JPH0629234Y2 - Barrier air for filling material in pipe laying work - Google Patents

Barrier air for filling material in pipe laying work

Info

Publication number
JPH0629234Y2
JPH0629234Y2 JP1987011269U JP1126987U JPH0629234Y2 JP H0629234 Y2 JPH0629234 Y2 JP H0629234Y2 JP 1987011269 U JP1987011269 U JP 1987011269U JP 1126987 U JP1126987 U JP 1126987U JP H0629234 Y2 JPH0629234 Y2 JP H0629234Y2
Authority
JP
Japan
Prior art keywords
air chamber
bag body
filling material
tunnel
bag
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Expired - Lifetime
Application number
JP1987011269U
Other languages
Japanese (ja)
Other versions
JPS63121653U (en
Inventor
秀昌 栗島
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Toyo Tire Corp
Original Assignee
Toyo Tire and Rubber Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Toyo Tire and Rubber Co Ltd filed Critical Toyo Tire and Rubber Co Ltd
Priority to JP1987011269U priority Critical patent/JPH0629234Y2/en
Publication of JPS63121653U publication Critical patent/JPS63121653U/ja
Application granted granted Critical
Publication of JPH0629234Y2 publication Critical patent/JPH0629234Y2/en
Anticipated expiration legal-status Critical
Expired - Lifetime legal-status Critical Current

Links

Classifications

    • YGENERAL TAGGING OF NEW TECHNOLOGICAL DEVELOPMENTS; GENERAL TAGGING OF CROSS-SECTIONAL TECHNOLOGIES SPANNING OVER SEVERAL SECTIONS OF THE IPC; TECHNICAL SUBJECTS COVERED BY FORMER USPC CROSS-REFERENCE ART COLLECTIONS [XRACs] AND DIGESTS
    • Y02TECHNOLOGIES OR APPLICATIONS FOR MITIGATION OR ADAPTATION AGAINST CLIMATE CHANGE
    • Y02EREDUCTION OF GREENHOUSE GAS [GHG] EMISSIONS, RELATED TO ENERGY GENERATION, TRANSMISSION OR DISTRIBUTION
    • Y02E10/00Energy generation through renewable energy sources
    • Y02E10/20Hydro energy

Landscapes

  • Pipe Accessories (AREA)

Description

【考案の詳細な説明】 [産業上の利用分野] 本考案は管敷設工事において、管或いはトンネル内に更
に本管を配設して後に、管又はトンネルと本管の間の空
間をスパン毎に充填材を注入する際に堰板として使用す
る堰止エアーバッグに関するものである。
[Detailed Description of the Invention] [Industrial field of application] In the pipe laying work, the present invention further arranges a main pipe in a pipe or a tunnel, and thereafter, a space between the pipe or the tunnel and the main pipe is spanned. The present invention relates to a damming air bag used as a dam plate when injecting a filling material into.

[従来技術] 従来管敷設工事において、管或いはトンネル内に本管を
固定させる際に、管或いはトンネルと本管の間の空間を
スパン毎に堰板を設けて充填材を注入しているが、この
堰板には、一般に木材から形成したものが使用されてい
る。
[Prior Art] In the conventional pipe laying work, when fixing the main pipe in the pipe or the tunnel, a weir plate is provided for each span in the space between the pipe or the tunnel and the main pipe to inject the filler. As the weir plate, one made of wood is generally used.

[考案が解決するための問題点] しかしながら、この種従来木材から成る堰板は製作に長
時間を要し、しかも破損しやすいことや一枚の使用回数
が3〜4回程度とその寿命も極めて短かいために、工事
距離が長い場合にはそれに応じた膨大な数の堰板を作成
用意しなければならない上に、コンクリートが付着する
ために使用毎に付着コンクリートの剥離作業をしなけれ
ばならず、堰板の設置作業はきわめて繁雑で多くの時間
を必要とする等の欠点があった。
[Problems to be solved by the invention] However, a dam plate made of this kind of conventional wood takes a long time to manufacture and is easily damaged, and the life of the dam plate is about 3 to 4 times. Since it is extremely short, if the construction distance is long, it is necessary to prepare and prepare a huge number of weir plates corresponding to it, and since concrete adheres, it is necessary to remove the adhered concrete after each use. However, there is a drawback in that the installation work of the weir plate is extremely complicated and requires a lot of time.

[問題点を解決するための手段] 以下図面によって本考案実施の一例を説明すると、第1
図乃至第3図に示すように、バッグ本体1は可撓性を有
する気密材から所定厚さを備えた膨脹気室体として形成
され、注排気栓2を有し、気室3には前壁4から背壁5
へ貫通する筒部6を備えせしめることにより構成する。
[Means for Solving Problems] An example of implementing the present invention will be described below with reference to the drawings.
As shown in FIG. 3 to FIG. 3, the bag body 1 is formed as an expanded air chamber body having a predetermined thickness from a flexible airtight material, has an injection / exhaust plug 2, and the air chamber 3 has a front portion. Wall 4 to back wall 5
It is configured by providing a cylindrical portion 6 penetrating to the.

[作用] 本考案は上記のような構成であるから、バッグ本体1は
可撓性を有する気密材から所定厚さを有する膨脹気室体
に形成される堰止エアーバッグとして提供され、第4図
に示すように、トンネル7内に更に本管8を配設して後
に、トンネル7と本管8の間の空間をスパン毎に充填材
を注入する場合に、気室3の筒部6に本管7を挿着させ
て気室3に注気するだけでバッグ本体1の設置を可能と
すると共にバッグ本体1は気質3内の空気圧を十分に確
保することにより確実な堰止め効果を得ることができ、
そして、所定の作業を終了した後、即ち、トンネル7内
の1スパンにおける充填材の注入を終了した後は気室3
を排気することによりバッグ本体1を容易に外すことが
でき、バッグ本体1の設置作業およびその他の取扱いも
極めて容易簡単に行なうことができる。
[Operation] Since the present invention is configured as described above, the bag body 1 is provided as a damming air bag formed from a flexible airtight material into an inflated air chamber body having a predetermined thickness. As shown in the drawing, when the main pipe 8 is further arranged in the tunnel 7 and then the filler is injected into the space between the tunnel 7 and the main pipe 8 for each span, the tubular portion 6 of the air chamber 3 The main body 7 can be installed by simply inserting the main tube 7 into the air chamber 3 and injecting air into the air chamber 3, and the bag main body 1 ensures a sufficient blocking effect by sufficiently securing the air pressure in the temperament 3. Can get
Then, after completing the predetermined work, that is, after injecting the filler in one span in the tunnel 7, the air chamber 3
The bag body 1 can be easily removed by evacuating, and the installation work and other handling of the bag body 1 can be performed very easily and easily.

[実施例] 第5図乃至第7図は本考案の第一実施例を示すもので、
バッグ本体1は可撓性を有する気密シート材から所定の
厚みを有する盤状に膨脹する膨脹気室体として形成さ
れ、このバッグ本体1は、断面形状において、上辺9及
び底辺10が水平な割円として形成され、隔壁11を介して
上部気室12と下部気質13に仕切られ、前記下部気室13に
は前壁4から背壁5へ貫通する筒部6を備えせしめると
共に上下の各気室12,13にはそれぞれ個々の注排気栓2a,
2bを有して形成する。
[Embodiment] FIGS. 5 to 7 show a first embodiment of the present invention.
The bag body 1 is formed from a flexible airtight sheet material as an expanded air chamber body that expands in a disk shape having a predetermined thickness. The bag body 1 has a cross-sectional shape in which an upper side 9 and a bottom side 10 are horizontal. It is formed as a circle and is divided into an upper air chamber 12 and a lower air quality 13 through a partition wall 11. The lower air chamber 13 is provided with a cylindrical portion 6 penetrating from the front wall 4 to the back wall 5 and the upper and lower air chambers. Each of the chambers 12 and 13 has an individual injection / exhaust plug 2a,
Formed with 2b.

また、14はバッグ本体1の前壁部4および背壁部5の筒
部6の外周部分に複数個設置された握手を示す。
Reference numeral 14 denotes a handshake provided on the front wall portion 4 and the back wall portion 5 of the bag body 1 on the outer peripheral portions of the tubular portion 6.

次に作用を説明すると、第8図に示すように、トンネル
7内に更に本管8を配設して後に、トンネル7と本管8
の間の空間をスパン毎に充填材を注入する場合に、バッ
グ本体1は排気した状態で、トンネル7に延長配設され
た本管8の端部にバッグ本体1の筒部6を挿着する。そ
して下部気室13を注気して膨張させる。この状態におい
て、バッグ本体1は底辺10と左右側面とがトンネル7の
底部に打設された水平な床板15及び左右の円弧面に密接
して下部気室13を隔壁11によって規制される高さ位置ま
で膨張し、上部気室12は収縮した排気状態になってい
る。そして前記隔壁11は筒部6の頂端から所定高さ位
置、即ち、トンネル7の天端16で作業員が自由に出入り
することができる空間を確保し得る高さ位置にある。そ
こで、作業員は隔壁11の上から自由に出入りして、バッ
グ本体1の設定位置を正したり、充填材の気泡抜き作業
をすることができる。
Next, the operation will be described. As shown in FIG. 8, after the main pipe 8 is further arranged in the tunnel 7, the tunnel 7 and the main pipe 8 are
When the filler is injected into the space between the spans, the bag body 1 is evacuated, and the tubular portion 6 of the bag body 1 is attached to the end of the main pipe 8 extended in the tunnel 7. To do. Then, the lower air chamber 13 is injected and expanded. In this state, the bottom 10 of the bag body 1 and the left and right side surfaces are in close contact with the horizontal floor plate 15 and the left and right circular arc surfaces that are placed at the bottom of the tunnel 7, and the height in which the lower air chamber 13 is regulated by the partition wall 11 The upper air chamber 12 is expanded to the position and the upper air chamber 12 is in a contracted exhaust state. The partition wall 11 is located at a predetermined height from the top end of the tubular portion 6, that is, at a top end 16 of the tunnel 7 where a space for workers to freely enter and exit can be secured. Therefore, the worker can freely move in and out from above the partition wall 11 to correct the set position of the bag body 1 and to perform the air bubble removal work of the filling material.

充填材が隔壁11の高さまで充填された際に、上部気室12
を注氣膨脹させると、この上部気室12の上辺9とトンネ
ル7の天端16の間に僅かな間隙を残して隔壁11から上方
を塞ぐ。そこで、上方気室12の上辺9のトンネル7の天
端16の間隙から充填材注入ホース(図示せず)をバッグ
本体1の内側のトンネル7の中へ押し込んで、トンネル
7の上部の未充填の箇所に充填材を充填し、バッグ本体
1で堰き止められたトンネル7の全体に充填材が注入充
填される。
When the filling material is filled to the height of the partition wall 11, the upper air chamber 12
Is inflated, the upper side of the upper air chamber 12 and the top end 16 of the tunnel 7 are left with a slight gap left to close the partition 11 from above. Then, a filling material injection hose (not shown) is pushed into the tunnel 7 inside the bag body 1 from the gap between the top end 16 of the tunnel 7 on the upper side 9 of the upper air chamber 12 to unfill the upper portion of the tunnel 7. The filling material is filled in the above position, and the filling material is injected and filled into the entire tunnel 7 blocked by the bag body 1.

このように、バッグ本体1を下部気室13と上部気室12の
2段階で膨脹させることにより、トンネル7の中への充
填材の充填作業を容易にすると共にトンネルの中に充填
した充填材がバッグ本体1で堰き止められて充填材がバ
ッグ本体1の外側へ漏出することが阻止される。
In this way, by expanding the bag body 1 in two stages of the lower air chamber 13 and the upper air chamber 12, the filling work into the tunnel 7 is facilitated and the filling material filled into the tunnel is filled. Is blocked by the bag body 1 to prevent the filler from leaking to the outside of the bag body 1.

1スパンにおける充填材の注入が終了した後、上下気室
12,13を排気収縮すれば、バッグ本体1は本管8から容
易に外すことができる。
After the injection of the filler in one span is completed, the upper and lower air chambers
The bag body 1 can be easily detached from the main pipe 8 by exhausting and contracting 12 and 13.

そして、次ぎのスパンにおける充填材の注入のために使
用することができ、1個のバッグ本体1で約90回の繰り
返し使用が可能である。
Then, it can be used for injecting the filler in the next span, and one bag body 1 can be repeatedly used about 90 times.

尚第11図は本考案の第二実施例を示すもので、トンネル
1内に2本の本管を敷設する場合の使用に供し、バッグ
本体1の下部気室13には、敷設される本管の数に対応し
て2本の筒部6a,6bを備えせしめて形成したものであ
る。
FIG. 11 shows a second embodiment of the present invention, which is used for laying two main pipes in the tunnel 1 and is laid in the lower air chamber 13 of the bag body 1. Two tubular portions 6a and 6b are provided and formed corresponding to the number of tubes.

[考案の効果] 従って、本考案は可撓性を有する気密材から所定厚さを
有する膨脹気質体に形成された堰止エアーバッグを提供
し、気室の筒部に本管を挿着させて気室に注気をするだ
けで堰板の設置を可能とすると共に充填材の注入を終了
した後は気室を排気することによりバッグ本体を容易に
外すことができ、堰止エアーバッグの設置作業およびそ
の他の取扱いも極めて容易簡単であり、また、一枚の寿
命が極めて長く、それ故に、工事距離が長い場合は工期
も著しく短縮することができる等の利点がある。
[Effects of the Invention] Accordingly, the present invention provides a dampening air bag formed from a flexible airtight material into an inflatable body having a predetermined thickness, and inserting the main tube into the tubular portion of the air chamber. It is possible to install the weir plate just by injecting air into the air chamber, and after the injection of the filling material is completed, the bag body can be easily removed by exhausting the air chamber. Installation work and other handling are extremely easy and easy, and the life of one piece is extremely long. Therefore, the construction period can be remarkably shortened when the construction distance is long.

【図面の簡単な説明】[Brief description of drawings]

図は本考案に係るもので、第1図はバッグ本体の斜視
図、第2図はその縦断正面図、第3図は縦断側面図、第
4図はバッグ本体を本管に設置して示す断面図、第5図
は本考案の第一実施例のバッグ本体の正面図、第6図は
その縦断正面図、第7図はその縦断側面図、第8図は1
スパンの充填材の注入において、バッグ本体を設置して
示す使用状態図、第9図は上部膨脹気室を排気した状態
で本管に設置して示す正面図、第10図はその要部縦断面
図である。第11図は本考案の第二実施例を示すバッグ本
体の正面図である。 1…バッグ本体、2…注排気栓 3…気室、4…前壁、5…背壁 6…筒部、9…上辺、10…底辺 11…隔壁、12…上部気室、13…下部気室
1 is a perspective view of a bag main body, FIG. 2 is a vertical sectional front view thereof, FIG. 3 is a vertical sectional side view thereof, and FIG. 4 shows the bag main body installed on a main pipe. FIG. 5 is a sectional view, FIG. 5 is a front view of the bag body of the first embodiment of the present invention, FIG. 6 is a vertical sectional front view thereof, FIG. 7 is a vertical sectional side view thereof, and FIG.
When injecting the filler for the span, a state of use shown with the bag body installed, FIG. 9 is a front view showing the main pipe installed with the upper expansion chamber exhausted, and FIG. 10 is a longitudinal section of the main part It is a side view. FIG. 11 is a front view of the bag body showing the second embodiment of the present invention. 1 ... Bag body, 2 ... injection / exhaust plug 3 ... air chamber, 4 ... front wall, 5 ... back wall 6 ... cylindrical part, 9 ... top side, 10 ... bottom side 11 ... division wall, 12 ... upper air chamber, 13 ... lower air Room

Claims (1)

【実用新案登録請求の範囲】[Scope of utility model registration request] 【請求項1】バッグ本体は可撓性を有する気密材から所
定厚さを備えた膨脹気室体として形成され、断面形状に
おいて、上辺及び底辺が水平な割円として形成し、隔壁
を介して上部気室と下部気室に仕切られ、下部気室には
前壁から背壁へ貫通する少なくとも1個の筒部を備えせ
しめると共に上下の各気室にはそれぞれ注排気栓を有し
て構成した管敷設工事における充填材の堰止エアーバッ
グ。
1. A bag body is formed as an expanded air chamber body having a predetermined thickness from a flexible airtight material, and in the cross-sectional shape, the top side and the bottom side are formed as horizontal split circles, and through a partition wall. It is divided into an upper air chamber and a lower air chamber, and the lower air chamber is provided with at least one tube portion that penetrates from the front wall to the back wall, and the upper and lower air chambers are each provided with an injection / exhaust plug. An air bag for filling material in the pipe laying work.
JP1987011269U 1987-01-28 1987-01-28 Barrier air for filling material in pipe laying work Expired - Lifetime JPH0629234Y2 (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
JP1987011269U JPH0629234Y2 (en) 1987-01-28 1987-01-28 Barrier air for filling material in pipe laying work

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
JP1987011269U JPH0629234Y2 (en) 1987-01-28 1987-01-28 Barrier air for filling material in pipe laying work

Publications (2)

Publication Number Publication Date
JPS63121653U JPS63121653U (en) 1988-08-08
JPH0629234Y2 true JPH0629234Y2 (en) 1994-08-10

Family

ID=30798329

Family Applications (1)

Application Number Title Priority Date Filing Date
JP1987011269U Expired - Lifetime JPH0629234Y2 (en) 1987-01-28 1987-01-28 Barrier air for filling material in pipe laying work

Country Status (1)

Country Link
JP (1) JPH0629234Y2 (en)

Family Cites Families (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPS616543U (en) * 1984-06-19 1986-01-16 丸誠重工業株式会社 Filler water stop device in PIP method

Also Published As

Publication number Publication date
JPS63121653U (en) 1988-08-08

Similar Documents

Publication Publication Date Title
JPH0629234Y2 (en) Barrier air for filling material in pipe laying work
NL7506068A (en) DOUBLE-WALL FACADE CONSTRUCTION PART FOR BUILDINGS WITH A PRESSURE VENTILATION OR CLIMATION EQUIPMENT.
JP2001520340A5 (en)
JPH10131690A (en) Tunnel sheet spreading construction method and tunnel sheet
KR20230041535A (en) Backflow prevention packer system of grouting apparatus
US1177311A (en) Tile and fastener for sewers, aqueducts, or like conduits.
JPS629381Y2 (en)
JP2832285B2 (en) Open shield method
JPH10259697A (en) Concrete board piece, tunnel lining body, and manufacture of concrete board piece
JP2812106B2 (en) Precast wall end groove forming method
JP3735825B2 (en) Reinforcing bar erection method and erection device
JPH0638957Y2 (en) Fume pipe joint structure for propulsion
JPH10259696A (en) Continuous lining excavation method
JP3092907B2 (en) Tunnel lining method and tunnel lining form device
JPH02164918A (en) Deformation preventing method for sheathing wall in sheathing
JPH0269796U (en)
US528342A (en) Ernest leslie ransome
JPS5843536B2 (en) The best way to get started
SU850843A1 (en) Method of erecting a monolithic structure with channel
JPH0342111Y2 (en)
JPH06137090A (en) Tunnel primary lining method
JPH0348320Y2 (en)
JP2023003791A (en) Chemical injection method
JPH05239989A (en) Shield machine starting device
JP3100239B2 (en) Grout injection method and injection apparatus