JPH076187B2 - Construction method of sheet pile - Google Patents

Construction method of sheet pile

Info

Publication number
JPH076187B2
JPH076187B2 JP23104686A JP23104686A JPH076187B2 JP H076187 B2 JPH076187 B2 JP H076187B2 JP 23104686 A JP23104686 A JP 23104686A JP 23104686 A JP23104686 A JP 23104686A JP H076187 B2 JPH076187 B2 JP H076187B2
Authority
JP
Japan
Prior art keywords
excavation
sheet pile
view
sand
bucket
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Expired - Lifetime
Application number
JP23104686A
Other languages
Japanese (ja)
Other versions
JPS6389727A (en
Inventor
一 松沢
要 仲山
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
SUN-TECH LIMITED
Original Assignee
SUN-TECH LIMITED
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by SUN-TECH LIMITED filed Critical SUN-TECH LIMITED
Priority to JP23104686A priority Critical patent/JPH076187B2/en
Publication of JPS6389727A publication Critical patent/JPS6389727A/en
Publication of JPH076187B2 publication Critical patent/JPH076187B2/en
Anticipated expiration legal-status Critical
Expired - Lifetime legal-status Critical Current

Links

Landscapes

  • Placing Or Removing Of Piles Or Sheet Piles, Or Accessories Thereof (AREA)

Description

【発明の詳細な説明】 〔産業上の利用分野〕 この発明は地盤中に矢板を連続して施工する施工方法に
関するものである。
The present invention relates to a construction method for continuously constructing sheet piles in the ground.

〔従来技術〕[Prior art]

従来から河川護岸工事や水路及び道路の土留擁壁等を構
成するのに鋼管矢板又は鋼矢板を地盤中に連続して施工
する手法が用いられている。
BACKGROUND ART Conventionally, a method of continuously constructing steel pipe sheet piles or steel sheet piles in the ground has been used for constructing river bank protection works and soil retaining walls for waterways and roads.

〔この発明が解決すべき問題点〕[Problems to be solved by this invention]

こうした従来型の矢板施工法では打込みによる場合が多
く、騒音公害の問題があり、掘削孔に矢板を建込む方法
では、掘削機を支持する。クローラタイプの大型ベース
マシーンを必要とすることが屡々ある。このため、作業
スペースの狭い現場では作業性は問題があり、また幅員
の狭い道路では路上作業の為に全面通行止にしなればな
らない場合もあった。
In such a conventional sheet pile construction method, there is a problem of noise pollution in many cases by driving, and in the method of constructing the sheet pile in the excavation hole, the excavator is supported. Often, a large crawler type base machine is needed. Therefore, there is a problem in workability at a site where the work space is narrow, and there are cases where roads with a narrow width must be completely closed for road work.

そこで、この発明は前記の様な従来工法の不都合な点を
改善して大型ベースマシンを必要とせず、作業スペース
の狭い所でも作業性がよく、掘削土砂,泥水の処理が容
易であり、路上の作業でも車の交通に与える影響を最小
限に押さえることの出来得る施工方法を提供することを
目的とする。
Therefore, the present invention improves the disadvantages of the conventional construction method as described above, does not require a large-sized base machine, has good workability even in a narrow working space, can easily process excavated earth and muddy water, and can It is an object of the present invention to provide a construction method capable of minimizing the influence on the traffic of vehicles even in the work of.

〔発明の構成〕[Structure of Invention]

この発明による矢板の施工法は掘削予定位置の両側に沿
って軌条を配設し、この上を走行する掘進機構及びバケ
ットを用いて所定の深度までケーシングを利用して泥水
掘削すると共にバケット内に掘削土砂を収容しつつ複数
本連続掘削して泥水の充満した掘削溝を造成し、この該
掘削溝内に矢板を連続配設してバケット内の土砂で掘削
溝を埋め戻し、オーバーフローする泥水を水中ポンプで
先行して掘削したケーシング内に注入する作業を順次繰
り返す点に特徴がある。
The method of constructing a sheet pile according to the present invention is to dispose a rail along both sides of a planned excavation position, and use a casing and a bucket that travel on it to make a predetermined depth and use a casing to perform a mud excavation and a bucket. Plural continuous excavation while accommodating the excavated earth and sand to create an excavated groove filled with muddy water, a sheet pile is continuously arranged in this excavated groove, the excavated groove is backfilled with the earth and sand in the bucket, and overflowed mud is removed. It is characterized in that the work of injecting into the casing previously excavated by the submersible pump is sequentially repeated.

〔実施例〕〔Example〕

以下、図示するこの発明の実施例により説明する。第1
図及び第2図はこの発明による施工法を用いて道路周辺
に鋼矢板を連続して施工する実施例の平面図及び立面図
を示した。
Hereinafter, description will be made with reference to the illustrated embodiment of the present invention. First
FIG. 2 and FIG. 2 show a plan view and an elevation view of an embodiment in which steel sheet piles are continuously constructed around a road by using the construction method according to the present invention.

ここで、掘削予定位置の両側に沿ってレール3が配設さ
れ、このレール3上を後述する掘進機12及び土砂投入用
バケット8が走行可能となっている。
Here, the rails 3 are arranged along both sides of the planned excavation position, and the excavator 12 and the earth and sand charging bucket 8 described later can run on the rails 3.

また、道路面上にはH型鋼4を置きその上にほぼレール
3高さと等しくなるように、メトロデッキ5を敷き、作
業台が構成されている。こうして構成された作業台の左
右にはすべり台7を配置して車の交通を可能としてい
る。
Further, an H-shaped steel 4 is placed on the road surface, and a metro deck 5 is laid on the H-shaped steel 4 so that the height is almost equal to the height of the rail 3 to form a workbench. The slides 7 are arranged on the left and right of the work table constructed in this way to enable vehicle traffic.

この施工法で用いられる掘進機12は、第6図(a),
(b)の平面図及び側面図で示した様にリーダー13掘進
機構10及び昇降シリンダー11を備えており、レール3上
を移動して所定の掘削位置にケーシング9を埋設して内
部を掘溝し、泥水注入後にケーシング9を引き抜いて、
次の掘削位置に移動するものである。
The excavator 12 used in this construction method is shown in FIG.
As shown in the plan view and side view of (b), it is equipped with a leader 13, an excavation mechanism 10 and an elevating cylinder 11, and moves on the rail 3 to bury a casing 9 at a predetermined excavation position to dig the inside of the trench. Then, after injecting muddy water, pull out the casing 9,
It moves to the next excavation position.

また、土砂投入用バケット8は第7図(a),(b),
(c),(d)の側面図,正面図,底面図及び平面図に
示した様に、開口上部に100m/m角程度のフルイを備えて
おり、掘削された土砂の中から所定値以上の玉石を除去
した埋戻し用の土砂を収容してレール3上を移動可能と
なっている。
In addition, the earth and sand loading bucket 8 is shown in Figs. 7 (a), (b),
As shown in the side view, front view, bottom view, and plan view of (c) and (d), the upper part of the opening is equipped with a sieve of about 100 m / m square, and more than a predetermined value from the excavated earth and sand. It is possible to move on the rail 3 by accommodating the earth and sand for backfilling from which the boulders have been removed.

ここで、第3図及び第4図に示した一列の掘削部分の平
面図及び断面図において施工手順を説明すると、まず掘
進機12で所定の深度まで掘削後、ケーシング9内に泥水
を注入してケーシング9を引き抜く。この作業を、3本
又は5本分程度繰返し、泥水の充満した掘削孔1を造成
する。(Cの工程) 泥水の充満した掘削孔1内に鋼矢板2の先端部が掘削孔
1内で芯ズレしない様にスペーサー2′が取付られる。
Here, the construction procedure will be described with reference to the plan view and cross-sectional view of the row of excavated portions shown in FIG. 3 and FIG. 4. First, after excavating to a predetermined depth with the excavator 12, muddy water is injected into the casing 9. And pull out the casing 9. This operation is repeated for about 3 or 5 pieces to form the excavation hole 1 filled with muddy water. (Step C) A spacer 2 ′ is attached in the excavation hole 1 filled with muddy water so that the tip of the steel sheet pile 2 is not displaced in the excavation hole 1.

このスペーサ2′は第5図(c)に示した形状であり、
クレーンで鋼矢板2を吊上げた時に同図(a),(b)
に示した様に取付られ、建込用定規6でガイドされつつ
掘削孔1内に自重でセットされる。(Bの工程) こうして、鋼矢板2の建込後に掘削した土砂は土砂投入
用バケット8のフルイで玉石を除去して鋼矢板2の周辺
に埋戻される。(Aの工程)この時、トーバーフローす
る泥水は水中ポンプ10で先行するケーシング9内に注入
される。
This spacer 2'has the shape shown in FIG. 5 (c),
When the steel sheet pile 2 is lifted by a crane, the same figure (a), (b)
It is attached as shown in FIG. 1 and is set in the excavation hole 1 by its own weight while being guided by the construction ruler 6. (Step B) In this way, the earth and sand excavated after the steel sheet pile 2 has been built is backfilled around the steel sheet pile 2 by removing boulders with a sieve in the earth and sand loading bucket 8. (Step A) At this time, the muddy water that flows through the tober is injected into the preceding casing 9 by the submersible pump 10.

〔発明の効果〕〔The invention's effect〕

この発明による矢板の施工方法実施例は以上の通りであ
り、次に述べる効果を挙げることができる。
The embodiment of the method for constructing a sheet pile according to the present invention is as described above, and the following effects can be obtained.

大型ベースマシンを必要とせず、作業スペースの狭い所
でも作業性がよく、掘削土砂をバケット内に収容して埋
戻しに効果的に利用し、泥水も先行するケーシングに順
次繰り返し注入利用するため全体の泥水使用量も少なく
処理も容易であり、路上の作業でも車の交通に与える影
響を最小限に押さえることができる。
It does not require a large base machine and has good workability even in a narrow work space. It stores excavated soil in a bucket and uses it effectively for backfilling. The amount of muddy water used is small and the treatment is easy, and the influence on the traffic of the car can be minimized even when working on the road.

また、バケット内に収容した土砂にセメント等の硬化剤
を混入して、掘削溝埋め戻し時の矢板支持力を高めるこ
ともできる。
It is also possible to mix a hardening agent such as cement into the earth and sand contained in the bucket to enhance the sheet pile supporting force when backfilling the excavation groove.

【図面の簡単な説明】[Brief description of drawings]

第1図及び第2図は実施例の全体平面図及び立面図、第
3図及び第4図は実施例の部分平面図及び地中の断面
図、第5図(a),(b)はスペーサの取付状態を示す
正面図及び平面図、同図(c)はクリップの拡大図、第
6図(a),(b)は掘削機の平面図及び正面図、第7
図(a),(b),(c),(d)はバケットの側面
図,正面図,底面図及び平面図である。 1……掘削機、2……鋼矢板、2′……スペーサ、3…
…レール、4……H型鋼、5……メトロデッキ、6……
建込用定規、7……スベリ台、8……土砂投入用バケッ
ト、9……ケーシング、10……掘進機構、11……昇降シ
リンダー、12……掘進機、13……リーダ。
1 and 2 are overall plan view and elevation view of the embodiment, FIGS. 3 and 4 are partial plan view and underground cross-section view of the embodiment, and FIGS. 5 (a) and 5 (b). Is a front view and a plan view showing a mounting state of a spacer, FIG. 6 (c) is an enlarged view of a clip, and FIGS. 6 (a) and 6 (b) are plan views and front views of an excavator.
Drawings (a), (b), (c), and (d) are a side view, a front view, a bottom view, and a plan view of a bucket. 1 ... Excavator, 2 ... Steel sheet pile, 2 '... Spacer, 3 ...
… Rail, 4 …… H-shaped steel, 5 …… Metro deck, 6 ……
Ruler for installation, 7 ... Sliding table, 8 ... Bucket for loading sand, 9 ... Casing, 10 ... Excavation mechanism, 11 ... Elevating cylinder, 12 ... Excavator, 13 ... Leader.

Claims (1)

【特許請求の範囲】[Claims] 【請求項1】地盤中に矢板を連続して施工する施工方法
であって、掘削予定位置の両側に沿って軌条を配設し、
当該軌条上を走行する掘進機で所定の深度までケーシン
グを利用して泥水掘削すると共に前記軌条上を走行する
バケット内に掘削土砂を収容し、複数本連続掘削して泥
水の充満した掘削溝を造成し、当該掘削溝内に矢板を連
続配設して前記バケット内の土砂で掘削溝を埋め戻し、
オーバーフローする泥水を水中ポンプで先行して掘削し
たケーシング内に注入する作業を順次繰り返すことを特
徴とする矢板の施工方法。
1. A construction method for continuously constructing sheet piles in the ground, wherein rails are arranged along both sides of a planned excavation position,
The excavator traveling on the rail is used for excavating mud to a predetermined depth using the casing, and the excavated earth and sand are stored in the bucket traveling on the rail, and a plurality of continuous excavation is performed to form the excavation groove filled with mud. Created, the sheet pile is continuously arranged in the excavation groove, and the excavation groove is backfilled with the earth and sand in the bucket,
A method for constructing sheet piles, characterized in that the work of injecting overflowing mud water into a casing previously excavated by a submersible pump is sequentially repeated.
JP23104686A 1986-09-29 1986-09-29 Construction method of sheet pile Expired - Lifetime JPH076187B2 (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
JP23104686A JPH076187B2 (en) 1986-09-29 1986-09-29 Construction method of sheet pile

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
JP23104686A JPH076187B2 (en) 1986-09-29 1986-09-29 Construction method of sheet pile

Publications (2)

Publication Number Publication Date
JPS6389727A JPS6389727A (en) 1988-04-20
JPH076187B2 true JPH076187B2 (en) 1995-01-30

Family

ID=16917433

Family Applications (1)

Application Number Title Priority Date Filing Date
JP23104686A Expired - Lifetime JPH076187B2 (en) 1986-09-29 1986-09-29 Construction method of sheet pile

Country Status (1)

Country Link
JP (1) JPH076187B2 (en)

Also Published As

Publication number Publication date
JPS6389727A (en) 1988-04-20

Similar Documents

Publication Publication Date Title
EP0810327B1 (en) Method and device for laying underground continuous walls
JPH0517946A (en) Excavating device for underground continuous wall
JPH04179726A (en) Wall member in simplified underground continuous wall construction method and simplified underground continuous wall construction method using the same
JPH07173835A (en) Excavator for underground continuous wall
JPH1136338A (en) Construction method of underground structure
JPH076187B2 (en) Construction method of sheet pile
JP2874906B2 (en) Shaft construction method
KR102225104B1 (en) Open shield method
JP2876265B2 (en) Sheet pile for underground continuous wall and underground continuous wall method
JP2668648B2 (en) Construction method of underground structure and starting pit used for it
JP3023575B2 (en) Track reinforcement machine
JP2673940B2 (en) How to build a horizontal plate-like structure in the ground
JP2963802B2 (en) How to build an underground parking
JPS63219727A (en) Construction of water-stop sheet pile wall
JPH03180614A (en) Construction of retaining wall for underground structure
JP2024092472A (en) Method of entering an open shield machine into a vertical shaft in an open shield construction method and a vertical shaft of an open shield machine
JPH07233697A (en) Method and equipment for forming dug ditch
JP4484068B2 (en) Open shield method
JP2736756B2 (en) Pipe burial method
JP2003041896A (en) Concrete caisson for use in open shield tunneling method
JPS61151314A (en) Method and device of building underground wall body
JPH0510084A (en) Execution method of deeper depth man hole
JPH0759877B2 (en) Open shield method
JPS6120754B2 (en)
JPH0553891B2 (en)