JPH0988014A - Temporary fixing method of block in pc precast block method by non-coupler - Google Patents

Temporary fixing method of block in pc precast block method by non-coupler

Info

Publication number
JPH0988014A
JPH0988014A JP7244636A JP24463695A JPH0988014A JP H0988014 A JPH0988014 A JP H0988014A JP 7244636 A JP7244636 A JP 7244636A JP 24463695 A JP24463695 A JP 24463695A JP H0988014 A JPH0988014 A JP H0988014A
Authority
JP
Japan
Prior art keywords
block
cable
fixed
temporary fixing
temporarily
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Granted
Application number
JP7244636A
Other languages
Japanese (ja)
Other versions
JP3608751B2 (en
Inventor
Yoshiki Watanabe
芳樹 渡辺
Masanobu Uno
正修 宇野
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Taisei Corp
Original Assignee
Taisei Corp
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Taisei Corp filed Critical Taisei Corp
Priority to JP24463695A priority Critical patent/JP3608751B2/en
Publication of JPH0988014A publication Critical patent/JPH0988014A/en
Application granted granted Critical
Publication of JP3608751B2 publication Critical patent/JP3608751B2/en
Anticipated expiration legal-status Critical
Expired - Fee Related legal-status Critical Current

Links

Landscapes

  • Bridges Or Land Bridges (AREA)

Abstract

PROBLEM TO BE SOLVED: To efficiently and safely carry out temporary fixing works of blocks in the PC precast block method of a structure by use of a post-tension way, in which a plurality of precast blocks are assembled and temporarily fixed and tension members are inserted in respective blocks temporarily fixed and applied with a tensile force and unified to form them integrally. SOLUTION: A sheath 2 in which a plurality of cables 1 used for a temporary fixing work are inserted, is embedded in advance in each divided block A1 and the cables 1 are inserted into the sheath 2 of blocks A1 , A1 from a structure to be fixed, as the base point. A jack 5 is connected to the end of the inserted cable and the cable is pulled to prestress it and join blocks A1 , A1 to the side to be fixed. Subsequently, blocks are temporarily fixed one after another in this procedure.

Description

【発明の詳細な説明】Detailed Description of the Invention

【0001】[0001]

【発明の属する技術分野】この発明は、PCプレキャス
トブロック工法による構造物の建設工事におけるブロッ
クの仮固定方法に関するものである。さらに詳しく言え
ば、構造物本体をあらかじめ複数のブロックに分割し、
この分割したブロックを工場または現場サイトに設けた
ブロック製作ヤードで製作し、つまりプレキャストし、
ついでこのプレキャストしたブロックを建設現場に搬入
して組み立てるとともに、各ブロックにあらかじめ埋設
したシースを介して緊張材(PC鋼より線)を挿通し、
これに緊張力を導入して各ブロックを一体的に結合定着
させて所望の構造物を組み立て建設する、いわゆるポス
トテンション方式によるプレストレストコンクリートプ
レキャストブロック工法(以下、PCプレキャストブロ
ック工法と呼ぶ)による構造物の建設工事において、前
記各ブロックを本定着させる前に、ブロック同志を一時
的に結合固定させるブロックの仮固定方法に関するもの
である。例えば、PCプレキャストブロック工法によっ
てPC橋を架設する場合におけるブロックの仮固定方法
に関するものである。
BACKGROUND OF THE INVENTION 1. Field of the Invention The present invention relates to a method of temporarily fixing a block in a construction work of a structure by a PC precast block method. More specifically, the structure body is divided into multiple blocks in advance,
This divided block is manufactured in the block manufacturing yard provided at the factory or on-site site, that is, precast,
Then, this precast block is carried into the construction site for assembly, and the tension material (PC steel stranded wire) is inserted through the sheath previously embedded in each block.
Structure by prestressed concrete precast block construction method (hereinafter referred to as PC precast block construction method) by so-called post-tension method, in which tension is introduced to integrally bond and fix each block to assemble and construct a desired structure In the construction work, the present invention relates to a block temporary fixing method for temporarily fixing the blocks to each other before permanently fixing the blocks. For example, it relates to a method of temporarily fixing a block when a PC bridge is erected by the PC precast block method.

【0002】[0002]

【従来の技術】図7は、PCプレキャストブロック工法
によって構築したPC橋の構造を示すものである。図示
において54は、各ブロックにポストテンションを導入
し、各ブロックを一体的に結合定着した緊張材である。
従来、この工法によってPC橋を建設する場合は、あら
かじめ橋脚50の柱頭部51を基準として橋桁を図示の
ように複数のブロックA1 ,A2 ,…An に分割し、こ
の分割したブロックA1,A2 ,…An を工場または建
設現場サイトに設けたブロック製作ヤードで製作する。
そして、このブロックA1 ,A2 ,…An を現場に搬入
する。
2. Description of the Related Art FIG. 7 shows the structure of a PC bridge constructed by the PC precast block method. In the figure, reference numeral 54 is a tension member that introduces post tension into each block to integrally bond and fix each block.
Conventionally, when a PC bridge is constructed by this method, the bridge girder is divided into a plurality of blocks A 1 , A 2 , ... A n with reference to the pillar head 51 of the pier 50 in advance, and the divided block A is Produce 1 , A 2 , ... A n in the block production yard provided at the factory or construction site.
Then, the blocks A 1 , A 2 , ... An are carried into the site.

【0003】他方、図8で示すように橋脚50の柱頭部
51上には、通称エレクションノーズ52と呼ばれる水
平移動自在な揚重機(ウインチ52a)を搭載配備し、
このエレクションノーズ52によって前記現場に搬入し
た、まず最初のブロックA1を前記柱頭部51における
左右の張り出し横桁部51aおよび51aに吊り込む。
On the other hand, as shown in FIG. 8, a horizontally movable hoist (winch 52a) commonly referred to as an erection nose 52 is mounted on the stilt head 51 of the pier 50.
The first block A 1 carried into the site by the erection nose 52 is suspended on the left and right overhanging lateral girders 51a and 51a of the column head 51.

【0004】ついで、吊り込んだブロックA1 と横桁部
51aとの接合面に接着剤等を塗布して双方を接合させ
る。その状態で横桁部51aとブロックA1 とを仮固定
部材53を用いて仮固定させる。
Next, an adhesive or the like is applied to the joint surface between the suspended block A 1 and the cross beam portion 51a to join them together. In this state, the transverse girder portion 51a and the block A 1 are temporarily fixed using the temporary fixing member 53.

【0005】仮固定が終了すると、柱頭部51と仮固定
させたブロックA1 との間にポストンテンションを導入
するための緊張材54(PC鋼より線)を挿通し、これ
に緊張力を導入し、そのブロックA1 をまず柱頭部51
に本定着させ、以下、前記ブロックA1 ,A2 ,…An
の吊り込みと、仮固定と、本定着の作業を順を繰り返し
て前記図7で示したような各ブロックを一体的に結合定
着し、PC橋として建設するようにしている。
When the temporary fixing is completed, a tensioning member 54 (PC steel stranded wire) for introducing Poston tension is inserted between the pillar head 51 and the temporarily fixed block A 1, and the tensioning force is introduced into this. Then, the block A 1 is first used for the stigma 51
Main fixing to the blocks A 1 , A 2 , ... A n
The steps of suspending, temporarily fixing, and main fixing are repeated in order to integrally bond and fix each block as shown in FIG. 7 to construct a PC bridge.

【0006】ちなみに図9は、5個のブロックA1 …A
5 を本定着し、6個目のブロックA 6 を吊り込み仮固定
する工程を示す。なお、ブロックA1 ,A2 ,…An
吊り込み、仮固定,本定着による一連の施工手順は、前
記図8で示すように橋脚50の両側双方に、順に吊り込
み張り出して仮固定するとともに、本定着して対称的に
施工する場合もあり、あるいは左右交互に、すなわち非
対称的な手順によって施工する場合もある。また、ポス
トテンションを導入するための、いわゆる本定着させる
ための緊張材54(PC鋼より線)およびそれを挿通す
るシース55の配置は、橋桁断面の形状やブロックの分
割位置等を考慮し、製作段階において配設している。
By the way, FIG. 9 shows five blocks A.1… A
FiveFix the 6th block A 6Suspend and temporarily fix
The process of doing is shown. Block A1, A2,… Anof
A series of construction procedures including hanging, temporary fixing, and permanent fixing
Suspend in order on both sides of the pier 50 as shown in Fig. 8.
It is overhanged and temporarily fixed, and finally fixed and symmetrical
It may be installed, or left and right alternate, that is, non-
There are also cases where construction is performed in a symmetrical procedure. Also, POS
To introduce so-called tension, so-called main fixing
Tension material 54 (PC steel stranded wire) for inserting it
Arrangement of the sheath 55 that corresponds to the shape of the bridge girder and the block
It is arranged at the manufacturing stage in consideration of the split position.

【0007】図10は、前記ブロックA1 ,A2 ,…A
n の断面構造図を示すものである。断面中に示す多数の
孔は、本定着用のポストテンションを導入するための緊
張材54を挿通するいわゆるシース55の配置例を示す
ものである。これらは当然のことであるが前記したよう
に橋桁断面の形状等によって配置し、ブロック自体の製
造段階において配管埋設させている。
FIG. 10 shows the blocks A 1 , A 2 , ... A.
It is a cross-sectional structural drawing of n . The large number of holes shown in the cross section show an example of the arrangement of a so-called sheath 55 through which a tension member 54 for introducing post tension for main fixing is inserted. As a matter of course, these are arranged according to the shape of the cross section of the bridge girder as described above, and the pipes are buried in the stage of manufacturing the block itself.

【0008】以上説明したように、このPCプレキャス
トブロック工法は、前記PC橋に例をとって説明したこ
とから理解されるように、 (1)ブロックを工場または現場サイトで製作するた
め、管理が十分に行きわたり、精度の高い部材断面のブ
ロックの製作ができる。 (2)ブロックの製作と併行して付随工事の展開ができ
る。 (3)各ブロックを一体化させるケーブルのシースは、
あらかじめブロックの製作工程において配置するので、
その製作はきわめて容易である。 ことなどのメリットにより、在来工法により建設した橋
梁構造物に比較し、製造品質はもとより、施工性、工期
短縮、意匠的な斬新性に優れ、橋梁等の建築構造物とし
て評価されている。
As described above, this PC precast block construction method is, as will be understood from the explanation given by taking the PC bridge as an example, (1) because the block is manufactured at the factory or on-site site, management is difficult. It is possible to manufacture blocks with sufficiently wide and accurate cross-sections. (2) Ancillary work can be developed in parallel with block production. (3) The cable sheath that integrates each block is
Since it is placed in advance in the block manufacturing process,
Its production is extremely easy. Due to such advantages, it is highly evaluated as a building structure such as a bridge because it is superior in terms of manufacturing quality, workability, shortening of construction period, and design novelty compared to bridge structures constructed by conventional construction methods.

【0009】[0009]

【発明が解決しようとする課題】しかしながら、この工
法において、分割したブロックを本定着させる前に、ブ
ロックを順に仮固定する必要がある。その手段として、
従来は先に説明したように仮固定部材53等を用いて連
結し仮固定している。例えば、図8を参考にしてその点
を具体的に説明すると、あらかじめ柱頭部51内に複数
の突起部56,56を設けておく。同様に連結すべきブ
ロックA1 (以下、すべてのブロック)の内部にも、前
記突起部56,56に対応する突起部57,57を設け
ておく。そして、この左右双方の突起部56,56およ
び突起部57,57間に、例えばタイロッドバー状の継
手部材(PC鋼材)58を通し、この継手部材58を介
して双方を連結し、仮固定させるようにしている。
However, in this method, it is necessary to temporarily fix the divided blocks in order before the main fixing of the divided blocks. As a means,
Conventionally, as described above, the temporary fixing members 53 and the like are used to connect and temporarily fix. For example, referring to FIG. 8, the point will be specifically described. A plurality of protrusions 56, 56 are provided in advance in the column head 51. Similarly, protrusions 57, 57 corresponding to the protrusions 56, 56 are provided inside the block A 1 (hereinafter, all blocks) to be connected. Then, for example, a tie rod bar-shaped joint member (PC steel material) 58 is inserted between the left and right protrusions 56, 56 and the protrusions 57, 57, and both are connected and temporarily fixed through the joint member 58. I am trying.

【0010】その他、柱頭部51をはじめ各ブロックA
1 ,A2 ,…An にあらかじめ切欠部を設けて、この切
欠部を利用して継手部材を取り付け、連結し、仮固定さ
せるとか、さらにはブロックA1 ,A2 ,…An 自体に
連結金具をあらかじめ埋設しておき、これを利用して連
結し、仮固定するようにしている。
In addition, each block A including the column head 51
A 1 , A 2 , ... A n is provided with a notch in advance, and the notch is used to attach, connect and temporarily fix the joint member, or to the blocks A 1 , A 2 , ... A n itself. The metal fittings are embedded in advance and used to connect and temporarily fix.

【0011】そのため、その仮固定の作業に人手はもち
ろん手間がかかりすぎ、しかも煩雑である。特に1個の
ブロックを仮固定し、本定着が終了するごとに、つまり
ポストテンションの導入作業が終了するごとに、それら
仮固定部材53は取り外し、それを次の仮固定部材53
として移設利用するようにしている。その結果、その仮
固定部材53による仮固定作業に大変な手間と労力が必
要とされていた。
Therefore, the temporary fixing work is of course labor-intensive as well as man-hours, and is complicated. In particular, one block is temporarily fixed, and each time the main fixing is completed, that is, each time the work of introducing the post tension is completed, the temporary fixing members 53 are removed and the next temporary fixing member 53 is removed.
I am trying to relocate and use it. As a result, the temporary fixing work by the temporary fixing member 53 requires great labor and labor.

【0012】また、従来の仮固定方式では、柱頭部51
やブロックA1 ,A2 ,…An に突起部や切欠部を設け
たり、継手部材を埋め込んだりしているため、当該部を
含む構造物自体の強度的信頼性にさらなる配慮が要求さ
れるといった問題点があった。この発明は、このような
組立て作業上の問題や構造的な強度や安全性、施工性を
改善する視点から、これまで仮固定用の連結手段として
用いられている部材53をなくし、いわゆるノン・カッ
プラー方式による仮固定工法を提供することを目的とし
開発を行ったものである。
In the conventional temporary fixing method, the column head 51
Further, since projections and notches are provided in the blocks and blocks A 1 , A 2 , ... A n , and joint members are embedded, further consideration is required for the strength reliability of the structure itself including the parts. There was a problem such as. The present invention eliminates the member 53 which has been used as a connecting means for temporary fixing so far from the viewpoint of improving the assembly work problems, structural strength, safety and workability. It was developed for the purpose of providing a temporary fixing method by the coupler method.

【0013】[0013]

【課題を解決する手段】そこで、前記目的を達成するた
め、どのような手段を講じたかと言えば、所望のコンク
リート構造物をあらかじめ複数のブロックに分割し、こ
の分割したブロックを被固定部となる構造部に順次結合
させるとともに仮固定し、仮固定したブロックをポスト
テンション用のケーブルを介して一体的に定着固定し、
いわゆるポストテンション方式によってプレストレスト
プレキャストコンクリート構造の構造物を建造するPC
プレキャストブロック工法において、 (1)まず、前記被固定部となる構造部と、各ブロック
にそれぞれ仮固定用のケーブルを挿通するシースをあら
かじめ設けておくとともに、被固定部となる構造部にお
けるシース入口側には、仮固定用のケーブル(本定着用
に用いる緊張材と同様なもの)を一時的にクランプする
仮定着具と、仮固定用のケーブルを巻装したケーブルド
ラムを設置した。そして、まず被固定部の構造部側方
に、最初のブロックを吊り込むとともに前記ケーブルド
ラムからケーブルを引き出し、被固定部となる構造部側
の前記仮定着具と、前記ブロックのシースを介してケー
ブルの端末、つまり先端部をブロックの前端部側に引き
出す(第1工程)。 (2)ついで、ブロックの前端部に引き出したケーブル
の先端部にジャッキを連結し、このジャッキによってケ
ーブルに前記仮定着具を反力点として緊張力を導入し、
ブロックを前記被固定部の構造部側に引き寄せ、ケーブ
ルによって仮固定させる(第2工程)。 (3)その状態で前記被固定部の構造部とブロックとの
間に、緊張材を挿入してポストテンションを導入し、双
方を一体的に本定着させ固定する(第3工程)。 (4)前記ポストテンションの導入による本定着が終了
すると構造部側の仮定着具から前記ケーブルを解放する
とともに、ジャッキをケーブルの先端部から取り外し、
次位のブロックを前記本定着させたブロックの側方に吊
り込み、その吊り込んだブロックのシースに、前記ジャ
ッキから取り外したケーブルの先端部を挿入して前端部
に引き出し、その引き出したケーブルの先端部にジャッ
キを再連結させ、ケーブルに緊張力を導入して、その次
位のブロックを仮固定させる(第4工程)。 (5)以下、前記引き出したケーブルの先端部にジャッ
キを再連結しブロックを仮固定させる第2工程から第4
工程を順次繰り返し、ブロック自体の仮固定を前記仮固
定用のケーブルを利用して行うようにしたことにある。
[Means for Solving the Problem] Therefore, what means is taken to achieve the above object is that a desired concrete structure is divided into a plurality of blocks in advance, and the divided blocks are referred to as fixed portions. The structure is fixed to the structure part and fixed temporarily, and the temporarily fixed block is integrally fixed and fixed via the cable for post tension,
PC for constructing prestressed precast concrete structure by so-called post tension method
In the precast block method, (1) First, a structure part to be the fixed part and a sheath for inserting a cable for temporary fixing are provided in advance in each block, and a sheath inlet in the structure part to be the fixed part. On the side, a hypothetical fixture for temporarily clamping a cable for temporary fixing (similar to the tension material used for main fixing) and a cable drum around which the cable for temporary fixing was wound were installed. Then, first, the first block is hung on the side of the structure part of the fixed part and the cable is pulled out from the cable drum, and the hypothetical fitting on the side of the structure part to be the fixed part and the sheath of the block are inserted. The end of the cable, that is, the tip end is pulled out to the front end side of the block (first step). (2) Then, a jack is connected to the tip of the cable pulled out to the front end of the block, and a tension force is introduced into the cable by using the hypothetical fastener as a reaction point,
The block is pulled toward the structural portion side of the fixed portion and temporarily fixed by a cable (second step). (3) In that state, a tension member is inserted between the structural portion of the fixed portion and the block to introduce post tension, and both are integrally fixed and fixed integrally (third step). (4) When the main fixing by the introduction of the post tension is completed, the cable is released from the assumed attachment on the structure side, and the jack is removed from the tip of the cable.
Suspend the next block to the side of the main-fixed block, insert the tip of the cable removed from the jack into the sheath of the suspended block, and pull it out to the front end. The jack is reconnected to the tip portion, tension is introduced to the cable, and the next block is temporarily fixed (fourth step). (5) In the following, from the second step to the fourth step of re-connecting the jack to the tip of the pulled-out cable and temporarily fixing the block
The steps are sequentially repeated so that the block itself is temporarily fixed by using the temporary fixing cable.

【0014】なお、前記被固定部となる構造部と、各ブ
ロックに設ける仮固定用のケーブルを挿通するシース
は、それぞれ複数位置に設けるとともに、これに対応し
て、前記ケーブルの仮定着具およびジャッキもそれぞれ
複数基を用いるようにしたことにある。
The structural portion to be the fixed portion and the sheath for inserting the temporary fixing cable provided in each block are respectively provided at a plurality of positions, and correspondingly, a hypothetical fitting of the cable and The jack is also designed to use multiple units.

【0015】[0015]

【発明の実施の形態】さらに、この発明の実施形態をP
C橋に適用した場合に基づいて具体的に説明する。ま
ず、図1は、PCプレキャストブロック工法に基づくP
C橋において、あらかじめ分割した橋桁の最初のブロッ
クA1 およびA1 をエレクションノーズ52を用いて橋
脚50の柱頭部51の左右側方に吊り込み仮固定する最
初の工程を示すものである。つまりブロックA1 および
1 の被固定部となる構造部に相当する柱頭部51の左
右に張り出す横桁部51aおよび51aの側方への吊り
込む最初の作業工程を示すものである。
Further, an embodiment of the present invention will be described.
A specific description will be given based on the case where it is applied to the C bridge. First, Fig. 1 shows P based on the PC precast block method.
In the C bridge, the first step of temporarily suspending the first blocks A 1 and A 1 of the previously divided bridge girder by suspending them to the left and right sides of the pier head 51 of the pier 50 using the erection nose 52 is shown. That is, it shows the first work process of laterally suspending the cross girders 51a and 51a that project to the left and right of the column head 51 corresponding to the structural part that is the fixed part of the blocks A 1 and A 1 .

【0016】なお、ブロックA1 およびA1 の吊り込み
作業を行う前に、あらかじめ柱頭部51を形成する左右
の横桁部51aおよび51aの上下ウエブには、それぞ
れ横桁部51aおよび51a内の隅部から端面に向け、
すなわち右側隅部から左側の端面へ、左側隅部から右側
の端面に通じる仮固定用のケーブル1を挿通させるシー
ス2および2をそれぞれ配設しておく。
Before the suspension work of the blocks A 1 and A 1 , the upper and lower webs of the left and right lateral girders 51a and 51a forming the column heads 51 are respectively provided in the lateral girders 51a and 51a. From the corner to the end,
That is, the sheaths 2 and 2 for inserting the cable 1 for temporary fixing, which communicates from the left corner to the right end surface, are arranged from the right corner to the left end surface.

【0017】また、ケーブル1の挿入口となる隅部に
は、それぞれ前記仮固定用のケーブル1を一時的にクラ
ンプし、アンカーヘッドとしての機能を持った仮定着具
3および3をそれぞれ設置した。さらに左右の横桁部5
1aおよび51aの内部には、前記仮固定用のケーブル
1を巻装したケーブルドラム4および4を配置した。
At the corners of the cable 1 where the cable 1 is inserted, the temporary fixing cable 1 is temporarily clamped, and hypothetical fittings 3 and 3 each having a function as an anchor head are installed. . Further left and right cross girders 5
Inside the 1a and 51a, cable drums 4 and 4 on which the cable 1 for temporary fixing is wound are arranged.

【0018】図2は、前記図1のB部の拡大詳細図で、
前記横桁部51aの隅部に設置し、仮固定用のケーブル
1のアンカーヘッドとして機能する仮定着具3の取付け
詳細図である。3aは、仮定着具3の取付け支圧板であ
る。
FIG. 2 is an enlarged detailed view of portion B of FIG.
FIG. 6 is a detailed view of the attachment of the assumed attachment 3 that is installed at the corner of the transverse beam portion 51a and functions as an anchor head of the cable 1 for temporary fixing. Reference numeral 3a is a mounting pressure plate for the hypothetical fitting 3.

【0019】図3は、エレクションノーズ52によりブ
ロックA1 およびA1 を吊り込んだのち、すなわち図1
の状態からそのブロックA1 ,A1 を横桁部51aおよ
び51aの側面に仮固定した工程を示す。つまり横桁部
51aおよび51a内に設置したケーブルドラム4およ
び4から、それぞれ仮固定用のケーブル1の端末(先端
部)を隅部に設けた仮定着具3および3、ついでブロッ
クA1 およびA1 のシース2および2(図1参照)を介
して左右の端面側に引き出し、図3で示すようにその端
末に仮定着具3bおよび3b(緊張側)を介してジャッ
キ5および5を連結し、このジャッキ5および5を作動
し、ケーブル1にそれぞれ前記仮定着具3および3を反
力点として緊張力を導入し、ブロックA1 およびA1
それぞれ柱頭部51側に引き寄せ、仮固定させた工程を
示すものである。
FIG. 3 shows that after the blocks A 1 and A 1 are suspended by the erection nose 52, that is, FIG.
From the above state, the steps of temporarily fixing the blocks A 1 and A 1 to the side surfaces of the cross girders 51a and 51a will be described. That is, from the cable drums 4 and 4 installed in the cross girders 51a and 51a, the hypothetical fittings 3 and 3 provided with the ends (tips) of the cables 1 for temporary fixing at the corners, and then the blocks A 1 and A drawer to the end surface side of the left and right through the first sheath 2 and 2 (see FIG. 1), connecting the jacks 5 and 5 via a temporary fixing member 3b and 3b (tight side) to its terminal as shown in Figure 3 , The jacks 5 and 5 were actuated, the tension was introduced into the cable 1 using the assumed fittings 3 and 3 as reaction points, and the blocks A 1 and A 1 were pulled toward the stigma 51 side and temporarily fixed. It shows a process.

【0020】図4は、先に図10で示したブロック
1 ,A2 ,…An の断面構造図と同一であるが、ここ
に示すブロックA1 の異なる点は、先に説明したように
仮固定用のケーブル1を用いて固定させる関係上、その
仮固定用のケーブル1を挿通する専用のシース2をあら
かじめ各ブロックA1 ,A2 ,…An の四隅近くに製作
段階で配設していることである。具体的には、図示のよ
うに四隅近くに合計4本のシース2を配設している。
FIG. 4 is the same as the sectional structural view of the blocks A 1 , A 2 , ... A n shown in FIG. 10, but the difference of the block A 1 shown here is as described above. temporary fixing of the cable 1 on relation to fixed using, each dedicated sheath 2 inserted through the cable 1 in advance blocks a 1 temporary fixing, a 2, ... distribution in fabrication steps near the four corners of a n in That is what we have set up. Specifically, as shown in the drawing, a total of four sheaths 2 are arranged near the four corners.

【0021】前記図3で説明したように、まず最初のブ
ロックA1 およびA1 の柱頭部51側に対する仮固定作
業が終了すると、従来の通り、双方間に本定着用のケー
ブル、つまり緊張材(PC鋼より線)を挿入セットし、
ポストテンションを導入して、そのブロックA1 および
1 を柱頭部51側に本定着させる(図9参照)。そし
て、このブロックA1 およびA1 の本定着作業が終了し
た時点で、ジャッキ5および5によりケーブル1を仮固
定していた仮定着具3,3bおよび3,3bを開放す
る。
As described above with reference to FIG. 3, when the temporary fixing work of the first blocks A 1 and A 1 to the column head 51 side is completed, a cable for main fixing, that is, a tension member, is provided between the blocks A 1 and A 1 as usual. Insert and set (PC steel strand),
Post tension is introduced to permanently fix the blocks A 1 and A 1 to the stigma 51 side (see FIG. 9). Then, at the time when the main fixing work of the blocks A 1 and A 1 is completed, the hypothetical attachments 3, 3b and 3, 3b that temporarily fix the cable 1 by the jacks 5 and 5 are released.

【0022】次に前記仮固定用のケーブル1からのジャ
ッキ5の取り外しと、仮定着具3および3からのケーブ
ル1の開放が終ると、次位のブロックA2 およびA2
図1で説明したようにエレクションノーズ52を利用し
て吊り込む。その作業が終わると、前記吊り込んだブロ
ックA2 およびA2 のそれぞれのシース2および2に前
記ジャッキ5から取り外したケーブル1の端末、つまり
先端部を挿入したのち、その先端部に再度仮定着具3b
および3bを取付け、ジャッキ5および5を連結する。
ついで、図3で説明した要領でケーブル1を緊張し、ブ
ロックA2 をA 1 の外側に仮固定させたのち、その状態
で本定着作業を行う。
Next, the jar from the cable 1 for temporary fixing is
Removal of the kick 5 and the cable from the hypothetical fittings 3 and 3
After the opening of Le 1, the next block A2And A2To
Using the erection nose 52 as explained in FIG.
Hang it. When the work is finished,
Click A2And A2In front of each sheath 2 and 2 of
The end of the cable 1 removed from the jack 5, that is,
After inserting the tip, the hypothetical fitting 3b is again attached to the tip.
And 3b are attached and the jacks 5 and 5 are connected.
Then, tighten the cable 1 as described in FIG.
Lock A2A 1After temporarily fixing it to the outside of the
The main fixing work is done in.

【0023】以下、前記ブロックの吊り込みと、仮固定
と、本定着との作業を順に繰り返すことにより、あらか
じめ分割しておいた各ブロックA1 ,A2 ,…An を一
体的に結合し、所望のPC橋構造体を構築した。
The steps of suspending, temporarily fixing and permanently fixing the blocks are sequentially repeated to integrally combine the previously divided blocks A 1 , A 2 , ... A n. The desired PC bridge structure was constructed.

【0024】ちなみに、図5は、ブロックA1 以下ブロ
ックA3 を本定着するとともに、仮固定用のケーブル1
の開放と、ジャッキ5の取り外しを行い、つぎのブロッ
クA 4 を吊り込む工程を示す。
By the way, FIG. 5 shows a block A.1Below
Click AThreeThe cable 1 for permanent fixing and temporary fixing
Open and remove the jack 5, and then
Ku A FourThe process of suspending is shown.

【0025】さらに図6は、前記図5の工程に引き続
き、ブロックA4 およびA4 に、前記仮固定用ケーブル
1を通し、ジャッキ5を作動してブロックA4 およびA
4 を仮固定させた工程を示すものである。
Furthermore 6, subsequent to step of FIG. 5, the block A 4 and A 4, through the temporary fixing cables 1, block A 4 and A by operating the jack 5
It shows the process of temporarily fixing 4 .

【0026】[0026]

【実施例】本発明によるブロックの仮固定方法は、以上
説明した手順によって仮固定することを特徴とするもの
で、従来のように、あらかじめブロック等に仮固定手段
としての継手部材(カップリング)等を組み付けるよう
な手段方法を採用していない点にある。つまりノン・カ
ップラー方式により仮固定させるようにしたことにあ
る。
DETAILED DESCRIPTION OF THE PREFERRED EMBODIMENTS The method for temporarily fixing a block according to the present invention is characterized in that the block is temporarily fixed by the procedure described above. As in the prior art, a joint member (coupling) as a temporary fixing means is previously provided on the block or the like. The point is that the method of assembling etc. is not adopted. In other words, the non-coupler method is used for temporary fixing.

【0027】なお、実施例においては、図1および図3
以下に示すように、仮固定用のケーブル1は、左右2基
づつのケーブルドラム4を設置し、合計4本のケーブル
1を用いて仮固定させるようにした。そのため、このケ
ーブル1を仮固定する仮定着具3は、図示のように柱頭
部51を形成する横桁部51aおよび51aと左右ブロ
ックA1 およびA1 の内部上下四隅に設けた。
In the embodiment, FIGS. 1 and 3 are used.
As shown below, the cable 1 for temporary fixing has two left and right cable drums 4 installed, and a total of four cables 1 are used for temporary fixing. Therefore, the hypothetical fittings 3 for temporarily fixing the cable 1 are provided in the horizontal girders 51a and 51a forming the column head 51 and the upper and lower four corners inside the left and right blocks A 1 and A 1 as shown in the figure.

【0028】そして右側に設置したケーブルドラム4お
よび4からのケーブル1は、それぞれ左側の横桁部51
aの上下ウエブを介してブロックA1 ,A2 ,…An
へ誘導し、逆に左側に設置したケーブルドラム4および
4からのケーブル1は、それぞれ右側の横桁部51aの
上下ウエブを介してブロックA1 ,A2 ,…An へ誘導
するよう構成した。
The cables 1 from the cable drums 4 and 4 installed on the right side are respectively connected to the transverse beam portion 51 on the left side.
The cables 1 from the cable drums 4 and 4 installed on the left side are guided to the blocks A 1 , A 2 , ... A n side through the upper and lower webs of a, respectively. block A 1, A 2 through, was constructed to direct to ... A n.

【0029】その結果、この実施例においては、ブロッ
クA1 ,A2 ,…An の仮固定、本定着は、橋脚50の
柱頭部51を出発点として左右に対称的に施工するよう
になっている。つまり、対称的にブロックを組み付け施
工するようにしている。しかし、これに限定されるもの
ではない。片持ち形式に組み付け施工することも、もち
ろん可能であり、かつ非対称的に施工することも可能で
ある。
As a result, in this embodiment, the blocks A 1 , A 2 , ... A n are temporarily fixed and permanently fixed so that the pillar heads 51 of the piers 50 are used as starting points and are symmetrically installed on the left and right sides. ing. That is, the blocks are symmetrically assembled and constructed. However, it is not limited to this. It is of course possible to assemble and install in a cantilever form, and it is also possible to carry out asymmetrical construction.

【0030】さらにケーブル1を一時的にクランプし、
仮固定する仮定着具3、すなわち図2で示した仮定着具
3としては、挿通したケーブル1に緊張力をかけると自
動的にそのケーブル1をクランプし、逆に緊張力を緩め
ると、クランプが自動的に開放されるクサビ機構を備え
た仮定着具3を用いた。また仮固定用のケーブル1とし
ては、本定着用とケーブルと同様PC鋼より線を用いる
とともに、ケーブル1に緊張力を導入するジャッキ5と
しては、センターホール型のジャッキを使用した。
Further, the cable 1 is temporarily clamped,
Assuming that the temporarily fixed fitting 3 is temporarily fixed, that is, the assumed fitting 3 shown in FIG. 2, when the tension force is applied to the inserted cable 1, the cable 1 is automatically clamped, and conversely, when the tension force is loosened, the clamp is made. The hypothetical garment 3 provided with a wedge mechanism that automatically opens is used. Further, as the cable 1 for temporary fixing, PC steel stranded wire was used similarly to the main fixing and the cable, and as the jack 5 for introducing a tension force to the cable 1, a center hole type jack was used.

【0031】[0031]

【発明の効果】この発明によるブロックの仮固定方法
は、以上実施例を通して説明したように、従来の仮固定
手段にみられるように、ブラケットや切欠きを利用した
PC鋼材による仮固定方式でなく、ケーブルを用いたノ
ン・カップラー方式による連結仮固定方式としたので、
従来のブロック工法に比較し、ブロックの組立作業が手
際よく、しかもより効果的に展開できる。特に各ブロッ
クに仮固定手段としての切欠部や埋設金具を設ける必要
がないため本来的にPCプレキャストブロックが持つ優
位性をさらにレベルアップさせ、構造的な強度不安を解
消することができる。しかも仮固定の主要な役割を分担
する部材としてPC鋼より線からなるケーブルを用い、
これを各ブロックにあらかじめ設置したシースを介して
誘導し、緊張力を導入するようにしたので、そのケーブ
ルの配設および取り扱いが容易で、PC橋にみられるよ
うに橋桁断面形状が変化する、つまり下面を湾曲するア
ーチに形成した橋梁の場合、その下面湾曲線に沿ってケ
ーブルを誘導させることができ、仮固定方法として無理
なく適用できる従来技術にはみられない効果を発揮する
ことがてきる。さらに仮固定作業の終了後は、そのケー
ブル自体に緊張力を導入することにより、橋梁自体にポ
ストテンションを加えて、PC橋としての部材要素とし
て残すことも可能である。
As described above with reference to the embodiments, the method of temporarily fixing a block according to the present invention is not the method of temporarily fixing a block of PC steel using brackets or notches, as seen in the conventional means for temporarily fixing. Since a non-coupler type temporary fixing method using cables is used,
Compared with the conventional block construction method, the work of assembling the block is more efficient and can be more effectively developed. In particular, since it is not necessary to provide notches or embedded metal fittings as temporary fixing means in each block, it is possible to further improve the inherent advantage of the PC precast block and eliminate structural anxiety. Moreover, a cable made of PC steel stranded wire is used as a member that shares the main role of temporary fixing,
Since this was guided through a sheath installed in advance in each block to introduce a tension force, it is easy to arrange and handle the cable, and the cross-section shape of the bridge girder changes as seen in a PC bridge. In other words, in the case of a bridge whose lower surface is curved, it is possible to guide the cable along the lower curved line, and it is possible to exert an effect not seen in the prior art that can be reasonably applied as a temporary fixing method. It Further, after the temporary fixing work is completed, it is possible to apply a post-tension to the bridge itself by introducing a tension force to the cable itself and leave it as a member element as a PC bridge.

【図面の簡単な説明】[Brief description of drawings]

【図1】橋脚柱頭部の左右両側にあらかじめ分割した主
桁のブロックを吊り込む工程図である。
FIG. 1 is a process diagram of suspending blocks of main girders divided in advance on both left and right sides of a pier column head.

【図2】図1のB部の拡大詳細図で、仮定着具の取付け
部を示す。
FIG. 2 is an enlarged detailed view of a portion B of FIG. 1, showing a mounting portion of a hypothetical garment.

【図3】ブロックを柱頭部の側面に仮固定させる工程図
である。
FIG. 3 is a process diagram of temporarily fixing a block to a side surface of a stigma.

【図4】ブロックの断面構造図である。FIG. 4 is a sectional structural view of a block.

【図5】ブロックA1 ……A3 の本定着作業が終了し、
仮定着具に対するケーブルの開放と、ジャッキとを取り
外し、次のブロックA4 を吊り込む工程図である。
[Fig. 5] Block A 1 ... A 3 main fixing work is completed,
And the opening of the cable with respect to the temporary fixing member, remove the jack is a process diagram Komu hanging next block A 4.

【図6】ブロックA1 ……A4 を仮固定させた工程図で
ある。
FIG. 6 is a process diagram in which blocks A 1 ... A 4 are temporarily fixed.

【図7】PCプレキャストブロック工法によるPC橋の
構造図である。
FIG. 7 is a structural diagram of a PC bridge made by a PC precast block method.

【図8】分割したブロックを橋脚の柱頭部両側に仮固定
させる工程図である。
FIG. 8 is a process diagram of temporarily fixing the divided blocks to both sides of the pier sill.

【図9】分割したブロックA1 ……A5 を本定着し、6
個目のブロックA6 を吊り込み仮固定する工程図を示
す。
FIG. 9: The divided blocks A 1 ... A 5 are permanently fixed, and 6
The process drawing of suspending and temporarily fixing the block A 6 is shown.

【図10】従来のブロックの断面構造図である。FIG. 10 is a sectional structural view of a conventional block.

【符号の説明】[Explanation of symbols]

1 ,A2 ,…An …ブロック(橋桁) 50…橋脚(ピア) 51…柱頭部 51a…横桁部 52…エレクションノーズ 52a…揚重機(ウインチ) 53…仮固定部材 54…緊張材 55…シース 56,57…突起部 58…タイロッドバー 1…ケーブル(仮固定用) 2…シース 3…仮定着具 3a…支圧板 3b…仮定着具(緊張側) 4…ケーブルドラム 5…ジャッキ(センターホール型)A 1 , A 2 , ... A n ... Block (bridge girder) 50 ... Bridge pier (pier) 51 ... Pillar head 51a ... Transverse part 52 ... Erection nose 52a ... Lifting machine (winch) 53 ... Temporary fixing member 54 ... Tension material 55 ... Sheath 56, 57 ... Projection 58 ... Tie rod bar 1 ... Cable (for temporary fixing) 2 ... Sheath 3 ... Assumption fitting 3a ... Pressure plate 3b ... Assumption fitting (tension side) 4 ... Cable drum 5 ... Jack (center) Hall type)

Claims (2)

【特許請求の範囲】[Claims] 【請求項1】 コンクリート構造物をあらかじめ複数の
ブロックに分割し、この分割したブロックを被固定部と
なる構造部に順次結合させるとともに仮固定し、仮固定
したブロックにポストテンション用の緊張材を通し、こ
れに緊張力を導入してブロックを一体的に定着固定させ
るプレストレストプレキャストコンクリート構造物を建
造するPCプレキャストブロック工法において、 前記被固定部となる構造部と、各ブロックにあらかじめ
仮固定用のケーブルを挿通するシースを設けておくとと
もに、被固定部となる構造部におけるシース入口側に
は、仮固定用のケーブルを一時的にクランプする仮定着
具と、仮固定用のケーブルを巻装したケーブルドラムと
を設置し、 前記被固定部の構造部側方に、最初のブロックを吊り込
むとともに、前記ケーブルドラムからケーブルを引き出
し、被固定部となる構造部側の前記仮定着具と、前記吊
り込んだブロックのシースを介してケーブルの先端部を
ブロックの前端部に引き出す第1工程と、 前記ブロックの前端部に引き出したケーブルの先端部に
ジャッキを連結し、このジャッキによってケーブルに前
記仮定着具を反力点として緊張力を導入し、ブロックを
前記被固定部の構造部側に引き寄せ仮固定させる第2工
程と、 その状態で、前記被固定部の構造部とブロックとの間に
ポストテンションを導入して双方を一体的に本定着させ
る第3工程と、 前記構造部側の仮定着具からケーブルを解放するととも
に、ジャッキをケーブルの先端部から取り外し、次位の
ブロックを前記本定着させたブロックの側方に吊り込
み、その吊り込んだブロックのシースに前記ジャッキか
ら取り外したケーブルの先端部を挿入して前端部に引き
出し、引き出したケーブルの先端部にジャッキを再連結
して緊張し、次位ブロックを仮固定する第4工程と、 以下、前記第2工程から第4工程を順次繰り返し、ブロ
ックをケーブルを介して一体的に仮固定させることを特
徴とするノン・カップラーによるPCプレキャストブロ
ック工法におけるブロックの仮固定方法。
1. A concrete structure is divided into a plurality of blocks in advance, and the divided blocks are sequentially joined to a structural portion to be a fixed portion and temporarily fixed, and a tension material for post tension is attached to the temporarily fixed block. In the PC precast block method of constructing a prestressed precast concrete structure through which tension is introduced to fix and integrally fix the block, the structural part to be the fixed part and the temporary fixing in advance to each block. A sheath for inserting the cable is provided, and a hypothetical fastener for temporarily clamping the cable for temporary fixing and a cable for temporary fixing are wound around the sheath entrance side of the structure part to be fixed. Install the cable drum and suspend the first block to the side of the structure of the fixed part, A first step of pulling out a cable from the cable drum and pulling out a tip end portion of the cable to a front end portion of the block through the hypothetical fitting on the side of the structural portion to be a fixed portion and a sheath of the suspended block; A jack is connected to the front end of the cable pulled out to the front end, and a tension force is introduced into the cable by using the hypothetical fastener as a reaction point, and the block is pulled to the structural portion side of the fixed portion and temporarily fixed. From the second step, the third step in which the post tension is introduced between the structural portion of the fixed portion and the block to integrally main-fix both of them, While releasing the cable, remove the jack from the tip of the cable, hang the next block to the side of the block where the main fixing is done, A fourth step of inserting the distal end of the cable removed from the jack into the sheath of the cord and pulling it out to the front end, reconnecting the jack to the distal end of the pulled-out cable and tensioning it, and temporarily fixing the next block. Hereinafter, the block temporary fixing method in the PC precast block construction method using a non-coupler, characterized in that the second step to the fourth step are sequentially repeated to integrally temporarily fix the block via a cable.
【請求項2】前記被固定部となる構造部と、各ブロック
に設ける仮固定用のケーブルを挿通するシースは、それ
ぞれ複数位置に設けるとともに、これに対応する前記ケ
ーブルの仮定着具およびジャッキもそれぞれ複数基を用
いることを特徴とする請求項1記載のノン・カップラー
によるPCプレキャストブロック工法におけるブロック
の仮固定方法。
2. The structure part to be the fixed part and the sheath for inserting the temporary fixing cable provided in each block are respectively provided at a plurality of positions, and corresponding hypothetical fasteners and jacks of the cable are also provided. A method for temporarily fixing a block in a PC precast block method using a non-coupler according to claim 1, wherein a plurality of groups are used for each.
JP24463695A 1995-09-22 1995-09-22 Temporary fixing method of block in PC precast block method by non-coupler Expired - Fee Related JP3608751B2 (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
JP24463695A JP3608751B2 (en) 1995-09-22 1995-09-22 Temporary fixing method of block in PC precast block method by non-coupler

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
JP24463695A JP3608751B2 (en) 1995-09-22 1995-09-22 Temporary fixing method of block in PC precast block method by non-coupler

Publications (2)

Publication Number Publication Date
JPH0988014A true JPH0988014A (en) 1997-03-31
JP3608751B2 JP3608751B2 (en) 2005-01-12

Family

ID=17121708

Family Applications (1)

Application Number Title Priority Date Filing Date
JP24463695A Expired - Fee Related JP3608751B2 (en) 1995-09-22 1995-09-22 Temporary fixing method of block in PC precast block method by non-coupler

Country Status (1)

Country Link
JP (1) JP3608751B2 (en)

Cited By (9)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
KR20000063515A (en) * 2000-07-19 2000-11-06 양현승 Pier Structure Construction Method Utilizing Precast Contrete Block And Pier Thereof
JP2001049622A (en) * 1999-08-05 2001-02-20 Vsl Japan Kk Bridge erecting apparatus and bridge erecting method
JP2001262513A (en) * 2000-03-17 2001-09-26 Nippon Steel Corp Cable stayed bridge having composite synthetic steel tube beam material with slab and method of installing the beam material
KR100497803B1 (en) * 2001-09-26 2005-06-29 (주)신성엔지니어링 Method of construction for building PSC(prestressed concrete) box girder bridge using precasttype anchorage segments
KR100924746B1 (en) * 2009-03-26 2009-11-05 (주)대우건설 Method for constructing precast coping by using multi-step tensioning
KR100981982B1 (en) * 2010-06-11 2010-09-13 (주)대우건설 Precast coping lifting system
JP2017082496A (en) * 2015-10-28 2017-05-18 西日本高速道路株式会社 Floor slab structure of steel bridge, floor slab replacement method of steel bridge and precast floor slab
JP2018053496A (en) * 2016-09-27 2018-04-05 三井住友建設株式会社 Bridge girder erection method for multiple span continuous bridge
CN109537472A (en) * 2019-01-17 2019-03-29 中交四公局第十工程有限公司 A kind of prefabricated beam end bed die turning hinge device and its application method

Families Citing this family (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN111501576A (en) * 2020-05-18 2020-08-07 湖南交通国际经济工程合作有限公司 Standardized prefabrication construction method for bridge beam plate and standardized prefabricated beam plate

Cited By (10)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP2001049622A (en) * 1999-08-05 2001-02-20 Vsl Japan Kk Bridge erecting apparatus and bridge erecting method
JP2001262513A (en) * 2000-03-17 2001-09-26 Nippon Steel Corp Cable stayed bridge having composite synthetic steel tube beam material with slab and method of installing the beam material
KR20000063515A (en) * 2000-07-19 2000-11-06 양현승 Pier Structure Construction Method Utilizing Precast Contrete Block And Pier Thereof
KR100497803B1 (en) * 2001-09-26 2005-06-29 (주)신성엔지니어링 Method of construction for building PSC(prestressed concrete) box girder bridge using precasttype anchorage segments
KR100924746B1 (en) * 2009-03-26 2009-11-05 (주)대우건설 Method for constructing precast coping by using multi-step tensioning
KR100981982B1 (en) * 2010-06-11 2010-09-13 (주)대우건설 Precast coping lifting system
JP2017082496A (en) * 2015-10-28 2017-05-18 西日本高速道路株式会社 Floor slab structure of steel bridge, floor slab replacement method of steel bridge and precast floor slab
JP2018053496A (en) * 2016-09-27 2018-04-05 三井住友建設株式会社 Bridge girder erection method for multiple span continuous bridge
CN109537472A (en) * 2019-01-17 2019-03-29 中交四公局第十工程有限公司 A kind of prefabricated beam end bed die turning hinge device and its application method
CN109537472B (en) * 2019-01-17 2023-08-15 中交四公局第十工程有限公司 Precast beam end bottom die rotating hinge device and application method thereof

Also Published As

Publication number Publication date
JP3608751B2 (en) 2005-01-12

Similar Documents

Publication Publication Date Title
WO2019206193A1 (en) Prefabricated wall panel, connection structure thereof and construction method therefor
WO2011055996A2 (en) Method for constructing a suspension bridge using temporary cables under tensionless stay cable conditions, and temporary cable for same
JPS5869908A (en) Free tension material, method and apparatus for producing and assembling obliquely tentioned cable of bridge
JPH0988014A (en) Temporary fixing method of block in pc precast block method by non-coupler
CN113463502B (en) Prefabricated assembled corrugated steel web composite bridge and cantilever construction method thereof
JP3797560B2 (en) Bridge segment and its construction method
JP3924192B2 (en) Bridge superstructure and substructure connection structure and its construction method
JP3108619B2 (en) Method of introducing prestress into concrete block for anchoring outer cable of concrete girder
JP2003138523A (en) Construction method for tension string girder bridge
KR100348633B1 (en) Apparatus to restrain prestress structure
WO2016200083A1 (en) Prestressed concrete girder
KR102116868B1 (en) Post tension press method for intrusion block of grout in PC joint connection
JP2807845B2 (en) Construction method of diagonal material for Stypanel Bridge
JPH084031A (en) Building method of lower part structure
CN220133153U (en) Assembled concrete type steel frame column-steel frame beam joint connection structure
JPS63284304A (en) Execution of bridge central closure part in cantilevered type construction method
JPH0416605A (en) Installation and tension method of diagonal tension cable
JPH09279518A (en) King post used for cable trussed bridge and erection method thereof
KR200268501Y1 (en) Dual Directional Prestressed Tendon Anchoring Apparatus
JPH11181880A (en) Connective structure of steel member with closed section
JPH0688349A (en) Connection structure of pc girder and post
CN112659357A (en) Steel bar connecting structure of prefabricated part and construction method thereof
JP3198642B2 (en) Prestressed concrete board
CN116591071A (en) Anchor cable buckling device and method for combined beam cable-stayed bridge no-cable area no-bracket construction
JP2004068332A (en) Tension fixing method of temporary cable

Legal Events

Date Code Title Description
A977 Report on retrieval

Free format text: JAPANESE INTERMEDIATE CODE: A971007

Effective date: 20040922

TRDD Decision of grant or rejection written
A01 Written decision to grant a patent or to grant a registration (utility model)

Free format text: JAPANESE INTERMEDIATE CODE: A01

Effective date: 20041006

A61 First payment of annual fees (during grant procedure)

Free format text: JAPANESE INTERMEDIATE CODE: A61

Effective date: 20041008

R150 Certificate of patent or registration of utility model

Free format text: JAPANESE INTERMEDIATE CODE: R150

LAPS Cancellation because of no payment of annual fees