JPS58127079A - Forced cooling operating device for cooler - Google Patents

Forced cooling operating device for cooler

Info

Publication number
JPS58127079A
JPS58127079A JP936582A JP936582A JPS58127079A JP S58127079 A JPS58127079 A JP S58127079A JP 936582 A JP936582 A JP 936582A JP 936582 A JP936582 A JP 936582A JP S58127079 A JPS58127079 A JP S58127079A
Authority
JP
Japan
Prior art keywords
circuit
cooler
output
forced cooling
cooling operation
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Granted
Application number
JP936582A
Other languages
Japanese (ja)
Other versions
JPS645231B2 (en
Inventor
秀夫 山本
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Panasonic Holdings Corp
Original Assignee
Matsushita Refrigeration Co
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Matsushita Refrigeration Co filed Critical Matsushita Refrigeration Co
Priority to JP936582A priority Critical patent/JPS58127079A/en
Publication of JPS58127079A publication Critical patent/JPS58127079A/en
Publication of JPS645231B2 publication Critical patent/JPS645231B2/ja
Granted legal-status Critical Current

Links

Landscapes

  • Devices That Are Associated With Refrigeration Equipment (AREA)

Abstract

(57)【要約】本公報は電子出願前の出願データであるた
め要約のデータは記録されません。
(57) [Abstract] This bulletin contains application data before electronic filing, so abstract data is not recorded.

Description

【発明の詳細な説明】 本発明は冷蔵庫等の冷却器の強制冷却運転装置に関する
ものである。
DETAILED DESCRIPTION OF THE INVENTION The present invention relates to a forced cooling operation device for a cooler such as a refrigerator.

2ぺ−2,゛ 従来、冷却器の強制冷却運転装置においては、強制冷却
運転中に圧縮機の運転積算時間が所定時間に達すると、
圧縮機の運転時間積算タイマより除霜信号が出力され、
冷却器の除霜を優先して、その間は強制冷却運転を中断
させている。
2 Page 2, Conventionally, in a forced cooling operation device for a cooler, when the cumulative operating time of the compressor reaches a predetermined time during forced cooling operation,
A defrost signal is output from the compressor operating time integration timer,
Priority is given to defrosting the cooler, and forced cooling operation is suspended during that time.

ところが、上記のような強制冷却運転制御では、利用者
が強制冷却運転を希望した場合においても、積算タイマ
より除霜信号が出力されると強制冷却運転が中断される
ため、強制冷却運転が必要であるにもかかわらず利用で
きないことになシ、利用者の立場から使い勝手の面で問
題があった。
However, with the forced cooling operation control described above, even if the user requests forced cooling operation, the forced cooling operation is interrupted when the defrost signal is output from the integration timer, so forced cooling operation is necessary. However, the fact that it was not available was a problem in terms of usability from the user's perspective.

本発明は、上記問題点を無くした冷却器の強制冷却運転
装置を提供することを目的とするものである。
An object of the present invention is to provide a forced cooling operation device for a cooler that eliminates the above-mentioned problems.

以下図面によシ本発明の一実施例を詳細に説明を行う。An embodiment of the present invention will be described in detail below with reference to the drawings.

第1図は本発明の一実施回路例である。FIG. 1 shows an example of a circuit for implementing the present invention.

1は冷蔵庫の冷凍サイクルを構成する冷却器(図示せず
)の冷却能力判定回路であシ、まずこの回路1について
説明すると2は冷却器の温度検出用の第1の温度センサ
、3は冷却器を設置した冷却3べ一部 室内(図示せず)の空気温度検出用の第2の温度センサ
であり、それぞれ分圧抵抗4,5を介している。各セン
サ2,3と各分圧抵抗4,5の接続点は各々作動アンプ
60入力となっており、これらが図示する如く接続され
て構成されている。前記差動アンプ6の出力は冷却器の
冷却能力がある場合にはH″(高)になる、ない場合に
はIt L Jl(低)となる。このアンプらの出力は
後述する単安定マルチバイブレーク16の出力Qと共に
AND回路11に入力されている。
Reference numeral 1 is a cooling capacity determination circuit for a cooler (not shown) that constitutes the refrigeration cycle of the refrigerator.First, to explain this circuit 1, reference numeral 2 is a first temperature sensor for detecting the temperature of the cooler, and reference numeral 3 is a cooling capacity determination circuit for a cooler (not shown). This is a second temperature sensor for detecting the air temperature in a room (not shown) in the cooling room where the cooling device is installed, and is connected through voltage dividing resistors 4 and 5, respectively. The connection points between each sensor 2, 3 and each voltage dividing resistor 4, 5 serve as an input to an operational amplifier 60, and these are connected as shown in the figure. The output of the differential amplifier 6 becomes H'' (high) when there is cooling capacity of the cooler, and it becomes It L Jl (low) when there is no cooling capacity. It is input to the AND circuit 11 together with the output Q of the break 16.

7は上述した冷凍サイクルの一部を成す圧縮機8の運転
時間を積算する運転時間積算タイマであり、圧縮機8の
運転時間が所定時間に達すると除霜開始信号として’ 
H” (高)を出力し、それ以外は” L ” (低)
を出力する。9は強制冷却運転スイッチであり、押すと
”H” (高)を出力する。
Reference numeral 7 denotes an operation time integration timer for accumulating the operation time of the compressor 8 which forms a part of the above-mentioned refrigeration cycle, and when the operation time of the compressor 8 reaches a predetermined time, a defrosting start signal is issued.
Outputs “H” (high), otherwise outputs “L” (low)
Output. 9 is a forced cooling operation switch, which outputs "H" (high) when pressed.

10はAND回路であり、タイプ了の出力と、AND回
路11の出力をインパーク12を介して入力としており
、前記タイマ回路7から除霜開始□信号1(HJlが出
力され、AND回路11の出力がIT L 11の時に
フリップフロップ13にIt HIIを出力する。フリ
ップフロップ13の出力Qは電源投入時はIt L″′
であり、前記AND回路1oからH″を入力されると出
力QはH1となり、リレーR1の駆動用のトランジスタ
14をONさせる。
10 is an AND circuit, which inputs the output of the type completion and the output of the AND circuit 11 via the impark 12, and the defrosting start signal 1 (HJl) is output from the timer circuit 7, and the AND circuit 11 When the output is IT L 11, It HII is output to the flip-flop 13. The output Q of the flip-flop 13 is It L''' when the power is turned on.
When H'' is input from the AND circuit 1o, the output Q becomes H1, turning on the transistor 14 for driving the relay R1.

15はAND回路であり、強制冷却運転スイッチ9から
の出力と、前記フリップフロップ13からの出力をイン
バータ16を介して入力としており、前記強制冷却運転
スイッチ9からH″が出力され、前記フリップフロップ
13の出力QがIt I、”の時に単安定マルチバイブ
レータ16aに”H″を出力する。単安定マルチバイブ
レータ16aの出力Qは電源投入時は”L″′であり、
前記AND回路15からH”を入力されると出力Qは一
定時間aHJ′となり、リレーR2の駆動用のトランジ
スタ1了を一定時間ONさせる。
15 is an AND circuit, which inputs the output from the forced cooling operation switch 9 and the output from the flip-flop 13 via the inverter 16, and H'' is output from the forced cooling operation switch 9, and the output from the flip-flop 13 is inputted through the inverter 16. When the output Q of 13 is "It I,", it outputs "H" to the monostable multivibrator 16a. The output Q of the monostable multivibrator 16a is "L"' when the power is turned on,
When H'' is input from the AND circuit 15, the output Q becomes aHJ' for a certain period of time, and the transistor 1 for driving the relay R2 is turned on for a certain period of time.

圧縮機8は庫内温度調節用のサーモスタット18゜リレ
ーR1の常閉接点R1aを介して電源19に接続されて
いる。そして、前記サーモスタット185ペー−′ に並列にリレーR2の常閉接点R2a 及び常開接点R
2bが接続されている。冷却器に設けられた除霜用ヒー
タ20はリレーR1の常開接点R1bを介して電源19
に接続されている。
The compressor 8 is connected to a power source 19 via a normally closed contact R1a of a thermostat 18° relay R1 for regulating the temperature inside the refrigerator. The normally closed contact R2a and the normally open contact R2 of relay R2 are connected in parallel to the thermostat 185 page'.
2b is connected. The defrosting heater 20 provided in the cooler is connected to the power source 19 via the normally open contact R1b of the relay R1.
It is connected to the.

第2図は第1の温度センサ2が検出する冷却器の温度T
1 と、第2の温度センサ3が検出する冷却室内の空気
温度T2の冷却器への着霜量による変化を示すものであ
る。着霜量が犬であるA点では、無霜時のB点に比べて
冷却器の熱交換が悪くなるので冷却室の空気温度T2は
上昇し、冷却器の温度T1 は降下する。
Figure 2 shows the temperature T of the cooler detected by the first temperature sensor 2.
1 and shows the change in the air temperature T2 in the cooling chamber detected by the second temperature sensor 3 depending on the amount of frost formed on the cooler. At point A, where the amount of frost is small, the heat exchange of the cooler is worse than at point B when there is no frost, so the air temperature T2 in the cooling room increases and the temperature T1 of the cooler decreases.

このような構成において動作を説明する。The operation in such a configuration will be explained.

まず、強制冷却運転中に積算タイマ7から除霜開始信号
が出力された場合について説明する。利用者が強制冷却
運転スイッチ9を押すと、AND回路15の1人力に”
H”が入力される。圧縮機8の運転積算時間が所定の時
間に達していない時には、積算タイマ7の出力はL#で
あるからAND回路1oは”L”を出力するので、フリ
ップフロップ13の出力Qはa L 31である。故に
AND6ベー′ 回路15への1人力はインバータ16を介しているため
11 HIIとなシ、AND回路1502人力は共にN
″H”となるのでAND回路16はl′H31を出力す
る。そして単安定マルチバイブレータ16aの出力Qは
H″となり、トランジスタ17がONしてリレーR2が
閉成し、その常閉接点R2aが開成して常開接点R2b
 が閉成する。すなわち、サーモスタット18は前記単
安定マルチパイプレーク16の出力Qが1H″である一
定時間の間短絡状態となり、圧縮機はその間強制冷却運
転を続ける。この強制冷却運転中に圧縮機8の運転積算
時間が所定時間に達すると、積算タイマ7の出力がu 
HIIとなり、AND回路10の1人力はH1と々る。
First, a case will be described in which the defrosting start signal is output from the integration timer 7 during forced cooling operation. When the user presses the forced cooling operation switch 9, the AND circuit 15 is operated by one person.
H" is input. When the cumulative operating time of the compressor 8 has not reached the predetermined time, the output of the cumulative timer 7 is L#, so the AND circuit 1o outputs "L", so the flip-flop 13 The output Q of is a L 31.Therefore, the AND6be' circuit 1502's human power is 11 HII because it is passed through the inverter 16, and the AND circuit 1502's human power is both N
Since the signal becomes "H", the AND circuit 16 outputs l'H31. Then, the output Q of the monostable multivibrator 16a becomes H'', the transistor 17 is turned on, the relay R2 is closed, the normally closed contact R2a is opened, and the normally open contact R2b is opened.
is closed. That is, the thermostat 18 is short-circuited for a certain period of time when the output Q of the monostable multi-pipe lake 16 is 1H'', and the compressor continues forced cooling operation during this period. When the time reaches the predetermined time, the output of the integration timer 7 becomes u.
It becomes HII, and one person's power of AND circuit 10 reaches H1.

この時AND回路10の他の1人力は、冷却器の冷却能
力の有無により′H”、9るいは+1 L”となる。
At this time, the other one's power in the AND circuit 10 is ``H'', 9 or +1 L'' depending on the presence or absence of the cooling capacity of the cooler.

つまシ冷却器への着霜量が小の場合は、冷却器の温度T
1 と冷却室の空気温度T2の温度差は微少であシ、差
動アンプ6の両人力はほぼ同電位にあり、その出力はH
”となる。強制冷却運転中7ベー゛ であるから、単安定マルチバイブレータ16の出力Qも
t+ Hnであり、AND回路11の2人力は共にH″
となるので、AND回路11はH′″を出力し、インバ
ータ12を介して、AND回路10への1人力はL 1
1となる。この時、圧縮機8の運転積算時間が所定時間
に達して積算タイマ7から除霜開始信号としてLt H
11が出力されるが、AND回路1oの出力はL″とな
り、フリップフロップ13の出力QはL′″を保持し、
強制冷却運転は継続することになる。
If the amount of frost on the cooler is small, the temperature of the cooler T
1 and the air temperature T2 in the cooling room is very small, and both differential amplifiers 6 are at almost the same potential, and their output is H.
". Since the current is 7 base during forced cooling operation, the output Q of the monostable multivibrator 16 is also t+Hn, and both the two-man power of the AND circuit 11 are H"
Therefore, the AND circuit 11 outputs H''', and the power input to the AND circuit 10 via the inverter 12 is L1.
It becomes 1. At this time, when the cumulative operating time of the compressor 8 reaches a predetermined time, the cumulative timer 7 outputs LtH as a defrosting start signal.
11 is output, but the output of the AND circuit 1o becomes L'', the output Q of the flip-flop 13 maintains L'',
Forced cooling operation will continue.

また冷却器への着霜量が大の場合は、第2図に示すよう
に冷却器の温度T1  と冷却室空気温度T2の温度差
が犬きくなるので、差動アンプ6の2人力の電位差が大
とカリ、その出力は+1 L IIとなる。
Furthermore, when the amount of frost on the cooler is large, the temperature difference between the cooler temperature T1 and the cooling room air temperature T2 becomes large as shown in FIG. If it is large and potash, its output will be +1 L II.

従って、AND回路11は+11 IIを出力し、イン
バータ12を介して、AND回路10への1人力は′H
″となる。この時、圧縮機8の運転積算時間に達して積
算タイマ7の出力がH”と々っているので、AND回路
10の2人力は共にゝ゛H゛であり、AND回路10は
1H″を出力し、フリップフロップ13の出力Qは+1
 H71となる。そして、トランジスタ14がONして
リレーR1が閉成し、その常閉接点R1a  が開成し
て常開接点R1b が閉成する。すなわち、電源19か
ら圧縮機8を切離して強制冷却運転を停止し、冷却器の
除霜用ヒータ20を電源に接続し除霜を開始する。この
時、フリップフロップ13の出力Qは除霜終了信号(図
示せず)がリセット端子Hに入力されるまで“H″を保
持する。
Therefore, the AND circuit 11 outputs +11 II, and the single power input to the AND circuit 10 via the inverter 12 is 'H
At this time, the cumulative operating time of the compressor 8 has been reached and the output of the cumulative timer 7 has jumped to H, so the two manpower outputs of the AND circuit 10 are both "H", and the AND circuit 10 is 1H", and the output Q of flip-flop 13 is +1
It will be H71. Then, transistor 14 is turned on, relay R1 is closed, its normally closed contact R1a is opened, and normally open contact R1b is closed. That is, the compressor 8 is disconnected from the power source 19 to stop the forced cooling operation, and the defrosting heater 20 of the cooler is connected to the power source to start defrosting. At this time, the output Q of the flip-flop 13 remains at "H" until a defrosting end signal (not shown) is input to the reset terminal H.

次に、除霜中に強制冷却スイッチを押した場合について
説明する。除霜時はフリップフロップ13の出力Qが′
H″′であるから、インバータ16を介して、AND回
路15の1人力はL”となる。
Next, a case where the forced cooling switch is pressed during defrosting will be explained. During defrosting, the output Q of flip-flop 13 is
Since the output voltage is H'', the output power of the AND circuit 15 becomes L'' through the inverter 16.

従って強制冷却運転スイッチ9の出力がII H11で
もAND回路15の出力は+1 L 11であり、単安
定マルチバイブレータ16aの出力も+1 L 11を
保持し、除霜が継続される。除霜終了時には、フリップ
フロップ13の出力Qが′L″′になり、インバータ1
6を介してAND回路の1人力がHIIになる。そして
、強制冷却運転スイッチ9の出力が9べ′ ′H″に保持されているのでAND回路15の出力はH
#となシ、単安定マルチバイブレータ16aは′H″を
出力し、リレーR2がR2a を閉成して強制冷却運転
を開始する。
Therefore, even if the output of the forced cooling operation switch 9 is II H11, the output of the AND circuit 15 is +1 L 11, the output of the monostable multivibrator 16a also remains +1 L 11, and defrosting is continued. At the end of defrosting, the output Q of the flip-flop 13 becomes 'L''', and the inverter 1
6, one person's power of AND circuit becomes HII. Since the output of the forced cooling operation switch 9 is held at 9'H'', the output of the AND circuit 15 is H.
At #, the monostable multivibrator 16a outputs 'H', relay R2 closes R2a, and forced cooling operation starts.

このように、強制冷却運転中に圧縮機の運転積算時間が
所定時間に達して積算タイマから除霜開始信号が出力さ
れる場合においても、冷却器の真の冷却能力を判定して
、コイルへの着霜量が少なく熱交換が良好な場合には除
霜よりも強制冷却運転を優先し、コイルへの着霜量が多
く熱交換が悪い場合には強制冷却運転よりも除霜を優先
するので、効率の良い強制冷却運転が可能になり、除霜
のため強制冷却運転が中断されるということも少なくな
る。まだ、不要な除霜による無駄な電力消費もなくすこ
とが可能となるものである。
In this way, even if the cumulative operating time of the compressor reaches a predetermined time during forced cooling operation and the defrosting start signal is output from the cumulative timer, the true cooling capacity of the cooler is determined and the When the amount of frost on the coil is small and heat exchange is good, priority is given to forced cooling operation over defrosting, and when the amount of frost on the coil is large and heat exchange is poor, priority is given to defrosting over forced cooling operation. Therefore, efficient forced cooling operation is possible, and forced cooling operations are less likely to be interrupted for defrosting. It is also possible to eliminate wasteful power consumption due to unnecessary defrosting.

以上の説明からも明らかなように本発明は冷却器の表面
温度検出用の第1の温度センサ、前記冷却器を設置した
冷却室内の空気温度検出用の第2の温度センサを具備し
、前記両温度センサの温度差を検出して前記冷却器の冷
却能力を判定する冷10   ′ 却能力判定回路と強制冷却運転スイッチと、このスイッ
チからの強制冷却運転信号により圧縮機を一定時間連続
通電させる回路と圧縮機運転時間の積算タイマと、この
タイマからの除霜開始信号によシ除霜を開始する回路と
、強制冷却運転信号と除霜開始信号が重なった場合に前
記冷却能力判定回路の出力により両信号の優先順位を決
定する優先制御回路とで構成したことを特徴とするもの
であるから、強制冷却運転が可能な時はこの運転を維持
し、着霜量が大で不可能な時は除霜を行ない効率の良い
理想的な強制冷却運転が可能となる。
As is clear from the above description, the present invention includes a first temperature sensor for detecting the surface temperature of the cooler, a second temperature sensor for detecting the air temperature in the cooling chamber in which the cooler is installed, and A cooling capacity determination circuit that detects the temperature difference between both temperature sensors and determines the cooling capacity of the cooler, a forced cooling operation switch, and a forced cooling operation signal from this switch to continuously energize the compressor for a certain period of time. A circuit that starts defrosting according to the integrated timer of the compressor operation time and a defrost start signal from this timer, and a circuit that starts defrosting according to the defrost start signal from this timer, and a circuit that starts defrosting when the forced cooling operation signal and the defrost start signal overlap. This system is characterized by being configured with a priority control circuit that determines the priority of both signals based on the output, so when forced cooling operation is possible, this operation is maintained, and when the amount of frost formation is large and it is impossible, Defrosting is performed at times to enable efficient and ideal forced cooling operation.

【図面の簡単な説明】[Brief explanation of the drawing]

第1図は本発明の一実施例の冷却器の強制冷却運転装置
を示す回路図、第2図は冷却器と冷却室の空気温度の着
霜量による変化を示す表である。 1、、、、。、冷却器の冷却能力判定回路、2 、、、
、、。 第1の温度センサ、300000.第2の温度センサ、
76.。、。、積算タイマ、90.、、、、強制冷却運
転スイッチ、10,11.15.、、、、AND回路(
優−光制御回路)、13 、、、、、、フィリップフロ
ップ(優11−1−パ 光制御回路)、16 、、、、、、単安定マルチバイブ
レータ(優先制御回路)。
FIG. 1 is a circuit diagram showing a forced cooling operation device for a cooler according to an embodiment of the present invention, and FIG. 2 is a table showing changes in air temperature in the cooler and cooling chamber depending on the amount of frost formation. 1,,,,. ,Cooling capacity determination circuit of cooler, 2.
,,. first temperature sensor, 300000. a second temperature sensor;
76. . ,. , integration timer, 90. ,,,, forced cooling operation switch, 10, 11.15. ,,,,AND circuit (
13. Philip flop (11-1 optical control circuit), 16. Monostable multivibrator (priority control circuit).

Claims (1)

【特許請求の範囲】[Claims] 冷却器の温度検出用の第1の温度センサ、前記冷却器を
設置した冷却室内の空気温度検出用の第2の温度センサ
を具備し前記両温度センサの温度差を検出して前記冷却
器の冷却能力を判定する冷却能力判定回路と、強制冷却
運転スイッチと、このスイッチからの強制冷却運転信号
により圧縮機を一定時間連続通電させる回路と、圧縮機
運転時間の積算タイマと、このタイマからの除霜開始信
号により除霜を開始する回路と強制冷却運転信号と除霜
開始信号が重なった場合に前記冷却能力判定回路の出力
により両信号の優先順位を決定する優先制御回路とで構
成した冷却器の強制冷却運転装置。
A first temperature sensor for detecting the temperature of the cooler, and a second temperature sensor for detecting the air temperature in the cooling chamber in which the cooler is installed, detecting the temperature difference between the two temperature sensors and detecting the temperature of the cooler. A cooling capacity determination circuit that determines the cooling capacity, a forced cooling operation switch, a circuit that continuously energizes the compressor for a certain period of time based on the forced cooling operation signal from this switch, a timer for accumulating compressor operation time, and a Cooling comprising a circuit that starts defrosting in response to a defrost start signal, and a priority control circuit that determines the priority of both signals based on the output of the cooling capacity determination circuit when the forced cooling operation signal and the defrost start signal overlap. Forced cooling operation device for equipment.
JP936582A 1982-01-22 1982-01-22 Forced cooling operating device for cooler Granted JPS58127079A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
JP936582A JPS58127079A (en) 1982-01-22 1982-01-22 Forced cooling operating device for cooler

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
JP936582A JPS58127079A (en) 1982-01-22 1982-01-22 Forced cooling operating device for cooler

Publications (2)

Publication Number Publication Date
JPS58127079A true JPS58127079A (en) 1983-07-28
JPS645231B2 JPS645231B2 (en) 1989-01-30

Family

ID=11718446

Family Applications (1)

Application Number Title Priority Date Filing Date
JP936582A Granted JPS58127079A (en) 1982-01-22 1982-01-22 Forced cooling operating device for cooler

Country Status (1)

Country Link
JP (1) JPS58127079A (en)

Also Published As

Publication number Publication date
JPS645231B2 (en) 1989-01-30

Similar Documents

Publication Publication Date Title
JPS58127079A (en) Forced cooling operating device for cooler
JPS592812B2 (en) temperature control device
JPS6113544B2 (en)
JPS62272078A (en) Temperature controller for refrigerator
JPS6370059A (en) Refrigerator
JPS5939585Y2 (en) Anti-condensation heater control device
JPS59180187U (en) refrigerator control device
JPS5912940B2 (en) temperature control device
JPS59116783U (en) air conditioner
JPS5972437U (en) air conditioner
JPS6380177A (en) Method of starting motor
JPS61173067A (en) Refrigerator controller
JPS5898534U (en) Air conditioner temperature control device
JPS58194479U (en) Refrigerator automatic control device
JPS6037746U (en) Air conditioner room temperature control circuit
JPS5913876A (en) Defrosting controller
JPS5837428U (en) Defrost device
JPS5988680U (en) Defrost control device for cooling equipment
JPS6068357U (en) Refrigeration equipment control device
JPH063316B2 (en) Remote control device for air conditioner
KR19990017474A (en) Mode changer of heat exchanger
JPS60186640A (en) Control device of air conditioner
JPS6130175B2 (en)
JPS62248985A (en) Self-diagnostic device for refrigerator
JPH04363533A (en) Control device for air-conditioner