Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Granted
Application number
JP8298914A
Other languages
Japanese (ja)
Other versions
JP3277131B2 (en
Inventor
Takeshi Kawachi
武 川地
Yoshimasa Hayashi
好正 林
Haruka Ogawa
晴果 小川
Kazufusa Mitani
一房 三谷
Masao Kawahara
正雄 川原
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Obayashi Corp
Schokbeton Japan Co Ltd
Original Assignee
Obayashi Corp
Schokbeton Japan Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Obayashi Corp, Schokbeton Japan Co Ltd filed Critical Obayashi Corp
Priority to JP29891496A priority Critical patent/JP3277131B2/en
Publication of JPH10140779A publication Critical patent/JPH10140779A/en
Application granted granted Critical
Publication of JP3277131B2 publication Critical patent/JP3277131B2/en
Anticipated expiration legal-status Critical
Expired - Lifetime legal-status Critical Current

Links

Landscapes

  • Working Measures On Existing Buildindgs (AREA)

Abstract

PROBLEM TO BE SOLVED: To make it possible to prevent chips produced by boring from becoming an obstacle to bonding work and protect a net from being damaged in an attempt to mount a mechanical anchor when forming a finished surface by using both the mechanical anchor and the net. SOLUTION: A marking is made on the surface of a tile 18, thereby forming a hole 34. After having formed the hole 34, water is discharged over the surface of the tile 18, thereby cleaning the tile. The axial part 32a of a mechanical anchor 32 is driven into the hole 34, thereby forming a coat-finished layer 24 on the surface of the tile 18 into which the axial part 32a is driven. A bristled 3D net 26 is stretched on the coat-finished layer 24. Then, the seat 32b of the mechanical anchor 32 is pushed from the surface side of the net 26 so that a female screw 32d may be fitted into the axial part 32a by way of the meshes of the tatege 3D net 26 and fixed therewith. After that, a finishing layer 28 and a highly weatherable paint are applied thereon.

Description

【発明の詳細な説明】DETAILED DESCRIPTION OF THE INVENTION

【0001】[0001]

【発明の属する技術分野】本発明は、新設のコンクリー
ト構造物に仕上げ面を形成したり、若しくは既設のコン
クリート構造物の既存仕上げ面を補修・改修したりする
ための仕上げ面の施工方法及び仕上げ面構造に関する。
BACKGROUND OF THE INVENTION 1. Field of the Invention The present invention relates to a method and a finishing method for a finished surface for forming a finished surface on a new concrete structure, or for repairing or modifying an existing finished surface of an existing concrete structure. Regarding surface structure.

【0002】[0002]

【従来の技術】従来、タイル張りの壁面を補修する場合
には、例えば特公平8−14182号公報(Int.Cl.E04F
13/02) に開示されているように、タイルの剥離部分の
表面に下地材としてラテックスモルタルを塗布してその
表面にネットを配置し、このネットの上からピンを打込
んでネットを押さえ、その後、ネットおよびピンがかく
れるように再度ラテックスモルタルを塗布するようにな
っている。つまり、タイル壁面にラテックスモルタルに
よってネットを張付けた後、このラテックスモルタルが
硬化した後にピン打込み用の穿孔を施してピンを打込
み、このピンで既存壁の剥離部分を固定するようにして
いる。
2. Description of the Related Art Conventionally, in the case of repairing a tiled wall surface, for example, Japanese Patent Publication No. 8-14182 (Int.
As disclosed in (13/02), latex mortar is applied as a base material on the surface of the peeled portion of the tile, a net is arranged on the surface, and a pin is hit on the net to hold down the net, Thereafter, the latex mortar is applied again so that the net and the pin are hidden. That is, after a net is stuck to the tile wall surface with latex mortar, after the latex mortar has hardened, a hole for pin driving is made and a pin is driven, and the peeled portion of the existing wall is fixed by the pin.

【0003】[0003]

【発明が解決しようとする課題】しかしながら、かかる
従来のタイル壁の補修方法では、上述したようにタイル
壁面にラテックスモルタルでネットを張付けた後に穿孔
してピンを打込む手順となっていて、モルタルの硬化後
にドリルによって穿孔するためその削り粉が外壁面に付
着してしまう。外壁面に付着した削り粉は完全に除去す
ることが非常に困難であり、次に塗布するラテックスモ
ルタルとの接着不良が生じやすい。
However, in such a conventional method for repairing a tile wall, as described above, a procedure is adopted in which a net is attached to the tile wall with latex mortar, and then a hole is punched and a pin is driven. Since the material is hardened by drilling, the shavings adhere to the outer wall surface. It is very difficult to completely remove the shavings adhering to the outer wall surface, and poor adhesion to the latex mortar to be applied next tends to occur.

【0004】また、前記ネットはこれを張付けるための
ラテックスモルタル内に埋設されるため、ピン打込み用
の孔部を形成すべくドリリングする際にネットを切断し
てしまうおそれがあり、このようにネットが切断される
と補修壁面の強度が著しく低下してしまうという各種課
題があった。
Further, since the net is buried in latex mortar for attaching the net, the net may be cut when drilling to form a hole for driving a pin. When the net was cut, there were various problems that the strength of the repair wall surface was significantly reduced.

【0005】またこのような課題は、ネットを用いた上
でピンをメカニカルアンカーとして躯体側に打ち込む構
成の仕上げ面形成方法及び仕上げ面構造では常につきま
とう問題点であり、従って上述したような補修の場合に
限らず、仕上げ面を改修する際や新設のコンクリート構
造物に仕上げを施す場合にあっても同様に問題となって
いた。
[0005] Further, such a problem is always a problem in a finished surface forming method and a finished surface structure in which a net is used and a pin is driven into a skeleton side as a mechanical anchor. Not only in the case, but also when refining a finished surface or when finishing a newly-constructed concrete structure, there has been a similar problem.

【0006】そこで、本発明はかかる従来の課題に鑑み
て、メカニカルアンカーとネットとを併用して仕上げ面
を形成する場合に、メカニカルアンカーの取り付けに際
して、穿孔による削り粉が接着の障害となることを防止
できるようにするとともに、ネットが傷つくことを防止
できるようにした仕上げ面の施工方法及び仕上げ面構造
を提供することを目的とする。
In view of the above-mentioned problems, the present invention is based on the problem that when a mechanical anchor and a net are used in combination to form a finished surface, shavings due to perforations may hinder the adhesion when the mechanical anchor is attached. It is an object of the present invention to provide a finishing surface construction method and a finished surface structure that can prevent the net from being damaged.

【0007】[0007]

【課題を解決するための手段】かかる目的を達成するた
めに本発明の請求項1の仕上げ面の施工方法は、コンク
リート構造物の表面を仕上げるに際して、施工対象面に
形成した穴部に、分離可能な埋め込み部材と押さえ部材
とからなるメカニカルアンカーの該埋め込み部材を挿入
し、次いで上記施工対象面に塗り仕上げ層を形成し、そ
の後該塗り仕上げ層の表面に、表裏に立毛部を有する3
次元構造のネットを、その裏面側立毛部を該塗り仕上げ
層に埋め込み、表面側立毛部を露出させて張り付け、次
いで上記ネットの表面側から網目を介して上記メカニカ
ルアンカーの上記押さえ部材を上記埋め込み部材に固定
して該押さえ部材で該ネットを押さえ、その後該ネット
上にその表面側立毛部を介して仕上げ層を形成するよう
にしたことを特徴とする。
According to a first aspect of the present invention, there is provided a method for constructing a finished surface, comprising the steps of: forming a hole in a surface formed on a surface to be constructed; Inserting the embedded member of the mechanical anchor composed of a possible embedded member and a holding member, then forming a coating finish layer on the surface to be applied, and then having a raised portion on the front and back of the surface of the coating finish layer
A net having a three-dimensional structure is embedded in the back layer on the back side of the coating layer, and the upper layer is exposed and attached. Then, the holding member of the mechanical anchor is embedded through the mesh from the front side of the net. The net is fixed to a member and the net is held down by the holding member, and thereafter, a finishing layer is formed on the net via a raised portion on the surface side.

【0008】請求項1の発明にあっては、埋め込み部材
と押さえ部材とが分離可能なメカニカルアンカーを用
い、施工対象面に形成した穴部に埋め込み部材を挿入し
た後に塗り仕上げ層を介して3次元構造のネットを張付
け、その後このネットの網目から前記メカニカルアンカ
ーの押さえ部材を前記埋め込み部材に固定するようにな
っている。つまり、前記ネットを張付ける以前に施工対
象面に穴部を確保しておいて、この穴部にメカニカルア
ンカーの埋め込み部材を挿入しておくことができるた
め、メカニカルアンカーの施工対象面への取り付けに際
してネットを傷付けてしまうことを確実に防止すること
ができる。また、前記穴部を形成した後に塗り仕上げ層
を形成するので、この塗り仕上げ層を形成する以前に、
施工対象面を十分にクリーニングしておくこともでき、
すなわち施工対象面が汚れている場合にもこれを容易か
つきれいに除去することができて、塗り仕上げ層の施工
対象面への接着性を著しく向上することができる。
According to the first aspect of the present invention, a mechanical anchor capable of separating an embedding member and a pressing member is used. A net having a three-dimensional structure is attached, and then the holding member of the mechanical anchor is fixed to the embedding member from the mesh of the net. That is, a hole is secured in the surface to be installed before the net is attached, and the embedded member of the mechanical anchor can be inserted into this hole, so that the mechanical anchor can be attached to the surface to be installed. In this case, it is possible to reliably prevent the net from being damaged. In addition, since the coating finish layer is formed after the formation of the hole portion, before forming the coating finish layer,
You can also clean the construction surface sufficiently,
That is, even when the surface to be applied is dirty, it can be easily and neatly removed, and the adhesion of the coating layer to the surface to be applied can be significantly improved.

【0009】また、上記構成の3次元構造のネットを用
い、裏面側立毛部を塗り仕上げ層に埋め込んで当該ネッ
トを施工対象面側に定着させる一方で、表面側立毛部を
介して当該ネット上に仕上げ層を施工するようにしたの
で、施工対象面側から順次重ねるようにして各層を形成
していくだけでネット表裏の立毛部によって各層同士の
十分な付着を確保して施工することができる。
In addition, while using the three-dimensionally structured net having the above-described structure, the back-side raised portion is embedded in the painted layer to fix the net on the construction target surface side, while the net is fixed on the net via the front-side raised portion. Since the finishing layer is formed on the surface of the net, the layers can be formed so as to be stacked sequentially from the surface to be processed.

【0010】本発明の請求項2の仕上げ面の施工方法
は、請求項1に記載の仕上げ面の施工方法であって、前
記メカニカルアンカーの前記埋め込み部材には前記押さ
え部材を固定するための孔部を形成しておき、前記施工
対象面に塗り仕上げ層を形成する前に、上記埋め込み部
材の孔部にこれを塞ぐための着脱自在なキャップを装着
するようにし、上記押さえ部材を上記埋め込み部材に固
定する際にこのキャップを取り外すようにしたことを特
徴とする。
According to a second aspect of the present invention, there is provided the method of constructing a finished surface according to the first aspect, wherein the embedded member of the mechanical anchor has a hole for fixing the holding member. Before forming a coating finish layer on the surface to be applied, a removable cap for closing the hole is filled in the hole of the embedding member, and the holding member is attached to the embedding member. The cap is detached when it is fixed to the housing.

【0011】請求項2の発明にあっては、埋め込み部材
に押さえ部材を固定するための孔部を形成し、施工対象
面に対して塗り仕上げ層を形成する前に埋め込み部材の
孔部にこれを塞ぐための着脱自在なキャップを装着し、
押さえ部材を埋め込み部材に固定する際にこのキャップ
を取り外すようにしていて、押さえ部材の埋め込み部材
への固定を孔部によって容易化する一方で、この孔部に
は着脱自在なキャップを装着して塗り仕上げ層の形成時
に孔部が塞がれるのを防止するとともに、押さえ部材を
埋め込み部材に装着する際に目印ともなるようにしてい
る。
According to the second aspect of the present invention, a hole for fixing the holding member is formed in the embedding member, and the hole is formed in the hole of the embedding member before forming the coating finish layer on the surface to be applied. With a removable cap to cover the
This cap is removed when the holding member is fixed to the embedded member, and the fixing of the holding member to the embedded member is facilitated by the hole, while the removable cap is attached to this hole. The hole is prevented from being closed at the time of forming the coating finish layer, and also serves as a mark when the holding member is mounted on the embedding member.

【0012】本発明の請求項3の仕上げ面構造は、コン
クリート構造物表面の仕上げ構造において、施工対象面
に形成した穴部に、分離可能な埋め込み部材と押さえ部
材とからなるメカニカルアンカーの該埋め込み部材を挿
入し、該埋め込み部材を挿入した上記施工対象面に塗り
仕上げ層を形成し、該塗り仕上げ層の表面に、表裏に立
毛部を有する3次元構造のネットを、その裏面側立毛部
を該塗り仕上げ層に埋め込み、表面側立毛部を露出させ
て張り付けるとともに、上記ネットの表面側から網目を
介して上記メカニカルアンカーの上記押さえ部材を上記
埋め込み部材に固定して該押さえ部材で該ネットを押さ
え、該ネット上にその表面側立毛部を介して仕上げ層を
形成したことを特徴とする。
According to a third aspect of the present invention, in the finishing structure for the surface of a concrete structure, a mechanical anchor including a separable embedding member and a pressing member is embedded in a hole formed in a construction target surface. A member is inserted, a coating finish layer is formed on the construction target surface where the embedded member is inserted, and a three-dimensional structure net having raised portions on the front and back surfaces on the surface of the coated finish layer, and a back-side raised portion is formed. It is embedded in the coating finish layer, and the surface-side raised portion is exposed and attached. The pressing member of the mechanical anchor is fixed to the embedding member via a mesh from the surface side of the net, and the net is fixed by the pressing member. , And a finishing layer is formed on the net via the napped portion on the surface side.

【0013】請求項3の発明は、請求項1の施工方法に
よって構成される仕上げ面構造であって、前記ネットを
張付ける以前に施工対象面の穴部にメカニカルアンカー
の埋め込み部材を挿入しておくことができる構造である
ため、メカニカルアンカーの施工対象面への取り付けに
際してネットを傷付けてしまうことを確実に防止するこ
とができる。また、前記穴部を形成した後に塗り仕上げ
層を形成する構造であるので、この塗り仕上げ層を形成
する以前に、施工対象面を十分にクリーニングしておく
こともでき、すなわち施工対象面が汚れている場合にも
これを容易かつきれいに除去することができて、塗り仕
上げ層と施工対象面との接着性を著しく向上することが
できる。
According to a third aspect of the present invention, there is provided a finished surface structure constituted by the construction method according to the first aspect, wherein a embedment member of a mechanical anchor is inserted into a hole of a construction target surface before the net is attached. Since the structure can be placed, it is possible to reliably prevent the net from being damaged when the mechanical anchor is attached to the construction target surface. Further, since the structure is such that the coating layer is formed after the hole is formed, the surface to be applied can be sufficiently cleaned before forming the coating layer. In this case, it can be easily and cleanly removed, and the adhesiveness between the painted layer and the construction target surface can be significantly improved.

【0014】また、上記構成の3次元構造のネットを用
い、裏面側立毛部を塗り仕上げ層に埋め込んで当該ネッ
トを施工対象面側に定着させる一方で、表面側立毛部を
介して当該ネット上に仕上げ層を施工するようにしたの
で、ネット表裏の立毛部によって仕上げ層の塗り仕上げ
層からの剥離、ひいては施工対象面からの剥離を確実に
防止することができる。
Further, using the three-dimensionally structured net having the above-mentioned structure, the back-side raised portion is embedded in the painted finishing layer to fix the net on the construction target surface side, while the net is fixed on the net via the front-side raised portion. Since the finishing layer is applied to the surface, the raised portions on the front and back surfaces of the net can reliably prevent the finishing layer from peeling off from the coating finishing layer and eventually from the construction target surface.

【0015】本発明の請求項4の仕上げ面構造は、請求
項3に記載の仕上げ面構造であって、前記ネットは、耐
アルカリ性を有する繊維を素材として、平面の縦横方向
およびその表裏の厚さ方向に繊維を配向させて織布ある
いは編布とした立毛3次元構造であることを特徴とす
る。
The finished surface structure according to a fourth aspect of the present invention is the finished surface structure according to the third aspect, wherein the net is made of an alkali-resistant fiber as a material, and has a thickness in the vertical and horizontal directions of the plane and the thickness of the front and back surfaces thereof. It is characterized by a three-dimensional raised structure in which the fibers are oriented in the vertical direction to form a woven or knitted fabric.

【0016】請求項4の発明は、上記構成のネットを用
いたので、平面の縦横方向の繊維で仕上げ層のひび割れ
を防止できると共に、表裏の厚さ方向の繊維で仕上げ層
の塗り仕上げ層からの剥離、ひいては施工対象面からの
剥離を確実に防止することができ、またこの繊維を、耐
アルカリ性を有する素材としていることから、コンクリ
ート構造物表面に発生するアルカリ成分に対して十分な
耐久性を発揮し、このネットによる剥離防止効果を長期
にわたって確実に維持することができる。
According to the fourth aspect of the present invention, since the net having the above structure is used, it is possible to prevent the finishing layer from cracking with the fibers in the vertical and horizontal directions of the plane, and to use the fibers in the thickness direction on the front and back to change the finish of the finishing layer. The fiber is made of a material that is resistant to alkali, so it has sufficient durability against alkali components generated on the surface of concrete structures. And the effect of preventing peeling by the net can be reliably maintained for a long period of time.

【0017】本発明の請求項5の仕上げ面の施工方法
は、補修・改修しようとするコンクリート構造物の既存
仕上げ面に穴部を穿設し、この穴部に分離可能な埋め込
み部材と押さえ部材とからなるメカニカルアンカーの該
埋め込み部材を挿入し、次いで上記既存仕上げ面にポリ
マーセメントモルタルで塗り仕上げ層を形成し、その後
該塗り仕上げ層の表面に、表裏に立毛部を有する3次元
構造のネットを、その裏面側立毛部を該塗り仕上げ層に
埋め込み、表面側立毛部を露出させて張り付け、次いで
上記ネットの表面側から網目を介して上記メカニカルア
ンカーの上記押さえ部材を上記埋め込み部材に固定して
該押さえ部材で該ネットを押さえ、その後該ネット上に
その表面側立毛部を介して塗り仕上げやタイル張りなど
の仕上げ層を形成するようにしたことを特徴とする。
According to a fifth aspect of the present invention, there is provided a method of constructing a finished surface, wherein a hole is formed in an existing finished surface of a concrete structure to be repaired / repaired, and an embedding member and a holding member which can be separated into the hole. Then, the embedded member of the mechanical anchor is inserted, and then a finish layer is formed on the existing finish surface with polymer cement mortar. Then, a three-dimensional structure net having raised portions on the front and back surfaces is formed on the surface of the finish layer. Embedded in the back layer on the coated layer, exposing the front-side raised portion, and then fixing the holding member of the mechanical anchor to the embedded member through a mesh from the front side of the net. And press the net with the pressing member, and then form a finishing layer such as painting or tiling on the net via the raised portion on the surface side. Characterized in that way the.

【0018】請求項5の発明は、請求項1の仕上げ面の
施工方法を、補修・改修しようとするコンクリート構造
物の既存仕上げ面に適用する場合であって、この場合に
は既存仕上げ面には一般に穴部がないので、先行してメ
カニカルアンカーの埋め込み部材を挿入するための穴部
を既存仕上げ面に穿設するようにする。穴部が存在する
場合には、請求項1の施工方法による。したがって、穿
孔作業の後は請求項1の施工方法と同様であって、埋め
込み部材と押さえ部材とが分離可能なメカニカルアンカ
ーを用い、既存仕上げ面に形成した穴部に埋め込み部材
を挿入した後に、当該既存仕上げ面であっても接着性能
の良好なポリマーセメントモルタルによる塗り仕上げ層
を形成し、その上に3次元構造のネットを張付け、その
後このネットの網目から前記メカニカルアンカーの押さ
え部材を前記埋め込み部材に固定するようになってい
る。当該請求項5の発明にあっても、メカニカルアンカ
ーの既存仕上げ面への取り付けに際してネットを傷付け
てしまうことを確実に防止することができる。また、前
記穴部を形成した後に塗り仕上げ層を形成するので、こ
の塗り仕上げ層を形成する以前に、既存仕上げ面を十分
にクリーニングしておくこともでき、すなわち既存仕上
げ面が汚れている場合にもこれを容易かつきれいに除去
することができて、塗り仕上げ層の既存仕上げ面への接
着性を著しく向上することができる。
According to a fifth aspect of the present invention, there is provided a method for applying the method for constructing a finished surface according to the first aspect to an existing finished surface of a concrete structure to be repaired or repaired. Since there is generally no hole, a hole for inserting the embedded member of the mechanical anchor is formed in the existing finished surface in advance. When a hole exists, the construction method according to claim 1 is used. Therefore, after the drilling operation is the same as the construction method of claim 1, using a mechanical anchor in which the embedded member and the pressing member can be separated, after inserting the embedded member into the hole formed in the existing finished surface, A coating layer of polymer cement mortar with good adhesion performance is formed even on the existing finished surface, a three-dimensional structure net is stuck thereon, and then the holding member of the mechanical anchor is embedded from the mesh of the net. It is designed to be fixed to a member. According to the invention of claim 5, it is possible to reliably prevent the net from being damaged when the mechanical anchor is attached to the existing finished surface. Further, since the coating finish layer is formed after the formation of the hole, the existing finish surface can be sufficiently cleaned before forming the coating finish layer, that is, when the existing finish surface is dirty. In addition, this can be easily and neatly removed, and the adhesion of the applied finishing layer to the existing finished surface can be significantly improved.

【0019】また、上記構成の3次元構造のネットを用
いたので、既存仕上げ面側から順次重ねるようにして各
層を形成していくだけでネット表裏の立毛部によって各
層同士の十分な付着を確保して施工することができる。
Further, since the three-dimensional net having the above-described structure is used, it is only necessary to form each layer in such a manner that the layers are sequentially stacked from the existing finished surface side, so that the napped portions on the front and back of the net ensure sufficient adhesion between the layers. Can be constructed.

【0020】本発明の請求項6の仕上げ面の施工方法
は、請求項5に記載の仕上げ面の施工方法であって、前
記既存仕上げ面に前記穴部を穿設した後で該既存仕上げ
面に塗り仕上げ層を形成する前に、この既存仕上げ面を
クリーニングするようにしたことを特徴とする。
According to a sixth aspect of the present invention, there is provided a method of constructing a finished surface according to the fifth aspect of the present invention, wherein the hole is formed in the existing finished surface. The method is characterized in that the existing finished surface is cleaned before forming a coating finish layer.

【0021】請求項6の発明は、既存仕上げ面に穴部を
穿設した後でかつ既存仕上げ面に塗り仕上げ層を形成す
る前に、当該既存仕上げ面をクリーニングするので、塗
り仕上げ層の既存仕上げ面への接着性をさらに向上する
ことができる。
According to the present invention, the existing finished surface is cleaned after the hole is formed in the existing finished surface and before the coating finished layer is formed on the existing finished surface. Adhesion to the finished surface can be further improved.

【0022】本発明の請求項7の仕上げ面の施工方法
は、新設のコンクリート構造物の仕上げ面に予め穴部を
形成し、この穴部に分離可能な埋め込み部材と押さえ部
材とからなるメカニカルアンカーの該埋め込み部材を挿
入し、次いで上記仕上げ面に下地モルタル層を形成し、
その後該下地モルタル層の表面に、表裏に立毛部を有す
る3次元構造のネットを、その裏面側立毛部を該下地モ
ルタル層側に埋め込み、表面側立毛部を露出させて張り
付け、次いで上記ネットの表面側から網目を介して上記
メカニカルアンカーの上記押さえ部材を上記埋め込み部
材に固定して該押さえ部材で該ネットを押さえ、その後
該ネット上にその表面側立毛部を介して塗り仕上げやタ
イル張りなどの仕上げ層を形成するようにしたことを特
徴とする。
According to a seventh aspect of the present invention, there is provided a method for constructing a finished surface, comprising the steps of: forming a hole in the finished surface of a new concrete structure in advance; Inserting the embedding member of, then forming a base mortar layer on the finished surface,
Thereafter, on the surface of the underlying mortar layer, a net having a three-dimensional structure having raised portions on the front and back sides is embedded with the raised portion on the back surface side of the underlying mortar layer, and the exposed portion on the front side is exposed and adhered. The holding member of the mechanical anchor is fixed to the embedding member via the mesh from the surface side to hold the net with the holding member, and then the net is coated or tiled on the net via the surface side raised portion. Characterized in that a finished layer is formed.

【0023】請求項7の発明は、請求項1の仕上げ面の
施工方法を新設のコンクリート構造物の仕上げ面に適用
する場合であり、メカニカルアンカーの埋め込み部材を
挿入するための穴部を確保した後は請求項1の施工方法
と同様であって、メカニカルアンカーの埋め込み部材を
穴部に挿入しておくことができるため、メカニカルアン
カーの仕上げ面への取り付けに際してネットを傷付けて
しまうことを確実に防止することができる。また、前記
穴部を形成した後に下地モルタル層を形成するので、こ
の下地モルタル層を形成する以前に、仕上げ面を十分に
クリーニングしておくこともでき、すなわち仕上げ面が
汚れている場合にもこれを容易かつきれいに除去するこ
とができて、下地モルタル層の仕上げ面への接着性を著
しく向上することができる。
According to a seventh aspect of the present invention, there is provided a method of applying the method of constructing a finished surface according to the first aspect to a finished surface of a new concrete structure, wherein a hole for inserting a buried member of a mechanical anchor is secured. The rest is the same as the construction method of claim 1, and the embedded member of the mechanical anchor can be inserted into the hole, so that the net is surely damaged when the mechanical anchor is attached to the finished surface. Can be prevented. Further, since the base mortar layer is formed after the formation of the hole, the finished surface can be sufficiently cleaned before forming the base mortar layer, that is, even when the finished surface is dirty. This can be easily and cleanly removed, and the adhesion of the underlying mortar layer to the finished surface can be significantly improved.

【0024】また、上記構成の3次元構造のネットを用
いているので、仕上げ面側から順次重ねるようにして下
地モルタル層や仕上げ層を形成していくだけでネット表
裏の立毛部によって各層同士の十分な付着を確保して施
工することができる。
Further, since the three-dimensional structure net having the above structure is used, the base mortar layer and the finishing layer are formed sequentially so as to be sequentially stacked from the finishing surface side. It is possible to secure the proper adhesion.

【0025】[0025]

【発明の実施の形態】以下、本発明の好適な実施形態
を、添付図面を参照して詳細に説明する。図1から図3
は本発明にかかる仕上げ面の施工方法及び仕上げ面構造
を、補修・改修しようとするコンクリート構造物の既存
仕上げ面に適用した場合の実施形態を示し、図1は補修
・改修を完了した既存壁の断面図、図2は本実施形態に
用いられるメカニカルアンカーおよびそのキャップを示
す図、図3は本実施形態に用いられる3次元構造のネッ
トの要部拡大図である。
Preferred embodiments of the present invention will be described below in detail with reference to the accompanying drawings. 1 to 3
FIG. 1 shows an embodiment in which the method for applying a finished surface and the finished surface structure according to the present invention are applied to an existing finished surface of a concrete structure to be repaired / repaired, and FIG. 1 shows an existing wall after the repair / repair is completed. FIG. 2 is a diagram showing a mechanical anchor and its cap used in the present embodiment, and FIG. 3 is an enlarged view of a main part of a three-dimensional structure net used in the present embodiment.

【0026】即ち、本実施形態の補修・改修しようとす
るコンクリート製既存壁10には、図1に示すように外
壁の本体部分12表面に形成した下塗り層14と、この
下塗り層14にモルタル16を介して張付けたタイル1
8とによって構成される既存仕上げ層20が設けられて
いる。そして、剥離による前記タイル18の落下を防止
するために、前記既存仕上げ層20を施工対象面として
その表面に改修若しくは補修による新たな改修層22が
本発明によって設けられる。
That is, as shown in FIG. 1, an existing concrete wall 10 to be repaired / repaired according to the present embodiment has an undercoat layer 14 formed on the surface of the main body 12 of the outer wall, and a mortar 16 Tile 1 pasted through
8 is provided. In order to prevent the tile 18 from dropping due to peeling, a new repair layer 22 is provided on the surface of the existing finish layer 20 by repair or repair according to the present invention.

【0027】前記改修層22は、前記タイル18の表面
に塗布されるポリマーセメントモルタルなどによる塗り
仕上げ層24と、この塗り仕上げ層24に対して張付け
られる立毛3次元ネット26と、この立毛3次元ネット
26の表面に塗布される上塗りモルタルなどの塗り仕上
げによる仕上げ層28と、この仕上げ層28の表面に塗
布される高耐候性塗料30とからなり、前記立毛3次元
ネット26はメカニカルアンカー32によって外壁本体
部分12に押付けて取り付けられるようになっている。
The repair layer 22 includes a finish layer 24 made of polymer cement mortar or the like applied to the surface of the tile 18, a three-dimensional raised net 26 attached to the finish layer 24, and a three-dimensional raised hair 3. The surface of the net 26 is composed of a finishing layer 28 formed by applying a finish such as overcoating mortar, and a highly weather-resistant paint 30 applied to the surface of the finishing layer 28. The outer wall body portion 12 is attached by being pressed.

【0028】メカニカルアンカー32は図2に示すよう
に傾斜機能型のものが用いられ、このメカニカルアンカ
ー32は埋め込み部材である軸部32aと押さえ部材で
ある大径円板状の座部32bとに分離可能となってお
り、座部32b中央の孔を介して軸部32aに形成され
た軸孔32cにネジ32dを螺入することにより、座部
32bが軸部32aに固定されて、両者が一体化される
ようになっている。
As shown in FIG. 2, the mechanical anchor 32 is of a tilt function type. The mechanical anchor 32 has a shaft portion 32a as an embedding member and a large-diameter disk-shaped seat portion 32b as a pressing member. The seat 32b is fixed to the shaft 32a by screwing a screw 32d into a shaft hole 32c formed in the shaft 32a through a hole in the center of the seat 32b. It is designed to be integrated.

【0029】また、立毛3次元ネット26は図3に示す
ように、耐アルカリ性を有する繊維26aを素材とし
て、平面の縦横方向(X軸,Y軸方向)およびその表裏
の厚さ方向(Z軸方向)に繊維26aを配向させて織布
あるいは編布としたものである。表裏の厚さ方向に配向
させた繊維26aについては、同図(a)のようにその
先端部に球状ないしは鍔状頭部26bを形成したり、ま
た同図(b)のようにループ状部分26cを形成したり
して、塗り仕上げ層24および仕上げ層28に十分に付
着させて、確実なアンカー効果を得ることができるよう
になっている。
As shown in FIG. 3, the napped three-dimensional net 26 is made of alkali-resistant fiber 26a as a material, and has a vertical and horizontal direction (X-axis, Y-axis direction) and a thickness direction (Z-axis) on its front and back sides. Direction), the fibers 26a are oriented to form a woven or knitted fabric. Regarding the fiber 26a oriented in the thickness direction of the front and back sides, a spherical or flange-like head 26b is formed at the tip end as shown in FIG. For example, by forming 26c and sufficiently adhering it to the coating finishing layer 24 and the finishing layer 28, a reliable anchor effect can be obtained.

【0030】ところで、前記改修層22を形成するにあ
たっては、まず、既存仕上げ層20の表面、つまりタイ
ル18の表面からメカニカルアンカー32を打ち込むた
めの墨出しを行い、この墨出しに沿ってドリリングによ
り多数の穴部34を穿設する。この穿設時には多量の削
り粉が出てタイル18表面に付着するが、これら穴部3
4を形成した後、前記タイル18の表面に放水するなど
してクリーニングする。
When the repair layer 22 is formed, first, blacking for driving the mechanical anchor 32 is performed from the surface of the existing finishing layer 20, that is, the surface of the tile 18, and drilling is performed along the blacking. A number of holes 34 are drilled. At the time of drilling, a large amount of shavings comes out and adheres to the surface of the tile 18.
After forming 4, the surface of the tile 18 is cleaned by, for example, discharging water.

【0031】その後、前記穴部34に前記メカニカルア
ンカー32の軸部32aを打込む。軸部32aを打込む
際には、この軸部32aの頭部が前記塗り仕上げ層24
の厚み分だけタイル18表面から突出するようにする。
また、前記軸部32aを打込んだ状態で、軸孔32cか
ら穴部34内に接着剤を注入しておく。次いでこの軸部
32aの軸孔32cに、これを塞ぐための着脱自在なキ
ャップ36を装着する。このキャップ36は図2に示し
たように、頭部が太径なニードル状に形成され、軸孔3
2cに嵌入されてこれを塞ぎ、塗り仕上げ層24の施工
にあたって、軸孔32cが目詰まりするのを防止するよ
うになっている。キャップ36を装着した後に、タイル
18表面に寸法安定性に優れた低収縮ポリマーセンメン
トモルタルを吹付けて塗り仕上げ層24を形成する。
Thereafter, the shaft 32a of the mechanical anchor 32 is driven into the hole 34. When the shaft 32a is driven, the head of the shaft 32a is
Of the tile 18 from the surface of the tile 18.
Further, with the shaft portion 32a being driven, an adhesive is injected into the hole portion 34 from the shaft hole 32c. Next, a removable cap 36 for closing the shaft hole 32c of the shaft portion 32a is attached. As shown in FIG. 2, the cap 36 is formed in a needle shape with a large diameter head, and
The shaft hole 32c is inserted into the plug 2c and closed to prevent the shaft hole 32c from being clogged when the coating finish layer 24 is applied. After the cap 36 is attached, a low shrinkage polymer cement mortar having excellent dimensional stability is sprayed on the surface of the tile 18 to form the painted finish layer 24.

【0032】塗り仕上げ層24を施工したならばこの表
面に前記立毛3次元ネット26を張付ける。この際、ネ
ット26の裏面側立毛部を塗り仕上げ層24中に埋め込
むようにするとともに、表面側立毛部を外側に露出させ
て張り付けるようにする。そして、前記立毛3次元ネッ
ト26を張付けた後、メカニカルアンカー32の軸孔3
2cを塞いでいた目印のキャップ36を取り外し、ネッ
ト26の表面側から前記メカニカルアンカー32の座部
32bを押し当てて、ネジ32dを立毛3次元ネット2
6の網目を介して軸部32aに嵌入して固定する。この
状態で前記立毛3次元ネット26は前記座部32bによ
って既存壁10に対して押え付けられることになり、そ
の後、ネット26の表面側立毛部に対して前記仕上げ層
28を施工するとともに、前記高耐候性塗料30を施工
する。前記高耐候性塗料30に代えてタイルを張付ける
こともできる。
After the finishing layer 24 has been applied, the three-dimensional raised net 26 is attached to this surface. At this time, the rear-side raised portion of the net 26 is embedded in the coating finish layer 24, and the front-side raised portion is exposed to the outside and attached. Then, after attaching the above-mentioned three-dimensional net 26, the shaft hole 3 of the mechanical anchor 32 is formed.
The cap 36 of the mark which closed the 2c is removed, the seat 32b of the mechanical anchor 32 is pressed from the surface side of the net 26, and the screw 32d is screwed to the napped three-dimensional net 2.
6 and fit into the shaft portion 32a through the mesh. In this state, the napped three-dimensional net 26 is pressed against the existing wall 10 by the seat portion 32b. Thereafter, the finishing layer 28 is applied to the napped surface on the front side of the net 26. A high weather resistance paint 30 is applied. Instead of the highly weather-resistant paint 30, a tile can be attached.

【0033】以上の本実施形態の補修・改修に係る仕上
げ面の施工方法及び仕上げ面構造は要するに、既存壁1
0のタイル18表面に穴部34を形成し、この穴部34
にメカニカルアンカー32の軸部32aを打込んだ後に
塗り仕上げ層24によって立毛3次元ネット26を張付
け、次いでこのネット26の網目からネジ32dを差し
込んで軸部32aに嵌入することにより、前記メカニカ
ルアンカー32の座部32bを前記軸部32aに固定す
るようにしている。したがって本実施形態では、前記立
毛3次元ネット26を張付ける以前にメカニカルアンカ
ー32の軸部32aを打込み、座部32bを軸部32a
に固定する際には立毛3次元ネット26を確認しつつ作
業を行うことができるため、この立毛3次元ネット26
が傷付くことを確実に防止することができる。したがっ
て、ネット26が切断されると補修・改修壁面の強度が
著しく低下してしまうという課題を確実に防ぐことがで
きる。
The construction method of the finished surface and the finished surface structure related to the repair / renovation of the present embodiment are basically the same as those of the existing wall 1.
0, a hole 34 is formed in the surface of the tile 18.
After the shaft portion 32a of the mechanical anchor 32 is driven into the mechanical anchor 32, the three-dimensional raised net 26 is stuck by the coating finish layer 24, and then a screw 32d is inserted from the mesh of the net 26 and fitted into the shaft portion 32a, thereby obtaining the mechanical anchor. The 32 seats 32b are fixed to the shaft 32a. Therefore, in this embodiment, the shaft 32a of the mechanical anchor 32 is driven before the three-dimensional raised net 26 is attached, and the seat 32b is moved to the shaft 32a.
When fixing to the three-dimensional net 26, it is possible to work while checking the three-dimensional net 26.
Can be reliably prevented from being damaged. Therefore, it is possible to reliably prevent the problem that the strength of the repair / repair wall surface is significantly reduced when the net 26 is cut.

【0034】また、前記穴部34を形成した後に前記立
毛3次元ネット26を張付けるための塗り仕上げ層24
を形成するので、この塗り仕上げ層24を施工する以前
にタイル18表面をクリーニングすることができ、穴部
34を形成した際の削り粉を容易にかつきれいに除去す
ることができる。このため、前記塗り仕上げ層24の既
存仕上げ層20に対する接着性を著しく向上でき、ひい
ては補修・改修面の強度を著しく増大することができ
る。
After the formation of the holes 34, the coating layer 24 for attaching the three-dimensional raised hairs 26 is provided.
Is formed, the surface of the tile 18 can be cleaned before applying the coating finish layer 24, and the shavings generated when the holes 34 are formed can be easily and cleanly removed. For this reason, the adhesiveness of the coating finishing layer 24 to the existing finishing layer 20 can be significantly improved, and the strength of the repaired / repaired surface can be significantly increased.

【0035】更に、本実施形態ではネットとして、平面
の縦横方向および厚さ方向に繊維26aを配向させて織
布若しくは編布とした前記立毛3次元ネット26を用い
たので、縦横方向の繊維26aで仕上げ層28のひび割
れを防止できると共に、表裏の厚さ方向の繊維26aで
仕上げ層28の塗り仕上げ層24からの剥離、ひいては
既存壁10からの剥離を確実に防止することができると
ともに、特にこの繊維26aを耐アルカリ性を有する素
材としていることから、コンクリート表面に発生するア
ルカリ成分に対して十分な耐久性を発揮し、このネット
26による剥離防止効果を長期にわたって確実に維持す
ることができる。
Further, in the present embodiment, the three-dimensional napping net 26 is used as a woven or knitted fabric by orienting the fibers 26a in the vertical and horizontal directions of the plane and the thickness direction, so that the fibers 26a in the vertical and horizontal directions are used. In addition to being able to prevent the finishing layer 28 from cracking, the peeling of the finishing layer 28 from the coating finishing layer 24 and thus the existing wall 10 can be reliably prevented by the fibers 26a in the thickness direction of the front and back, and in particular Since the fiber 26a is made of a material having alkali resistance, the fiber 26a exhibits sufficient durability against alkali components generated on the concrete surface, and the effect of preventing the net 26 from peeling can be reliably maintained for a long time.

【0036】また、上述した3次元構造のネット26を
用い、裏面側立毛部を塗り仕上げ層24に埋め込んで当
該ネット26を既存壁10側に定着させる一方で、表面
側立毛部を介して当該ネット26上に仕上げ層28を施
工するようにしたので、既存壁10側から順次重ねるよ
うにして各層24,28を形成していくだけでネット2
6表裏の立毛部によって各層24,28同士の十分な付
着を確保しつつ施工することができる。
Further, using the above-described three-dimensionally structured net 26, the back-side raised portion is embedded in the finishing layer 24 to fix the net 26 to the existing wall 10 side, while the net 26 is fixed via the front-side raised portion. Since the finishing layer 28 is constructed on the net 26, the net 2 can be formed simply by forming the layers 24 and 28 so as to sequentially overlap the existing wall 10 side.
(6) With the napped portions on the front and back, the layers 24 and 28 can be constructed while ensuring sufficient adhesion between them.

【0037】さらに、メカニカルアンカー32に関し
て、軸部32aに座部32bを固定するための軸孔32
cを形成し、既存仕上げ層20に対して塗り仕上げ層2
4を形成する前に軸部32aの軸孔32cにこれを塞ぐ
ための着脱自在なキャップ36を装着し、座部32bを
軸部32aに固定する際にこのキャップ36を取り外す
ようにして、座部32bの軸部32aへの固定を軸孔3
2cによって容易化する一方で、この軸孔32cには着
脱自在なキャップ36を装着して塗り仕上げ層24の形
成時に軸孔32cが塞がれるのを防止するとともに、座
部32bを軸部32aに装着する際に目印ともなるよう
に用いることができ、良好な施工性を確保することがで
きる。
Further, regarding the mechanical anchor 32, a shaft hole 32 for fixing the seat portion 32b to the shaft portion 32a.
c to form a finish layer 2 on the existing finish layer 20
Before forming the seat 4, a detachable cap 36 for closing the shaft hole 32c of the shaft portion 32a is attached to the shaft portion 32a, and the cap 36 is removed when the seat portion 32b is fixed to the shaft portion 32a. Fixing the portion 32b to the shaft portion 32a
2c, a removable cap 36 is attached to the shaft hole 32c to prevent the shaft hole 32c from being closed at the time of forming the coating layer 24, and the seat portion 32b is connected to the shaft portion 32a. It can be used as a mark when it is mounted on a vehicle, and good workability can be secured.

【0038】図4から図6は本発明にかかる仕上げ面の
施工方法及び仕上げ面構造を新設のコンクリート壁に適
用した場合の実施形態を示し、図4は新設のコンクリー
ト壁の要部拡大断面図、図5は本実施形態の第1工程を
示す要部拡大断面図、図6は本実施形態の第2工程を示
す要部拡大断面図である。
FIGS. 4 to 6 show an embodiment in which the method for applying a finished surface and the finished surface structure according to the present invention are applied to a newly installed concrete wall. FIG. 4 is an enlarged sectional view of a main part of the newly installed concrete wall. FIG. 5 is an enlarged sectional view of a main part showing a first step of the embodiment, and FIG. 6 is an enlarged sectional view of a principal part showing a second step of the embodiment.

【0039】通常、新設のコンクリート壁40は、セパ
レータ42を介して間隔を隔てて設けた一対の合板型枠
間にコンクリートを現場打ちして形成され、したがって
コンクリート壁40の仕上げ面40aには、合板型枠と
セパレータ42とを結合するために設けられ、施工後コ
ンクリート壁40から取り外されるPコンと称されるセ
パレータ取付具の撤去跡が、あるいはコンクリート壁4
0内にそのまま埋め込まれるレジコン44と称されるセ
パレータ取付具の埋め込み跡が穴部46として存在す
る。この様子が第4図に示されている。そして本実施形
態では、この穴部46を利用して上記実施形態と同様な
メカニカルアンカー48を取り付けて仕上げ面の施工を
行うようになっている。まず、後述するメカニカルアン
カー48のパイプ48aをこの穴部46に装着するため
に、Pコンの場合には、これを撤去した穴部46内に突
出しているセパレータ42端部に螺合可能なナット部5
0aを有し、かつコンクリート壁40仕上げ面側の開口
を塞ぐ鍔部50bを一端に有する筒状のアタッチメント
50を準備し、これを穴部46に装着してセパレータ4
2に結合する。筒体状に形成されてコンクリート壁40
に埋め込まれるレジコン44の場合には、セパレータ4
2端部に螺合するナット部44aを有しているので、こ
れをそのまま利用する。以後の説明にあっては、レジコ
ン44を用いた場合を図5および図6に例示して説明す
るが、Pコンを撤去してアタッチメント50を装着した
場合にあっても同様に適用することができる。
Normally, a new concrete wall 40 is formed by casting concrete between a pair of plywood forms provided at intervals through a separator 42, so that the finished surface 40a of the concrete wall 40 has A removal mark of a separator fixture called P-con, which is provided to connect the plywood formwork and the separator 42 and is removed from the concrete wall 40 after construction, or the concrete wall 4
There is a hole 46 in which a separator mounting tool called a resin condenser 44 is directly embedded in the hole 0. This is shown in FIG. In the present embodiment, a mechanical anchor 48 similar to that of the above embodiment is attached by using the hole 46, and the finishing surface is constructed. First, in order to mount a pipe 48a of a mechanical anchor 48 to be described later in the hole 46, in the case of a P-con, a nut capable of being screwed to an end of the separator 42 protruding into the hole 46 from which it is removed. Part 5
0a and a cylindrical attachment 50 having at one end a flange 50b that closes the opening on the finished surface side of the concrete wall 40, is mounted in the hole 46, and
2 Concrete wall 40 formed in cylindrical shape
In the case of the cash register 44 embedded in the
Since it has the nut part 44a screwed to two ends, it is used as it is. In the following description, the case where the registration control 44 is used will be described with reference to FIGS. 5 and 6, but the same applies to the case where the P control is removed and the attachment 50 is attached. it can.

【0040】本実施形態のメカニカルアンカー48は、
分離可能な埋め込み部材としてのパイプ48aと押さえ
部材としての座部48bとから主に構成され、座部48
bは上記実施形態と同様にネジ52によってパイプ48
aに固定されるようになっている。
The mechanical anchor 48 of this embodiment is
It mainly comprises a pipe 48a as a separable embedded member and a seat 48b as a holding member.
b is the pipe 48 with the screw 52 as in the above embodiment.
a.

【0041】まずパイプ48aをレジコン44のナット
部44aにコンクリート壁40の仕上げ面側から挿入す
る。パイプ48aは、その内外周にネジ条が形成されて
いて、外周のネジ条によってレジコン44のナット部4
4aに螺入されるようになっている。その後、このパイ
プ48a内にその内周のネジ条を利用してさらに固定ビ
ス54を螺入して、レジコン44のナット部44aとの
間に挟んでパイプ48aをレジコン44に固定する。次
いで、コンクリート壁40の仕上げ面からこれに施工す
る左官下地モルタル層56の厚み相当分だけ突出させた
位置でパイプ48aを切断する。
First, the pipe 48a is inserted into the nut portion 44a of the register 44 from the finished surface side of the concrete wall 40. The pipe 48a has a thread formed on the inner and outer circumferences thereof, and the nut 4 on the resin cone 44 is formed by the outer circumference thread.
4a. Thereafter, a fixing screw 54 is further screwed into the pipe 48 a by using a screw thread on the inner circumference thereof, and the pipe 48 a is fixed to the register 44 with the nut 48 a between the nut 44 a of the register 44. Next, the pipe 48a is cut at a position protruding from the finished surface of the concrete wall 40 by the thickness of the plaster base mortar layer 56 to be applied thereto.

【0042】このようにしてメカニカルアンカー48の
パイプ48aの取り付けが完了したならば、左官下地モ
ルタル層56を施工する。次いで、この左官下地モルタ
ル層56の表面にネット張り付けモルタル58を施工
し、この張り付けモルタル層58に対して上記実施形態
と同様に上記立毛3次元ネット26を張り付ける。メカ
ニカルアンカー48の座部48bにはネジ52を接合し
ておき、ネット26の上から網目を介してパイプ48a
内にネジ52を螺入していくことで座部48bをパイプ
48aに固定するとともに、この座部48bでネット2
6を押さえる。その後、ネット26の表面側立毛部を利
用してこのネット26の上にタイル張り付けモルタル6
0を施工し、さらにタイル62を張り付けて仕上げ層6
4の施工を完了する。
When the attachment of the pipe 48a of the mechanical anchor 48 is completed in this way, the plaster base mortar layer 56 is applied. Next, a net attaching mortar 58 is applied to the surface of the plaster base mortar layer 56, and the three-dimensional raised net 26 is attached to the attaching mortar layer 58 as in the above embodiment. A screw 52 is joined to a seat portion 48b of the mechanical anchor 48, and a pipe 48a is inserted from above the net 26 through a mesh.
The seat 48b is fixed to the pipe 48a by screwing the screw 52 into the inside, and the net 48 is fixed by the seat 48b.
Hold down 6. After that, the mortar 6 is tiled on the net 26 by using the napped portion on the surface side of the net 26.
No. 0, and furthermore, the tile 62 is stuck and the finishing layer 6
4 is completed.

【0043】このような新設のコンクリート構造物の仕
上げ面に適用した実施形態であっても、上記実施形態と
同様にメカニカルアンカー48のパイプ48aを穴部4
6に挿入しておくことができるため、メカニカルアンカ
ー48の仕上げ面への取り付けに際してネット26を傷
付けてしまうことを確実に防止することができる。ま
た、前記穴部46を形成した後に左官下地モルタル層5
6を形成するので、この左官下地モルタル層56を形成
する以前に、仕上げ面を十分にクリーニングしておくこ
ともでき、すなわち仕上げ面が汚れている場合にもこれ
を容易かつきれいに除去することができて、左官下地モ
ルタル層56の仕上げ面40aへの接着性を著しく向上
することができる。
Even in the embodiment applied to the finished surface of such a newly-constructed concrete structure, the pipe 48a of the mechanical anchor 48 is connected to the hole 4 in the same manner as in the above embodiment.
6, the net 26 can be reliably prevented from being damaged when the mechanical anchor 48 is attached to the finished surface. After forming the hole 46, the plaster base mortar layer 5 is formed.
6, the finished surface can be sufficiently cleaned before forming the plastering base mortar layer 56. That is, even if the finished surface is dirty, it can be easily and cleanly removed. As a result, the adhesion of the plaster base mortar layer 56 to the finished surface 40a can be significantly improved.

【0044】また、上記構成の3次元構造のネット26
を用いているので、仕上げ面40a側から順次重ねるよ
うにして左官下地モルタル層56や仕上げ層64を形成
していくだけでネット26表裏の立毛部によって各層5
6,64同士の十分な付着を確保して施工することがで
きる。
Further, the net 26 having the three-dimensional structure having the above-described structure is used.
Is used, only by forming the plaster base mortar layer 56 and the finishing layer 64 so as to sequentially overlap from the finishing surface 40a side, each layer 5 is formed by the raised portions on the front and back of the net 26.
It is possible to secure the sufficient adhesion between the 6,64 and the construction.

【0045】図7から図9は本発明にかかる仕上げ面の
施工方法及び仕上げ面構造を新設のコンクリート壁に適
用した場合の他の実施形態を示し、図7は本実施形態の
第1工程を示す要部拡大断面図、図8は本実施形態の第
2工程を示す要部拡大断面図、図9は本実施形態の第3
工程を示す要部拡大断面図である。
FIGS. 7 to 9 show another embodiment in which the method for applying a finished surface and the finished surface structure according to the present invention are applied to a new concrete wall. FIG. 7 shows a first step of the present embodiment. FIG. 8 is an enlarged cross-sectional view of a main part showing a second step of the present embodiment, and FIG.
It is a principal part expanded sectional view which shows a process.

【0046】本実施形態にあっても、レジコン44やP
コンの埋め込み跡、撤去跡をメカニカルアンカー66用
の穴部46として利用していて、以後の説明にあって
は、レジコン44を用いた場合を図示して説明するが、
上記実施形態と同じようにPコンを撤去してアタッチメ
ント50を装着した場合にあっても同様に適用すること
ができる。
In the present embodiment, the registration control 44 and the P
The embedded traces and the removal traces of the condenser are used as the holes 46 for the mechanical anchor 66, and in the following description, the case where the resin condenser 44 is used is illustrated and described.
The same applies to the case where the P-con is removed and the attachment 50 is attached as in the above embodiment.

【0047】本実施形態のメカニカルアンカー66にあ
っても、分離可能な埋め込み部材としてのパイプ66a
と押さえ部材としての座部66bとから主に構成され、
座部66bは上記実施形態と同様にネジ52によってパ
イプ66aに固定されるようになっている。
Even in the mechanical anchor 66 of the present embodiment, the pipe 66a as a separable embedding member is used.
And a seat 66b as a holding member.
The seat 66b is fixed to the pipe 66a by the screw 52 similarly to the above embodiment.

【0048】まずパイプ66aをレジコン44のナット
部44aにコンクリート壁40の仕上げ面側から挿入す
る。本実施形態のパイプ66aは、レジコン44のナッ
ト部44aに螺入される基端部66cの外周にネジ条が
形成され、また長さ方向中央部の内周面にもネジ条が形
成され、他方先端部66dは漸次先細りに形成されると
ともにその周方向に適宜間隔を隔てて長さ方向に切り込
みが入れられていて、その尖端を切断すると径方向外方
へ萼様に広げることができるように形成され、さらにパ
イプ66aをレジコン44に固定した際に左官下地モル
タル層56の施工厚さ程度の突出位置には六角ナット6
6eが接合されている。
First, the pipe 66a is inserted into the nut portion 44a of the register 44 from the finished surface side of the concrete wall 40. In the pipe 66a of the present embodiment, a thread is formed on the outer periphery of the base end 66c that is screwed into the nut 44a of the register controller 44, and a thread is also formed on the inner peripheral surface at the center in the length direction. On the other hand, the tip 66d is gradually tapered and cut in the length direction at appropriate intervals in the circumferential direction so that when the tip is cut, it can be radially outwardly expanded like a calyx. When the pipe 66a is fixed to the register 44, the hex nut 6
6e is joined.

【0049】このように構成されたパイプ66aをレジ
コン44のナット部44aに螺合して固定したならば、
左官下地モルタル層56を施工する。次いで、この左官
下地モルタル層56の表面にネット張り付けモルタル5
8を施工し、この張り付けモルタル層58に対して上記
実施形態と同様に上記立毛3次元ネット26を張り付け
る。この際、ネット26の網目をパイプ66aの先端部
66dに通しながら張り付けるようにする。この状態で
上述したようにパイプ66aの尖端を切断し、先端部6
6dを広げてネット26に押しつける。メカニカルアン
カー66の座部66bにはネジ52を接合しておき、パ
イプ66a内にネジ52を螺入していくことで座部66
bをパイプ66aに固定するとともに、この座部66b
でネット26をさらに押さえる。その後、ネット26の
表面側立毛部を利用してこのネット26の上にタイル張
り付けモルタル60を施工し、さらにタイル62を張り
付けて仕上げ層64の施工を完了する。
If the pipe 66a constructed as described above is screwed and fixed to the nut 44a of the register 44,
Plasterer mortar layer 56 is constructed. Next, the mortar 5 is attached to the surface of the plaster base mortar layer 56 by a net.
8 and the three-dimensional raised net 26 is attached to the attaching mortar layer 58 in the same manner as in the above embodiment. At this time, the net 26 is stuck while passing the mesh through the end 66d of the pipe 66a. In this state, the tip of the pipe 66a is cut as described above,
6d is spread and pressed against the net 26. The screw 52 is joined to the seat 66b of the mechanical anchor 66, and the screw 52 is screwed into the pipe 66a to thereby provide the seat 66.
b is fixed to the pipe 66a, and the seat 66b
Press the net 26 further. Thereafter, a tile attaching mortar 60 is applied on the net 26 by using the raised portion on the surface side of the net 26, and the tile 62 is further attached on the net 26 to complete the application of the finishing layer 64.

【0050】本実施形態による新設のコンクリート構造
物の仕上げ面に適用した実施形態であっても、上記実施
形態と同様にメカニカルアンカー66の仕上げ面40a
への取り付けに際してネット26を傷付けてしまうこと
を確実に防止することができる。また、左官下地モルタ
ル層56を形成する以前に、仕上げ面40aを十分にク
リーニングしておくこともでき、左官下地モルタル層5
6の仕上げ面40aへの接着性を著しく向上することが
できる。
Even in the embodiment applied to the finished surface of a new concrete structure according to this embodiment, the finished surface 40a of the mechanical anchor 66 is similar to the above embodiment.
It is possible to reliably prevent the net 26 from being damaged at the time of attachment to the device. Further, before forming the plastering base mortar layer 56, the finished surface 40a can be sufficiently cleaned.
6 can significantly improve the adhesion to the finished surface 40a.

【0051】そしてまた、上記構成の3次元構造のネッ
ト26を用いているので、ネット26表裏の立毛部によ
って各層56,64同士の十分な付着を確保して施工す
ることができる。
Further, since the three-dimensional net 26 having the above-described structure is used, it is possible to ensure the sufficient adhesion between the layers 56 and 64 by the raised portions on the front and back of the net 26, and to perform the construction.

【0052】[0052]

【発明の効果】以上説明したように本発明の請求項1に
示す仕上げ面の施工方法にあっては、メカニカルアンカ
ーの施工対象面への取り付けに際してネットを傷付けて
しまうことを確実に防止することができ、ネットの切断
による仕上げ面の強度低下を確実に防ぐことができる。
As described above, in the method for applying a finished surface according to the first aspect of the present invention, it is possible to reliably prevent the net from being damaged when the mechanical anchor is attached to the surface to be applied. Thus, a decrease in the strength of the finished surface due to the cutting of the net can be reliably prevented.

【0053】また、この塗り仕上げ層を形成する以前に
施工対象面を十分にクリーニングしておくこともでき、
すなわち施工対象面が汚れている場合にもこれを容易か
つきれいに除去することができて、塗り仕上げ層の施工
対象面への接着性を著しく向上することができる。
Further, the surface to be applied can be sufficiently cleaned before forming the coating finish layer.
That is, even when the surface to be applied is dirty, it can be easily and neatly removed, and the adhesion of the coating layer to the surface to be applied can be significantly improved.

【0054】また、施工対象面側から順次重ねるように
して各層を形成していくだけでネット表裏の立毛部によ
って各層同士の十分な付着を確保して施工することがで
きる。
Further, by simply forming each layer in such a manner that the layers are sequentially stacked from the construction target surface side, it is possible to carry out the construction while ensuring sufficient adhesion between the layers by the raised portions on the front and back of the net.

【0055】また、本発明の請求項2に示す仕上げ面の
施工方法にあっては、押さえ部材の埋め込み部材への固
定を孔部によって容易化できる一方で、この孔部には着
脱自在なキャップを装着して塗り仕上げ層の形成時に孔
部が塞がれるのを防止できるとともに、押さえ部材を埋
め込み部材に装着する際にこのキャップを目印とするこ
ともでき、施工性を向上することができる。
In the method for applying a finished surface according to a second aspect of the present invention, the fixing of the holding member to the embedding member can be facilitated by the hole, and the cap is detachably provided in the hole. The cap can be used as a mark when mounting the holding member on the embedding member, and the workability can be improved. .

【0056】さらに、本発明の請求項3に示す仕上げ面
構造にあっては、ネットを張付ける以前に施工対象面の
穴部にメカニカルアンカーの埋め込み部材を挿入してお
くことができる構造であるため、メカニカルアンカーの
施工対象面への取り付けに際してネットを傷付けてしま
うことを確実に防止することができる。
Further, in the finished surface structure according to the third aspect of the present invention, the embedded member of the mechanical anchor can be inserted into the hole of the construction target surface before the net is attached. Therefore, it is possible to reliably prevent the net from being damaged when the mechanical anchor is attached to the construction target surface.

【0057】また、前記穴部を形成した後に塗り仕上げ
層を形成する構造であるので、この塗り仕上げ層を形成
する以前に、施工対象面を十分にクリーニングしておく
こともでき、塗り仕上げ層と施工対象面との接着性を著
しく向上することができる。
Further, since the coating finish layer is formed after the hole is formed, the surface to be applied can be sufficiently cleaned before forming the coating finish layer. Adhesiveness between the surface and the construction target surface can be significantly improved.

【0058】また、3次元構造のネットを用い、裏面側
立毛部を塗り仕上げ層に埋め込んで当該ネットを施工対
象面側に定着させる一方で、表面側立毛部を介して当該
ネット上に仕上げ層を施工するようにしたので、ネット
表裏の立毛部によって仕上げ層の塗り仕上げ層からの剥
離、ひいては施工対象面からの剥離を確実に防止するこ
とができる。
Also, using a three-dimensionally structured net, the back-side raised portion is embedded in the painted finishing layer to fix the net on the construction target surface side, while the finishing layer is formed on the net via the front-side raised portion. The peeling of the finishing layer from the coating finishing layer, and eventually the peeling from the construction target surface, can be reliably prevented by the raised portions on the front and back surfaces of the net.

【0059】さらに、本発明の請求項4に示す仕上げ面
構造にあっては、平面の縦横方向の繊維で仕上げ層のひ
び割れを防止できると共に、表裏の厚さ方向の繊維で仕
上げ層の塗り仕上げ層からの剥離、ひいては施工対象面
からの剥離を確実に防止することができ、そしてまたこ
の繊維を耐アルカリ性を有する素材としていることか
ら、コンクリート構造物表面に発生するアルカリ成分に
対して十分な耐久性を発揮させて、このネットによる剥
離防止効果を長期にわたって確実に維持することができ
る。
Further, in the finished surface structure according to the fourth aspect of the present invention, cracks in the finished layer can be prevented by the fibers in the vertical and horizontal directions of the plane, and the finish of the finish layer can be finished by the fibers in the thickness direction on the front and back sides. Peeling from the layer, and eventually peeling from the construction surface, can be reliably prevented, and since this fiber is made of a material having alkali resistance, it is sufficient for alkali components generated on the surface of the concrete structure. By exhibiting the durability, the peel prevention effect of the net can be reliably maintained for a long period of time.

【0060】また、本発明の請求項5に示す仕上げ面の
施工方法にあっては、補修・改修しようとするコンクリ
ート構造物の既存仕上げ面に適用する場合であって、こ
のような場合であってもメカニカルアンカーの既存仕上
げ面への取り付けに際してネットを傷付けてしまうこと
を確実に防止することができる。
The method for constructing a finished surface according to claim 5 of the present invention is applied to an existing finished surface of a concrete structure to be repaired / repaired. However, it is possible to reliably prevent the net from being damaged when the mechanical anchor is attached to the existing finished surface.

【0061】また、既存仕上げ面を十分にクリーニング
しておくこともできて、塗り仕上げ層の既存仕上げ面へ
の接着性を著しく向上することができる。
Further, the existing finished surface can be sufficiently cleaned, and the adhesiveness of the coated finishing layer to the existing finished surface can be remarkably improved.

【0062】また、3次元構造のネットにより各層同士
の十分な付着を確保して施工することができる。
The three-dimensional net can be used to ensure sufficient adhesion between the layers.

【0063】また、本発明の請求項6に示す仕上げ面の
施工方法にあっては、既存仕上げ面に穴部を穿設した後
でかつ既存仕上げ面に塗り仕上げ層を形成する前に、当
該既存仕上げ面をクリーニングするようにしたので、塗
り仕上げ層の既存仕上げ面への接着性をさらに向上する
ことができる。
Further, in the method for applying a finished surface according to claim 6 of the present invention, after forming a hole in the existing finished surface and before forming a coating finish layer on the existing finished surface, Since the existing finished surface is cleaned, the adhesiveness of the painted finish layer to the existing finished surface can be further improved.

【0064】また、本発明の請求項7に示す仕上げ面の
施工方法にあっては、新設のコンクリート構造物の仕上
げ面に適用する場合であって、このような場合であって
もメカニカルアンカーの仕上げ面への取り付けに際して
ネットを傷付けてしまうことを確実に防止することがで
きる。
Further, the method for constructing a finished surface according to claim 7 of the present invention is applied to the finished surface of a new concrete structure. It is possible to reliably prevent the net from being damaged when it is attached to the finished surface.

【0065】また、仕上げ面を十分にクリーニングして
おくこともできて、下地モルタル層の仕上げ面への接着
性を著しく向上することができる。
Further, the finished surface can be sufficiently cleaned, and the adhesion of the underlying mortar layer to the finished surface can be significantly improved.

【0066】また、3次元構造のネットにより各層同士
の十分な付着を確保して施工することができるという各
種優れた効果を奏する。
In addition, various excellent effects can be obtained in that the three-dimensional net can be used to ensure sufficient adhesion between the layers.

【図面の簡単な説明】[Brief description of the drawings]

【図1】本発明にかかる仕上げ面の施工方法及び仕上げ
面構造の一実施形態を示す補修・改修を完了した既存壁
の断面図である。
FIG. 1 is a cross-sectional view of an existing wall after completion of repair / repair showing one embodiment of a method for applying a finished surface and a finished surface structure according to the present invention.

【図2】図1の実施形態に用いられるメカニカルアンカ
ーおよびそのキャップを示す図である。
FIG. 2 is a diagram showing a mechanical anchor and its cap used in the embodiment of FIG. 1;

【図3】図1の実施形態に用いられる3次元構造のネッ
トの要部拡大図である。
FIG. 3 is an enlarged view of a main part of a net having a three-dimensional structure used in the embodiment of FIG. 1;

【図4】本発明にかかる仕上げ面の施工方法及び仕上げ
面構造を新設のコンクリート壁に適用した場合の実施形
態を示す要部拡大断面図である。
FIG. 4 is an enlarged sectional view of a main part showing an embodiment in which the method for applying a finished surface and the finished surface structure according to the present invention are applied to a newly installed concrete wall.

【図5】図4の実施形態の第1工程を示す要部拡大断面
図である。
FIG. 5 is an enlarged sectional view of a main part showing a first step of the embodiment of FIG. 4;

【図6】図4の実施形態の第2工程を示す要部拡大断面
図である。
FIG. 6 is an enlarged sectional view of a main part showing a second step of the embodiment in FIG. 4;

【図7】本発明にかかる仕上げ面の施工方法及び仕上げ
面構造を新設のコンクリート壁に適用した場合の他の実
施形態における第1工程を示す要部拡大断面図である。
FIG. 7 is an enlarged sectional view of a main part showing a first step in another embodiment when the method for applying a finished surface and the finished surface structure according to the present invention are applied to a newly installed concrete wall.

【図8】本発明にかかる新設のコンクリート壁に適用し
た場合の他の実施形態における第2工程を示す要部拡大
断面図である。
FIG. 8 is an enlarged sectional view of a main part showing a second step in another embodiment when applied to a new concrete wall according to the present invention.

【図9】本発明にかかる新設のコンクリート壁に適用し
た場合の他の実施形態における第3工程を示す要部拡大
断面図である。
FIG. 9 is an enlarged sectional view of a main part showing a third step in another embodiment when applied to a new concrete wall according to the present invention.

【符号の説明】[Explanation of symbols]

10 既存壁 20 既存仕上げ層 22 改修層 24 塗り仕上げ層 26 立毛3次元ネット 28,64 仕上げ層 32,48 メカニカルアンカー 32a 軸部 32b 座部 32c 軸孔 34 穴部 36 キャップ 40 新設のコンクリート壁 40a 仕上げ面 44 レジコン 44a レジコンのナット部 46 穴部 48a パイプ 48b 座部 56 左官下地モルタル層 66 メカニカルアンカー 66a パイプ 66b 座部 10 Existing wall 20 Existing finishing layer 22 Renovation layer 24 Coating finishing layer 26 Napped three-dimensional net 28,64 Finishing layer 32,48 Mechanical anchor 32a Shaft 32b Seat 32c Shaft hole 34 Hole 36 Cap 40 New concrete wall 40a Finish Surface 44 Resincon 44a Resin nut 46 Hole 48a Pipe 48b Seat 56 Plastering mortar layer 66 Mechanical anchor 66a Pipe 66b Seat

───────────────────────────────────────────────────── フロントページの続き (72)発明者 小川 晴果 東京都清瀬市下清戸4丁目640番地 株式 会社大林組技術研究所内 (72)発明者 三谷 一房 東京都清瀬市下清戸4丁目640番地 株式 会社大林組技術研究所内 (72)発明者 川原 正雄 埼玉県川越市南台1−10−4 株式会社シ ョックベトン・ジャパン内 ──────────────────────────────────────────────────続 き Continuing on the front page (72) Inventor Haruka Ogawa 4-640 Shimoseito, Kiyose-shi, Tokyo Inside the Obayashi Gumi Technical Research Institute, Inc. Within the Technical Research Institute (72) Inventor Masao Kawahara 1-10-4 Minamidai, Kawagoe-shi, Saitama Prefecture Shokbeton Japan Co., Ltd.

Claims (7)

【特許請求の範囲】[Claims] 【請求項1】 コンクリート構造物の表面を仕上げるに
際して、施工対象面に形成した穴部に、分離可能な埋め
込み部材と押さえ部材とからなるメカニカルアンカーの
該埋め込み部材を挿入し、次いで上記施工対象面に塗り
仕上げ層を形成し、その後該塗り仕上げ層の表面に、表
裏に立毛部を有する3次元構造のネットを、その裏面側
立毛部を該塗り仕上げ層に埋め込み、表面側立毛部を露
出させて張り付け、次いで上記ネットの表面側から網目
を介して上記メカニカルアンカーの上記押さえ部材を上
記埋め込み部材に固定して該押さえ部材で該ネットを押
さえ、その後該ネット上にその表面側立毛部を介して仕
上げ層を形成するようにしたことを特徴とする仕上げ面
の施工方法。
When finishing the surface of a concrete structure, the embedded member of a mechanical anchor comprising a separable embedded member and a holding member is inserted into a hole formed in the surface to be worked, and then the surface to be worked is Then, a net having a three-dimensional structure having raised portions on the front and back sides is embedded on the surface of the coated finishing layer, and the raised portion on the back side is embedded in the coated finished layer to expose the raised portion on the surface side. Then, the pressing member of the mechanical anchor is fixed to the embedding member via the mesh from the surface side of the net, and the net is pressed by the pressing member. A method for constructing a finished surface, characterized in that a finished layer is formed by forming.
【請求項2】 請求項1に記載の仕上げ面の施工方法で
あって、前記メカニカルアンカーの前記埋め込み部材に
は前記押さえ部材を固定するための孔部を形成してお
き、前記施工対象面に塗り仕上げ層を形成する前に、上
記埋め込み部材の孔部にこれを塞ぐための着脱自在なキ
ャップを装着するようにし、上記押さえ部材を上記埋め
込み部材に固定する際にこのキャップを取り外すように
したことを特徴とする仕上げ面の施工方法。
2. The method according to claim 1, wherein a hole for fixing the holding member is formed in the embedded member of the mechanical anchor, and the hole is formed in the surface to be processed. Before forming the coating finishing layer, a detachable cap for closing the hole was filled in the hole of the embedded member, and the cap was removed when the holding member was fixed to the embedded member. A method for constructing a finished surface, characterized in that:
【請求項3】 コンクリート構造物表面の仕上げ構造に
おいて、施工対象面に形成した穴部に、分離可能な埋め
込み部材と押さえ部材とからなるメカニカルアンカーの
該埋め込み部材を挿入し、該埋め込み部材を挿入した上
記施工対象面に塗り仕上げ層を形成し、該塗り仕上げ層
の表面に、表裏に立毛部を有する3次元構造のネット
を、その裏面側立毛部を該塗り仕上げ層に埋め込み、表
面側立毛部を露出させて張り付けるとともに、上記ネッ
トの表面側から網目を介して上記メカニカルアンカーの
上記押さえ部材を上記埋め込み部材に固定して該押さえ
部材で該ネットを押さえ、該ネット上にその表面側立毛
部を介して仕上げ層を形成したことを特徴とする仕上げ
面構造。
3. In a finishing structure of a concrete structure surface, the embedded member of a mechanical anchor including a separable embedded member and a holding member is inserted into a hole formed in a construction target surface, and the embedded member is inserted. Forming a coating finish layer on the surface to be applied, and embedding a three-dimensional structure net having a raised portion on the front and back surfaces on the surface of the coating finish layer, and embedding the back side raised portion in the coated finish layer; A part is exposed and attached, and the pressing member of the mechanical anchor is fixed to the embedding member via a mesh from the surface side of the net, and the net is pressed by the pressing member, and the surface side of the net is positioned on the net. A finished surface structure characterized by forming a finished layer via a raised portion.
【請求項4】 請求項3に記載の仕上げ面構造であっ
て、前記ネットは、耐アルカリ性を有する繊維を素材と
して、平面の縦横方向およびその表裏の厚さ方向に繊維
を配向させて織布あるいは編布とした立毛3次元構造で
あることを特徴とする仕上げ面構造。
4. The finished surface structure according to claim 3, wherein the net is made of a fiber having alkali resistance, and the fibers are oriented in the vertical and horizontal directions of the plane and the thickness directions of the front and back surfaces thereof. Alternatively, a finished surface structure characterized by a three-dimensional standing hair made of a knitted fabric.
【請求項5】 補修・改修しようとするコンクリート構
造物の既存仕上げ面に穴部を穿設し、この穴部に分離可
能な埋め込み部材と押さえ部材とからなるメカニカルア
ンカーの該埋め込み部材を挿入し、次いで上記既存仕上
げ面にポリマーセメントモルタルで塗り仕上げ層を形成
し、その後該塗り仕上げ層の表面に、表裏に立毛部を有
する3次元構造のネットを、その裏面側立毛部を該塗り
仕上げ層に埋め込み、表面側立毛部を露出させて張り付
け、次いで上記ネットの表面側から網目を介して上記メ
カニカルアンカーの上記押さえ部材を上記埋め込み部材
に固定して該押さえ部材で該ネットを押さえ、その後該
ネット上にその表面側立毛部を介して塗り仕上げやタイ
ル張りなどの仕上げ層を形成するようにしたことを特徴
とする仕上げ面の施工方法。
5. A hole is formed in an existing finished surface of a concrete structure to be repaired or repaired, and the embedded member of a mechanical anchor including a separable embedded member and a holding member is inserted into the hole. Then, a coating finish layer is formed on the existing finish surface with polymer cement mortar, and then a three-dimensional structure net having raised portions on the front and back sides is formed on the surface of the coated finish layer, and the raised portion on the back surface is coated with the coated finish layer. Embedded on the surface, and the surface-side raised portion is exposed and attached.Then, the pressing member of the mechanical anchor is fixed to the embedding member through a mesh from the surface side of the net, and the net is pressed by the pressing member. A finishing surface characterized by forming a finishing layer such as painting or tiling on the surface of the net through the raised portion on the front side. Construction method.
【請求項6】 請求項5に記載の仕上げ面の施工方法で
あって、前記既存仕上げ面に前記穴部を穿設した後で該
既存仕上げ面に塗り仕上げ層を形成する前に、この既存
仕上げ面をクリーニングするようにしたことを特徴とす
る仕上げ面の施工方法。
6. The method for applying a finished surface according to claim 5, wherein after forming the hole in the existing finished surface and before forming a coating finish layer on the existing finished surface, the method includes the steps of: A method for constructing a finished surface, wherein the finished surface is cleaned.
【請求項7】 新設のコンクリート構造物の仕上げ面に
予め穴部を形成し、この穴部に分離可能な埋め込み部材
と押さえ部材とからなるメカニカルアンカーの該埋め込
み部材を挿入し、次いで上記仕上げ面に下地モルタル層
を形成し、その後該下地モルタル層の表面に、表裏に立
毛部を有する3次元構造のネットを、その裏面側立毛部
を該下地モルタル層側に埋め込み、表面側立毛部を露出
させて張り付け、次いで上記ネットの表面側から網目を
介して上記メカニカルアンカーの上記押さえ部材を上記
埋め込み部材に固定して該押さえ部材で該ネットを押さ
え、その後該ネット上にその表面側立毛部を介して塗り
仕上げやタイル張りなどの仕上げ層を形成するようにし
たことを特徴とする仕上げ面の施工方法。
7. A hole is previously formed in a finished surface of a new concrete structure, and the embedded member of a mechanical anchor including a separable embedded member and a pressing member is inserted into the hole, and then the finished surface is formed. A base mortar layer is formed on the surface of the base mortar layer. Thereafter, a three-dimensional structure net having raised portions on the front and back sides is buried on the surface of the base mortar layer, and the raised portion on the back side is embedded in the base mortar layer side to expose the raised portion on the surface side Then, the pressing member of the mechanical anchor is fixed to the embedding member through the mesh from the surface side of the net via the mesh, and the net is pressed by the pressing member. A method of constructing a finished surface, wherein a finishing layer such as a painted finish or a tiled is formed through the intermediate layer.
JP29891496A 1996-11-11 1996-11-11 Finished surface construction method Expired - Lifetime JP3277131B2 (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
JP29891496A JP3277131B2 (en) 1996-11-11 1996-11-11 Finished surface construction method

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
JP29891496A JP3277131B2 (en) 1996-11-11 1996-11-11 Finished surface construction method

Publications (2)

Publication Number Publication Date
JPH10140779A true JPH10140779A (en) 1998-05-26
JP3277131B2 JP3277131B2 (en) 2002-04-22

Family

ID=17865815

Family Applications (1)

Application Number Title Priority Date Filing Date
JP29891496A Expired - Lifetime JP3277131B2 (en) 1996-11-11 1996-11-11 Finished surface construction method

Country Status (1)

Country Link
JP (1) JP3277131B2 (en)

Cited By (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP2009062427A (en) * 2007-09-05 2009-03-26 Fuji Ultrasonic Engineering Co Ltd Asbestos-treating method using asbestos-treating agent
JP2015010453A (en) * 2013-07-02 2015-01-19 株式会社竹中工務店 Tile laying method and outer wall
JP2015200093A (en) * 2014-04-07 2015-11-12 株式会社大林組 Construction method of concrete structure
KR20190085411A (en) * 2018-01-10 2019-07-18 한수명 A drybit assembly for building outer wall

Families Citing this family (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN109853888A (en) * 2019-03-07 2019-06-07 上海市房地产科学研究院(上海市住宅修缮工程质量检测中心) A kind of historical building plucking wall surface construction technology

Citations (7)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPS57181835U (en) * 1981-05-14 1982-11-18
JPS60175665A (en) * 1984-02-23 1985-09-09 日興化成株式会社 Repairing of outer wall of building
JPS6125403U (en) * 1984-07-19 1986-02-15 東興産業株式会社 insert button
JPS63147056A (en) * 1986-12-09 1988-06-20 河田 繁行 Undercoating execution method to building
JPH0333360A (en) * 1989-06-29 1991-02-13 Shimizu Corp Tile facing exterior technique
JPH03191163A (en) * 1989-12-19 1991-08-21 Kobe Kizai:Kk Method for forming mortar wall
JPH08158216A (en) * 1994-12-06 1996-06-18 Toyobo Co Ltd Double-side pile knit or woven fabric for bonding finish material

Patent Citations (7)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPS57181835U (en) * 1981-05-14 1982-11-18
JPS60175665A (en) * 1984-02-23 1985-09-09 日興化成株式会社 Repairing of outer wall of building
JPS6125403U (en) * 1984-07-19 1986-02-15 東興産業株式会社 insert button
JPS63147056A (en) * 1986-12-09 1988-06-20 河田 繁行 Undercoating execution method to building
JPH0333360A (en) * 1989-06-29 1991-02-13 Shimizu Corp Tile facing exterior technique
JPH03191163A (en) * 1989-12-19 1991-08-21 Kobe Kizai:Kk Method for forming mortar wall
JPH08158216A (en) * 1994-12-06 1996-06-18 Toyobo Co Ltd Double-side pile knit or woven fabric for bonding finish material

Cited By (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP2009062427A (en) * 2007-09-05 2009-03-26 Fuji Ultrasonic Engineering Co Ltd Asbestos-treating method using asbestos-treating agent
JP2015010453A (en) * 2013-07-02 2015-01-19 株式会社竹中工務店 Tile laying method and outer wall
JP2015200093A (en) * 2014-04-07 2015-11-12 株式会社大林組 Construction method of concrete structure
KR20190085411A (en) * 2018-01-10 2019-07-18 한수명 A drybit assembly for building outer wall

Also Published As

Publication number Publication date
JP3277131B2 (en) 2002-04-22

Similar Documents

Publication Publication Date Title
US20050120660A1 (en) Plastic micro packer and construction method using it
US20030098081A1 (en) Swimming pool plumbing water/debris barrier device and method
JPH10140779A (en) Construction method of finished surface and finished surface structure
JP2832430B2 (en) Building outer wall repair method
JP2006274744A (en) Exterior wall and tiling construction method for the same
JP5333961B2 (en) Tiles, anchor tiles, unit tiles, tile upholstery methods, tile formwork attaching methods, and tile PC plate attaching methods
JP2006348687A (en) Method for preventing tile of interior and exterior facing wall from falling
JP3686593B2 (en) Resin combined anchor device
JP3349376B2 (en) Prevention of peeling of wet finishing materials
JPH05195634A (en) Exterior wall repairing method for building
JP6608348B2 (en) Metal bonding auxiliary device and bonding auxiliary system including the metal bonding auxiliary device
JP2010144381A (en) Metal fitting, structure and construction method for repairing exterior wall
AU2019203672A1 (en) Tactile Marker and Installation Method
JP3468965B2 (en) Floating tile bonding method
JP6801180B2 (en) Repair structure of existing outer wall and repair method of existing outer wall
JPH09217497A (en) Attachment for injecting filler
JPH07238690A (en) Wall repaired to prevent falling of mortar layer, method for repairing same, and anchor pin
JPH11303361A (en) Tiled wall surface repairing method
JP2016113810A (en) Building material for pin-net construction method, and pin-net construction method using the same
JP3748766B2 (en) Repair method and repair metal fittings for concrete structures
JPH07180368A (en) Method for repairing exterior wall of building
JP6316469B2 (en) Repair method for exterior wall finishing materials
JP2000213181A (en) Method for execution of finish of alc exterior wall and finish structure
JPH0528288Y2 (en)
JP2003056157A (en) Modifying method for wall face

Legal Events

Date Code Title Description
S111 Request for change of ownership or part of ownership

Free format text: JAPANESE INTERMEDIATE CODE: R313117

R350 Written notification of registration of transfer

Free format text: JAPANESE INTERMEDIATE CODE: R350

R250 Receipt of annual fees

Free format text: JAPANESE INTERMEDIATE CODE: R250

FPAY Renewal fee payment (event date is renewal date of database)

Free format text: PAYMENT UNTIL: 20080208

Year of fee payment: 6

FPAY Renewal fee payment (event date is renewal date of database)

Free format text: PAYMENT UNTIL: 20090208

Year of fee payment: 7

FPAY Renewal fee payment (event date is renewal date of database)

Free format text: PAYMENT UNTIL: 20100208

Year of fee payment: 8

FPAY Renewal fee payment (event date is renewal date of database)

Free format text: PAYMENT UNTIL: 20100208

Year of fee payment: 8

FPAY Renewal fee payment (event date is renewal date of database)

Free format text: PAYMENT UNTIL: 20110208

Year of fee payment: 9

S531 Written request for registration of change of domicile

Free format text: JAPANESE INTERMEDIATE CODE: R313531

FPAY Renewal fee payment (event date is renewal date of database)

Free format text: PAYMENT UNTIL: 20110208

Year of fee payment: 9

R350 Written notification of registration of transfer

Free format text: JAPANESE INTERMEDIATE CODE: R350

FPAY Renewal fee payment (event date is renewal date of database)

Free format text: PAYMENT UNTIL: 20120208

Year of fee payment: 10

FPAY Renewal fee payment (event date is renewal date of database)

Free format text: PAYMENT UNTIL: 20130208

Year of fee payment: 11

FPAY Renewal fee payment (event date is renewal date of database)

Free format text: PAYMENT UNTIL: 20130208

Year of fee payment: 11

FPAY Renewal fee payment (event date is renewal date of database)

Free format text: PAYMENT UNTIL: 20140208

Year of fee payment: 12

EXPY Cancellation because of completion of term