JPS5977276A JP18837982A JP18837982A JPS5977276A JP S5977276 A JPS5977276 A JP S5977276A JP 18837982 A JP18837982 A JP 18837982A JP 18837982 A JP18837982 A JP 18837982A JP S5977276 A JPS5977276 A JP S5977276A
Authority
JP
Japan
Prior art keywords
water
ice
dehydration
counter
water supply
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Granted
Application number
JP18837982A
Other languages
Japanese (ja)
Other versions
JPH0333995B2 (en
Inventor
広瀬 謙司
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Panasonic Holdings Corp
Original Assignee
Matsushita Refrigeration Co
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Matsushita Refrigeration Co filed Critical Matsushita Refrigeration Co
Priority to JP18837982A priority Critical patent/JPS5977276A/en
Publication of JPS5977276A publication Critical patent/JPS5977276A/en
Publication of JPH0333995B2 publication Critical patent/JPH0333995B2/ja
Granted legal-status Critical Current

Links

Landscapes

  • Production, Working, Storing, Or Distribution Of Ice (AREA)

Abstract

(57)【要約】本公報は電子出願前の出願データであるた
め要約のデータは記録されません。
(57) [Summary] This bulletin contains application data before electronic filing, so abstract data is not recorded.

Description

【発明の詳細な説明】 産業上の利用分野 本発明は水道直結型の製氷機、すなわち貯水タンク内の
水位に応じて必要時に水道水を自動的に導入し得る製氷
機において、水道の断水検知を行なう断水検知手段を備
えた製氷機に関する。
DETAILED DESCRIPTION OF THE INVENTION Field of Industrial Application The present invention relates to an ice maker that is directly connected to a water supply system, that is, an ice maker that can automatically introduce tap water when necessary according to the water level in a water storage tank. The present invention relates to an ice maker equipped with water cutoff detection means.

従来例の構成とその問題点 水道直結型の製氷機において、断水時には製氷部材上を
水が、循環しないため氷の生成はなさ汎ない。この様々
状況下においても現状の製氷機では簡便な断水検知方法
がなかっただめ、通常の運転動作を断続する事もなシ、
このため電力の消費がなされたり適冷却による機器の破
損等の問題かあった。
Conventional Structure and Problems In an ice maker that is directly connected to the water supply, ice is not produced because water does not circulate over the ice maker when the water supply is cut off. Even under these various circumstances, the current ice maker does not have to interrupt normal operation because there is no simple way to detect water outage.
This led to problems such as power consumption and equipment damage due to improper cooling.

発明の目的 そこで本発明は製氷機の機能、つまり給水動作と と脱水動作利用する事により、簡単に断水検知し、もっ
て断水時の電力消費低減、機器の破損防止を計る事を目
的としている。
Purpose of the Invention Therefore, the present invention aims to easily detect a water outage by utilizing the functions of an ice maker, that is, water supply operation and dehydration operation, thereby reducing power consumption and preventing equipment damage during water outage.

発明の構成 この目的を達成するために、以下の様な構成としている
。すなわち、製氷機の貯水タンク内に設けた下限設定ス
イッチにて製氷完了を検出し、脱水開始を行ないこの時
2種類のカウンタを同時に作動させる。一方のカウンタ
は貯水タンク内に設けた上限設定スイッチが作動した時
、すなわち給水完了と同時に停止させ、又他方のカウン
タは製氷部材に密着させて設置した脱水検知装置の作動
、すなわち、脱水完了と共に停止させる。この2種類の
カウンタ時間を判断回路にて判断させるわけであるが、
通常、脱水に要する時間より、給水に要する時間の方が
短い事が実測されているため、上記判断回路にて判別し
たものが、脱水時間の方が、給水時間より長ければ正常
、逆であれば断水である事を判別して制御装置により製
氷運転を停止させるようにしたものである。
Structure of the Invention In order to achieve this object, the following structure is adopted. That is, the completion of ice making is detected by a lower limit setting switch provided in the water storage tank of the ice maker, dehydration is started, and at this time two types of counters are operated at the same time. One counter is stopped when the upper limit setting switch installed in the water storage tank is activated, that is, when the water supply is completed, and the other counter is activated when the dehydration detection device installed in close contact with the ice making member is activated, that is, when the dehydration is completed. make it stop. These two types of counter times are judged by a judgment circuit,
It has been actually measured that the time required for water supply is usually shorter than the time required for dehydration, so if the judgment circuit above determines that the dehydration time is longer than the water supply time, it is normal, and vice versa. For example, the system detects that there is a water outage and uses a control device to stop the ice-making operation.

実施例の説明 以下に本発明の一実施例を図面に基づき説明する。第1
図は、本発明の製氷機の一例を示しており、1は断熱壁
にて形成されている製氷機本体であり、製氷室2と機械
室3から構成され、製氷室2内には蒸発器4を具備する
製氷部材5が傾斜設置され、又、製氷用水を貯溜する貯
水タンク6及びこのタンク6内に循環水ポンプ装置7を
装設して流水循環式製氷系統が構成されている。前記製
氷部材5の下方に貯氷室8及び脱氷後の板氷を受は所定
の大きさの氷塊に切断する板氷切断用ヒータ装置9を設
けている。又、機械室3には蒸発器4と共に冷凍回路を
形成する電動圧縮機1o及び凝縮器11を配置している
。12は凝縮器11の空冷用ファンである。又13は前
記貯水室8内の所定水量を検出する感温部を持った貯水
量検出装置で、氷塊の接触温度を感知して全ての製氷運
転を停止する様に設けられている。
DESCRIPTION OF EMBODIMENTS An embodiment of the present invention will be described below with reference to the drawings. 1st
The figure shows an example of an ice maker according to the present invention. 1 is an ice maker main body formed of a heat insulating wall, and is composed of an ice making compartment 2 and a machine compartment 3. The ice making compartment 2 has an evaporator An ice-making member 5 having an ice-making member 4 is installed at an angle, and a water storage tank 6 for storing ice-making water and a circulating water pump device 7 are installed in this tank 6 to constitute a flowing water circulation type ice-making system. An ice storage chamber 8 and an ice cube cutting heater device 9 are provided below the ice making member 5, and an ice cube cutting heater device 9 is provided for cutting ice cubes into ice blocks of a predetermined size after deicing. Further, in the machine room 3, an electric compressor 1o and a condenser 11, which together with the evaporator 4 form a refrigeration circuit, are arranged. 12 is an air cooling fan for the condenser 11. Further, reference numeral 13 denotes a water storage amount detection device having a temperature sensing portion for detecting a predetermined amount of water in the water storage chamber 8, and is provided so as to sense the contact temperature of the ice block and stop all ice making operations.

14は水源(水道)に接続された給水管路15を電気的
に開閉し貯水タンク6内に製氷水を導入する給水弁であ
る。貯水タンクθ内には、所定水位を維持する排水パイ
プ16と、水位17を検出する上限設定スイッチ18と
下限設定スイッチ19が配置されている。
A water supply valve 14 electrically opens and closes a water supply pipe 15 connected to a water source (water supply) to introduce ice-making water into the water storage tank 6. Inside the water storage tank θ, a drain pipe 16 for maintaining a predetermined water level, and an upper limit setting switch 18 and a lower limit setting switch 19 for detecting the water level 17 are arranged.

2oは製氷部材5に生成した氷を脱水する際、蒸発器4
に電動圧縮機1oより流すホットガスを電気的に制御す
る電磁弁である。
2o is the evaporator 4 when dehydrating the ice generated in the ice making member 5.
This is a solenoid valve that electrically controls the hot gas flowing from the electric compressor 1o.

21は製氷部材6に接着させてこの製氷部材50所定温
度」二昇によって脱水終了を検出する脱水検知装置であ
る。
Reference numeral 21 denotes a dehydration detection device which is attached to the ice making member 6 and detects the completion of dehydration when the ice making member 50 reaches a predetermined temperature.

第2図は上記製氷機の制御装置を示すブロック図である
。前記循環水ポンプ装置了、電動圧縮機10、及び空冷
用ファン12はマイクロコンピュータ22の出力01 
 よりドライバー23を介し、リレー24にて駆動され
る。又、同様に前記給水弁14はマイクロコンピュータ
22の出力02  よりドライバー25を介し、リレー
26で、前記電磁弁20は出力03よりドライバー27
を介しリレー28で、前記板状氷切断用ヒータ装置9は
出力o4 よりドライバー29を介しリレー30にて各
々駆動される様設計されている。
FIG. 2 is a block diagram showing a control device for the ice making machine. The circulating water pump device, electric compressor 10, and air cooling fan 12 are controlled by the output 01 of the microcomputer 22.
It is driven by a relay 24 via a driver 23. Similarly, the water supply valve 14 is connected to the output 02 of the microcomputer 22 via the driver 25 and the relay 26, and the solenoid valve 20 is connected to the output 03 of the microcomputer 22 via the driver 27.
The plate ice cutting heater device 9 is designed to be driven by the output o4 via a driver 29 and a relay 30, respectively.

また31は前記下限設定スイッチ19をS入力(セット
入力)に、前記上限設定スイッチ18をR入力(リセッ
ト入力)に接続した第1のRSフリップフロップであり
、この出力の内Q1  出力は第1のカウンタ32のカ
ウント開始入力である01人力に接続され、Q2 出力
はカウント停止入力である02人力に接続されている。
31 is a first RS flip-flop in which the lower limit setting switch 19 is connected to the S input (set input) and the upper limit setting switch 18 is connected to the R input (reset input); The Q2 output is connected to 02 manual power, which is the count start input of the counter 32, and the Q2 output is connected to 02 manual power, which is the count stop input.

同様に、33は前記下限設定スイッチ19をS入力(カ
ット入力)に、前記脱水検知装置21をR入力(リセッ
ト入力)に接続した第2のRSフリソゲフロップであり
、Ql  出力は第2のカウンタ34のカウント開始人
力C1に、Q2出力はカウント停止人力C2に接続され
ている。
Similarly, numeral 33 is a second RS Frisogeflop in which the lower limit setting switch 19 is connected to the S input (cut input), the dehydration detection device 21 is connected to the R input (reset input), and the Ql output is connected to the second counter 34. The output of Q2 is connected to the human power C1 for starting the count and the human power C2 for stopping the count.

尚36は前記第1のカウンタ32及び第2のカウンタ3
4を動作させるクロックパルス発生回路である。
Note that 36 represents the first counter 32 and the second counter 3.
This is a clock pulse generation circuit that operates 4.

マタ、マイクロコンピュータ22の入力端子にはD1〜
D5まであり、前記下限設定スイッチ19の出力を入力
信号D1  として、上限設定スイッチ1Bの出力をD
2 として、第10カウンタ32の出力をD3 として
、脱水検知装置の出力をD4 として、そして、第20
カウンタ34の出力をD5 として入力する様に設計坏
れている。前記マイクロコンピユータ22は判断回路3
6を内蔵しており、これには前記第1のカウンタ32及
び第2のカウンタ34の出力、すなわち入力信号D3 
及びD5が接続されており、いずれのカウンタ時間が長
いかを判断するものである。
The input terminal of the microcomputer 22 is D1~
D5, the output of the lower limit setting switch 19 is used as the input signal D1, and the output of the upper limit setting switch 1B is inputted to D5.
2, the output of the 10th counter 32 is D3, the output of the dehydration detection device is D4, and the 20th
It is designed so that the output of the counter 34 is input as D5. The microcomputer 22 is a judgment circuit 3.
6, which includes the outputs of the first counter 32 and the second counter 34, that is, the input signal D3.
and D5 are connected, and it is determined which counter time is longer.

第3図は本実施例の製氷機において、脱水及び給水に要
する時間を外気温をパラメータとして示した表であり、
この値は冷凍能力及び給水能力等によって変動するが、
例えば電動圧縮機1oの出力180W製氷部材6の面積
700 cnI、貯水タンクの貯水量1600m1及び
水圧I Kg/ Cmの製氷機にて実測したものであり
、条件的にはこの種の製氷機として一般的なものである
FIG. 3 is a table showing the time required for dehydration and water supply in the ice making machine of this embodiment, using outside temperature as a parameter.
This value varies depending on refrigeration capacity, water supply capacity, etc.
For example, the measurements were taken using an ice maker with an electric compressor 1o output of 180W, an area of the ice making member 6 of 700 cnI, a water storage capacity of 1600 m1 in the water storage tank, and a water pressure of I Kg/Cm. It is something like that.

この第3図の値からもわかる様に、給水時間は脱水時間
の%以下であり、たとえ、給水水圧がかなり低下したと
しても、給水時間が脱水時間を上回る事は考えられず、
仮にこの様な現象が起ったとすればそれは断水としか判
断しえないものである。本発明の主要件はこの事実に基
づいて構成されている。
As can be seen from the values in Figure 3, the water supply time is less than % of the dehydration time, and even if the water supply pressure drops considerably, it is unlikely that the water supply time will exceed the dehydration time.
If such a phenomenon were to occur, it could only be interpreted as a water outage. The main feature of the invention is based on this fact.

次に上記構成における動作を第4図のフローチャートを
基に説明する。
Next, the operation of the above configuration will be explained based on the flowchart of FIG. 4.

まず運転スイッチ(図示せず)の投入により、マイクロ
コンピュータ22の出力信号01 がドライバー23を
動作させこれによりリレー24を動作し、電動圧縮機1
0.循環水ポンプ装置7及び空冷用ファンモータ12を
動かし、製氷が開始される(第4図イ)。つまり、循環
水ポンプ装置7によって貯水タンク6内の製氷水を製氷
部材5上に循環し、この製氷部材5上に氷層を形成する
ものである。
First, by turning on the operation switch (not shown), the output signal 01 of the microcomputer 22 operates the driver 23, which in turn operates the relay 24, and the electric compressor 1
0. The circulating water pump device 7 and the air cooling fan motor 12 are operated to start ice making (FIG. 4A). In other words, ice-making water in the water storage tank 6 is circulated over the ice-making member 5 by the circulating water pump device 7, and an ice layer is formed on the ice-making member 5.

この後、製氷の進み、貯水タンク6内の水位17が下降
して下限設定スイッチ19が作動すると(第4図口)マ
イクロコンピュータ22に入力信号D1  を与え、製
氷は完了し脱水が開始される。
After this, as the ice making progresses and the water level 17 in the water storage tank 6 falls and the lower limit setting switch 19 is activated (Figure 4), the input signal D1 is given to the microcomputer 22, and ice making is completed and dehydration is started. .

これと同時に前記下限設定スイッチ19の出力id第1
Rsフリップフロップ31及び第2のRSフリップフロ
ップ33のS入力を”ON”l、、第1、第2のRSフ
リッフリロツプ31.33のQ1出力から°’ ON 
”信号を出すだめ、第1のカウンタ32及び第2のカウ
ンタ34は同時に作動開始する。(第4図ハ及び二)。
At the same time, the output ID 1 of the lower limit setting switch 19
The S inputs of the Rs flip-flop 31 and the second RS flip-flop 33 are turned on, and the Q1 outputs of the first and second RS flip-flops 31 and 33 are turned on.
``When the signal is issued, the first counter 32 and the second counter 34 start operating at the same time (FIG. 4 C and 2).

他方マイクロコンピュータ出力は前記入力信号D1  
をうけとり、出、力信号o3がドライバー27を動作さ
せて、リレー28を働かせ、電磁弁2oを開き、蒸発器
4に電動圧縮機1oよりホットガスを流し、製氷部材6
に生成した氷を脱水する様になる。又、同時に出力信号
02がドライバー26を作動し、リレー26を働かせ給
水弁14を開き、給水を開始する(第4図示)。
On the other hand, the microcomputer output is the input signal D1.
The force signal o3 operates the driver 27, activates the relay 28, opens the solenoid valve 2o, causes hot gas to flow from the electric compressor 1o to the evaporator 4, and causes the ice making member 6 to flow.
This will dehydrate the ice that is generated. At the same time, the output signal 02 activates the driver 26, activates the relay 26, opens the water supply valve 14, and starts water supply (as shown in the fourth diagram).

この後、給水が進み、貯水量/り6に、給水管路15よ
り、給水された水位17が、上限設定スイッチ18まで
上昇するとマイクロコンピュータ22へ入力信号D2が
入り、給水を終了する(第4図へ)。
After that, water supply progresses, and when the water level 17 supplied from the water supply pipe 15 rises to the upper limit setting switch 18 when the water storage amount/6 is reached, the input signal D2 is input to the microcomputer 22, and the water supply is terminated. (See Figure 4).

この時前記上限設定スイッチ18は前記第1のRSフリ
ップ70ツブ31のR入力にも“’ ON ”信号を送
るため、第1のRSフリップフロップ31はQ2 出力
に” ON ”信号を発生し、第1のカウンタ32はC
2の停止入力をうけとることになり、第1のカウンタ3
2はカウント停止し、このカウント数をマイクロコンピ
ュータ220入力信号D3として送る(第4図ト)。
At this time, the upper limit setting switch 18 also sends an "ON" signal to the R input of the first RS flip 70 knob 31, so the first RS flip-flop 31 generates an "ON" signal at the Q2 output. The first counter 32 is C
2 stop input is received, and the first counter 3
2 stops counting, and sends this count number to the microcomputer 220 as an input signal D3 (FIG. 4-G).

この後さらに、脱水は進み、蒸発器4にとりつけだ脱水
検知装置21が作動し、脱水を検知するト、マイクロコ
ンピュータ22は入力信号D4ヲうけとり出力信号03
を○F F ” j、電磁弁20は停止され、脱水は解
除される(第4図チ)。
After this, the dehydration further progresses, and the dehydration detection device 21 attached to the evaporator 4 operates to detect the dehydration, and the microcomputer 22 receives the input signal D4 and outputs the output signal 03.
○F F "j, the solenoid valve 20 is stopped and dehydration is canceled (Fig. 4 H).

この時、前記脱水検知装置21の出力は同時に第2のR
Sフリップフロップ34のR入力にも” ON ”信号
を出力するため、このRSフリップフロップ34の02
 出力は”ON″′し、第2のカウンタ34は02人力
をうけとり、停止し、このカウント数をマイクロコンピ
ュータ220入力信号D6 として送る(第4図り)。
At this time, the output of the dehydration detection device 21 is simultaneously
Since the "ON" signal is also output to the R input of the S flip-flop 34, the 02
The output is turned "ON", the second counter 34 receives 02 human power, stops, and sends this counted number as the input signal D6 to the microcomputer 220 (fourth diagram).

この様にして送られた入力信号D3 及びD5 をマイ
クロコンピュータ22に内蔵されている判断回路36に
て判別し、第2のカウンタ34の時間(すなわち脱水時
間)が第1のカウンタ32の時間(すなわち給水時間)
より長ければ゛断水ではない″との判断をし、製氷開始
の動作へ移行するが(第4図ヌ)もし、長くなければ゛
断水である″との判断をする(第4図ル)。
The input signals D3 and D5 sent in this way are judged by the judgment circuit 36 built in the microcomputer 22, and the time of the second counter 34 (i.e. dehydration time) is determined by the time of the first counter 32 ( i.e. water supply time)
If it is longer, it is determined that there is no water outage, and the operation moves to start making ice (Fig. 4), but if it is not longer, it is determined that there is a water outage (Fig. 4, l).

そして、゛断水″の判断を行なった時にはマイクロコン
ピュータ22は出力信号Q3のみを○N ++し他の出
力は全て“’ OF F ”する動作を行ない、給水弁
14のみ作動し他の機能は全て停止という断水状態の動
作に移る(第4図ヲ)。
When it is determined that the water has been cut off, the microcomputer 22 outputs only the output signal Q3 to ○N++ and all other outputs to ``OFF'', operating only the water supply valve 14 and turning off all other functions. The system moves on to the water cutoff state (Fig. 4).

この後、断水が解除されると給水弁14は開いている(
動作している)ので、水道水は給水弁14を通って貯水
タンク6内に注水され、水位1了は上昇し上限設定スイ
ッチ18壕で上昇すると、スイッチは作動しく第4図ワ
)、入力信号02 を入力し、製氷動作にもどり、通常
の動作を行なう様になる。
After this, when the water cutoff is lifted, the water supply valve 14 is open (
The tap water is injected into the water storage tank 6 through the water supply valve 14, and when the water level rises and reaches the upper limit setting switch 18, the switch is activated and input Input signal 02 and return to ice-making operation to perform normal operation.

尚、上記した31〜35の各部品は個別部品として示し
たがマイクロコンピュータ23に内蔵しプログラム上で
処理し、個別部品とする必要のない事は明らかである。
Incidentally, although each of the above-mentioned parts 31 to 35 is shown as an individual part, it is clear that they are built into the microcomputer 23 and processed on a program, so there is no need for them to be made into individual parts.

発明の効果 以上の説明から明らかな様に、本発明の製氷機は断水時
には給水時間が脱水時間より長くなるという事実をもと
に、両者の時間を計測するカウンタと、この時間を比較
しいずれが長いかを判断する判断回路とこの回路の判断
によって製氷運転を停止する制御装置とを構成する事に
より、断水を判別可能とし、断水時の省電力化が図れ、
また断水時の機器の破損も防止できるものである。
Effects of the Invention As is clear from the above explanation, the ice maker of the present invention is based on the fact that the water supply time is longer than the dehydration time when the water is cut off. By configuring a judgment circuit that judges whether the ice-making operation is long and a control device that stops the ice-making operation based on the judgment of this circuit, it is possible to determine a water outage, and it is possible to save power during a water outage.
It also prevents damage to equipment during water outages.

【図面の簡単な説明】[Brief explanation of drawings]

第1図は本発明の一実施例における製氷機の断面図、第
2図は同製氷機のブロック図、第3図は制御装置に記憶
された特性値、第4図は同製氷機の動作を説明するフロ
ーチャートである。 5・・・・・・製氷部材、6・・・・・・貯水タンク、
7・・・・・・循環水ポンプ装置、18・・・・・・上
限設定スイッチ、19・・・・・・下限設定スイッチ、
21・・・・・・脱氷検知装置、22 ・・・マイクロ
コンピュータ(制御装置)、32・・・・・・第1のカ
ウンタ、34・・・・・第2のカウンタ、36・・・・
・・判断回路。 代理人の氏名 弁理士 中 尾 敏 男 ほか1名第1
図 z  10 第3図 第4図 402
Fig. 1 is a sectional view of an ice maker according to an embodiment of the present invention, Fig. 2 is a block diagram of the ice maker, Fig. 3 is a characteristic value stored in the control device, and Fig. 4 is an operation of the ice maker. It is a flow chart explaining. 5...Ice making component, 6...Water storage tank,
7... Circulating water pump device, 18... Upper limit setting switch, 19... Lower limit setting switch,
21...Deicing detection device, 22...Microcomputer (control device), 32...First counter, 34...Second counter, 36...・
...Judgment circuit. Name of agent: Patent attorney Toshio Nakao and 1 other person No. 1
Figure z 10 Figure 3 Figure 4 402

Claims (1)

【特許請求の範囲】 板状氷を生成する製氷部材と、この製氷部材に橢ぼ1.
ri 製氷水幌盾環水ポンプ装置と、水道からの製氷水を導入
し貯水する貯水タンクと、貯水タンク内の製氷水の上限
水位を検出して給水完了せしめる上限設定スイッチ及び
下限水位を検出して給水開始し脱水開始する下限設定ス
イッチと、生成された板状氷が前記製氷部材から脱落し
だことを検知して脱水完了せしめる脱水検知装置と、給
水開始から給水完了までの時間をカウントする第1のカ
ウンタと、脱水開始から脱水完了までの時間をカウント
する第2のカウンタと、前記第1.第2のカウント時間
を比較し、いずれが長いかを判断する判断回路と、この
判断回路により第1のカウンタによるカウント時間が第
2のカウンタによるカウント時間より長い時製氷運転を
停止する制御装置とを備えた製氷機。
[Scope of Claims] An ice making member that generates sheet ice, and an ice making member that includes: 1.
ri An ice making water canopy ring water pump device, a water storage tank that introduces ice making water from the tap and stores it, an upper limit setting switch that detects the upper limit water level of the ice making water in the water storage tank and completes water supply, and a lower limit water level detecting device. a lower limit setting switch that starts water supply and dehydration; a dehydration detection device that detects when the generated sheet ice begins to fall off the ice making member and completes dehydration; and a dehydration detection device that counts the time from the start of water supply to the completion of water supply. a first counter; a second counter that counts the time from the start of dehydration to the completion of dehydration; and the first counter. a determination circuit that compares second count times and determines which one is longer; and a control device that stops ice-making operation when the count time of the first counter is longer than the count time of the second counter based on the determination circuit; Ice maker with.
JP18837982A 1982-10-27 1982-10-27 Ice machine Granted JPS5977276A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
JP18837982A JPS5977276A (en) 1982-10-27 1982-10-27 Ice machine

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
JP18837982A JPS5977276A (en) 1982-10-27 1982-10-27 Ice machine

Publications (2)

Publication Number Publication Date
JPS5977276A true JPS5977276A (en) 1984-05-02
JPH0333995B2 JPH0333995B2 (en) 1991-05-21

Family

ID=16222584

Family Applications (1)

Application Number Title Priority Date Filing Date
JP18837982A Granted JPS5977276A (en) 1982-10-27 1982-10-27 Ice machine

Country Status (1)

Country Link
JP (1) JPS5977276A (en)

Citations (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPS5321135A (en) * 1976-08-05 1978-02-27 Clesa Spa Ddthreoo11phenyll22trifluoroacetoamidee 1*33propane diol derivative*process for preparation therefor and composition having broad spectrum of antibiotic activity

Patent Citations (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPS5321135A (en) * 1976-08-05 1978-02-27 Clesa Spa Ddthreoo11phenyll22trifluoroacetoamidee 1*33propane diol derivative*process for preparation therefor and composition having broad spectrum of antibiotic activity

Also Published As

Publication number Publication date
JPH0333995B2 (en) 1991-05-21

Similar Documents

Publication Publication Date Title
JPS60259866A (en) Method of operating refrigeration system and control system of refrigeration system
JPS5977276A (en) Ice machine
JPS5986879A (en) Ice machine
JPS63163725A (en) Air conditioner
JPS59173671A (en) Controller for ice machine
JPS5934940B2 (en) Ice-making control device for automatic ice-making machine
JPS642137Y2 (en)
JPS5929960A (en) Method of detecting temperature of atmospheric air of ice machine
JPH056103B2 (en)
JPS5935763A (en) Method of detecting temperature of atmospheric air of ice machine
JPS62299667A (en) Protective device for ice machine
JPS5950035B2 (en) How to detect ice maker water outage
JPS58148333A (en) Method for defrosting air heat source heat pump
JPH0493545A (en) Control device of drain pump in air conditioner
JPS63243652A (en) Air-conditioning machine
JPS613968A (en) Ice machine
CN115751564A (en) Ventilation equipment with anti-freezing function
JPH035827Y2 (en)
CN115574509A (en) Refrigerator and ice making method thereof
JPS5913547Y2 (en) Air conditioner control circuit
JPS62245061A (en) Controller for automatic ice machine
JPS62206358A (en) Controller for ice machine
JP2003065603A (en) Hot water storage tank and heat pump device
JPS60164151A (en) Heat pump type hot water supplier
JPS601545B2 (en) Ice making time automatic control device for ice making machines