plates (or reinforced concrete), it can also be applied to composite structures in which various materials are used, such as synthetic resin plates instead of steel plates and foamed polyurethane 19 instead of concrete.

以上述べた本発明によれは、銹板とコンクリートが一体
化して優nた靭性をイjし、しかも群サイロ等に適用し
た場合に副ビンの気密性を適切に確保することができる
複合構造貯槽を提供でき、しかも、このような構造の貯
槽を、支保工や端角等の機材を吸することなく短期間で
効率的且つ経済的に(]4公できるものである。また特
に本発明の第2のオ′14祭法によnば、以上の効果に
加えti”’i板の建万工jjlとコンクリート工事と
を完全に分離して行えるため、工事管理を簡素化しs 
jiulの効率化を図ることができ、さらに内圧で槽軸
方向にかかる引張力によシ薄鋼板でらっても斤・hl(
することなく、施工時の荷重に耐えることができる等の
優れた効果を有する。
The present invention described above provides a composite structure in which the rust plate and concrete are integrated, exhibiting excellent toughness, and which can appropriately ensure the airtightness of sub-bins when applied to group silos, etc. Furthermore, the storage tank having such a structure can be made efficiently and economically in a short period of time without having to use equipment such as shoring or end corners.In addition, the present invention particularly According to the second O'14 ritual, in addition to the above-mentioned effects, construction management can be simplified and the concrete work can be completely separated from the concrete work.
It is possible to improve the efficiency of the tank, and furthermore, even if a thin steel plate is used, the tensile force applied in the axial direction of the tank due to internal pressure will reduce the
It has excellent effects such as being able to withstand the load during construction without any damage.

【図面の簡単な説明】[Brief explanation of the drawing]

第1図は従来の貯槽構造による群ザイロの水平IM面図
である。第2図は本発明の貯槽の壁構造を示す縦断面図
である。第3図は本発明の貯槽を群サイロに適用した場
合の水平断面図である。第4図は本願第1の構築法の実
施状況を示す説明図である。第5図は本願第2の構築法
の実施状況を示す説明図である。 図において、(1)は内壁鋼板、(2)は外壁り調板、
(3)はコンクリート、(4)はシアコイ・フタ、(8
)は作業用足場、0υは鋼製把・を名水ず。 ’l’!rrl出願人 日本鋼管株式会社発 明 渚 
松 村 弘 連 間 佐々木 昌 克 同 小 原 俊 − 同 出 口 Gヱ 治 同 木 内 貞 数 代]−11人弁理士 71 原 省 三筒1図 第2図 第3図 X ( 第 4 図
FIG. 1 is a horizontal IM view of a group silo with a conventional storage tank structure. FIG. 2 is a longitudinal sectional view showing the wall structure of the storage tank of the present invention. FIG. 3 is a horizontal sectional view when the storage tank of the present invention is applied to a group of silos. FIG. 4 is an explanatory diagram showing the implementation status of the first construction method of the present application. FIG. 5 is an explanatory diagram showing the implementation status of the second construction method of the present application. In the figure, (1) is the inner wall steel plate, (2) is the outer wall tone plate,
(3) is concrete, (4) is Siakoi lid, (8
) is a work scaffold, and 0υ is a steel handle. 'l'! rrl Applicant Nippon Kokan Co., Ltd. Inventor Nagisa
Hiroshi Matsumura, Masato Sasaki, Katsudo, Shun Ohara - Deguchi G, Harudo Kiuchi, Sadato Kiuchi] - 11 patent attorneys 71 Masato Hara, Figure 1, Figure 2, Figure 3, X (Figure 4)

Claims (3)

【特許請求の範囲】[Claims] (1)片面にシアコネクタを有し且つ互いのシアコネク
タが向き合うようにして配設された内壁銅板及び外壁鋼
板と、画調板間に打設さ!tたコンクリートとからなる
壁構造を有する複合構造貯槽。
(1) Cast between an inner wall copper plate and an outer wall steel plate, which have a shear connector on one side and are arranged so that the shear connectors face each other, and the drawing board! A composite structure storage tank with a wall structure made of concrete.
(2)貯槽を高さ方向で数段に分けて構築するに当勺、
各段毎に、片面にシアコネクタを有する内壁銅板及び外
壁鋼板を互いのシアコネクタが向き合うように配設し、
内壁鋼板内側に配設された作業用足場により内壁鋼板の
内側への変形を防止しつつ、内壁鋼板及び外壁鋼板間に
コンクリートを打設することを特徴とする複合構造貯槽
の構築方法。
(2) When constructing a storage tank in several stages in the height direction,
For each stage, an inner wall copper plate and an outer wall steel plate having a shear connector on one side are arranged so that the shear connectors face each other,
A method for constructing a composite structure storage tank, comprising: pouring concrete between an inner steel plate and an outer steel plate while preventing the inner steel plate from deforming inward using a work scaffold placed inside the steel plate.
(3)片面にシアコネクタを有する内壁鋼板及び外壁鋼
板を互いのシアコネクタが向き合うようにして配設して
鋼製槽を構築し、該鋼製槽を密閉して内圧をかけつつ内
壁銅板及び外壁銅板間にコンクリートを打設することを
特徴とする複合構造貯槽の構築方法7
(3) A steel tank is constructed by arranging an inner wall steel plate and an outer wall steel plate with shear connectors on one side so that the shear connectors face each other, and the steel tank is sealed and internal pressure is applied while the inner wall copper plate and Method 7 for constructing a composite structure storage tank characterized by pouring concrete between outer wall copper plates
JP58160283A 1983-09-02 1983-09-02 Composite structure storage tank and construction method thereof Pending JPS6058370A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
JP58160283A JPS6058370A (en) 1983-09-02 1983-09-02 Composite structure storage tank and construction method thereof

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
JP58160283A JPS6058370A (en) 1983-09-02 1983-09-02 Composite structure storage tank and construction method thereof

Publications (1)

Publication Number Publication Date
JPS6058370A true JPS6058370A (en) 1985-04-04

Family

ID=15711637

Family Applications (1)

Application Number Title Priority Date Filing Date
JP58160283A Pending JPS6058370A (en) 1983-09-02 1983-09-02 Composite structure storage tank and construction method thereof

Country Status (1)

Country Link
JP (1) JPS6058370A (en)

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPS62287879A (en) * 1986-05-27 1987-12-14 清水建設株式会社 Square type silo structure

Citations (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPS57119068A (en) * 1981-01-16 1982-07-24 Fujita Corp Erection of cylindrical bullding and erection unit therefor

Patent Citations (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPS57119068A (en) * 1981-01-16 1982-07-24 Fujita Corp Erection of cylindrical bullding and erection unit therefor

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPS62287879A (en) * 1986-05-27 1987-12-14 清水建設株式会社 Square type silo structure

Similar Documents

Publication Publication Date Title
KR100832848B1 (en) Method for constructing pier and concrete permanent form applied to it
CN107119851A (en) A kind of assembly concrete post plug-in type bolt splicing node and making construction method
US3182948A (en) Form for concrete slabs
JPH09209451A (en) Joint construction of up and down columns with beam and joint method
JP2571418B2 (en) Relocation method of masonry wall of existing structure
JPS6058370A (en) Composite structure storage tank and construction method thereof
US3643908A (en) Apparatus for casting large monolithic structures
US5201161A (en) Nuclear power plant construction method
JP3137448B2 (en) Construction method of concrete main tower
US1898304A (en) Reenforced concrete construction and method of building same
CN210482352U (en) Assembled main basis that becomes of high voltage mortise-tenon joint structure
JP3044459B2 (en) Tower structure construction method
JPS6055176A (en) Construction of composite structural storage tank
JPS6055175A (en) Construction of composite structural storage tank
RU97140U1 (en) COMPOUND PILET JOINT
JPS61290137A (en) Construction of columnar pillar
KR102482691B1 (en) Foundation structures using strut-tie reinforcement and its construction method
JPH06117052A (en) Precast horizontal central pillar
JP2023074188A (en) Panel type buried mold, concrete structural body and construction method thereof
JPH0830336B2 (en) Column row underground wall construction method and stress bearing material used for it
JPH0340175B2 (en)
JPH073879A (en) Form structure by lise of buried form
JPH0743491A (en) Reactor container made of steel and constructing method therefor
JPH01502438A (en) Low bulk density load-bearing structures consisting of thin slabs and shells of reinforced concrete
JPS62170640A (en) Outer wall structure of building