JPS6022151B2 - Precast reinforced concrete beam section split vertically - Google Patents
Precast reinforced concrete beam section split verticallyInfo
- Publication number
- JPS6022151B2 JPS6022151B2 JP14492076A JP14492076A JPS6022151B2 JP S6022151 B2 JPS6022151 B2 JP S6022151B2 JP 14492076 A JP14492076 A JP 14492076A JP 14492076 A JP14492076 A JP 14492076A JP S6022151 B2 JPS6022151 B2 JP S6022151B2
- Authority
- JP
- Japan
- Prior art keywords
- reinforced concrete
- concrete beam
- bars
- precast reinforced
- reinforcing bars
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Expired
Links
Landscapes
- Joining Of Building Structures In Genera (AREA)
- Rod-Shaped Construction Members (AREA)
Description
【発明の詳細な説明】
本発明は軸線方向に沿い縦方向に分割したプレキャスト
鉄筋コンクリート梁部材に関するものである。DETAILED DESCRIPTION OF THE INVENTION The present invention relates to a precast reinforced concrete beam member that is longitudinally divided along an axial direction.
プレキャストコンクリート部材を構造物の構築素子とし
て用いることは、現場における施工過程を簡略化し、工
期の短縮と工費の低廉化を図る手段として建設業界には
広く応用されてその用途も拡大の一途をたどっている。The use of precast concrete members as building elements for structures has been widely applied in the construction industry as a means of simplifying the construction process on site, shortening the construction period and reducing construction costs, and its applications are continuing to expand. ing.
しかしながら、このプレキヤストコンクリート部材を用
いる工法においても、これら部材間相互の結合構造に種
々な工夫が施されているにもかかわらずかならずしも十
分なものがなくすべての条件を満足するものとは言えな
かった。本発明はこのようなことから、ブレキャストコ
ンクリート工法と現場施工法とを折衷することによりこ
れら両者の最現所を採用するよう工夫して創作したもの
である。However, even in this construction method using precast concrete members, although various improvements have been made to the mutual connection structure between these members, there are not always sufficient structures and it cannot be said that it satisfies all conditions. Ta. In view of the above, the present invention was created by making a compromise between the precast concrete construction method and the on-site construction method, thereby employing the best of both methods.
以下、本発明を添付の図面の実施例について説明すれば
、1は両側の縦割りプレキヤスト鉄筋コンクリート梁部
材で、矩形の灘断補強筋2,2′,2へ・…・を多数一
定間隔をおいて並列に配置し、該灘断補強筋と上端主筋
3,3′,3″とを配して累結し、下端主筋4,4′,
4″とも同じく累結して鉄筋篭を構成し、多数並列の灘
断補強筋2,2′,2へ・・・・・の一辺とこれに隣接
する二辺の一部を残して大部分をコンクリート躯体中に
埋込するようにコンクリートを打設して製したものであ
る。5は中間用補助縦割りプレキャスト鉄筋コンクリー
ト梁部材で、均しく矩形の奥断補強筋6,6′,6″・
・・・・・を多数一定間隔をおいて並列に配置し、これ
らの矩形の奥断補強筋の上辺下ならびに下辺上に上端主
筋7,7′,7″ならびに下端主筋8,8′,8″を並
列に配して累結して鉄筋篭を構成し、この鉄筋篭の多数
並列の鯛断補強筋6,6′,6″・・・・・・の上下二
辺の中央部分をコンクリート鯛体中に埋込するとともに
これの両側辺をコンクリート蝿体中より突出させたもの
である。Hereinafter, the present invention will be described with reference to the embodiments shown in the attached drawings. 1 is a longitudinally split precast reinforced concrete beam member on both sides, and a large number of rectangular reinforcing bars 2, 2', 2, etc. are connected at regular intervals. The Nada reinforcing bars and the upper main reinforcements 3, 3', 3'' are arranged in parallel, and the lower end main reinforcements 4, 4', 3'' are arranged in parallel.
4'' are similarly integrated to form a reinforcing bar cage, and the majority of the reinforcing bars 2, 2', 2 are connected in parallel, except for one side and a portion of the two adjacent sides. It is made by pouring concrete so as to be embedded in the concrete frame. 5 is an intermediate auxiliary vertically split precast reinforced concrete beam member, and evenly rectangular deep reinforcing bars 6, 6', 6'' are used.・
... are arranged in parallel at regular intervals, and upper end main reinforcements 7, 7', 7'' and lower end main reinforcements 8, 8', 8 are placed below the upper and lower sides of these rectangular deep reinforcing bars. '' are arranged in parallel and piled up to form a reinforcing bar cage, and the center portions of the upper and lower two sides of the many parallel reinforcing bars 6, 6', 6'', etc. of this reinforcing bar cage are concreted. It is embedded in the body of the sea bream and has both sides protruding from the inside of the concrete body of the sea bream.
次に、このようにして製した縦割りしたプレキャスト鉄
筋コンクリート梁部材2個を互にその磯断補強筋の突出
する部分を対向せしめて立設し、該籾断補強筋を互い違
いに挿入させて第2図のような状態とし、これらの奥断
補強筋の重複部分を貫通して、上端主筋9,9′ならび
に下端主筋l0,10′を挿入してそれぞれ敷断補強筋
に累結したのち、底面部分には必要な型枠またはプレキ
ャスト版等を配して両縦割りプレキャスト鉄筋コンクリ
ート梁部材間にコンクリートを打設して梁として完成す
るものである。しかして、大梁の場合は第3図に示すよ
うにこの中間用補強縦割りプレキャスト鉄筋コンクリー
ト梁部材5の両側に縦割りプレキャスト鉄筋コンクリー
ト梁部材1,1′を配し、三者の縦割りプレキャスト鉄
筋コンクリート梁部村1,5,1′から突出している雛
断補強筋の重複部分に梁主筋11,11′,12,12
′を貫通せしめ、このニ者の間隙部分に必要な型枠また
はプレキャスト版等を配してのち、この間隙部分にコン
クリートを打設して大梁は完成するものである。Next, the two vertically split precast reinforced concrete beam members manufactured in this manner are erected with the protruding parts of the rock reinforcement bars facing each other, and the rice hull reinforcement bars are inserted alternately. After making the state as shown in Figure 2, passing through the overlapping part of these deep reinforcement bars, inserting the upper end main reinforcements 9, 9' and the lower end main reinforcements 10, 10', and connecting them to the bottom reinforcement bars, respectively. Necessary formwork or precast slabs are placed on the bottom part, and concrete is poured between both vertically split precast reinforced concrete beam members to complete the beam. In the case of a large beam, as shown in FIG. Beam main reinforcements 11, 11', 12, 12 are installed in the overlapping parts of the reinforcement bars protruding from sections 1, 5, 1'.
′ is penetrated, and necessary formwork or precast slabs are placed in the gap between the two, and then concrete is poured into the gap to complete the girder.
本発明になる縦割りプレキャスト鉄筋コンクリート梁部
村は上記の通りの構造で、かつ、上記のように使用する
ものなので、建方に際して錫重機は小型のものでたり、
かつまた、プレキャスト部材と現場施工を折衷すること
による工期の短縮と工費の低廉化に成功したものである
。Since the vertically divided precast reinforced concrete beam village according to the present invention has the structure as described above and is used as described above, the tin heavy machinery used for erection is small.
Moreover, by combining precast parts and on-site construction, we succeeded in shortening the construction period and reducing construction costs.
第1図は縦割りブレキャスト鉄筋コンクリート梁部材の
斜視図、第2図は岡部材で、梁を構成した際の断面図、
第3図は補強の部材を用いて大梁を構成した際の断面図
を示す。
1,1′・・・・・・両側の縦割りプレキャスト鉄筋コ
ンクリート梁部材、2,6・・・・・・敷断補強筋、3
,7,9,11・…・・上端主筋、4,8,10,12
・・・・・・下端主筋、5・・・・・・補助縦割りブレ
キヤスト鉄筋コンクリート梁部村。
第1図
策2図
第3図Figure 1 is a perspective view of a vertically split pre-cast reinforced concrete beam member, Figure 2 is a cross-sectional view of the Oka member when the beam is constructed,
FIG. 3 shows a cross-sectional view of a girder constructed using reinforcing members. 1, 1'... Vertical precast reinforced concrete beam members on both sides, 2, 6... Strengthening bars, 3
, 7, 9, 11...Top main reinforcement, 4, 8, 10, 12
...Lower end main reinforcement, 5...Auxiliary vertical break cast reinforced concrete beam village. Figure 1 Plan 2 Figure 3
Claims (1)
筋と主筋とを緊結した鉄筋籠の剪断補強筋の一辺とこれ
に相い隣接する二辺の大部分を躯体中に埋込するように
コンクリートを打設して製した両側の縦割りプレキヤス
ト鉄筋コンクリート梁部材と;均しく矩形の剪断補強筋
を一定間隔をおいて並列に配置し、これに主筋を緊結し
た鉄筋籠の剪断補強筋の対向二辺の中央部分を躯体中に
埋込した補強縦割りプレキヤスト鉄筋コンクリート梁部
材とよりなる縦方向に分割したプレキヤスト鉄筋コンク
リート梁部材。1. A large number of rectangular shear reinforcing bars are arranged in parallel, and one side of the shear reinforcing bars and most of the two adjacent sides of the reinforcing bars of the reinforcing bar cage, in which the shear reinforcing bars and the main bars are tied together, are embedded in the frame. Vertical precast reinforced concrete beam members on both sides made by pouring concrete; Shear reinforcement bars of a reinforcing bar cage with evenly rectangular shear reinforcement bars arranged in parallel at regular intervals and the main reinforcements tied to these. A vertically divided precast reinforced concrete beam member consisting of reinforced vertically divided precast reinforced concrete beam members whose central portions on two opposing sides are embedded in the frame.
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
JP14492076A JPS6022151B2 (en) | 1976-12-01 | 1976-12-01 | Precast reinforced concrete beam section split vertically |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
JP14492076A JPS6022151B2 (en) | 1976-12-01 | 1976-12-01 | Precast reinforced concrete beam section split vertically |
Publications (2)
Publication Number | Publication Date |
---|---|
JPS5369417A JPS5369417A (en) | 1978-06-20 |
JPS6022151B2 true JPS6022151B2 (en) | 1985-05-31 |
Family
ID=15373297
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
JP14492076A Expired JPS6022151B2 (en) | 1976-12-01 | 1976-12-01 | Precast reinforced concrete beam section split vertically |
Country Status (1)
Country | Link |
---|---|
JP (1) | JPS6022151B2 (en) |
Cited By (2)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
JPH02128622A (en) * | 1988-11-07 | 1990-05-17 | Kureha Chem Ind Co Ltd | Molded material for plant culture |
JPH02145133A (en) * | 1988-11-28 | 1990-06-04 | Kureha Chem Ind Co Ltd | Granular material for cultivating plant |
Families Citing this family (3)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
JPS60215959A (en) * | 1984-11-26 | 1985-10-29 | 株式会社大林組 | Precast reinforced concrete pillar member divided in longitudinal direction |
JPH0280746A (en) * | 1988-09-14 | 1990-03-20 | Supankuriito Seizo Kk | Precast beam |
JPH02144915U (en) * | 1989-05-11 | 1990-12-10 |
-
1976
- 1976-12-01 JP JP14492076A patent/JPS6022151B2/en not_active Expired
Cited By (2)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
JPH02128622A (en) * | 1988-11-07 | 1990-05-17 | Kureha Chem Ind Co Ltd | Molded material for plant culture |
JPH02145133A (en) * | 1988-11-28 | 1990-06-04 | Kureha Chem Ind Co Ltd | Granular material for cultivating plant |
Also Published As
Publication number | Publication date |
---|---|
JPS5369417A (en) | 1978-06-20 |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
CN106639037A (en) | Energy-dissipation and seismic-mitigation oblique prestress shear wall structural system suitable for prefabrication and assembly construction | |
US20090120025A1 (en) | Prefabricated concrete reinforcement system | |
CN206428853U (en) | A kind of oblique prestressed shear wall structure system of the energy-dissipating and shock-absorbing for being applicable prefabrication and assembly construction | |
KR101519086B1 (en) | Bridg using t-girder with pile supporting apparatus and bridge continuous construction method using the same | |
CN113638491A (en) | Assembled beam-column connecting joint and construction method thereof | |
JPH042725B2 (en) | ||
JPS6022151B2 (en) | Precast reinforced concrete beam section split vertically | |
JP2001303584A (en) | Structure for connecting head of foundation pile with footing | |
JP2622013B2 (en) | Reinforced concrete shear wall structure | |
JPS58199957A (en) | Composite reinforced concrete structure | |
JPS6134539B2 (en) | ||
US1508325A (en) | Concrete building construction | |
JPH0326736B2 (en) | ||
JP6684088B2 (en) | Seismic retrofitting structure and method for existing buildings | |
CN108716246A (en) | Frame structure system | |
JPH0333856B2 (en) | ||
CN216428794U (en) | Assembled multi-cavity composite concrete frame column | |
CN216740879U (en) | Underground prefabricated assembly type stereo parking garage | |
KR102415136B1 (en) | Optimized two-way precast concrete block slab | |
JPS63184609A (en) | Method for constructing underground continuous wall | |
JPH06158863A (en) | Method for constructing concrete frame | |
JPS6311499B2 (en) | ||
JPS6335773B2 (en) | ||
JPH06158712A (en) | Construction method of beam | |
JPH02236328A (en) | Construction method for super-highrice building |