JPS60119823A - Construction work of caisson operation chamber and soil centre therefor - Google Patents
Construction work of caisson operation chamber and soil centre thereforInfo
- Publication number
- JPS60119823A JPS60119823A JP22440183A JP22440183A JPS60119823A JP S60119823 A JPS60119823 A JP S60119823A JP 22440183 A JP22440183 A JP 22440183A JP 22440183 A JP22440183 A JP 22440183A JP S60119823 A JPS60119823 A JP S60119823A
- Authority
- JP
- Japan
- Prior art keywords
- sand
- caisson
- center
- earth
- hole
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Granted
Links
Classifications
-
- E—FIXED CONSTRUCTIONS
- E02—HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
- E02D—FOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
- E02D23/00—Caissons; Construction or placing of caissons
- E02D23/08—Lowering or sinking caissons
Landscapes
- Engineering & Computer Science (AREA)
- Life Sciences & Earth Sciences (AREA)
- General Life Sciences & Earth Sciences (AREA)
- Mining & Mineral Resources (AREA)
- Paleontology (AREA)
- Civil Engineering (AREA)
- General Engineering & Computer Science (AREA)
- Structural Engineering (AREA)
Abstract
Description
【発明の詳細な説明】
本発明はケーソン作業室の施工法及びこの施工に用いる
土砂セントルに関するものである。DETAILED DESCRIPTION OF THE INVENTION The present invention relates to a method of constructing a caisson work chamber and an earth and sand center used in this construction.
従来、土砂セントルを用いてケーソン工事を行う場会に
は、まず施工すべき位置の地盤上に盛土により土砂セン
トルを造成し、ついでこの土砂セントル上にケーソンの
Ml躯体を形成し、七の後この躯体のシャフト孔を利用
して入力により初期掘削をして、土砂セントル内に作業
孔を設け、この作業孔内でシャフト孔を通じて降ろした
掘削機械10品を組み立てて、組立て後に土砂セントル
を機械掘削して第1躯体の下方に作業室を施工するもの
であった。しかしながらこの施工法に↓ると。Conventionally, when constructing a caisson using an earth and sand center, the earth and sand center is first created using embankment on the ground at the location where the construction is to be performed, then the Ml frame of the caisson is formed on this earth and sand center, and after Initial excavation is performed by input using the shaft hole of this frame, a working hole is created in the earth and sand center, and the 10 excavating machines that are lowered through the shaft hole are assembled in this working hole, and after assembly, the earth and sand center is machined. This involved excavating and constructing a work room below the first frame. However, with this construction method.
初期掘削としての作業孔を入力に工9掘削して形成する
ので、機械掘削に至るまでに入手と時間がかかる問題が
あった。Since the initial excavation hole is formed by drilling 9 drills as input, there is a problem in that it takes time to obtain materials before mechanical excavation.
本発明の目的は作業孔の施工作業をiKj累化して、機
械掘削に至るまでの作業の省力化と迅速化とを図ること
にある。An object of the present invention is to accumulate the work of constructing a working hole to save labor and speed up the work up to mechanical excavation.
本発明の万石工法においては、土砂セントルとして施工
されるべきケーソンのシャフト孔のF部のこれと対向す
る位置のセントル内glIに、予め砂入り缶等の仮埋設
支保体を埋込んだものを用いる。In the Mangoku construction method of the present invention, a temporary buried support such as a sand-filled can is embedded in advance in the center glI at a position opposite to the F section of the shaft hole of the caisson to be constructed as an earth and sand center. Use.
この埋設支保体は上記シャフト孔から第1躯体外へ取り
出し得る大きさと型銅’t N−fる。そして施工法は
、まず、上記土砂セントル上にケーソンの第1@体を施
工し、ついでこの第1@体のシャフト孔を利用して、埋
込んである支保体を重体上刃へ引き上げ、この引上げに
よって土砂セントル内に孔ができ、この孔を作業孔とし
てこの孔内でllj削機械の組立てを行ってから、土砂
セントルの機械掘削等の掘削をして、第1扇体F力に作
業室を施工するものである。This buried support has a size and type that allows it to be taken out of the first body through the shaft hole. The construction method is to first construct the first body of the caisson on the earth and sand center, then use the shaft hole of this first body to pull up the embedded support to the upper blade of the heavy body. A hole is created in the earth and sand center by pulling up, and this hole is used as a working hole. After assembling the llj excavation machine in this hole, excavation such as mechanical excavation of the earth and sand center is carried out, and work is performed on the first fan F force. The purpose is to construct a room.
以F本発明の一実施例を図面に基づいて説明する。Hereinafter, one embodiment of the present invention will be described based on the drawings.
まず本発明に係る土砂セントルの具体的構成を説明し、
次にこの土砂セントルを用いて行う作業室の施工法を説
明1−る。First, the specific structure of the sediment center according to the present invention will be explained,
Next, we will explain how to construct a work room using this earth and sand center.
第1.2図において、土砂セントルlは地盤上に高さ2
mの盛土により造成したものである。この土砂セントル
内には、その外表面で受けているケーソンの第1躯体2
のシャフト孔2a及び2bと対向する位置に、仮埋設支
保体としての砂入り山3がM足数予め埋込んでめる。f
なわち作来員が利用するシャフト孔2aと対向する位置
には、9本の砂入り缶3・・・が、下段に5本、上段に
4本と積上げた状態で埋設してあり、掘削機械部品等の
運搬路として利用するシャフト孔2bと対向する位置に
は、20本の砂−人シ缶3・・・が、上F段各lO本ず
つ積上げた状態で埋設しである。In Figure 1.2, the sediment center l is located at a height of 2 above the ground.
It was created using an embankment of m. Inside this earth and sand center is the first frame 2 of the caisson, which is supported on its outer surface.
M feet of sand-filled mounds 3 as temporary buried supports are embedded in advance in positions facing the shaft holes 2a and 2b. f
In other words, in a position facing the shaft hole 2a used by the cultivation workers, nine cans 3 containing sand are buried in a stacked state, five at the bottom and four at the top. At a position facing the shaft hole 2b used as a conveyance path for mechanical parts, etc., 20 sand canisters 3 are buried, stacked one on top of the other in each of the upper F tiers.
砂入ジ缶3は、第3.4図に示すように高さ約900+
m、外径が約550mmのドラム缶状のもので、内部一
杯に砂が収納しである。砂入り缶の外面には、縦方向及
び水平方向にそ扛ぞn補強筋4及び4aが溶接してあジ
、縦方向の補強筋4は水平方向の補強筋4a工9幾分太
いものを用いである。砂入り缶3の上端部にはワイヤか
らなる吊シ紐5が取り付けCある。The sand canister 3 has a height of about 900+ as shown in Figure 3.4.
It is a drum-shaped container with an outer diameter of approximately 550 mm, and is filled with sand. On the outer surface of the sand can, reinforcing bars 4 and 4a are welded vertically and horizontally, and the vertical reinforcing bars 4 and 9 are somewhat thicker. It is useful. A hanging cord 5 made of wire is attached to the upper end of the sand can 3.
土砂セントルlの外表面は捨てコンクリート6で岐覆し
てりる。The outer surface of the earth and sand center 1 is covered with waste concrete 6.
なお、第l@体2の外周の刃口は地盤G中に打込んであ
る杭7上で支持されている。Note that the cutting edge on the outer periphery of the first body 2 is supported on a pile 7 driven into the ground G.
次に第1一体の作業室の施工法を、土砂セントルの施工
作業と共に説明′Tる。Next, the construction method for the first integrated work chamber will be explained along with the construction work for the earth and sand center.
まず、施工さ扛るべきケーソンの第1躯体2゜シャフト
孔2a 、2bに対向する位置の地盤G上の2個所に砂
入り缶3・・・k 11次積重ね、ついで盛土をして砂
入り缶全埋設しく第5図)、その後に盛土の外表面に捨
てコンクリート6を打設し−C外表面′f:榎って、土
砂セントルlの造成を終える。First, sand-filled cans 3...k are stacked in two places on the ground G opposite to the shaft holes 2a and 2b of the first frame of the caisson to be constructed. After fully burying the can (Fig. 5), concrete 6 is placed on the outer surface of the embankment, and the outer surface 'f: is removed to complete the creation of the earth and sand center 1.
そして土砂セントルl上に、第1図に示すように型枠全
組立て、配筋し、コンフリートラ打設して・ ケーソン
の第1躯体2を形成する。その鏝、この第1躯体に設け
たシャフト孔2a 、2bを利用して、クレーンにて順
次砂入シ缶3・・・を第l@体外へ取り出す。最初の1
〜2本を収り出す時に、街と缶の間隙に詰まっている土
砂を取り除くために、この間隙にジェットを使用丁れば
、その引上げが円滑となる。すべての砂入り缶3を引上
げ牡ば、土砂セントルl内の2個所には、第6図に示す
ように各シャフト孔2a、2bと対向する位置に作業孔
1a及び1bがそれぞれ形成される。各作業孔内及び周
辺を必硬に応じて掘削整地して、一方のシャフト孔2b
からil削機械部品等全作業孔lb内に降ろし、機械組
立てをしてから掘削機械にエリ、また必做に応じて入力
により土砂セントルlを掘削して、第7図に示jように
第1鴫体2のF方に作業室8を形成する。Then, as shown in Fig. 1, the formwork is completely assembled, reinforcement is placed, and a comfleet track is cast on the earth and sand center l to form the first frame 2 of the caisson. Using the iron and the shaft holes 2a and 2b provided in the first body, the sand cans 3 are sequentially taken out of the first body by a crane. first 1
~ When removing the two cans, if you use a jet in the gap between the city and the can to remove the dirt stuck in the gap, the lifting will be smooth. When all the sand cans 3 are pulled up, two working holes 1a and 1b are formed in the sand center 1 at positions facing the shaft holes 2a and 2b, respectively, as shown in FIG. Excavate and level the ground in and around each work hole as required, and then drill one shaft hole 2b.
All the parts of the excavating machine are lowered into the working hole lb, and after the machine is assembled, the excavating machine is moved to the excavation machine. 1. A working chamber 8 is formed on the F side of the body 2.
なお、砂入シ缶3としてドラム缶状のものを用いれば、
安価で槓重ね及び撤去作業が迅速に行えるが、必ずしも
砂入りのものに限定されず・砂に代えて土、砕石等でお
ってもよい。缶の本数も、土砂セントルの商さ、ケーソ
ンの第1@体の大きさ等にエリ適宜選択的である。//
Jra、仮埋設支保体は缶に眠ら扛るものではl工く、
砂製等であってもよい。In addition, if a drum-shaped one is used as the sand canister 3,
Although it is inexpensive and allows quick stacking and removal work, it is not necessarily limited to those containing sand; earth, crushed stone, etc. may be used instead of sand. The number of cans can also be selected depending on the quotient of the sediment center, the size of the first body of the caisson, etc. ///
JRA, the temporary burial support is not something that can be stored in a can.
It may be made of sand or the like.
以上説明したように本発明に工nば、従来のように入力
掘削により作業孔を施工する必要がないので、この作業
孔の施工作業が簡素化でき、したがって作業孔を利用し
て機械掘削ができるまでの作業の省力化及び迅速化を図
ることができる。また仮埋設支保体の体積に相当する量
の盛土用土砂を節約できる。As explained above, if the present invention is used, there is no need to construct a working hole by input drilling as in the conventional method, so the construction work of this working hole can be simplified, and therefore mechanical excavation using the working hole can be performed. It is possible to save labor and speed up the work until completion. Furthermore, it is possible to save earth and sand for embankment in an amount equivalent to the volume of the temporary burial support.
第1図は施工状態を示す縦断面図、
第2図は第1図の平面図、
第3図は砂入り缶の正面図、
請4図は第3図バーバ線断面図、
粛5図は砂人缶を埋設した状態を示す断面図、第6図は
砂人缶を取出した状態を示j断面図、第7図は作業室を
施工した状態を示す断面図である。
1・・・土砂セントル、la、1b°・・作業孔、2°
°。
第1堝体、2a 、2b・・・シャフト孔、3・・・砂
入シ缶、5・・・吊り紐、8・・・作業室。
以 上
第2図
第3図Figure 1 is a longitudinal sectional view showing the construction status, Figure 2 is a plan view of Figure 1, Figure 3 is a front view of the sand can, Figure 4 is a cross-sectional view along the line in Figure 3, and Figure 5 is a cross-sectional view of the can. FIG. 6 is a cross-sectional view showing a state in which the sandman can is buried, FIG. 6 is a cross-sectional view showing a state in which the sandman can is removed, and FIG. 7 is a cross-sectional view showing a state in which a work chamber has been constructed. 1... Earth and sand center, la, 1b°... working hole, 2°
°. First carton, 2a, 2b...shaft hole, 3...sand canister, 5...hanging string, 8...work chamber. Above Figure 2 Figure 3
Claims (1)
その後この第1躯体に設りであるシャフト孔と対向する
位置の土砂セントル内部に埋込んである仮埋設支保体を
上記シャフト孔を利用してクレーン等で第l堝体外力へ
取り出し、そしてこの仮埋膜支持体の撤去によって土砂
セントル内に生じた孔を作業孔として、この孔内で機械
掘削等の掘削をして第1躯体F力に作業室を形成するこ
とを%敵とするケーソン作業室の施工法。 (2) 施工さnるべきケーソンの第1@体のシャフト
孔に対向する位置の土砂セントル内部に、仮埋設支保体
を理込んであり、この仮埋設支保体は上1已シャフト孔
よりu”r 1 ’AA体夕$へ取出し1■能の大きさ
と重量を有することを特徴とするケーソン作業室の施工
に用いる土砂セントル。 (3)特許請求の範囲第2項において、仮埋設支保体は
吊り紐を取シ付けているドラム缶状の砂入り缶であるこ
とを特徴とする土砂セントル。[Claims] (Li) Constructing the first frame of the caisson on the soil center,
After that, the temporary buried support buried inside the earth and sand center at a position opposite to the shaft hole provided in this first body is taken out to the outside force of the first body using a crane or the like using the shaft hole. The hole created in the soil center by the removal of the temporary burial membrane support is used as a working hole, and the caisson is designed to form a working chamber in the first frame F force by excavating by mechanical excavation or the like in this hole. Construction method of work room. (2) A temporary buried support is embedded inside the earth and sand center at a position opposite to the shaft hole of the first body of the caisson to be constructed, and this temporary buried support is located one foot above the shaft hole. An earth and sand center used in the construction of a caisson work chamber, characterized in that it has a size and weight that can be taken out from an AA body. (3) In claim 2, a temporary burial support A sand center is characterized by being a drum-shaped sand-filled can with a hanging string attached.
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
JP22440183A JPS60119823A (en) | 1983-11-30 | 1983-11-30 | Construction work of caisson operation chamber and soil centre therefor |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
JP22440183A JPS60119823A (en) | 1983-11-30 | 1983-11-30 | Construction work of caisson operation chamber and soil centre therefor |
Publications (2)
Publication Number | Publication Date |
---|---|
JPS60119823A true JPS60119823A (en) | 1985-06-27 |
JPS6143496B2 JPS6143496B2 (en) | 1986-09-27 |
Family
ID=16813172
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
JP22440183A Granted JPS60119823A (en) | 1983-11-30 | 1983-11-30 | Construction work of caisson operation chamber and soil centre therefor |
Country Status (1)
Country | Link |
---|---|
JP (1) | JPS60119823A (en) |
Families Citing this family (2)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
JP2003020656A (en) * | 2001-07-05 | 2003-01-24 | Taisei Corp | Caisson construction method |
JP2016520461A (en) | 2013-06-06 | 2016-07-14 | スリーエム イノベイティブ プロパティズ カンパニー | Continuously peelable coextruded polymer film with antimicrobial embedded layer |
-
1983
- 1983-11-30 JP JP22440183A patent/JPS60119823A/en active Granted
Also Published As
Publication number | Publication date |
---|---|
JPS6143496B2 (en) | 1986-09-27 |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
CN114108654A (en) | Construction method for removing obstacles in foundation pit area invaded by pressure-bearing water dock | |
JP6595825B2 (en) | Underground building construction method | |
JP2019148070A (en) | Construction method of underground structure | |
JPS60119823A (en) | Construction work of caisson operation chamber and soil centre therefor | |
CN111042104A (en) | Method for constructing diaphragm wall at existing underground structure | |
CN210163888U (en) | Quick construction structure of major diameter socketed pile | |
WO2021160798A1 (en) | Method for introducing a soil penetrating tool into a soil and underground construction device | |
JPS59179993A (en) | Method of constructing shaft | |
KR20210051326A (en) | Batch down wall demolition method | |
US2003393A (en) | Method of forming piles | |
JPH0442498B2 (en) | ||
JP7049976B2 (en) | Construction method of Shinbashira | |
CN112112170B (en) | Construction process for manually digging hole and pouring pile in weakly weathered rock or moderately weathered rock stratum area | |
CN106337433A (en) | Construction method and device on basis of sandy stratums prone to liquefaction under vibration | |
TW322522B (en) | C-pile wall method | |
US1665797A (en) | Method of excavating and producing foundations | |
JP2750442B2 (en) | Caisson and its construction method | |
JPH07102557A (en) | Rotation drive method for surface casing for underground vertical shaft excavation work | |
JP3179243B2 (en) | Concrete placement method for deep foundation work | |
JP2553987B2 (en) | Deep foundation foundation excavation construction method | |
JPS6332929B2 (en) | ||
JP2821933B2 (en) | Underground structure construction method | |
JPS5921831A (en) | Reverse placement work | |
JPS62129423A (en) | Construction method for foundation | |
JPS6229625A (en) | Settling construction for open caisson |