JPH11286956A - Working device of construction vehicle - Google Patents

Working device of construction vehicle

Info

Publication number
JPH11286956A
JPH11286956A JP8875798A JP8875798A JPH11286956A JP H11286956 A JPH11286956 A JP H11286956A JP 8875798 A JP8875798 A JP 8875798A JP 8875798 A JP8875798 A JP 8875798A JP H11286956 A JPH11286956 A JP H11286956A
Authority
JP
Japan
Prior art keywords
stopper
bucket
boom
receiving portion
tilt
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
JP8875798A
Other languages
Japanese (ja)
Inventor
Keiju Akutsu
桂樹 阿久津
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Furukawa Co Ltd
Original Assignee
Furukawa Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Furukawa Co Ltd filed Critical Furukawa Co Ltd
Priority to JP8875798A priority Critical patent/JPH11286956A/en
Publication of JPH11286956A publication Critical patent/JPH11286956A/en
Pending legal-status Critical Current

Links

Landscapes

  • Shovels (AREA)

Abstract

PROBLEM TO BE SOLVED: To increase the distance from the connecting center between a boom and a bucket to a stopper receiving part and to reduce the load received when the stopper abuts the stopper receiving part. SOLUTION: This device is provided with a boom 1, a bucket 2 tiltably mounted on the tip of the boom 1, and a tilt mechanism consisting of a tilt link 7, intermediate link 4 and tilt cylinder 10 for longitudinally tilting the bucket 2. Either one of a stopper 13 for fixing the bucket 2 in a backward tilted position or a stopper receiving part 14 is provided on the intermediate link 4.

Description

【発明の詳細な説明】DETAILED DESCRIPTION OF THE INVENTION

【0001】[0001]

【発明の属する技術分野】本発明は、ホイールローダ等
の建設車両に設けられる作業装置に関する。
The present invention relates to a working device provided in a construction vehicle such as a wheel loader.

【0002】[0002]

【従来の技術】ホイールローダ等の建設車両には、ブー
ムの先端部に作業具としてバケットやその他の各種作業
用アタッチメントを取付けた作業装置が装備されてい
る。
2. Description of the Related Art A construction vehicle such as a wheel loader is equipped with a working device in which a bucket and other various work attachments are attached as working tools at the tip of a boom.

【0003】例えば、図4に示すように、ブーム1の先
端部に作業具としてバケット2を取付けた作業装置で
は、ブーム1は建設車両の台車11の前部にその基端部
が枢設され、台車11とブーム1との間に取付けたリフ
トシリンダ12で昇降可能になっており、ブーム1の先
端部に取付ピン3で取付けられているバケット2は、チ
ルトリンク7と中間リンク4とチルトシリンダ10とか
らなるチルト機構によって前後傾動可能になっている。
For example, as shown in FIG. 4, in a working device in which a bucket 2 is attached as a working tool to a distal end portion of a boom 1, a base end of the boom 1 is pivotally provided at a front portion of a bogie 11 of a construction vehicle. The bucket 2, which can be moved up and down by a lift cylinder 12 attached between the bogie 11 and the boom 1, is attached to the tip end of the boom 1 by an attachment pin 3, It can be tilted back and forth by a tilt mechanism including the cylinder 10.

【0004】ここで、チルト機構は、中間リンク4がブ
ーム1の中間部に支持ピン5で回動自在に支持されてお
り、この中間リンク4の下端部にチルトリンク7の後端
部が連結ピン8で連結され、チルトリンク7の先端部が
取付ピン6でバケット2に取付けられている。また、中
間リンク4の上端部とブーム1との間にチルトシリンダ
10が取付けられている。
In the tilt mechanism, an intermediate link 4 is rotatably supported by a support pin 5 at an intermediate portion of the boom 1, and a rear end of the tilt link 7 is connected to a lower end of the intermediate link 4. The tip of the tilt link 7 is attached to the bucket 2 by an attachment pin 6. Further, a tilt cylinder 10 is mounted between the upper end of the intermediate link 4 and the boom 1.

【0005】このチルト機構で、チルトシリンダ10を
短縮させると、中間リンク4は支持ピン5を中心として
図上時計方向に回動し、チルトリンク7を介してバケッ
ト2を取付ピン3を中心として反時計方向に回動させる
ので、バケット2は前傾する。また、チルトシリンダ1
0を伸長させると、中間リンク4は支持ピン5を中心と
して図上反時計方向に回動し、チルトリンク7を介して
バケット2を取付ピン3を中心として時計方向に回動さ
せるので、バケット2は後傾する。
When the tilt cylinder 10 is shortened by the tilt mechanism, the intermediate link 4 rotates clockwise about the support pin 5 and the bucket 2 is rotated about the mounting pin 3 via the tilt link 7. Since the bucket 2 is rotated counterclockwise, the bucket 2 tilts forward. Also, tilt cylinder 1
When 0 is extended, the intermediate link 4 rotates counterclockwise about the support pin 5 in the figure, and rotates the bucket 2 clockwise about the mounting pin 3 via the tilt link 7. 2 leans backward.

【0006】この作業装置を用いて土砂等の荷の積込作
業を行う場合には、先ずバケット2を前傾させて建設車
両を荷に向けて前進させ、次にバケット2を後傾させて
荷をバケット2に掬い込む。それからブーム1を上昇さ
せバケット2を後傾した状態に保持して建設車両を所定
位置まで走行させる。
When loading work such as earth and sand using this working device, the bucket 2 is first tilted forward to move the construction vehicle toward the load, and then the bucket 2 is tilted rearward. Scoop the load into the bucket 2. Then, the boom 1 is raised and the bucket 2 is held in the backwardly inclined state, and the construction vehicle is caused to travel to a predetermined position.

【0007】このときバケット2が揺動しないように固
定するため、バケット2の背部にはストッパ13、ブー
ム1にはバケット2を所定位置まで後傾させたときスト
ッパ13が当接する位置にストッパ受け部14がそれぞ
れ設けられている。
At this time, in order to fix the bucket 2 so as not to swing, a stopper 13 is provided at the back of the bucket 2 and a stopper receiving member is provided at a position where the stopper 13 comes into contact with the boom 1 when the bucket 2 is tilted backward to a predetermined position. Parts 14 are provided respectively.

【0008】なお、ストッパ13をブーム1側に、スト
ッパ受け部14をバケット2側に設けることもできる。
The stopper 13 can be provided on the boom 1 side and the stopper receiving portion 14 can be provided on the bucket 2 side.

【0009】[0009]

【発明が解決しようとする課題】バケット2が後傾して
ストッパ13とストッパ受け部14とが当接していると
きに受ける荷重が大きいと、ストッパ13とストッパ受
け部14とは強度を大にするため鋼材等を用いた頑丈な
ものにしなければならなくなる。
If the load received when the bucket 2 is tilted rearward and the stopper 13 and the stopper receiving portion 14 are in contact with each other is large, the strength of the stopper 13 and the stopper receiving portion 14 is increased. Therefore, it is necessary to use a strong steel material or the like.

【0010】ストッパ13とストッパ受け部14とが当
接しているときに受ける荷重を軽くするためには、ブー
ム1とバケット2との連結中心である取付ピン3の中心
点Oについてのバケット2のモーメントを考えると、ス
トッパ13とストッパ受け部14とは、取付ピン3の中
心点Oからできるだけ離れた位置に設けることが望まし
い。
In order to reduce the load received when the stopper 13 and the stopper receiving portion 14 are in contact with each other, the bucket 2 is moved with respect to the center point O of the mounting pin 3 which is the connection center between the boom 1 and the bucket 2. Considering the moment, the stopper 13 and the stopper receiving portion 14 are desirably provided at positions as far as possible from the center point O of the mounting pin 3.

【0011】しかし、従来の作業装置では、ストッパ受
け部14はブーム1に設けられるので、取付位置の範囲
が限定され、取付ピン3の中心点Oからストッパ13及
びストッパ受け部14までの距離L2 を大きくすること
ができず、従って、ストッパ13とストッパ受け部14
が当接しているときに受ける荷重を大幅に低減すること
は不可能である。
However, in the conventional working apparatus, since the stopper receiving portion 14 is provided on the boom 1, the range of the mounting position is limited, and the distance L from the center point O of the mounting pin 3 to the stopper 13 and the stopper receiving portion 14 is limited. 2 cannot be increased, and therefore the stopper 13 and the stopper receiving portion 14
It is not possible to significantly reduce the load received when abuts against.

【0012】また、ストッパ13とストッパ受け部14
とが当接したとき受ける衝撃を吸収するには、ストッパ
13あるいはストッパ受け部14の材質を弾性体にする
ことが望ましいが、ストッパ13とストッパ受け部14
の受ける荷重が大であるので弾性体では強度が不足し、
耐久性が得られない。
The stopper 13 and the stopper receiving portion 14
In order to absorb the shock received when the stopper 13 comes into contact with the stopper 13, it is preferable that the material of the stopper 13 or the stopper receiving portion 14 is an elastic body.
The elastic body has insufficient strength because the load received is large,
Durability cannot be obtained.

【0013】この問題は、バケット2に代えて他の作業
具を取付けた場合も同様に生ずるものである。本発明
は、建設車両の作業装置における上記問題を解決するも
のであって、ブームと作業具との連結中心からストッパ
及びストッパ受け部までの距離を大きくして、ストッパ
とストッパ受け部とが当接しているときに受ける荷重を
大幅に低減することができ、ストッパ及びストッパ受け
部を弾性体として衝撃を吸収することが可能で、運転者
の疲労を軽減でき、耐久性も向上させることのできる建
設車両の作業装置を提供することを目的とする。
This problem also occurs when another work tool is attached instead of the bucket 2. The present invention solves the above-described problem in a working device of a construction vehicle, and increases the distance from the center of connection between a boom and a working tool to a stopper and a stopper receiving portion so that the stopper and the stopper receiving portion contact each other. The load received during contact can be greatly reduced, the impact can be absorbed by using the stopper and the stopper receiving portion as elastic bodies, the driver's fatigue can be reduced, and the durability can be improved. An object of the present invention is to provide a working device for a construction vehicle.

【0014】[0014]

【課題を解決するための手段】この発明の建設車両の作
業装置は、ブームと、ブームの先端部に傾動可能に取付
けられた作業具と、作業具を前後傾動させるチルトリン
クと中間リンクとチルトシリンダとからなるチルト機構
と、を備えた建設車両の作業装置において、作業具を後
傾位置で固定するためのストッパとストッパ受け部のい
ずれか一方を中間リンクに設けることにより上記課題を
解決している。
SUMMARY OF THE INVENTION A working device for a construction vehicle according to the present invention includes a boom, a work implement tiltably attached to a tip of the boom, a tilt link for tilting the work implement back and forth, an intermediate link, and a tilt. In a working device of a construction vehicle having a tilt mechanism including a cylinder, the above-mentioned problem is solved by providing one of a stopper and a stopper receiving portion for fixing a working tool at a backward inclined position at an intermediate link. ing.

【0015】この建設車両の作業装置では、ストッパと
ストッパ受け部のいずれか一方が中間リンクに設けられ
るので、ブームと作業具との連結中心からストッパ及び
ストッパ受け部までの距離が大きくなり、ストッパとス
トッパ受け部とが当接しているときに受ける荷重が大幅
に低減される。
In this construction vehicle working device, one of the stopper and the stopper receiving portion is provided on the intermediate link, so that the distance from the connection center between the boom and the working tool to the stopper and the stopper receiving portion increases, and The load received when the and stopper receiving portions are in contact with each other is greatly reduced.

【0016】ストッパ及びストッパ受け部を、従来のよ
うに強度の大きい頑丈なものとする必要はない。従っ
て、ストッパとストッパ受け部のいずれか一方、もしく
は双方を弾性体とし、ストッパとストッパ受け部とが当
接したときの衝撃を吸収して運転者の疲労を軽減させる
ことができる。ストッパとストッパ受け部の耐久性も向
上する。
The stopper and the stopper receiving portion do not need to be made strong and strong as in the prior art. Therefore, one or both of the stopper and the stopper receiving portion are made of an elastic body, and the impact when the stopper and the stopper receiving portion come into contact with each other can be absorbed to reduce driver fatigue. The durability of the stopper and the stopper receiving portion is also improved.

【0017】弾性体のストッパ又はストッパ受け部を弾
頭形にすると、ストッパとストッパ受け部とが当接する
ときの負荷は、最初小さくその後徐々に大きくなるので
瞬間的に衝撃を受けることがなく、スムーズに衝撃を吸
収でき寿命をより長くすることができる。
When the stopper or the stopper receiving portion of the elastic body has a warhead shape, the load at the time when the stopper and the stopper receiving portion come into contact with each other is small at first and then gradually increased, so that the impact is not instantaneously received, so that the impact is smooth. Impact can be absorbed and the life can be prolonged.

【0018】[0018]

【発明の実施の形態】図1は本発明の実施の一形態を示
す建設車両の作業装置の側面図、図2はホイールローダ
の側面図、図3は弾性体を弾頭形としたストッパの側面
図である。
DESCRIPTION OF THE PREFERRED EMBODIMENTS FIG. 1 is a side view of a working device of a construction vehicle showing one embodiment of the present invention, FIG. 2 is a side view of a wheel loader, and FIG. 3 is a side view of a stopper having an elastic body as a warhead. FIG.

【0019】建設車両であるホイールローダ16には、
その台車11の前部に、ブーム1の先端部に作業具とし
てバケット2を取付けた作業装置17が装備されてい
る。この作業装置17では、ブーム1はホイールローダ
16の台車11の前部にその基端部が枢設され、台車1
1とブーム1との間に取付けたリフトシリンダ12で昇
降可能になっている。ブーム1の先端部に取付ピン3で
取付けられているバケット2は、チルトリンク7と中間
リンク4とチルトシリンダ10とからなるチルト機構に
よって前後傾動可能になっている。
The wheel loader 16, which is a construction vehicle, has
A work device 17 having a bucket 2 as a work tool attached to a front end of the boom 1 is provided at a front portion of the cart 11. In this working device 17, the base of the boom 1 is pivotally mounted at the front of the truck 11 of the wheel loader 16,
The lift cylinder 12 can be moved up and down between the boom 1 and the boom 1. The bucket 2 attached to the tip of the boom 1 by the attachment pin 3 can be tilted back and forth by a tilt mechanism including a tilt link 7, an intermediate link 4, and a tilt cylinder 10.

【0020】ここで、チルト機構は、中間リンク4がブ
ーム1の中間部に支持ピン5で回動自在に支持されてお
り、この中間リンク4の下端部にチルトリンク7の後端
部が連結ピン8で連結され、チルトリンク7の先端部が
取付ピン6でバケット2に取付けられている。また、中
間リンク4の上端部とブーム1との間にチルトシリンダ
10が取付けられている。
In the tilt mechanism, the intermediate link 4 is rotatably supported by a support pin 5 at an intermediate portion of the boom 1 and a rear end of the tilt link 7 is connected to a lower end of the intermediate link 4. The tip of the tilt link 7 is attached to the bucket 2 by an attachment pin 6. Further, a tilt cylinder 10 is mounted between the upper end of the intermediate link 4 and the boom 1.

【0021】このチルト機構で、図1に示す状態からチ
ルトシリンダ10を短縮させると、中間リンク4は支持
ピン5を中心として図上時計方向に回動し、チルトリン
ク7を介してバケット2を取付ピン3を中心として反時
計方向に回動させるので、バケット2は前傾して図2に
示す状態となる。
When the tilt cylinder 10 is shortened from the state shown in FIG. 1 by this tilt mechanism, the intermediate link 4 rotates clockwise about the support pin 5 in the figure, and the bucket 2 is moved via the tilt link 7. Since the bucket 2 is rotated counterclockwise about the mounting pin 3, the bucket 2 is inclined forward to the state shown in FIG. 2.

【0022】また、図2の状態からチルトシリンダ10
を伸長させると、中間リンク4は支持ピン5を中心とし
て図上反時計方向に回動し、チルトリンク7を介してバ
ケット2を取付ピン3を中心として時計方向に回動させ
るので、バケット2は後傾して図1の状態となる。
The tilt cylinder 10 is moved from the state shown in FIG.
Is extended, the intermediate link 4 rotates counterclockwise about the support pin 5 in the figure, and rotates the bucket 2 clockwise about the mounting pin 3 via the tilt link 7. Tilts backward to the state shown in FIG.

【0023】この作業装置17を用いて土砂等の荷の積
込作業を行う場合には、先ずバケット2を前傾させてホ
イールローダ16を荷に向けて前進させ、次にバケット
2を後傾させて荷をバケット2に掬い込む。それからブ
ーム1を上昇させバケット2を後傾した状態に保持して
ホイールローダを所定位置まで走行させる。
When loading work such as earth and sand using the working device 17, the bucket 2 is first tilted forward to move the wheel loader 16 toward the load, and then the bucket 2 is tilted rearward. Then, the load is scooped into the bucket 2. Then, the boom 1 is raised, and the bucket 2 is held in the backwardly inclined state, and the wheel loader is driven to a predetermined position.

【0024】このときバケット2が揺動しないように固
定するため、バケット2の背部上端にストッパ13、中
間リンク4の上部にはバケット2を所定位置まで後傾さ
せたときストッパ13が当接する位置にストッパ受け部
14がそれぞれ設けられている。
At this time, in order to fix the bucket 2 so as not to swing, a stopper 13 is provided at the upper end of the back of the bucket 2 and a position at which the stopper 13 contacts the upper part of the intermediate link 4 when the bucket 2 is tilted backward to a predetermined position. Are provided with stopper stoppers 14, respectively.

【0025】なお、ストッパ13を中間リンク4側に、
ストッパ受け部14をバケット2側に設けることもでき
る。このように、ストッパ受け部14を中間リンク4に
設けているので、ブーム1とバケット2との連結中心で
ある取付ピン3の中心点Oからストッパ13及びストッ
パ受け部14までの距離L1 は従来のものに較べて大き
くなっている。
The stopper 13 is located on the intermediate link 4 side.
The stopper receiving portion 14 may be provided on the bucket 2 side. As described above, since the stopper receiving portion 14 is provided on the intermediate link 4, the distance L 1 from the center point O of the mounting pin 3 which is the connection center between the boom 1 and the bucket 2 to the stopper 13 and the stopper receiving portion 14 is It is larger than the conventional one.

【0026】このため、ストッパ13とストッパ受け部
14とが当接しているときに受ける荷重が大幅に低減さ
れる。ストッパ13及びストッパ受け部14を、従来の
ように鋼材等を用いた強度の大きい頑丈なものとする必
要はない。
Therefore, the load received when the stopper 13 and the stopper receiving portion 14 are in contact with each other is greatly reduced. It is not necessary that the stopper 13 and the stopper receiving portion 14 be made of a steel material or the like and have high strength and rigidity as in the related art.

【0027】従って、ストッパ13とストッパ受け部1
4のいずれか一方、もしくは双方を弾性体とし、ストッ
パ13とストッパ受け部14とが当接したときの衝撃を
吸収して運転者の疲労を軽減させることができる。スト
ッパ13とストッパ受け部14の耐久性も向上する。
Therefore, the stopper 13 and the stopper receiving portion 1
Either one or both of them can be made of an elastic body, and the impact when the stopper 13 and the stopper receiving portion 14 come into contact can be absorbed to reduce the driver's fatigue. The durability of the stopper 13 and the stopper receiving portion 14 is also improved.

【0028】図3は、弾頭形の弾性体Eを取付具15に
固着して、バケット2の背面に取付けるようにしたスト
ッパ13の例を示している。このストッパ13は、スト
ッパ受け部14と当接するときの負荷が、最初小さくそ
の後徐々に大きくなるので瞬間的に衝撃を受けることが
なく、スムーズに衝撃を吸収でき運転者の疲労を大幅に
軽減できる。ストッパ13とストッパ受け部14の寿命
もより長くすることができる。
FIG. 3 shows an example of a stopper 13 in which a warhead-shaped elastic body E is fixed to a fixture 15 and attached to the back of the bucket 2. Since the load at the time of contact with the stopper receiving portion 14 is initially small and then gradually increased, the stopper 13 does not receive an instantaneous impact, so that the impact can be absorbed smoothly and the fatigue of the driver can be greatly reduced. . The service life of the stopper 13 and the stopper receiving portion 14 can be made longer.

【0029】[0029]

【発明の効果】以上説明したように、本発明の建設車両
の作業装置は、ブームと作業具との連結中心からストッ
パ及びストッパ受け部までの距離を大きくして、ストッ
パとストッパ受け部とが当接しているときに受ける荷重
を大幅に低減するので、ストッパとストッパ受け部はさ
ほど頑丈にする必要はない。従って、材質を弾性体とす
ることで、衝撃を吸収することが可能で、運転者の疲労
を軽減し、耐久性を向上させることができる。
As described above, according to the working device for a construction vehicle of the present invention, the distance from the connection center between the boom and the working tool to the stopper and the stopper receiving portion is increased, so that the stopper and the stopper receiving portion are separated from each other. The stopper and the stopper receiving part do not need to be very strong because the load received during the contact is greatly reduced. Therefore, by using an elastic material, it is possible to absorb impact, reduce driver fatigue, and improve durability.

【0030】弾性体のストッパ又はストッパ受け部を弾
頭形にすると、ストッパとストッパ受け部とが当接する
ときの負荷は、最初小さくその後徐々に大きくなるので
瞬間的に衝撃を受けることがなく、スムーズに衝撃を吸
収でき寿命をより長くすることができる。
When the stopper or the stopper receiving portion of the elastic body has a warhead shape, the load when the stopper and the stopper receiving portion come into contact with each other is small at first and then gradually increased, so that there is no momentary impact, so that the impact is smooth. Impact can be absorbed and the life can be prolonged.

【図面の簡単な説明】[Brief description of the drawings]

【図1】本発明の実施の一形態を示す建設車両の作業装
置の側面図である。
FIG. 1 is a side view of a working device of a construction vehicle according to an embodiment of the present invention.

【図2】ホイールローダの側面図である。FIG. 2 is a side view of the wheel loader.

【図3】弾性体を弾頭形としたストッパの側面図であ
る。
FIG. 3 is a side view of a stopper in which an elastic body has a warhead shape.

【図4】従来の建設車両の作業装置の側面図である。FIG. 4 is a side view of a working device of a conventional construction vehicle.

【符号の説明】[Explanation of symbols]

1 ブーム 2 バケット 3 取付ピン 4 中間リンク 5 支持ピン 6 取付ピン 7 チルトリンク 8 連結ピン 10 チルトシリンダ 11 台車 12 リフトシリンダ 13 ストッパ 14 ストッパ受け部 15 取付具 16 ホイールローダ 17 作業装置 E 弾性体 L1 ブームとバケットとの連結中心からストッパまで
の距離 O 中心点
DESCRIPTION OF SYMBOLS 1 Boom 2 Bucket 3 Mounting pin 4 Intermediate link 5 Support pin 6 Mounting pin 7 Tilt link 8 Connecting pin 10 Tilt cylinder 11 Bogie 12 Lift cylinder 13 Stopper 14 Stopper receiving part 15 Fixture 16 Wheel loader 17 Working device E elastic body L 1 Distance from center of connection between boom and bucket to stopper O Center point

Claims (3)

【特許請求の範囲】[Claims] 【請求項1】 ブームと、ブームの先端部に傾動可能に
取付けられた作業具と、作業具を前後傾動させるチルト
リンクと中間リンクとチルトシリンダとからなるチルト
機構と、を備えた建設車両の作業装置であって、 作業具を後傾位置で固定するためのストッパとストッパ
受け部のいずれか一方を中間リンクに設けたことを特徴
とする建設車両の作業装置。
1. A construction vehicle comprising: a boom; a work implement tiltably attached to a tip end of the boom; and a tilt mechanism including a tilt link for tilting the work implement back and forth, an intermediate link, and a tilt cylinder. A working device for a construction vehicle, wherein one of a stopper and a stopper receiving portion for fixing a working tool at a backward inclined position is provided on an intermediate link.
【請求項2】 ストッパとストッパ受け部のいずれか一
方、もしくは双方が弾性体であることを特徴とする請求
項1記載の建設車両の作業装置。
2. The working device for a construction vehicle according to claim 1, wherein one or both of the stopper and the stopper receiving portion is an elastic body.
【請求項3】 弾性体のストッパ又はストッパ受け部
が、弾頭形であることを特徴とする請求項2記載の建設
車両の作業装置。
3. The working device for a construction vehicle according to claim 2, wherein the stopper or the stopper receiving portion of the elastic body has a warhead shape.
JP8875798A 1998-04-01 1998-04-01 Working device of construction vehicle Pending JPH11286956A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
JP8875798A JPH11286956A (en) 1998-04-01 1998-04-01 Working device of construction vehicle

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
JP8875798A JPH11286956A (en) 1998-04-01 1998-04-01 Working device of construction vehicle

Publications (1)

Publication Number Publication Date
JPH11286956A true JPH11286956A (en) 1999-10-19

Family

ID=13951767

Family Applications (1)

Application Number Title Priority Date Filing Date
JP8875798A Pending JPH11286956A (en) 1998-04-01 1998-04-01 Working device of construction vehicle

Country Status (1)

Country Link
JP (1) JPH11286956A (en)

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
WO2005113902A1 (en) * 2004-05-21 2005-12-01 Yanmar Co., Ltd. Loading apparatus
JP5973090B2 (en) * 2015-07-15 2016-08-23 株式会社小松製作所 Bucket and work vehicle equipped with the same

Cited By (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
WO2005113902A1 (en) * 2004-05-21 2005-12-01 Yanmar Co., Ltd. Loading apparatus
US7510364B2 (en) 2004-05-21 2009-03-31 Yanmar Co., Ltd. Loading apparatus
JP5973090B2 (en) * 2015-07-15 2016-08-23 株式会社小松製作所 Bucket and work vehicle equipped with the same
US9719229B2 (en) 2015-07-15 2017-08-01 Komatsu Ltd. Bucket and working vehicle provided with the same

Similar Documents

Publication Publication Date Title
US4393607A (en) Hydraulic excavator
US4768917A (en) Loader boom mechanism
US7013983B2 (en) Blade mounting structure of bulldozer
EP1775389A1 (en) Loading apparatus
WO2002027107A1 (en) Vertical lift type arm device
KR100465184B1 (en) Backhoe unit detachably attached to a tractor
JPH11286956A (en) Working device of construction vehicle
JP2003184122A (en) Loading vehicle
KR20220126296A (en) working machine
JP2007146547A (en) Bucket of wheel loader
US7083002B2 (en) Blade mounting structure of bulldozer
JPH0729116Y2 (en) Excavator loader work machine
JP2001020310A (en) Boom device
JP4324069B2 (en) Construction work machine
JPH11140900A (en) Quadruple link mechanism of working vehicle
JP2001348904A (en) Dozer device for working machine
JPS623013B2 (en)
JP4081186B2 (en) Ultra-small turning machine
JPH0211486Y2 (en)
JP3718672B2 (en) Ultra-small turning machine
JPS6261738B2 (en)
JP3737997B2 (en) Work machine
JPS6237182B2 (en)
JP4740989B2 (en) Dozer equipment
JPS6049736B2 (en) Earthmoving vehicle equipped with a torsion bar that reduces the load acting on the tilt link

Legal Events

Date Code Title Description
A621 Written request for application examination

Free format text: JAPANESE INTERMEDIATE CODE: A621

Effective date: 20050204

A521 Written amendment

Effective date: 20051005

Free format text: JAPANESE INTERMEDIATE CODE: A821

A711 Notification of change in applicant

Free format text: JAPANESE INTERMEDIATE CODE: A711

Effective date: 20051005

A977 Report on retrieval

Free format text: JAPANESE INTERMEDIATE CODE: A971007

Effective date: 20070126

A131 Notification of reasons for refusal

Free format text: JAPANESE INTERMEDIATE CODE: A131

Effective date: 20070206

A02 Decision of refusal

Effective date: 20070612

Free format text: JAPANESE INTERMEDIATE CODE: A02