JPH071195U - Steel frame erection equipment - Google Patents

Steel frame erection equipment

Info

Publication number
JPH071195U
JPH071195U JP3147593U JP3147593U JPH071195U JP H071195 U JPH071195 U JP H071195U JP 3147593 U JP3147593 U JP 3147593U JP 3147593 U JP3147593 U JP 3147593U JP H071195 U JPH071195 U JP H071195U
Authority
JP
Japan
Prior art keywords
column
steel
erection
box
base end
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
JP3147593U
Other languages
Japanese (ja)
Inventor
隆次 今村
岡野  正
弘司 近藤
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Shimizu Corp
Original Assignee
Shimizu Corp
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Shimizu Corp filed Critical Shimizu Corp
Priority to JP3147593U priority Critical patent/JPH071195U/en
Publication of JPH071195U publication Critical patent/JPH071195U/en
Pending legal-status Critical Current

Links

Landscapes

  • Conveying And Assembling Of Building Elements In Situ (AREA)

Abstract

(57)【要約】 【目的】 クレーンやホイスト等を上下方向に移動させ
るのみで、容易に鉄骨柱の建方作業を行うことのできる
鉄骨建方装置を提供することを目的とする。 【構成】 一方向に進退自在な台車11と、台車11上
に縦回動自在に設けられた支持部材13とを備え、支持
部材13を、ボックス柱12の基端部12aの側面を支
持するための側部支持面18と、基端部12aの下面を
支持するための下部支持面19とを備えた略L字状の形
状とする構成とした。
(57) [Abstract] [Purpose] It is an object to provide a steel frame erection device that can easily perform a erection work of a steel column by simply moving a crane, a hoist or the like in the vertical direction. [Structure] A dolly 11 that can move back and forth in one direction, and a support member 13 that is vertically rotatably provided on the dolly 11 are provided. And a lower support surface 19 for supporting the lower surface of the base end portion 12a. The side support surface 18 has a substantially L shape.

Description

【考案の詳細な説明】[Detailed description of the device]

【0001】[0001]

【産業上の利用分野】[Industrial applications]

本考案は、建築構造物の躯体を構築するに際し、横臥状態の鉄骨柱を鉛直に起 立させるのに好適な鉄骨建方装置に関するものである。 The present invention relates to a steel erection device suitable for vertically erecting a steel column in a recumbent state when constructing a skeleton of a building structure.

【0002】[0002]

【従来の技術】[Prior art]

一般に、建築構造物の躯体を構成する鉄骨柱を地盤あるいはスラブ上に設置す る建方作業は、横臥状態の鉄骨柱の先端部をクレーンやホイスト等により吊り上 げることによりこの鉄骨柱を起立させ、これを所定の位置に建方するようにして いる。 しかしながら、このような方法では、鉄骨柱を起立させる際に、地盤あるいは スラブの立設面を支点とするため、鉄骨柱の仕口部分がこの立設面と擦れて傷つ いてしまう。また、鉄骨柱に柱鉄筋を先組しておく場合においては、鉄骨柱の両 端から突出した柱鉄筋が立設面と接触して曲がってしまう恐れがあるという問題 がある。 Generally, erection work in which steel columns that form the frame of a building structure are installed on the ground or on a slab is performed by suspending the tip of the steel columns in a recumbent state by a crane or hoist. It stands upright and is erected at a predetermined position. However, in such a method, when the steel column is erected, the standing surface of the ground or the slab is used as a fulcrum, so that the joint portion of the steel column rubs against the standing surface and is damaged. Further, when the column rebars are assembled to the steel columns first, there is a problem that the column rebars protruding from both ends of the steel columns may come into contact with the standing surface and be bent.

【0003】 このような問題を解決するため、本出願人は、以下に示すような鉄骨柱の建方 装置を、先に出願している(特願昭63ー219233)。 図7および図8に示すように、建方装置1は、鉄骨柱2の基端部2aに一端を 固定する連結部材3と、この連結部材3の他端を縦回動自在に軸支するシャフト 4と、地盤やスラブ等の立設面5に固定されかつシャフト4を水平に嵌挿する一 対の側板6を有する支持台7とを具備した構造となっている。この建方装置1は 、立設面5からシャフト4までの高さ寸法が、少なくとも鉄骨柱2に先組された 柱鉄筋8の下端8aの回動半径よりも大きく設定されている。 このような構成の建方装置1では、連結部材3に鉄骨柱2の基端部2aをボル ト等で固定し、鉄骨柱2の先端部を図示しないクレーンやホイスト等により吊り 上げることにより、鉄骨柱2を、シャフト4を回動軸として90度縦回動させて 起立させるようになっている。このとき、前述したように立設面5からシャフト 4までの高さ寸法が、含なくとも柱鉄筋8の下端8aの回動半径よりも大きいの で、柱鉄筋8の下端8aが立設面5に接触することがなく、上記問題を解決する ことができる。In order to solve such a problem, the applicant of the present invention has previously applied for a steel frame erection device as described below (Japanese Patent Application No. 63-219233). As shown in FIGS. 7 and 8, the erection device 1 has a connecting member 3 having one end fixed to the base end 2a of the steel frame column 2 and the other end of the connecting member 3 rotatably supported vertically. The structure is provided with a shaft 4 and a support base 7 having a pair of side plates 6 fixed to an upright surface 5 such as the ground or a slab and into which the shaft 4 is horizontally inserted. In this erection device 1, the height dimension from the standing surface 5 to the shaft 4 is set to be larger than at least the turning radius of the lower end 8a of the column reinforcing bar 8 assembled in advance to the steel frame column 2. In the erection device 1 having such a configuration, the base end portion 2a of the steel frame pillar 2 is fixed to the connecting member 3 with a bolt or the like, and the tip end portion of the steel frame pillar 2 is lifted by a crane, hoist, or the like, which is not shown. The steel frame column 2 is vertically rotated 90 degrees about the shaft 4 to be erected. At this time, as described above, the height dimension from the upright surface 5 to the shaft 4 is larger than the turning radius of the lower end 8a of the column reinforcing bar 8 even if it is not included. It is possible to solve the above-mentioned problem without touching 5.

【0004】[0004]

【考案が解決しようとする課題】[Problems to be solved by the device]

しかしながら、上述したような従来の建方装置1には、以下のような問題が存 在する。 まず、鉄骨柱2を起立させるときに、シャフト4を回動軸として鉄骨柱2が縦 回動するので、これを吊り上げるクレーンやホイストを、鉄骨柱2の先端部がシ ャフト4を中心とした円弧を描くように、鉛直方向および水平方向の2方向に移 動させなければならない。 さて、近年、中高層のビルなどを建築する際に、下面にホイスト等を備えた架 設ユニットを用い、これを上昇させつつ、この下方でビルを構築していく方法が 、開発・実現されている。このような方法においては、ビルの各施工階において 立設すべき鉄骨柱の位置が一定であるため、架設ユニットの所定位置にホイスト を固定しておき、このホイストで鉄骨柱を建方することが考えられる。このよう な場合に前記建方装置1を適用しようとすると、鉄骨柱2を吊り上げるホイスト が固定されており、水平方向に移動不可能であるため、この建方装置1では鉄骨 柱2を起立させることができないという問題がある。 However, the conventional erection apparatus 1 as described above has the following problems. First, when the steel column 2 is erected, the steel column 2 vertically rotates about the shaft 4 as a rotation axis. Therefore, a crane or hoist that lifts the shaft 4 is centered on the shaft 4 with the tip of the steel column 2 as the center. It must be moved in two directions, vertical and horizontal, so as to draw an arc. Now, in recent years, when building middle-high-rise buildings, etc., a method has been developed and realized in which a construction unit with a hoist or the like on the lower surface is used and the building unit is built up under this while raising it. There is. In such a method, the position of the steel column to be erected on each construction floor of the building is constant, so it is necessary to fix the hoist at a predetermined position of the erection unit and construct the steel column with this hoist. Can be considered. In such a case, if the erection device 1 is applied, the hoist for hoisting the steel column 2 is fixed and cannot be moved in the horizontal direction, so that the steel column 2 is erected in this erection device 1. There is a problem that you can not.

【0005】 また、建方装置1では、連結部材3に鉄骨柱2の基端部2aをボルトなどで固 定する構成となっているため、ボルトなどの着脱作業に手間がかかる。 さらには、例えば建方装置1で起立させる鉄骨柱が、その内部にコンクリート を打設するボックス柱である場合などにおいては、コンクリートを打設する際に 、連結部材3に固定するために鉄骨柱に形成したボルト穴を塞ぐ必要があり、手 間がかかるという問題がある。 本考案は、以上のような点を考慮してなされたもので、クレーンやホイスト等 を上下方向に移動させるのみで、容易に鉄骨柱の建方作業を行うことのできる鉄 骨建方装置を提供することを目的とする。Further, in the erection device 1, since the base end portion 2a of the steel frame column 2 is fixed to the connecting member 3 with a bolt or the like, it is troublesome to attach and detach the bolt and the like. Furthermore, for example, in the case where the steel frame pillars to be erected by the erection device 1 are box pillars into which concrete is to be placed, for example, when the concrete is to be poured, the steel frame pillars are to be fixed to the connecting member 3. Since it is necessary to close the bolt hole formed in the above, there is a problem that it takes time. The present invention has been made in consideration of the above points, and provides a steel frame erection device that can easily perform a erection work of a steel frame column simply by moving a crane, a hoist or the like in the vertical direction. The purpose is to provide.

【0006】[0006]

【課題を解決するための手段】[Means for Solving the Problems]

本考案は、鉄骨柱を地盤やスラブ等の立設面に建方するための装置であって、 少なくとも一方向に進退自在な台車と、前記鉄骨柱の基端部を載置するため、該 台車に縦回動自在に設けられた支持部材とを備えてなり、該支持部材は、前記鉄 骨柱の基端部の側面を支持するための第1の支持面と、前記基端部の下面を支持 するための第2の支持面とを備えた略L字状の形状とされていることを特徴とし ている。 The present invention is a device for erection of a steel column on an upright surface such as a ground or a slab, in which at least a trolley and a base end portion of the steel column for mounting the trolley are mounted. And a supporting member rotatably provided on the carriage for vertical rotation. The supporting member includes a first supporting surface for supporting a side surface of the base end portion of the steel column and a base end portion of the base end portion. It is characterized by having a substantially L-shape with a second support surface for supporting the lower surface.

【0007】[0007]

【作用】[Action]

本考案の鉄骨建方装置では、鉄骨柱を建方するためには、横臥状態の鉄骨柱の 基端部を支持部材上に載置し、クレーンやホイスト等により鉄骨柱の先端部を鉛 直上方に吊り上げると、台車上の支持部材が縦回動しつつ、台車が鉄骨柱の先端 部の位置していた方向に引き寄せられて移動し、これにより鉄骨柱が起立する。 このとき、鉄骨柱の基端部は、横臥状態においてはその側面が支持部材の第1の 支持面で支持され、起立した状態においてはその下面が支持部材の第2の支持面 で支持されることになる。 In the steel erection device of the present invention, in order to construct a steel column, the base end of the steel column in a recumbent state is placed on the support member, and the tip of the steel column is vertically moved by a crane or a hoist. When it is lifted up, the supporting member on the bogie is vertically rotated and the bogie is attracted and moved in the direction in which the tip of the steel column was located, whereby the steel column stands up. At this time, the base end of the steel column is supported at its side surface by the first supporting surface of the supporting member in the recumbent state, and at its lower surface in the standing state by the second supporting surface of the supporting member. It will be.

【0008】[0008]

【実施例】【Example】

以下、本考案を図面に示す一実施例を参照して説明する。ここでは、例えば、 鉄骨鉄筋コンクリート造の躯体を、ホイスト等を備えた架設ユニットを用い、こ の架設ユニットを上昇させつつこの下方で順次躯体を構築していくとともに、躯 体を構成するボックス柱を、架設ユニットに固定されて水平方向に移動不可能な ホイストを用いて建方する場合の実施例を用いて説明する。 図1および図2は、本考案に係る建方装置(鉄骨建方装置)10の一例を示す ものである。 これらの図に示すように、建方装置10は、台車11と、建方すべきボックス 柱(鉄骨柱)12の基端部12aを支持するための支持部材13とを備えてなっ ている。 The present invention will be described below with reference to an embodiment shown in the drawings. Here, for example, a frame made of steel reinforced concrete is used with an erection unit equipped with a hoist, etc., and while raising this erection unit, the skeleton is successively constructed under this, and at the same time the box pillars that make up the skeleton are constructed. A description will be given using an embodiment in which a hoist that is fixed to the erection unit and cannot move in the horizontal direction is used for erection. 1 and 2 show an example of a erection device (steel frame erection device) 10 according to the present invention. As shown in these drawings, the erection device 10 includes a carriage 11 and a support member 13 for supporting a base end 12a of a box column (steel frame column) 12 to be erected.

【0009】 台車11は、基台14に車輪15,15,…が回転自在に取り付けられて、一 方向に進退自在な構造とされている。 図2に示すように、この台車11の基台14には、鉛直上方に延びる一対の側 板16,16が形成されている。この側板16,16には、水平方向に位置する シャフト17が固定されている。Wheels 15, 15, ... Are rotatably attached to a base 14 of the dolly 11 so that the dolly 11 can move back and forth in one direction. As shown in FIG. 2, a pair of side plates 16, 16 extending vertically upward is formed on a base 14 of the truck 11. A shaft 17 positioned in the horizontal direction is fixed to the side plates 16, 16.

【0010】 図1に示したように、前記支持部材13は、H鋼材を外観略L字状に組み立て たものであり、建方すべきボックス柱12の基端部12aの側面を支持する側部 支持面(第1の支持面)18と、基端部12aの下面を支持する下部支持面(第 2の支持面)19とを備えた構成とされている。 図2に示したように、側部支持面18の、支持すべきボックス柱12の延在す る方向に沿った両側部には、支持部材13上にボックス柱12を載置するときに これをガイドするため、図2に示した状態において、上方が開いた形状のガイド 板20,20が設けられている。 このような構造の支持部材13は、前記シャフト17に回動自在に軸支されて おり、これにより、支持部材13は、台車11上で縦回動自在な構造とされてい る。ここで、シャフト17の立設面5からの高さ寸法は、支持部材13が縦回動 したときに、支持部材13の角部13aが立設面5に接触しないように設定され ている。As shown in FIG. 1, the support member 13 is an H steel material assembled into a substantially L-shaped appearance, and is a side that supports the side surface of the base end 12 a of the box column 12 to be built. It is configured to include a partial support surface (first support surface) 18 and a lower support surface (second support surface) 19 that supports the lower surface of the base end portion 12a. As shown in FIG. 2, on both sides of the side support surface 18 along the extending direction of the box column 12 to be supported, when the box column 12 is mounted on the support member 13, 2 is provided with the guide plates 20 and 20 having an open upper shape in order to guide the sheet. The support member 13 having such a structure is rotatably supported on the shaft 17, whereby the support member 13 is vertically rotatable on the carriage 11. Here, the height dimension of the shaft 17 from the standing surface 5 is set so that the corner portion 13a of the supporting member 13 does not contact the standing surface 5 when the supporting member 13 is vertically rotated.

【0011】 次に、上記のような構成からなる建方装置10を用いて、ボックス柱12を建 方する方法について、図1ないし図6を参照して説明する。 ここで、構築すべき躯体(図示なし)は、図3に示すように、ホイスト23等 を備えた架設ユニット24を用い、この架設ユニット24をリフタ等で上昇させ つつ、この下方で順次躯体(図示なし)を構築していく。 また、ボックス柱12の建方作業は、架設ユニット24の下面の、ボックス柱 12を建方すべき所定位置に固定したホイスト23で行う。 さらに、前記建方装置10を用いてボックス柱12を建方するに際しては、図 4に示すように、横臥状態のボックス柱12の先端部12bを支持するために支 持台車25を用いる。この支持台車25は、台車26上に支持台27を備えると ともに、一方向に進退自在な構造とされている。Next, a method of erection of the box pillar 12 using the erection device 10 having the above-described configuration will be described with reference to FIGS. 1 to 6. Here, as a skeleton (not shown) to be constructed, as shown in FIG. 3, an erection unit 24 equipped with a hoist 23 and the like is used. (Not shown) will be built. Further, the erection work of the box pillar 12 is performed by the hoist 23 which is fixed to the lower surface of the erection unit 24 at a predetermined position where the box pillar 12 should be erected. Further, when the box pillar 12 is erected using the erection device 10, as shown in FIG. 4, a supporting carriage 25 is used to support the tip portion 12b of the box pillar 12 in the recumbent state. The support carriage 25 is provided with a support base 27 on a carriage 26 and has a structure capable of moving back and forth in one direction.

【0012】 まず、建方すべきボックス柱12は、立設面5の、ボックス柱12を立設すべ き所定の位置の鉛直上方に固定されたホイスト23の下方に、クレーン(図示な し)などで運び込んでおく。このときボックス柱12のブレース12cは上向き にする。 次いで、ボックス柱12を、ホイスト23のワイヤ29を玉掛けして吊り上げ た状態で、このボックス柱12の基端部12aの下方には建方装置10を配置し 、先端部12bの下方には支持台車25を配置する。 そして、ボックス柱12を降下させ、建方装置10および支持台車25上に載 置する(図3参照)。このとき、図2に示したように、建方装置10の支持部材 13にはガイド板20,20が設けられているので、ボックス柱12の基端部1 2aを容易に支持部材13上に載置することができる。また、ボックス柱12の 基端部12aは建方装置10の支持部材13の側部支持面18で支持され(図1 参照)、先端部12bは支持台車25の支持台27で支持されることになる(図 4参照)。First, the box column 12 to be erected is provided with a crane (not shown) below the hoist 23 fixed vertically above the standing surface 5 at a predetermined position where the box column 12 should be erected. Bring it in. At this time, the brace 12c of the box pillar 12 faces upward. Next, in a state in which the wire 29 of the hoist 23 is slung up to suspend the box pillar 12, the erection device 10 is arranged below the base end portion 12a of the box pillar 12 and is supported below the tip end portion 12b. A dolly 25 is arranged. Then, the box column 12 is lowered and placed on the erection device 10 and the support cart 25 (see FIG. 3). At this time, as shown in FIG. 2, since the support member 13 of the erection device 10 is provided with the guide plates 20 and 20, the base end portion 12a of the box column 12 can be easily placed on the support member 13. Can be placed. Further, the base end 12a of the box column 12 is supported by the side support surface 18 of the support member 13 of the erection device 10 (see FIG. 1), and the tip 12b is supported by the support base 27 of the support carriage 25. (See Figure 4).

【0013】 次いで、図5に示すように、立設面5上で建方装置10および支持台車25を 水平方向に移動させ、ホイスト23の略鉛直下方にボックス柱12の先端部12 bを位置させる。このとき、建方装置10,支持台車25は、それぞれ台車11 ,26を備えているので、容易に移動させることができる。Next, as shown in FIG. 5, the erection device 10 and the support carriage 25 are moved horizontally on the standing surface 5, and the tip portion 12 b of the box column 12 is positioned substantially vertically below the hoist 23. Let At this time, since the erection device 10 and the support carriage 25 are provided with the carriages 11 and 26, respectively, they can be easily moved.

【0014】 そして、ホイスト23のワイヤ29をボックス柱12の先端部12bに玉掛け し、これを鉛直上方に吊り上げる。 すると、図6に示すように、ボックス柱12の基端部12aを支持する支持部 材13がシャフト17(図1参照)を中心として縦回動しつつ、台車11がボッ クス柱12の先端部12bの位置していた方向、すなわちホイスト23の鉛直下 方に向けて引き寄せられて移動する。これにより、ボックス柱12が基端部12 aを略中心として縦回動して起立していく。 そして、ボックス柱12が鉛直に起立した時点で、ホイスト23による吊り上 げを停止させる。ボックス柱12が起立した状態においては、ボックス柱12は 、建方装置10の支持部材13の下部支持面19(図1参照)で支持されたこと になる。Then, the wire 29 of the hoist 23 is slid on the tip portion 12 b of the box column 12 and is lifted vertically upward. Then, as shown in FIG. 6, while the supporting member 13 that supports the base end portion 12a of the box column 12 vertically rotates about the shaft 17 (see FIG. 1), the carriage 11 moves toward the tip of the box column 12. The portion 12b is pulled and moved in the direction in which the portion 12b was located, that is, in the vertically downward direction of the hoist 23. As a result, the box column 12 vertically rotates about the base end portion 12 a and stands up. Then, when the box column 12 stands upright, the hoisting by the hoist 23 is stopped. In the state in which the box column 12 stands up, the box column 12 is supported by the lower support surface 19 (see FIG. 1) of the support member 13 of the erection apparatus 10.

【0015】 この後は、ホイスト23でボックス柱12をさらに上方に吊り上げて建方装置 10を取り除いてから、ボックス柱12を立設面5上に降下させ、固定その他の 作業を行うとともにワイヤ29の玉外しを行えば、所定の位置へのボックス柱1 2の建方作業が完了する。 この建方作業を、当該施工階の各ボックス柱12に対し、同様にして行う。そ して、この他図示しない梁等の施工を行った後、架設ユニット24を上昇させ、 上階の施工を上記と同様にして行い、これを繰り返すことにより、躯体(図示な し)の構築が完了する。After that, the box column 12 is further lifted up by the hoist 23 to remove the erection device 10, and then the box column 12 is lowered onto the erected surface 5 to perform fixing and other work and wire 29. If the ball is removed, the erection work of the box pillar 12 at the predetermined position is completed. This erection work is similarly performed for each box pillar 12 on the construction floor. Then, after construction of beams and the like not shown in the figure, the erection unit 24 is raised, construction of the upper floor is performed in the same manner as above, and by repeating this, construction of a frame (not shown) is performed. Is completed.

【0016】 上述したように、建方装置10では、ボックス柱12の先端部12bを鉛直上 方に吊り上げると、ボックス柱12の基端部12aを支持する支持部材13が縦 回動しつつ、台車11がボックス柱12の先端部12bの位置していた方向、す なわちホイスト23の鉛直下方に向けて移動することにより、ボックス柱12を 起立させることができる。これにより、架設ユニット24に固定されて、水平面 内で移動不可能なホイスト23によっても、ボックス柱12を建方することが可 能となる。したがって、架設ユニット24の下方でビルの躯体(図示なし)を順 次構築していく場合に、この建方装置10を適用して効率良くボックス柱12の 建方を行うことができる。 また、ボックス柱12を起立させるときに、ボックス柱12の基端部12aは 、横臥状態においては支持部材13の側部支持面18で支持され、起立した状態 においては下部支持面19で支持されている。これにより、従来のようにボック ス柱12をボルトなどで固定することなく、建方装置10の支持部材13上に載 置するのみでボックス柱12の建方作業を行うことができる。したがって、従来 の、ボックス柱12を固定するためのボルトの脱着作業を廃することができ、ま たボックス柱12にボルト穴を形成する必要がないので、建方作業の効率化,工 期の短縮化を図ることができる。 さらに、支持部材13でボックス柱12の基端部12aを支持した状態で、立 設面5に接触することなくボックス柱12を起立させるので、ボックス柱12の 基端部12aの仕口部分に傷がつくことがないのは言うまでもない。As described above, in the erection device 10, when the tip portion 12b of the box column 12 is lifted vertically upward, the support member 13 that supports the base end portion 12a of the box column 12 vertically rotates, By moving the carriage 11 in the direction in which the tip portion 12b of the box column 12 was located, that is, vertically below the hoist 23, the box column 12 can be erected. As a result, the box column 12 can be erected even by the hoist 23 that is fixed to the erection unit 24 and cannot move in the horizontal plane. Therefore, when the building frame (not shown) is sequentially constructed below the erection unit 24, the erection device 10 can be applied to efficiently construct the box pillars 12. When the box column 12 is erected, the base end 12a of the box column 12 is supported by the side support surface 18 of the support member 13 in the recumbent state, and by the lower support surface 19 in the erected state. ing. As a result, it is possible to perform the erection work of the box column 12 simply by placing it on the support member 13 of the erection apparatus 10 without fixing the box column 12 with bolts or the like as in the conventional case. Therefore, it is possible to eliminate the conventional work for attaching and detaching the bolts for fixing the box pillars 12, and since it is not necessary to form the bolt holes in the box pillars 12, the efficiency of erection work and the construction period can be improved. It can be shortened. Further, since the box pillar 12 is erected without contacting the standing surface 5 with the support member 13 supporting the base end portion 12a of the box pillar 12, the joint portion of the base end portion 12a of the box pillar 12 is It goes without saying that it is not hurt.

【0017】 なお、上記実施例において、ボックス柱12を、架設ユニット24に固定され て水平方向に移動不可能なホイスト23で建方する例を用いたが、これを水平方 向にも移動自在なホイストやクレーンなどで行うようにしてもよい。このような 場合には、例えば立設面5上の一箇所において各ボックス柱12を起立させ、起 立させた状態のままホイストやクレーンで各ボックス柱12をそれぞれ所定の位 置に移動させて建方作業を行ってもよい。このようなとき、建方装置10により 、上記実施例と同様にして、ホイストやクレーンを鉛直方向にのみ操作すればボ ックス柱12を起立させることができる。したがって、従来のようにホイストや クレーンを、ボックス柱12の先端部12bが円弧を描くように、水平方向およ び鉛直方向に同時に操作する必要がなくなり、ホイストの操作が容易になるとい う効果を奏することができる。 さらに、ボックス柱12を建方する例を用いたが、これに限るものではなく、 例えば図7および図8に示した従来例のように、柱鉄筋8を先組した柱鉄骨2を 建方する場合であっても、上記と同様の効果を得ることができる。In the above embodiment, the example in which the box column 12 is erected by the hoist 23 which is fixed to the erection unit 24 and cannot move in the horizontal direction is used, but it can be moved in the horizontal direction as well. The hoist or crane may be used. In such a case, for example, each box pillar 12 is erected at one place on the standing surface 5, and each hoist or crane is used to move each box pillar 12 to a predetermined position in the standing state. You may perform erection work. In such a case, the erection device 10 allows the box column 12 to be erected by operating the hoist or crane only in the vertical direction in the same manner as in the above embodiment. Therefore, it is not necessary to simultaneously operate the hoist and crane in the horizontal direction and the vertical direction at the same time so that the tip portion 12b of the box column 12 draws an arc, which is advantageous in that the hoist can be easily operated. Can be played. Further, although the example in which the box pillar 12 is erected is used, the invention is not limited to this. For example, as in the conventional example shown in FIG. 7 and FIG. Even in such a case, the same effect as described above can be obtained.

【0018】[0018]

【考案の効果】[Effect of device]

以上説明したように、本考案の鉄骨建方装置によれば、鉄骨柱の先端部を鉛直 上方に吊り上げると、鉄骨柱の基端部を支持する支持部材が縦回動しつつ、台車 が鉄骨柱の先端部の位置していた方向に移動することにより、鉄骨柱を起立させ ることができる。これにより、水平面内で移動不可能なホイスト等によっても、 鉄骨柱を建方することが可能となる。したがって、例えば近年開発されている架 設ユニットの下方でビルを順次構築していく方法においても、この建方装置を適 用して、効率よく鉄骨柱の建方を行うことができる。 また、鉄骨柱を起立させるときに、鉄骨柱の基端部は、横臥状態においては支 持部材の第1の支持面で支持され、起立した状態においては第2の支持面で支持 されている。これにより、鉄骨柱をボルトなどで固定することなく、支持部材上 に載置するのみで鉄骨柱の建方作業を行うことができる。したがって、従来の、 鉄骨柱を固定するためのボルトの脱着作業を廃することができ、また鉄骨柱にボ ルト穴を形成する必要がないので、建方作業の効率化,工期の短縮化を図ること ができる。 さらに、支持部材で鉄骨柱の基端部を支持した状態で、立設面に接触すること なく鉄骨柱を起立させるので、鉄骨柱の基端部の仕口部分に傷がつくことがない のは言うまでもない。 As described above, according to the steel erection device of the present invention, when the tip end of the steel frame column is lifted vertically upward, the supporting member supporting the base end part of the steel frame column is vertically rotated and the trolley is moved to the steel frame. By moving in the direction in which the tip of the column was located, the steel column can be erected. As a result, it is possible to build a steel column even with a hoist that cannot move in the horizontal plane. Therefore, for example, even in a method of sequentially building buildings under a construction unit that has been developed in recent years, the erection device can be applied to efficiently construct a steel column. Further, when the steel column is erected, the base end of the steel column is supported by the first supporting surface of the supporting member in the recumbent state, and is supported by the second supporting surface in the erected state. . As a result, it is possible to perform the erection work of the steel-framed column simply by placing it on the support member without fixing the steel-framed column with bolts or the like. Therefore, it is possible to eliminate the conventional work of removing and installing the bolts for fixing the steel column, and since it is not necessary to form a bolt hole in the steel column, the efficiency of erection work and the shortening of the construction period can be reduced. Can be planned. Further, since the steel column is erected without contacting the standing surface while the base end of the steel column is supported by the support member, the joint part at the base end of the steel column is not damaged. Needless to say.

【図面の簡単な説明】[Brief description of drawings]

【図1】本考案に係る鉄骨建方装置の一例を示す正面図
である。
FIG. 1 is a front view showing an example of a steel frame erection device according to the present invention.

【図2】同鉄骨建方装置を示す側面図である。FIG. 2 is a side view showing the steel frame erection device.

【図3】同鉄骨建方装置を適用して鉄骨柱を建方する方
法において、鉄骨柱を鉄骨建方装置上に載置した状態を
示す正面図である。
FIG. 3 is a front view showing a state in which a steel column is placed on the steel erection device in the method of erection of the steel column by applying the same steel erection device.

【図4】同鉄骨建方装置を適用して鉄骨柱を建方する際
に用いる支持台車を示す正面図である。
FIG. 4 is a front view showing a support carriage used when constructing a steel frame column by applying the steel frame constructing apparatus.

【図5】同鉄骨建方装置を適用して鉄骨柱を建方する方
法において、鉄骨柱の先端部を吊り上げる前段の状態を
示す正面図である。
FIG. 5 is a front view showing a front stage state in which a tip end portion of a steel frame column is lifted in a method of constructing a steel frame column by applying the same steel frame erection device.

【図6】同鉄骨建方装置を適用して鉄骨柱を建方する方
法において、鉄骨柱を起立させる状態を示す正面図であ
る。
FIG. 6 is a front view showing a state in which the steel frame columns are erected in the method of constructing the steel frame columns by applying the same steel frame erection device.

【図7】従来の鉄骨建方装置の一例を示す正面図であ
る。
FIG. 7 is a front view showing an example of a conventional steel frame erection device.

【図8】同鉄骨建方装置を示す側面図である。FIG. 8 is a side view showing the steel erection device.

【符号の説明】[Explanation of symbols]

5 立設面 10 建方装置(鉄骨建方装置) 11 台車 12 ボックス柱(鉄骨柱) 12a 基端部 12b 先端部 13 支持部材 18 側部支持面(第1の支持面) 19 下部支持面(第2の支持面) 5 Standing Surface 10 Standing Device (Steel Building Device) 11 Carriage 12 Box Column (Steel Column) 12a Base End 12b Tip 13 Supporting Member 18 Side Supporting Surface (First Supporting Surface) 19 Lower Supporting Surface ( Second support surface)

Claims (1)

【実用新案登録請求の範囲】[Scope of utility model registration request] 【請求項1】 鉄骨柱を地盤やスラブ等の立設面に建方
するための装置であって、少なくとも一方向に進退自在
な台車と、前記鉄骨柱の基端部を載置するため、該台車
に縦回動自在に設けられた支持部材とを備えてなり、該
支持部材は、前記鉄骨柱の基端部の側面を支持するため
の第1の支持面と、前記基端部の下面を支持するための
第2の支持面とを備えた略L字状の形状とされているこ
とを特徴とする鉄骨建方装置。
1. A device for constructing a steel column on a standing surface such as a ground or a slab, in which at least a bogie that can move forward and backward and a base end portion of the steel column are mounted. A supporting member provided on the carriage so as to be vertically rotatable. The supporting member includes a first supporting surface for supporting a side surface of the base end portion of the steel column, and the base end portion. A steel-frame erection apparatus having a substantially L-shaped configuration including a second support surface for supporting a lower surface.
JP3147593U 1993-06-11 1993-06-11 Steel frame erection equipment Pending JPH071195U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
JP3147593U JPH071195U (en) 1993-06-11 1993-06-11 Steel frame erection equipment

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
JP3147593U JPH071195U (en) 1993-06-11 1993-06-11 Steel frame erection equipment

Publications (1)

Publication Number Publication Date
JPH071195U true JPH071195U (en) 1995-01-10

Family

ID=12332296

Family Applications (1)

Application Number Title Priority Date Filing Date
JP3147593U Pending JPH071195U (en) 1993-06-11 1993-06-11 Steel frame erection equipment

Country Status (1)

Country Link
JP (1) JPH071195U (en)

Cited By (8)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPS4948254U (en) * 1972-07-31 1974-04-26
JPS49125953U (en) * 1973-02-21 1974-10-29
JPS50108054U (en) * 1974-02-13 1975-09-04
JPS5125810Y1 (en) * 1975-06-26 1976-07-01
JPH07145672A (en) * 1993-11-24 1995-06-06 Kajima Corp Device for raising up column member
JP2019085845A (en) * 2017-11-10 2019-06-06 五洋建設株式会社 Pipe pile lifting device and pipe pile lifting method
JP2021001495A (en) * 2019-06-24 2021-01-07 株式会社大林組 Long material supply system and long material installation method
JP2022001705A (en) * 2020-06-19 2022-01-06 大成建設株式会社 Column member electing device and column member erecting method

Cited By (8)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPS4948254U (en) * 1972-07-31 1974-04-26
JPS49125953U (en) * 1973-02-21 1974-10-29
JPS50108054U (en) * 1974-02-13 1975-09-04
JPS5125810Y1 (en) * 1975-06-26 1976-07-01
JPH07145672A (en) * 1993-11-24 1995-06-06 Kajima Corp Device for raising up column member
JP2019085845A (en) * 2017-11-10 2019-06-06 五洋建設株式会社 Pipe pile lifting device and pipe pile lifting method
JP2021001495A (en) * 2019-06-24 2021-01-07 株式会社大林組 Long material supply system and long material installation method
JP2022001705A (en) * 2020-06-19 2022-01-06 大成建設株式会社 Column member electing device and column member erecting method

Similar Documents

Publication Publication Date Title
JP2003328323A (en) Construction method of tower structure
JPH071195U (en) Steel frame erection equipment
JP2003026397A (en) Beam system form fitting lifter
JP3069835B2 (en) Uchigumi scaffold structure
JPH04161566A (en) Constructing apparatus for large space building
JP3141775B2 (en) Main girder rebar construction method and device for PC bridge
JPH10317661A (en) Erection scaffolding used for outer peripheral part reinforcing of existing building
JP2942879B2 (en) Temporary house for all-weather construction
JP2001088063A (en) Reinforcement joint crimping device
JPH10131496A (en) Running carriage for erecting steel framed pillar and steel framed pillar erection method
JP2524615Y2 (en) Site precast equipment
JP3781497B2 (en) How to install beams
JPH0447100B2 (en)
JPH07102524A (en) Method for building concrete cable-stayed bridge and form supporting truck using the same
JP4186144B2 (en) Temporary gantry assembly / disassembly apparatus, temporary gantry assembly / disassembly method, and temporary gantry
JPS6113059B2 (en)
JPS5918836A (en) Construction of prefabricated house
JP2004076525A (en) Temporary stage
JPH04319172A (en) Skeleton building construction workbench
JPH05321484A (en) Method for moving building and part thereof
JP2764481B2 (en) Construction machine for precast concrete members
JPS6323519Y2 (en)
JP2600443B2 (en) How to build high-rise buildings
JP3240270B2 (en) Scaffold assembling method and scaffolding device
JP2003081554A (en) Erecting method for elevator shaft

Legal Events

Date Code Title Description
A02 Decision of refusal

Free format text: JAPANESE INTERMEDIATE CODE: A02