JPH08277515A - Breakwater structure and breakwater unit and breakwater by use of the unit - Google Patents

Breakwater structure and breakwater unit and breakwater by use of the unit

Info

Publication number
JPH08277515A
JPH08277515A JP7107019A JP10701995A JPH08277515A JP H08277515 A JPH08277515 A JP H08277515A JP 7107019 A JP7107019 A JP 7107019A JP 10701995 A JP10701995 A JP 10701995A JP H08277515 A JPH08277515 A JP H08277515A
Authority
JP
Japan
Prior art keywords
breakwater
pile
foundation
steel pipe
bottom slab
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
JP7107019A
Other languages
Japanese (ja)
Inventor
Kenji Ito
賢治 伊東
Yasuo Kurihara
安男 栗原
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Mitsui Construction Co Ltd
Original Assignee
Mitsui Construction Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Mitsui Construction Co Ltd filed Critical Mitsui Construction Co Ltd
Priority to JP7107019A priority Critical patent/JPH08277515A/en
Publication of JPH08277515A publication Critical patent/JPH08277515A/en
Pending legal-status Critical Current

Links

Classifications

    • YGENERAL TAGGING OF NEW TECHNOLOGICAL DEVELOPMENTS; GENERAL TAGGING OF CROSS-SECTIONAL TECHNOLOGIES SPANNING OVER SEVERAL SECTIONS OF THE IPC; TECHNICAL SUBJECTS COVERED BY FORMER USPC CROSS-REFERENCE ART COLLECTIONS [XRACs] AND DIGESTS
    • Y02TECHNOLOGIES OR APPLICATIONS FOR MITIGATION OR ADAPTATION AGAINST CLIMATE CHANGE
    • Y02ATECHNOLOGIES FOR ADAPTATION TO CLIMATE CHANGE
    • Y02A10/00TECHNOLOGIES FOR ADAPTATION TO CLIMATE CHANGE at coastal zones; at river basins
    • Y02A10/11Hard structures, e.g. dams, dykes or breakwaters

Landscapes

  • Revetment (AREA)

Abstract

PURPOSE: To easily construct a breakwater even on the bottom ground of 20m or deeper sea. CONSTITUTION: An upper concrete block 11 with the upper length L2 is connected to a bottom slab concrete block 11 with the length L1 of bottom slab forming reducing holes 12 for the lifting pressure through the front face steel pipe pile 13, the first stay pile 15, and the second stay pile 16. In this time, the first stay pile is arranged to connect the back face 13c of the front face steel pipe pile and the bottom slab concrete block so that the front face of the front face steel pipe pile turns to the diagonal upward direction.

Description

【発明の詳細な説明】Detailed Description of the Invention

【0001】[0001]

【産業上の利用分野】本発明は、水深20m以上の大水
深において使用する防波堤を構築するのに好適な防波堤
構造と、防波堤ユニット及び該ユニットを用いた防波堤
に関する。
BACKGROUND OF THE INVENTION 1. Field of the Invention The present invention relates to a breakwater structure suitable for constructing a breakwater to be used at a deep water depth of 20 m or more, a breakwater unit, and a breakwater using the breakwater unit.

【0002】[0002]

【従来の技術】従来、水深20m程度の大水深下の海底
地盤上に防波堤を構築する場合、防波堤を構築すべき海
底地盤上に、基礎部として捨石マウンドを形成し、その
捨石マウンド上に、海上輸送してきたコンクリート製の
ケーソンを沈下させて設置する方法が多く取られてい
た。(以下、「捨石マウンド+ケーソン方式」と称す
る。)
2. Description of the Related Art Conventionally, when constructing a breakwater on a submarine ground under a deep water of about 20 m, a rubble mound is formed as a foundation on the submarine ground where the breakwater is to be constructed, and on the rubble mound, There were many methods of sinking and installing concrete caisson that had been transported by sea. (Hereinafter, it is called "Scrap stone mound + caisson method".)

【0003】[0003]

【発明が解決しようとする課題】しかし、この捨石マウ
ンド+ケーソン方式では、ケーソンを地上のヤード等に
おいて製作して海上輸送するため、水深20m程度に対
応したケーソンを製作することが限界である。そこで、
ケーソンの大型化に対して捨石マウンドの高さを高くす
ることにより、ケーソン自体の高さを抑えてヤードにお
いて製作することも考えられる。しかし、捨石マウンド
を高くするためには、大量の捨石が必要となり、今度は
捨石の確保が困難となる。また、他の防波堤構築方法と
して、直杭式、組杭式など鋼管杭を海底地盤に打ち込ん
で防波堤を構築する方法がある。しかし、大水深に適用
した実績がなく信頼性に欠けるので、大水深用防波堤の
設置に適用するには無理がある。そこで、本発明は、上
記事情に鑑み、水深20m以上の大水深下の海底地盤上
においても耐久性の高い防波堤を容易に構築でき、また
省資源化、省力化して構築でき、更に防波堤を確実に海
底地盤上に設置することが可能な防波堤構造、防波堤ユ
ニット及び該ユニットを用いた防波堤を提供することを
目的とする。
However, in this rubble mound + caisson system, since the caisson is manufactured in a yard on the ground and transported by sea, it is limited to manufacture a caisson corresponding to a water depth of about 20 m. Therefore,
It is also possible to increase the height of the rubble mound to increase the size of the caisson, thereby suppressing the height of the caisson itself and manufacturing it in the yard. However, in order to raise the rubble mound, a large amount of rubble is required, and this time it becomes difficult to secure rubble. As another breakwater construction method, there is a method of driving a steel pipe pile such as a straight pile type or a pile pile type into the seabed to construct a breakwater. However, since it has not been applied to deep water and lacks reliability, it is not possible to apply it to the installation of breakwaters for deep water. Therefore, in view of the above circumstances, the present invention can easily construct a breakwater with high durability even on a seabed under a deep water depth of 20 m or more, and can be constructed with resource saving and labor saving. Another object of the present invention is to provide a breakwater structure, a breakwater unit and a breakwater using the unit, which can be installed on the seabed.

【0004】[0004]

【課題を解決するための手段】即ち本発明のうち第1の
発明は、海底地盤(60)上に設けられる防波堤におい
て、前記海底地盤上に、基礎部(3)を防波堤構築方向
に沿って設け、前記基礎部上に、底版部(11)を該基
礎部に沿って設け、前記底版部に、防波部(17)を杭
部材(13、15、16)を介して接続する形で設けて
構成される。また本発明のうち第2の発明は、第1の発
明において、前記底版部に、揚圧力低減穴(12)を該
底版部を上下方向に貫通する形で設けて構成される。更
に本発明のうち第3の発明は、所定長さ(L1)に形成
されたコンクリートから成る底版部(11)を有し、前
記底版部に、所定長さ(L2)に形成されたコンクリー
トから成る防波部(17)を鋼管から成る杭部材(1
3、15、16)を介して接続するようにして構成され
る。更に本発明のうち第4の発明は、第3の発明におい
て、前記底版部に、揚圧力低減穴(12)を該底版部を
上下方向に貫通する形で設けて構成される。更に本発明
のうち第5の発明は、第3の発明において、前記杭部材
は、第1の杭部材(13、15)及び第2の杭部材(1
6)から成り、前記第1の杭部材は、前面鋼管矢板(1
3)と補助控え杭(15)から成り、前記前面鋼管矢板
には、波を受ける前面部(13d)と、該前面部とは背
向する背面部(13c)が形成されており、前記補助控
え杭は、前記前面鋼管矢板の背面部と前記底版部を接続
する形で設けられていることを特徴として構成される。
更に本発明のうち第6の発明は、第3の発明において、
前記杭部材は、第1の杭部材(13、15)及び第2の
杭部材(16)から成り、前記第1の杭部材は、波を受
ける前面部(13d)を有しており、前記前面部が、斜
め上方を向いていることを特徴として構成される。更に
本発明のうち第7の発明は、海底地盤(60)上に設け
られる防波堤において、前記海底地盤上に、捨石(5)
から成る基礎部(3)を防波堤構築方向に沿って設け、
前記基礎部上に、第3の発明における防波堤ユニット
(10)を、該基礎部に沿って複数個配置して構成され
る。なお、括弧内の番号等は、図面における対応する要
素を示す便宜的なものであり、従って、本記述は図面上
の記載に限定拘束されるものではない。以下の「作用」
の欄についても同様である。
[Means for Solving the Problems] That is, the first aspect of the present invention is to provide a breakwater provided on the seabed (60), in which the foundation (3) is provided on the seabed along the breakwater construction direction. A bottom plate part (11) is provided on the base part along the base part, and a wave preventing part (17) is connected to the bottom plate part through pile members (13, 15, 16). It is provided and configured. The second invention of the present invention is the first invention according to the first invention, wherein the bottom plate portion is provided with a lifting pressure reducing hole (12) so as to vertically penetrate the bottom plate portion. A third aspect of the present invention further comprises a bottom slab portion (11) made of concrete having a predetermined length (L1), wherein the bottom slab portion is made of concrete having a predetermined length (L2). The wave breaker (17) consisting of a pile member (1
3, 15, 16). Further, a fourth aspect of the present invention is the third aspect of the invention, wherein the bottom plate portion is provided with a lifting pressure reducing hole (12) so as to vertically penetrate the bottom plate portion. Furthermore, 5th invention among this invention is a 3rd invention, Comprising: The said pile member is a 1st pile member (13, 15) and a 2nd pile member (1).
6), wherein the first pile member is a front steel pipe sheet pile (1
3) and auxiliary restraint piles (15), the front steel pipe sheet pile is formed with a front surface portion (13d) for receiving waves and a rear surface portion (13c) facing away from the front surface portion. The retaining pile is characterized in that it is provided so as to connect the rear surface portion of the front steel pipe sheet pile and the bottom plate portion.
A sixth aspect of the present invention is the same as the third aspect,
The pile member comprises a first pile member (13, 15) and a second pile member (16), the first pile member having a front part (13d) for receiving waves, and The front surface is configured to face obliquely upward. Furthermore, the seventh invention of the present invention is the breakwater provided on the seabed (60), wherein the rubble (5) is provided on the seabed.
The foundation (3) consisting of is installed along the breakwater construction direction,
A plurality of breakwater units (10) according to the third aspect of the invention are arranged on the base portion along the base portion. The numbers in parentheses are for convenience of showing the corresponding elements in the drawings, and therefore the present description is not limited to the description in the drawings. The following "action"
The same applies to the column of.

【0005】[0005]

【作用】上記した構成により、本発明のうち第1の発明
は、大水深下の海底地盤(60)上に防波堤を構築する
場合に、基礎部(3)を高くすることなく、かつ大量の
コンクリートを使用することなく、それら底版部(1
1)と防波部(17)を容易に接続し得るように作用す
る。また本発明のうち第2の発明及び第4の発明は、底
版部(11)の下方に浸入した浸透水などは揚圧力低減
穴(12)を通して底版部の下方から上方へ向けて流す
ことができるように作用する。更に本発明のうち第3の
発明は、陸上ヤードなどにおいて底版部(11)、杭部
材(13、15、16)、防波部(17)などと分割し
て製作し得るように作用する。また杭部材の長さを長く
することにより大型の防波堤ユニットを形成し得るよう
に作用する。更に本発明のうち第5の発明は、補助控え
杭(15)が前面鋼管矢板(13)を背面部(13c)
側から支持することにより、前面鋼管矢板が前面部(1
3d)で波の力を受けた際に該前面鋼管矢板に生じる曲
げモーメントを低減するように作用する。更に本発明の
うち第6の発明は、前面鋼管矢板(13)の前面部(1
3d)で受けた波の力の分力が、底版部(11)を海底
地盤(60)上の基礎部(3)に押し付ける方向に働く
ように作用する。更に本発明のうち第7の発明は、防波
堤ユニット(1)を海上輸送して防波堤を構築すべき位
置に形成された基礎部(3)上に沈設するだけで、防波
堤を構築し得るように作用する。
With the above-mentioned structure, the first aspect of the present invention is such that, when constructing a breakwater on the seabed (60) under deep water, the foundation (3) does not need to be raised, and a large amount of the foundation (3) is used. Without using concrete, those bottom slabs (1
It works so that 1) and the breakwater (17) can be easily connected. In addition, in the second and fourth aspects of the present invention, the permeated water that has penetrated below the bottom slab (11) can flow upward from below the bottom slab through the lifting pressure reduction hole (12). Act as you can. Furthermore, the third aspect of the present invention acts so that it can be manufactured separately from the bottom slab portion (11), the pile members (13, 15, 16), the wave preventing portion (17) and the like in a land yard or the like. Further, by increasing the length of the pile member, it works so that a large breakwater unit can be formed. Further, in a fifth aspect of the present invention, the auxiliary stay pile (15) has the front steel pipe sheet pile (13) at the back portion (13c).
By supporting from the side, the front steel pipe sheet pile is
In 3d), it acts to reduce the bending moment generated in the front steel pipe sheet pile when it receives the wave force. Furthermore, a sixth aspect of the present invention is the front part (1) of the front steel pipe sheet pile (13).
The component of the wave force received in 3d) acts so as to work in the direction of pressing the bottom slab (11) against the foundation (3) on the seabed (60). Furthermore, the seventh aspect of the present invention enables the breakwater to be constructed by simply transporting the breakwater unit (1) over the sea and submerging it on the foundation (3) formed at the position where the breakwater should be constructed. To work.

【0006】[0006]

【実施例】以下、本発明の実施例を図面に基づき説明す
る。図1は、本発明による防波堤構造と、防波堤ユニッ
ト及び該ユニットを用いた防波堤が適用された防波堤の
一実施例を示す斜視図である。
Embodiments of the present invention will be described below with reference to the drawings. FIG. 1 is a perspective view showing an embodiment of a breakwater structure according to the present invention, a breakwater unit, and a breakwater to which the breakwater using the breakwater unit is applied.

【0007】本発明による防波堤構造並びに防波堤ユニ
ットを用いた防波堤が適用された防波堤1は、図1に示
すように、防波堤を構築すべき位置の海底地盤60上に
所定の防波堤構築長さに亙り伸延する形で構築されてい
る。つまり、防波堤1は、波HEIを防御する防波面1
aを有しており、防波面1aは、波HEIが伝わる波浪
伝播方向(矢印E、F方向)と交差する方向である防波
堤構築方向(矢印C、D方向)に沿って前記防波堤構築
長さに亙り形成されている。また防波面1aは、水深S
Lに対応して海水63中から海水面63a上に突出する
までの所定の防波高さに形成されている。なお、海底地
盤60は、海水63の海水面63aから地表面60aま
での水深SLが40m程度の大水深下にある。防波堤1
は、基礎捨石部3及び複数の防波堤ユニット10から構
成されており、防波堤ユニット10は、基礎捨石部3に
沿って複数個配置されている。基礎捨石部3は、捨石5
が基礎高さT0に積層される形で形成されており、基礎
捨石部3は、防波堤構築方向に沿って設けられている。
基礎捨石部3の上部には、略平坦で防波堤ユニット10
を設置可能な基礎面3aが形成されており、基礎面3a
は、基礎幅D0で、かつ前記防波堤構築長さに対応して
防波堤構築方向(矢印C、D方向)に沿って形成されて
いる。本発明による防波堤ユニットが適用された防波堤
ユニット10は、図1に示すように、コンクリートなど
から成る底版コンクリート部11を有しており、底版コ
ンクリート部11は、底版高さT1、底版幅D1(D1
<D0)、底版長さL1の直方体形状のブロックであ
る。底版コンクリート部11には、小径の揚圧力低減穴
12が該底版コンクリート部11を上下方向(矢印A、
B方向)に貫通する形で多数形成されており、揚圧力低
減穴12は、海水63の浸透水65などが通水し得る形
で形成されている。底版コンクリート部11の上方(矢
印A方向)には、コンクリートなどから成る上部コンク
リート部17が、前面鋼管矢板13及び第1控え杭15
と、第2控え杭16といった2種の杭部材を介して接続
する形で設けられている。上部コンクリート部17は、
上部幅D2、上部長さL2(=L1)の逆T字断面形状
のブロックであり、上部コンクリート部17の前面17
a及び背面17bは、それぞれ上部高さT2の階段状に
形成されている。つまり、底版コンクリート部11に
は、図1に示すように、複数の前面鋼管矢板13が立設
されており、前面鋼管矢板13は、沖側(矢印E方向)
下方(矢印B方向)から岸側(矢印F方向)上方(矢印
A方向)に向けて傾斜している。これら前面鋼管矢板1
3の一端13aは、それぞれ底版コンクリート部11中
に埋設されており、これら前面鋼管矢板13は、互いに
防波堤構築方向(矢印C、D方向)に隙間を生ずること
なく接続されている。前面鋼管矢板13の前側(矢印E
方向)には、波HEIを受ける前面部13dが形成され
ており、前面鋼管矢板13の後側(矢印F方向)には、
前面部13dとは背向する背面部13cが形成されてい
る。つまり前面鋼管矢板13の前面部13dは、沖側下
方から岸側上方に向けて傾斜し、かつ防波堤構築方向に
沿って形成されており、即ち前面部13dは、斜め上方
を向いている。また底版コンクリート部11には、第1
控え杭15が各前面鋼管矢板13を背面部13c側から
それぞれ支持する形で設けられており、第1控え杭15
は、岸側(矢印F方向)下方(矢印B方向)から沖側
(矢印E方向)上方(矢印A方向)に向けて傾斜してい
る。第1控え杭15の一端15aは、底版コンクリート
部11中に埋設されており、第1控え杭15の他端15
bは、前面鋼管矢板13の背面部13cの略中間に接続
されている。即ち、第1控え杭15は、前面鋼管矢板1
3と底版コンクリート部11を接続する形で設けられて
いる。更に底版コンクリート部11には、第2控え杭1
6が所定の間隔で立設されており、第2控え杭16は、
前記第1控え杭15と同様に岸側下方から沖側上方に向
けて傾斜して立設されている。第2控え杭16の一端1
6aは、底版コンクリート部11中に埋設されている。
そして前面鋼管矢板13の他端13bと第2控え杭16
の他端16bは、上部コンクリート部17中に埋設され
ている。つまり上部コンクリート部17は、これら前面
鋼管矢板13及び第1控え杭15と、第2控え杭16に
より支持される形で底版コンクリート部11の上方(矢
印A方向)に配置されている。
The breakwater 1 to which the breakwater structure and breakwater using the breakwater unit according to the present invention is applied has a predetermined breakwater construction length on the seabed 60 at a position where the breakwater is to be constructed, as shown in FIG. It is constructed in a distracting manner. In other words, the breakwater 1 is the breakwater 1 that protects against the wave HEI.
a, and the breakwater 1a has the breakwater building length along the breakwater building direction (arrow C, D direction) which is the direction intersecting the wave propagation direction (arrow E, F direction) in which the wave HEI is transmitted. Is formed over. In addition, the breakwater 1a has a water depth S
Corresponding to L, the seawater 63 is formed to have a predetermined breakwater height until it projects above the seawater surface 63a. The seabed 60 has a deep water depth SL of about 40 m from the seawater surface 63a of the seawater 63 to the ground surface 60a. Breakwater 1
Is composed of the foundation rubble part 3 and a plurality of breakwater units 10, and a plurality of the breakwater units 10 are arranged along the foundation rubble part 3. Foundation rubble part 3 is rubble stone 5
Are piled up at the foundation height T0, and the foundation rubble part 3 is provided along the breakwater construction direction.
The breakwater unit 10 is substantially flat on the upper part of the foundation rubble part 3.
The base surface 3a on which the base can be installed is formed.
Is formed along the breakwater building direction (directions of arrows C and D) having a foundation width D0 and corresponding to the breakwater building length. The breakwater unit 10 to which the breakwater unit according to the present invention is applied has a bottom slab concrete portion 11 made of concrete as shown in FIG. 1, and the bottom slab concrete portion 11 has a bottom slab height T1 and a bottom slab width D1 ( D1
<D0), a rectangular parallelepiped block having a bottom plate length L1. In the bottom slab concrete portion 11, a small diameter lifting pressure reducing hole 12 is formed in the bottom slab concrete portion 11 in the vertical direction (arrow A,
A large number of holes are formed so as to penetrate in the B direction), and the lifting pressure reduction holes 12 are formed so that the permeated water 65 of the seawater 63 and the like can pass through. Above the slab concrete portion 11 (direction of arrow A), an upper concrete portion 17 made of concrete or the like is provided on the front steel pipe sheet pile 13 and the first retaining pile 15
And the second retaining pile 16 are connected via two types of pile members. The upper concrete part 17 is
The front side 17 of the upper concrete portion 17 is an inverted T-shaped block having an upper width D2 and an upper length L2 (= L1).
The a and the back surface 17b are each formed in a stepped shape having an upper height T2. That is, as shown in FIG. 1, a plurality of front steel pipe sheet piles 13 are erected on the bottom slab concrete portion 11, and the front steel pipe sheet piles 13 are offshore (in the direction of arrow E).
It is inclined from the lower side (arrow B direction) toward the shore side (arrow F direction) and upward (arrow A direction). These front steel pipe sheet piles 1
One end 13a of 3 is embedded in the bottom slab concrete part 11, respectively, and these front steel pipe sheet piles 13 are connected to each other without forming a gap in the breakwater building direction (arrow C, D direction). Front side of the front steel pipe sheet pile 13 (arrow E
Direction), a front surface portion 13d that receives the wave HEI is formed, and on the rear side of the front steel pipe sheet pile 13 (direction of arrow F),
A back surface portion 13c, which faces the front surface portion 13d, is formed. That is, the front surface portion 13d of the front steel pipe sheet pile 13 is inclined from the lower side of the offshore side to the upper side of the shore and is formed along the breakwater construction direction, that is, the front surface portion 13d is directed obliquely upward. In addition, the bottom slab concrete part 11 has a first
The retaining piles 15 are provided so as to respectively support the front steel pipe sheet piles 13 from the rear portion 13c side, and the first retaining piles 15 are provided.
Is inclined from the lower side of the shore (direction of arrow F) (direction of arrow B) toward the upper side of sea (direction of arrow E) (direction of arrow A). One end 15 a of the first retaining pile 15 is embedded in the bottom slab concrete portion 11, and the other end 15 a of the first retaining pile 15 is provided.
b is connected to approximately the middle of the back surface portion 13c of the front steel pipe sheet pile 13. That is, the first retaining pile 15 is the front steel pipe sheet pile 1
3 and the slab concrete portion 11 are connected to each other. Further, the bottom slab concrete part 11 has a second retaining pile 1
6 are erected at predetermined intervals, and the second retaining pile 16 is
Similar to the first retaining pile 15, it is erected from the lower side of the shore toward the upper side of the offshore. One end 1 of the second retaining pile 16
6a is embedded in the bottom slab concrete portion 11.
And the other end 13b of the front steel pipe sheet pile 13 and the second retaining pile 16
The other end 16b is embedded in the upper concrete portion 17. That is, the upper concrete portion 17 is arranged above the bottom slab concrete portion 11 (in the direction of arrow A) so as to be supported by the front steel pipe sheet pile 13, the first retaining pile 15 and the second retaining pile 16.

【0008】本発明は以上のような構成を有するので、
防波堤ユニット10を用いて防波堤1を構築するには、
まず、防波堤ユニット10を製作する。つまり、防波堤
ユニット10は、図示しない陸上ヤードにおいて、底版
コンクリート部11、前面鋼管矢板13、第1控え杭1
5、第2控え杭16及び上部コンクリート部17をブロ
ック割製作することが可能である。また、大水深用に大
型化した場合、ケーソンを製作する場合のように大量の
コンクリートを使用せずとも、前面鋼管矢板13、第1
控え杭15、第2控え杭16の長さを水深SLに対応さ
せて長く設定することにより防波堤ユニット1は形成で
きる。即ち、防波堤ユニット1はケーソンなどと比較し
て極めて軽量に形成することができる。従って、大水深
下の海底地盤60上に防波堤1を構築する場合、従来は
大型のケーソンなどを形成する必要があるが、ケーソン
などよりも極めて軽量に形成し得る防波堤ユニット1
は、大型化しても陸上ヤードなどにおいて分割形成し、
それら分割形成されたものを吊下した状態で一つのユニ
ットとして組立てることができる。よって、防波堤を構
築すべき海底、海上におけるコンクリート打設、加工、
組立等の作業を省くことができ、省力化し得る。なお、
防波堤1を構築する上で作業効率を考慮して、上部コン
クリート部17を防波堤構築現場で製作するなど上記し
た陸上ヤードでの一部の作業を海上において実施するよ
うにしても良いことは言うまでもない。一方、防波堤を
構築すべき位置の海底地盤60上には、捨石5を積層し
て基礎捨石部3を、構築すべき防波堤1の防波堤構築方
向(矢印C、D方向)に沿って基礎面3aを形成する形
で設けておく。ところで、基礎捨石部3は、その基礎高
さT0を、防波堤ユニット10の荷重などを支持し該ユ
ニット10を設置し得るために最低限必要な高さに設定
する形で形成する。つまり、前面鋼管矢板13、第1及
び第2控え杭15、16は鋼管から形成されており、加
工は容易で、長さは自由に設定できるので、基礎捨石部
3の基礎高さT0を低くしても何ら問題はない。即ち、
前面鋼管矢板13、第1及び第2控え杭16の長さは、
基礎捨石部3の基礎高さT0を考慮し、かつ底版コンク
リート部11を基礎捨石部3上に設置した際に上部コン
クリート部17が海水面63a上に所望する高さだけ突
出し得るように、防波堤1を構築すべき海底地盤60の
水深SLに対応させて適宜設定すれば良い。このように
基礎捨石部3の基礎高さT0を低く抑えることにより、
基礎捨石部3を形成するのに必要な捨石5の量は少なく
て済み、省資源化することができるばかりか、海底にお
いて基礎捨石部3を形成する作業量も少なくて済む。よ
って、大水深用の防波堤1を省資源、省力化して構築し
得る。そこで、陸上ヤードで製作した防波堤ユニット1
0を、図示しない吊り船などに吊下する形で防波堤1を
構築すべき位置まで海上輸送する。そして、該海上輸送
した防波堤ユニット10を、海底地盤60上に形成され
た基礎捨石部3上に向けて沈下させ、該基礎捨石部3の
基礎面3aと該防波堤ユニット10の底版コンクリート
部11の底面11aが当接するように設置する。このと
き、防波堤ユニット10の前面鋼管矢板13の前面部1
3dが、沖側(矢印E方向)を向くように、即ち前面鋼
管矢板13の前面部13dが沖側から岸側(矢印F方
向)に向けた波HEIに対向する形で配置する。(以
下、これら一連の作業を「防波堤ユニット10の沈設作
業」と称する)。このような防波堤ユニット10の沈設
作業を繰り返して、基礎捨石部3の基礎面3a上に防波
堤ユニット10を基礎捨石部3に沿って(防波堤構築方
向に)直列に順次並べる形で伸延させてゆき、基礎捨石
部3上に、防波堤ユニット10を構築すべき防波堤1の
長さに対応させて複数個配置する。すると、防波堤1が
海底地盤60上に構築される。このとき、隣接する防波
堤ユニット10、10同士をそれぞれ接続することによ
り、波HEIの力SFに対してより抵抗力が増すことは
言うまでもない。以上のように、陸上ヤードで製作した
防波堤ユニット10を海上輸送して、防波堤1を構築す
べき海底地盤60上に形成された基礎捨石部3上に沈設
するだけで、大水深下の海底地盤60上に容易に防波堤
1を構築することができる。また防波堤ユニット10を
沈設する際に、防波堤ユニット10の前面鋼管矢板13
の前面部13dが沖側を向くように配置することによ
り、前面鋼管矢板13の前面部13dで沖側から岸側に
向けた波HEIの力SFを受ける。すると、前面鋼管矢
板13に曲げモーメントが生じるが、第1控え杭15が
前面鋼管矢板13の背面部13cを岸側から沖側に向け
て支持しているので、前面鋼管矢板13に生じる曲げモ
ーメントは大幅に低減される。よって、防波堤ユニット
10の強度は第1控え杭15が無い場合よりも大幅に向
上し、耐久性が増す。更に防波堤ユニット10は、沖側
から岸側に向けた波HEIの力SFを、斜め上方に傾斜
させた前面鋼管矢板13の前面部13dで受けることに
より、該波HEIの力SFの分力が底版コンクリート部
11を基礎捨石3に押し付けるように働くので、基礎捨
石3上に確実に設置される。更に防波堤ユニット10の
底版コンクリート部11には揚圧力低減穴12を多数設
けたので、海水63が基礎捨石3を成す捨石5間から浸
入する等して底版コンクリート部11下方に浸透水65
が生じても、浸透水65を、図中二点鎖線で示すよう
に、揚圧力低減穴12を通して底版コンクリート11の
底面11a側から上方に向けて流す形で排出することが
できる。つまり、浸透水65による揚圧力は底版コンク
リート部11を持ち上げる程大きく作用せず、低減され
るので、防波堤ユニット10は確実に基礎捨石3上に設
置される。
Since the present invention has the above configuration,
To construct the breakwater 1 using the breakwater unit 10,
First, the breakwater unit 10 is manufactured. That is, the breakwater unit 10 includes the bottom slab concrete portion 11, the front steel pipe sheet pile 13, the first retaining pile 1 in the land yard (not shown).
5, it is possible to divide the second retaining pile 16 and the upper concrete portion 17 into blocks. In addition, in the case of increasing the size for deep water, without using a large amount of concrete as in the case of manufacturing caisson, front steel pipe sheet pile 13,
The breakwater unit 1 can be formed by setting the lengths of the retaining piles 15 and the second retaining piles 16 to correspond to the water depth SL. That is, the breakwater unit 1 can be formed to be extremely lightweight as compared with a caisson or the like. Therefore, when constructing the breakwater 1 on the seabed 60 under the deep water, it is necessary to form a large caisson conventionally, but the breakwater unit 1 that can be formed to be extremely lighter than a caisson or the like.
Can be formed separately on land yard, etc.
Those divided and formed can be assembled as one unit in a suspended state. Therefore, the seabed where the breakwater should be constructed, concrete placing and processing on the sea,
It is possible to save work such as assembling and save labor. In addition,
Needless to say, in consideration of work efficiency in constructing the breakwater 1, part of the work in the above-mentioned land yard may be carried out at sea, for example, by manufacturing the upper concrete portion 17 at the breakwater construction site. . On the other hand, on the seabed 60 at the position where the breakwater should be built, the rubble stone 5 is stacked to form the foundation rubble part 3 along the breakwater building direction (arrow C, D direction) of the breakwater 1 to be built. It is provided in the form of forming. By the way, the foundation rubble part 3 is formed in a form in which the foundation height T0 is set to the minimum required height for supporting the load of the breakwater unit 10 and the like so that the unit 10 can be installed. That is, since the front steel pipe sheet pile 13, the first and second retaining piles 15 and 16 are formed from steel pipes, the processing is easy, and the length can be freely set, so that the foundation height T0 of the foundation rubble part 3 is lowered. But there is no problem. That is,
The length of the front steel pipe sheet pile 13, the first and second retaining piles 16 is
In consideration of the foundation height T0 of the foundation rubble portion 3, and when the bottom slab concrete portion 11 is installed on the foundation rubble portion 3, the breakwater so that the upper concrete portion 17 can project to the desired height above the sea surface 63a. 1 may be appropriately set according to the water depth SL of the seabed 60 to be constructed. In this way, by keeping the foundation height T0 of the foundation rubble part 3 low,
The amount of rubble stones 5 required to form the rubble stone portion 3 is small, and not only resource saving can be achieved but also the amount of work to form the rubble stone portion 3 on the seabed is small. Therefore, the breakwater 1 for deep water can be constructed with resource saving and labor saving. Therefore, the breakwater unit 1 made in the land yard
0 is hung by a suspension ship (not shown) and transported by sea to a position where the breakwater 1 should be constructed. Then, the breakwater unit 10 transported by sea is sunk toward the foundation rubble portion 3 formed on the seabed 60, and the foundation surface 3a of the foundation rubble portion 3 and the bottom slab concrete portion 11 of the breakwater unit 10 are submerged. It is installed so that the bottom surface 11a contacts. At this time, the front part 1 of the front steel pipe sheet pile 13 of the breakwater unit 10
3d is arranged so as to face the offshore side (direction of arrow E), that is, the front portion 13d of the front steel pipe sheet pile 13 is arranged so as to face the wave HEI directed from the offshore side to the shore side (direction of arrow F). (Hereinafter, this series of operations will be referred to as "deposition work of the breakwater unit 10"). By repeating the work of burying the breakwater unit 10 as described above, the breakwater units 10 are extended on the foundation surface 3a of the foundation rubble part 3 along the foundation rubble part 3 (in the direction of building the breakwater) in series. A plurality of breakwater units 10 are arranged on the foundation rubble part 3 in accordance with the length of the breakwater 1 to be constructed. Then, the breakwater 1 is built on the seabed 60. At this time, it is needless to say that the resistance to the force SF of the wave HEI is further increased by connecting the adjacent breakwater units 10 and 10 to each other. As described above, by simply transporting the breakwater unit 10 manufactured in the land yard over the sea and immersing the breakwater unit 10 on the foundation rubble part 3 formed on the seabed ground 60 on which the breakwater 1 should be constructed, the seabed ground at a deep water depth can be obtained. The breakwater 1 can be easily constructed on the 60. Further, when the breakwater unit 10 is sunk, the front steel pipe sheet pile 13 of the breakwater unit 10 is
By arranging the front surface portion 13d of the front surface 13d to face the offshore side, the front surface portion 13d of the front steel pipe sheet pile 13 receives the force SF of the wave HEI directed from the offshore side to the shore side. Then, a bending moment is generated in the front steel pipe sheet pile 13, but since the first retaining pile 15 supports the rear portion 13c of the front steel pipe sheet pile 13 from the shore side to the offshore side, the bending moment generated in the front steel pipe sheet pile 13 is generated. Is significantly reduced. Therefore, the strength of the breakwater unit 10 is significantly improved as compared with the case where the first retaining pile 15 is not provided, and the durability is increased. Further, the breakwater unit 10 receives the force SF of the wave HEI directed from the offshore side to the shore side by the front face portion 13d of the front steel pipe sheet pile 13 inclined obliquely upward, so that the component force of the force SF of the wave HEI is obtained. Since it works so as to press the bottom slab concrete portion 11 against the foundation rubble 3, it is reliably installed on the foundation rubble 3. Further, since the bottom plate concrete portion 11 of the breakwater unit 10 is provided with a large number of lifting pressure reducing holes 12, seawater 63 intrudes from between the rubble stones 5 forming the foundation rubble 3 and so on.
Even if this occurs, the permeated water 65 can be discharged in a form of flowing upward from the bottom surface 11a side of the slab concrete 11 through the lifting pressure reduction hole 12, as shown by the chain double-dashed line in the figure. That is, the lifting pressure by the permeated water 65 does not act as much as lifting the bottom slab concrete portion 11 and is reduced, so that the breakwater unit 10 is reliably installed on the foundation rubble 3.

【0009】[0009]

【発明の効果】以上説明したように、本発明のうち第1
の発明は、海底地盤60上に設けられる防波堤におい
て、前記海底地盤上に、基礎捨石部3等の基礎部を防波
堤構築方向に沿って設け、前記基礎部上に、底版コンク
リート部11等の底版部を該基礎部に沿って設け、前記
底版部に、上部コンクリート部17等の防波部を前面鋼
管矢板13、第1控え杭15、第2控え杭16等の杭部
材を介して接続する形で設けて構成したので、防波堤を
構築すべき海底地盤が大水深下にあっても、基礎部を高
くすることなく、かつ大量のコンクリートを使用するこ
となく、底版部と防波部を容易に接続することができ
る。つまり、大水深下の海底地盤上に防波堤を設置する
場合、基礎部の高さを必要最低限の高さに構築しても、
杭部材の長さを必要な長さに適宜設定して底版部と防波
部を接続するだけで、大量にコンクリートを使用するこ
となく、容易に防波堤を構築し得る。また、基礎部の高
さを低く抑えることにより、基礎部を形成するために要
する捨石などの資材は少なくて済むばかりか、海底にお
いて基礎部を形成する作業量も少なくて済み、大水深用
の防波堤を省資源、省力化して構築し得る。
As described above, the first aspect of the present invention
Of the present invention, in a breakwater provided on the seabed 60, a foundation such as a rubble foundation 3 is provided on the seabed along the breakwater construction direction, and a bottom slab such as a concrete slab 11 is provided on the foundation. A portion is provided along the foundation portion, and a wave preventing portion such as an upper concrete portion 17 is connected to the bottom slab portion through a pile member such as a front steel pipe sheet pile 13, a first retaining pile 15, a second retaining pile 16 or the like. Since it is constructed in a shape, even if the seabed where the breakwater is to be constructed is under deep water, the bottom plate and the breakwater can be easily constructed without raising the foundation and using a large amount of concrete. Can be connected to. In other words, when installing a breakwater on the seabed below the deep water, even if the height of the foundation is set to the minimum required height,
By simply setting the length of the pile member to a required length and connecting the bottom slab and the breakwater, the breakwater can be easily constructed without using a large amount of concrete. In addition, by keeping the height of the foundation low, not only the amount of materials such as rubble stones required to form the foundation can be reduced, but also the amount of work to form the foundation on the seabed can be reduced, making it suitable for deep water. The breakwater can be constructed by saving resources and labor.

【0010】また本発明のうち第2の発明は、第1の発
明において、前記底版部に、揚圧力低減穴12を該底版
部を上下方向に貫通する形で設けて構成したので、底版
部の下方に浸入した浸透水などは揚圧力低減穴を通して
底版部の下方から上方へ向けて流すことができるので、
該浸透水による揚圧力は底版部に大きく働かない。つま
り、第1の発明の効果に加えて、底版部に作用する揚圧
力を低減し、防波堤を確実に海底地盤上に設置すること
が可能となる。
The second aspect of the present invention is the first aspect of the invention, wherein the bottom plate portion is provided with a lifting pressure reducing hole 12 so as to vertically penetrate the bottom plate portion. Since the permeated water that has infiltrated into the lower part of the bottom can flow from the lower part of the bottom plate part to the upper part through the lifting pressure reduction hole,
The lifting pressure due to the permeated water does not work significantly on the bottom slab. That is, in addition to the effect of the first invention, it is possible to reduce the lifting pressure acting on the bottom slab and reliably install the breakwater on the seabed ground.

【0011】更に本発明のうち第3の発明は、底版長さ
L1等の所定長さに形成されたコンクリートから成る底
版コンクリート部11等の底版部を有し、前記底版部
に、上部長さL2等の所定長さに形成されたコンクリー
トから成る上部コンクリート部17等の防波部を鋼管か
ら成る前面鋼管矢板13、第1控え杭15、第2控え杭
16等の杭部材を介して接続するようにして構成したの
で、陸上ヤードなどにおいて底版部、杭部材、防波部な
どと分割して製作することができるばかりか、特に大型
化した場合、ケーソンのように大量のコンクリートを使
用することなく杭部材の長さを長くする形で防波堤ユニ
ットを形成できるので、防波堤ユニットはケーソンなど
と比較して極めて軽量に形成される。つまり、大水深下
の海底地盤上に防波堤を構築する場合、従来は大型のケ
ーソンなどを形成する必要があるが、ケーソンなどより
も極めて軽量に形成し得る防波堤ユニットは大型化して
も陸上ヤードなどにおいて分割形成して吊下した状態で
防波堤ユニットとして組立てることができる。そして、
該防波堤ユニットを防波堤を構築すべき位置に海上輸送
して沈設するだけで、防波堤を容易に構築することがで
きる。
A third aspect of the present invention further comprises a bottom slab portion such as a bottom slab concrete portion 11 made of concrete formed to have a predetermined length such as a bottom slab length L1 and the like. A wave-proof part such as an upper concrete part 17 made of concrete having a predetermined length such as L2 is connected through pile members such as a front steel pipe sheet pile 13, a first retaining pile 15 and a second retaining pile 16 made of steel pipe. Since it is configured as described above, it can be manufactured separately from the bottom slab, pile member, wave breaker, etc. on the land yard, etc. In addition, if the size is large, use a large amount of concrete like caisson. Since the breakwater unit can be formed without increasing the length of the pile member without using the breakwater unit, the breakwater unit is formed to be extremely lightweight as compared with a caisson or the like. In other words, when constructing a breakwater on the seabed under deep water, it has conventionally been necessary to form a large caisson, etc., but a breakwater unit that can be made extremely lighter than a caisson, etc., can be formed on a land yard even if it becomes large. It is possible to assemble it as a breakwater unit in the state where it is dividedly formed and suspended. And
The breakwater can be easily constructed only by transporting the breakwater unit to the position where the breakwater should be constructed by sea and sunk.

【0012】更に本発明のうち第4の発明は、第3の発
明において、前記底版部に、揚圧力低減穴12を該底版
部を上下方向に貫通する形で設けて構成したので、底版
部の下方に浸入した浸透水などは揚圧力低減穴を通して
底版部の下方から上方へ向けて流すことができるので、
該浸透水による揚圧力は底版部に大きく働かない。つま
り、第3の発明の効果に加えて、底版部に作用する揚圧
力を低減し、防波堤ユニットを確実に海底地盤上に設置
することが可能となる。
Further, the fourth aspect of the present invention is the third aspect of the present invention, wherein the bottom plate portion is provided with a lifting pressure reducing hole 12 so as to vertically penetrate the bottom plate portion. Since the permeated water that has infiltrated into the lower part of the bottom can flow from the lower part of the bottom plate part to the upper part through the lifting pressure reduction hole,
The lifting pressure due to the permeated water does not work significantly on the bottom slab. That is, in addition to the effect of the third invention, it is possible to reduce the lifting pressure that acts on the bottom slab and reliably install the breakwater unit on the seabed ground.

【0013】更に本発明のうち第5の発明は、第3の発
明において、前記杭部材は、前面鋼管矢板13、第1控
え杭15等の第1の杭部材及び第2控え杭16等の第2
の杭部材から成り、前記第1の杭部材は、前面鋼管矢板
13と補助控え杭15から成り、前記前面鋼管矢板に
は、波を受ける前面部13dと、該前面部とは背向する
背面部13cが形成されており、前記補助控え杭は、前
記前面鋼管矢板の背面部と前記底版部を接続する形で設
けられていることを特徴として構成したので、第3の発
明の効果に加えて、補助控え杭が前面鋼管矢板を背面部
側から支持することにより、前面鋼管矢板が前面部で波
の力を受けた際に該前面鋼管矢板に生じる曲げモーメン
トを低減することができるので、防波堤ユニットの強度
が向上しより耐久性の高いものにすることができる。
A fifth aspect of the present invention is the third aspect of the invention, wherein the pile members are the first pile members such as the front steel pipe sheet pile 13, the first pile piles 15 and the second pile piles 16 and the like. Second
The first pile member comprises a front steel pipe sheet pile 13 and an auxiliary retaining pile 15, and the front steel pipe sheet pile has a front portion 13d for receiving waves and a back surface opposite to the front portion. Since the portion 13c is formed and the auxiliary retaining pile is configured so as to be provided so as to connect the back surface portion of the front steel pipe sheet pile and the bottom plate portion, in addition to the effect of the third invention. By supporting the front steel pipe sheet pile from the rear portion side by the auxiliary retaining pile, it is possible to reduce the bending moment generated in the front steel pipe sheet pile when the front steel pipe sheet pile receives a wave force at the front portion. The strength of the breakwater unit is improved and the breakwater unit can be made more durable.

【0014】更に本発明のうち第6の発明は、第3の発
明において、前記杭部材は、前面鋼管矢板13、第1控
え杭15等の第1の杭部材及び第2控え杭16等の第2
の杭部材から成り、前記第1の杭部材は、波を受ける前
面部13dを有しており、前記前面部が、斜め上方を向
いていることを特徴として構成したので、第3の発明の
効果に加えて、前面鋼管矢板の前面部で受けた波の力の
分力を底版部を海底地盤上の基礎部に押し付ける方向に
作用させることができるので、防波堤ユニットをより確
実に海底地盤上に設置することが可能となる。
Further, in a sixth aspect of the present invention based on the third aspect, the pile members are the first pile member such as the front steel pipe sheet pile 13, the first retaining pile 15 and the second retaining pile 16 and the like. Second
Since the first pile member has a front surface portion 13d that receives waves, and the front surface portion is directed obliquely upward, the third pile member of the third invention is formed. In addition to the effect, the component of the wave force received by the front part of the front steel pipe sheet pile can be made to act in the direction of pressing the bottom slab against the foundation part on the seabed ground, so the breakwater unit can be more reliably located on the seabed ground. Can be installed in

【0015】更に本発明のうち第7の発明は、海底地盤
60上に設けられる防波堤において、前記海底地盤上
に、捨石5から成る基礎捨石部3等の基礎部を防波堤構
築方向に沿って設け、前記基礎部上に、第3の発明にお
ける防波堤ユニット10を、該基礎部に沿って複数個配
置して構成したので、防波堤ユニットを海上輸送して防
波堤を構築すべき位置に形成された基礎部上に沈設する
だけで、防波堤を構築することができるので、海上にお
ける作業量は極く少なく、防波堤を容易に構築すること
ができる。
Furthermore, a seventh aspect of the present invention is the breakwater provided on the seabed 60, in which a foundation such as a rubble part 3 made of rubble 5 is provided on the seabed along the breakwater construction direction. Since a plurality of breakwater units 10 according to the third aspect of the invention are arranged on the foundation portion along the foundation portion, a foundation formed at a position where the breakwater unit is to be transported by sea to construct a breakwater. Since the breakwater can be constructed simply by burying it on the part, the amount of work on the sea is extremely small, and the breakwater can be constructed easily.

【図面の簡単な説明】[Brief description of drawings]

【図1】図1は、本発明による防波堤構造と、防波堤ユ
ニット及び該ユニットを用いた防波堤が適用された防波
堤の一実施例を示す斜視図である。
FIG. 1 is a perspective view showing an embodiment of a breakwater structure according to the present invention, a breakwater unit, and a breakwater to which the breakwater using the breakwater unit is applied.

【符号の説明】 3……基礎部(基礎捨石部) 5……捨石 10……防波堤ユニット 11……底版部(底版コンクリート部) 12……揚圧力低減穴 13……杭部材、第1の杭部材、前面鋼管矢板(前面鋼
管矢板) 13c……背面部 13d……前面部 15……杭部材、第1の杭部材、補助控え杭(第1控え
杭) 16……杭部材、第2の杭部材(第2控え杭) 17……防波部(上部コンクリート部) 60……海底地盤 L1……所定の長さ(底版長さ) L2……所定の長さ(上部長さ)
[Explanation of symbols] 3 ... Foundation (basic rubble) 5 ... Rubble 10 ... Breakwater unit 11 ... Bottom slab (bottom concrete) 12 ... Lifting pressure reducing hole 13 ... Pile member, first Pile member, front steel pipe sheet pile (front steel pipe sheet pile) 13c ...... rear portion 13d ...... front portion 15 ...... pile member, first pile member, auxiliary restraining pile (first restraining pile) 16 ... pile member, second Pile member (2nd retaining pile) 17 …… Wavebreak part (upper concrete part) 60 …… Sea floor L1 …… Predetermined length (bottom plate length) L2 …… Predetermined length (upper length)

Claims (7)

【特許請求の範囲】[Claims] 【請求項1】 海底地盤上に設けられる防波堤におい
て、 前記海底地盤上に、基礎部を防波堤構築方向に沿って設
け、 前記基礎部上に、底版部を該基礎部に沿って設け、 前記底版部に、防波部を杭部材を介して接続する形で設
けて構成した防波堤構造。
1. A breakwater provided on the seabed, wherein a foundation is provided on the seabed along the breakwater construction direction, and a bottom slab is provided on the foundation along the foundation. A breakwater structure in which a wave breaker is connected to a section through a pile member.
【請求項2】 前記底版部に、揚圧力低減穴を該底版部
を上下方向に貫通する形で設けて構成した請求項1記載
の防波堤構造。
2. The breakwater structure according to claim 1, wherein a lifting pressure reducing hole is provided in the bottom slab so as to vertically penetrate the bottom slab.
【請求項3】 所定長さに形成されたコンクリートから
成る底版部を有し、 前記底版部に、所定長さに形成されたコンクリートから
成る防波部を鋼管から成る杭部材を介して接続するよう
にして構成した防波堤ユニット。
3. A bottom slab portion made of concrete having a predetermined length, and a wave preventing portion made of concrete having a predetermined length is connected to the bottom slab portion through a pile member made of steel pipe. Breakwater unit configured in this way.
【請求項4】 前記底版部に、揚圧力低減穴を該底版部
を上下方向に貫通する形で設けて構成した請求項3記載
の防波堤ユニット。
4. The breakwater unit according to claim 3, wherein a lifting pressure reducing hole is provided in the bottom slab so as to vertically penetrate the bottom slab.
【請求項5】 前記杭部材は、第1の杭部材及び第2の
杭部材から成り、 前記第1の杭部材は、前面鋼管矢板と補助控え杭から成
り、 前記前面鋼管矢板には、波を受ける前面部と、該前面部
とは背向する背面部が形成されており、 前記補助控え杭は、前記前面鋼管矢板の背面部と前記底
版部を接続する形で設けられていることを特徴とする請
求項3記載の防波堤ユニット。
5. The pile member includes a first pile member and a second pile member, the first pile member includes a front steel pipe sheet pile and an auxiliary stay pile, and the front steel pipe sheet pile has a corrugated plate. A front surface portion that receives the front surface portion and a back surface portion that faces the front surface portion are formed, and the auxiliary retaining pile is provided so as to connect the rear surface portion of the front steel pipe sheet pile and the bottom plate portion. The breakwater unit according to claim 3, wherein the breakwater unit is a breakwater unit.
【請求項6】 前記杭部材は、第1の杭部材及び第2の
杭部材から成り、 前記第1の杭部材は、波を受ける前面部を有しており、 前記前面部が、斜め上方を向いていることを特徴とする
請求項3記載の防波堤ユニット。
6. The pile member includes a first pile member and a second pile member, and the first pile member has a front surface portion that receives waves, and the front surface portion is obliquely upward. The breakwater unit according to claim 3, which faces the breakwater unit.
【請求項7】 海底地盤上に設けられる防波堤におい
て、 前記海底地盤上に、捨石から成る基礎部を防波堤構築方
向に沿って設け、 前記基礎部上に、請求項3記載の防波堤ユニットを、該
基礎部に沿って複数個配置して構成した防波堤ユニット
を用いた防波堤。
7. A breakwater provided on a seabed, wherein a foundation made of rubble is provided on the seabed along a breakwater construction direction, and the breakwater unit according to claim 3 is provided on the foundation. A breakwater using a breakwater unit configured by arranging a plurality along the foundation.
JP7107019A 1995-04-06 1995-04-06 Breakwater structure and breakwater unit and breakwater by use of the unit Pending JPH08277515A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
JP7107019A JPH08277515A (en) 1995-04-06 1995-04-06 Breakwater structure and breakwater unit and breakwater by use of the unit

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
JP7107019A JPH08277515A (en) 1995-04-06 1995-04-06 Breakwater structure and breakwater unit and breakwater by use of the unit

Publications (1)

Publication Number Publication Date
JPH08277515A true JPH08277515A (en) 1996-10-22

Family

ID=14448458

Family Applications (1)

Application Number Title Priority Date Filing Date
JP7107019A Pending JPH08277515A (en) 1995-04-06 1995-04-06 Breakwater structure and breakwater unit and breakwater by use of the unit

Country Status (1)

Country Link
JP (1) JPH08277515A (en)

Cited By (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
KR100450309B1 (en) * 2002-02-15 2004-09-30 (주)대우건설 Breakwater using pile foundation
JP2010255312A (en) * 2009-04-24 2010-11-11 Hitachi Zosen Corp Roof gate type breakwater
JP2015227581A (en) * 2014-06-02 2015-12-17 鹿島建設株式会社 Lateral flow prevention structure

Cited By (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
KR100450309B1 (en) * 2002-02-15 2004-09-30 (주)대우건설 Breakwater using pile foundation
JP2010255312A (en) * 2009-04-24 2010-11-11 Hitachi Zosen Corp Roof gate type breakwater
JP2015227581A (en) * 2014-06-02 2015-12-17 鹿島建設株式会社 Lateral flow prevention structure

Similar Documents

Publication Publication Date Title
JP3603193B2 (en) How to build an underwater foundation
JP4958064B2 (en) Seismic reinforcement structure of quay
JPH08277515A (en) Breakwater structure and breakwater unit and breakwater by use of the unit
JP4229056B2 (en) External pressure resistance structure and construction method thereof
JP2001248135A (en) Jacket structure
JPH056601B2 (en)
JP6944807B2 (en) Seawall and seawall construction method
JP4504864B2 (en) Dam body reinforcement structure with wave-dissipating function
GB1560703A (en) Marine walls
CN214497367U (en) Vertical prefabricated retaining wall
KR100483885B1 (en) Method for constructing bank protection in soft ground of river-mouth or the seaside
JP2519602B2 (en) How to construct a breakwater
JP3585037B2 (en) Stationary double curtain wall type breakwater and its construction method
JP3372448B2 (en) Soft ground landing type breakwater and its landing method
JP3772945B2 (en) Footing caisson and method for installing the footing caisson
JP2022089637A (en) Embedment type wharf wall
JP6659430B2 (en) How to improve wavebreak structures
JP2021167523A (en) Quay reinforcement structure and reinforcement method of quay structure
KR101275500B1 (en) Breakwater using jacket structures
JPS63219714A (en) Breakwater, its construction, and concrete caisson therefor
JP2024068713A (en) Construction method of the support structure
JP3614825B2 (en) River slope protection mat and civil engineering structure using this river slope protection mat
JP2556380B2 (en) Construction method of revetment structure
JP2023075460A (en) Breakwater and construction method for breakwater
JP2564819B2 (en) Seismic reinforcement structure of existing caisson

Legal Events

Date Code Title Description
A977 Report on retrieval

Free format text: JAPANESE INTERMEDIATE CODE: A971007

Effective date: 20040420

A131 Notification of reasons for refusal

Free format text: JAPANESE INTERMEDIATE CODE: A131

Effective date: 20040427

A521 Written amendment

Free format text: JAPANESE INTERMEDIATE CODE: A523

Effective date: 20040618

A02 Decision of refusal

Free format text: JAPANESE INTERMEDIATE CODE: A02

Effective date: 20040907