JPH1096211A - Method for removing bridge - Google Patents

Method for removing bridge

Info

Publication number
JPH1096211A
JPH1096211A JP25052696A JP25052696A JPH1096211A JP H1096211 A JPH1096211 A JP H1096211A JP 25052696 A JP25052696 A JP 25052696A JP 25052696 A JP25052696 A JP 25052696A JP H1096211 A JPH1096211 A JP H1096211A
Authority
JP
Japan
Prior art keywords
bridge
girder
bridge girder
barge
bridge pier
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
JP25052696A
Other languages
Japanese (ja)
Inventor
Tatsumasa Takaku
達將 高久
Hiroshi Sunahara
弘 砂原
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
JFE Engineering Corp
Original Assignee
NKK Corp
Nippon Kokan Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by NKK Corp, Nippon Kokan Ltd filed Critical NKK Corp
Priority to JP25052696A priority Critical patent/JPH1096211A/en
Publication of JPH1096211A publication Critical patent/JPH1096211A/en
Pending legal-status Critical Current

Links

Landscapes

  • Bridges Or Land Bridges (AREA)

Abstract

PROBLEM TO BE SOLVED: To conduct safely promptly the removal work of a large bridge pier crossed over a water channel such as river. SOLUTION: The removal method of a bridge is that both the ends of a bridge pier 3 are cut in a state being supported tentatively, and the bridge pier 3 is lifted by pontoons with a pair of lifting mechanisms arranged within the bridge pier and then moved in the direction of a land side bridge pier 4, and after the bridge pier 3 is mounted on the land side bridge pier 4, the pontoons 14 situated at the tip end of the bridge pier 3 are withdrawn, and the bridge pier 3 is moved onto the land side bridge pier 4 by the pontoon 14a situated at the rear end of the bridge pier 3. Also, one and half span bridge piers 3, 4 are removed by the same method.

Description

【発明の詳細な説明】DETAILED DESCRIPTION OF THE INVENTION

【0001】[0001]

【発明の属する技術分野】本発明は、河川等に架設され
ている橋梁の撤去方法に関する。
The present invention relates to a method for removing a bridge installed on a river or the like.

【0002】[0002]

【従来の技術】河川等の水路に架設されている橋梁は、
道路事情または老朽化のため、撤去して新規橋梁に架設
替えする需要が増大している。
2. Description of the Related Art Bridges installed in waterways such as rivers are:
Due to road conditions or aging, the demand for removing and replacing with new bridges is increasing.

【0003】既設橋梁の撤去方法の従来技術として、
「道路構造物の解体技術に関する調査研究報告書」
((財)道路保全技術センター道路構造物保全協会解体
部会)によれば、図16、図17に示す方法が知られて
いる。
As a conventional technique for removing an existing bridge,
"Survey and Research Report on Road Structure Demolition Technology"
According to the Road Conservation Technology Center Road Structure Conservation Association Dismantling Subcommittee, the methods shown in FIGS. 16 and 17 are known.

【0004】図16は、従来技術における橋梁の撤去方
法を示した側面図で、橋桁20上の床版コンクリート2
1を除去し橋軸方向で分割した主桁22を、橋体上のク
ローラクレーン23で吊り上げ、トラック24に積込み
解体場所へ撤去する方法(以下、従来技術1という。)
である。
FIG. 16 is a side view showing a method of removing a bridge according to the prior art.
1 is removed and the main girder 22 divided in the bridge axis direction is lifted by a crawler crane 23 on the bridge body, loaded on a truck 24 and removed to a dismantling place (hereinafter referred to as prior art 1).
It is.

【0005】尚、P1 、P2 、P3 、P4 は橋脚であ
り、6は水路面、A2 は橋台である。また、図17は、
他の従来技術における橋梁の撤去方法を示した側面図
で、ゲルバー桁30上の床版コンクリートを除去し橋軸
方向で分割した主桁31を、橋台A1 ,A2 側はトラッ
ククレーン32で撤去し、水路面6側の主桁31は、桁
受け33が設けられた台船34を主桁31の下部に位置
させ、満潮を利用して主桁31を持ち上げ、撤去する方
法(以下、従来技術2という。)である。
Incidentally, P 1 , P 2 , P 3 and P 4 are piers, 6 is a waterway surface, and A 2 is an abutment. Also, FIG.
In side view showing a removing method of the bridges in the other prior art, a main girder 31 divided by Hashijiku direction to remove the slab concrete on Gelber digits 30, abutments A 1, A 2 side in truck cranes 32 The main girder 31 on the waterway surface 6 side is removed by positioning a barge 34 provided with a girder support 33 below the main girder 31, lifting the main girder 31 by using high tide, and removing the main girder 31 (hereinafter, referred to as a method) Conventional technology 2).

【0006】[0006]

【発明が解決しようとする課題】しかしながら、前記従
来技術1は、クローラクレーンを用いる方法であるか
ら、吊られる主桁は35トン程度が限度となり、橋梁が
比較的小型であるか、または、軽量化のため床版コンク
リートを除去した橋桁を橋軸方向に分割した主桁とする
必要があり、作業効率が悪いという問題点がある。
However, since the prior art 1 is a method using a crawler crane, the main girder to be suspended is limited to about 35 tons, and the bridge is relatively small or lightweight. For this purpose, the bridge girder from which the slab concrete has been removed must be used as the main girder divided in the bridge axis direction, and there is a problem that work efficiency is poor.

【0007】また、前記従来技術2は、台船を用いるも
のの満潮時を利用して主桁を持ち上げ、撤去する方法で
あるので、撤去作業に長時間を要するという問題点があ
り、また、長時間の作業は、他の通航船の航行を阻害す
るという問題点がある。
Further, the prior art 2 uses a barge to lift and remove the main girder at high tide, so that the removal operation requires a long time. There is a problem that time work hinders the navigation of other passing vessels.

【0008】また、前記従来技術以外の想定技術とし
て、橋梁の撤去に大型のフローティングクレーンを使用
すれば一挙に解決できるが、通常、河川等の水路には複
数の橋が架設されており、前記大型のフローティングク
レーンは、他の既設橋梁の下部の通航が不可能であり、
使用できない制約がある。
[0008] As a supposed technology other than the conventional technology, a large floating crane can be used to remove a bridge, which can be solved at once. However, usually, a plurality of bridges are installed in waterways such as rivers. Large floating cranes cannot pass under other existing bridges,
Some restrictions cannot be used.

【0009】本発明は、河川等の水路に架設された橋桁
の撤去作業を、安全かつ迅速に行うことを目的とするも
のである。
An object of the present invention is to safely and promptly remove a bridge girder installed on a waterway such as a river.

【0010】[0010]

【課題を解決するための手段】前述の課題を解決する第
一の手段は、橋桁の両端を仮支持した状態で切断すると
ともに、該橋桁を橋脚内に配置された対の吊り上げ機構
付台船で持ち上げて陸側橋桁方向へ移動させ、前記橋桁
が陸側橋桁上に載置されたら、橋桁の先端に位置する台
船を撤去し、橋桁の後端部に位置する台船で該橋桁を前
記陸側橋桁上へ移動することを特徴とする橋梁の撤去方
法である。
A first means for solving the above-mentioned problems is to cut the bridge girder while temporarily supporting both ends thereof and to connect the bridge girder to a pair of barges with a lifting mechanism arranged in a pier. And move it in the direction of the land side bridge girder.When the bridge girder is placed on the land side bridge girder, remove the barge located at the tip of the bridge girder and replace the bridge girder with the barge located at the rear end of the bridge girder. A method for removing a bridge, wherein the bridge is moved on the land-side bridge girder.

【0011】前記の第一の手段によれば、橋桁は陸側橋
桁上を利用して陸地へ移動し解体されるので、解体場所
への台船の移動がないので、他船の通航を阻害すること
無く橋桁が撤去できる。
According to the first means, since the bridge girder moves to the land using the land bridge girder and is dismantled, there is no movement of the barge to the dismantling place, so that traffic of other ships is hindered. The bridge girder can be removed without having to do it.

【0012】前述の課題を解決する第二の手段は、橋桁
の両端を仮支持した状態で1スパン半の長さに切断する
とともに、該橋桁を橋脚を挟んで配置された対の吊り上
げ機構付台船で持ち上げて陸側橋桁方向へ移動させ、前
記橋桁が陸側橋桁上に載置されたら、橋桁の後端部の台
船を先頭の台船と隣接させて橋脚内に配置し、その後、
橋桁の先頭に位置する台船を撤去し、橋桁の後端部に位
置する台船で該橋桁を前記陸側橋桁上へ移動することを
特徴とする橋梁の撤去方法である。
A second means for solving the above-mentioned problem is to cut the bridge girder to a length of one and a half span while temporarily supporting both ends of the bridge girder, and to attach the bridge girder to a pair of lifting mechanisms arranged with a pier sandwiched therebetween. Lift up with a barge and move in the direction of the land side bridge girder, and when the bridge girder is placed on the land side girder, place the barge at the rear end of the bridge girder adjacent to the leading barge and place it in the pier, ,
A method for removing a bridge, comprising removing a barge located at the head of a bridge girder, and moving the bridge girder onto the land-side bridge girder with a barge located at the rear end of the bridge girder.

【0013】前記の第二の手段によれば、1スパン半の
巨大橋桁が陸側橋桁上を利用して台船により陸側に移動
されるので、他船の通航を阻害すること無く橋桁が撤去
できる。
According to the second means, since the giant bridge girder of one and a half spans is moved to the land side by the barge using the land side bridge girder, the bridge girder can be formed without obstructing the passage of other ships. Can be removed.

【0014】また、橋桁の切断時には、橋桁が中央寄り
の橋脚で支持されて切断されるので安全である。
Further, when the bridge girder is cut, the bridge girder is cut off while being supported by the pier near the center.

【0015】[0015]

【発明の実施の形態】以下、本発明にかかる橋梁の撤去
方法について、図面を参照しながら説明する。
DETAILED DESCRIPTION OF THE PREFERRED EMBODIMENTS A method for removing a bridge according to the present invention will be described below with reference to the drawings.

【0016】図1は、連続箱桁橋で例示した本発明にか
かる橋梁の撤去方法の準備工程を示す橋梁の側面図であ
る。
FIG. 1 is a side view of a bridge showing a preparation step of a method for removing a bridge according to the present invention exemplified by a continuous box girder bridge.

【0017】図1において、1、2、3、4、5は連続
箱桁からなる橋桁で、その中で1、2、4、5は側径間
桁、3は中央径間桁である。
In FIG. 1, reference numerals 1, 2, 3, 4, and 5 denote bridge girders composed of continuous box girders, in which 1, 2, 4, and 5 denote side span girders and 3 denotes a center span girder.

【0018】A1 およびA2 は橋台で、前記橋桁1、
2、3、4、5は、橋脚P1 、P2 、P3 、P4 上に架
けられており、6は河川等の水路面を示す。
A 1 and A 2 are abutments, and the bridge girder 1,
2, 3, 4, and 5 are bridged on piers P 1 , P 2 , P 3 , and P 4 , and 6 indicates a waterway surface such as a river.

【0019】7、8は仮受連結梁で、中央径間桁3の撤
去に備えて設けられたものである。9、9は中央径間桁
3の切断部であり、モーメントが中立する反曲点または
その近傍が望ましい。
Reference numerals 7 and 8 denote temporary connecting beams, which are provided in preparation for removing the center span girder 3. Numerals 9 and 9 denote cut portions of the center span girder 3, preferably at or near the inflection point where the moment is neutral.

【0020】また、10、10は、側径間桁1、5がコ
ンクリート製で構築されている場合の、鋼製の側径間桁
2、4、との桁連結部を示しており、図示しない対の支
承沓に各々架設されている。尚、10、10は側径間桁
1、5が鋼製の場合は、切断部となる。
Numerals 10 and 10 designate girder connecting portions with steel side girder beams 2 and 4 when side girder beams 1 and 5 are made of concrete. Each is mounted on a pair of bearing shoes. In addition, 10 and 10 become cutting parts when the side span girders 1 and 5 are made of steel.

【0021】図2(部分側面図)、図3(部分平面図)
および図4(図3のA−A断面図)は、前記仮受連結梁
8の説明図で、側径間桁4および中央径間桁3上の床版
コンクリート11を除去し、前記側径間桁4および中央
径間桁3の間にヒンジ8a,8bにより仮受連結梁8を
取付ける。この仮受連結梁8は、側径間桁4および中央
径間桁3の補強のために設けたものである。尚、8cは
中央径間桁3の切断後の反力を受ける固定材で、側径間
桁4と仮受連結梁8とをボルト締結で一体化したもので
ある。
FIG. 2 (partial side view), FIG. 3 (partial plan view)
4 and FIG. 4 (a sectional view taken along line AA in FIG. 3) are explanatory views of the temporary receiving connection beam 8, in which the slab concrete 11 on the side span girder 4 and the center span girder 3 is removed, and The temporary connecting beam 8 is mounted between the span girder 4 and the center span girder 3 by hinges 8a and 8b. The temporary connection beam 8 is provided to reinforce the side span girder 4 and the center span girder 3. Reference numeral 8c denotes a fixing member that receives a reaction force after the center span girder 3 is cut, and is formed by integrating the side span girder 4 and the temporary connection beam 8 with bolts.

【0022】尚、13は既設のヒンジタイプの支承沓で
あり、図4における3a,3aは二条の主桁、3bは横
桁、3cは主桁3a,3a間に設けられた添加物支持梁
である。
Reference numeral 13 denotes an existing hinge-type support shoe. In FIG. 4, reference numerals 3a and 3a denote two main girder beams, 3b denotes a horizontal girder, and 3c denotes an additive support beam provided between the main girder beams 3a and 3a. It is.

【0023】本発明は前記仮受連結梁7、8の取付けが
完了したら、中央径間桁3と側径間桁2、4との間の切
断を行う。切断部9の面は、図1、図2に示すように支
承沓13、側径間桁2、4が載置された状態で中央寄り
で切断する。切断はガス切断またはプラズマ切断あるい
はカッターによる機械的切断のいずれでもよい。
In the present invention, when the attachment of the temporary receiving connection beams 7 and 8 is completed, cutting between the center span girder 3 and the side span girder 2 and 4 is performed. As shown in FIGS. 1 and 2, the surface of the cutting portion 9 is cut near the center with the support shoe 13 and the side span girders 2 and 4 placed thereon. The cutting may be gas cutting, plasma cutting, or mechanical cutting with a cutter.

【0024】中央径間桁3の切断に際し、図1に示すよ
うに、中央径間桁3の下方、即ち、橋脚P2,3,の間
に、対の台船(14)14A、14Bを配置する。台船
14A、14Bは間隔を調整できる連結体14aで連結
されており、船上には架構14b,14bと吊り上げ機
構15の架台15bが分離可能に設けられている。
[0024] Upon cleavage of the center span girder 3, as shown in FIG. 1, the lower center span girder 3, i.e., piers P 2, P 3, between the pair of barge (14) 14A, 14B Place. The hulls 14A, 14B are connected by a connecting body 14a whose distance can be adjusted, and the frames 14b, 14b and the gantry 15b of the lifting mechanism 15 are provided on the hull so as to be separable.

【0025】図5は、図1の左側の台船14Aを上方か
ら見た平面図(台船14Bも同一構造である)で、台船
14Aには、甲板上にウィンチ14cおよび係留索14
dが設けられ該台船14Aの微調整移動を行う構造とな
っており、即ち、前記台船14Aの移動は、一方のウィ
ンチ14cで係留索14dを手繰り寄せ、他方のウィン
チ14cで他方の係留索14dを繰り出すことにより行
う。
FIG. 5 is a plan view of the barge 14A on the left side of FIG. 1 as viewed from above (the barge 14B has the same structure). The barge 14A has a winch 14c and a mooring line 14 on the deck.
d is provided to perform fine adjustment movement of the barge 14A. That is, the movement of the barge 14A is performed by dragging the mooring line 14d with one winch 14c and mooring the other with the other winch 14c. This is performed by extending the rope 14d.

【0026】前記台船14A,14Bには前記架構14
b,14bが中央径間桁3の下方に位置するように配置
される。
The frame 14A, 14B is provided with the frame 14
b and 14b are arranged so as to be located below the center span girder 3.

【0027】中央径間桁3の床版3bにはハッチングで
示す貫通長孔3dが穿たれ、吊り上げ機構15の架台1
5aの支柱15dおよび該支柱15dのブレース材(図
示せず)が貫通する。同じように、台船14の架構14
b,14bの支柱も前記中央径間桁3の床版3bの貫通
長孔3dを貫通する。さらに、3eは同じように中央径
間桁3の主桁3aに穿たれた貫通孔で、吊り上げ機構1
5の吊り索15cが貫通する。吊り索15cは主桁3a
の底面に係止される。
The floor slab 3b of the center span girder 3 is provided with a through-hole 3d indicated by hatching, and the base 1 of the lifting mechanism 15 is provided.
The support 15d of 5a and the brace material (not shown) of the support 15d penetrate. Similarly, the frame 14 of the barge 14
The columns b and 14b also pass through the through-holes 3d of the floor slab 3b of the center span girder 3. 3e is a through hole formed in the main girder 3a of the center span girder 3 in the same manner.
5 hanging cables 15c penetrate. The hanging cable 15c is the main girder 3a.
It is locked to the bottom of.

【0028】図6は、図5のA矢視図で、台船14A上
の架構14bに吊り上げ機構15の支柱15dが係合し
ており、中央径間桁3が破線図の如く降下する状態を示
している。尚、図6に図示したブレース材15eおよび
水平継材15fは取外し可能である。
FIG. 6 is a view taken in the direction of arrow A in FIG. 5, in which the support 15d of the lifting mechanism 15 is engaged with the frame 14b on the barge 14A, and the center span girder 3 descends as shown by the broken line. Is shown. The brace 15e and the horizontal joint 15f shown in FIG. 6 are removable.

【0029】台船14Aの架構14bの支柱14b′と
前記吊り上げ機構15、15の架構15aの支柱15d
は、フランジによるボルト締結で分離可能となってい
る。
The column 14b 'of the frame 14b of the barge 14A and the column 15d of the frame 15a of the lifting mechanisms 15,15.
Can be separated by bolting with a flange.

【0030】尚、台船14Bも前述と同様の構造で中央
径間桁3に係合している。吊り上げ機構15、15のセ
ッティングが完了したら、該吊り上げ機構15、15の
吊り索15cの下部を主桁3aの下面に係止する。その
後、前記仮連結梁7、8の側径間桁2、4側の連結を解
除する。
The barge 14B is also engaged with the center span girder 3 with the same structure as described above. When the setting of the lifting mechanisms 15, 15 is completed, the lower part of the hanging cable 15c of the lifting mechanisms 15, 15 is locked to the lower surface of the main girder 3a. Then, the connection of the temporary connecting beams 7 and 8 on the side span girders 2 and 4 is released.

【0031】尚、台船14の配置は、中央径間桁3の切
断に際し前記仮受連結梁7、8で充分仮支持される場合
は不要であるが、対の台船14、14の吊り上げ機構1
5、15で中央径間桁3の両端を支持しながら切断すれ
ばより安全である。
The barge 14 is not necessary if it is sufficiently temporarily supported by the temporary connection beams 7 and 8 when the center span girder 3 is cut, but the barges 14 are lifted. Mechanism 1
It is safer to cut while supporting both ends of the center span girder 3 at 5 and 15.

【0032】吊り上げ機構15、15について、図6に
より説明すると、ジャッキ15aと架台15bとから構
成され、ジャッキ15aは橋桁下部に係止されたストラ
ンド等の吊り索15cを2ケのクランプ(図示せず)で
交互に把持しシリンダー機構(図示せず)で該把持状態
のクランプを上下動されることにより橋桁の上昇、下降
を行わせるもので、VSLジャッキ(商標)として公知
のものである。該吊り上げ機構15は、同様の機能のも
のであれば、特に、前記VSLジャッキに限定されな
い。前記架台15bは、台船14に固定された架構14
bに前記架台15bの柱15dが取外し自在に取付けら
れている。
Referring to FIG. 6, the lifting mechanisms 15, 15 are composed of a jack 15a and a gantry 15b, and the jack 15a is provided with two hanging ropes 15c such as strands fixed to the lower part of the bridge girder by two clamps (not shown). The bridge girder is raised and lowered by alternately holding the clamp in the holding state by a cylinder mechanism (not shown), and is known as a VSL jack (trademark). The lifting mechanism 15 is not particularly limited to the VSL jack as long as it has a similar function. The frame 15b is a frame 14 fixed to the barge 14.
The column 15d of the gantry 15b is removably attached to b.

【0033】図7は、本発明の次工程を示す橋梁の側面
図で、前記吊り上げ機構15、15で中央径間桁3を側
径間桁2、4より上方に吊り上げ、台船14A、14B
を側径間桁4方向へ移動し、中央径間桁3の先端を側径
間桁4の上部に置く。図示しないが、側径間桁4の上部
には、中央径間桁3の移動を円滑にするため、台車等の
滑動体が設けられる。
FIG. 7 is a side view of the bridge showing the next step of the present invention. The center span girders 3 are lifted above the side span girders 2 and 4 by the hoisting mechanisms 15 and 15, and the barges 14A and 14B.
Is moved in the direction of the side span girder 4, and the tip of the center span girder 3 is placed on the upper side of the side span girder 4. Although not shown, a sliding body such as a bogie is provided on the upper side of the side span girder 4 in order to smoothly move the center span girder 3.

【0034】中央径間桁3の先端が側径間桁4に置かれ
たら、台船14Bを退避させる。この退避は、吊り上げ
機構15の架台15bを台船14Bの架構14bからク
レーン等を使用して撤去させ、台船14Bを橋桁の幅方
向に移動させて退避させる。
When the tip of the center span girder 3 is placed on the side span girder 4, the barge 14B is retracted. In this evacuation, the platform 15b of the lifting mechanism 15 is removed from the frame 14b of the barge 14B using a crane or the like, and the barge 14B is moved in the width direction of the bridge girder and retracted.

【0035】図8は、本発明の次工程を示す橋梁の側面
図で、残りの台船14Aで中央径間桁3の後端部を吊り
上げながら、引続き側径間桁4方向へ移動する。移動に
際しては、側径間桁4上にウィンチ等を設けて牽引と併
用してもよい。
FIG. 8 is a side view of the bridge showing the next step of the present invention. The bridge is moved in the direction of the side span girder 4 while the rear end of the center span girder 3 is lifted by the remaining barge 14A. When moving, a winch or the like may be provided on the side span girder 4 and used together with traction.

【0036】中央径間桁3が完全に側径間桁4上に載置
されたら、公知の牽引装置により側径間桁5を経由して
陸地へ移動され、解体される。
When the center span girder 3 is completely placed on the side span girder 4, the center span girder 3 is moved to the land via the side span girder 5 by a known traction device and disassembled.

【0037】図9は、本発明の次工程を示す橋梁の側面
図で、中央径間桁3が撤去されたら、橋脚P3,4 の間
に、再び、対の台船14A,14Bを配置し前述と同様
の方法で、側径間桁4を陸側の側径間桁5上に移動さ
せ、陸側へ移動して撤去する。
[0037] Figure 9 is a side view of a bridge showing the next step of the present invention, when the center span girder 3 is removed, while the piers P 3, P 4, again, the pair barge 14A, and 14B The side span girder 4 is moved on the land side side span girder 5 in the same manner as described above, and then moved to the land side and removed.

【0038】図10は、本発明の次工程を示す橋梁の側
面図で、前述のとおり、側径間桁4が撤去されたら、残
りの側径間桁2も前述と同様の方法で陸側へ撤去する。
FIG. 10 is a side view of the bridge showing the next step of the present invention. As described above, when the side span girder 4 is removed, the remaining side span girder 2 is also moved to the land side in the same manner as described above. To remove.

【0039】尚、側径間桁1、5は、水深の浅い部分の
架設であり、コンクリート製でもあるので、適当に細分
化して撤去され、また、鋼製の場合も撤去は同様であ
る。
The side span girders 1 and 5 are erected at a shallow portion of the water depth and are also made of concrete. Therefore, the side span girders 1 and 5 are appropriately divided and removed, and the same applies to the case of steel.

【0040】図11〜図15は、本発明の橋梁の撤去方
法の第二の実施の形態に関する橋梁の側面図である。
FIGS. 11 to 15 are side views of a bridge according to a second embodiment of the method for removing the bridge of the present invention.

【0041】図11において、この発明においては、中
央径間桁3の中央線Φに切断部9を形成する。尚、10
は側径間桁4、5の桁連結部であり、1スパン半の橋桁
(3、4)を陸揚げせんとするものである。橋桁は中央
寄りの橋脚P3 およびP4 で支持された状態で切断され
る。尚、切断部9には、前述の実施の形態と同様に、仮
受連結梁7を取付け、また、側径間桁4、5の桁継ぎ目
で支持が不安定な場合は、仮受連結梁8を設ければよ
い。
In FIG. 11, in the present invention, a cut portion 9 is formed at the center line Φ of the center span girder 3. In addition, 10
Is a girder connection part of side span girder 4,5, and is used for landing a bridge girder (3,4) of 1 and a half span. The bridge girder is cut while being supported by piers P 3 and P 4 near the center. The temporary connection beam 7 is attached to the cut portion 9 in the same manner as the above-described embodiment. 8 may be provided.

【0042】図12は、本発明の次工程を示した橋梁の
側面図で、橋桁(3、4)の後端部(橋脚P2,3
間)と、橋桁(3、4)の先端部(橋脚P3,4 の間)
の間に台船14Aと台船14Bを配置する。
[0042] Figure 12 is a side view of a bridge showing the next step of the present invention, the rear end portion of the bridge girder (3, 4) and (between piers P 2, P 3), girders of (3,4) tip (between piers P 3, P 4)
The barge 14A and the barge 14B are arranged between them.

【0043】その後、台船14Aと台船14Bの吊り上
げ機構15で橋桁(3、4)を吊り上げ、陸側へ移動
し、橋桁(3、4)の先端が側径間桁5上に載置された
ら、橋桁(3、4)の後端部を一時橋脚P3 に支持さ
せ、台船14Aを離脱させて、橋脚P3 とP4 の間に配
置されている隣の台船14Bの後方に回航し、橋桁
(3、4)の後端部を支持させる。
Thereafter, the bridge girders (3, 4) are lifted by the lifting mechanism 15 of the barges 14A and 14B and moved to the land side, and the ends of the bridge girders (3, 4) are placed on the side span girders 5. When the rear end portion is supported in the temporary piers P 3 the bridge girder (3, 4), thereby disengaging the barge 14A, behind the next, which is arranged between the piers P 3 and P 4 barge 14B And support the rear end of the bridge girder (3, 4).

【0044】図13は、本発明の次工程を示した橋梁の
側面図で、台船14Aが橋脚P3 とP4 の間に配置され
たら、台船14Bを離脱させ、台船14Aで橋桁(3、
4)を吊り上げながら、陸側へ移動させる。
[0044] Figure 13 is a side view of a bridge showing the next step of the present invention, when the barge 14A is disposed between the piers P 3 and P 4, thereby disengaging the barge 14B, girders in barge 14A (3,
4) Lift and move to the land side.

【0045】図14は、本発明の次工程を示した橋梁の
側面図で、台船14Aが橋脚P4 に当接しそうになった
ら、台船14Bを再び配置し、台船14Aを離脱させ
る。
[0045] Figure 14 is a side view of a bridge showing the next step of the present invention, when the barge 14A becomes likely contact a pier P 4, again placing the barge 14B, disengaging the barge 14A .

【0046】図15は、本発明の次工程を示した橋梁の
側面図で、前記で配置された台船14Bで橋桁(3、
4)をさらに陸側へ移動させる。当然、移動について
は、陸側のウィンチ等の牽引装置を併用してもよい。
FIG. 15 is a side view of the bridge showing the next step of the present invention. The bridge girder (3,
Move 4) further to the land side. Naturally, a traction device such as a land-side winch may be used for movement.

【0047】橋梁の反対側の橋桁(2、3)も前述と同
様の方法で反対側の陸上へ移動させ、解体される。
The bridge girders (2, 3) on the opposite side of the bridge are moved to the land on the opposite side in the same manner as described above and dismantled.

【0048】[0048]

【発明の効果】本発明は、以上のとおりであるから、橋
桁は既存の側径間桁上を使用して陸上の既設道路へ移動
されるので、該既設道路を解体場所として使用でき、台
船で運搬するケースのように航路を確保する必要がな
く、また、他船の通航を阻害することがない。
As described above, according to the present invention, since the bridge girder is moved to the existing road on land using the existing span girder, the existing road can be used as a dismantling place. There is no need to secure a navigation route as in the case of transport by ship, and there is no hindrance to the passage of other ships.

【0049】さらに、橋桁を台船で運搬し、解体場所で
陸揚げしないので、特殊なクレーン等の設備も必要とし
ない利点がある。
Further, since the bridge girder is transported by the barge and not landed at the dismantling place, there is an advantage that no special crane or other equipment is required.

【図面の簡単な説明】[Brief description of the drawings]

【図1】本発明にかかる橋梁の撤去工程を示す側面図。FIG. 1 is a side view showing a bridge removing step according to the present invention.

【図2】本発明の橋梁の撤去方法に使用する仮受連結梁
の側面図。
FIG. 2 is a side view of a temporary connection beam used in the method for removing a bridge of the present invention.

【図3】本発明の橋梁の撤去方法に使用する仮受連結梁
の平面図。
FIG. 3 is a plan view of a temporary connection beam used in the bridge removal method of the present invention.

【図4】図3のA矢視図。FIG. 4 is a view taken in the direction of the arrow A in FIG. 3;

【図5】本発明の橋梁の撤去方法に使用する台船と橋桁
の関係を示す平面図。
FIG. 5 is a plan view showing a relationship between a barge and a bridge girder used in the method for removing a bridge according to the present invention.

【図6】図5のB矢視図。FIG. 6 is a view as seen from the arrow B in FIG. 5;

【図7】本発明にかかる橋梁の撤去工程を示す側面図。FIG. 7 is a side view showing a bridge removing step according to the present invention.

【図8】本発明にかかる橋梁の撤去工程を示す側面図。FIG. 8 is a side view showing a bridge removing step according to the present invention.

【図9】本発明にかかる橋梁の撤去工程を示す側面図。FIG. 9 is a side view showing a bridge removing step according to the present invention.

【図10】本発明にかかる橋梁の撤去工程を示す側面
図。
FIG. 10 is a side view showing a bridge removing step according to the present invention.

【図11】本発明の第二の実施の形態にかかる橋梁の撤
去工程を示す側面図。
FIG. 11 is a side view showing a bridge removing step according to the second embodiment of the present invention.

【図12】本発明の第二の実施の形態にかかる橋梁の撤
去工程を示す側面図。
FIG. 12 is a side view showing a bridge removing step according to the second embodiment of the present invention.

【図13】本発明の第二の実施の形態にかかる橋梁の撤
去工程を示す側面図。
FIG. 13 is a side view showing a bridge removing step according to the second embodiment of the present invention.

【図14】本発明の第二の実施の形態にかかる橋梁の撤
去工程を示す側面図。
FIG. 14 is a side view showing a bridge removing step according to the second embodiment of the present invention.

【図15】本発明の第二の実施の形態にかかる橋梁の撤
去工程を示す側面図。
FIG. 15 is a side view showing a bridge removing step according to the second embodiment of the present invention.

【図16】従来技術1の側面図。FIG. 16 is a side view of the prior art 1;

【図17】従来技術2の側面図。FIG. 17 is a side view of the second prior art.

【符号の説明】[Explanation of symbols]

1 橋桁(側径間桁) 2 橋桁(側径間桁) 3 橋桁(中央径間桁) 4 橋桁(側径間桁) 5 橋桁(側径間桁) P1 橋脚 P2 橋脚 P3 橋脚 P4 橋脚 6 水路面 7 仮受連結梁 8 仮受連結梁 9 切断部 10 桁連結部(切断部) 11 床版コンクリート 13 支承沓 14 台船 15 吊り上げ機構1 Bridge girder (side span girder) 2 Bridge girder (side span girder) 3 Bridge girder (center span girder) 4 Bridge girder (side span girder) 5 Bridge girder (side span girder) P 1 Pier P 2 Pier P 3 Pier P 4 Bridge pier 6 Waterway surface 7 Temporary connecting beam 8 Temporary connecting beam 9 Cutting part 10 Girder connecting part (cutting part) 11 Floor slab concrete 13 Bearing shoe 14 Barge 15 Lifting mechanism

Claims (2)

【特許請求の範囲】[Claims] 【請求項1】 橋桁の両端を仮支持した状態で切断する
とともに、該橋桁を橋脚内に配置された対の吊り上げ機
構付台船で持ち上げて陸側橋桁方向へ移動させ、前記橋
桁が陸側橋桁上に載置されたら、橋桁の先端に位置する
台船を撤去し、橋桁の後端部に位置する台船で該橋桁を
前記陸側橋桁上へ移動することを特徴とする橋梁の撤去
方法。
1. A bridge girder is cut in a state where both ends thereof are temporarily supported, and the bridge girder is lifted by a pair of barges with a lifting mechanism arranged in a pier and moved in a land side bridge girder direction. Removing the barge located at the tip of the bridge girder after being placed on the bridge girder, and moving the bridge girder onto the land-side bridge girder with the barge located at the rear end of the bridge girder; Method.
【請求項2】 橋桁の両端を仮支持した状態で1スパン
半の長さに切断するとともに、該橋桁を橋脚を挟んで配
置された対の吊り上げ機構付台船で持ち上げて陸側橋桁
方向へ移動させ、前記橋桁が陸側橋桁上に載置された
ら、橋桁の後端部の台船を先頭の台船と隣接させて橋脚
内に配置し、その後、橋桁の先頭に位置する台船を撤去
し、橋桁の後端部に位置する台船で該橋桁を前記陸側橋
桁上へ移動することを特徴とする橋梁の撤去方法。
2. A bridge girder is cut to a length of one and a half spans while both ends of the bridge girder are temporarily supported, and the bridge girder is lifted up by a pair of barges with a lifting mechanism arranged with a pier interposed therebetween, and is moved toward the land side bridge girder. When the bridge girder is placed on the land-side bridge girder, the barge at the rear end of the bridge girder is placed in the pier adjacent to the leading barge, and then the barge located at the head of the bridge girder is moved. A method for removing a bridge, comprising removing the bridge girder and moving the bridge girder onto the land-side bridge girder using a barge located at the rear end of the bridge girder.
JP25052696A 1996-09-20 1996-09-20 Method for removing bridge Pending JPH1096211A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
JP25052696A JPH1096211A (en) 1996-09-20 1996-09-20 Method for removing bridge

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
JP25052696A JPH1096211A (en) 1996-09-20 1996-09-20 Method for removing bridge

Publications (1)

Publication Number Publication Date
JPH1096211A true JPH1096211A (en) 1998-04-14

Family

ID=17209213

Family Applications (1)

Application Number Title Priority Date Filing Date
JP25052696A Pending JPH1096211A (en) 1996-09-20 1996-09-20 Method for removing bridge

Country Status (1)

Country Link
JP (1) JPH1096211A (en)

Cited By (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
KR20040040695A (en) * 2002-11-07 2004-05-13 주식회사 하이테크한상 Temporary apparatus for dismantalement of slab
KR101153779B1 (en) 2011-08-26 2012-06-07 (주) 한국비계 Device for bridge dismantle using the strand jack and its methode
CN110067206A (en) * 2019-05-16 2019-07-30 成都建工路桥建设有限公司 A kind of ovum type underpass bridge construction method
CN114855656A (en) * 2022-05-25 2022-08-05 中国铁建港航局集团有限公司 Construction method for dismantling old bridge by bridge girder erection machine

Cited By (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
KR20040040695A (en) * 2002-11-07 2004-05-13 주식회사 하이테크한상 Temporary apparatus for dismantalement of slab
KR101153779B1 (en) 2011-08-26 2012-06-07 (주) 한국비계 Device for bridge dismantle using the strand jack and its methode
CN110067206A (en) * 2019-05-16 2019-07-30 成都建工路桥建设有限公司 A kind of ovum type underpass bridge construction method
CN110067206B (en) * 2019-05-16 2020-08-18 成都建工路桥建设有限公司 Construction method of egg-shaped underpass bridge
CN114855656A (en) * 2022-05-25 2022-08-05 中国铁建港航局集团有限公司 Construction method for dismantling old bridge by bridge girder erection machine

Similar Documents

Publication Publication Date Title
EP1021624B1 (en) Method and apparatus for the offshore installation of multi-ton packages such as deck packages and jackets
US8070388B2 (en) Structure for transporting, commissioning and decommissioning the elements of a fixed oil platform and methods for implementing such a structure
US6318931B1 (en) Method and apparatus for the offshore installation of multi-ton packages such as deck packages and jackets
EP1189804B1 (en) Device for positioning and lifting a marine structure, particularly a platform deck
KR20100087094A (en) Method for installing a drilling apparatus on a rig and for preparing drilling operations
US6736571B2 (en) Removal of decks from offshore structures
JPH0841826A (en) Erection method of bridge and equipment thereof and main girder unit
CN104060592B (en) Method for 1/4 land territory preassembling and overwater dispersion of large cylinder main grids of cellular steel sheet piles
JPH1096211A (en) Method for removing bridge
JPH10280328A (en) Removal and erection method for bridge and pontoon equipment used to the method
JPH10147912A (en) Method for removing and erecting bridge
JPH1096212A (en) Method for removing bridge
GB2156286A (en) Installation and removal vessel
KR20020074130A (en) Methodology in one united body for pre-fabrication upper part of bridge using lifting System with push pull mechanism.
CN211340438U (en) Steel bridge pushing and pulling system in navigation water area
JP7197118B2 (en) Work barge equipped with a crane and its crane operation method
CN105926466A (en) Device and construction method for steel truss bridge integral transporting
JPH10168826A (en) Bridge construction method
RU2737748C1 (en) Installation of underwater road demountable bridge in design position of superstructure with one intermediate pile-shoe support
EP0551665A1 (en) Crane relocation and erection
CN112227214B (en) Splicing structure of steel members and mounting method thereof
SU1555424A1 (en) Method and apparatus for mounting upper structure of stationary drilling platform onto supporting foundation
GB2564152A (en) Offshore decommissioning vessel and methods of use
JPH10168829A (en) Bridge construction method
JPH1087080A (en) Unloading and loading method for structures