JPS58199925A - Construction of underground wall and underground foundation pile with brace - Google Patents

Construction of underground wall and underground foundation pile with brace

Info

Publication number
JPS58199925A
JPS58199925A JP8105282A JP8105282A JPS58199925A JP S58199925 A JPS58199925 A JP S58199925A JP 8105282 A JP8105282 A JP 8105282A JP 8105282 A JP8105282 A JP 8105282A JP S58199925 A JPS58199925 A JP S58199925A
Authority
JP
Japan
Prior art keywords
underground
foundation
ground
joints
piles
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Granted
Application number
JP8105282A
Other languages
Japanese (ja)
Other versions
JPS6262206B2 (en
Inventor
Hideyoshi Takahashi
高橋 秀吉
Takashi Ueki
植木 隆司
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
TOMOEGUMI IRON WORKS Ltd
Original Assignee
TOMOEGUMI IRON WORKS Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by TOMOEGUMI IRON WORKS Ltd filed Critical TOMOEGUMI IRON WORKS Ltd
Priority to JP8105282A priority Critical patent/JPS58199925A/en
Publication of JPS58199925A publication Critical patent/JPS58199925A/en
Publication of JPS6262206B2 publication Critical patent/JPS6262206B2/ja
Granted legal-status Critical Current

Links

Classifications

    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D5/00Bulkheads, piles, or other structural elements specially adapted to foundation engineering
    • E02D5/20Bulkheads or similar walls made of prefabricated parts and concrete, including reinforced concrete, in situ

Landscapes

  • Engineering & Computer Science (AREA)
  • Structural Engineering (AREA)
  • Life Sciences & Earth Sciences (AREA)
  • General Life Sciences & Earth Sciences (AREA)
  • Mining & Mineral Resources (AREA)
  • Paleontology (AREA)
  • Civil Engineering (AREA)
  • General Engineering & Computer Science (AREA)
  • Piles And Underground Anchors (AREA)

Abstract

PURPOSE:To enhance the horizontal bearing force against horizontal external force and the horizontal rigidity of foundation pile by a method in which foundation piles having joints on their sides are erected into the ground and an underground wall with couplers is settled between the foundation piles. CONSTITUTION:Foundation piles 2 having joints 1 on their sides are erected into the ground by facing their joints 1. Also, T-shaped couplers 7 to be joined with the joints 1 are formed at the left and right-handed ends of the underground piles 2, and an underground wall 4 erected in a trench between the foundation piles 2 while guiding the couplers 7 on the left and right-handed ends toward the joints 1 of the foundation piles 2. Under the ground, a packing material 6, e.g., cement mortar or concrete, etc., is packed into the joints 1 to integrally combine the foundation piles 2 and the underground wall 4.

Description

【発明の詳細な説明】 この発明は地中壁および地中プレース付杭基礎の施工方
法に関する。
DETAILED DESCRIPTION OF THE INVENTION The present invention relates to a method of constructing an underground wall and a pile foundation with an underground place.

一般に、支持杭はその鉛直支持力は大きいが、水平抵抗
は手延い。ところか、軟弱地盤に立つ建物や地ト室のな
い建ヅの揚台には地薦刀、風圧力(/(起因する水平力
の大部分な支持杭の水平抵抗力によって受けることとな
り、前記水平力の大部分を水平抵抗力の弱い支持杭で受
ける従来建物にに構造的に大さyzi1fi洒が七つた
っまた、不同沈下に対する対応策にも完全全期するもの
がなかった。てこで、描出願人は地盤中に打込まれた支
持杭間に地中壁を支持杭と一本に設けることによつ1地
−中風等の水平外力に対する支持杭の水平耐力および水
平層性を尚め、かつ変位を少なくするとともに杭&iの
年目1沈下を低、1jCaセた地中条田き杭基礎を一発
した(特願昭54−152572参照)。
In general, support piles have a large vertical bearing capacity, but their horizontal resistance is low. On the other hand, buildings that stand on soft ground or platforms with no basement floor are exposed to wind pressure (/() due to the horizontal resistance force of the supporting piles, which causes most of the horizontal force, and the above-mentioned Conventional buildings, in which most of the horizontal force is received by support piles with weak horizontal resistance, are structurally weak, and there is no perfect countermeasure against uneven settlement. , the applicant has proposed to improve the horizontal bearing capacity and horizontal stratification of the support piles against horizontal external forces such as wind and wind by installing an underground wall between the support piles driven into the ground. In addition, we have created an underground pile foundation that reduces displacement and reduces the annual settlement of the pile by 1JCa (see Japanese Patent Application No. 54-152572).

しかし、前記特許出願に係る発明では、支持杭を建込み
、この支持杭の周辺を一足範囲に亘って掘削した彼、執
喘打ちコンクリートによる地中壁を支持杭と一体糺構既
するものでめり、施工に際し、多大な手間・暇を必要と
した。ま次、水平荷重に対してきわめて優nた抵抗力を
発揮するプレース金支持机間に投打る施工方法は考えら
nていなかった。
However, in the invention related to the above patent application, he erected a support pile, excavated an area around the support pile, and then integrated an underground wall made of poured concrete with the support pile. A great deal of time and effort was required for the construction. Next, no one had thought of a construction method in which the metal is cast between the support plates, which exhibits extremely high resistance to horizontal loads.

この発明は前記特許発明と発展・改良したもので、支持
杭の水平耐力および水平剛性を著しく尚めることかでさ
るとともに不同沈下を防止す心ことができ、施工に際し
ては工期の短縮化。
This invention has been developed and improved from the above-mentioned patented invention, and it significantly improves the horizontal strength and horizontal rigidity of the support pile, and also prevents uneven settlement, thereby shortening the construction period.

工事のrN@化、省力化を図フ得る地中壁および地中プ
レース付杭基鍵の11工)法を提供することを目的とす
る。
The purpose of the present invention is to provide 11) construction methods for underground walls and pile foundations with underground placements that will improve construction work and save labor.

この発明に係る地中壁2よび1甲プレース付杭基礎の施
工方法は、′1g1部に接合部を設けた基礎杭を前記接
曾部を対向させて地盤中に建てこむとともに前記基礎杭
間に儂削溝を掘削し、次いで前記掘削溝内に、地中壁1
之は地中プレースをでの左右縁端部を前記拙合揶に係合
させかつ前記接合部で案内させつつ建てこみ地盤中にお
いて、WJJ記基礎杭と地中壁ftは池中プレースとを
一体とする方法でめるっなお、前記のように掘削して建
てこむ方法の他に地中壁または地中プレースの下4部に
掘削または地盤を弱体化させる装置i1を付けて沈設す
る方法もめる。
The method for constructing a pile foundation with an underground wall 2 and a first-floor place according to the present invention is to erect a foundation pile with a joint part in the 1g1 part into the ground with the contacting part facing each other, and to place the foundation pile between the foundation piles. excavate a groove by myself, and then install an underground wall 1 in the excavated groove.
This is done by engaging the left and right edges of the underground place with the above-mentioned joints and guiding it at the joint part, and in the ground, the WJJ foundation pile and the underground wall ft are connected to the pond place. In addition to the method of excavating and building as described above, there is also a method of installing equipment i1 that excavates or weakens the ground in the lower four parts of the underground wall or underground place. quarrel.

そして、この発明によれは地盤中に建込1れた基礎杭間
に地中壁’E ’fC(’:f、地中プレースを基礎杭
と一体に設けるので地震や風等の水平外力に対する水平
耐力および水平剛性を著しく高めることができるととも
に杭の変位および不同沈下を防止することができる。
According to this invention, an underground wall 'E'fC (':f) is provided between the foundation piles built in the ground, and an underground place is provided integrally with the foundation pile, so that it can withstand horizontal external forces such as earthquakes and wind. Horizontal bearing capacity and horizontal rigidity can be significantly increased, and pile displacement and uneven settlement can be prevented.

ま友、施工に際しては、関部に接合部を設けた基礎杭を
前記接合Sを対向させて建込むとともに前記基礎杭間[
fIA1!1l11を掘削し、かつこの掘削溝内に予め
地上で組立てた地中壁または地中プレースt−その左右
縁端部を前記接合部に保合しかつ接合部で案内させつつ
建込み、地盤中において接合部にモルタルやコンクリ−
)を充填して基礎杭と地中壁または地中プレースとを一
体とするから、在米施工法ではどうしても必安な基礎杭
周辺の掘削作業、清掃作業2よびコンクリート工事を省
略することができ、地中壁や地中プレースは同一方法に
よってきわめて簡単かつ迅速に掘削溝内に建込むことか
でさ、工期の大幅な短纏化、工事の簡略化、省力化が図
れる。また、基礎杭の建込み間隔のバラツキや基礎杭の
傾斜による寸法誤差は基礎杭側部に設けた接合部によっ
て極めて簡単に吸収することができる。また、鋼管杭や
コンクリート杭等の在米杭を使用することができ工事費
の低減化が図れる。
During construction, the foundation piles with joints at the junctions should be erected with the joints S facing each other, and the distance between the foundation piles [
fIA1!1l11 is excavated, and an underground wall or underground place t is assembled on the ground in advance in this excavated trench, and the left and right edges thereof are secured to the joint and are guided by the joint, and are erected; Do not use mortar or concrete at joints in the ground.
) to integrate the foundation pile and underground wall or underground place, it is possible to omit the excavation work, cleaning work 2, and concrete work around the foundation pile, which are unavoidable in the American construction method. By using the same method, underground walls and underground places can be built extremely easily and quickly in excavated trenches, thereby significantly shortening the construction period, simplifying the construction work, and saving labor. In addition, dimensional errors due to variations in the pitch between foundation piles and inclination of the foundation piles can be absorbed very easily by the joints provided on the sides of the foundation piles. Additionally, American piles such as steel pipe piles and concrete piles can be used, reducing construction costs.

以下、この発明に係る施工方法を図示する実施例によっ
て説明すると、まず、W部に接合部1、lt−設けm複
数本の基礎杭2,2を接合部1.1を地盤中に適宜間隔
離しかつ接合111+lt−相対向させて打込み式ある
いは埋込み式により建込む。
Hereinafter, the construction method according to the present invention will be explained with reference to the illustrated embodiment. First, a joint part 1, lt- is provided in the W part, and a plurality of foundation piles 2, 2 are placed in the ground at appropriate intervals. Separate and join 111+lt- to face each other and erect by a driving method or an embedded method.

接合部1.1は2本のアングル型材を相方が相俟って断
面略リップ溝状の凹部を形成するように基礎杭20m1
1面部に溶接等により固着してなり、地上において予め
形成しておく、接合部1.1の下端部および側面部の開
口面には塞ぎ板3t−収付け、基礎杭2の建込み中に土
が接合部l内にはいらないようにしである。なお、接合
部1の側面部の開ロ面t−塞ぐ塞ぎ板3は着脱自任に取
付けてあり、基礎杭2の翅込み後真上に引き抜ける構成
になっている。
The joint part 1.1 is a foundation pile of 20 m1 in which two angle-shaped members are joined together to form a recess with a roughly lip groove shape in cross section.
A closing plate 3t is attached to the opening surface of the lower end and side surface of the joint part 1.1, which is fixed by welding etc. to the joint part 1.1 and is previously formed on the ground. This is to prevent soil from entering the joint l. The closing plate 3 that closes the opening surface t of the side surface of the joint 1 is detachably attached, and is configured to be pulled out directly above after the foundation pile 2 is inserted.

次に、基礎杭2,2間に後述する地中壁I′ft。Next, an underground wall I'ft, which will be described later, is formed between the foundation piles 2 and 2.

は地中プレース4t−建込1cるような掘削45を所定
深さに掘削する。次に、塞ぎ板3を引き抜き掘削45内
に地中壁または地中プレース4f:その左右縁端部を接
合部1.1に保合しかつ接合部1.1で案内ぢゼつつ建
込むっそして地盤中において接&部1.1にモルタルや
コンクリート等の光礪材6を充填して基礎杭2.2と地
中壁17′cは地中プレース4とを一体とする。地中壁
または地中プレース4の左右縁端部には接合部1.1に
保合させる@F!IJ略T字状の保合都7.7が形成し
である。保合部7μ地上において予め形成しておく。
An excavation 45 is excavated to a predetermined depth such that the underground place is 4t and the construction is 1c. Next, pull out the closing plate 3 and install the underground wall or underground place 4f in the excavation 45, fixing its left and right edges to the joint 1.1 and guiding it with the joint 1.1. Then, the contact portion 1.1 in the ground is filled with a glazing material 6 such as mortar or concrete to integrate the foundation pile 2.2 and the underground wall 17'c with the underground place 4. Attach the left and right edges of the underground wall or underground place 4 to the joint 1.1 @F! It is formed by IJ approximately T-shaped retaining capital 7.7. A holding portion 7μ is formed in advance on the ground.

第6図、第7図、i48図、第9図お、こび第10図は
この発明の他の実施例ケ示し友もので、第6図、嶌7図
および第8図は基礎杭2の一面部に断面丁字状の型材を
溶接等により固着して接合部8.8’j(杉成し、地′
P萱または池中プレース4は接合部*9’に介して脹合
部3,8て連結しである。
Figures 6, 7, 48, 9 and 10 show other embodiments of the invention, and Figures 6, 7 and 8 show the foundation pile 2. A T-shaped cross section is fixed to one side by welding etc. to form a joint 8.8'j (cedar, ground
The P 萱 or Ikenaka place 4 is connected to the bulges 3 and 8 via the joint *9'.

接合部−1119u、&合部8を係合させ得る断面路リ
ップ溝状の保合部10と地中壁または地中プレース4t
−保合させ得る町面略溝状の係合部11とからな9、そ
の下端部には、テーパを付けて月形が形成されている。
Joint part 1119u, & joint part 8 can be engaged with retaining part 10 having a cross-sectional road lip groove shape and underground wall or underground place 4t
- The engagement portion 11 and the lattice 9, which can be engaged with each other in the shape of a groove, are tapered to form a moon shape at their lower ends.

なお、地盤によっては下41都に月形を形成しないで水
平に形成してもよい。係合部10および11の下端部の
開口面は塞いであり、係合部10の底面部には接合部8
の断面形状に対応する断面略T字状の開口孔12が形成
されている、係&部11の側面部の開口面には壜ぎ板3
が膚脱自在に覗付けてあり、1ぎ板3は真上に引き抜け
るf41戊になっている。Iた、保合soの内側にはス
タッドボルト等のシアコネクター17 、17や突東部
1.3 、13が突設されている。
In addition, depending on the ground, the lower 41 mounds may be formed horizontally instead of forming a moon shape. The opening surfaces at the lower ends of the engaging portions 10 and 11 are closed, and the bottom surface of the engaging portion 10 has a joint portion 8.
A bottle plate 3 is provided on the opening surface of the side surface of the engaging part 11, in which an opening hole 12 having a substantially T-shaped cross section corresponding to the cross-sectional shape of is formed.
can be seen freely, and the first plate 3 has an f41 hole that can be pulled out directly above. In addition, shear connectors 17, 17 such as stud bolts, and protruding parts 1.3, 13 are provided protruding from the inside of the joint.

施工に際しては、基に杭2+2′ft:建込み、掘削#
5奮掘剛し′rc埃、接合↓物9t−接合部8と保合部
lOとt−開口孔12ヲ通して係合し、かつ接合部8で
案内6ぜつつ地盤中に打込む。この場合、接せ部8に付
層した土砂は開口孔12の周縁部でIIIり落すことか
でさる。また、接合金物9の下端部に月形が形成しであ
るので接合金物9の打込み作業がしやすい。
During construction, piles 2 + 2'ft: erection, excavation #
5. Dig and harden the joint ↓ to engage the joint 9t-joint part 8, retaining part lO, and t-opening hole 12, and drive it into the ground while guiding the joint part 8. In this case, the earth and sand layered on the contact portion 8 can be washed off at the periphery of the opening hole 12. Further, since a moon shape is formed at the lower end of the joining hardware 9, the work of driving the joining hardware 9 is facilitated.

次に、塞ぎ板3を引き抜き、掘削溝5内に地中壁または
地中プレース4t−その左右縁m5t−接合金物9の係
合部11 、11に係合し、かつ保合部11 、11で
案内させつつ建込む。そして地盤中において、係合部l
Oおよび11にモルタルやコンクリート等の充填材6f
:充填して基礎杭2と接合金物9と地中壁lたは地中プ
レース4とk 一体とする。
Next, the closing plate 3 is pulled out and inserted into the excavated groove 5 into the underground wall or underground place 4t, its left and right edges m5t, and engaged with the engaging parts 11, 11 of the joining hardware 9, and the retaining parts 11, 11. We will guide you through the construction process. Then, in the ground, the engaging portion l
6f filler such as mortar or concrete for O and 11
:Fill and integrate the foundation pile 2, joint hardware 9, underground wall l or underground place 4 and k.

第7図は地中プレース4が鉄骨からなる実施例を示した
ものであシ、lI8図は地中壁4の一部が現場打ちコン
クリートからなる実施例を示したも゛のであ夛、符号1
4はケーシング、符号15は鉄筋、符号16はスペーサ
ーである。第9図は既成コンクリート杭18の外周IC
!jk合部1を固着し友外殻鋼管19’ii配し、この
外殻鋼管19と既成コンクリート杭18間にコンクリー
ト20ヲ光填することによって基礎杭2が構成された実
施例であるっ 以上、この発明に係る施工方法によれば基礎杭の水平耐
力および水平141性を著しく高めること〃・できると
ともに不同沈下′に防止することができる。ま友施工に
際しては工期短編化、工事の簡略化、省力化が図れる。
Figure 7 shows an example in which the underground place 4 is made of a steel frame, and Figure 1I8 shows an example in which a part of the underground wall 4 is made of cast-in-place concrete. 1
4 is a casing, 15 is a reinforcing bar, and 16 is a spacer. Figure 9 shows the outer circumference IC of the precast concrete pile 18.
! This is an embodiment in which the foundation pile 2 is constructed by fixing the jk joint 1, disposing the outer shell steel pipe 19'ii, and filling the space between the outer shell steel pipe 19 and the prefabricated concrete pile 18 with concrete 20. According to the construction method according to the present invention, it is possible to significantly increase the horizontal strength and horizontal stability of the foundation pile, and it is also possible to prevent uneven settlement'. When performing construction, it is possible to shorten the construction period, simplify construction work, and save labor.

また、基礎杭の建込み間隔のほらつきや基礎杭の傾斜に
よる寸法誤差は接合部分できわめて簡単に吸収できる。
In addition, dimensional errors due to irregularities in the spacing between foundation piles and inclination of the foundation piles can be absorbed very easily at the joints.

業た、在来杭を使用できるので工事費の低減化が図nる
Furthermore, since conventional piles can be used, construction costs can be reduced.

【図面の簡単な説明】[Brief explanation of the drawing]

第1図〜第3図はこの発明に係る施工方法の工程図、l
I4図は構成され危地中壁および地中プレース付基礎の
横m&図、第5図はその一部11411面図、第6図、
第7図、第8図および第9図はこの発明の他の央a例を
示すもので、第6図。 第7凶、第8図および第9図は地中壁および地中プレー
スb基謎の−S慣町面図、第10図はその一部tIli
l向図でめる。 ■・・・・・・接合部、2・・・・・・:kLa杭、3
・・・・・・基ぎ板、4・・・・・・地中壁まfCは地
中プレース、5・・・・・・細目1j溝、6・・・・・
・充填材、7・・・・・・係合部、8・・・・・・接合
部、9・・・・・・接合金物、10 、11・・・・・
・係合部、12・・・開口孔、13・・・・・・突I!
Ji!部、14・・・・・・ケーシング、15・・・・
・・鉄筋、16・・・・・・スペーサー、17・・・・
・・シアコネクター、18・・・・・・既成コンクリー
ト杭、19・・・・・・外殻鋼管、加・・・・・・コン
クリート。 第1図 第6し1 第4図 第5図 第10図 第8図 第7図 第9図
Figures 1 to 3 are process diagrams of the construction method according to the present invention.
Diagram I4 is a cross-sectional view of the underground walls and foundations with underground places, Figure 5 is a partial 11411 view, Figure 6,
FIGS. 7, 8, and 9 show another example of the present invention, and FIG. Figures 7, 8, and 9 are the underground walls and underground place b base mysterious -S practice area plan, and Figure 10 is a part of it.
I can draw the diagram in the direction of l. ■...Joint part, 2...: kLa pile, 3
...Base board, 4...Underground wall fC is underground place, 5...Small 1j groove, 6...
・Filling material, 7...Engaging part, 8...Joining part, 9...Joining hardware, 10, 11...
・Engagement part, 12...opening hole, 13...protrusion I!
Ji! Part, 14... Casing, 15...
...Reinforcing bar, 16...Spacer, 17...
... Shear connector, 18 ... Precast concrete pile, 19 ... Outer shell steel pipe, processing ... Concrete. Figure 1 Figure 6 1 Figure 4 Figure 5 Figure 10 Figure 8 Figure 7 Figure 9

Claims (1)

【特許請求の範囲】[Claims] 4部に接合部を設は九基礎杭を前記接合部を対向させて
地盤中に建てこむとともに前記基礎杭間に予め組み立て
られた地中壁lftは地中プレースをその左右縁端部を
前記接合部に係合しかつ接合部で案内させつつ沈設し、
地盤中において前記基礎杭と地中壁’E7’cは地中プ
レースとを一体とアクことt%徴とする地中壁および地
中プレース付杭基礎の施工方法。
9 foundation piles are built into the ground with the joints facing each other, and the underground wall lft assembled in advance between the foundation piles is placed in an underground place with its left and right edges facing the ground. Engaging with the joint part and sinking while being guided by the joint part,
A construction method for an underground wall and a pile foundation with an underground place, in which the foundation pile and the underground wall 'E7'c are integrated with the underground place in the ground.
JP8105282A 1982-05-14 1982-05-14 Construction of underground wall and underground foundation pile with brace Granted JPS58199925A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
JP8105282A JPS58199925A (en) 1982-05-14 1982-05-14 Construction of underground wall and underground foundation pile with brace

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
JP8105282A JPS58199925A (en) 1982-05-14 1982-05-14 Construction of underground wall and underground foundation pile with brace

Publications (2)

Publication Number Publication Date
JPS58199925A true JPS58199925A (en) 1983-11-21
JPS6262206B2 JPS6262206B2 (en) 1987-12-25

Family

ID=13735637

Family Applications (1)

Application Number Title Priority Date Filing Date
JP8105282A Granted JPS58199925A (en) 1982-05-14 1982-05-14 Construction of underground wall and underground foundation pile with brace

Country Status (1)

Country Link
JP (1) JPS58199925A (en)

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP2016191191A (en) * 2015-03-30 2016-11-10 株式会社熊谷組 Reinforcing structure for existing pile foundation
JP2020169467A (en) * 2019-04-02 2020-10-15 鹿島建設株式会社 Shear force transmission mechanism and construction method of steel pipe sheet pile foundation

Families Citing this family (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
IT1229577B (en) * 1988-05-30 1991-09-04 Hauni Werke Koerber & Co Kg PROCEDURE AND DEVICE FOR DETERMINING THE CIGARETTE DIAMETER.

Citations (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPS4863513A (en) * 1971-12-06 1973-09-04

Patent Citations (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPS4863513A (en) * 1971-12-06 1973-09-04

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP2016191191A (en) * 2015-03-30 2016-11-10 株式会社熊谷組 Reinforcing structure for existing pile foundation
JP2020169467A (en) * 2019-04-02 2020-10-15 鹿島建設株式会社 Shear force transmission mechanism and construction method of steel pipe sheet pile foundation

Also Published As

Publication number Publication date
JPS6262206B2 (en) 1987-12-25

Similar Documents

Publication Publication Date Title
JP6632028B2 (en) Concrete assembly retaining wall
KR100289256B1 (en) Tunnel construction method in shallow toffee area
JP2000352296A (en) Method o constructing passage just under underground structure
JPS58199925A (en) Construction of underground wall and underground foundation pile with brace
JP7275844B2 (en) WALL-LIKE STRUCTURE AND METHOD OF CONSTRUCTING WALL-LIKE STRUCTURE
JP2003268770A (en) Earth retaining construction method and reinforcing structure of sheet pile used for this construction method
JPH0721196B2 (en) Reverse construction method of underground structure
KR20200029075A (en) Pile for Earth self-retaining wall using double I beam
JP2571426B2 (en) Construction method of retaining wall
JPH01315520A (en) Underground outer wall constructing method for superstructure
JP2657671B2 (en) Reconstruction method for existing structures
JPS6018769B2 (en) Construction method of underground structure
JP2000355941A (en) Building and its construction method
JPH073777A (en) Method for constructing self-supporting land slide protection wall
JP4657759B2 (en) Building pile foundation structure
JPS6024249B2 (en) How to build a basement
JP4871764B2 (en) Construction method of underground structure and pipe roof
JPS6046216B2 (en) Pile foundation with underground brace made of triangular members
JPS6017898B2 (en) Construction method of pile foundation with underground wall
JPS6128774B2 (en)
JP6826820B2 (en) Insertion pile type retaining wall
JPS5853321Y2 (en) Element for mountain retainer
JPH101957A (en) Underground construction method for building
JPH03147926A (en) construction method for basement
JP2947083B2 (en) Construction method of deep groove block