JPH10168900A - Precast reinforced concrete independent foundation - Google Patents

Precast reinforced concrete independent foundation

Info

Publication number
JPH10168900A
JPH10168900A JP33596896A JP33596896A JPH10168900A JP H10168900 A JPH10168900 A JP H10168900A JP 33596896 A JP33596896 A JP 33596896A JP 33596896 A JP33596896 A JP 33596896A JP H10168900 A JPH10168900 A JP H10168900A
Authority
JP
Japan
Prior art keywords
factory
base
site
reinforced concrete
precast reinforced
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
JP33596896A
Other languages
Japanese (ja)
Inventor
Atsushi Abe
淳 阿部
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
HOPPO JUBUNKA KENKYUSHO KK
Sekisui Chemical Co Ltd
Hoppo Jubunka Kenkyusho KK
Original Assignee
HOPPO JUBUNKA KENKYUSHO KK
Sekisui Chemical Co Ltd
Hoppo Jubunka Kenkyusho KK
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by HOPPO JUBUNKA KENKYUSHO KK, Sekisui Chemical Co Ltd, Hoppo Jubunka Kenkyusho KK filed Critical HOPPO JUBUNKA KENKYUSHO KK
Priority to JP33596896A priority Critical patent/JPH10168900A/en
Publication of JPH10168900A publication Critical patent/JPH10168900A/en
Pending legal-status Critical Current

Links

Landscapes

  • Foundations (AREA)

Abstract

PROBLEM TO BE SOLVED: To improve the transportability from a factory to a construction site by forming a precast reinforced concrete independent foundation of a rectangular column-like raised part and a base part having the same width, and concreting a reinforcement part laid in the protruded state in the site to form a base. SOLUTION: A precast reinforced concrete independent foundation 10 is formed of a base part 11 and a raised part 12 having an anchor bolt 13, and a cast-in-place base part 11B has a reinforcement 14 preliminarily protruded thereon. When the foundation 10 produced in a factory is transported to a construction site, the reinforcement 14 may be bent upward so as to lay the foundation 10 in a compact state. The foundation 10 is arranged in the construction site having a setting base, and the top end height is regulated by a height regulating tool mounted on the base part 11. The reinforcements vertical to the reinforcement 14 are bundled, a base form is mounted on the basis of the lateral end surface of the base part 11A, and concrete is placed in the cast-in- place base part 11B and integrated with the base part 11. Thus, transportability and field constructing property of precast reinforced concrete can be improved.

Description

【発明の詳細な説明】DETAILED DESCRIPTION OF THE INVENTION

【0001】[0001]

【発明の属する技術分野】本発明はプレキャスト鉄筋コ
ンクリート独立基礎に関する。
[0001] The present invention relates to a precast reinforced concrete independent foundation.

【0002】[0002]

【従来の技術】従来、プレキャスト鉄筋コンクリート独
立基礎は、ベース部が立上り部の下部で側方に広げられ
たものであり、ベース部と立上り部とからなる全体を工
場にて打設済としている。
2. Description of the Related Art Conventionally, in a precast reinforced concrete independent foundation, a base portion is expanded laterally at a lower portion of a rising portion, and an entire structure including a base portion and a rising portion is already cast at a factory.

【0003】尚、実開平1-61243 号公報には、プレキャ
スト鉄筋コンクリート独立基礎において、立上り部だけ
を工場にて打設し、ベース部は現場にて打設するように
したものが提案されている。この従来技術では、立上り
部の底部にジャッキプレートを埋め込み、このジャッキ
プレートのナットに螺着したジャッキボルトにより据付
高さを調整可能としている。
Japanese Utility Model Laid-Open No. 1-61243 proposes a precast reinforced concrete independent foundation in which only the rising portion is cast at the factory and the base portion is cast at the site. . In this prior art, a jack plate is embedded in the bottom of the rising portion, and the installation height can be adjusted by jack bolts screwed onto nuts of the jack plate.

【0004】[0004]

【発明が解決しようとする課題】然しながら、ベース部
と立上り部の全体を工場打設する従来技術では、工場生
産された基礎の形態が立上り部の下部にて側方に大きく
張り出るベース部を備えた大型で複雑な形状をしてお
り、工場から現場への輸送性が悪い。
However, in the prior art in which the entire base portion and the rising portion are cast into a factory, the form of the factory-produced foundation has a base portion that largely projects laterally below the rising portion. It has a large and complicated shape with poor transportability from the factory to the site.

【0005】他方、実開平1-61243 号公報に記載の如く
に立上り部だけを工場打設する従来技術では、現場据付
時の基盤に対する着座安定性が悪く、ベース部の工場打
設時に位置ずれする等、現場施工性が悪い。
On the other hand, in the prior art in which only the rising portion is factory-casted as described in Japanese Utility Model Laid-Open No. 1-61243, the seating stability with respect to the base at the time of installation at the site is poor, and the base is misaligned when the factory is installed. The workability on site is poor.

【0006】本発明の課題は、プレキャスト鉄筋コンク
リート独立基礎において、工場から現場への輸送性を向
上するとともに、現場施工性を向上することにある。
An object of the present invention is to improve the transportability from a factory to a site and to improve the site workability in a precast reinforced concrete independent foundation.

【0007】[0007]

【課題を解決するための手段】請求項1に記載の本発明
は、ベース部と立上り部とからなり、ベース部は立上り
部の下部で側方に広げられたものであるプレキャスト鉄
筋コンクリート独立基礎において、ベース部の一部を工
場打設ベース部とし、残部を現場打設ベース部としてな
るようにしたものである。
According to a first aspect of the present invention, there is provided a precast reinforced concrete independent foundation comprising a base portion and a rising portion, the base portion extending laterally at a lower portion of the rising portion. A part of the base part is a factory casting base part, and the remaining part is a field casting base part.

【0008】請求項2に記載の本発明は、請求項1に記
載の本発明において更に、前記現場打設ベース部には、
工場打設ベース部から予め鉄筋が突出せしめられてなる
ようにしたものである。
According to a second aspect of the present invention, in the first aspect of the present invention, further, the on-site casting base portion further comprises:
The reinforcing bar is made to protrude from the factory casting base in advance.

【0009】請求項3に記載の本発明は、請求項1又は
2に記載の本発明において更に、前記工場打設ベース部
の幅が、現場コンクリート打設後の仕上り状態における
ベース部の幅と略等しくされてなるようにしたものであ
る。
According to a third aspect of the present invention, in addition to the first or second aspect of the present invention, the width of the factory casting base portion is equal to the width of the base portion in a finished state after casting concrete on site. It is made to be substantially equal.

【0010】請求項4に記載の本発明は、請求項1〜3
のいずれかに記載の本発明において更に、前記工場打設
ベース部には、高さ調整具が取付け可能とされてなるよ
うにしたものである。
The present invention described in claim 4 is the first to third aspects of the present invention.
In the present invention described in any one of the above, further, a height adjusting tool can be attached to the factory casting base portion.

【0011】請求項5に記載の本発明は、請求項4に記
載の本発明において更に、前記高さ調整具が、前記工場
打設ベース部の底面から両側に延びるジャッキプレート
と、該ジャッキプレートの両端部に螺着されたジャッキ
ボルトからなるようにしたものである。
According to a fifth aspect of the present invention, in the fourth aspect of the present invention, the height adjuster further includes a jack plate extending to both sides from a bottom surface of the factory casting base portion, and the jack plate. Are formed by jack bolts screwed to both ends.

【0012】請求項1に記載の本発明によれば下記、
の作用がある。 立上り部の下部にて側方に張り出るベース部の一部だ
けを工場打設部分としたので、工場から現場への輸送形
態をコンパクトとし、輸送性を向上できる。
According to the first aspect of the present invention,
Has the effect of Since only a part of the base portion that protrudes laterally at the lower part of the rising portion is used as a factory casting portion, the form of transportation from the factory to the site can be made compact, and transportability can be improved.

【0013】現場据付時に既に工場打設ベース部を備
えており、基礎は未完成状態ではあっても低重心で、且
つ基盤に対する広い着座面も備える。従って、現場据付
時の基盤に対する着座安定性が良く、現場打設時におけ
る位置ずれ等も起こりにくく、現場施工性も向上でき
る。
At the time of installation at the site, the base is already provided with a factory casting base, and the foundation has a low center of gravity even though it is in an unfinished state, and also has a wide seating surface for the base. Therefore, the seating stability with respect to the base at the time of installation on the site is good, the displacement is not likely to occur at the time of on-site installation, and the on-site workability can be improved.

【0014】請求項2に記載の本発明によれば下記、
の作用がある。 現場打設ベース部には工場打設ベース部から予め鉄筋
が出ているので、これに垂直に鉄筋を結束するだけで、
現場での配筋作業を終了でき、現場施工性を向上でき
る。
According to the second aspect of the present invention,
Has the effect of Reinforcing bars come out from the factory casting base part in the site casting base part in advance, so just tie the reinforcing steel perpendicular to this,
Bar arrangement work at the site can be completed, and workability at the site can be improved.

【0015】工場から現場への輸送時に、工場打設ベ
ース部から出ている鉄筋を折り曲げた状態にすることに
より、輸送形態の単純化を図り、輸送性を向上できる。
[0015] During transportation from the factory to the site, by bending the reinforcing bars protruding from the factory casting base, the transportation mode can be simplified and the transportability can be improved.

【0016】請求項3に記載の本発明によれば下記の
作用がある。 工場打設ベース部の幅を現場コンクリート打設後の仕
上り状態におけるベース部の幅と略等しくしておくこと
により、現場ではこの幅を基準にベース型枠を取付けて
コンクリート打設でき、現場施工性を向上できる。
According to the third aspect of the present invention, the following effects are obtained. By setting the width of the base for casting at the factory to be approximately equal to the width of the base in the finished state after casting the concrete at the site, it is possible to install the base formwork on the basis of this width and cast concrete at the site. Performance can be improved.

【0017】請求項4、5に記載の本発明によれば下記
の作用がある。 工場打設ベース部にジャッキプレート、ジャッキボル
ト等の高さ調整具を備えることにより、現場での据付高
さを簡易に調整できる。
According to the present invention, the following effects are obtained. By providing a height adjustment tool such as a jack plate or jack bolt on the factory casting base, the installation height at the site can be easily adjusted.

【0018】[0018]

【発明の実施の形態】図1はプレキャスト鉄筋コンクリ
ート独立基礎の工場生産状態を示す模式図、図2はプレ
キャスト鉄筋コンクリート独立基礎に高さ調整具を取付
けた状態を示す模式図、図3はプレキャスト鉄筋コンク
リート独立基礎の現場施工中間状態を示す模式図、図4
はプレキャスト鉄筋コンクリート独立基礎の現場施工完
了状態を示す模式図、図5はプレキャスト鉄筋コンクリ
ート独立基礎の鉄筋接続構造を示す模式図である。
DESCRIPTION OF THE PREFERRED EMBODIMENTS FIG. 1 is a schematic view showing a factory production state of a precast reinforced concrete independent foundation, FIG. 2 is a schematic view showing a state in which a height adjuster is attached to the precast reinforced concrete independent foundation, and FIG. FIG. 4 is a schematic view showing an intermediate state of the foundation on-site construction.
FIG. 5 is a schematic view showing a completed state of the precast reinforced concrete independent foundation on site, and FIG. 5 is a schematic view showing a reinforcing bar connection structure of the precast reinforced concrete independent foundation.

【0019】プレキャスト鉄筋コンクリート独立基礎1
0は、図4に示す如く、ベース部11と立上り部12と
からなり、ベース部11は立上り部12の下部で側方に
広げられたものである。立上り部12は、アンカーボル
ト13を備える。
Precast reinforced concrete independent foundation 1
Numeral 0, as shown in FIG. 4, includes a base portion 11 and a rising portion 12, and the base portion 11 is expanded laterally below the rising portion 12. The rising portion 12 includes an anchor bolt 13.

【0020】基礎10は、ベース部11の一部を工場に
て施工される工場打設ベース部11Aとし、残部を現場
にて施工される現場打設ベース部11Bとしている(図
1)。
In the foundation 10, a part of the base portion 11 is a factory casting base portion 11A to be constructed in a factory, and the remaining portion is a field casting base portion 11B to be constructed in the field (FIG. 1).

【0021】基礎10の現場打設ベース部11Bには、
工場打設ベース部11Aから予め鉄筋14が突出せしめ
られている。尚、基礎10は、工場打設ベース部11A
における現場打設ベース部11Bに臨む端面に埋め込ん
であるねじ込み式金具15に上記鉄筋14を現場施工段
階でねじ込み接続し、この鉄筋14を現場打設ベース部
11Bに突出すものであっても良い(図5)。
The on-site casting base portion 11B of the foundation 10 includes:
The reinforcing bar 14 is projected from the factory casting base 11A in advance. In addition, the foundation 10 is a factory casting base part 11A.
The above-mentioned rebar 14 may be screwed and connected at the on-site construction stage to the screw-type metal fitting 15 embedded in the end face facing the on-site casting base 11B in the above, and the rebar 14 may be projected to the on-site casting base 11B. (FIG. 5).

【0022】基礎10の工場打設ベース部11Aの幅W
(図1)は、基礎10の現場コンクリート打設後の仕上
り状態におけるベース部の幅W(図4)に設定されてい
る。
The width W of the base 10A of the base 10 at the factory
(FIG. 1) is set to the width W (FIG. 4) of the base in the finished state after the concrete is cast on the foundation 10.

【0023】基礎10の工場打設ベース部11Aには、
工場施工段階もしくは現場施工段階で、高さ調整具16
が取付け可能とされている。高さ調整具16は、図2、
図3に示す如く、工場打設ベース部11Aの底面から両
側に延びるジャッキプレート17と、ジャッキプレート
17の両端部に螺着されたジャッキボルト18とからな
るものにて構成することができる。
The factory casting base 11A of the foundation 10 includes:
At the factory construction stage or on-site construction stage, the height adjustment tool 16
Can be attached. The height adjuster 16 is shown in FIG.
As shown in FIG. 3, it can be constituted by a jack plate 17 extending to both sides from the bottom surface of the factory casting base 11A, and jack bolts 18 screwed to both ends of the jack plate 17.

【0024】以下、基礎10の施工手順について説明す
る。 (1) 工場生産した基礎10を現場に輸送する。この時、
鉄筋14を上方に折り曲げて、更にコンパクトな状態に
することもできる。
The procedure for constructing the foundation 10 will be described below. (1) Transport the factory-produced foundation 10 to the site. At this time,
The reinforcing bar 14 can be bent upward to make it more compact.

【0025】(2) 現場では、基礎10の設置基盤が整え
られる。
(2) At the site, an installation base for the foundation 10 is prepared.

【0026】(3) 基礎10をクレーンで吊り込み設置す
る。このとき、基礎10は、工場打設ベース部11Aに
工場生産段階もしくは現場施工段階で取り付けられる高
さ調整具16により、高さ方向位置を調整され、基礎1
0の通りと天端高さを揃えられる。
(3) The foundation 10 is suspended by a crane and installed. At this time, the height direction position of the foundation 10 is adjusted by the height adjustment tool 16 attached to the factory casting base portion 11A at the factory production stage or on-site construction stage.
The height of the top is aligned with zero.

【0027】(4) 工場打設ベース部11Aから現場打設
ベース部11Bに突き出ている鉄筋14に垂直に鉄筋1
9を結束する(図3)。
(4) The reinforcing bar 1 is perpendicular to the reinforcing bar 14 projecting from the factory casting base 11A to the on-site casting base 11B.
9 (FIG. 3).

【0028】(5) 工場打設ベース部11Aの幅(W)方
向端面を基準にベース片枠を取付け、現場打設ベース部
11Bにコンクリートを打設し、工場打設ベース部11
Aと現場打設ベース部11Bとからなるベース部11を
備えた基礎10の施工を完了する(図4)。
(5) A base single frame is mounted on the basis of the end face in the width (W) direction of the factory casting base 11A, and concrete is cast into the on-site casting base 11B.
The construction of the foundation 10 including the base portion 11 composed of A and the cast-in-place base portion 11B is completed (FIG. 4).

【0029】以下、本実施形態の作用について説明す
る。 立上り部12の下部にて側方に張り出るベース部11
の一部だけを工場打設部分としたので、工場から現場へ
の輸送形態をコンパクトとし、輸送性を向上できる。
Hereinafter, the operation of the present embodiment will be described. Base portion 11 that projects laterally at the lower part of rising portion 12
Since only a part of the factory is set in the factory, the transport from the factory to the site can be made compact, and transportability can be improved.

【0030】現場据付時に既に工場打設ベース部11
Aを備えており、基礎10は未完成状態ではあっても低
重心で、且つ基盤に対する広い着座面も備える。従っ
て、現場据付時の基盤に対する着座安定性が良く、現場
打設時における位置ずれ等も起こりにくく、現場施工性
も向上できる。
At the time of installation at the site, the base 11 is already installed at the factory.
A, the foundation 10 has a low center of gravity, even in an unfinished state, and also has a wide seating surface for the base. Therefore, the seating stability with respect to the base at the time of installation on the site is good, the displacement is not likely to occur at the time of on-site installation, and the on-site workability can be improved.

【0031】現場打設ベース部11Bには工場打設ベ
ース部11Aから予め鉄筋14がでているので、これに
垂直に鉄筋19を結束するだけで、現場での配筋作業を
終了でき、現場施工性を向上できる。
Since the reinforcing bar 14 is previously provided on the on-site casting base 11B from the factory casting base 11A, the reinforcing bar 19 can be completed by simply binding the reinforcing bar 19 perpendicularly thereto. Workability can be improved.

【0032】工場から現場への輸送時に、工場打設ベ
ース部11Aから出ている鉄筋14を折り曲げた状態に
することにより、輸送形態の単純化を図り、輸送性を向
上できる。
When transporting from the factory to the site, the reinforcing bars 14 protruding from the factory casting base 11A are bent so that the transport mode can be simplified and transportability can be improved.

【0033】工場打設ベース部11Aの幅を現場コン
クリート打設後の仕上り状態におけるベース部の幅とし
ておくことにより、現場ではこの幅を基準にベース型枠
を取付けてコンクリート打設でき、現場施工性を向上で
きる。
By setting the width of the base part 11A at the factory as the width of the base part in the finished state after the concrete is cast on site, the base formwork can be mounted on the site based on this width and the concrete can be cast. Performance can be improved.

【0034】工場打設ベース部11Aにジャッキプレ
ート17、ジャッキボルト18等の高さ調整具16を備
えることにより、現場での据付高さを簡易に調整でき
る。
By providing the height setting tool 16 such as the jack plate 17 and the jack bolt 18 on the factory casting base 11A, the installation height at the site can be easily adjusted.

【0035】以上、本発明の実施の形態を図面により詳
述したが、本発明の具体的な構成はこの実施の形態に限
られるものではなく、本発明の要旨を逸脱しない範囲の
設計の変更等があっても本発明に含まれる。例えば、基
礎のベース部は、立上り部の下部で両側方に逆T字状な
すように張り出るものに限らず、片側方にL字状に張り
出るものであっても良い。
The embodiment of the present invention has been described in detail with reference to the drawings. However, the specific configuration of the present invention is not limited to this embodiment, and the design may be changed without departing from the scope of the present invention. The present invention is also included in the present invention. For example, the base portion of the foundation is not limited to one that protrudes in an inverted T-shape on both sides below the rising portion, and may be one that protrudes in an L-shape on one side.

【0036】[0036]

【発明の効果】以上のように本発明によれば、プレキャ
スト鉄筋コンクリート独立基礎において、工場から現場
への輸送性を向上するとともに、現場施工性を向上する
ことができる。
As described above, according to the present invention, in the precast reinforced concrete independent foundation, the transportability from the factory to the site and the on-site workability can be improved.

【図面の簡単な説明】[Brief description of the drawings]

【図1】図1はプレキャスト鉄筋コンクリート独立基礎
の工場生産状態を示す模式図である。
FIG. 1 is a schematic view showing a factory production state of a precast reinforced concrete independent foundation.

【図2】図2はプレキャスト鉄筋コンクリート独立基礎
に高さ調整具を取付けた状態を示す模式図である。
FIG. 2 is a schematic diagram showing a state in which a height adjuster is attached to a precast reinforced concrete independent foundation.

【図3】図3はプレキャスト鉄筋コンクリート独立基礎
の現場施工中間状態を示す模式図である。
FIG. 3 is a schematic view showing an intermediate state of construction of a precast reinforced concrete independent foundation on site.

【図4】図4はプレキャスト鉄筋コンクリート独立基礎
の現場施工完了状態を示す模式図である。
FIG. 4 is a schematic view showing a completed state of on-site construction of a precast reinforced concrete independent foundation.

【図5】図5はプレキャスト鉄筋コンクリート独立基礎
の鉄筋接続構造を示す模式図である。
FIG. 5 is a schematic view showing a reinforcing bar connection structure of a precast reinforced concrete independent foundation.

【符号の説明】[Explanation of symbols]

10 プレキャスト鉄筋コンクリート独立基礎 11 ベース部 11A 工場打設ベース部 11B 現場打設ベース部 12 立上り部 14 鉄筋 16 高さ調整具 17 ジャッキプレート 18 ジャッキボルト DESCRIPTION OF SYMBOLS 10 Precast reinforced concrete independent foundation 11 Base part 11A Factory casting base part 11B On-site casting base part 12 Rise part 14 Reinforcing bar 16 Height adjustment tool 17 Jack plate 18 Jack bolt

Claims (5)

【特許請求の範囲】[Claims] 【請求項1】 ベース部と立上り部とからなり、ベース
部は立上り部の下部で側方に広げられたものであるプレ
キャスト鉄筋コンクリート独立基礎において、 ベース部の一部を工場打設ベース部とし、残部を現場打
設ベース部としてなることを特徴とするプレキャスト鉄
筋コンクリート独立基礎。
1. A precast reinforced concrete independent foundation comprising a base portion and a rising portion, the base portion extending laterally below a rising portion, wherein a part of the base portion is a factory cast base portion, Precast reinforced concrete independent foundation characterized in that the remaining part is used as a base for casting on site.
【請求項2】 前記現場打設ベース部には、工場打設ベ
ース部から予め鉄筋が突出せしめられてなる請求項1記
載のプレキャスト鉄筋コンクリート独立基礎。
2. The precast reinforced concrete independent foundation according to claim 1, wherein a reinforcing bar is protruded from the factory casting base portion in advance at the site casting base portion.
【請求項3】 前記工場打設ベース部の幅が、現場コン
クリート打設後の仕上り状態におけるベース部の幅と略
等しくされてなる請求項1又は2記載のプレキャスト鉄
筋コンクリート独立基礎。
3. The precast reinforced concrete independent foundation according to claim 1, wherein a width of the factory cast base portion is substantially equal to a width of the base portion in a finished state after the on-site concrete casting.
【請求項4】 前記工場打設ベース部には、高さ調整具
が取付け可能とされてなる請求項1〜3のいずれかに記
載のプレキャスト鉄筋コンクリート独立基礎。
4. The precast reinforced concrete independent foundation according to claim 1, wherein a height adjuster is attachable to the factory casting base portion.
【請求項5】 前記高さ調整具が、前記工場打設ベース
部の底面から両側に延びるジャッキプレートと、該ジャ
ッキプレートの両端部に螺着されたジャッキボルトから
なる請求項4記載のプレキャスト鉄筋コンクリート独立
基礎。
5. The precast reinforced concrete according to claim 4, wherein said height adjusting tool comprises a jack plate extending to both sides from a bottom surface of said factory casting base portion, and jack bolts screwed to both ends of said jack plate. Independent foundation.
JP33596896A 1996-12-16 1996-12-16 Precast reinforced concrete independent foundation Pending JPH10168900A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
JP33596896A JPH10168900A (en) 1996-12-16 1996-12-16 Precast reinforced concrete independent foundation

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
JP33596896A JPH10168900A (en) 1996-12-16 1996-12-16 Precast reinforced concrete independent foundation

Publications (1)

Publication Number Publication Date
JPH10168900A true JPH10168900A (en) 1998-06-23

Family

ID=18294341

Family Applications (1)

Application Number Title Priority Date Filing Date
JP33596896A Pending JPH10168900A (en) 1996-12-16 1996-12-16 Precast reinforced concrete independent foundation

Country Status (1)

Country Link
JP (1) JPH10168900A (en)

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP2016205051A (en) * 2015-04-27 2016-12-08 株式会社竹中工務店 Construction method for structure

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP2016205051A (en) * 2015-04-27 2016-12-08 株式会社竹中工務店 Construction method for structure

Similar Documents

Publication Publication Date Title
JP3611510B2 (en) Half precast floor slab
JP3748817B2 (en) Concrete assembly structure
JPH10168900A (en) Precast reinforced concrete independent foundation
JP3191951B2 (en) Foundation construction method
JP2002180420A (en) Steel-concrete synthetic floor slab and its execution method and constitutive member of this synthetic floor slab and bridge suing this synthetic floor slab
JPH07286332A (en) Execution method of precast concrete foundation and installation spacer used therefor
JP3662207B2 (en) Construction block for concrete foundation for construction and construction method for concrete foundation for construction
JPH0517957A (en) Foundation for building
JPH07113240A (en) Housing long-strip footing and construction method thereof
JP2741849B2 (en) Construction method of L-shaped retaining wall corner
JPH0716764Y2 (en) Retaining wall block
JP3868336B2 (en) Molded floor board support member and stepped floor forming method
JPH0610436A (en) Method for constructing beam-equipped slab
JPH0841899A (en) Construction method for foundation beam and pc plate for beam
JPH0732755Y2 (en) Foundation bolt installation frame that also serves as a concrete formwork
JPS6133088Y2 (en)
CN111335152A (en) Prefabricated abutment
JPS6343281Y2 (en)
JP2724891B2 (en) Construction method of pillar half PCa formwork
JP3082147B2 (en) Construction method of reinforced concrete structures
JPH026901B2 (en)
JP3088568B2 (en) Precast concrete foundation block and construction method
JPH0762669A (en) Method for constructing column base of precast concrete
JPH08105064A (en) Construction of footing
JPH03295979A (en) Frame and construction method using frame thereof