Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
JP596694A
Other languages
Japanese (ja)
Inventor
Masaki Omori
雅樹 大森
Takeshi Ikeda
武 池田
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Mitsubishi Plastics Inc
Original Assignee
Mitsubishi Plastics Inc
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Mitsubishi Plastics Inc filed Critical Mitsubishi Plastics Inc
Priority to JP596694A priority Critical patent/JPH07205281A/en
Publication of JPH07205281A publication Critical patent/JPH07205281A/en
Pending legal-status Critical Current

Links

Landscapes

  • Shaping Of Tube Ends By Bending Or Straightening (AREA)

Abstract

PURPOSE:To continuously mold a receiving mouth at the end part of a synthetic resin pipe member. CONSTITUTION:A heating device 4 is arranged on one side of a clamp device 1 and a receiving mouth molding machine 6 is arranged on the other side thereof. The end part of the synthetic resin pipe member P clamped by a clamp device 1 is heated and softened by the heating device 4 and, subsequently, the clamp device 1 is rotated by 180 deg. on a horizontal surface to insert the core mold 61 of the receiving mouth molding machine 6 in the heated and softened end part of the pipe member P to mold an expanded receiving mouth. By this constitution, the receiving mouth can be efficiently and continuously molded at the end part of the synthetic resin pipe member P.

Description

【発明の詳細な説明】Detailed Description of the Invention

【0001】[0001]

【産業上の利用分野】本発明は、合成樹脂製管体の端部
に拡径受口を成形する方法、及びその装置に関する。
BACKGROUND OF THE INVENTION 1. Field of the Invention The present invention relates to a method and apparatus for molding a diameter-enlarging port at the end of a synthetic resin tube.

【0002】[0002]

【従来の技術】合成樹脂製管体の端部に受口を成形する
場合、従来から広く行なわれている方法として、例えば
管体の端部を加熱オイルに浸漬して加熱軟化し、次いで
この管体を成形装置にセットした後、加熱軟化した端部
にコア型を圧入して拡径受口を成形する方法がある。
2. Description of the Related Art As a conventional method widely used for molding a socket at the end of a synthetic resin pipe, for example, the end of the pipe is immersed in heating oil to be softened by heating and then There is a method in which the tube body is set in a molding device, and then a core die is press-fitted into the end portion that has been softened by heating to mold the expanded diameter receiving port.

【0003】[0003]

【発明が解決しようとする課題】ところが、この従来成
形法の場合には、加熱工程と、コア型の圧入による拡径
工程とが分離・独立した工程からなるため、この工程の
中間段階の搬送、セッティング作業等に時間がかかると
いう問題があった。
However, in the case of this conventional molding method, the heating step and the diameter-expanding step by press-fitting the core mold are separated and independent steps. However, there was a problem that setting work took time.

【0004】本発明はかかる課題を解決したものであっ
て、加熱工程と拡径工程とを連続して行なうことのでき
る受口の成形方法及び装置を提供するものである。
The present invention has been made to solve the above problems and provides a method and apparatus for molding a receptacle capable of continuously performing a heating step and a diameter expanding step.

【0005】[0005]

【課題を解決するための手段】請求項1の発明は、クラ
ンプ装置の一方側に加熱装置を配設すると共に他方側に
受口成形装置を配設し、該クランプ装置に把持した合成
樹脂製管体の端部を加熱装置で加熱軟化し、次いでクラ
ンプ装置を水平面上で180°回転させて加熱軟化した
管体の端部に受口成形装置のコア型を圧入して拡径受口
を成形することを特徴とする。
According to a first aspect of the present invention, a heating device is provided on one side of a clamp device, and a mouthpiece forming device is provided on the other side, and the clamp device is made of synthetic resin. The end of the pipe is heated and softened by a heating device, and then the clamp device is rotated 180 ° on a horizontal plane to press and insert the core mold of the mouth forming device into the end of the heat-softened pipe to expand the diameter. It is characterized by being molded.

【0006】請求項2の発明は、2台のクランプ装置を
並設してその一方側に加熱装置を配設すると共に他方側
に受口成形装置を配設し、前記クランプ装置に把持した
合成樹脂製管体の端部に拡径受口を成形するにあたり、
次の各成形工程からなるものである。即ち、第1工程で
は、第1クランプ装置に把持した合成樹脂製管体の端部
を加熱装置で加熱軟化すると共に、第2クランプ装置に
把持した合成樹脂製管体の加熱軟化した端部に受口成形
装置のコア型を圧入して拡径受口を成形する。次の第2
工程では、2台のクランプ装置を一体に平行移動させる
と共に第1クランプ装置のみを水平面上で180°回転
させ、また加熱装置をそれぞれのクランプ装置と共に平
行移動させて所定位置にセットする。第3工程では、第
1クランプ装置に把持した管体の加熱軟化した端部に受
口成形装置のコア型を圧入して拡径受口を成形すると共
に、第2クランプ装置に把持した管体の端部を加熱装置
で加熱軟化するか、または新たに第2クランプ装置に把
持した別の管体の端部を加熱装置で加熱軟化することを
特徴とする。
According to a second aspect of the present invention, two clamp devices are arranged in parallel, a heating device is provided on one side of the clamp device, and a mouthpiece forming device is provided on the other side of the clamp device. When molding the diameter expansion socket at the end of the resin tube,
It comprises the following respective molding steps. That is, in the first step, the end portion of the synthetic resin pipe body held by the first clamp device is heated and softened by the heating device, and the end portion of the synthetic resin pipe body held by the second clamp device is softened by heating. The core mold of the mouthpiece forming device is press-fitted to form the expanded diameter mouthpiece. Next second
In the step, the two clamp devices are translated in parallel with each other, only the first clamp device is rotated by 180 ° on the horizontal plane, and the heating device is translated in parallel with the respective clamp devices and set in a predetermined position. In the third step, the core mold of the mouthpiece forming device is press-fitted into the heat-softened end of the pipe body gripped by the first clamp device to form a diameter-enlarged receptacle, and the pipe body gripped by the second clamp device is formed. Is characterized in that the end of the tube is heated and softened by a heating device, or the end of another tube newly gripped by the second clamp device is heated and softened by the heating device.

【0007】請求項3の発明は、2台のクランプ装置を
ベース板上に並設すると共に、それぞれのクランプ装置
をベース板の水平面上で180°回転可能に軸支する。
そして、ベース板を架台に差し渡したガイドレールに沿
って移動可能に設け、該ベース板の移動方向と直交する
架台の一方側に加熱装置を配設すると共に他方側に受口
成形装置を配設し、更に前記加熱装置をベース板の移動
方向と平行に移動可能としたことを特徴とする。
According to the third aspect of the invention, the two clamp devices are arranged side by side on the base plate, and the respective clamp devices are pivotally supported by 180 ° on the horizontal plane of the base plate.
Then, the base plate is movably provided along a guide rail extending over the gantry, and the heating device is arranged on one side of the gantry orthogonal to the moving direction of the base plate and the mouth forming device is arranged on the other side. In addition, the heating device can be moved in parallel with the moving direction of the base plate.

【0008】[0008]

【作用】請求項1の発明は、クランプ装置を水平面上で
180°回転させることによって、該クランプ装置に把
持した管体の端部を加熱する工程と、拡径する工程を連
続して行なうことができる。
According to the first aspect of the present invention, the step of heating the end portion of the pipe body held by the clamp device and the step of expanding the diameter are performed continuously by rotating the clamp device by 180 ° on a horizontal plane. You can

【0009】請求項2及び3の発明は、2台のクランプ
装置を一体に並設してその一方側に加熱装置を配設する
と共に他方側に受口成形装置を配設し、一方のクランプ
装置に把持した管体の端部を加熱しつつ、他方のクラン
プ装置に把持した管体の端部に拡径するので、作業時間
を短縮できる。
According to the second and third aspects of the invention, the two clamp devices are integrally arranged side by side, the heating device is provided on one side of the clamp device, and the mouthpiece forming device is provided on the other side of the clamp device. The working time can be shortened because the end portion of the tubular body held by the device is heated and the diameter is expanded to the end portion of the tubular body held by the other clamp device.

【0010】[0010]

【実施例】以下、本発明の実施例を図面にて詳細に説明
する。図1は本発明の成形装置の概略を示す平面図、図
2〜5は本発明の成形工程を説明する概略図、図6は加
熱工程の一実施例を示す部分断面図、図7は受口の拡径
工程の一実施例を示す断面図、図8は受口の拡径工程の
他の実施例を示す断面図である。図中符号1はクランプ
装置、2は基台、3はベース板、4は熱風ヒータ等の加
熱装置、5は枠体、6は受口成形装置、7及び8は架台
である。Pは塩化ビニル樹脂等の合成樹脂からなる管体
であって、図中のPa,Pb,Pcは別の管体Pを便宜
上表示するものである。
Embodiments of the present invention will now be described in detail with reference to the drawings. 1 is a plan view showing an outline of a molding apparatus of the present invention, FIGS. 2 to 5 are schematic views illustrating a molding step of the present invention, FIG. 6 is a partial sectional view showing an embodiment of a heating step, and FIG. FIG. 8 is a cross-sectional view showing an example of the diameter expanding process of the mouth, and FIG. 8 is a cross-sectional view showing another embodiment of the diameter expanding process of the receiving port. In the figure, reference numeral 1 is a clamp device, 2 is a base, 3 is a base plate, 4 is a heating device such as a hot air heater, 5 is a frame, 6 is a mouth forming device, and 7 and 8 are pedestals. P is a tubular body made of a synthetic resin such as vinyl chloride resin, and Pa, Pb, and Pc in the figure are different tubular bodies P for convenience sake.

【0011】クランプ装置1は第1クランプ装置1aと
第2クランプ装置1bとからなり、この2台のクランプ
装置1a,1bはベース板3上に所定間隔を保って並設
されている。そして、2台のクランプ装置1a,1bの
間隔を隔てて第1加工ラインL1 、第2加工ラインL2
及び第3加工ラインL3 が並列に設けられている。
The clamp device 1 comprises a first clamp device 1a and a second clamp device 1b, and these two clamp devices 1a and 1b are arranged side by side on a base plate 3 with a predetermined space. Then, the first machining line L1 and the second machining line L2 are spaced apart by the two clamp devices 1a and 1b.
And the third processing line L3 are provided in parallel.

【0012】前記ベース板3は架台7に差し渡したガイ
ドレール71,71に沿って移動可能となっており、こ
のベース板3の移動にしたがって第1クランプ装置1a
が第1加工ラインL1 と第2加工ラインL2 の間を移動
し、第2クランプ装置1bが第2加工ラインL2 と第3
加工ラインL3 の間を移動できるようになっている。
The base plate 3 is movable along the guide rails 71, 71 extending over the pedestal 7, and the first clamp device 1a is moved as the base plate 3 moves.
Moves between the first processing line L1 and the second processing line L2, and the second clamp device 1b moves between the second processing line L2 and the third processing line L2.
It is possible to move between processing lines L3.

【0013】クランプ装置1a,1bはターンテーブル
11上に支持されており、該ターンテーブル11は基台
2に回転可能に軸支されている。そして、図示しない駆
動装置が作動したときターンテーブル11が水平面上で
180°回転し、クランプ装置1a,1bに把持した管
体Pa,Pbの端部が加工ラインL1 ,L2 ,L3 と平
行する方向を向くようになっている。また、ベース板3
には前記ガイドレール71と直交する方向にガイドレー
ル31,31が設けられており、該ガイドレール31,
31に沿って基台2に支持されたクランプ装置1a,1
bが単独に移動できるようになっている。
The clamp devices 1a and 1b are supported on a turntable 11, and the turntable 11 is rotatably supported by a base 2. Then, when a drive device (not shown) is operated, the turntable 11 rotates 180 ° on a horizontal plane, and the ends of the pipe bodies Pa and Pb held by the clamp devices 1a and 1b are parallel to the machining lines L1, L2 and L3. To face. Also, the base plate 3
Is provided with guide rails 31, 31 in a direction orthogonal to the guide rail 71.
Clamping devices 1a, 1 supported on the base 2 along 31
b can move independently.

【0014】クランプ装置1a,1bの一方側、即ち図
1に示した架台7の右側には架台8が配設されており、
該架台8上に加熱装置4が設けられている。加熱装置4
は枠体5に支持されており、該枠体5が架台8に差し渡
したガイドレール81,81に沿って第1加工ラインL
1 と第3加工ラインL3 の間を移動できるようになって
いる。また、枠体5には前記ガイドレール81と直交す
る方向にガイドレール51,51が設けられており、該
ガイドレール51,51に沿って加熱装置4が移動でき
るようになっている。一方、架台7の左側の第2加工ラ
インL2 上には、コア型61を備えた受口成形装置6が
配設されている。
A mount 8 is provided on one side of the clamp devices 1a and 1b, that is, on the right side of the mount 7 shown in FIG.
The heating device 4 is provided on the pedestal 8. Heating device 4
Is supported by the frame body 5, and the first machining line L is provided along the guide rails 81, 81 which the frame body 5 extends to the frame 8.
It is possible to move between 1 and the third processing line L3. Further, the frame body 5 is provided with guide rails 51 and 51 in a direction orthogonal to the guide rail 81, and the heating device 4 can be moved along the guide rails 51 and 51. On the other hand, on the second processing line L2 on the left side of the gantry 7, the mouth forming device 6 having the core die 61 is arranged.

【0015】本発明の成形装置は上記の構成からなるも
のであって、この成形装置による受口の成形工程を図2
〜5に基づいて説明する。図2は成形工程の途中段階を
示すものであって、第1クランプ装置1aと加熱装置4
が第1加工ラインL1 上に位置しており、第1クランプ
装置1aに把持された管体Paの両端部は加熱されてい
ない。一方、第2クランプ装置1bは第2加工ラインL
2 上に位置しており、該クランプ装置1bに把持された
管体Pbの加熱装置4側の端部は加熱されておらず、受
口成形装置6側の端部は所定温度に加熱軟化している。
The molding apparatus of the present invention has the above-mentioned structure, and the molding process of the receptacle by this molding apparatus is shown in FIG.
5 to 5. FIG. 2 shows an intermediate stage of the molding process, in which the first clamp device 1a and the heating device 4 are used.
Is located on the first processing line L1, and both ends of the pipe body Pa gripped by the first clamp device 1a are not heated. On the other hand, the second clamp device 1b has a second processing line L
2 the end of the pipe Pb gripped by the clamp device 1b on the side of the heating device 4 is not heated, and the end on the side of the mouth forming device 6 is softened by heating to a predetermined temperature. ing.

【0016】本発明の第1工程では、この図2に示した
状態から第1加工ラインL1 では加熱装置4が図の左側
に移動し、図6に示した如く第1クランプ装置1aに把
持した管体Paの端部が加熱装置4内に挿入される。そ
こで、管体Paの端部を所定温度に加熱軟化してから加
熱装置4をもとの位置に戻す。一方、第2加工ラインL
2 では第2クランプ装置1bが図の左側に移動し、図7
に示した如くクランプ装置1bに把持された管体Pbの
端部に受口成形装置6のコア型61を圧入して拡径受口
を形成した後、クランプ装置1bをもとの位置に戻す。
In the first step of the present invention, the heating device 4 is moved to the left side of the drawing from the state shown in FIG. 2 in the first processing line L1 and is held by the first clamp device 1a as shown in FIG. The end of the pipe body Pa is inserted into the heating device 4. Therefore, after heating and softening the end portion of the pipe body Pa to a predetermined temperature, the heating device 4 is returned to the original position. On the other hand, the second processing line L
2, the second clamp device 1b moves to the left side of the figure, and
After the core die 61 of the mouthpiece forming device 6 is press-fitted into the end portion of the pipe body Pb gripped by the clamp device 1b to form a diameter-enlarged mouth, the clamp device 1b is returned to its original position. .

【0017】第2工程では、図3に示した如くクランプ
装置1a,1bを一体に平行移動させて第1クランプ装
置1aを第2加工ラインL2 上に位置させると共に、第
2クランプ装置1bを第3加工ラインL3 上に位置させ
る。そこで、第1クランプ装置1aのみを水平面上で1
80°回転させて管体Paの加熱軟化した端部を受口成
形装置6側に向ける。また、これらの作業工程と同時に
加熱装置4を移動させて第3加工ラインL3 上に位置さ
せる。
In the second step, as shown in FIG. 3, the clamp devices 1a and 1b are integrally moved in parallel to position the first clamp device 1a on the second processing line L2, and the second clamp device 1b is moved to the first processing line L2. 3 Position on processing line L3. Therefore, only the first clamp device 1a is set to 1 on the horizontal plane.
The end portion of the pipe Pa, which has been heated and softened, is turned toward the mouthpiece forming device 6 side by rotating it by 80 °. At the same time as these working steps, the heating device 4 is moved and positioned on the third processing line L3.

【0018】次の第3工程では、第1クランプ装置1a
を図の左側に移動させ、該第1クランプ装置1aに把持
した管体Paの加熱軟化した端部に受口成形装置6のコ
ア型61を圧入して拡径受口を成形する。そして、これ
同時に加熱装置4を図の左側に移動させ、該加熱装置4
に第2クランプ装置1bに把持した管体Pbの端部を挿
入して加熱軟化する。
In the next third step, the first clamp device 1a
Is moved to the left side of the figure, and the core die 61 of the mouthpiece forming device 6 is press-fitted into the heat-softened end of the pipe body Pa held by the first clamp device 1a to form the expanded diameter mouthpiece. At the same time, the heating device 4 is moved to the left side of the drawing, and the heating device 4
Then, the end portion of the tubular body Pb gripped by the second clamp device 1b is inserted and softened by heating.

【0019】第4工程では、図4に示した如くクランプ
装置1a,1bを一体に平行移動させ、第1クランプ装
置1aを第1加工ラインL1 上に位置させると共に、第
2クランプ装置1bを第2加工ラインL2 上に位置さ
せ、第2クランプ装置1bのみを水平面上で180°回
転させる。そして、前記同様にして、第1加工ラインL
1 で受口が形成されていない管体Paの端部を加熱装置
4で加熱軟化し、第2加工ラインL2 上で受口が形成さ
れていない管体Pbの端部に受口成形装置6のコア型6
1を圧入して拡径受口を形成する。かくして、管体Pb
の両端部に受口が形成されるので、第2クランプ装置1
bから管体Pbを取り外して新たな管体Pcを把持す
る。
In the fourth step, as shown in FIG. 4, the clamp devices 1a and 1b are integrally moved in parallel so that the first clamp device 1a is located on the first processing line L1 and the second clamp device 1b is moved to the first processing line L1. 2 Position on the processing line L2, and rotate only the second clamp device 1b by 180 ° on the horizontal plane. Then, similarly to the above, the first processing line L
The end portion of the pipe body Pa in which the mouth is not formed in 1 is heated and softened by the heating device 4, and the mouth end forming device 6 is attached to the end portion of the pipe body Pb in which the mouth is not formed on the second processing line L2. Core mold 6
1 is press-fitted to form the expanded diameter receiving port. Thus, the tube Pb
Since the receiving ports are formed at both ends of the second clamping device 1,
The pipe body Pb is removed from b and a new pipe body Pc is gripped.

【0020】第5工程では、図5に示した如くクランプ
装置1a,1bを一体に平行移動させ、第1クランプ装
置1aを第2加工ラインL2 上に位置させると共に第2
クランプ装置1bを第3加工ラインL3 上に位置させ、
第1クランプ装置1aのみを水平面上で180°回転さ
せる。そして、前記同様にして第2加工ラインL2 で受
口が形成されていない管体Paの端部に受口成形装置6
のコア型61を圧入すると、管体Paの両端部に受口が
形成される。一方、第3加工ラインL3 上に位置してい
る管体Pcの端部を加熱装置4で加熱軟化する。この成
形工程を順次繰り返すことによって、管体Pの両端部に
連続して受口を成形することができる。
In the fifth step, as shown in FIG. 5, the clamping devices 1a and 1b are integrally translated in parallel to position the first clamping device 1a on the second machining line L2 and the second clamping line 1a.
Position the clamp device 1b on the third machining line L3,
Only the first clamp device 1a is rotated 180 ° on the horizontal plane. Then, in the same manner as described above, the mouthpiece forming device 6 is attached to the end portion of the pipe Pa where the mouthpiece is not formed in the second processing line L2.
When the core mold 61 is press-fitted, receiving ports are formed at both ends of the tubular body Pa. On the other hand, the end portion of the pipe body Pc located on the third processing line L3 is heated and softened by the heating device 4. By sequentially repeating this molding process, the receiving ports can be continuously formed at both ends of the pipe body P.

【0021】尚、前記成形工程では管体Pの両端部に受
口を成形する場合について説明したが、管体Pの一端部
に受口を成形するだけの場合には図3に示した管体Pb
の一端に受口を成形した後、該管体Pbを新たな管体P
cと取替え、また図4に示した管体Paの一端に受口を
形成した後、該管体Paを新たな管体Pcと取替えれば
よい。また、図7には接着剤を用いて管体を接続する拡
径受口の成形方法を例示したが、拡径受口の内周面にゴ
ムリングを装着するための環状溝を形成することもでき
る。
In the molding step, the case where the receiving ports are formed at both ends of the pipe P has been described, but in the case where the receiving ports are only formed at one end of the pipe P, the pipe shown in FIG. Body Pb
After forming a receptacle at one end of the pipe, the pipe Pb is replaced with a new pipe P.
c, or after forming a receptacle at one end of the pipe body Pa shown in FIG. 4, the pipe body Pa may be replaced with a new pipe body Pc. In addition, FIG. 7 illustrates a method for forming the expanded diameter receiving port that connects the pipes with an adhesive. However, an annular groove for mounting a rubber ring should be formed on the inner peripheral surface of the expanded diameter receiving port. You can also

【0022】このゴムリング装着溝を有する受口を成形
する場合には、図8に断面図で示した如く環状溝62に
複数個の溝形成部材63が装着され、該溝形成部材63
を楔部材64の軸方向移動によって出没させるようにし
たコア型61を用いて成形するとよい。即ち、コア型6
1を管体Pの端部に圧入して拡径受口を成形した後、図
8の下半図に示す如く楔部材64を移動させて環状溝6
2から溝形成部材63を突出させると、ゴムリング装着
溝を成形することができる。
When molding a receptacle having this rubber ring mounting groove, a plurality of groove forming members 63 are mounted in the annular groove 62 as shown in the sectional view of FIG.
Is preferably formed by using a core mold 61 which is configured to be projected and retracted by the axial movement of the wedge member 64. That is, core type 6
After press-fitting 1 into the end of the pipe P to form the expanded diameter receiving port, the wedge member 64 is moved to move the annular groove 6 as shown in the lower half of FIG.
By protruding the groove forming member 63 from 2, the rubber ring mounting groove can be formed.

【0023】また、前述した成形工程において、加熱装
置として熱風ヒータを用いる場合には、管体を回転させ
なくても該管体の端部を円周上に亘って均一温度に加熱
することができるので、特に管体の中間部から枝管が突
出した枝管付き管体の端部に受口を成形する場合に好適
である。
When a hot air heater is used as the heating device in the above-mentioned molding step, the end of the tubular body can be heated to a uniform temperature over the circumference without rotating the tubular body. Therefore, it is particularly suitable for forming the receiving port at the end of the tubular body with the branch pipe in which the branch pipe projects from the intermediate portion of the tubular body.

【0024】[0024]

【発明の効果】以上詳述した如く、本発明は加熱工程と
拡径工程を連続した一連の作業工程で行なうので、合成
樹脂製管体の端部に連続して受口を成形することができ
る。また、2台のクランプ装置を一体に並設してその一
方側に加熱装置を配設すると共に他方側に受口成形装置
を配設した本発明の成形装置を用いると、一方のクラン
プ装置に把持した管体の端部を加熱しつつ、他方のクラ
ンプ装置に把持した管体の端部を拡径できるので、従来
装置と比較して作業時間を大幅に短縮することができ
る。
As described above in detail, since the present invention performs the heating step and the diameter expanding step in a series of continuous working steps, it is possible to continuously form the receiving port at the end of the synthetic resin pipe body. it can. Further, by using the molding apparatus of the present invention in which two clamp devices are integrally arranged side by side and the heating device is disposed on one side of the clamp device, and the mouthpiece molding device is disposed on the other side, one clamp device is provided. Since the diameter of the end of the gripped tube can be increased while heating the end of the gripped tube, the working time can be significantly reduced compared to the conventional device.

【図面の簡単な説明】[Brief description of drawings]

【図1】図1は本発明の成形装置の概略を示す平面図で
ある。
FIG. 1 is a plan view showing the outline of a molding apparatus of the present invention.

【図2】図2は本発明の第1工程を示す概略図である。FIG. 2 is a schematic view showing a first step of the present invention.

【図3】図3は本発明の第2、及び第3工程を示す概略
図である。
FIG. 3 is a schematic view showing second and third steps of the present invention.

【図4】図4は本発明の第4工程を示す概略図である。FIG. 4 is a schematic view showing a fourth step of the present invention.

【図5】図5は本発明の第5工程を示す概略図である。FIG. 5 is a schematic view showing a fifth step of the present invention.

【図6】図6は加熱工程の一実施例を示す部分断面図で
ある。
FIG. 6 is a partial cross-sectional view showing an example of a heating step.

【図7】図7は受口の拡径工程の一実施例を示す断面図
である。
FIG. 7 is a cross-sectional view showing an embodiment of a diameter expansion process of a receiving port.

【図8】図8は受口の拡径工程の他の実施例を示す断面
図である。
FIG. 8 is a cross-sectional view showing another embodiment of the diameter expansion process of the receiving port.

【符号の説明】[Explanation of symbols]

1 クランプ装置 2 基台 3 ベース板 4 加熱装置 5 枠体 6 受口成形装置 61 コア型 P 合成樹脂製管体 1a 第1クランプ装置 1b 第2クランプ装置 DESCRIPTION OF SYMBOLS 1 Clamping device 2 Base 3 Base plate 4 Heating device 5 Frame 6 Receptacle forming device 61 Core type P Synthetic resin pipe body 1a 1st clamping device 1b 2nd clamping device

Claims (3)

【特許請求の範囲】[Claims] 【請求項1】 クランプ装置(1)の一方側に加熱装置
(4)を配設すると共に他方側に受口成形装置(6)を
配設し、該クランプ装置(1)に把持した合成樹脂製管
体(P)の端部を加熱装置(4)で加熱軟化し、次いで
クランプ装置(1)を水平面上で180°回転させて加
熱軟化した管体(P)の端部に受口成形装置(6)のコ
ア型(61)を圧入して拡径受口を成形することを特徴
とする受口の成形方法。
1. A synthetic resin which is provided with a heating device (4) on one side of the clamp device (1) and a mouthpiece forming device (6) on the other side, and is gripped by the clamp device (1). The end portion of the pipe body (P) is softened by heating with a heating device (4), and then the clamp device (1) is rotated 180 ° on a horizontal plane to form a socket on the end portion of the heat-softened pipe body (P). A method for forming a receiving opening, characterized in that a core die (61) of an apparatus (6) is press-fitted to form an expanded diameter receiving opening.
【請求項2】 2台のクランプ装置(1a),(1b)
を並設してその一方側に加熱装置(4)を配設すると共
に他方側に受口成形装置(6)を配設し、前記クランプ
装置(1a),(1b)に把持した合成樹脂製管体(P
a),(Pb)の端部に拡径受口を成形するにあたり、
次の〜の各成形工程からなることを特徴とする受口
の成形方法。 第1工程では、第1クランプ装置(1a)に把持した
合成樹脂製管体(Pa)の端部を加熱装置(4)で加熱
軟化すると共に、第2クランプ装置(1b)に把持した
合成樹脂製管体(Pb)の加熱軟化した端部に受口成形
装置(6)のコア型(61)を圧入して拡径受口を成形
し、 第2工程では、2台のクランプ装置(1a),(1
b)を一体に平行移動させると共に第1クランプ装置
(1a)のみを水平面上で180°回転させ、また加熱
装置(4)をそれぞれのクランプ装置(1a),(1
b)と共に平行移動させて所定位置にセットし、 第3工程では、第1クランプ装置(1a)に把持した
管体(Pa)の加熱軟化した端部に受口成形装置(6)
のコア型(61)を圧入して拡径受口を成形すると共
に、第2クランプ装置(1b)に把持した管体(Pb)
の端部を加熱装置(4)で加熱軟化するか、または新た
に第2クランプ装置(1b)に把持した別の管体(P
c)の端部を加熱装置(4)で加熱軟化すること、
2. Two clamp devices (1a), (1b)
Are arranged in parallel, the heating device (4) is arranged on one side thereof, the mouthpiece forming device (6) is arranged on the other side thereof, and the clamp device (1a), (1b) is gripped by the synthetic resin. Tube (P
When forming the expanded diameter receiving port at the ends of a) and (Pb),
A method for forming a receptacle, comprising the following forming steps (1) to (3). In the first step, the heating device (4) heats and softens the end of the synthetic resin pipe (Pa) held by the first clamp device (1a), and the synthetic resin held by the second clamp device (1b). The core die (61) of the mouthpiece forming device (6) is press-fitted into the heat-softened end of the pipe body (Pb) to form a diameter-enlarged mouthpiece. In the second step, two clamp devices (1a ), (1
b) is integrally translated, and only the first clamp device (1a) is rotated by 180 ° on the horizontal plane, and the heating device (4) is connected to the respective clamp devices (1a), (1).
b) is moved in parallel with and set at a predetermined position, and in the third step, the mouth forming device (6) is attached to the heat-softened end of the pipe body (Pa) held by the first clamp device (1a).
The core body (61) is press-fitted to form the expanded diameter receiving port, and the tubular body (Pb) gripped by the second clamp device (1b).
The end portion of the pipe is heated and softened by the heating device (4), or another pipe (P) newly gripped by the second clamp device (1b) is used.
heating and softening the end of c) with a heating device (4),
【請求項3】 2台のクランプ装置(1a),(1b)
をベース板(3)上に並設すると共に、それぞれのクラ
ンプ装置(1a),(1b)をベース板(3)の水平面
上で180°回転可能に軸支し、またベース板(3)を
架台(7)に差し渡したガイドレール(71),(7
1)に沿って移動可能に設け、該ベース板(3)の移動
方向と直交する架台(7)の一方側に加熱装置(4)を
配設すると共に他方側に受口成形装置(6)を配設し、
更に前記加熱装置(4)をベース板(3)の移動方向と
平行に移動可能としたことを特徴とする受口の成形装
置。
3. Two clamp devices (1a), (1b)
Are installed side by side on the base plate (3), and the respective clamp devices (1a) and (1b) are pivotally supported by 180 ° on the horizontal plane of the base plate (3), and the base plate (3) is also supported. Guide rails (71), (7
1) is provided so as to be movable, and a heating device (4) is provided on one side of a pedestal (7) orthogonal to the moving direction of the base plate (3), and a mouth forming device (6) is provided on the other side. Is installed,
Further, the heating device (4) can be moved in parallel with the moving direction of the base plate (3), and a molding device for a receptacle.
JP596694A 1994-01-24 1994-01-24 Method and apparatus for molding receiving mouth Pending JPH07205281A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
JP596694A JPH07205281A (en) 1994-01-24 1994-01-24 Method and apparatus for molding receiving mouth

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
JP596694A JPH07205281A (en) 1994-01-24 1994-01-24 Method and apparatus for molding receiving mouth

Publications (1)

Publication Number Publication Date
JPH07205281A true JPH07205281A (en) 1995-08-08

Family

ID=11625623

Family Applications (1)

Application Number Title Priority Date Filing Date
JP596694A Pending JPH07205281A (en) 1994-01-24 1994-01-24 Method and apparatus for molding receiving mouth

Country Status (1)

Country Link
JP (1) JPH07205281A (en)

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP2007537054A (en) * 2003-07-12 2007-12-20 ヘイズ、フランク・エフ・ジュニア Method and apparatus for forming a flared end in a tube
CN102225617A (en) * 2011-06-14 2011-10-26 上海长园电子材料有限公司 Pipe fitting expanding device

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP2007537054A (en) * 2003-07-12 2007-12-20 ヘイズ、フランク・エフ・ジュニア Method and apparatus for forming a flared end in a tube
CN102225617A (en) * 2011-06-14 2011-10-26 上海长园电子材料有限公司 Pipe fitting expanding device

Similar Documents

Publication Publication Date Title
JPH0639839A (en) Production of tire for road vehicle
US4059379A (en) Method of belling plastic pipe and apparatus therefor
JPH07205281A (en) Method and apparatus for molding receiving mouth
JPH0364294B2 (en)
US4304037A (en) Method and apparatus for installing a sealing ring
JPH09273421A (en) Joint and manufacture thereof
JP2007283343A (en) Drawing method and its apparatus
TWI290542B (en) Glass mold forming device, apparatus and method
JPH07155879A (en) Production of tube joint and oscillating working device therefor
KR101321062B1 (en) Pulling apparatus of mandrel for hose
CN115583004A (en) Flaring device for PVC (polyvinyl chloride) pipe
JP3978362B2 (en) Manufacturing method of bent resin tube
CN110901033B (en) Core layer foaming thermoplastic plastic pipe interface processing method and product
JPS587402B2 (en) Automatic fume pipe supply/discharge device for fume pipe socket cutting machine
JPH08217477A (en) Device for cutting glass pipe and its method
WO2002007906A3 (en) Method and forming machine for deforming a hollow workpiece
JP4600900B2 (en) Method and apparatus for bending thin metal pipe
JP2713452B2 (en) Bamboo imitation machine
US20050044679A1 (en) Apparatus and method for forming duct members
JPH0885149A (en) Molding of curved pipe
CN220329790U (en) Socket steel pipe end expanding device
JPH06106610A (en) Tube folding method
JP2004262111A (en) Method and apparatus for bending thermoplastic resin pipe
JP2583513Y2 (en) Tube folding device
JP2003326525A (en) Method and apparatus for preforming tire

Legal Events

Date Code Title Description
A131 Notification of reasons for refusal

Free format text: JAPANESE INTERMEDIATE CODE: A131

Effective date: 20040823

A02 Decision of refusal

Free format text: JAPANESE INTERMEDIATE CODE: A02

Effective date: 20041227