JPH0633627B2 - New construction method on existing facility - Google Patents
New construction method on existing facilityInfo
- Publication number
- JPH0633627B2 JPH0633627B2 JP61213019A JP21301986A JPH0633627B2 JP H0633627 B2 JPH0633627 B2 JP H0633627B2 JP 61213019 A JP61213019 A JP 61213019A JP 21301986 A JP21301986 A JP 21301986A JP H0633627 B2 JPH0633627 B2 JP H0633627B2
- Authority
- JP
- Japan
- Prior art keywords
- steel
- existing facility
- beams
- truss
- existing
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Expired - Lifetime
Links
Landscapes
- Working Measures On Existing Buildindgs (AREA)
Description
【発明の詳細な説明】 [産業上の利用分野] この発明は建物などの既存施設をそのままにして、その
上に新しい建築物を造る構法に関するものである。DETAILED DESCRIPTION OF THE INVENTION [Industrial field of use] The present invention relates to a construction method for building a new building on an existing facility such as a building as it is.
[従来の技術] 通常建物の建かえは、既存の建物を撤去し、更地にして
から行っている。[Prior Art] A normal building is rebuilt after the existing building is removed and the land is reclaimed.
[発明が解決しようとする問題点] このため既存の建物を使用している場合には、新しい建
物が完成するまでの期間、他の場所に移転しなければな
らない不便さがあり、また移転や建物の使用料などに多
大な費用を要するばかりか、転移先に落着くまで営業な
どを正常に行うことができないなど多くの問題点があっ
た。[Problems to be solved by the invention] Therefore, when an existing building is used, there is an inconvenience of having to move to another place until the new building is completed. There were many problems, such as not only being extremely expensive for building usage fees, but also not being able to perform sales normally until the settlement site was reached.
このような問題を解決する手段として、既設施設の上に
架構を跨設することが特公昭61−14302号公報に
より開示されているが、この場合には、既設施設の両側
に立設した柱間に架設した桁方向の梁上にレールを設置
する一方、既設施設の側部に作業溝台の組立てを必要と
し、また作業構台にて大梁、小梁、デッキプレート、仮
受梁等をユニット化したのち、そのユニットを順次レー
ル上に送り出し、既存施設の上部全域にわたる作業床を
構築したのち、その作業床に走行クレーンを搭載して上
部鉄骨の建方を行っているため、極めて大掛かりな準備
と工事とを要する。このため規模が中小の建物などの既
存施設が密集した市街地での採用は、きわめて難しいも
のであった。As a means for solving such a problem, it is disclosed in Japanese Examined Patent Publication No. 61-14302 that a frame is laid over an existing facility. In this case, a pillar erected on both sides of the existing facility. While installing rails on beams in the girder direction installed between them, it is necessary to assemble work gutters on the side of the existing facility, and at the work gantry, girders, girders, deck plates, temporary beams, etc. are united. After that, the units are sequentially sent out onto the rails to build a work floor over the entire upper part of the existing facility, and then a traveling crane is mounted on the work floor to construct the upper steel frame, which is extremely large-scale. Requires preparation and construction. Therefore, it was extremely difficult to adopt it in urban areas where existing facilities such as small and medium-sized buildings are densely packed.
この発明は上記従来の課題を解決するために考えられた
ものであって、その目的は、既存施設の上に架設する鉄
骨梁を柱脚部とともにトラスに構成することにより、レ
ールや仮設梁などを用いることなく、従来よりも簡単に
架構の跨設ができ、また建物が比較的密集した市街地の
中小規模の既存施設に対しても適用でき、既存施設の撤
去跡えの増設も容易な新たな既存施設上の新築構法を提
供することにある。This invention was conceived in order to solve the above-mentioned conventional problems, and its purpose is to construct a rail or temporary beam by constructing a truss with a steel frame beam installed on an existing facility together with a column base. It is possible to span the frame more easily than before without using the existing structure, and it can be applied to existing small and medium-sized facilities in urban areas where the buildings are relatively dense, and it is easy to add a trace of the removal of existing facilities. To provide a new construction method over existing facilities.
[問題点を解決するための手段] 上記目的によるこの発明の特徴は、既存施設の周囲地盤
に基礎を造り、その基礎に所要高さの柱を建て、その柱
に各層分の梁を架設して既存施設上に架構を跨設するに
あたり、柱の基部から既存施設に近接した鉄骨梁に鉄骨
斜材を取付け、その鉄骨斜材と柱との間及び上記鉄骨梁
とその上層に架設した鉄骨梁との間に斜材を配設し、上
下層の鉄骨梁を柱脚部とともにトラスに構成して、1層
分の高さの大スパンのトラス梁となし、そのトラス梁に
中間柱の建込みを行うことにある。[Means for Solving Problems] The feature of the present invention based on the above object is that a foundation is built on the ground around the existing facility, a pillar of a required height is built on the foundation, and beams for each layer are erected on the pillar. When straddling the frame over the existing facility, a steel diagonal member is attached to the steel beam near the existing facility from the base of the column, and the steel frame is installed between the steel diagonal member and the column and above the steel beam and the upper layer. A diagonal member is placed between the beam and the upper and lower steel beams together with the column base to form a truss, and a truss beam with a large span of one layer is formed. It is in building.
またこの発明は、上記トラス梁の上弦材となる上層の鉄
骨梁をPC鋼材からなる型鋼により構成し、下弦材とな
る下層の鉄骨梁にPC鋼線を配設してなることを特徴と
するものでもある。Further, the present invention is characterized in that the upper-layer steel beam serving as the upper chord member of the truss beam is made of shaped steel made of PC steel, and the PC steel wire is arranged on the lower-layer steel beam serving as the lower chord member. It is also a thing.
この発明を図示の実施例により更に具体的に説明する。The present invention will be described more specifically with reference to the illustrated embodiments.
[実施例] 第1図 まず既存建物1の周辺を整理して、周囲地盤2に基礎3
を造成し、基礎3に所要高さの鉄骨柱4,4を建てる。
次に既存建物1の上方にて鉄骨梁5を鉄骨柱4,4に架
設するとともに、鉄骨柱4,4の基部から上記鉄骨梁5
に鉄骨斜材6,6を取付ける。そしてその鉄骨斜材6を
鉄骨柱4とに斜材7,7を架け渡してトラス構造の柱脚
部を構成し、柱脚部に曲げモーメントが生じないように
する。[Example] Fig. 1 First, the surroundings of the existing building 1 are arranged, and the foundation 3 is provided on the surrounding ground 2.
And the steel pillars 4 and 4 of the required height are built on the foundation 3.
Next, the steel beam 5 is erected on the steel columns 4 and 4 above the existing building 1, and the steel beams 5 are installed from the bases of the steel columns 4 and 4.
Attach the steel diagonal members 6 and 6. Then, the steel diagonal member 6 is bridged over the steel column 4 and the diagonal members 7, 7 to form a column base portion of the truss structure so that no bending moment is generated in the column base portion.
第2図 上記鉄骨梁5にはPC鋼線9が配置され、その上方にC
P鋼材からなる型鋼をもって構成された上層分の鉄骨梁
8を鉄骨柱4,4に架設する。なお上記PC鋼線9の配
置は第1図に鎖線で示すように中間の柱材を利用して弓
形にしてもよい。次に上記鉄骨梁5,8にわたり斜材1
0,10を配設した、下層分の上記鉄骨梁5が下弦材、上
層分の上記鉄骨梁8が上弦材となるトラスを構成する。Fig. 2 PC steel wire 9 is arranged on the steel beam 5, and C is provided above it.
A steel beam 8 for the upper layer, which is made of a type steel made of P steel, is installed on the steel columns 4 and 4. The PC steel wire 9 may be arranged in an arc shape by using an intermediate pillar material as shown by a chain line in FIG. Next, diagonal member 1 over the steel beams 5 and 8
A truss in which the steel beams 5 of the lower layer, in which 0 and 10 are arranged, serves as the lower chord member and the steel beams 8 of the upper layer serve as the upper chord member are configured.
第3図 上記のようにして大スパンのトラス梁を構成し、上層分
の荷重を支持できるようにしたならば、中間の鉄骨柱1
1,11を建込みながら上層分の鉄骨梁12,13を順次鉄骨
柱4,4に架設して、新しい建物の架構を既存建物1上
に跨設する。また中間の鉄骨柱11,11の建込みに際して
は、増設時における柱の接続を容易となすために柱端部
11a ,11a を梁より突出させて置く。そして図面では省
略したが、柱、梁の施工後、順次スラブ、壁版などを施
工する。Fig. 3 If a truss beam with a large span is constructed as described above and it is possible to support the load of the upper layer, the steel column in the middle 1
While building 1 and 11, steel beams 12 and 13 for the upper layers are sequentially erected on the steel columns 4 and 4, and the frame of the new building is laid over the existing building 1. In addition, when constructing the intermediate steel columns 11, 11, in order to facilitate the connection of the columns at the time of expansion, the column ends
Place 11a and 11a so that they protrude from the beam. Although not shown in the drawing, after the pillars and beams are constructed, slabs, wall slabs, etc. are sequentially constructed.
上記構法により完成された建物は、通常の建物と同様に
使用することができる。また必要に応じ上方への建増は
勿論のこと、既存建物1を撤去した跡にも下階を建増す
ることができる。このときには既存建物内諸設備を上階
に移して営業等を断続しながら行うことができる。The building completed by the above construction method can be used like a normal building. In addition, the lower floors can be added to the site where the existing building 1 has been removed, as well as the upper one if necessary. At this time, it is possible to move various facilities in the existing building to the upper floor and perform operations while intermittently operating.
既存建物跡への建増しは、まず建物1の撤去跡に基礎3
を造成する。次に第4図に示すように、鉄骨柱14,14を
建てて、上記中間の鉄骨梁11,11と接合し、更に各
層分の鉄骨梁15,16を架設して、下層の骨組を行う。ま
た鉄骨梁の施工後、順次スラブ、壁版を施工する。上記
柱及び梁の骨組が一定ブロックで終了した段階で、上記
大スパンのトラス梁の斜材及び柱の斜材等を取外し、既
存建物跡の部分のフレームを建設する場合の部材として
転用する。転用が無加工で済むように新築部分と斜材の
寸法、断面等を予め整合させて置く、整合が無理な場合
は若干の加工を施して転用する。To build an existing building, first build the foundation of the building 1 demolition site 3
To create. Next, as shown in FIG. 4, steel columns 14 and 14 are erected, joined to the intermediate steel beams 11 and 11 described above, and further steel beams 15 and 16 for each layer are erected to perform the lower-layer skeleton. . After the construction of steel beams, slabs and wall slabs will be constructed in sequence. When the skeleton of the pillars and beams is finished in a certain block, the diagonal members of the large span truss beams and the diagonal members of the columns are removed and used as members for constructing the frame of the existing building traces. The size and cross-section of the newly constructed part and the diagonal members are pre-aligned so that they can be diverted without processing. If alignment is not possible, some processing is performed before diverting.
なお、上方へ階数を増設する場合には、在来に準じて建
設を行う。If the number of floors is to be increased upwards, construction will be carried out according to conventional methods.
[発明の効果] この発明は上述のように、既存施設の上に新しい建物を
跨設してなることから、下記のごとき効果を奏する。[Effect of the Invention] As described above, the present invention has the following effects because a new building is laid over an existing facility.
○ 新築工事中でも既存施設をそのまま継続使用でき、
移転費用や建物の使用料を節減できる。○ Even during new construction work, existing facilities can be used as they are,
Relocation costs and building usage fees can be saved.
○ 既存施設の建替が後に生じたときには、既存施設を
撤去してその跡に増設を行えばよく、また先行構造物と
接続して一体化を図ることができる。○ When the existing facility is rebuilt later, the existing facility can be removed and added to the site, and it can be connected to the preceding structure for integration.
○ 増設に特別な手段を要せぬことから、更地から建築
を始める在来の建築と何ら変るところがなく、工期が特
に長くなるようなこともない。○ Since no special means is required for expansion, there is no difference from conventional construction that starts from a vacant lot, and the construction period will not be particularly long.
○ 架構の1層分をトラスとしてなるため、柱脚部のト
ラスと相俟って、既存施設上に跨設された大スパンのも
のでありながら堅牢である。-Because one layer of the frame is used as a truss, it is a large span spanning over the existing facility in combination with the truss of the column base, but it is robust.
○ トラス梁の上弦材となる上梁をPC鋼材からなる型
鋼により構成し、また下弦材となる下梁にPC鋼線を配
設したことから、大スパンのトラス梁を少ない鋼材量
で、しかも小さい梁背で構成でき、建築費の節減を図る
ことができる。○ The upper beam, which is the upper chord member of the truss beam, is composed of the shape steel made of PC steel, and the PC steel wire is arranged on the lower beam, which is the lower chord member. It can be constructed with a small beam back, which can reduce the construction cost.
図面はこの発明に係る既存施設上の新築構法を略示する
もので、第1図から第3図は工程を順に示す説明図、第
4図は既存施設跡への増設を示す説明図である。 1……既存建物、3……基 礎 4……鉄骨柱、5,8……鉄骨梁 6……鉄骨斜材、7,10……斜材 9……PC鋼材、11……中間の鉄骨柱 12,13……上層分の鉄骨梁The drawings schematically show a new construction method on an existing facility according to the present invention. FIGS. 1 to 3 are explanatory diagrams showing the steps in order, and FIG. 4 is an explanatory diagram showing expansion to the existing facility trace. . 1 …… Existing building 3 …… Foundation 4 …… Steel column, 5,8 …… Steel beam 6 …… Steel slant, 7,10 …… Staff 9 …… PC steel, 11 …… Intermediate steel frame Pillars 12, 13 ... Steel beams for the upper layers
Claims (2)
礎に所要高さの柱を建て、その柱に各層分の梁を架設し
て既存施設上に架構を跨設するにあたり、柱の基部から
既存施設に近接した鉄骨梁に鉄骨斜材を取付け、その鉄
骨斜材と柱との間及び上記鉄骨梁とその上層に架設した
鉄骨梁との間に斜材を配設し、上下層の鉄骨梁を柱脚部
とともにトラスに構成して、1層分の高さの大スパンの
トラス梁となし、そのトラス梁に中間柱の建込みを行う
ことを特徴とする既存施設上の新築構法。[Claim 1] When a foundation is built on the ground around an existing facility, a pillar of a required height is built on the foundation, a beam for each layer is erected on the pillar, and a frame of the pillar is laid on the existing facility. Steel diagonal members are attached to the steel beams near the existing facility from the base, and diagonal members are arranged between the steel diagonal members and columns, and between the steel beams and the steel beams above it, and the upper and lower layers. A new construction on an existing facility characterized by constructing a steel beam of the above together with a column base into a truss to form a large span truss beam with a height of one layer, and building an intermediate column into the truss beam. Construction method.
礎に所要高さの柱を建て、その柱に各層分の梁を架設し
て既存施設上に架構を跨設するにあたり、柱の基部から
既存施設に近接した鉄骨梁に鉄骨斜材を取付け、その鉄
骨斜材と柱との間及び上記鉄骨梁とその上層に架設した
鉄骨梁との間に斜材を配設し、上下層の鉄骨梁を柱脚部
とともにトラスに構成して、1層分の高さの大スパンの
トラス梁となし、そのトラス梁の上弦材となる上層の鉄
骨梁をPC鋼材からなる型鋼により構成し、下弦材とな
る下層の鉄骨梁にPC鋼線を配設してなることを特徴と
する既存施設上の新築構法。[Claim 2] When a foundation is built on the ground around the existing facility, a pillar of a required height is built on the foundation, and beams for each layer are erected on the pillar to bridge the frame on the existing facility. Steel diagonal members are attached to the steel beams near the existing facility from the base, and diagonal members are arranged between the steel diagonal members and columns, and between the steel beams and the steel beams above it, and the upper and lower layers. The steel beam with the column base is constructed into a truss to form a large span truss beam with a height of one layer, and the upper beam of the truss beam, which is the upper chord member of the truss beam, is made of PC steel. , A new construction method on an existing facility, characterized in that a PC steel wire is arranged on the lower-layer steel beam that serves as the lower chord member.
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
JP61213019A JPH0633627B2 (en) | 1986-09-10 | 1986-09-10 | New construction method on existing facility |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
JP61213019A JPH0633627B2 (en) | 1986-09-10 | 1986-09-10 | New construction method on existing facility |
Publications (2)
Publication Number | Publication Date |
---|---|
JPS6367349A JPS6367349A (en) | 1988-03-26 |
JPH0633627B2 true JPH0633627B2 (en) | 1994-05-02 |
Family
ID=16632157
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
JP61213019A Expired - Lifetime JPH0633627B2 (en) | 1986-09-10 | 1986-09-10 | New construction method on existing facility |
Country Status (1)
Country | Link |
---|---|
JP (1) | JPH0633627B2 (en) |
Cited By (3)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
WO2004031512A1 (en) * | 2002-10-03 | 2004-04-15 | Kabushiki Kaisha Miracle Three Corporation | Method for extending staircase type apartment house and building extended using that method |
JP2008082168A (en) * | 2007-12-21 | 2008-04-10 | Miracle Three Corporation | Method for extending existing store, and extended store obtained by the method |
JP2008082169A (en) * | 2007-12-21 | 2008-04-10 | Miracle Three Corporation | Method for extending existing store, and extended store obtained by the method |
Families Citing this family (6)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
JPH0230854A (en) * | 1988-07-18 | 1990-02-01 | Shimizu Corp | Method for reconstructing multistoried building |
JP2583462B2 (en) * | 1990-12-20 | 1997-02-19 | 株式会社フジタ | Reconstruction construction method of building in operation |
JPH05133114A (en) * | 1991-11-11 | 1993-05-28 | Takayoshi Kato | Building method of house |
JP4163539B2 (en) * | 2003-03-20 | 2008-10-08 | 株式会社ミラクルスリーコーポレーション | Seismic reinforcement extension method of building and earthquake resistance reinforcement extension building |
JP2006063699A (en) * | 2004-08-27 | 2006-03-09 | Miracle Three Corporation | Multistory parking space attached building |
JP4550534B2 (en) * | 2004-09-14 | 2010-09-22 | 森 直樹 | Building basic structure |
Family Cites Families (1)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
JPH0237442B2 (en) * | 1984-06-29 | 1990-08-24 | Kensetsu Kiso Eng | DOROKAKUFUKUKOHO |
-
1986
- 1986-09-10 JP JP61213019A patent/JPH0633627B2/en not_active Expired - Lifetime
Cited By (3)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
WO2004031512A1 (en) * | 2002-10-03 | 2004-04-15 | Kabushiki Kaisha Miracle Three Corporation | Method for extending staircase type apartment house and building extended using that method |
JP2008082168A (en) * | 2007-12-21 | 2008-04-10 | Miracle Three Corporation | Method for extending existing store, and extended store obtained by the method |
JP2008082169A (en) * | 2007-12-21 | 2008-04-10 | Miracle Three Corporation | Method for extending existing store, and extended store obtained by the method |
Also Published As
Publication number | Publication date |
---|---|
JPS6367349A (en) | 1988-03-26 |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
CN113638304B (en) | Concrete beam type bridge hidden cover beam structure system and construction method thereof | |
EA006995B1 (en) | Method and apparatus for precast and framed block element construction | |
JPH0633627B2 (en) | New construction method on existing facility | |
JPH0643686B2 (en) | Construction method of arch bridge by precast members | |
JPH10159344A (en) | Building method of multi-layered structure provided with a plurality of super beam | |
JPH07107360B2 (en) | Station construction method using multi-connection shield method | |
JPH08165662A (en) | Construction method of underground structure | |
JP2000104220A (en) | Erection of combined truss bridge | |
JPH082181Y2 (en) | Foundation for steel structures | |
JP2817591B2 (en) | Construction method of steel reinforced concrete building | |
JPH0312172B2 (en) | ||
JP2938682B2 (en) | Traveling method for multi-story buildings | |
JP2581248B2 (en) | Building construction method | |
JP3318717B2 (en) | Construction method of PC cable stayed bridge | |
JPS6363849A (en) | Structural member for pillar | |
JPH07217230A (en) | Hanging stair and erecting method thereof | |
JP2903076B2 (en) | Construction method of artificial ground in the upper space on orbit | |
JPS5811240A (en) | Constructing of multi-layered stair building | |
JPH0230854A (en) | Method for reconstructing multistoried building | |
JPH0414567A (en) | Lamination construction method of building | |
SU617516A1 (en) | Method of constructing hollow structures and structure erected by this method | |
SU1726702A1 (en) | Method of construction skeleton of a building | |
JPS61207765A (en) | Construction of building skeletal composed of reinforcement bars | |
JPH03103547A (en) | Skeleton construction method | |
JP2012117217A (en) | Construction structure of composite viaduct and construction method of composite viaduct |