JPH0633405A - Method for constructing railroad elevated bridge - Google Patents

Method for constructing railroad elevated bridge

Info

Publication number
JPH0633405A
JPH0633405A JP4212402A JP21240292A JPH0633405A JP H0633405 A JPH0633405 A JP H0633405A JP 4212402 A JP4212402 A JP 4212402A JP 21240292 A JP21240292 A JP 21240292A JP H0633405 A JPH0633405 A JP H0633405A
Authority
JP
Japan
Prior art keywords
vertical
track
fixed
rail
construction
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Granted
Application number
JP4212402A
Other languages
Japanese (ja)
Other versions
JP3028156B2 (en
Inventor
Shinichi Tamai
真一 玉井
Atsushi Nariyuki
惇 成行
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Tokyu Construction Co Ltd
Original Assignee
Tokyu Construction Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Tokyu Construction Co Ltd filed Critical Tokyu Construction Co Ltd
Priority to JP4212402A priority Critical patent/JP3028156B2/en
Publication of JPH0633405A publication Critical patent/JPH0633405A/en
Application granted granted Critical
Publication of JP3028156B2 publication Critical patent/JP3028156B2/en
Anticipated expiration legal-status Critical
Expired - Fee Related legal-status Critical Current

Links

Landscapes

  • Railway Tracks (AREA)
  • Machines For Laying And Maintaining Railways (AREA)
  • Bridges Or Land Bridges (AREA)

Abstract

PURPOSE:To carry out economical construction of an elevated bridge which reduces the number of members, shortens a term of works, and prevents noises from being produced. CONSTITUTION:In a construction method wherein a longitudinal beam 1 to which a rail or a track skeleton is fixed directly is used, bridge piers 2 are erected on both sides of a track and a cross beam 3 is fixed in a direction, in which the track is crossed, between the bridge piers 2 on both sides. The longitudinal beam 1 is fixed to the upper part of the cross beam 3 and in parallel to the track, and the periphery of the longitudinal beam 1 is surrounded with a material absorbing the noise.

Description

【発明の詳細な説明】Detailed Description of the Invention

【0001】[0001]

【産業上の利用分野】本発明は、鉄道高架橋の施工方法
に関するものである。
BACKGROUND OF THE INVENTION 1. Field of the Invention The present invention relates to a method for constructing a railway viaduct.

【0002】[0002]

【従来の技術】従来の鉄道高架橋の施工方法において
は、橋脚の上部にスラブを施工したらその上に砕石道
床、あるいはスラブ道床を搭載し、道床の上にまくらぎ
を敷設し、その上に軌条を敷設する構造であった。
2. Description of the Related Art In the conventional construction method for railway viaducts, after slabs have been constructed on the piers, crushed stone slabs or slabs are mounted on them, sleepers are laid on the slabs, and railroad tracks are laid on them. It was a structure to lay.

【0003】[0003]

【発明が解決しようとする問題点】前記した従来の鉄道
高架橋の施工方法にあっては、次のような問題点があ
る。 <イ>スラブの自重は0.6t/ m2 道床の自重は0.9t/ m
2 程度である。このように死荷重が大きいため、それを
支持する高架橋の各断面が大きくなり不経済である。 <ロ>スラブコンクリートの打設のためにはその下部型
枠を支保工で支持しなければならない。そのために特に
使用中の鉄道の上にさらにスラブを設ける場合には、支
保工の高さだけスラブを高く設置しなければならない。 <ハ>市街地を走行する高架橋では、騒音の発生は周辺
の住民の生活に大きな影響を与える。
The above-mentioned conventional method of constructing a railway viaduct has the following problems. <I>Slab's own weight is 0.6t / m 2 Roadbed's own weight is 0.9t / m
It is about 2 . Since the dead load is large in this way, each cross section of the viaduct supporting it becomes large, which is uneconomical. <B> In order to place slab concrete, the lower formwork must be supported by shoring. For this reason, especially if additional slabs are to be installed on the railroads in use, the slabs must be set higher by the height of the support work. <C> In viaducts running in urban areas, noise generation has a great impact on the lives of residents in the surrounding area.

【0004】[0004]

【本発明の目的】本発明は上記のような従来の問題を改
善するためになされたもので、部材数が少なく、短い工
期において経済的に施工することのでき、騒音の周囲へ
の伝播を防ぐことのできる鉄道高架橋の施工方法を提供
することを目的とする。
SUMMARY OF THE INVENTION The present invention has been made to solve the above-mentioned conventional problems. It has a small number of members, can be economically constructed in a short construction period, and propagates noise to the surroundings. It is an object to provide a method of constructing a railway viaduct that can be prevented.

【0005】[0005]

【問題点を解決するための手段】すなわち本発明は、軌
条または軌框を直接固定した縦粱を使用する施工方法で
あって、軌道の両側に橋脚を立設し、両側の橋脚間に、
軌道を横断する方向に横断粱を固定し、前記の縦粱を、
横断粱の上部に、軌道と平行方向に固定し、縦粱の周囲
を音を遮断する材料で包囲して行う、鉄道高架橋の施工
方法である。
[Means for Solving the Problems] That is, the present invention is a construction method using a vertical gruel directly fixing a rail or a rail, in which piers are erected on both sides of the track, and between the piers on both sides,
Fix the traverse to the direction traversing the orbit, the vertical trough,
This is a construction method for railway viaducts, which is fixed on the upper part of the crosscuts in a direction parallel to the track, and is surrounded by a material that blocks sound around the vertical cuts.

【0006】[0006]

【本発明の構成】以下図面を参照しながら本発明鉄道高
架橋の施工方法について説明する。 <イ>使用する部材 本発明の施工方法に使用する部材は、すべて工場で製造
したプレキャスト部材で構成する。したがって良好な品
質管理の下に製造された部材を使用することができる。
さらに各コンクリート部材はプレストレスを導入したも
のを使用する。したがって、小さい断面で軽量でありな
がら十分な強度を期待できる。本発明の方法に使用する
主要な部材とは、橋脚、横断粱、縦粱である。
DETAILED DESCRIPTION OF THE INVENTION The construction method of the railway viaduct of the present invention will be described below with reference to the drawings. <B> Members to be used All members used in the construction method of the present invention are precast members manufactured in a factory. Therefore, the member manufactured under good quality control can be used.
Furthermore, as each concrete member, one in which prestress is introduced is used. Therefore, it is possible to expect sufficient strength while having a small cross section and being lightweight. The main members used in the method of the present invention are bridge piers, transverse lees and vertical lees.

【0007】<ロ>縦粱 鉄道の軌道と平行方向に設置する粱を縦粱1と称する。
本発明の施工方法においては、特にこの縦粱1に軌条ま
たは軌框を一体に取り付けた構造のものを使用する。す
なわち軌条などを工場で一体に取り付けた、軌条付きプ
レストレス粱を使用することを特徴とする。軌条などが
縦粱1と一体化しているから、縦粱1の運搬、架設作業
によって、軌条を同時に運搬、架設されることになる。
さらに軌条などと縦粱1が一体化しているから、道床な
どを別に施工する必要がなく、縦粱1の架設の完了と同
時に、軌条の敷設も完了することになる。
<B> Vertical sluice A vertical sluice 1 is a sluice installed in a direction parallel to a railroad track.
In the construction method of the present invention, a structure in which a rail or a rail is integrally attached to the vertical grout 1 is used. That is, it is characterized by using prestressed grits with rails, which are integrally mounted with rails at the factory. Since the rails and the like are integrated with the vertical grove 1, the rails are simultaneously transported and erected by the transportation and erection work of the vertical gruel 1.
Further, since the railroad track and the vertical rail 1 are integrated, it is not necessary to separately construct a roadbed or the like, and at the same time the construction of the vertical rail 1 is completed, the railroad construction is completed.

【0008】[0008]

【施工方法】次に本発明の施工方法について説明する。 <イ>橋脚の立設 現在使用中の軌道の両側の地中には基礎を設置し、その
基礎の上には橋脚2を立設する。この橋脚2も工場生産
したプレストレスの部材であり、したがって現場でコン
クリートを打設して構築する方法に比較して施工はきわ
めて迅速である。
[Construction Method] Next, the construction method of the present invention will be described. <a> Standing of piers Foundations will be installed in the ground on both sides of the track currently in use, and piers 2 will be erected on the foundations. This bridge pier 2 is also a factory-produced prestressing member, and therefore construction is extremely quick compared to the method of pouring and constructing concrete on site.

【0009】<ロ>横断粱の架設 軌道の両側に立設した橋脚2の上部を連結する状態で、
横断粱3を架設する。この横断粱3は当然、橋脚2の上
端と一体に固定しなければならない。そのためには図2
に示すように交差する鉄筋を場所打ちコンクリートで固
定したり、横断粱3と橋脚2とを貫通したPC鋼材を橋
脚2の外側から緊張したり、橋脚2の上部に横断粱3を
搭載して橋脚2の上端から露出させたPC鋼材で横断粱
3を緊張したり、その他各種の固定方法を採用すること
ができる。
<B> Construction of traverses With the upper parts of the bridge piers 2 standing on both sides of the track connected,
A crossing pad 3 is installed. Naturally, the cross-cuts 3 must be fixed integrally with the upper end of the pier 2. To do that, see Figure 2.
As shown in Fig. 4, fix the intersecting rebars with cast-in-place concrete, or tension the PC steel material that penetrates the crossbridge 3 and the pier 2 from the outside of the pier 2, or install the crossover 3 on top of the pier 2. It is possible to use a PC steel material exposed from the upper end of the pier 2 for tensioning the transverse lees 3 and various other fixing methods.

【0010】<ハ>縦粱1の架設 こうして橋脚2の上端に固定した横断粱3の上部に、縦
粱1を架設して固定する。縦粱1には前記したように直
接、軌条または軌框を固定してある。したがって横断粱
3の上部に縦粱1を架設することによって、軌条の敷設
までが一体で完了する。その後に横断粱3と縦粱1とは
一体に強固に固定する。架設に際して、1本の縦粱1に
1本の軌条を固定してあるから、2本の縦粱1を横断粱
3上に平行に架設することによって1組の軌道が完成す
る。
<C> Construction of the vertical grout 1 The vertical grout 1 is erected and fixed on the upper part of the transverse grout 3 fixed to the upper end of the pier 2 in this way. A rail or rail is directly fixed to the vertical grove 1 as described above. Therefore, by laying the vertical grits 1 on the upper part of the cross grates 3, the laying of rails is completed in one. After that, the transverse gruel 3 and the vertical gruel 1 are integrally and firmly fixed. At the time of erection, since one rail is fixed to one vertical grove 1, a set of tracks is completed by erection of two vertical grates 1 on the transverse grates 3 in parallel.

【0011】<ニ>音の伝播の阻止 架設の終了した縦粱1の下面と周囲を遮音材4によって
包囲する。そのために例えば縦粱1の下面に遮音材4を
張り付ける。さらに縦粱1と縦粱1との間、縦粱1と遮
音材4との間には発泡材などの吸音材5を充填する。以
上のような構成を採用すると縦粱1の上部を走行する車
両の発生する音は、吸音材5に吸収され、さらに周囲の
遮音材4によって反射して周囲への伝播を阻止すること
ができる。
<D> Prevention of Sound Propagation A sound insulating material 4 surrounds the lower surface and the periphery of the vertical sluice 1 which has been installed. For that purpose, for example, the sound insulating material 4 is attached to the lower surface of the vertical grain 1. Further, a sound absorbing material 5 such as a foam material is filled between the vertical grout 1 and the vertical grout 1, and between the vertical grout 1 and the sound insulating material 4. When the above configuration is adopted, the sound generated by the vehicle traveling on the upper part of the vertical sill 1 is absorbed by the sound absorbing material 5 and further reflected by the surrounding sound insulating material 4 to prevent propagation to the surroundings. .

【0012】[0012]

【発明の効果】本発明の鉄道高架橋の施工方法は以上説
明したようになるから次のような効果を得ることができ
る。 <イ>縦粱1と軌条とがすでに一体となったものを使用
する。そのためにスラブの施工が不要であり、さらにス
ラブの上に搭載する多量の道床が不要となる。したがっ
て死荷重を大幅に減少することができ、その結果、地震
時の水平慣性力が小さくなるために、橋脚2断面、基礎
構造その他の構造、断面を小さくすることができ、きわ
めて経済的である。 <ロ>工場で製造した部材を使用して組み立てる方法で
ある。したがって現場で型枠を組んでコンクリートを打
設する方法に比較して部品、部材点数が少なく、工期を
大幅に短縮することができる。 <ハ>現場打ちのスラブを使用せず、軌条と固定した粱
を使用するから、スラブ型枠などを支持する支保工が不
要である。したがって使用中の鉄道の上部に施工する場
合にも支保工や型枠の高さだけ低くすることができ、経
済的な施工が可能である。 <ニ>縦粱1は独立して横断粱3との間を連結してい
る。そのために車両走行の騒音が、縦粱1間から周囲に
広く伝播してしまい市街地などでは不都合な場合があ
る。そのために本発明の方法では、縦粱1の周囲を音を
遮断する材料で包囲したものである。したがって高架橋
の周囲に車両走行の騒音が伝播しがたく、広い範囲で利
用できるものである。
The construction method of the railway viaduct according to the present invention is as described above, so that the following effects can be obtained. <B> Use the vertical sluice 1 and rail already integrated. Therefore, slab construction is unnecessary, and further, a large amount of trackbeds mounted on the slab are unnecessary. Therefore, the dead load can be greatly reduced, and as a result, the horizontal inertial force at the time of the earthquake becomes small, so that the pier 2 cross section, foundation structure and other structures and sections can be made small, which is extremely economical. . <B> It is a method of assembling using the members manufactured in the factory. Therefore, the number of parts and members is small as compared with the method of forming a concrete form and pouring concrete on site, and the construction period can be significantly shortened. <C> Since the slab cast in place is not used, but the rails and the fixed grits are used, there is no need to support the slab formwork. Therefore, even when constructing on the upper part of the railway in use, it is possible to reduce the height of the supporting work and the formwork, and economical construction is possible. <D> The vertical grain 1 is independently connected to the horizontal grain 3. For this reason, the noise of vehicle running may be widely propagated from the space between the vertical groves 1 to the surroundings, which may be inconvenient in an urban area. Therefore, in the method of the present invention, the vertical grout 1 is surrounded by a material that blocks sound. Therefore, it is difficult for vehicle running noise to propagate around the viaduct and it can be used in a wide range.

【図面の簡単な説明】[Brief description of drawings]

【図1】本発明の鉄道高架橋の施工方法の例の説明図FIG. 1 is an explanatory view of an example of a method for constructing a railway viaduct according to the present invention.

【図2】完成状態の説明図[Figure 2] Illustration of the completed state

Claims (1)

【特許請求の範囲】[Claims] 【請求項1】軌条または軌框を直接固定した縦粱を使用
する施工方法であって、 軌道の両側に橋脚を立設し、 両側の橋脚間に、軌道を横断する方向に横断粱を固定
し、 前記の縦粱を、横断粱の上部に、軌道と平行方向に固定
し、 縦粱の周囲を音を遮断、吸収する材料で包囲して行う、 鉄道高架橋の施工方法
[Claim 1] A construction method using a vertical girder directly fixing a rail or a rail, wherein bridge piers are erected on both sides of the track, and the cross grate is fixed between the piers on both sides in a direction crossing the track. However, the above-mentioned vertical gruel is fixed to the upper part of the horizontal gruel in the direction parallel to the track, and the circumference of the vertical gruel is surrounded by a material that blocks and absorbs sound.
JP4212402A 1992-07-17 1992-07-17 Construction method of railway viaduct Expired - Fee Related JP3028156B2 (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
JP4212402A JP3028156B2 (en) 1992-07-17 1992-07-17 Construction method of railway viaduct

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
JP4212402A JP3028156B2 (en) 1992-07-17 1992-07-17 Construction method of railway viaduct

Publications (2)

Publication Number Publication Date
JPH0633405A true JPH0633405A (en) 1994-02-08
JP3028156B2 JP3028156B2 (en) 2000-04-04

Family

ID=16621996

Family Applications (1)

Application Number Title Priority Date Filing Date
JP4212402A Expired - Fee Related JP3028156B2 (en) 1992-07-17 1992-07-17 Construction method of railway viaduct

Country Status (1)

Country Link
JP (1) JP3028156B2 (en)

Cited By (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN105755957A (en) * 2016-03-01 2016-07-13 共享钢构有限责任公司 Rapid hoisting method for large-span pedestrian overcrossing striding over rail
CN106592438A (en) * 2016-12-27 2017-04-26 中铁六局集团有限公司 Two-column pier and middle tie beam construction method employing integral movement of trusses
JP2020012306A (en) * 2018-07-18 2020-01-23 公益財団法人鉄道総合技術研究所 Noise reduction device for bridge
JP2020204254A (en) * 2018-07-18 2020-12-24 公益財団法人鉄道総合技術研究所 Viaduct and noise reduction device

Cited By (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN105755957A (en) * 2016-03-01 2016-07-13 共享钢构有限责任公司 Rapid hoisting method for large-span pedestrian overcrossing striding over rail
CN106592438A (en) * 2016-12-27 2017-04-26 中铁六局集团有限公司 Two-column pier and middle tie beam construction method employing integral movement of trusses
JP2020012306A (en) * 2018-07-18 2020-01-23 公益財団法人鉄道総合技術研究所 Noise reduction device for bridge
JP2020204254A (en) * 2018-07-18 2020-12-24 公益財団法人鉄道総合技術研究所 Viaduct and noise reduction device

Also Published As

Publication number Publication date
JP3028156B2 (en) 2000-04-04

Similar Documents

Publication Publication Date Title
JP7121179B2 (en) System and method for construction of composite U-shaped reinforced girder bridge deck
US4905896A (en) Railroad roadway for high speed rail-mounted vehicles
Bastin Development of German non-ballasted track forms
JPH0633405A (en) Method for constructing railroad elevated bridge
JPH02120401A (en) Parmanent way with compound structure
JP4162291B2 (en) Railway work girder cradle and rail work girder cradle construction method
JP3460572B2 (en) Substructure of road viaduct
KR100613862B1 (en) Light weight pc-steelgirder bridge construction
JPH0633406A (en) Structure for longitudunal beam for railroad elevated bridge
CN211571239U (en) Temporary covering structure for subway station construction
JP4080652B2 (en) Railway viaduct girder
JPH0633404A (en) Method for constructing railroad elevated bridge
JPH0633408A (en) Structure for longitudinal beam for railroad elevated bridge
JP2000064222A (en) Elevated bridge
CN110439027B (en) Structure for controlling influence of subway operation vibration and noise on upper cover property and construction method thereof
EP0504753A2 (en) Railroad viaduct structure
CN203583343U (en) Support type frame bridge
JP3788774B2 (en) Railroad track structure and railroad track construction method
JP3307867B2 (en) Track support girder elevated track structure
JPH0633407A (en) Method for constructing railroad elevated bridge
CN220685751U (en) Prefabricated integral bridge deck railway simply supported T beam structure with sound barrier
JP3881342B2 (en) Bubble mortar embankment structure
JP3967953B2 (en) Construction method of steel solid ramen viaduct
US2028741A (en) Bridge construction
KR102670768B1 (en) Steel composite ramen bridge reinforced with section steel supports and crossing rebars and its construction method

Legal Events

Date Code Title Description
R250 Receipt of annual fees

Free format text: JAPANESE INTERMEDIATE CODE: R250

R250 Receipt of annual fees

Free format text: JAPANESE INTERMEDIATE CODE: R250

R250 Receipt of annual fees

Free format text: JAPANESE INTERMEDIATE CODE: R250

FPAY Renewal fee payment (event date is renewal date of database)

Free format text: PAYMENT UNTIL: 20090204

Year of fee payment: 9

FPAY Renewal fee payment (event date is renewal date of database)

Free format text: PAYMENT UNTIL: 20100204

Year of fee payment: 10

FPAY Renewal fee payment (event date is renewal date of database)

Free format text: PAYMENT UNTIL: 20110204

Year of fee payment: 11

FPAY Renewal fee payment (event date is renewal date of database)

Free format text: PAYMENT UNTIL: 20110204

Year of fee payment: 11

FPAY Renewal fee payment (event date is renewal date of database)

Free format text: PAYMENT UNTIL: 20120204

Year of fee payment: 12

LAPS Cancellation because of no payment of annual fees