Method and device for removing pile head extra-banking part concrete

Info

Publication number
JPH1150451A
JPH1150451A JP21981697A JP21981697A JPH1150451A JP H1150451 A JPH1150451 A JP H1150451A JP 21981697 A JP21981697 A JP 21981697A JP 21981697 A JP21981697 A JP 21981697A JP H1150451 A JPH1150451 A JP H1150451A
Authority
JP
Japan
Prior art keywords
concrete
hole
opening
separator
pile head
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Granted
Application number
JP21981697A
Other languages
Japanese (ja)
Other versions
JP3077747B2 (en
Inventor
Koichi Otsuka
浩一 大塚
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Toto Electric Industry Co Ltd
Original Assignee
Toto Electric Industry Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Toto Electric Industry Co Ltd filed Critical Toto Electric Industry Co Ltd
Priority to JP09219816A priority Critical patent/JP3077747B2/en
Publication of JPH1150451A publication Critical patent/JPH1150451A/en
Application granted granted Critical
Publication of JP3077747B2 publication Critical patent/JP3077747B2/en
Anticipated expiration legal-status Critical
Expired - Fee Related legal-status Critical Current

Links

Abstract

PROBLEM TO BE SOLVED: To facilitate removal of an extra-banking part by a method wherein ready mixed-concrete poured from below a separator brought into an opening state and when an extra banking part reached a given position, an opening is placed in a closed state and after curing, a portion above a separator part is removed. SOLUTION: In a cage 4, hoop ties 5 are arranged up to a position where a pile body is formed. The vertical reinforcement of the cage 4 in a position equivalent to an extra-banking part 8 is inserted in a vertical reinforcement hole of a partition plate 11 to set a section member 30. By operating a lever 24, the hole of the partition plate 11 and the hole of an opening closing plate 21 are positioned flush with each other and brought into a mutually opening state. Ready mixed-concrete is poured through a tremie pipe 3. When ready mixed-concrete is raised to the size of the extra- banking part through an opening composed of the hole of the partition plate 11 and the hole of the opening closing plate 21, concreting is completed and the opening is blocked by a lever 24. After curing of the concrete, the whole of the section member 30 and the concrete extra-banking part 8 are lifted by a lifting tool 16 and is removed from the head part of a pile body. This constitution prevents the occurrence of environment pollution due to vibration, noise, and dusting.

Description

【発明の詳細な説明】DETAILED DESCRIPTION OF THE INVENTION

【0001】[0001]

【発明の属する技術分野】本発明は、土木・建築工事な
どの構造物基礎工事において、場所打ちコンクリート杭
の頭部余盛り部を除去するための杭頭余盛り部コンクリ
ートの除去方法およびその装置に関し、特に、構築する
コンクリート杭本体とこの杭の頭部余盛り部の境目とな
る位置に、両者を区画する部材を装着し、確実、かつ、
容易に余盛り部を除去するようにした方法およびその装
置に関するものである。
BACKGROUND OF THE INVENTION 1. Field of the Invention The present invention relates to a method and an apparatus for removing an excess pile head portion concrete for removing an excess pile head portion of a cast-in-place concrete pile in a foundation work of a structure such as civil engineering and construction work. With regard to the concrete pile body to be built, in particular, a member for partitioning the concrete pile body at a position that is a boundary between the head pile portion and the pile, and reliably and,
The present invention relates to a method and an apparatus for easily removing a surplus portion.

【0002】[0002]

【従来の技術】一般的な場所打ちコンクリート杭の構築
と、そのコンクリート杭の杭頭余盛り部の除去方法を図
1に基づき説明する。 図1(a):コンクリート杭打ちのために地面1に、所
定の大きさで、所定の深さの縦孔2を穿つ。この縦孔2
に、鉄筋籠4を挿入後、トレミー管3を介してミキサー
車9から生コンクリート6を流し込む。通常、縦孔2に
は、孔壁の崩落を防止するためにベントナイト泥水を充
満させており、縦孔2の底部へ生コンクリート6を流し
込むと、それに対応する量のベントナイト泥水が置換さ
れて外部へ排除される。また、鉄筋籠4は、略円形状に
配置された縦筋に一定間隔で横方向の帯筋5が設けられ
て円筒籠状に形成されているが、余盛り部8に相当する
上部の帯筋5は除かれている。穿たれた縦孔2の地表1
からある深さまでは、孔上部の崩落を防止するため、通
常は、縦孔2に密着する径の保護管が挿入されるが、図
示を省略している。
2. Description of the Related Art A general construction of a cast-in-place concrete pile and a method of removing an extra pile head portion of the concrete pile will be described with reference to FIG. FIG. 1 (a): A vertical hole 2 of a predetermined size and a predetermined depth is drilled in the ground 1 for concrete pile driving. This vertical hole 2
After the rebar basket 4 is inserted, the ready-mixed concrete 6 is poured from the mixer truck 9 through the tremy tube 3. Normally, the vertical hole 2 is filled with bentonite muddy water in order to prevent the hole wall from collapsing, and when the ready-mixed concrete 6 is poured into the bottom of the vertical hole 2, a corresponding amount of bentonite muddy water is replaced and the outside is replaced. To be eliminated. Further, the reinforcing bar cage 4 is formed in a cylindrical cage shape by providing horizontal band bars 5 at regular intervals on vertical bars arranged in a substantially circular shape, but the upper band corresponding to the excess portion 8 is formed. Streak 5 has been removed. Ground surface 1 of vertical hole 2 drilled
In order to prevent the upper part of the hole from collapsing at a certain depth, a protective tube having a diameter closely contacting the vertical hole 2 is usually inserted, but is not shown.

【0003】図1(b):縦孔2への生コンクリート6
の流し込み工程が進捗し、略最終段階に入った状態を示
している。トレミー管3は、縦孔2に堆積された構造コ
ンクリート7の堆積高さに応じて段階的に短縮され、崩
落泥土、木くずなど不純混合物を含むコンクリートは、
上部に押し上げられ余盛り部8を形成する。
FIG. 1 (b): Ready-mixed concrete 6 in vertical hole 2
This shows a state in which the pouring process has progressed and has almost entered the final stage. The tremy pipe 3 is gradually reduced in accordance with the pile height of the structural concrete 7 deposited in the vertical hole 2, and concrete containing an impure mixture such as landslide mud, wood chips,
It is pushed up to form a margin 8.

【0004】図1(c):縦孔2への流し込みが完了
し、トレミー管3を抜き取った状態を示しており、コン
クリート杭本体の頭部に、余盛り部8が形成されてい
る。
FIG. 1 (c) shows a state in which the pouring into the vertical hole 2 is completed and the tremy tube 3 is pulled out, and an extra embossed portion 8 is formed at the head of the concrete pile main body.

【0005】図1(d):流し込んだコンクリートが固
化した後、杭頭の余盛り部8を破砕、除去した状態を示
している。
FIG. 1 (d) shows a state where the excess pile 8 of the pile head is crushed and removed after the poured concrete is solidified.

【0006】縦孔2に生コンクリート6を流し込むと、
孔壁より崩落した泥土や木くずなどは、コンクリート中
を浮上するので、構築された杭頭部のコンクリートは不
純混合物を含み、強度的なな信頼性が失われる。したが
って、余盛り部8と称して杭の頭部に不純混合物を含む
余分なコンクリートを打設し、コンクリートが固化して
から信頼できないその余盛り部8のコンクリートを除去
する工法が採られている。
When the ready-mixed concrete 6 is poured into the vertical hole 2,
Mud and wood chips that have collapsed from the bored wall float in the concrete, so the concrete at the head of the constructed pile contains an impure mixture and loses strong reliability. Therefore, a method is adopted in which excess concrete containing an impurity mixture is poured into the head of the pile, referred to as the extra bank 8, and the unreliable concrete in the extra bank 8 is removed after the concrete solidifies. .

【0007】従来、固化したコンクリート余盛り部8の
除去には、ドリルハンマー、振動ハンマー、たがねなど
を使用した人力による破砕、除去方法が採られている。
また、自動化、機械化が難しい杭頭除去工程は、場所打
ち杭構築のなかでも工期、費用ともに大きな比重を占め
ており、現場における工期、コスト的に大きな負担を強
いられている。
Conventionally, a method of removing and solidifying the excess concrete portion 8 by manual crushing and removal using a drill hammer, a vibration hammer, a chisel or the like has been adopted.
In addition, the pile head removal process, which is difficult to automate and mechanize, occupies a large proportion of both the construction period and cost in the construction of cast-in-place piles, and places a heavy burden on the construction period and cost at the site.

【0008】従来、打設したコンクリートの余盛り部8
に限定的に空気や発泡剤を混合して脆弱化し、杭頭除去
作業を容易にする方法が提案されている。
Conventionally, an excess portion 8 of cast concrete
A method has been proposed in which air and a foaming agent are mixed to make the material brittle to facilitate pile head removal work.

【0009】また、機械的破砕を人力によらず、専用の
回転式破砕機を使用して行う方法も提案されている。
[0009] A method has also been proposed in which mechanical crushing is performed using a dedicated rotary crusher without using human power.

【0010】杭頭を破砕した破砕片の除去、排出は、鉄
筋籠が邪魔するためにパワーシャベルなどの機械力を導
入し難く、杭頭の破砕作業を機械化した場合でも、破砕
片の除去、排除作業は、人力による手作業で行われてい
る。
[0010] The removal and discharge of the crushed pieces that crushed the pile head is difficult to introduce mechanical force such as a power shovel because the steel cage hinders the crushed pieces. The elimination work is performed manually by hand.

【0011】[0011]

【発明が解決しようとする課題】場所打ち杭頭部除去作
業における削岩機、振動ハンマー、たがねなどを使用す
る従来方法は、固化した杭頭部コンクリート破砕作業に
伴う振動、騒音、粉塵の発生などが環境問題となってい
る。
The conventional method using a rock drill, a vibrating hammer, a chisel and the like in a cast-in-place pile head removal operation is based on the vibration, noise, dust and the dust associated with the solidified pile head concrete crushing operation. Is an environmental problem.

【0012】また、発生粉塵による気管、呼吸器疾患、
振動による白蝋病などの労働衛生上の問題も惹起してい
る。
In addition, tracheal and respiratory diseases caused by the generated dust,
Occupational health problems such as white wax caused by vibration have also been raised.

【0013】杭頭部のコンクリートを脆弱化する方法
は、頭部コンクリートの破砕が容易になり、振動、騒
音、発塵が軽減されるとはいえ、基本的に機械的破砕で
あり、破砕作業に伴う諸問題を皆無にすることはできな
い上、破砕片の除去は人力による手作業に頼らざるを得
なかった。
[0013] The method of weakening the concrete at the pile head is basically mechanical crushing, although the crushing of the head concrete is facilitated and vibration, noise and dust generation are reduced. In addition to eliminating the various problems associated with the above, the removal of debris had to rely on manual work by humans.

【0014】また、従来の杭頭部コンクリート脆弱化方
法は、除去すべき余盛り部分と本来の性能を保持すべき
杭本体部分の境界を明確にすることができないので、脆
弱化すべき部分に過不足が生ずる。
Further, the conventional method of weakening the pile head concrete does not make it possible to clarify the boundary between the extra pile portion to be removed and the pile main body portion to maintain the original performance. Shortage occurs.

【0015】人力に依存しない回転式破砕機を使用した
破砕方法にあっては、鉄筋籠の内側にあるコンクリート
の大部分は破砕できるが、鉄筋に固化、付着しているコ
ンクリートの剥離、除去および破砕片の除去は、依然と
して人力によって行わなければならないなど、種々の問
題を有している。
In the crushing method using a rotary crusher that does not depend on human power, most of the concrete inside the reinforcing bar can be crushed, but concrete that has solidified and adhered to the reinforcing bar can be separated, removed and removed. There are various problems, such as removal of crushed pieces still having to be performed manually.

【0016】本発明の目的は、振動、騒音、発塵などに
よる環境汚染および労働衛生上の問題を皆無にした場所
打ち杭の杭頭余盛り部の除去方法および装置を提供する
ことにある。
SUMMARY OF THE INVENTION An object of the present invention is to provide a method and an apparatus for removing an extra pile head portion of a cast-in-place pile which eliminates environmental pollution and occupational health problems due to vibration, noise, dust generation and the like.

【0017】本発明の他の目的は、場所打ち杭の構築作
業の省人化および工程の短縮化を図り、工費を低減した
方法および装置を提供することにある。
Another object of the present invention is to provide a method and an apparatus which reduce labor and labor of construction work of cast-in-place piles and reduce the cost.

【0018】本発明のさらに他の目的は、除去すべき杭
頭の余盛り部と杭本体を構成するコンクリートの間に区
画部材を設けて施工することにより、除去すべき部分を
脆弱化しても、その部分に過不足を生ずることのない方
法および装置を提供することにある。
Still another object of the present invention is to provide a partition member between an extra pile portion of a pile head to be removed and concrete constituting a pile main body and to construct the pile, thereby making the portion to be removed weak. To provide a method and an apparatus that does not cause excess or shortage in the portion.

【0019】[0019]

【課題を解決するための手段】本発明は、削孔に生コン
クリートを流し込み、コンクリート杭を構築する構造物
基礎工事において、流動性生コンクリートの通過可能な
孔を開閉自在に形成してなるセパレータを杭頭位置に設
置する工程と、前記削孔に流し込んだ生コンクリートが
杭頭位置に達した後、セパレータの孔から余盛り部コン
クリートを上昇させる工程と、余盛り部が所定位置まで
達したら生コンクリートの流し込みを止め、セパレータ
の孔を閉じる工程と、打設したコンクリートが固化また
は半固化したらセパレータとともに余盛り部を取り除く
工程とからなることを特徴とする杭頭余盛り部コンクリ
ートの除去方法である。
SUMMARY OF THE INVENTION The present invention relates to a separator in which a hole through which fluid ready-mixed concrete can pass is formed freely in a foundation work for a structure in which ready-mixed concrete is poured into a drilled hole to construct a concrete pile. A step of installing the concrete at the pile head position, and after the ready-mixed concrete poured into the borehole reaches the pile head position, a step of raising the excess concrete from the hole of the separator, and when the excess part reaches the predetermined position. A method for removing excess concrete in a pile head, comprising a step of stopping the flow of ready-mixed concrete and closing a hole in the separator, and a step of removing an excess part together with the separator when the poured concrete is solidified or semi-solidified. It is.

【0020】本発明による方法は、破砕作業を伴わない
ので、作業に起因する振動、騒音、粉塵の発生がなく、
環境汚染、労働衛生上の問題を避けることができる上、
人の力に頼らざるを得ない杭頭構築場所における破砕片
の除去作業を不要とするものである。
Since the method according to the present invention does not involve a crushing operation, there is no generation of vibration, noise and dust due to the operation, and
Avoid environmental pollution, occupational health problems,
This eliminates the need to remove crushed pieces at the pile head construction site, which must rely on human power.

【0021】杭頭の余盛り部における鉄筋は、縦方向の
みであり、横方向のフープと称される帯筋は設けられて
いないので、この部分の縦鉄筋を樹脂製などのスリーブ
で覆うことにより、コンクリート塊が鉄筋に固着するの
を防止し、余盛り部を除去するために吊り上げる際の摩
擦を軽減化する。
[0021] The reinforcing bar in the extra pile portion of the pile head is only in the vertical direction, and there is no strip bar called a horizontal hoop. Therefore, the vertical reinforcing bar in this portion should be covered with a sleeve made of resin or the like. Thereby, the concrete lump is prevented from sticking to the reinforcing bar, and the friction at the time of lifting in order to remove the excess pile portion is reduced.

【0022】セパレータで余盛り部コンクリートを完全
に分離できるので、あらかじめ脆弱化しておけば、セパ
レータと一体の状態で排除された余盛り部コンクリート
塊の破砕を容易にし、短時間でセパレータの再使用を可
能にする。
Since the excess concrete can be completely separated by the separator, if it is weakened in advance, it is easy to crush the excess concrete mass removed in an integrated state with the separator, and the separator can be reused in a short time. Enable.

【0023】[0023]

【発明の実施の形態】以下、本発明による杭頭余盛り部
コンクリートの除去方法およびその装置の実施例を図2
から図6に基づき説明する。図2は、杭頭に区画部材3
0を装着してコンクリートの流し込み施工した場合を示
している。この図2において、10は、区画部材30の
主体となるセパレータで、このセパレータ10は、杭本
体の構造コンクリート7と、この杭本体頭部の余盛り部
8とを上下に区画するものである。このセパレータ10
は、図2および図3に示すように、円形または多角形の
仕切り板11と、この仕切り板11よりやや小さい開閉
板21とがに互いに重合されて構成されている。
DETAILED DESCRIPTION OF THE PREFERRED EMBODIMENTS FIG. 2 shows an embodiment of a method and an apparatus for removing concrete at an extra pile portion of a pile head according to the present invention.
This will be described with reference to FIG. FIG. 2 shows the partition member 3 on the pile head.
0 shows the case where concrete is poured and installed. In FIG. 2, reference numeral 10 denotes a separator that is a main component of the partition member 30. The separator 10 vertically partitions the structural concrete 7 of the pile main body and the extra bank 8 of the pile main body head. . This separator 10
As shown in FIG. 2 and FIG. 3, a circular or polygonal partition plate 11 and an opening / closing plate 21 slightly smaller than the partition plate 11 are overlapped with each other.

【0024】前記仕切り板11の中央部には、垂直に管
状スリーブ12が補強リブ13で固着され、また、この
管状スリーブ12の上端部に固着したステー受け15と
前記仕切り板11の間には、複数本の補強用のステー1
4で連結され、前記ステー受け15の上面には、逆U字
形の吊り具16が2個設けられている。前記管状スリー
ブ12の内径は、前記トレミー管3が上下方向に遊嵌す
るだけの大きさを有する。
A tubular sleeve 12 is vertically fixed to a center portion of the partition plate 11 by a reinforcing rib 13, and a stay receiver 15 fixed to an upper end portion of the tubular sleeve 12 and the partition plate 11 are provided. , A plurality of reinforcement stays 1
4, two inverted U-shaped hanging members 16 are provided on the upper surface of the stay receiver 15. The inner diameter of the tubular sleeve 12 is large enough to allow the tremee tube 3 to loosely fit in the vertical direction.

【0025】前記開閉板21の中央部にも垂直に管22
が補強リブ23で固着され、この管22は、前記管状ス
リーブ12の外周に回転自在に遊嵌している。また、管
22の上端部には、水平方向にハンドル24が設けられ
ている。前記仕切り板11と開閉板21には、それぞれ
中心角30度またはそれよりやや小さい扇形の孔17、
27が等間隔で6個所に形成されており、ハンドル24
で開閉板21を水平方向に回動することによって、仕切
り板11の孔17と開閉板21の孔27が一致すると開
き、開いた位置から30度回動すると閉じるようになっ
ている。前記仕切り板11には、杭の構造材である鉄筋
籠4の縦筋部を貫通させる孔32が対応する位置に必要
数だけ開けられている。
The pipe 22 is also vertically arranged at the center of the opening / closing plate 21.
The tube 22 is rotatably loosely fitted on the outer periphery of the tubular sleeve 12. A handle 24 is provided at the upper end of the tube 22 in the horizontal direction. The partition plate 11 and the opening / closing plate 21 are each provided with a fan-shaped hole 17 having a central angle of 30 degrees or slightly smaller,
27 are formed at six locations at equal intervals.
By rotating the opening / closing plate 21 in the horizontal direction, the opening 17 is opened when the hole 17 of the partition plate 11 and the hole 27 of the opening / closing plate 21 coincide with each other, and closed when the opening 17 is rotated 30 degrees from the open position. The partition plate 11 is provided with a required number of holes 32 at the corresponding positions to penetrate the vertical bars of the reinforcing bar cage 4 which is a structural material of the pile.

【0026】図3(a)は、仕切り板11の孔17と開
閉板21の孔27を一致させて開口している状態を示し
ている。図3(b)は、図3(a)の開口状態から開閉
板21を水平方向に約30度回動して孔17と孔27が
閉鎖した状態を示している。なお、図3は、前記仕切り
板11の孔17と開閉板21の孔27の数をそれぞれ6
個所とし、孔の形状を扇形とした場合について図示した
が、重合する2枚の仕切り板11と開閉板21を、回動
する場合に限らず、面方向に移動して相対位置を変える
ことにより、選択的に開閉し、かつ、開口の大きさが生
コンクリートを通過せしむるに十分な大きさであればよ
く、孔数、形状に制約はない。
FIG. 3A shows a state in which the opening 17 of the partition plate 11 and the opening 27 of the opening / closing plate 21 are aligned and opened. FIG. 3B shows a state in which the opening and closing plate 21 is rotated about 30 degrees in the horizontal direction from the opening state in FIG. 3A and the holes 17 and 27 are closed. FIG. 3 shows that the number of holes 17 in the partition plate 11 and the number of holes 27 in the
Although the case where the shape of the hole is fan-shaped is shown in the figure, the two partitioning plates 11 and the opening / closing plate 21 to be superimposed are not limited to the case of rotating, but are moved in the plane direction to change the relative position. The opening and closing may be selectively performed, and the size of the opening may be large enough to pass through the ready-mixed concrete, and there is no restriction on the number of holes and the shape.

【0027】つぎに、本発明による方法および装置を使
用した場所打ち杭の構築手順を、図2について説明す
る。穿たれた削孔として縦孔2に鉄筋籠4を挿入する。
この鉄筋籠4には、杭本体を構成する位置まで帯筋5を
有するが、余盛り部8に相当する位置には、縦の鉄筋4
のみとなる。そこで、この余盛り部8に相当する位置の
縦鉄筋4の外周にコンクリート固着防止用スリーブ31
を被せる。このスリーブ31を被せた鉄筋籠4の縦筋
を、仕切り板11の孔32に差し込み案内して区画部材
30を縦孔2にセットする。仕切り板11は、鉄筋籠4
の最上部の帯筋5に妨げられ、それより深い位置に装着
することはできないが、その位置が余盛り部8に相当す
る位置である。もし、その位置が深すぎる場合、すなわ
ち、余盛り部8に相当する位置より下方である場合に
は、余盛り部8の設定寸法に応じて、帯筋5と仕切り板
11の間に、図示しないスペーサを介在するようにすれ
ばよい。
Next, a construction procedure of the cast-in-place pile using the method and the apparatus according to the present invention will be described with reference to FIG. The rebar basket 4 is inserted into the vertical hole 2 as a drilled hole.
The reinforcing bar cage 4 has a band 5 up to the position constituting the pile main body.
Only. Therefore, a concrete sticking prevention sleeve 31 is provided on the outer periphery of the vertical reinforcing bar 4 at a position corresponding to the surplus portion 8.
Put on. The vertical bar of the reinforcing bar cage 4 covered with the sleeve 31 is inserted into the hole 32 of the partition plate 11 and guided to set the partition member 30 in the vertical hole 2. The partition plate 11 is made of a reinforcing bar 4
Is not obstructed by the uppermost stirrup 5, and cannot be mounted at a position deeper than that. If the position is too deep, that is, if the position is lower than the position corresponding to the extra banking portion 8, depending on the set dimensions of the extra banking portion 8, the space between the strip 5 and the partition plate 11 is shown. What is necessary is just to make it intervene the spacer which does not do.

【0028】レバー24を操作して開閉板21を右また
は左に回動して、仕切り板11の孔17と開閉板21の
孔27が同じ位置にあり、互いに開口状態にあるように
しておく。トレミー管3を経由して縦孔2に生コンクリ
ート6を流し込む。生コンクリート6のレベルが上昇し
てセパレータ10の真下位置まで到達する。生コンクリ
ート6の流し込みによりトレミー管3は、少しずつ引き
上げられてくるが、不純混合物を含んだ余盛り部8は、
常に最上部に浮き上がるように、トレミー管3の下端の
コンクリート吐出部分は、余盛り部8よりも下方に位置
している。さらに、下部から吐出された生コンクリート
6に対応する体積のコンクリートが、孔17、27によ
って形成されている開口を通してセパレータ10の上部
に上昇してくる。
The lever 24 is operated to rotate the opening / closing plate 21 to the right or left so that the hole 17 of the partition plate 11 and the hole 27 of the opening / closing plate 21 are at the same position and are open to each other. . The ready-mixed concrete 6 is poured into the vertical hole 2 via the tremy tube 3. The level of the ready-mixed concrete 6 rises and reaches the position immediately below the separator 10. The tremy tube 3 is gradually pulled up by pouring the ready-mixed concrete 6, but the surplus portion 8 containing the impure mixture is
The concrete discharge portion at the lower end of the tremy tube 3 is located lower than the surplus portion 8 so as to always rise to the uppermost portion. Further, the concrete of the volume corresponding to the fresh concrete 6 discharged from the lower part rises to the upper part of the separator 10 through the opening formed by the holes 17 and 27.

【0029】ここでセパレータ10を通過してくるコン
クリートは、不純混合物を含んだ余盛り部8であり、決
められた余盛り部寸法までコンクリートが上昇すればコ
ンクリートの打設は完了する。コンクリートの打設完了
後、レバー24により開閉板20を回動して孔17、2
7によって形成される開口を閉止し、トレミー管3を引
き抜き、コンクリートが固化または半固化するまで放置
する。なお、コンクリートの打設後では、孔17、27
によって形成される開口が開いているか、閉じているか
が目視観察できないので、レバー20を回したとき、孔
17、27によって形成される開口が開または閉となる
位置を明確にし、それ以上にレバー20が回動しないよ
うに図示しないストッパーを設ければ、取り扱いを簡便
ならしむることができる。
Here, the concrete passing through the separator 10 is the surplus portion 8 containing the impure mixture. When the concrete rises to the predetermined surplus portion size, the concrete placement is completed. After the concrete has been poured, the opening / closing plate 20 is rotated by the lever 24 and the holes 17, 2
The opening formed by 7 is closed, the tremy tube 3 is withdrawn and left until the concrete has solidified or semi-solidified. After the concrete is cast, holes 17, 27
When the lever 20 is turned, the position where the opening formed by the holes 17 and 27 is opened or closed is clarified because the opening formed by the opening or closing cannot be visually observed. If a stopper (not shown) is provided to prevent the 20 from rotating, the handling can be simplified.

【0030】コンクリートが固化または半固化したら、
吊り具16で区画部材30全体を、コンクリート余盛り
部8とともに吊り上げて、杭本体の頭部から取り除く。
このとき鉄筋籠4に装着されたスリーブ31は、区画部
材30とともに吊り上げられるか、または縦筋側に残る
が、このスリーブ31は、使い捨て部材でありいずれで
あってもよい。区画部材30と一体に取り出された余盛
り部8のコンクリート塊は、適宜な場所で破砕、分離し
て、区画部材30の再使用ができるようにする。
When the concrete is solidified or semi-solidified,
The entire partition member 30 is lifted together with the extra concrete portion 8 by the lifting tool 16 and removed from the head of the pile body.
At this time, the sleeve 31 attached to the rebar basket 4 is lifted together with the partition member 30 or remains on the vertical streak side. However, this sleeve 31 may be a disposable member and may be any one. The concrete mass of the extra bank 8 taken out integrally with the partition member 30 is crushed and separated at an appropriate place so that the partition member 30 can be reused.

【0031】図2に示した区画部材30のステー14
は、余盛り部8を吊り上げるときの補強であり、縦孔2
の孔径、すなわち余盛り部8の重量によって相違する
が、補強リブ13のみで強度的に十分であれば必ずしも
必要とするものではない。また、図示例ではセパレータ
10を構成する仕切り板11の上に開閉板21を配置し
たが、この配置が上下逆であってもよく、要するに、孔
17と27とが開閉するものであれば、本発明による杭
頭コンクリート除去装置の機能、性能に影響はなく、い
ずれの配置とするかは任意である。
The stay 14 of the partition member 30 shown in FIG.
Is a reinforcement when lifting the extra pile portion 8, and the vertical hole 2
However, it is not always necessary if the reinforcing rib 13 alone is sufficient in terms of strength, though it depends on the hole diameter, ie, the weight of the surplus portion 8. Further, in the illustrated example, the opening / closing plate 21 is arranged on the partition plate 11 constituting the separator 10, but this arrangement may be upside down. In other words, as long as the holes 17 and 27 open and close, There is no effect on the function and performance of the pile head concrete removing device according to the present invention, and any arrangement is arbitrary.

【0032】図4は、セパレータ10を構成する仕切り
板11の外周に可撓性のあるゴム材などで構成されるシ
ール18を設け、縦孔2の孔壁と仕切り板11との間の
隙間をなくし、杭構造部コンクリート7と余盛り部8の
区画をさらに的確にし、後述のように、余盛り部8に脆
弱化処理をしたときに、杭構造部コンクリート7に悪影
響を与えないようにしたものである。
FIG. 4 shows a seal 18 made of a flexible rubber material or the like provided on the outer periphery of the partition plate 11 constituting the separator 10, and a gap between the hole wall of the vertical hole 2 and the partition plate 11. And the section of the pile structure portion concrete 7 and the extra pile portion 8 is made more accurate so that the pile portion concrete portion 7 is not adversely affected when the extra pile portion 8 is subjected to the weakening treatment as described later. It was done.

【0033】図5は、管状スリーブ12の上端に設けた
スプリング受け19と管22の上端に設けたレバー24
位置との間にコイルスプリング29を介在し、開閉板2
1を常に下方へ付勢して仕切り板11に密接するように
したものである。このような構成とすることにより、セ
パレータ10を構成する仕切り板11と開閉板21とが
互いに確実に面接触しつつ回動し、開閉板21と仕切り
板11との間にコンクリートが入り込むのを極力防いで
いる。この場合、スプリング受け19を管状スリーブ1
2にねじで螺合する構成にすれば、仕切り板11と開閉
板21とを分離、分解することが可能である。
FIG. 5 shows a spring receiver 19 provided at the upper end of the tubular sleeve 12 and a lever 24 provided at the upper end of the tube 22.
A coil spring 29 is interposed between the
1 is always urged downward so as to be in close contact with the partition plate 11. With such a configuration, the partition plate 11 and the opening / closing plate 21 constituting the separator 10 rotate while reliably making surface contact with each other, and the concrete enters between the opening / closing plate 21 and the partition plate 11. We are preventing as much as possible. In this case, the spring receiver 19 is attached to the tubular sleeve 1.
If the configuration is such that the partition plate 11 and the opening and closing plate 21 are screwed together with the screw 2, the partition plate 11 and the opening and closing plate 21 can be separated and disassembled.

【0034】図6は、余盛り部8を脆弱化処理するため
の装置を付加した例を示すもので、開閉板21の上面に
上向きの複数の吹き出しノズル41を設け、この吹き出
しのズル41に、管22に添って上端部から設けた注入
管40を連結し、脆弱化する薬液Pを加圧空気とともに
注入するようにしたものである。このような構成によ
り、コンクリートの打設完了後、レバー24により開閉
板20を回して孔17、27によって形成される開口を
閉止し、トレミー管3を引き抜き、注入管40から薬液
Pを加圧空気とともに注入し、複数の吹き出しノズル4
1から余盛り部8に浸透させ、脆弱化する。
FIG. 6 shows an example in which a device for weakening the extra pile portion 8 is added. A plurality of upward blowing nozzles 41 are provided on the upper surface of the opening / closing plate 21, and the chisels 41 of the blowing are provided. An injection pipe 40 provided from the upper end along the pipe 22 is connected to inject the weakened chemical solution P together with pressurized air. With such a configuration, after the concrete is poured, the opening formed by the holes 17 and 27 is closed by turning the opening / closing plate 20 by the lever 24, the tremy tube 3 is pulled out, and the chemical solution P is pressurized from the injection tube 40. Inject with the air, multiple blowing nozzles 4
It penetrates from 1 to the excess portion 8 and becomes weak.

【0035】[0035]

【発明の効果】本発明によれば、上記に説明したよう
に、土木・建築工事などの構造物基礎工事における場所
打ち杭の杭頭コンクリート除去について、破砕除去を行
わず、除去すべき余盛り部と構造体コンクリート部を区
画して余盛り部を一括吊り上げ除去することにより、振
動、騒音、発塵などによる環境汚染、および労働衛生上
の問題点を皆無にした場所打ち杭の杭頭コンクリート除
去が可能となる。
According to the present invention, as described above, for removing pile head concrete of cast-in-place piles in structural foundation work such as civil engineering and construction work, crushing removal is not performed, and extra pile to be removed is required. Pile head concrete for cast-in-place piles that eliminates environmental pollution and occupational health problems caused by vibration, noise, dust generation, etc. Removal is possible.

【0036】さらに本発明によれば、構築場所における
破砕作業が不要であり、場所打ち杭の構築作業を省人化
させることができ、作業工程が短縮化され、工費の低減
化に大きく寄与することができる。
Further, according to the present invention, the crushing work at the construction site is unnecessary, the construction work of the cast-in-place pile can be saved, the work process is shortened, and the construction cost is greatly reduced. be able to.

【0037】また、本発明によれば、除去すべき杭頭の
余盛り部にコンクリートを脆弱化する薬剤を注入したと
き、杭の構造部を形成するコンクリート部分に支障を与
える恐れのない施工が可能であり、区画部材と一体で除
去された余盛り部コンクリート塊の破砕が容易である。
Further, according to the present invention, there is provided a construction which does not hinder the concrete portion forming the structural portion of the pile when the agent for weakening the concrete is injected into the extra pile portion of the pile head to be removed. It is possible, and it is easy to crush the overfill concrete mass removed integrally with the partition member.

【図面の簡単な説明】[Brief description of the drawings]

【図1】一般的な場所打ち杭の構築工程を説明する説明
図である。
BRIEF DESCRIPTION OF DRAWINGS FIG. 1 is an explanatory diagram illustrating a general construction process of a cast-in-place pile.

【図2】本発明による杭頭余盛り部コンクリートの除去
方法およびその装置の機能を説明する断面図である。
FIG. 2 is a cross-sectional view illustrating the function of the method and the apparatus for removing the pile head extra concrete according to the present invention.

【図3】セパレータを構成する仕切り板と開閉板の平面
図で、(a)は、開口状態の平面図、(b)は、閉鎖状
態の平面図である。
3A and 3B are plan views of a partition plate and an opening / closing plate constituting a separator, wherein FIG. 3A is a plan view in an open state, and FIG. 3B is a plan view in a closed state.

【図4】セパレータの外周に可撓性のシールを設けた要
部の断面図である。
FIG. 4 is a sectional view of a main part in which a flexible seal is provided on the outer periphery of a separator.

【図5】セパレータの仕切り板と開閉板の面接触を強制
するためにスプリングを設けた断面図である。
FIG. 5 is a cross-sectional view in which a spring is provided for forcing surface contact between a partition plate of a separator and an opening / closing plate.

【図6】本発明による杭頭余盛り部コンクリートの除去
装置に余盛り部を脆弱化する薬液注入手段を付加した断
面図である。
FIG. 6 is a cross-sectional view of a device for removing concrete at a pile head extra portion according to the present invention, in which a chemical injection means for weakening the extra portion is added.

【符号の説明】[Explanation of symbols]

1…地面、2…縦孔(削孔)、3…トレミー管、4…鉄
筋、5…帯筋、6…生コンクリート、7…構造コンクリ
ート、8…余盛り部コンクリート、9…ミキサー車、1
0…セパレータ、11…仕切り板、12…管状スリー
ブ、13…補強リブ、14…ステー、15…ステー受
け、16…吊り具、17…孔、18…シール、19…ス
プリング受け、21…開閉板、22…管、23…補強リ
ブ、24…レバー、、27…孔、29…スプリング、3
0…区画部材、32…縦筋孔、40…注入配管、41…
吹き出しノズル。
DESCRIPTION OF SYMBOLS 1 ... Ground, 2 ... Vertical hole (drilling), 3 ... Tremey tube, 4 ... Reinforcing bar, 5 ... Strip reinforcing bar, 6 ... Fresh concrete, 7 ... Structural concrete, 8 ... Extra concrete, 9 ... Mixer truck, 1
0: Separator, 11: Partition plate, 12: Tubular sleeve, 13: Reinforcement rib, 14: Stay, 15: Stay receiver, 16: Hanging tool, 17: Hole, 18: Seal, 19: Spring receiver, 21: Opening / closing plate , 22 ... tube, 23 ... reinforcement rib, 24 ... lever, 27 ... hole, 29 ... spring, 3
0 ... partition member, 32 ... vertical stoma, 40 ... injection pipe, 41 ...
Spout nozzle.

Claims (6)

【特許請求の範囲】[Claims] 【請求項1】 削孔に生コンクリートを流し込み、コン
クリート杭を構築する構造物基礎工事において、流動性
生コンクリートの通過可能な孔を開閉自在に形成してな
るセパレータを杭頭位置に設置する工程と、前記削孔に
流し込んだ生コンクリートが杭頭位置に達した後、セパ
レータの孔から余盛り部コンクリートを上昇させる工程
と、余盛り部が所定位置まで達したら生コンクリートの
流し込みを止め、セパレータの孔を閉じる工程と、打設
したコンクリートが固化または半固化したらセパレータ
とともに余盛り部を取り除く工程とからなることを特徴
とする杭頭余盛り部コンクリートの除去方法。
1. A step of pouring ready-mixed concrete into a drilled hole to construct a concrete pile, and installing a separator at a pile head position, which is formed by opening and closing a hole through which fluidized ready-mixed concrete can pass. And, after the ready-mixed concrete poured into the drilling reaches the pile head position, a step of raising the excess concrete from the hole of the separator, and when the excess portion reaches a predetermined position, stop the pouring of the ready-mixed concrete, And removing the excess portion together with the separator when the poured concrete is solidified or semi-solidified.
【請求項2】 セパレータの孔を閉じる工程の後に、余
盛り部コンクリートに脆弱化処理剤を注入する工程を付
加してなることを特徴とする請求項1記載の杭頭余盛り
部コンクリートの除去方法。
2. A method according to claim 1, further comprising, after the step of closing the hole of the separator, a step of injecting an embrittlement treating agent into the concrete of the extra pile. Method.
【請求項3】 削孔に構築されるコンクリートの杭頭位
置に設置され、流動性生コンクリートの通過可能な孔を
開閉自在に形成したセパレータを具備し、このセパレー
タは、削孔を杭頭位置で流動性生コンクリートの上下流
動を遮断するための仕切り板とこの仕切り板に重合した
開閉板とからなり、前記流動性生コンクリートの通過可
能な孔は、前記仕切り板と開閉板の相互の位置を変える
ことにより開閉するようにし、前記セパレータの孔から
上昇させた余盛り部コンクリートをセパレータとともに
取り除くようにしたことを特徴とする杭頭余盛り部コン
クリートの除去装置。
3. A separator, which is installed at a pile head position of concrete to be drilled and has a hole formed so as to be able to open and close a hole through which fluid ready-mixed concrete can pass, the separator having a hole at a pile head position. A partition plate for blocking the vertical flow of the flowable ready-mixed concrete, and an opening / closing plate superimposed on the partitioning plate. The holes through which the flowable ready-mixed concrete can pass are located at the mutual positions of the partitioning plate and the opening / closing plate. A pile head excess portion concrete removing device, characterized in that it is opened and closed by changing the height of the pile, and the excess portion concrete raised from the hole of the separator is removed together with the separator.
【請求項4】 削孔に鉄筋を挿入して構築されるコンク
リートの杭頭位置に設置され、流動性生コンクリートの
通過可能な孔を開閉自在に形成したセパレータを具備
し、このセパレータは、前記削孔を杭頭位置で流動性生
コンクリートの上下流動を遮断するための仕切り板と、
この仕切り板に重合した開閉板とからなり、前記仕切り
板に、生コンクリート流し込み用トレミー管に遊嵌した
管状スリーブを固着するとともに、前記鉄筋を挿通する
鉄筋用孔を形成し、前記開閉板に、管状スリーブに遊嵌
した管を固着し、この開閉板を水平方向に回動すること
によって前記流動性生コンクリートの通過可能な孔を構
成する仕切り板の孔と開閉板の孔が相互に開閉するよう
になし、前記セパレータの孔から上昇させた余盛り部コ
ンクリートをセパレータとともに取り除くようにしたこ
とを特徴とする杭頭余盛り部コンクリートの除去装置。
4. A separator which is installed at a pile head position of a concrete constructed by inserting a reinforcing bar into a drilled hole and has a hole formed so as to be freely openable and closable through a fluid ready-mixed concrete, wherein the separator comprises A partition plate for blocking the vertical flow of fluid ready-mixed concrete at the pile head position,
An opening / closing plate superposed on the partition plate, a tubular sleeve loosely fitted to the fresh concrete pouring tremy tube is fixed to the partition plate, and a hole for a reinforcing bar through which the reinforcing bar is inserted is formed. By fixing the tube loosely fitted to the tubular sleeve and rotating the opening and closing plate in the horizontal direction, the opening of the partition plate and the opening of the opening and closing plate which constitute the hole through which the fluid ready-mixed concrete can pass are opened and closed mutually. A pile head excess portion concrete removing device, wherein the excess portion concrete raised from the hole of the separator is removed together with the separator.
【請求項5】 構築されるコンクリートの杭頭位置より
上方の縦鉄筋に、打設コンクリートの固着防止用スリー
ブを覆せ、このスリーブ部分を仕切り板の鉄筋用孔に挿
通してなることを特徴とする請求項4記載の杭頭余盛り
部コンクリートの除去装置。
5. A vertical reinforcing bar above a pile head position of concrete to be constructed is covered with a sleeve for preventing concrete from being cast, and this sleeve portion is inserted through a hole for a reinforcing bar of a partition plate. The pile head extra concrete removal device according to claim 4.
【請求項6】 仕切り板に固着した管状スリーブと開閉
板に固着した管との間に、前記開閉板を前記仕切り板に
密着せしめるスプリングを介在してなることを特徴とす
る請求項4または5記載の杭頭余盛り部コンクリートの
除去装置。
6. A spring which makes the opening / closing plate adhere to the partition plate, is interposed between the tubular sleeve fixed to the partition plate and the pipe fixed to the opening / closing plate. The concrete removal device for the pile head extra portion described.
JP09219816A 1997-08-01 1997-08-01 Method and apparatus for removing concrete at pile head extra Expired - Fee Related JP3077747B2 (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
JP09219816A JP3077747B2 (en) 1997-08-01 1997-08-01 Method and apparatus for removing concrete at pile head extra

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
JP09219816A JP3077747B2 (en) 1997-08-01 1997-08-01 Method and apparatus for removing concrete at pile head extra

Publications (2)

Publication Number Publication Date
JPH1150451A true JPH1150451A (en) 1999-02-23
JP3077747B2 JP3077747B2 (en) 2000-08-14

Family

ID=16741492

Family Applications (1)

Application Number Title Priority Date Filing Date
JP09219816A Expired - Fee Related JP3077747B2 (en) 1997-08-01 1997-08-01 Method and apparatus for removing concrete at pile head extra

Country Status (1)

Country Link
JP (1) JP3077747B2 (en)

Cited By (7)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN104631438A (en) * 2015-01-27 2015-05-20 安徽同济建设集团有限责任公司 Method for constructing long auger bored cast-with-pressure concrete uplift pile
CN104727305A (en) * 2015-01-27 2015-06-24 安徽同济建设集团有限责任公司 Drilling and high-pressure grouting construction method for uplift pile
JP6093466B1 (en) * 2016-04-05 2017-03-08 株式会社サンエイ Extra concrete removal bucket
CN109024574A (en) * 2018-08-09 2018-12-18 聊城安泰黄河水利工程维修养护有限公司 Integrated joint bar concrete pile construction method is perfused in pore-creating
JP2019015043A (en) * 2017-07-04 2019-01-31 株式会社サンエイ Pile head treatment bucket
CN111042132A (en) * 2020-01-13 2020-04-21 江苏鼎达建筑新技术有限公司 Pile head breaking device and construction method thereof
CN115094892A (en) * 2022-05-18 2022-09-23 安徽省交通规划设计研究总院股份有限公司 Multi-station auxiliary device and method for bridge construction

Cited By (10)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN104631438A (en) * 2015-01-27 2015-05-20 安徽同济建设集团有限责任公司 Method for constructing long auger bored cast-with-pressure concrete uplift pile
CN104727305A (en) * 2015-01-27 2015-06-24 安徽同济建设集团有限责任公司 Drilling and high-pressure grouting construction method for uplift pile
CN104727305B (en) * 2015-01-27 2016-11-02 安徽同济建设集团有限责任公司 Boring high-pressure slip-casting uplift pile construction method
JP6093466B1 (en) * 2016-04-05 2017-03-08 株式会社サンエイ Extra concrete removal bucket
JP2019015043A (en) * 2017-07-04 2019-01-31 株式会社サンエイ Pile head treatment bucket
CN109024574A (en) * 2018-08-09 2018-12-18 聊城安泰黄河水利工程维修养护有限公司 Integrated joint bar concrete pile construction method is perfused in pore-creating
CN109024574B (en) * 2018-08-09 2019-07-09 聊城安泰黄河水利工程维修养护有限公司 Integrated joint bar concrete pile construction method is perfused in pore-creating
CN111042132A (en) * 2020-01-13 2020-04-21 江苏鼎达建筑新技术有限公司 Pile head breaking device and construction method thereof
CN115094892A (en) * 2022-05-18 2022-09-23 安徽省交通规划设计研究总院股份有限公司 Multi-station auxiliary device and method for bridge construction
CN115094892B (en) * 2022-05-18 2023-08-22 安徽省交通规划设计研究总院股份有限公司 Multi-station auxiliary device and auxiliary method for bridge construction

Also Published As

Publication number Publication date
JP3077747B2 (en) 2000-08-14

Similar Documents

Publication Publication Date Title
JPS587765B2 (en) Method and apparatus for forming columns of underground fillings
JPS5991214A (en) Head treatment work of on-site pile
JP3077747B2 (en) Method and apparatus for removing concrete at pile head extra
EP2084331B1 (en) A method of constructing a pile
JPH10168880A (en) Removing device for obstacle to underground structure and removing method for the obstacle
JP2007224657A (en) Cast-in-place concrete pile construction method
JP2003147782A (en) Foundation structure for constructing new building on existing basement and its construction method
JPS59126821A (en) Erection work of foundation pile
JPH08209686A (en) Pile head processing tool and pile head processing construction method for cast-in-place pile
JPH0833007B2 (en) Grout method at cast-in-place concrete pile tip
GB2132667A (en) Method of installing precast concrete piles
JP6634251B2 (en) Pile foundation structure, ready-made pile burying device, method of constructing pile foundation structure using said ready-made pile burying device
JP2006322190A (en) Pile head processing method of cast-in-place concrete pile and concrete processing agent mixing device
JPH0613766B2 (en) Construction method of open-ended pile foundation
JPH0562170B2 (en)
JP2004150070A (en) Treatment method for removed soil, and removed soil-treated construction method for foundation pile
JPH0712422Y2 (en) Grout injection device at the tip of cast-in-place concrete pile
JP2640542B2 (en) Waterproof shaft construction method
JP2564465B2 (en) Ready-made pile burying method
JP3470954B2 (en) Method of laying interruption of manhole to existing buried pipe
JP2001090060A (en) Driving method for pile and constructing method for cut- off wall using the method
JPS63223215A (en) In-situ concrete piling work
JPH0430014A (en) Forming method for pile and forming construction method for foundation
JP2002348887A (en) Connecting method of pc pile and footing foundation
JPS63156118A (en) Bucket for taking out bentonite or the like

Legal Events

Date Code Title Description
R250 Receipt of annual fees

Free format text: JAPANESE INTERMEDIATE CODE: R250

R250 Receipt of annual fees

Free format text: JAPANESE INTERMEDIATE CODE: R250

LAPS Cancellation because of no payment of annual fees