JPH06219665A - Guide rail hang-up device for elevator - Google Patents

Guide rail hang-up device for elevator

Info

Publication number
JPH06219665A
JPH06219665A JP1032293A JP1032293A JPH06219665A JP H06219665 A JPH06219665 A JP H06219665A JP 1032293 A JP1032293 A JP 1032293A JP 1032293 A JP1032293 A JP 1032293A JP H06219665 A JPH06219665 A JP H06219665A
Authority
JP
Japan
Prior art keywords
guide rail
rail
elevator
hang
lifting
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Granted
Application number
JP1032293A
Other languages
Japanese (ja)
Other versions
JP2748812B2 (en
Inventor
Takashi Natsume
隆 夏目
Yoshito Tsukahara
義人 塚原
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Mitsubishi Electric Corp
Original Assignee
Mitsubishi Electric Corp
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Mitsubishi Electric Corp filed Critical Mitsubishi Electric Corp
Priority to JP5010322A priority Critical patent/JP2748812B2/en
Publication of JPH06219665A publication Critical patent/JPH06219665A/en
Application granted granted Critical
Publication of JP2748812B2 publication Critical patent/JP2748812B2/en
Anticipated expiration legal-status Critical
Expired - Lifetime legal-status Critical Current

Links

Classifications

    • BPERFORMING OPERATIONS; TRANSPORTING
    • B66HOISTING; LIFTING; HAULING
    • B66BELEVATORS; ESCALATORS OR MOVING WALKWAYS
    • B66B19/00Mining-hoist operation
    • B66B19/002Mining-hoist operation installing or exchanging guide rails

Landscapes

  • Load-Engaging Elements For Cranes (AREA)
  • Lift-Guide Devices, And Elevator Ropes And Cables (AREA)

Abstract

PURPOSE:To provide a guide rail hang-up device which can secure the rail hang margin in whichever structure an elevator pit, be removed from any altitude of scaffolding, hang the rail with no use of special hang-up device, be constructed light and compact, and which allows the process preparatory works and the removing work in a short period of time. CONSTITUTION:Pinching tools 8c, 8d on which a hang plate 8b having a hang hole for hanging up is installed projectingly, are fastened using a fastening tool 8e to the desired place arranged in the longitudinal direction of a guide rail for elevator in T-form.

Description

【発明の詳細な説明】Detailed Description of the Invention

【0001】[0001]

【産業上の利用分野】この発明は、エレベーターの据付
工事に付帯するエレベーター用のガイドレール吊上げ装
置に関するものである。
BACKGROUND OF THE INVENTION 1. Field of the Invention The present invention relates to a guide rail lifting device for an elevator, which is incidental to elevator installation work.

【0002】[0002]

【従来の技術】図7は例えば実開昭61−11676号
公報に示された従来のエレベーター用のガイドレール吊
上げ装置に関するものである。図において、(21)はエレ
ベーターの昇降路、(22)は昇降路(21)の上部に設けられ
た機械室、(23)はエレベーターかごを案内するレール
で、一般に5mの長さを有している。(23a)はレール(2
3)の直立部、(23b)は同じく基板部である。(24)は昇降
路(21)内に敷設されるレール(23)を接続するための目板
で、ボルト(B)により予めレール(23)に固定されてい
る。
2. Description of the Related Art FIG. 7 relates to a conventional guide rail hoisting device for an elevator shown in Japanese Utility Model Laid-Open No. 61-11676. In the figure, (21) is an elevator hoistway, (22) is a machine room provided above the hoistway (21), (23) is a rail for guiding an elevator car, and generally has a length of 5 m. ing. (23a) is rail (2
The upright part of (3), (23b) is also the substrate part. Reference numeral (24) is an eye plate for connecting rails (23) laid in the hoistway (21), and is fixed to the rails (23) in advance by bolts (B).

【0003】(25)は昇降路(21)の下部側壁に形成したレ
ール搬入用の開口部、(26)は開口部(25)に対応して床面
上に設置されたレール(23)を搬入するためのウインチで
あって、このウインチ(26)に巻回されている吊りロープ
(27)の引出端側は、昇降路(21)の下部に取付けた案内車
(28a)および機械室(22)内に配設した案内車(28b)(28c)
に順次巻掛けられて、昇降路(21)の上部から垂下され、
シャックル(29)が連結されている。(30)は昇降路(21)内
の下部側壁に設けられた足場である。(31)はレール吊具
で、レールの断面より稍々大きい断面の空間が2片の金
具をボルト結合することによって形成されている。
Reference numeral (25) is an opening for carrying in rails formed on the lower side wall of the hoistway (21), and (26) is a rail (23) installed on the floor corresponding to the opening (25). A winch for carrying in, the hanging rope wound around this winch (26)
The leading end side of (27) is a guide car installed at the bottom of the hoistway (21).
(28a) and guide cars (28b) and (28c) installed in the machine room (22)
It is sequentially wound around, and hung from the upper part of the hoistway (21),
The shackle (29) is connected. (30) is a scaffold provided on the lower side wall in the hoistway (21). Reference numeral (31) is a rail suspension, and a space having a cross section slightly larger than the cross section of the rail is formed by bolting two pieces of metal fittings together.

【0004】上記構成のレール吊具を用いてレール(23)
の昇降路(21)への搬入を行う場合は、まず、レール(23)
を挟んで吊具(31)の2片をボルトで結合し、ウインチ(2
6)を操作して吊りロープ(27)を巻き取り、吊具(31)がボ
ルト(B)で固定された目板(24)に当接するまでスライド
させる。このとき、吊具(31)は目板(24)に掛止し、これ
以上スライドしない。さらに吊りロープ(27)を巻き取っ
てレール(23)を吊り上げ、足場(30)の上にいる作業者が
誘導して昇降路(21)内に搬入する。
[0004] The rail (23) using the rail suspension of the above configuration
When loading into the hoistway (21), first set the rail (23).
The two pieces of the hanger (31) are connected with a bolt with the
6) Operate the suspension rope (27) by winding it up, and slide it until the suspension tool (31) comes into contact with the eye plate (24) fixed with the bolt (B). At this time, the suspending tool (31) is hooked on the eye plate (24) and does not slide any further. Further, the suspension rope (27) is wound up and the rail (23) is suspended, and the worker on the scaffold (30) guides it and carries it into the hoistway (21).

【0005】[0005]

【発明が解決しようとする課題】従来のレール吊上げ装
置は、以上のように構成されていて吊具を目板に当接す
るまでスライドさせるので、機械室が昇降路の直上にな
い構造、若しくは昇降路天井上に吊ることができるスペ
ースがない昇降路構造では、最上部連結レールの上端で
吊ると吊代がなく、また、その1段下のレールとの連結
用目板では作業足場から適正な姿勢で取外せなくなるお
それがあった。
Since the conventional rail hoisting device is constructed as described above and the hoisting tool is slid until it abuts on the eye plate, the machine room is not directly above the hoistway, or the hoisting and lowering device is not lifted. In a hoistway structure where there is no space to hang it on the road ceiling, there is no hanging allowance if it is hung at the upper end of the uppermost connecting rail, and if it is a connecting board with the rail one step below it, it is appropriate from the work scaffolding. There was a risk that it could not be removed due to posture.

【0006】この発明は上記問題を解決するためになさ
れたもので、機械室が昇降路直上にない、若しくは、昇
降路天井上に吊ることができるスペースがないエレベー
ター昇降路構造であっても、レール吊代が確保できると
共に、どの高さの作業足場からでも取外しができ、コン
パクト且つ軽量であって、段取り、取外しを短時間でな
しうる装置を提供することを目的とする。
The present invention has been made to solve the above problems, and even if the machine room is not directly above the hoistway, or even if there is no elevator hoistway structure that can be hung on the hoistway ceiling, It is an object of the present invention to provide a device that can secure a rail suspension allowance, can be removed from a work scaffold of any height, is compact and lightweight, and can perform setup and removal in a short time.

【0007】[0007]

【課題を解決するための手段】請求項1の発明に係るエ
レベーター用のガイドレール吊上げ装置は、吊上げ用の
吊孔を有する吊板を突設した挟持金具を、締結具を用い
てT字形のエレベーター用のガイドレールの長手方向の
所望の位置に締付け固定するようにしたことを主要な構
成としている。
According to a first aspect of the invention, there is provided a guide rail hoisting device for an elevator according to the first aspect of the present invention, wherein a holding metal fitting having a hanging plate having a hoisting hole for hoisting is formed into a T-shape by using a fastener. The main structure is that the guide rails for an elevator are fastened and fixed at desired positions in the longitudinal direction.

【0008】請求項2の発明に係るエレベーター用のガ
イドレール吊上げ装置は、基板部と直立部とからなるT
字形のエレベーター用のガイドレールにおいて、上記基
板部の適宜の位置に1つ以上の吊上げ用の吊孔を設けた
ことを主要な構成としている。
A guide rail hoisting device for an elevator according to a second aspect of the present invention is a T-shaped device including a substrate portion and an upright portion.
The main configuration of the letter-shaped elevator guide rail is to provide one or more hoisting holes for hoisting at appropriate positions on the substrate portion.

【0009】請求項3の発明に係るエレベーター用のガ
イドレール吊上げ装置は、基板部と直立部とからなるT
字形のエレベーター用のガイドレールにおいて、上記基
板部の所望の位置に1つ以上のメネジ孔を設け、吊上げ
用のアイボルトを所望の上記メネジ孔に螺合させるよう
にしたことを主要な構成としている。
According to a third aspect of the invention, there is provided a guide rail hoisting device for an elevator, which comprises a base portion and an upright portion.
In a character-shaped elevator guide rail, one or more female screw holes are provided at desired positions of the board portion, and a lifting eyebolt is screwed into the desired female screw hole. .

【0010】[0010]

【作用】請求項1の発明に係るエレベーター用のガイド
レール吊上げ装置は、挟持金具をボルトナット等の締結
具を用いて、T字形のエレベーター用のガイドレールの
長手方向に沿った所望の位置に締付け固定し、挟持金具
より突設した吊板の吊孔に吊上げ装置としてのシャック
ルを通し、吊りロープにより吊上げるものである。
In the elevator guide rail lifting device according to the first aspect of the present invention, the clamping metal fitting is attached to a desired position along the longitudinal direction of the T-shaped elevator guide rail by using fasteners such as bolts and nuts. A shackle as a hoisting device is passed through a hoisting hole of a hoisting plate that is fixed by tightening and protrudes from a sandwiching metal fitting, and hoisted by a hoisting rope.

【0011】請求項2の発明に係るエレベーター用のガ
イドレール吊上げ装置は、T字形のエレベーター用のガ
イドレールの基板部に設けた1つ以上の吊孔のいずれか
に吊上げ装置としてのシャックルを通し、吊りロープに
より吊上げるものである。
According to a second aspect of the present invention, there is provided an elevator guide rail hoisting device, wherein a shackle as a hoisting device is passed through one or more hoisting holes provided in a base plate portion of a T-shaped elevator guide rail. , It is lifted by a hanging rope.

【0012】請求項3の発明に係るエレベーター用のガ
イドレール吊上げ装置は、T字形のエレベーター用のガ
イドレールの基板部に設けた1つ以上のメネジ孔のいず
れかに吊上げ用のアイボルトを螺合させ、揚重ロープ先
端の吊りフックを引掛け吊り上げるものである。
According to a third aspect of the present invention, there is provided an elevator guide rail hoisting device, wherein an eyebolt for hoisting is screwed into any one or more female screw holes provided in the base plate portion of the T-shaped elevator guide rail. Then, the hanging hook at the end of the lifting rope is hooked and lifted.

【0013】[0013]

【実施例】【Example】

実施例1.以下、この発明の一実施例を図について説明
する。図1において、(1)は昇降路、(1a)は昇降路(1)の
下部に設けられたピット、(2)はピット(1a)面に置かれ
たジャッキベース、(3)はジャッキベース(2)と係合し昇
降路(1)の全長にわたり井桁状に単管パイプをクランプ
により組立てた作業足場、(1b)は最下階乗場床、(4)は
この最下階乗場床にアンカーを用いて固定された揚重ウ
インチ、(5)はこの揚重ウインチ(4)に巻取られる揚重ロ
ープ、(6a)(6b)(6c)はこの揚重ロープ(5)を案内する滑
車である。
Example 1. An embodiment of the present invention will be described below with reference to the drawings. In FIG. 1, (1) is a hoistway, (1a) is a pit provided at the bottom of the hoistway (1), (2) is a jack base placed on the pit (1a) surface, and (3) is a jack base. A work scaffold that engages with (2) and assembles single pipes with clamps over the entire length of the hoistway (1) by clamps, (1b) is the lowest floor landing floor, and (4) is this lowest floor landing floor. Lifting winch fixed with an anchor, (5) is a lifting rope wound around this lifting winch (4), (6a) (6b) (6c) guides this lifting rope (5) It is a pulley.

【0014】(7)は昇降路(1)の全長にわたり連結された
ガイドレール、(7a)はガイドレール(7)の最上部連結レ
ール、(8)はこの最上部連結レール(7a)の上端と下端と
の中間に位置するガイドレール吊上げ装置で、最上部連
結レール(7a)の上端と次のレールとのレールジョイント
部(7b)との間の作業足場(3)から取外し可能な所望の位
置に挟着固定できる。
(7) is a guide rail connected over the entire length of the hoistway (1), (7a) is the uppermost connecting rail of the guide rail (7), and (8) is the upper end of this uppermost connecting rail (7a). A guide rail hoisting device located between the upper and lower ends of the uppermost connecting rail (7a) and the rail joint part (7b) of the next rail, which is removable from the desired work scaffold (3). Can be pinched and fixed in position.

【0015】図2はガイドレール吊上げ装置(8)の拡大
斜視図である。図において、(8b)は挟持金具としての挟
持基板で、4隅に配設された挟持クリップ(8a)との間で
T字形のエレベーター用のガイドレール(7)の基板部(7
f)を挟み込み、締付けボルト(8f)により締付けすること
ができる。(8c)は挟持部が連結された挟持金具としての
連結クリップで、T字形のガイドレールが入るT字形の
隙間を存して上記挟持基板(8b)に重ね合わされ、締結具
としての締付けボルト(8e)を締付けることにより、ガイ
ドレールを緊締挟持することができる。(8d)は上記連結
クリップ(8c)の連結頂部に突設された吊り板で、吊孔(8
g)を有している。(9)はこの吊孔(8g)に係止されたシャ
ックルで、揚重ロープ(5)と接続されている。(8h)は三
角形状の補強リブである。
FIG. 2 is an enlarged perspective view of the guide rail lifting device (8). In the figure, (8b) is a holding board as a holding metal fitting, and a board portion (7) of a guide rail (7) for a T-shaped elevator with a holding clip (8a) arranged at four corners.
It can be tightened with the tightening bolt (8f). Reference numeral (8c) is a connecting clip as a holding metal fitting to which the holding portions are connected. The connecting clip is superposed on the holding board (8b) with a T-shaped gap into which a T-shaped guide rail is inserted, and a tightening bolt (a fastener). The guide rail can be clamped by tightening 8e). (8d) is a hanging plate protruding from the connecting top of the connecting clip (8c).
g). (9) is a shackle locked in this suspension hole (8g) and is connected to the lifting rope (5). (8h) is a triangular reinforcing rib.

【0016】次に作用・動作について説明する。図1、
図2において、最上部連結レール(7a)に挟持金具として
の挟持基板(8b)と、これに対向する挟持クリップ(8a)お
よび挟持金具としての連結クリップ(8c)とを、レールの
長手方向に沿ってスライドさせつつ適当な場所にて締結
具としての締付けボルト(8f)(8e)を締付けることにより
挟持金具を締付け固定する。上記適当な場所とは、作業
足場(3)から適正な姿勢で取外しできる高さである。
Next, the operation and operation will be described. Figure 1,
In FIG. 2, the uppermost connecting rail (7a) is provided with a sandwiching board (8b) as a sandwiching metal fitting, a sandwiching clip (8a) and a connecting clip (8c) as a sandwiching metal fitting facing each other in the longitudinal direction of the rail. While sliding along, tighten the clamp bolts (8f) (8e) as fasteners at appropriate places to clamp and clamp the clamps. The appropriate place is a height at which the work scaffold (3) can be detached in a proper posture.

【0017】揚重ウインチ(4)を運転しながら順次レー
ル(7)を吊り、先ずレール(7a)と次下段のレール(7d)を
目板を用いてボルトナットで接続する。このような方法
で順次下段のレールを接続してゆく。このとき最下部連
結レール(7e)は予めピット(1a)に設置されたバッファ台
(12)と最下部ブラケット(13)により昇降路(1)の下に固
定する。ついで、最下部連結レール(7e)の上端と吊り上
げたレール(7)の下端を連結し、最上部連結レール(7a)
を最上部レールブラケット(14)で固定する。ガイドレー
ル(7)の設置が終了すれば作業足場(3)の上からレール吊
上げ装置を取外す。
While the lifting winch (4) is being operated, the rail (7) is suspended in order, and first the rail (7a) and the next lower rail (7d) are connected with bolts and nuts by using an eye plate. The lower rails are sequentially connected in this way. At this time, the lowermost connecting rail (7e) is a buffer stand previously installed in the pit (1a).
Fasten under hoistway (1) with (12) and bottom bracket (13). Then, connect the upper end of the lowermost connecting rail (7e) and the lower end of the suspended rail (7) to the uppermost connecting rail (7a).
Secure with the top rail bracket (14). When the guide rail (7) is installed, remove the rail lifting device from the work platform (3).

【0018】この実施例では、挟持金具としての連結ク
リップ(8c)の他に挟持クリップ(8a)を4個用いている
が、連結クリップ(8c)がなくてもよい。
In this embodiment, four holding clips (8a) are used in addition to the connecting clip (8c) as the holding metal fitting, but the connecting clip (8c) may be omitted.

【0019】実施例2.なお、上記実施例では、挟持金
具より吊孔を有する吊板を突設したものであるが、ガイ
ドレール(7)の基板部(7f)に1つ以上の吊孔を設けたも
のでもよい。すなわち、図3、図4に示すように、ガイ
ドレール(7)の基板部(7f)に1つ以上の吊孔(7b)が設け
られている。この所望の吊孔(7b)にシャックル(9)を連
結し、揚重ロープ(5)を用いて吊上げることができる。
Example 2. In addition, in the above embodiment, the hanging plate having the hanging hole is projected from the holding metal fitting, but one or more hanging holes may be provided in the base plate portion (7f) of the guide rail (7). That is, as shown in FIGS. 3 and 4, one or more suspension holes (7b) are provided in the base plate portion (7f) of the guide rail (7). A shackle (9) can be connected to this desired suspension hole (7b) and can be lifted using a lifting rope (5).

【0020】実施例3.なお、上記実施例では、いずれ
も吊孔を設け、これにシャックルを連結し揚重ロープを
用いて吊上げるものであるが、吊孔の代りに1つ以上の
メネジ孔を用いたものでもよい。すなわち、図5、図6
に示すように、ガイドレール(7)の基板部(7f)に1つ以
上のメネジ孔(7c)が設けられている。この所望のメネジ
孔(7c)にアイボルト(10)を螺合し、揚重フック(11)を係
合し、揚重ロープ(5)を用いて吊上げることができる。
Example 3. In each of the above-described embodiments, a suspension hole is provided, and a shackle is connected to the suspension hole to lift it using a lifting rope. However, one or more female screw holes may be used instead of the suspension hole. . That is, FIG. 5 and FIG.
As shown in FIG. 1, one or more female screw holes (7c) are provided in the base plate portion (7f) of the guide rail (7). The eyebolt (10) can be screwed into the desired female screw hole (7c), the lifting hook (11) can be engaged, and the lifting rope (5) can be used to lift the lifting screw.

【0021】[0021]

【発明の効果】請求項1の発明によれば、挟持金具をガ
イドレールの長手方向に沿った所望の位置に、締結具を
用いて締付け固定することができるので、どのような昇
降路構造に対しても吊代を確保することができ、また、
どのような作業足場高さからでも取外しが可能で安全性
を確保することができる。
According to the invention of claim 1, since the holding metal fitting can be fastened and fixed at a desired position along the longitudinal direction of the guide rail by using a fastener, any hoistway structure can be obtained. You can also secure a hanging allowance, and also
It can be removed from any work scaffold height to ensure safety.

【0022】また、請求項2および請求項3の発明によ
れば、ガイドレールの基板部の適宜の位置に設けた1つ
以上の吊孔またはメネジ孔を設けたので、所望の吊孔ま
たはメネジ孔を用いて吊上げることができるため、特別
な吊金具を要することなく、ガイドレール吊上げ装置の
軽量簡易化が図れるとともに、ガイドレール吊りの段取
り、取外し時間の短縮化が図れる。さらにまた、吊孔ま
たはメネジ孔の数を増加することによって、どのような
昇降路構造に対しても吊代を確保することができ、ま
た、どのような作業足場高さからでも取外しが可能で安
全性を確保することができる。
Further, according to the inventions of claims 2 and 3, since one or more suspension holes or female screw holes provided at appropriate positions of the base plate portion of the guide rail are provided, a desired suspension hole or female screw is provided. Since it can be lifted by using the holes, the guide rail lifting device can be made light and simple without the need for a special hanging metal fitting, and the setup and removal time of the guide rail can be shortened. Furthermore, by increasing the number of hanging holes or female screw holes, it is possible to secure a hanging allowance for any hoistway structure, and it is possible to remove it from any working scaffold height. It is possible to ensure safety.

【図面の簡単な説明】[Brief description of drawings]

【図1】この発明の一実施例による昇降路概略側面断面
図。
FIG. 1 is a schematic side sectional view of a hoistway according to an embodiment of the present invention.

【図2】請求項1の発明に係る吊上げ装置の拡大斜視
図。
FIG. 2 is an enlarged perspective view of the lifting device according to the first aspect of the invention.

【図3】請求項2の発明に係るガイドレールの拡大斜視
図。
FIG. 3 is an enlarged perspective view of a guide rail according to a second aspect of the invention.

【図4】図3のガイドレールを吊る状態を示す拡大斜視
図。
FIG. 4 is an enlarged perspective view showing a state in which the guide rail of FIG. 3 is suspended.

【図5】請求項3の発明に係るガイドレールの拡大斜視
図。
FIG. 5 is an enlarged perspective view of the guide rail according to the invention of claim 3;

【図6】図5のガイドレールを吊る状態を示す拡大斜視
図。
6 is an enlarged perspective view showing a state in which the guide rail of FIG. 5 is suspended.

【図7】従来のエレベーター用レール吊上げ装置の昇降
路概略側面断面図。
FIG. 7 is a schematic side sectional view of a hoistway of a conventional elevator rail lifting device.

【符号の説明】[Explanation of symbols]

1 昇降路 3 作業足場 5 揚重ロープ 7 ガイドレール 7b 吊孔 7c メネジ孔 7f ガイドレールの基板部 8 ガイドレール吊上げ装置 8b 挟持金具としての挟持基板 8c 挟持金具としての連結クリップ 8d 吊板 8e 締結具としての締付けボルト 8g 吊孔 9 シャックル 10 アイボルト 11 揚重フック 1 hoistway 3 working scaffold 5 lifting rope 7 guide rail 7b hanging hole 7c female screw hole 7f guide rail base plate 8 guide rail lifting device 8b holding board as a holding metal fitting 8c connecting clip as a holding metal fitting 8d hanging plate 8e fastener Bolts 8g Suspended hole 9 Shackle 10 Eye bolt 11 Lifting hook

Claims (3)

【特許請求の範囲】[Claims] 【請求項1】 吊上げ用の吊孔を有する吊板を突設した
挟持金具を、締結具を用いてT字形のエレベーター用の
ガイドレールの長手方向に沿った所望の位置に締付け固
定するようにしたことを特徴とするエレベーター用のガ
イドレール吊上げ装置。
1. A clamping metal fitting projecting a suspension plate having a suspension hole for lifting is clamped and fixed at a desired position along the longitudinal direction of a T-shaped elevator guide rail using a fastener. A guide rail hoisting device for elevators that is characterized.
【請求項2】 基板部と直立部とからなるT字形のエレ
ベーター用のガイドレールにおいて、上記基板部の適宜
の位置に1つ以上の吊上げ用の吊孔を設けたことを特徴
とするエレベーター用のガイドレール吊上げ装置。
2. A T-shaped elevator guide rail comprising a base plate portion and an upright portion, wherein one or more suspension holes for lifting are provided at appropriate positions on the base plate portion. Guide rail lifting device.
【請求項3】 基板部と直立部とからなるT字形のエレ
ベーター用のガイドレールにおいて、上記基板部の適宜
の位置に1つ以上のメネジ孔を設け、吊上げ用のアイボ
ルトを所望の上記メネジ孔に螺合させるようにしたこと
を特徴とするエレベーター用のガイドレール吊上げ装
置。
3. A T-shaped elevator guide rail comprising a base plate portion and an upright portion, wherein one or more female screw holes are provided at appropriate positions of the base plate portion, and a lifting eyebolt is used as a desired female screw hole. A guide rail hoisting device for an elevator, which is adapted to be screwed into the.
JP5010322A 1993-01-26 1993-01-26 Guide rail lifting device for elevators Expired - Lifetime JP2748812B2 (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
JP5010322A JP2748812B2 (en) 1993-01-26 1993-01-26 Guide rail lifting device for elevators

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
JP5010322A JP2748812B2 (en) 1993-01-26 1993-01-26 Guide rail lifting device for elevators

Publications (2)

Publication Number Publication Date
JPH06219665A true JPH06219665A (en) 1994-08-09
JP2748812B2 JP2748812B2 (en) 1998-05-13

Family

ID=11746996

Family Applications (1)

Application Number Title Priority Date Filing Date
JP5010322A Expired - Lifetime JP2748812B2 (en) 1993-01-26 1993-01-26 Guide rail lifting device for elevators

Country Status (1)

Country Link
JP (1) JP2748812B2 (en)

Cited By (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
GB2518514A (en) * 2013-08-12 2015-03-25 James Somerville Mulvaney A clamp for use in the raising and lowering of at least one corrugated sheet
JP2016108115A (en) * 2014-12-08 2016-06-20 株式会社日立ビルシステム Elevator guide rail suspension fixture
JP2020200601A (en) * 2019-06-06 2020-12-17 大成建設株式会社 Hoisting jig and method for disassembling steel tower
US11365095B2 (en) * 2019-07-16 2022-06-21 Kone Corporation Method and an arrangement for installing elevator guide rails into an elevator shaft

Citations (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPS57158658U (en) * 1981-04-01 1982-10-05

Patent Citations (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPS57158658U (en) * 1981-04-01 1982-10-05

Cited By (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
GB2518514A (en) * 2013-08-12 2015-03-25 James Somerville Mulvaney A clamp for use in the raising and lowering of at least one corrugated sheet
GB2518514B (en) * 2013-08-12 2017-06-14 Somerville Mulvaney James A clamp for use in the raising and lowering of at least one corrugated sheet
JP2016108115A (en) * 2014-12-08 2016-06-20 株式会社日立ビルシステム Elevator guide rail suspension fixture
JP2020200601A (en) * 2019-06-06 2020-12-17 大成建設株式会社 Hoisting jig and method for disassembling steel tower
US11365095B2 (en) * 2019-07-16 2022-06-21 Kone Corporation Method and an arrangement for installing elevator guide rails into an elevator shaft

Also Published As

Publication number Publication date
JP2748812B2 (en) 1998-05-13

Similar Documents

Publication Publication Date Title
JPH06219665A (en) Guide rail hang-up device for elevator
JPH05178561A (en) Installation method for guide rail for elevator
JPH0220354Y2 (en)
JPS6034710Y2 (en) Lifting equipment for elevator rails
JPH0466485A (en) Device for suspending guide rail for elevator
JP2551532B2 (en) Lifting jig
JP2001354374A (en) Lifting device in hoistway of elevator
JP3043691B2 (en) Mounting device for loading stage for frame scaffold
JPH092774A (en) Heavy object suspending device
JP3332210B2 (en) Mounting bracket for frame scaffold
JPH0736001Y2 (en) Detachable lifting device
JPH0388685A (en) Method for vertically providing guide rail of elevator
JPS5817083A (en) Hanger for guide rail for elevator
JP3464628B2 (en) Elevator basket hanging jig
JP2695286B2 (en) Elevator guide rail standing guide device
CN206735624U (en) A kind of curtain wall plate lifting fixing device and Lift-on/Lift-off System
JPH021066B2 (en)
JPS61257890A (en) Panel hanging jig and panel hanger using said jig
JPH0520756Y2 (en)
JP2005298207A (en) Emergency stop device for elevator
JPH10167613A (en) Installation device for elevator guide rail
JP2023144549A (en) Hanging tool and hanging method of wall panel
JPS6143278B2 (en)
JP2002020057A (en) Fixing device and method for elevator car
JPS61183072A (en) Rail hanger

Legal Events

Date Code Title Description
FPAY Renewal fee payment (prs date is renewal date of database)

Free format text: PAYMENT UNTIL: 20080220

Year of fee payment: 10

FPAY Renewal fee payment (prs date is renewal date of database)

Free format text: PAYMENT UNTIL: 20090220

Year of fee payment: 11

FPAY Renewal fee payment (prs date is renewal date of database)

Free format text: PAYMENT UNTIL: 20100220

Year of fee payment: 12

FPAY Renewal fee payment (prs date is renewal date of database)

Year of fee payment: 12

Free format text: PAYMENT UNTIL: 20100220

FPAY Renewal fee payment (prs date is renewal date of database)

Year of fee payment: 13

Free format text: PAYMENT UNTIL: 20110220

FPAY Renewal fee payment (prs date is renewal date of database)

Free format text: PAYMENT UNTIL: 20120220

Year of fee payment: 14

FPAY Renewal fee payment (prs date is renewal date of database)

Year of fee payment: 15

Free format text: PAYMENT UNTIL: 20130220

EXPY Cancellation because of completion of term