JPH11303403A - Constructing method of building using temporary roof frame - Google Patents

Constructing method of building using temporary roof frame

Info

Publication number
JPH11303403A
JPH11303403A JP10634198A JP10634198A JPH11303403A JP H11303403 A JPH11303403 A JP H11303403A JP 10634198 A JP10634198 A JP 10634198A JP 10634198 A JP10634198 A JP 10634198A JP H11303403 A JPH11303403 A JP H11303403A
Authority
JP
Japan
Prior art keywords
building
frame
temporary roof
materials
roof frame
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
JP10634198A
Other languages
Japanese (ja)
Inventor
Yuutaro Omote
佑太郎 表
Noriyuki Furuya
則之 古屋
Haruka Ogawa
晴果 小川
Kohei Kurita
康平 栗田
Yasushi Hamada
耕史 浜田
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Obayashi Corp
Original Assignee
Obayashi Corp
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Obayashi Corp filed Critical Obayashi Corp
Priority to JP10634198A priority Critical patent/JPH11303403A/en
Publication of JPH11303403A publication Critical patent/JPH11303403A/en
Pending legal-status Critical Current

Links

Landscapes

  • Conveying And Assembling Of Building Elements In Situ (AREA)

Abstract

PROBLEM TO BE SOLVED: To solve the shortage of a site for construction works, and to carry out efficient transport by assembling a building member unit in a temporary roof frame. SOLUTION: A working floor 24 is installed to the lower section of the temporary roof frame 18 being elevated as well as the construction of a building frame 10 and covering the top face of the building frame 10 and a working space is formed on the inside, and materials 20 on a ground are taken into the working floor 24 by a jib crane 22 carrying the materials 20 into the space. The materials 20 are stocked or the materials 20 are unitized on the working floor 24 and a building member unit 26 is prepared, and the materials 20 and/or the building member unit 26 stocked are hung down on the structure of the building frame 10 under the execution of works through the floor opening section 24a of the working space by hoists 30, 32 mounted on an upper section in the temporary roof frame 18, and set up at specified places.

Description

【発明の詳細な説明】DETAILED DESCRIPTION OF THE INVENTION

【0001】[0001]

【発明の属する技術分野】本発明は、仮設屋根の架構を
利用して内・外装仕上げ材・構造部材その他のストッ
ク、およびそれらのユニットの組立ができるようにした
建物の構築方法に関する。
BACKGROUND OF THE INVENTION 1. Field of the Invention The present invention relates to a method of constructing a building in which a frame of a temporary roof can be used to assemble interior and exterior finishing materials, structural members and other stocks, and their units.

【0002】[0002]

【従来の技術】例えば、特開平5−239927公報、
特許第2657577号公報に開示されているように、
施工位置の上部に架設した昇降可能な仮設屋根架構を利
用して建物を構築することが知られている。
2. Description of the Related Art For example, Japanese Patent Laid-Open No. 5-239927,
As disclosed in Japanese Patent No. 2657577,
2. Description of the Related Art It is known to construct a building using a temporary roof frame that can be moved up and down, which is installed above a construction position.

【0003】この架構は、通常、大スパンのトラス構造
であり、建物の一階分にあたる空間を持つものであり、
昇降装置などによって建物躯体の構築に伴い順次上方に
移動する。
[0003] This frame is usually a large span truss structure having a space equivalent to one floor of a building.
It moves upwards sequentially with the construction of the building frame by a lifting device.

【0004】そして、仮設屋根架構の内部は、架構の昇
降および架構の下側に設置されたレールを走行するクレ
ーン、ホイスト、ロボットアームなどの資材搬送取付け
装置の制御室として使用され、全天候型の構築が可能で
ある。
[0004] The interior of the temporary roof frame is used as a control room for a material transporting and mounting device such as a crane, a hoist, and a robot arm that travels on rails installed under the frame and lifts and lowers the frame. Construction is possible.

【0005】一方、例えば、建築の技術施工1996年
3月号110頁に開示されているように、予め床スラ
ブ、梁材および設備配管・機器をユニット化することも
知られている。
On the other hand, it is also known to unitize floor slabs, beams, and piping / equipment in advance as disclosed in, for example, page 110 of the March 1996 issue of construction engineering.

【0006】以上の仮設屋根架構による建物躯体の構築
方法に、ユニット化工法を組合わせれば、さらに合理的
で、施工も短縮できる。
[0006] By combining the above-mentioned method of constructing a building frame with a temporary roof frame with a unitized construction method, it is more rational and the construction can be shortened.

【0007】図3は、その組合せ例を示すもので、施工
中の建物躯体1の上部には、昇降装置2によって、昇降
可能な仮設屋根架構3が配置されており、架構3内に配
備された制御室4からの制御操作によってその下部に設
けた資材搬送取付装置5を駆動して、建物躯体1が順次
組立てられる。
FIG. 3 shows an example of such a combination. A temporary roof frame 3 which can be raised and lowered by an elevating device 2 is disposed above a building frame 1 under construction. The material transport mounting device 5 provided thereunder is driven by a control operation from the control room 4, and the building frame 1 is sequentially assembled.

【0008】また、この作業と並行して地上部において
は、前述の構築部材ユニット6が組立てられ、仮設屋根
架構3の上部に配置されたジブクレーンなどの搬送設備
7によって揚重され、建物躯体1の各階に据付けられる
ことで、躯体工事と同時に、内装仕上げも並行して行わ
れる。
In parallel with this operation, the above-mentioned building member unit 6 is assembled on the ground portion, and is lifted by a transfer facility 7 such as a jib crane arranged above the temporary roof frame 3, so that the building frame 1 is lifted. By installing it on each floor, the interior finishing will be done at the same time as the skeleton work.

【0009】[0009]

【発明が解決しようとする課題】しかしながら、この組
合せ方法では、構築部材ユニット6を地上のストックヤ
ード8で組立てることになり、かさばって搬送効率を低
下させ、かつ工事用の敷地の不足を生ずる欠点が生じ
た。
However, in this combination method, the construction member unit 6 is assembled in the stock yard 8 on the ground, which disadvantageously causes bulky transportation efficiency and shortage of construction site. Occurred.

【0010】本発明は、以上の課題を解決するためにな
されたものであって、構築部材ユニット等の資材を仮設
屋根架構内でストックまたは組立てることによって、工
事用敷地の不足を解消し、効率的な搬送を行えるように
した仮設屋根架構を利用した建物の内装構築方法を提供
するものである。
SUMMARY OF THE INVENTION The present invention has been made to solve the above-mentioned problems, and solves the problem of shortage of a construction site by stocking or assembling materials such as building member units in a temporary roof frame. It is an object of the present invention to provide a method for constructing the interior of a building using a temporary roof frame capable of performing a specific transport.

【0011】[0011]

【課題を解決するための手段】以上の目的を達成するた
め本発明方法は、建物躯体の構築とともに上昇し、該建
物躯体の上面を覆う仮設屋根架構の下部に作業床を設置
して内部に作業空間を形成し、地上の資材をこの空間に
搬送する搬送設備により作業床に取り込み、この作業床
上において、資材をストックし、または資材をユニット
化して構築部材ユニットとなし、仮設屋根架構内に設置
した架構内搬送設備により、ストックされている前記資
材および/または前記構築部材ユニットを作業空間の床
開口部を通して、施工中の建物躯体の構造上に吊り降ろ
し、所定位置に取付けることを特徴とする。
In order to achieve the above object, the method of the present invention raises with the construction of a building frame, and installs a work floor under a temporary roof frame that covers the upper surface of the building frame. A work space is formed, and materials on the ground are taken into the work floor by transport equipment that conveys the materials to this space.On this work floor, the materials are stocked, or the materials are unitized to form a building member unit, which is installed in the temporary roof frame The above-mentioned material and / or the building member unit that are stocked are suspended by the installed in-frame transport equipment on the structure of the building under construction through the floor opening of the working space, and are attached to predetermined positions. I do.

【0012】以上により、本発明方法では、地上のスト
ックヤードを使用しないため、搬送効率がよく、かつ工
事用の敷地の不足を解消できる。
As described above, according to the method of the present invention, since the stockyard on the ground is not used, the transportation efficiency is good and the shortage of the construction site can be solved.

【0013】[0013]

【発明の実施の形態】以下、本発明の好ましい実施の形
態につき、添付図面を参照して詳細に説明する。図1
は、本発明方法の全体的な概念図を示している。
Preferred embodiments of the present invention will be described below in detail with reference to the accompanying drawings. FIG.
Shows an overall conceptual diagram of the method of the present invention.

【0014】図において、構築中の建物躯体10の周囲
には仮設支柱12が配置され、建物躯体10に控え14
を介して支持される。仮設支柱12の頂部には油圧ジャ
ッキなどによるクライミング装置16を介して仮設屋根
架構18が昇降可能に配置され、建物躯体10の上面を
覆っている。
In the drawing, a temporary support 12 is arranged around a building body 10 under construction, and
Supported through. A temporary roof frame 18 is disposed at the top of the temporary support 12 via a climbing device 16 such as a hydraulic jack so as to be able to move up and down, and covers the upper surface of the building frame 10.

【0015】仮設屋根架構18は、建物躯体10の一階
分よりやや高く設定された天井高さ寸法であって、その
屋根上部には地上部に搬入される資材20の揚重用ジブ
クレーン22が配置されている。
The temporary roof frame 18 has a ceiling height slightly higher than the first floor of the building frame 10, and a jib crane 22 for lifting materials 20 to be carried into the ground is disposed above the roof. Have been.

【0016】また、架構18の内部の一部には作業床2
4が形成され、この床面を構築部材ユニット26の組立
ヤードおよび前記資材20のストックヤードとしてい
る。
The work floor 2 is partially provided inside the frame 18.
4 are formed, and this floor is used as an assembly yard of the building member unit 26 and a stock yard of the material 20.

【0017】さらに、架構18の天井面内側には、架構
内搬送設備すなわち資材搬送用ホイスト30が配置され
ているとともに、架構18の下部には、天井走行クレー
ンによって走行可能な複数の資材搬送取付用のホイスト
32が配置されており、それぞれ資材20および/また
は組立てられた構築部材ユニット26を建物躯体10の
各部に供給する。
Further, inside the ceiling surface of the frame 18, an in-frame transport facility, that is, a material transport hoist 30 is arranged, and a plurality of material transport mountings that can be moved by an overhead traveling crane are provided below the frame 18. A hoist 32 is provided for supplying the material 20 and / or the assembled building member unit 26 to each part of the building frame 10.

【0018】図2は以上の仮設屋根架構18内での構築
部材ユニット26の組立から各部への取付作業手順を示
すものである。図において、資材20は搬送設備22に
よって揚重され、架構18の上部一側部に開口された資
材受入れ用開口18aを通じて作業床24上に供給さ
れ、ここで前記資材20を活用した構築部材ユニット2
6が組立られる。
FIG. 2 shows the procedure for assembling the building member unit 26 in the temporary roof frame 18 and attaching it to each part. In the figure, a material 20 is lifted by a transport equipment 22 and supplied onto a work floor 24 through a material receiving opening 18a opened at one upper side of the frame 18, where a building member unit utilizing the material 20 is used. 2
6 is assembled.

【0019】組立てられた構築部材ユニット26は、ホ
イスト30により揚重され、床開口部24aを通じてそ
の下部の建物躯体10の各部に供給され、躯体の組立と
同時に内装材の組込みも行われることになる。
The assembled building member unit 26 is lifted by the hoist 30 and supplied to each part of the lower building frame 10 through the floor opening 24a, so that the assembling of the frame is performed simultaneously with the assembly of the frame. Become.

【0020】また、ユニット化およびストックが不要な
箇所であって、躯体構造工事のみ必要な箇所は、資材搬
送取付装置32により柱、梁などの資材20が吊り込ま
れ、順次建物躯体が構築される。
Further, at a place where unitization and stocking are unnecessary, and where only the skeleton structure construction is required, the materials 20 such as pillars and beams are suspended by the material transport mounting device 32, and the building skeleton is sequentially constructed. You.

【0021】なお、床開口部24aの大きさは限定され
ているため、ホイスト30は構築部材ユニット26をそ
の直下までしか吊りおろすことができないが、吊りおろ
した後、構築部材ユニット26を資材搬送取付用ホイス
ト32に移し替えて玉掛し、これに吊り込めば、建物躯
体10の各部に自由に移動させて、目的位置に吊りおろ
し、据付け作業を行うことができる。
Since the size of the floor opening 24a is limited, the hoist 30 can only lower the building member unit 26 to a position directly below the hoist 30. If it is transferred to the mounting hoist 32 and slung on it, it can be freely moved to each part of the building frame 10, lowered to the target position, and installed.

【0022】[0022]

【発明の効果】以上の説明により明らかなように、本発
明による仮設屋根架構を用いた構築方法によれば、揚重
した資材を架構内部で構築部材ユニットに組立てること
ができるため、地上部で組立作業を行った後揚重して各
部に据付ける場合に比べて、効率的な作業を行うことが
でき、工事用敷地の不足を解消できる。
As is apparent from the above description, according to the construction method using the temporary roof frame according to the present invention, the lifted materials can be assembled into the construction member unit inside the frame, and therefore, the above-mentioned method can be used in the above-ground portion. Compared to the case where the assembly work is performed and then lifted and installed in each part, more efficient work can be performed, and the shortage of the construction site can be solved.

【図面の簡単な説明】[Brief description of the drawings]

【図1】本発明方法の全体的な概念図である。FIG. 1 is an overall conceptual diagram of the method of the present invention.

【図2】同方法による組立・据付け手順の説明図であ
る。
FIG. 2 is an explanatory diagram of an assembling / installing procedure by the same method.

【図3】地上部で組付け揚重を行う場合における据付け
手順を示す説明図である。
FIG. 3 is an explanatory diagram showing an installation procedure in a case where assembling and lifting is performed on the ground portion.

【符号の説明】[Explanation of symbols]

10 建物躯体 16 クライミング装置 18 仮設屋根架構 18a 資材受入れ用開口部 20 資材 22 ジブクレーン(搬送設備) 24 作業床 24a 床開口部 26 構築部材ユニット 30 資材搬送用ホイスト 32 資材搬送取付用ホイスト Reference Signs List 10 Building frame 16 Climbing device 18 Temporary roof frame 18a Material receiving opening 20 Material 22 Jib crane (transport equipment) 24 Work floor 24a Floor opening 26 Construction member unit 30 Material transport hoist 32 Material transport mounting hoist

───────────────────────────────────────────────────── フロントページの続き (72)発明者 栗田 康平 東京都清瀬市下清戸4丁目640番地 株式 会社大林組技術研究所内 (72)発明者 浜田 耕史 東京都清瀬市下清戸4丁目640番地 株式 会社大林組技術研究所内 ──────────────────────────────────────────────────続 き Continuing from the front page (72) Inventor Kohei Kurita 4-640 Shimoseito, Kiyose-shi, Tokyo Inside the Obayashi-gumi Technical Research Institute Co., Ltd. (72) Inventor Koji Hamada 4-640 Shimoseito, Kiyose-shi, Tokyo, Japan Inside

Claims (1)

【特許請求の範囲】[Claims] 【請求項1】 建物躯体の構築とともに上昇し、該建物
躯体の上面を覆う仮設屋根架構の下部に作業床を設置し
て内部に作業空間を形成し、地上の資材をこの空間に搬
送する搬送設備により作業床に取り込み、この作業床上
において、資材をストックし、または資材をユニット化
して構築部材ユニットとなし、仮設屋根架構内に設置し
た架構内搬送設備により、ストックされている前記資材
および/または前記構築部材ユニットを作業空間の床開
口部を通して、施工中の建物躯体の構造上に吊り降ろ
し、所定位置に取付けることを特徴とする仮設屋根架構
を用いた建物の構築方法。
1. A work space that rises with the construction of a building frame, forms a work space inside by installing a work floor under a temporary roof frame that covers the upper surface of the building frame, and transports ground materials to this space. It is taken into the work floor by the equipment, and the material is stocked on this work floor, or the material is unitized to form a building member unit, and the material and / or stocked by the transport equipment in the frame installed in the temporary roof frame. Alternatively, a method of constructing a building using a temporary roof frame, wherein the building member unit is suspended on a structure of a building under construction through a floor opening of a work space and attached to a predetermined position.
JP10634198A 1998-04-16 1998-04-16 Constructing method of building using temporary roof frame Pending JPH11303403A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
JP10634198A JPH11303403A (en) 1998-04-16 1998-04-16 Constructing method of building using temporary roof frame

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
JP10634198A JPH11303403A (en) 1998-04-16 1998-04-16 Constructing method of building using temporary roof frame

Publications (1)

Publication Number Publication Date
JPH11303403A true JPH11303403A (en) 1999-11-02

Family

ID=14431144

Family Applications (1)

Application Number Title Priority Date Filing Date
JP10634198A Pending JPH11303403A (en) 1998-04-16 1998-04-16 Constructing method of building using temporary roof frame

Country Status (1)

Country Link
JP (1) JPH11303403A (en)

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP2017179834A (en) * 2016-03-30 2017-10-05 大成建設株式会社 Building Construction Method

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP2017179834A (en) * 2016-03-30 2017-10-05 大成建設株式会社 Building Construction Method

Similar Documents

Publication Publication Date Title
JP4651857B2 (en) Building demolition method
JP2736478B2 (en) How to build structures
JP6646220B2 (en) Construction method of suspended steel frame for suspended ceiling
JPH11303403A (en) Constructing method of building using temporary roof frame
JPH04257602A (en) Installation method of hanging type boiler
JPH04237764A (en) Method for constructing high-strorey building
JPH05133016A (en) Peripheral supporting self-rising type building engineering method
JPH10245994A (en) Temporary curing body
JPH08120936A (en) Method and device for constructing multistoried building
KR200200364Y1 (en) High building construction apparatus
JPH08184207A (en) Construction method for power plant using ceiling crane
JPH08326323A (en) Constructing device for multistoried building
JPH0447072A (en) Construction method for multistory building and its device
JPH05179815A (en) Construction method for temporary roof
JP2835880B2 (en) High-rise building frame construction method
JP2590671B2 (en) Construction method of steel frame using overhead crane frame
JPH06158731A (en) Platform for building construction
JPH04118438A (en) Method and apparatus for construction of building
JPH06185209A (en) Method for constructing facing in roof push-up construction method
JPH04231530A (en) Method for constructing main frames of high-rise building
JPH08312147A (en) Method of lifting roof surface section
JPH09136788A (en) Hoist and transfer device and method thereof
JPH0317356A (en) Construction of multi-story building
JPH08326321A (en) Construction of multistoried building
JPH10331432A (en) Temporary cured body and execution method for building using the same