JPS5789018A - Construction work for cut-off wall - Google Patents

Construction work for cut-off wall

Info

Publication number
JPS5789018A
JPS5789018A JP16556680A JP16556680A JPS5789018A JP S5789018 A JPS5789018 A JP S5789018A JP 16556680 A JP16556680 A JP 16556680A JP 16556680 A JP16556680 A JP 16556680A JP S5789018 A JPS5789018 A JP S5789018A
Authority
JP
Japan
Prior art keywords
liquid
bentonite
supplied
sand
pump
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
JP16556680A
Other languages
Japanese (ja)
Inventor
Michitake Ueda
Toshio Kato
Okio Yoshida
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Tone Boring Co Ltd
TONE BORING KK
Original Assignee
Tone Boring Co Ltd
TONE BORING KK
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Tone Boring Co Ltd, TONE BORING KK filed Critical Tone Boring Co Ltd
Priority to JP16556680A priority Critical patent/JPS5789018A/en
Publication of JPS5789018A publication Critical patent/JPS5789018A/en
Pending legal-status Critical Current

Links

Landscapes

  • Bulkheads Adapted To Foundation Construction (AREA)

Abstract

PURPOSE: To economically construct a cut-off wall of uniform structure by a method in which bentonite liquid for excavating a trench is separated from soil and sand for recovery and then mixed with cement, and the mixture liquid is supplied to the excavated trench so as to replace a grout and also to solidify.
CONSTITUTION: A bentonite liquid is supplied through a silo 32 and a quantitative supplier 64 to a continuous injection mixer 30 and also water is supplied through a hose 34 and a quantitative supply pump 66 to the injection mixer 30, where they are mixed together and supplied through a tank 36 and a pump 38 to a tank 10. The bentonite stabilization liquid is put through a sand pump 12 and a hose 14 into an excavated trench 16 and recovered with excavated soil and sand through a reverse hose 20 and suction pump 22. And, soil and sand separated from the bentonite by a soil and sand separator 26 are discarded by a container 28. Then, an admixture, e.g., cement, etc., is sent from a silo 44 and mixed with bentonite in a mixer 30, and the mixture liquid thus obtained is supplied through a tank 46 and an injection pump 48 to the bottom of the trench 16. Whereupon, the stabilizer in the upper part is pushed up by the mixture liquid and replaced, but the stabilizer liquid is not mixed with the mixture liquid even when the difference between their specific gravities is slight.
COPYRIGHT: (C)1982,JPO&Japio
JP16556680A 1980-11-25 1980-11-25 Construction work for cut-off wall Pending JPS5789018A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
JP16556680A JPS5789018A (en) 1980-11-25 1980-11-25 Construction work for cut-off wall

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
JP16556680A JPS5789018A (en) 1980-11-25 1980-11-25 Construction work for cut-off wall

Publications (1)

Publication Number Publication Date
JPS5789018A true JPS5789018A (en) 1982-06-03

Family

ID=15814791

Family Applications (1)

Application Number Title Priority Date Filing Date
JP16556680A Pending JPS5789018A (en) 1980-11-25 1980-11-25 Construction work for cut-off wall

Country Status (1)

Country Link
JP (1) JPS5789018A (en)

Cited By (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPS5931310A (en) * 1982-08-14 1984-02-20 Shimizu Constr Co Ltd Continuous manufacturing apparatus for stabilizer liquid
JPS60141917A (en) * 1983-12-28 1985-07-27 Takenaka Komuten Co Ltd Plant reusing extra liquid for production of soil pile
JPS60141989A (en) * 1983-12-27 1985-07-27 東邦技建株式会社 Muddy water cementing method

Citations (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPS491011A (en) * 1972-04-18 1974-01-08
JPS543322A (en) * 1977-06-09 1979-01-11 Mitsui Constr Method of constructing underground structure

Patent Citations (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPS491011A (en) * 1972-04-18 1974-01-08
JPS543322A (en) * 1977-06-09 1979-01-11 Mitsui Constr Method of constructing underground structure

Cited By (6)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPS5931310A (en) * 1982-08-14 1984-02-20 Shimizu Constr Co Ltd Continuous manufacturing apparatus for stabilizer liquid
JPS6357564B2 (en) * 1982-08-14 1988-11-11 Shimizu Kensetsu Kk
JPS60141989A (en) * 1983-12-27 1985-07-27 東邦技建株式会社 Muddy water cementing method
JPS6350493B2 (en) * 1983-12-27 1988-10-11 Toho Giken Kk
JPS60141917A (en) * 1983-12-28 1985-07-27 Takenaka Komuten Co Ltd Plant reusing extra liquid for production of soil pile
JPH0115654B2 (en) * 1983-12-28 1989-03-20 Takenaka Komuten Co

Similar Documents

Publication Publication Date Title
CN1165667C (en) Method of filling hole by using aggregate
CN112723906A (en) Preparation and construction method of light filler based on building slurry
JPS5789018A (en) Construction work for cut-off wall
JPS5513332A (en) Circulation mixture system sludge solidifying process
JPS63233115A (en) Soil reclaiming and filling work
CN110639939A (en) Industrial salt slag landfill system and leachate treatment method
CN205475280U (en) Interim dock entrance cofferdam structure convenient to resume
JPS55105035A (en) Removal of gravels on civil engineering job site
JPS5774427A (en) Construction method for underground continuous wall
JPS56119013A (en) Hollow fill-type dam
JPS55165317A (en) Burying method for steel-pipe sheet pile
JPS54128486A (en) Excavation method using stabilizing fluid in engineering fundamental work
JPS5740031A (en) Replacement treatment of mixed mud water for underground wall construction
JPS57155423A (en) Method of construction of solidification of muddy water
JP2504682B2 (en) Underwater landfill method
JPS57165519A (en) Stabilization work for ground
JPS55161117A (en) Constructing method for underground continuous wall by precast concrete member
JPH01102122A (en) Ground improving work
JPS641812A (en) Hardened reinforcement construction and manufacture thereof
JPH0135032B2 (en)
JPH0423990Y2 (en)
JPS56111720A (en) Constructing method for cast-in-site pile
JPS5555722A (en) Constructing mooring anchorage for ship or foundation of structure on ground such as sea bottom
SU939739A1 (en) Method of isolating inflow of subsoil water into well
JPH07100822A (en) Manufacture of hydraulic material