Remote monitor equipment

Info

Publication number
JPH06237495A
JPH06237495A JP5022879A JP2287993A JPH06237495A JP H06237495 A JPH06237495 A JP H06237495A JP 5022879 A JP5022879 A JP 5022879A JP 2287993 A JP2287993 A JP 2287993A JP H06237495 A JPH06237495 A JP H06237495A
Authority
JP
Japan
Prior art keywords
monitoring device
simulated
report
equipment
informing
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
JP5022879A
Other languages
Japanese (ja)
Inventor
Ryoichi Ito
良一 井藤
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Mitsubishi Electric Building Solutions Corp
Original Assignee
Mitsubishi Electric Building Techno Service Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Mitsubishi Electric Building Techno Service Co Ltd filed Critical Mitsubishi Electric Building Techno Service Co Ltd
Priority to JP5022879A priority Critical patent/JPH06237495A/en
Publication of JPH06237495A publication Critical patent/JPH06237495A/en
Pending legal-status Critical Current

Links

Classifications

    • YGENERAL TAGGING OF NEW TECHNOLOGICAL DEVELOPMENTS; GENERAL TAGGING OF CROSS-SECTIONAL TECHNOLOGIES SPANNING OVER SEVERAL SECTIONS OF THE IPC; TECHNICAL SUBJECTS COVERED BY FORMER USPC CROSS-REFERENCE ART COLLECTIONS [XRACs] AND DIGESTS
    • Y02TECHNOLOGIES OR APPLICATIONS FOR MITIGATION OR ADAPTATION AGAINST CLIMATE CHANGE
    • Y02EREDUCTION OF GREENHOUSE GAS [GHG] EMISSIONS, RELATED TO ENERGY GENERATION, TRANSMISSION OR DISTRIBUTION
    • Y02E60/00Enabling technologies; Technologies with a potential or indirect contribution to GHG emissions mitigation

Landscapes

  • Arrangements For Transmission Of Measured Signals (AREA)
  • Remote Monitoring And Control Of Power-Distribution Networks (AREA)
  • Selective Calling Equipment (AREA)

Abstract

PURPOSE:To obtain the remote monitor equipment able to confirm a communication path between a monitor equipment and a center equipment without routine time informing. CONSTITUTION:When no informing operation is executed within an optional time for example, 23 hours from a final informing operation of a monitor equipment 2, a simulating informing operation section 2h makes simulating informing to a center equipment 3. Then the simulating informing result is stored in the monitor equipment 2. Succeedingly when no informing reception is present within an orbitrary time such as 24 hours from the reception of final informing of the center equipment 3, a polling operation section 3 collects the result of simulating informing to the monitor equipment 2 and when the collected simulating time informing result is inferior a communication path fault is informed from the center equipment 3.

Description

【発明の詳細な説明】Detailed Description of the Invention

【0001】[0001]

【産業上の利用分野】この発明は、監視装置により検出
される設備異常を外部に設けられたセンター装置へ発報
する遠隔監視装置に関する。
BACKGROUND OF THE INVENTION 1. Field of the Invention The present invention relates to a remote monitoring device for reporting a facility abnormality detected by a monitoring device to a center device provided outside.

【0002】[0002]

【従来の技術】従来、この種の遠隔監視装置において、
監視装置とセンター装置間の通信経路を確認するものと
して、監視装置からセンター装置へ例えば毎日定期的に
発報する定時発報がある。
2. Description of the Related Art Conventionally, in this type of remote monitoring device,
As a means for confirming the communication path between the monitoring device and the center device, there is a periodical alarm that is periodically issued from the monitoring device to the center device.

【0003】このような遠隔監視装置では、センター装
置が毎日定期的に定時発報を受信することにより、監視
装置の発報動作確認や、監視装置とセンター装置との間
の通信回線状態の確認、センター装置への発報に必要な
監視装置側に設定される電話番号などのデータ確認等の
通信経路の正常確認ができる。
In such a remote monitoring device, the center device receives a regular timed alert every day to check the alerting operation of the monitoring device and the state of the communication line between the monitoring device and the center device. , It is possible to confirm the normality of the communication path such as confirmation of data such as a telephone number set on the monitoring device side necessary for issuing a report to the center device.

【0004】[0004]

【発明が解決しようとする課題】しかしながら、上述し
たような従来の遠隔監視装置では、通信経路の正常確認
はできても、監視装置側では定時発報に要する通信料金
の負担があると共に、センター装置側の受信処理負荷は
定時発報と設備異常発報が半々であり、定時発報受信に
より本来重要な設備異常発報の受信処理能力を圧迫する
という問題点があった。
However, in the conventional remote monitoring device as described above, although the communication route can be normally confirmed, the monitoring device side is burdened with the communication charge required for the periodical notification, and The reception processing load on the device side is half and half, and there is a problem that the reception processing capability of the originally important equipment abnormality notification is compressed by the reception of the timely notification.

【0005】この発明は、かかる問題点を解消するもの
であり、定時発報によらないで通信経路の確認ができる
遠隔監視装置を得ることを目的とする。
The present invention solves such a problem, and an object of the present invention is to obtain a remote monitoring device capable of confirming a communication path without relying on a periodical alarm.

【0006】[0006]

【課題を解決するための手段】この発明の請求項1に係
る遠隔監視装置は、設備異常時に発報動作する監視装置
と、この監視装置からの発報を受信するセンター装置と
を備えた遠隔監視装置において、上記監視装置に、最終
発報動作から所定時間内に発報動作がないときに模擬発
報動作する模擬発報動作部を備えると共に、上記センタ
ー装置に、上記監視装置との通信経路確認のための模擬
発報を受信する模擬発報受信部を備えたことを特徴とす
るものである。
A remote monitoring device according to claim 1 of the present invention is a remote monitoring device comprising a monitoring device for issuing an alarm when an equipment abnormality occurs, and a center device for receiving an alarm from this monitoring device. In the monitoring device, the monitoring device includes a simulated reporting operation unit that performs a simulated reporting operation when there is no reporting operation within a predetermined time from the final reporting operation, and the center device communicates with the monitoring device. It is characterized by including a simulated report receiving unit for receiving a simulated report for route confirmation.

【0007】また、請求項2に係る遠隔監視装置は、設
備異常時に発報動作する監視装置と、この監視装置から
の発報を受信するセンター装置とを備えた遠隔監視装置
において、上記センター装置に、最終発報受信から所定
時間経過したときに上記監視装置にポーリング動作して
模擬発報結果を収集するためのポーリング動作部を備え
ると共に、上記監視装置に、上記センター装置からのポ
ーリング時に模擬発報結果をセンター装置に伝えるため
のポーリング受信部を備えたことを特徴とするものであ
る。
A remote monitoring device according to a second aspect of the present invention is a remote monitoring device including a monitoring device that issues an alarm when a facility abnormality occurs, and a center device that receives an alert from the monitoring device. In addition, a polling operation unit for polling the monitoring device to collect a simulated reporting result when a predetermined time has elapsed from the reception of the final report is provided, and the monitoring device is simulated when polling from the center device. It is characterized in that it is provided with a polling reception unit for transmitting the report result to the center device.

【0008】[0008]

【作用】この発明の請求項1に係る遠隔監視装置におい
て、監視装置に備えられた模擬発報動作部は、最終発報
動作から所定時間内に発報動作がないときに模擬発報動
作し、センター装置に備えられた模擬発報受信部は、上
記模擬発報を受信して、監視装置との通信経路の確認が
行われて、模擬発報結果が上記監視装置に記憶される。
In the remote monitoring device according to the first aspect of the present invention, the simulated alarm operation unit provided in the monitoring device performs the simulated alarm operation when there is no alarm operation within a predetermined time from the final alarm operation. The simulated report receiving unit provided in the center device receives the simulated report, confirms the communication path with the monitoring device, and stores the simulated report result in the monitoring device.

【0009】また、請求項2に係る遠隔監視装置におい
ては、センター装置に備えられたポーリング動作部は、
最終発報受信から所定時間経過したときに監視装置にポ
ーリング動作し、監視装置に備えられたポーリング受信
部は、上記センター装置からのポーリング時に模擬発報
結果をセンター装置に伝える。そのため、上記センター
装置には、模擬発報結果が収集され、その結果がよくな
ければ、通信経路の異常を報知することができる。
Further, in the remote monitoring device according to the second aspect, the polling operation unit provided in the center device is
When a predetermined time has elapsed since the last notification was received, the monitoring device performs a polling operation, and the polling reception unit provided in the monitoring device notifies the center device of the simulated notification result at the time of polling from the center device. Therefore, the above-mentioned center device collects the simulated report result, and if the result is not good, it can notify the abnormality of the communication path.

【0010】[0010]

【実施例】【Example】

実施例1.図1〜図4はこの発明の一実施例を示す図で
ある。図1は遠隔監視装置の概念的構成図で、図中、1
は監視装置2に異常監視される設備、2は設備1の異常
信号をセンター装置3に発報するプログラムや模擬発報
するプログラム等を有する監視装置、3は監視装置2か
らの発報を受信処理するプログラムや模擬発報結果を収
集するプログラム等を有するセンター装置で、上記監視
装置2に通信経路を介して外部に設けられている。
Example 1. 1 to 4 are views showing an embodiment of the present invention. FIG. 1 is a conceptual configuration diagram of a remote monitoring device.
Is a facility whose abnormality is monitored by the monitoring device 2, 2 is a monitoring device having a program for issuing an abnormal signal of the facility 1 to the center device 3, a program for issuing a simulated signal, and 3 is a device for receiving an alert from the monitoring device 2. A center device having a program for processing, a program for collecting simulated report results, etc., and is provided outside the monitoring device 2 via a communication path.

【0011】ここで、上記監視装置2は、図2に示すよ
うに、I/Oポート2aと、処理データ及び入力データ
等を一時記憶するRAM2b、CPU2c、設備1の異
常信号をセンター装置3に発報するプログラムや模擬発
報するプログラム及び固定データ等を記憶するROM2
dが設けられたコンピュータ2eと、設備1の異常を監
視する設備異常発報成立部2fと、設備異常発報成立部
2fで成立した内容をセンター装置3に発報する設備異
常発報動作部2gと、プログラム演算結果による模擬発
報をセンター装置3に発報する模擬発報動作部2hと、
センター装置3の模擬発報結果収集に対するポーリング
受信部2iによって形成されている。
As shown in FIG. 2, the monitoring device 2 sends to the center device 3 an I / O port 2a, a RAM 2b for temporarily storing processing data and input data, a CPU 2c, and an abnormal signal of the equipment 1. ROM2 for storing programs to issue reports, programs to issue simulated reports, fixed data, etc.
The computer 2e provided with d, the equipment abnormality report establishment unit 2f that monitors the equipment 1 for abnormality, and the equipment abnormality report operation unit that reports the content established by the equipment abnormality report formation unit 2f to the center apparatus 3. 2g, and a simulated reporting operation unit 2h that reports a simulated report based on the result of the program calculation to the center device 3.
It is formed by the polling reception unit 2i for collecting the simulated report results of the center device 3.

【0012】また、上記センター装置3は、I/Oポー
ト3aと、処理データ及び入力データ等を一時記憶する
RAM3b、CPU3c、監視装置2からの発報を受信
処理するプログラムや模擬発報結果を収集するプログラ
ム及び固定データ等を記憶するROM3dが設けられた
コンピュータ3eと、監視装置2からの設備異常発報を
受信する設備異常発報受信部3fと、監視装置2からの
模擬発報を受信する模擬発報受信部3gと、監視装置2
に対して模擬発報結果を収集するためのポーリング動作
部3hと、ポーリング結果を報知する結果報知部3iに
よって形成されている。
The center device 3 also stores an I / O port 3a, a RAM 3b for temporarily storing processing data and input data, a CPU 3c, a program for receiving a report from the monitoring device 2, and a simulated report result. A computer 3e provided with a ROM 3d for storing programs and fixed data to be collected, an equipment abnormality report receiving section 3f for receiving an equipment abnormality report from the monitoring apparatus 2, and a simulated report from the monitoring apparatus 2 Simulated report receiving unit 3g and monitoring device 2
A polling operation unit 3h for collecting the simulated report result and a result notification unit 3i for notifying the polling result.

【0013】上記のように構成された遠隔監視装置の監
視動作を図3に示すフローチャートによって説明する。
すなわち、ステップ101において、設備異常発報成立
部2fで設備1の設備異常が成立しなければステップ1
02へ進み、ステップ102において、監視装置2の稼
動開始または最終発報動作から任意時間、例えば23時
間経過していればステップ103へ進む。
The monitoring operation of the remote monitoring device configured as described above will be described with reference to the flowchart shown in FIG.
That is, in step 101, if the equipment abnormality of the equipment 1 is not established in the equipment abnormality report establishment unit 2f, step 1
In step 102, if an arbitrary time, for example, 23 hours has elapsed from the start of the operation of the monitoring device 2 or the final notification operation in step 102, the process proceeds to step 103.

【0014】ステップ103では、模擬発報動作部2h
が模擬発報受信部3gに対して模擬発報が行われる。な
お、ステップ101において、設備異常発報成立部2f
で設備1の設備異常が成立すればステップ107へ進
み、ステップ107では、設備異常発報動作部2gから
設備異常発報受信部3fに対して設備異常発報が行われ
る。
In step 103, the simulated alarm operation unit 2h
A simulated report is issued to the simulated report receiving unit 3g. In step 101, the equipment abnormality report establishment unit 2f
If the equipment abnormality of the equipment 1 is established in step 107, the process proceeds to step 107. In step 107, the equipment abnormality reporting operation unit 2g issues a facility abnormality notification to the equipment abnormality reporting receiving unit 3f.

【0015】次に、ステップ104において、模擬発報
受信部3gへの呼出音または話中音の応答を検出すれば
ステップ105へ進み、ステップ105では、成功が記
憶される。また、ステップ104において、模擬発報受
信部3gへの呼出音または話中音の応答を検出しなけれ
ばステップ106へ進み、ステップ106では失敗が記
憶される。
Next, in step 104, if the response of the ringing tone or the busy tone to the simulated alarm receiving unit 3g is detected, the process proceeds to step 105, and in step 105, the success is stored. Further, in step 104, if the response of the ringing tone or the busy tone to the simulated alarm reception unit 3g is not detected, the process proceeds to step 106, and the failure is stored in step 106.

【0016】したがって、上記実施例1によれば、監視
装置2に最終発報動作から所定時間内に発報動作がない
ときに模擬発報動作する模擬発報動作部2hと、センタ
ー装置3からのポーリングを受信するポーリング受信部
とを備えると共に、上記センター装置3に、上記監視装
置2との通信経路確認のための模擬発報を受信する模擬
発報受信部3gと、ポーリング動作部3hとを備えたの
で、定時発報によらなくても通信経路の確認ができるこ
とになる。
Therefore, according to the above-described first embodiment, the monitoring device 2 has a simulated reporting operation unit 2h for performing a simulated reporting operation when there is no reporting operation within a predetermined time from the final reporting operation, and from the center device 3. And a polling operation unit 3h, which includes a polling receiving unit for receiving the polling of the monitoring device 2. Since it is equipped with, it is possible to confirm the communication route without relying on the scheduled notification.

【0017】実施例2.次に、実施例2について説明す
る。この実施例2においては、上述した実施例1の動作
に加えて後述するようにして動作する。上記実施例1の
動作に続いて、遠隔監視装置のセンター装置3は、図4
に示すフローチャートにしたがって動作する。すなわ
ち、ステップ201において、設備異常発報受信部3f
で設備異常発報を受信しなければステップ202へ進
み、ステップ202において、センター装置3の稼動開
始または最終発報受信から任意時間、例えば24時間経
過していればステップ203へ進む。ステップ203で
は、ポーリング動作部3hがポーリング受信部2iに対
して模擬発報結果の収集を行う。この時、監視装置2に
設定されている設備異常発報受信部3fの電話番号デー
タも収集される。
Example 2. Next, a second embodiment will be described. In the second embodiment, in addition to the operation of the first embodiment described above, the operation is performed as described later. Subsequent to the operation of the first embodiment, the center device 3 of the remote monitoring device operates as shown in FIG.
It operates according to the flowchart shown in. That is, in step 201, the equipment abnormality report receiving unit 3f
If the equipment abnormality report is not received at step 202, the process proceeds to step 202, and at step 202, if an arbitrary time, for example, 24 hours has elapsed since the start of the operation of the center device 3 or the last report reception, the process proceeds to step 203. In step 203, the polling operation unit 3h collects the simulated report results for the polling reception unit 2i. At this time, the telephone number data of the equipment abnormality report receiving unit 3f set in the monitoring device 2 is also collected.

【0018】次に、ステップ204において、収集した
模擬発報結果が成功でなければステップ205へ進み、
ステップ205では、結果報知部3iより通信経路異常
が報知される。
Next, at step 204, if the collected simulated report result is not successful, the routine proceeds to step 205,
In step 205, the result notification unit 3i reports a communication path abnormality.

【0019】要するに、上記実施例2においては、実施
例1において、監視装置2の最終発報動作から任意時
間、例えば23時間経過、すなわち、23時間内に発報
動作が無ければセンター装置3に対して模擬発報が行わ
れ、次に、模擬発報結果が監視装置2に記憶されるのに
対し、続いて、センター装置3の最終発報受信から任意
時間、例えば24時間経過、すなわち、24時間内に発
報受信が無ければ監視装置2に対して模擬発報結果の収
集が行われ、次に、収集した模擬発報結果がよくなけれ
ばセンター装置より通信経路の異常が報知される。
In summary, in the second embodiment, in the first embodiment, the center device 3 is notified if an arbitrary time, for example, 23 hours has elapsed from the last alarming operation of the monitoring device 2, that is, if there is no alarming operation within 23 hours. A simulated report is issued to the monitoring device 2 while the simulated report result is stored in the monitoring device 2. Then, an arbitrary time, for example, 24 hours has elapsed from the last report reception of the center device 3, that is, If no report is received within 24 hours, a simulated report result is collected for the monitoring device 2. Next, if the collected simulated report result is not good, the center device reports an abnormality in the communication path. .

【0020】したがって、上記実施例2によれば、模擬
発報結果の収集に基づいてセンター装置より通信経路の
異常をも検知できるという効果がある。
Therefore, according to the second embodiment, it is possible to detect an abnormality in the communication path from the center device based on the collection of the simulated report results.

【0021】[0021]

【発明の効果】以上のように、この発明の請求項1によ
れば、監視装置に、最終発報動作から所定時間内に発報
動作がないときに模擬発報動作する模擬発報動作部を備
えると共に、センター装置に、上記監視装置との通信経
路確認のための模擬発報を受信する模擬発報受信部を備
えることにより、監視装置との通信経路を確認すること
ができ、センター装置の定時発報による受信負荷がなく
なり、本来重要な設備異常の発報受信処理に運用できる
という効果がある。
As described above, according to the first aspect of the present invention, the simulated alarm operation unit for performing the simulated alarm operation in the monitoring device when the alarm operation is not performed within the predetermined time from the final alarm operation. And the center device is provided with a simulated report receiving unit for receiving a simulated report for confirming the communication route with the monitoring device, so that the communication route with the monitoring device can be confirmed. There is an effect that the reception load due to the scheduled notification of is removed, and the system can be used for the notification reception processing of the originally important equipment abnormality.

【0022】また、請求項2によれば、センター装置
に、最終発報受信から所定時間経過したときに上記監視
装置にポーリング動作して模擬発報結果を収集するため
のポーリング動作部を備えると共に、監視装置に、上記
センター装置からのポーリング時に模擬発報結果をセン
ター装置に伝えるためのポーリング受信部を備え、ポー
リング時に模擬発報結果をセンター装置に伝えるように
したので、センター装置には、模擬発報結果が収集さ
れ、その結果に基づいて通信経路の異常を報知すること
ができる。
According to a second aspect of the present invention, the center device is provided with a polling operation unit for performing a polling operation on the monitoring device when a predetermined time has elapsed from the last notification reception and collecting the simulated notification result. Since the monitoring device is provided with a polling receiving unit for transmitting the simulated report result to the center device at the time of polling from the center device, and the simulated report result is transmitted to the center device at the time of polling, the center device has The simulated report result is collected, and the abnormality of the communication path can be notified based on the result.

【図面の簡単な説明】[Brief description of drawings]

【図1】この発明の一実施例を概念的に示す全体概念図
である。
FIG. 1 is an overall conceptual diagram conceptually showing an embodiment of the present invention.

【図2】図1の監視装置2とセンター装置3の内部構成
を示す概念回路図である。
FIG. 2 is a conceptual circuit diagram showing an internal configuration of a monitoring device 2 and a center device 3 of FIG.

【図3】図1の監視装置2の動作を説明したフローチャ
ートである。
FIG. 3 is a flowchart illustrating an operation of the monitoring device 2 of FIG.

【図4】図1のセンター装置3の動作を説明したフロー
チャートである。
FIG. 4 is a flowchart illustrating an operation of the center device 3 of FIG.

【符号の説明】[Explanation of symbols]

1 設備 2 監視装置 2e コンピュータ 2f 設備異常発報成立部 2g 設備異常発報動作部 2h 模擬発報動作部 2i ポーリング受信部 3 センター装置 3e コンピュータ 3f 設備異常発報受信部 3g 模擬発報受信部 3h ポーリング受信部 3i 結果報知部 1 Equipment 2 Monitoring Device 2e Computer 2f Equipment Abnormality Report Established Section 2g Equipment Abnormality Report Operation Section 2h Simulated Report Operation Section 2i Polling Reception Section 3 Center Equipment 3e Computer 3f Equipment Abnormality Report Reception Section 3g Simulated Report Reception Section 3h Polling receiver 3i Result notifier

─────────────────────────────────────────────────────
─────────────────────────────────────────────────── ───

【手続補正書】[Procedure amendment]

【提出日】平成5年4月13日[Submission date] April 13, 1993

【手続補正1】[Procedure Amendment 1]

【補正対象書類名】図面[Document name to be corrected] Drawing

【補正対象項目名】図4[Name of item to be corrected] Fig. 4

【補正方法】変更[Correction method] Change

【補正内容】[Correction content]

【図4】 [Figure 4]

Claims (2)

【特許請求の範囲】[Claims] 【請求項1】 設備異常時に発報動作する監視装置と、
この監視装置からの発報を受信するセンター装置とを備
えた遠隔監視装置において、上記監視装置に、最終発報
動作から所定時間内に発報動作がないときに模擬発報動
作する模擬発報動作部を備えると共に、上記センター装
置に、上記監視装置との通信経路確認のための模擬発報
を受信する模擬発報受信部を備えたことを特徴とする遠
隔監視装置。
1. A monitoring device for issuing an alarm when equipment is abnormal,
In a remote monitoring device including a center device that receives a report from the monitoring device, the monitoring device performs a simulated reporting operation in which a simulated reporting operation is performed when the reporting operation is not performed within a predetermined time from the final reporting operation. A remote monitoring device comprising an operating unit, and the center device including a simulated report receiving unit for receiving a simulated report for confirming a communication path with the monitoring device.
【請求項2】 設備異常時に発報動作する監視装置と、
この監視装置からの発報を受信するセンター装置とを備
えた遠隔監視装置において、上記センター装置に、最終
発報受信から所定時間経過したときに上記監視装置にポ
ーリング動作して模擬発報結果を収集するためのポーリ
ング動作部を備えると共に、上記監視装置に、上記セン
ター装置からのポーリング時に模擬発報結果をセンター
装置に伝えるためのポーリング受信部を備えたことを特
徴とする遠隔監視装置。
2. A monitoring device for issuing an alarm when equipment is abnormal,
In a remote monitoring device including a center device that receives a report from the monitoring device, the center device polls the monitoring device when a predetermined time has elapsed from the last report reception, and displays a simulated report result. A remote monitoring device comprising a polling operation unit for collecting and a polling receiving unit for transmitting a simulated report result to the center device when the monitoring device polls from the center device.
JP5022879A 1993-02-10 1993-02-10 Remote monitor equipment Pending JPH06237495A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
JP5022879A JPH06237495A (en) 1993-02-10 1993-02-10 Remote monitor equipment

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
JP5022879A JPH06237495A (en) 1993-02-10 1993-02-10 Remote monitor equipment

Publications (1)

Publication Number Publication Date
JPH06237495A true JPH06237495A (en) 1994-08-23

Family

ID=12094984

Family Applications (1)

Application Number Title Priority Date Filing Date
JP5022879A Pending JPH06237495A (en) 1993-02-10 1993-02-10 Remote monitor equipment

Country Status (1)

Country Link
JP (1) JPH06237495A (en)

Cited By (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
US4827094A (en) * 1987-07-02 1989-05-02 Fuji Koki Manufacturing Co., Ltd. Dual-action pressure switch apparatus
JP2009245109A (en) * 2008-03-31 2009-10-22 Tokyo Electric Power Co Inc:The Equipment-monitoring system using radio communication and measuring instrument using the same
JP4814475B2 (en) * 2000-05-31 2011-11-16 アークレイ株式会社 Remote data management system and measurement data collection method
CN106571689A (en) * 2016-11-23 2017-04-19 国网福建省电力有限公司 Online monitoring system for diagnosing substation telemetering fault based on multi-data source comparison technology

Cited By (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
US4827094A (en) * 1987-07-02 1989-05-02 Fuji Koki Manufacturing Co., Ltd. Dual-action pressure switch apparatus
JP4814475B2 (en) * 2000-05-31 2011-11-16 アークレイ株式会社 Remote data management system and measurement data collection method
JP2009245109A (en) * 2008-03-31 2009-10-22 Tokyo Electric Power Co Inc:The Equipment-monitoring system using radio communication and measuring instrument using the same
CN106571689A (en) * 2016-11-23 2017-04-19 国网福建省电力有限公司 Online monitoring system for diagnosing substation telemetering fault based on multi-data source comparison technology
CN106571689B (en) * 2016-11-23 2024-02-02 国网福建省电力有限公司 Multi-data-source comparison technology diagnosis substation telemetry fault online monitoring system

Similar Documents

Publication Publication Date Title
CN1121384A (en) Event correlation
JPH06237495A (en) Remote monitor equipment
JP2003206081A (en) Aseismic remote monitoring system of elevator
JPH10326109A (en) Pump yard remote monitoring system
JP2001006079A (en) Method and device for supporting mechanical security
JP3373666B2 (en) Wireless security system
JP2002323997A (en) System, method and program for monitoring fault history
JP3025573B2 (en) Building remote monitoring device
JP2007013928A (en) Remote fault monitoring apparatus and remote fault monitoring method
JPH09130877A (en) Equipment fault informing device
JP2011030094A (en) Radio communication system for traveling body and failure processing method of the same
JP3195250B2 (en) Remote monitoring device
JP2002169706A (en) Monitor system
JP2003015735A (en) Plant monitoring and reporting device
JPH10304469A (en) Result collection device and its method
JP3316624B2 (en) Monitoring terminal controller for monitoring and alarm system
JP2000076570A (en) Video alarm display device and video alarm display method
JPH0830887A (en) Emergency reporting device
JP2950965B2 (en) Remote monitoring device
KR19980066622A (en) Remote system failure management device and method using radio pager
JPH11167405A (en) Operation management/monitoring device
JPH1056450A (en) Communication monitor equipment
JPH08242305A (en) Automatic informing system
JP2001202583A (en) Remote monitoring system for gas supply pressure