JPS57108321A - Construction of foundation for building and structure - Google Patents

Construction of foundation for building and structure

Info

Publication number
JPS57108321A
JPS57108321A JP18373880A JP18373880A JPS57108321A JP S57108321 A JPS57108321 A JP S57108321A JP 18373880 A JP18373880 A JP 18373880A JP 18373880 A JP18373880 A JP 18373880A JP S57108321 A JPS57108321 A JP S57108321A
Authority
JP
Japan
Prior art keywords
foundation
pit
soil
excavated
building
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
JP18373880A
Other languages
Japanese (ja)
Inventor
Morio Yashiki
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Individual
Original Assignee
Individual
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Individual filed Critical Individual
Priority to JP18373880A priority Critical patent/JPS57108321A/en
Publication of JPS57108321A publication Critical patent/JPS57108321A/en
Pending legal-status Critical Current

Links

Landscapes

  • Foundations (AREA)

Abstract

PURPOSE: To simply construct a foundation having excellent strength by a method in which soil and sand from the excavation of a pit are mixed with a hardening agent for soil, and then the mixture is filled in the excavated pit, compacted, and then hardened.
CONSTITUTION: A pit 2 is excavated to the shape of a foundation to be formed under the ground, and soil and sand 3 from the excavation of the pit are a soil hardening agent 4 in a mixing proportion of about 5W20wt%. Then, the mixture is filled in the excavated pit 2, compacted by a rammer, etc., and then hardened to construct the foundation 6.
COPYRIGHT: (C)1982,JPO&Japio
JP18373880A 1980-12-26 1980-12-26 Construction of foundation for building and structure Pending JPS57108321A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
JP18373880A JPS57108321A (en) 1980-12-26 1980-12-26 Construction of foundation for building and structure

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
JP18373880A JPS57108321A (en) 1980-12-26 1980-12-26 Construction of foundation for building and structure

Publications (1)

Publication Number Publication Date
JPS57108321A true JPS57108321A (en) 1982-07-06

Family

ID=16141102

Family Applications (1)

Application Number Title Priority Date Filing Date
JP18373880A Pending JPS57108321A (en) 1980-12-26 1980-12-26 Construction of foundation for building and structure

Country Status (1)

Country Link
JP (1) JPS57108321A (en)

Cited By (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPS6192220A (en) * 1984-10-09 1986-05-10 Tobishima Kensetsu Kk Method of building underground structure using ground improving agent
JPS63233115A (en) * 1987-03-20 1988-09-28 Sumitomo Cement Co Ltd Soil reclaiming and filling work
JP2006294673A (en) * 2005-04-06 2006-10-26 Mitsubishi Electric Corp Transformer content supporting device

Cited By (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPS6192220A (en) * 1984-10-09 1986-05-10 Tobishima Kensetsu Kk Method of building underground structure using ground improving agent
JPS63233115A (en) * 1987-03-20 1988-09-28 Sumitomo Cement Co Ltd Soil reclaiming and filling work
JP2006294673A (en) * 2005-04-06 2006-10-26 Mitsubishi Electric Corp Transformer content supporting device

Similar Documents

Publication Publication Date Title
JPS57108321A (en) Construction of foundation for building and structure
JPS57108328A (en) Formation of basement
JPS5536584A (en) Construction process for continuous underground wall
JPS56142923A (en) Construction of foundation pile and case auger used therefor
JPS5631928A (en) Constructing method for soil pile
JPS6436820A (en) Filler grouting work by h-steel drawing in underground structure construction
JPS5664028A (en) Sheathing construction work by antecedent support framework
JPS57108329A (en) Formation of basement
JPS56142922A (en) Treatment of top of in-place concrete pile
JPS57112513A (en) Construction of foundation pile for ground improvement
JPS5721622A (en) Construction of large-diameter pile in site
JPS5526356A (en) Soft ground improvement method and its device
JPS5774427A (en) Construction method for underground continuous wall
GB1252244A (en)
JPS56156315A (en) Ground-hardened foundation structure and its construction work
JPS554487A (en) Foundation pile
JPS5751331A (en) Construction of continuous underground wall
JPS5568931A (en) Construction of block piled retaining wall and block
JPS55105032A (en) Formation of basic structure in poor subsoil
JPS5796124A (en) Solidification work of ground
JPS56163318A (en) Settling guider for foundation pile
JPS57100217A (en) Refilling work for vacant area of concrete pile driven in site
JPS5927022A (en) Continuous cut-off wall work of cement mortar
SU949052A1 (en) Injection mortar for concreting building joints of water engineering structures and consolidation rocks
SU1666620A1 (en) Method for constructing earth upstream apron of water retaining structures