JPS6033983A - Construction of concrete body - Google Patents

Construction of concrete body

Info

Publication number
JPS6033983A
JPS6033983A JP14329983A JP14329983A JPS6033983A JP S6033983 A JPS6033983 A JP S6033983A JP 14329983 A JP14329983 A JP 14329983A JP 14329983 A JP14329983 A JP 14329983A JP S6033983 A JPS6033983 A JP S6033983A
Authority
JP
Japan
Prior art keywords
formwork
reinforcing bar
assembly
reinforcing
main
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
JP14329983A
Other languages
Japanese (ja)
Inventor
森田 建男
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Tekken Corp
Original Assignee
Tekken Corp
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Tekken Corp filed Critical Tekken Corp
Priority to JP14329983A priority Critical patent/JPS6033983A/en
Publication of JPS6033983A publication Critical patent/JPS6033983A/en
Pending legal-status Critical Current

Links

Landscapes

  • On-Site Construction Work That Accompanies The Preparation And Application Of Concrete (AREA)

Abstract

(57)【要約】本公報は電子出願前の出願データであるた
め要約のデータは記録されません。
(57) [Summary] This bulletin contains application data before electronic filing, so abstract data is not recorded.

Description

【発明の詳細な説明】 この発明はコンクリート躯体の構築方法に関するもので
ある。
DETAILED DESCRIPTION OF THE INVENTION The present invention relates to a method of constructing a concrete frame.

従来、建築物のコンクリート躯体は、現場において配筋
、型枠の製作、組立を行5いわゆる労務集約型工法によ
り構築されている。
Conventionally, concrete frames for buildings have been constructed using a so-called labor-intensive construction method in which reinforcement is placed, formwork is manufactured, and assembled on-site.

そのため施工に多大な労力と時間を要し、非能率的であ
ることから、あらかじめ工場において鉄筋を組立て、あ
るいは型枠yrM作することが試られているが、大幅な
作条能率の向上は望めない。
This requires a great deal of labor and time to construct and is inefficient, so attempts have been made to assemble reinforcing bars or formwork in advance at a factory, but it is not expected to significantly improve construction efficiency. do not have.

この発明は、上記のような従来工法を更に改良すべくな
されたものであり、あらかじめ工場において鉄筋と型枠
とを一体化し、この一体化された組立体′?:現場に設
置することにより、更に省力化を図るとともに、根体性
能を向上させることができるコンクリート躯体の構築方
法を提供することを目的とする。
This invention was made in order to further improve the conventional construction method as described above, and involves integrating reinforcing bars and formwork in advance in a factory, and creating this integrated assembly. : The purpose is to provide a method for constructing a concrete frame that can be installed on-site to further save labor and improve the performance of the foundation.

すなわちこの発明のコンクリート8体の構築方法は、互
いに平行となるように配置した所要数の主筋の周囲に、
この主筋に対し垂直となるように所要数のせん断補強筋
枠体を配置して、主筋とせん断補強筋枠体とを固定し、
前記せんの部材を構成する鉄筋型枠組立体をあらかじめ
製作し、この組立体を所定位置に設置した後、前記型枠
の内方にコンクリートを打設して硬化させることを特徴
とする。
In other words, the method for constructing eight concrete bodies according to the present invention is to
Arrange the required number of shear reinforcing bars perpendicularly to the main bars, fix the main bars and the shear reinforcing bars,
The present invention is characterized in that a reinforcing steel formwork assembly constituting the members of the shear is manufactured in advance, and after this assembly is installed at a predetermined position, concrete is poured inside the formwork and hardened.

以下図面に示す実施例を参照しながらこの発明を説明す
る。
The present invention will be described below with reference to embodiments shown in the drawings.

第1〜第5図に示すように、lはこの発明方法に使用さ
れ、柱、梁等を4待成する鉄筋型枠組立体であって、こ
の鉄筋型枠組立体1は工場等においてあらかじめ製作さ
れる。
As shown in FIGS. 1 to 5, 1 is a reinforcing bar formwork assembly 1 used in the method of the present invention, in which columns, beams, etc. are prepared in four stages. Ru.

鉄筋型枠組立体lは、主筋2とぜん断補強筋枠体3とt
具え、主筋2はこの例では2本の鉄筋2a、2bを1組
として束ねた束ね鉄筋からなり、所要数互いに平行とな
るように配置されている。せん断補強筋枠体3は多数の
縦筋3aおよび横筋3b’&網状に固着してなり、こす
せん断補強筋枠体3は主筋2に対し垂直となるように所
要数配置されている。すなわち主筋2はせん断補強筋枠
体3の上下の網目を貫通し、さらに適宜数のせん断桶強
筋枠体3に固定しだ補強鉄板(第5図参照)に設けた孔
5を貫通してこの補強鉄板4に固定されている。
Reinforcing bar formwork assembly 1 consists of main bar 2, shear reinforcing bar frame 3, and t.
In this example, the main reinforcing bars 2 are made up of bundled reinforcing bars in which two reinforcing bars 2a and 2b are bundled together as a set, and a required number of reinforcing bars are arranged parallel to each other. The shear reinforcement frame 3 is made up of a large number of longitudinal reinforcements 3a and transverse reinforcements 3b' and fixed in a net shape, and a required number of shear reinforcement frames 3 are arranged perpendicular to the main reinforcement 2. That is, the main reinforcement 2 passes through the upper and lower meshes of the shear reinforcing bar frame 3, and further passes through holes 5 provided in the reinforcing steel plate (see Fig. 5) fixed to the appropriate number of shear reinforcing bar frames 3. It is fixed to this reinforcing iron plate 4.

型枠6はこの例では多数の孔を有する平ラスからなり、
その孔にぜん断補強筋枠体3の縦横筋aa、3bの端部
が貫通するこ□とにより型枠6がせん断補強筋枠体3に
取付けられている。
In this example, the formwork 6 consists of a flat lath with a large number of holes,
The formwork 6 is attached to the shear reinforcing bar frame 3 by passing the ends of the longitudinal and transverse bars aa and 3b of the shear reinforcing bar frame 3 through the holes.

7は型枠6の押え部材であり、この押え部材7は多数の
縦筋7aおよび横筋7bを網状に固着してなり、その網
目からせん断補強筋枠体3の縦横筋3m 、3bの端部
を突出してこの端部に押え部材7の縦横筋7a 、7b
が接合されている。
Reference numeral 7 denotes a holding member for the formwork 6, and this holding member 7 is formed by fixing a large number of vertical bars 7a and horizontal bars 7b in a net shape, and from the mesh, the ends of the vertical and horizontal bars 3m and 3b of the shear reinforcing bar frame 3 are attached. The vertical and horizontal stripes 7a and 7b of the presser member 7 are projected at this end.
are joined.

第6図は鉄筋型枠組立体lの別の実施例を示し、鉄筋型
枠組立体1は型枠6′にリプ8を有するリプラスが使用
され、リプ8はせん断補強筋枠体3の縦横筋3m、3b
に接合されている。
FIG. 6 shows another embodiment of the reinforcing bar formwork assembly 1, in which a replus having a lip 8 on the formwork 6' is used, and the lip 8 is a longitudinal and transverse bar 3m of the shear reinforcing bar frame 3. , 3b
is joined to.

第7図は鉄筋型枠組立体1のさらに別の実施例を示し、
鉄筋型枠組立体1は型枠6″に仕上材となる石綿板、ベ
ニヤ板等が使用され、型枠6“はせん断補強筋枠体3に
固定された角パイプ9にビスIOおよび接着材等を介し
て接合されている。
FIG. 7 shows yet another embodiment of the reinforcing bar formwork assembly 1,
In the reinforcing bar formwork assembly 1, asbestos board, plywood board, etc. are used as finishing materials for the formwork 6'', and the formwork 6'' is made by attaching screws IO, adhesive, etc. to the square pipe 9 fixed to the shear reinforcing bar frame 3. are connected through.

上記各実施例において鉄筋型枠組立体1が柱を構成する
ものであれば4側面に型枠が配置され、梁を構成するも
のであれば3側面に型枠が配置されることになる。
In each of the above embodiments, if the reinforcing bar formwork assembly 1 constitutes a column, formwork will be placed on four sides, and if it constitutes a beam, formwork will be placed on three sides.

上記のような鉄筋型枠組立体1を使用してコンクリート
躯体は次のようにして構築される。
A concrete frame is constructed as follows using the reinforcing steel formwork assembly 1 as described above.

すなわち第8、第9白に示すように柱を構成する鉄筋型
枠組立体1aY施工現場においてクレーン等により吊下
げ、すでKm桑した柱あるいは基礎から突出する主筋2
に鉄筋型枠組立装置する。主筋2の接合に際しては上下
の主筋2゜2の端部なスリーブlo内で重ね合せ、該ス
リーブの両端を閉塞し、スリーブ内に高強度モルタルを
注入して固化させる。なお主筋2の接合部周囲の型枠6
は主筋1を接合した後に組立てろ。
In other words, as shown in No. 8 and No. 9, the reinforcing bar formwork assembly 1a that constitutes the column is suspended by a crane or the like at the construction site, and the main reinforcing bar 2 protruding from the column or foundation that has already been cleared for Km.
Install reinforcing bar formwork assembly equipment. When joining the main reinforcing bars 2, the upper and lower main reinforcing bars 2°2 are overlapped in a sleeve lo at the end thereof, both ends of the sleeve are closed, and high-strength mortar is injected into the sleeve and solidified. In addition, the formwork 6 around the joint of the main reinforcement 2
Assemble after joining main reinforcement 1.

次に鉄筋型枠組立体1aの型枠6の内方にコンクリート
を打設し、硬化させ、柱を構築する。
Next, concrete is placed inside the formwork 6 of the reinforcing steel formwork assembly 1a and hardened to construct columns.

柱の栴祭後、その側面に梁受はブラケット11を取付け
、このブラケット上に梁を構成する鉄筋型枠組立体lb
の端部を固定し、柱上において対向する鉄筋型枠組立体
1bの主筋どうしtジヨイント用鉄筋12を介して接合
する。
After the pillar is installed, a bracket 11 is attached to the side of the pillar, and the reinforcing bar formwork assembly lb that makes up the beam is placed on this bracket.
The main bars of the opposing reinforcing bar formwork assemblies 1b are connected to each other via the T-joint reinforcing bars 12 on the column.

接合に際してはジヨイント用鉄筋12と主筋2との端部
を前記と同様にスリーブlo内で重ね合せ、該スリーブ
の両端を閉塞した後スリーブ10内に高強度モルタルを
注入して硬化させる。
When joining, the ends of the joint reinforcing bars 12 and the main bars 2 are overlapped in the sleeve lo in the same manner as described above, and after closing both ends of the sleeve, high-strength mortar is injected into the sleeve 10 and hardened.

柱および梁ともに型枠6の解体は行なわず、その上に仕
上げをする。
For both columns and beams, the formwork 6 is not dismantled, and finishing is done on it.

次にスラブのを枠(図示せず)を従来と同様な工法によ
り組立て、スラブ筋を配置し、梁およびスラブのコンク
リートを同時に打設して硬化させ、梁およびスラブを構
築する。
Next, a frame (not shown) for the slab is assembled using a conventional construction method, slab reinforcements are placed, and concrete for the beam and slab is poured and hardened at the same time to construct the beam and slab.

以上のような作業ビ順次繰り返し、建染物のコンクリー
ト躯体を構築する。
The above-mentioned work is repeated in sequence to construct the concrete frame of the building.

この発明は上記のようであって、型枠の内側に所要数の
主筋およびせん断補強枠体を配置した鉄筋型枠組立体乞
あらかじめ製作し、この組立体を所定位置に設置した後
、コンクリートを打設して柱、梁等の部材を横条するの
で、建築現場における作業は組立体の設置およびコンク
リートの打設のみとなり、作業能率を向上させることが
できる。また組立体の製作は通常工場で行われるので、
寸法精度を上げることができ、したがって躯体性能の向
上を図ることができる。
This invention is as described above, in which a reinforcing steel formwork assembly is manufactured in advance in which a required number of main reinforcements and shear reinforcing frames are arranged inside the formwork, and after this assembly is installed at a predetermined position, concrete is poured. Since members such as columns and beams are horizontally strung by installing the structure, the only work required at the construction site is installing the assembly and pouring concrete, improving work efficiency. In addition, since the assembly is usually manufactured in a factory,
Dimensional accuracy can be increased, and therefore the performance of the frame can be improved.

【図面の簡単な説明】[Brief explanation of the drawing]

第1図はこの発明方法に使用する鉄筋型枠組立体の平面
図、第2図は同上のものの一部破断した正面図、第3図
は同上のものの分解斜視図、第4図は第1図イ部分の拡
大図、第5図は補強鉄板の斜視図、第6図は鉄筋型枠組
立体の別な実施例7示す第4図と同様な図面、第7図は
鉄筋型枠組立体のさらに別な実施例7示す一部の拡大正
面図、第8、第9図は柱を構成する鉄筋型枠組立体の設
置状態を示す正面図、第10図は梁を構成する鉄筋型枠
組立体の設置状7.!、、14 Y示す正面図。 1.1+l、lb・・・鉄筋型枠組立体2・・・主筋 3・・・せん断補強筋枠外 6 、6’、 6″・・・型枠 筋1図 す 市2図 唱5目 弔6閃 69 扇8圀
Fig. 1 is a plan view of the reinforcing steel formwork assembly used in the method of the present invention, Fig. 2 is a partially cutaway front view of the same as above, Fig. 3 is an exploded perspective view of the same as above, and Fig. 4 is the same as Fig. 1. Fig. 5 is a perspective view of the reinforcing iron plate, Fig. 6 is a drawing similar to Fig. 4 showing another embodiment 7 of the reinforcing bar formwork assembly, and Fig. 7 is yet another example of the reinforcing bar formwork assembly. FIGS. 8 and 9 are front views showing the installed state of the reinforcing bar formwork assemblies that make up the columns, and FIG. 10 shows the installed states of the reinforcing bar form assemblies that make up the beams. 7. ! ,,14 A front view showing Y. 1.1+l, lb...Reinforcing bar formwork assembly 2...Main bar 3...Shear reinforcing bar outside the frame 6, 6', 6''...Formwork bar 1 zu city 2 illustration 5 memo 6 flashes 69 Ougi 8 area

Claims (1)

【特許請求の範囲】[Claims] 1、互いに平行となるよ5に配置した所要数の主筋の周
囲に、この主筋に対し垂直となるように所要数のせん断
補強筋枠体を配置して、主筋とせん断補強筋枠体とな固
定し、前記せ梁等の部材を構成する鉄筋型枠組立体をあ
らかじめ製作し、この組立体を所定位置に設置した後、
前記型枠の内方にコンフリートラ打設して硬化させるこ
とを特徴とするコンクリート躯体の構築方法。
1. Arrange the required number of shear reinforcement frames perpendicular to the main reinforcements around the required number of main reinforcements arranged parallel to each other in 5 to form the main reinforcement and shear reinforcement frames. A reinforcing bar formwork assembly that is fixed and constitutes members such as the above-mentioned beams is fabricated in advance, and after this assembly is installed in a predetermined position,
A method for constructing a concrete frame, characterized by pouring a confetti slab inside the formwork and curing it.
JP14329983A 1983-08-05 1983-08-05 Construction of concrete body Pending JPS6033983A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
JP14329983A JPS6033983A (en) 1983-08-05 1983-08-05 Construction of concrete body

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
JP14329983A JPS6033983A (en) 1983-08-05 1983-08-05 Construction of concrete body

Publications (1)

Publication Number Publication Date
JPS6033983A true JPS6033983A (en) 1985-02-21

Family

ID=15335516

Family Applications (1)

Application Number Title Priority Date Filing Date
JP14329983A Pending JPS6033983A (en) 1983-08-05 1983-08-05 Construction of concrete body

Country Status (1)

Country Link
JP (1) JPS6033983A (en)

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPS61216933A (en) * 1985-03-22 1986-09-26 Nippon Steel Corp Prevention of corrosion of driven steel part for bottom ground under water
JPH0349339U (en) * 1989-09-19 1991-05-14

Citations (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPS5241429A (en) * 1975-09-29 1977-03-31 Okabe Kk Method of executing concrete construction
JPS5427055A (en) * 1977-07-26 1979-03-01 Kasuga Electric Co Warp yarn detecting system of weaving machine
JPS5759529U (en) * 1980-09-27 1982-04-08

Patent Citations (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPS5241429A (en) * 1975-09-29 1977-03-31 Okabe Kk Method of executing concrete construction
JPS5427055A (en) * 1977-07-26 1979-03-01 Kasuga Electric Co Warp yarn detecting system of weaving machine
JPS5759529U (en) * 1980-09-27 1982-04-08

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPS61216933A (en) * 1985-03-22 1986-09-26 Nippon Steel Corp Prevention of corrosion of driven steel part for bottom ground under water
JPH0349339U (en) * 1989-09-19 1991-05-14

Similar Documents

Publication Publication Date Title
JP2522714B2 (en) Construction method of building frame
JP2000144896A (en) Construction method of rahmen frame using beam having step difference
JP2986751B2 (en) Seismic performance enhancement method for buildings and seismic blocks
JPS6033983A (en) Construction of concrete body
JP2860699B2 (en) Prefabricated damping wall
JPS6157732A (en) Construction of multilayered building skeletal by precast reinforced concrete unit
JPH084196A (en) Panel for building
RU2153561C1 (en) Method of erecting building structures
JPS62178634A (en) Framework construction method of structure
JPH02236325A (en) Construction method for super-highrise building
JPS6043547A (en) Mold frame and reinforcement iron integral assembling and constructing method
JPH077384Y2 (en) Panels for surface formation of concrete foundations
JPH0366878A (en) Construction method for precast column and beam and precast anti-seismic wall
JPS62121249A (en) Construction of pillar/beam connection part
JPH08209831A (en) Compound ultra-light floor board and manufacture thereof
JPS62170640A (en) Outer wall structure of building
JPS6375231A (en) Building housing
JP3312945B2 (en) Construction method of concrete structure
JP2783053B2 (en) Wall-type reinforced concrete structure
JPH05311748A (en) Connecting execution method of pole and beam
JPH01111922A (en) Natural ground reinforcing structure and formwork therefor
JPS63268833A (en) Method for constructing body of multi-storied building
JP2673235B2 (en) Parallel string reinforcement truss frame structure of building
JPS62260967A (en) Method for assembling reinforcement for reinforced concrete structure
JPH0213694B2 (en)