JPH06185139A - Horizontal joining method of precast concrete earthquake resisting wall with steel beam - Google Patents

Horizontal joining method of precast concrete earthquake resisting wall with steel beam

Info

Publication number
JPH06185139A
JPH06185139A JP33710792A JP33710792A JPH06185139A JP H06185139 A JPH06185139 A JP H06185139A JP 33710792 A JP33710792 A JP 33710792A JP 33710792 A JP33710792 A JP 33710792A JP H06185139 A JPH06185139 A JP H06185139A
Authority
JP
Japan
Prior art keywords
steel beam
wall
joining
resisting wall
earthquake resisting
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
JP33710792A
Other languages
Japanese (ja)
Inventor
Hiroshi Matsubara
洋志 松原
Akihiko Sanpei
昭彦 三瓶
Hitoshi Sasaki
仁 佐々木
Masashi Matsudo
正士 松戸
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Fujita Corp
Original Assignee
Fujita Corp
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Fujita Corp filed Critical Fujita Corp
Priority to JP33710792A priority Critical patent/JPH06185139A/en
Publication of JPH06185139A publication Critical patent/JPH06185139A/en
Pending legal-status Critical Current

Links

Landscapes

  • Load-Bearing And Curtain Walls (AREA)
  • Buildings Adapted To Withstand Abnormal External Influences (AREA)

Abstract

PURPOSE:To facilitate execution of the work by dividing only upper part of a steel beam or its lower flanges in two each, joining a precast concrete earthquake resisting wall in advance to the flanges, and conducting the horizontal joining work only in the steel beam parts at the site. CONSTITUTION:At a factory, an upper PCa earthquake resisting wall 2 is joined with the upper flange 1a of each steel beam 1 in advance. An L-shaped joining metal piece 3 is joined to each side of the web bottom of this steel beam 1. After erecting a column, beam-equipped PCa earthquake resisting wall is erected. The upper wall 2 and steel beam 1 are sunk, and the two metal pieces 3 at the bottom of the steel beam 1 are seated on the lower flange 4 on a lower PCa earthquake resisting wall 5, and fastening is made using a bolt 6 and a but 7. In this manner the PCa earthquake resisting wall is in advance joined with the flanges by dividing only the upper part of the steel beam or its lower flanges in two each, and the horizontal joining work at the site take place only in the steel beam parts with the aid of joining metal pieces.

Description

【発明の詳細な説明】Detailed Description of the Invention

【0001】[0001]

【産業上の利用分野】本発明は、梁が鉄骨造の場合にお
けるプレキャストコンクリート耐震壁(以下PCa耐震
壁と称す)の水平接合部の接合方法に係るものである。
BACKGROUND OF THE INVENTION 1. Field of the Invention The present invention relates to a method for joining a horizontal joint portion of a precast concrete earthquake resistant wall (hereinafter referred to as PCa earthquake resistant wall) when the beam is a steel frame structure.

【0002】[0002]

【従来の技術】従来、鉄筋コンクリート造耐震壁と鉄骨
梁の接合においては、鉄骨梁側面に鉄筋コンクリート部
分を打ち増して、その部分に耐震壁を偏心させて取付け
る方法や、梁鉄骨にスタッドボルトを接合しておき、同
スタッドボルトによって耐震壁に水平力を伝達する方法
が採用されていた。
2. Description of the Related Art Conventionally, when joining a reinforced concrete earthquake-resistant wall to a steel beam, a method of additionally installing a reinforced concrete portion on the side of the steel beam and eccentrically installing the earthquake-resistant wall to that portion, or joining a stud bolt to the beam steel frame In addition, the method of transmitting horizontal force to the earthquake-resistant wall by the stud bolt was adopted.

【0003】[0003]

【発明が解決しようとする課題】しかしながら、耐震壁
を偏心接合させる場合、偏心させない場合に比して耐力
の低下が予想される。また鉄骨梁に鉄筋コンクリートを
打ち増すのに多大の労力を要し、工費も嵩む。
However, when the seismic wall is eccentrically joined, the yield strength is expected to be lower than when it is not eccentric. In addition, it takes a lot of labor to increase the amount of reinforced concrete on the steel beam, and the construction cost increases.

【0004】更にスタッドボルトを梁鉄骨に接合する方
法においては、スタッドボルト付近ではコンクリートの
充填が難しく、十分に剪断力を伝達できない場合が考え
られる。本発明は前記従来技術の有する問題点に鑑みて
提案されたもので、その目的は、施工性が向上され、構
造的に信頼性の高い鉄骨梁付きプレキャストコンクリー
ト耐震壁における水平接合方法を提供する点にある。
Further, in the method of joining the stud bolt to the beam steel frame, it may be difficult to fill the concrete near the stud bolt and the shear force may not be sufficiently transmitted. The present invention has been proposed in view of the above problems of the prior art, and an object thereof is to provide a horizontal joining method in a precast concrete earthquake-resistant wall with a steel beam, which has improved workability and is structurally highly reliable. In point.

【0005】[0005]

【課題を解決するための手段】前記の目的を達成するた
め、本発明に係る鉄骨梁付きプレキャストコンクリート
耐震壁における水平接合方法によれば、梁鉄骨の上部フ
ランジまたは下部フランジだけを他の部分と2分割し、
同上下各フランジに予めプレキャストコンクリート耐震
壁を接合しておき、現場での水平接合は接合金具を介し
て梁鉄骨のフランジ位置で行なうものである。
To achieve the above object, according to the horizontal joining method for a precast concrete earthquake-resistant wall with a steel beam according to the present invention, only the upper flange or the lower flange of the beam steel frame is different from other portions. Divided into two,
Precast concrete earthquake-resistant walls are joined to the upper and lower flanges in advance, and horizontal joining at the site is performed at the flange position of the beam steel frame through joining fittings.

【0006】[0006]

【作用】本発明によれば前記したように、梁鉄骨の上部
フランジまたは下部フランジだけを他の部分と2分割し
て、同上下フランジに予めプレキャストコンクリート耐
震壁を接合しておき、現場での水平接合は接合金具を介
してフランジ位置で行うようにしたので、上下層の壁鉄
筋からの応力が梁鉄骨を介して伝達できる。またこのよ
うに耐震壁の接合は鉄骨同士の接合となるため、接合後
の養生が不要となり、またコンクリート部分と鉄骨部分
とが工場で接合できるため、コンクリートの充填性がよ
くなり、施工が容易になる。
According to the present invention, as described above, only the upper flange or the lower flange of the beam steel frame is divided into two parts, and the pre-cast concrete seismic wall is preliminarily joined to the upper and lower flanges, and Since the horizontal joining is performed at the flange position through the joining metal fitting, the stress from the upper and lower wall reinforcing bars can be transmitted through the beam steel frame. In addition, since the joints of earthquake-resistant walls are joined to each other by steel frames, there is no need for curing after joining.Because the concrete part and the steel frame part can be joined at the factory, the filling of concrete is improved and construction is easy. become.

【0007】[0007]

【実施例】以下本発明を図示の実施例について説明す
る。図1及び図2は本発明の第1の実施例を示し、1は
鉄骨梁で、その上部フランジ1aに上部PCa耐震壁2
が予め工場で接合されている。図中2aは上部PCa耐
震壁2に埋設され、且つ上部フランジ1aに溶接された
壁鉄筋、2bは同壁鉄筋2a間の壁鉄筋である。更に前
記鉄骨梁1のウェブ下端両側に、L型の接合金具3が溶
接等によって接合されている。
The present invention will be described below with reference to the illustrated embodiments. 1 and 2 show a first embodiment of the present invention, in which 1 is a steel beam, and its upper flange 1a has an upper PCa seismic wall 2
Are pre-bonded at the factory. In the figure, 2a is a wall rebar embedded in the upper PCa earthquake-resistant wall 2 and welded to the upper flange 1a, and 2b is a wall rebar between the wall rebars 2a. Further, L-shaped joint fittings 3 are joined to both sides of the lower end of the web of the steel frame beam 1 by welding or the like.

【0008】4は下部PCa耐震壁5の上端に定着され
た前記鉄骨梁1の下部フランジとなるべき部分で、同フ
ランジ4にはボルト6が植立されている。図中5aは壁
鉄筋で前記下部フランジ4に溶接されている。5bは同
壁鉄筋5a間の壁鉄筋である。而して柱建方の完了後、
梁付きPCa耐震壁の建方を行なう。即ち図3(イ)に
示す如く、上部PCa耐震壁2及び鉄骨梁1を下降し
て、前記下部PCa耐震壁5上の下部フランジ4に鉄骨
梁1下端の一双のL型の接合金具3を着座せしめ、ボル
ト6を貫通し(図3(ロ)参照)、同ボルト6の突出部
にナット7を螺着緊締する(図3(ハ)参照)。
Reference numeral 4 denotes a portion to be a lower flange of the steel beam 1 fixed to the upper end of the lower PCa earthquake-resistant wall 5, and a bolt 6 is planted on the flange 4. Reference numeral 5a in the figure is a wall reinforcing bar and is welded to the lower flange 4. 5b is a wall reinforcing bar between the same wall reinforcing bars 5a. After the completion of pillar construction,
Construction of PCa earthquake-resistant wall with beams. That is, as shown in FIG. 3 (a), the upper PCa earthquake-resistant wall 2 and the steel frame beam 1 are lowered, and the lower flange 4 on the lower PCa earthquake-resistant wall 5 is fitted with a pair of L-shaped fittings 3 at the lower end of the steel frame beam 1. The seat 6 is seated, the bolt 6 is penetrated (see FIG. 3B), and the nut 7 is screwed and tightened on the protruding portion of the bolt 6 (see FIG. 3C).

【0009】図4及び図5は本発明の第2の実施例を示
し、一双のL型の接合金具3、3のうち、一方の接合金
具3が前記鉄骨梁1の一側に、他方の接合金具3が前記
下部フランジ4の他側に取付けられ前記両金具3、3を
貫通するボルト8、ナット9によって上下のPCa耐震
壁2、5を一体化するものである。図中、前記実施例と
均等部分には同一符号が付されている。
FIG. 4 and FIG. 5 show a second embodiment of the present invention. One of the pair of L-shaped joining fittings 3, 3 has one joining fitting 3 on one side of the steel beam 1 and the other. The joining metal fitting 3 is attached to the other side of the lower flange 4, and the upper and lower PCa earthquake-resistant walls 2 and 5 are integrated by bolts 8 and nuts 9 penetrating the both metal fittings 3 and 3. In the figure, the same parts as those in the above embodiment are designated by the same reference numerals.

【0010】[0010]

【発明の効果】前記したように本発明によれば、梁鉄骨
の上部フランジまたは下部フランジだけを他の部分と2
分割し、同各フランジに予めPCa耐震壁を接合してお
き、現場での水平接合は接合金具を介して梁鉄骨のフラ
ンジ位置で行なうようにしたので、水平接合部の施工が
容易で工期を短縮でき、梁幅を増さなくてもよく、構造
上信頼性の高い鉄骨梁付きプレキャストコンクリート耐
震壁が構成されるものである。
As described above, according to the present invention, only the upper flange or the lower flange of the beam steel frame is replaced with other portions.
Since the PCa seismic wall was divided and the PCa seismic wall was joined in advance to each flange, and the horizontal joining at the site was performed at the flange position of the beam steel frame through the joining metal fittings, the construction of the horizontal joining part is easy and the construction period is shortened. Precast concrete seismic wall with steel beams, which can be shortened and does not need to increase beam width, is structurally highly reliable.

【図面の簡単な説明】[Brief description of drawings]

【図1】本発明に係る鉄骨梁付きプレキャストコンクリ
ート耐震壁における水平接合方法の第1の実施例の実施
状況を示す縦断面図である。
FIG. 1 is a longitudinal sectional view showing an implementation state of a first embodiment of a horizontal joining method for a precast concrete earthquake-resistant wall with a steel beam according to the present invention.

【図2】図1の立面図である。FIG. 2 is an elevational view of FIG.

【図3】(イ)(ロ)(ハ)は前記第1の実施例の工程
説明図である。
3A, 3B, and 3C are process explanatory diagrams of the first embodiment.

【図4】本発明の第1の実施例の縦断面図である。FIG. 4 is a vertical cross-sectional view of the first embodiment of the present invention.

【図5】図4の立面図である。FIG. 5 is an elevational view of FIG.

【図6】(イ)(ロ)(ハ)は本発明の第2の実施例の
工程説明図である。
6A, 6B, 6C, 6D, 6E, 6F, 6G, and 6H are process diagrams of the second embodiment of the present invention.

【符号の説明】[Explanation of symbols]

1 鉄骨梁 1a 上部フランジ 2 上部PCa耐震壁 2a 壁鉄筋 2b 壁鉄筋 3 接合金具 4 鉄骨梁の下部フランジ 5 下部PCa耐震壁 5a 壁鉄筋 5b 壁鉄筋 6 ボルト 7 ナット 8 ボルト 9 ナット 1 Steel Beam 1a Upper Flange 2 Upper PCa Seismic Wall 2a Wall Reinforcing Bar 2b Wall Reinforcing Bar 3 Bonding Metal 4 Lower Flange of Steel Beam 5 Lower PCa Seismic Wall 5a Wall Reinforcing Bar 5b Wall Reinforcing Bar 6 Bolt 7 Nut 8 Bolt 9 Nut

───────────────────────────────────────────────────── フロントページの続き (72)発明者 松戸 正士 東京都渋谷区千駄ヶ谷四丁目6番15号 株 式会社フジタ内 ─────────────────────────────────────────────────── ─── Continuation of the front page (72) Inventor Masashi Matsudo 4-6-15 Sendagaya, Shibuya-ku, Tokyo Fujita Co., Ltd.

Claims (1)

【特許請求の範囲】[Claims] 【請求項1】 梁鉄骨の上部フランジまたは下部フラン
ジだけを他の部分と2分割し、同上下各フランジに予め
プレキャストコンクリート耐震壁を接合しておき、現場
での水平接合は接合金具を介して梁鉄骨のフランジ位置
で行なうことを特徴とする鉄骨梁付きプレキャストコン
クリート耐震壁における水平接合方法。
1. An upper flange or a lower flange of a beam steel frame is divided into two parts with other parts, and a precast concrete earthquake-resistant wall is preliminarily joined to each of the upper and lower flanges, and horizontal joining at the site is carried out through joining fittings. Horizontal joining method for precast concrete earthquake-resistant wall with steel beam, which is performed at flange position of beam steel frame.
JP33710792A 1992-12-17 1992-12-17 Horizontal joining method of precast concrete earthquake resisting wall with steel beam Pending JPH06185139A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
JP33710792A JPH06185139A (en) 1992-12-17 1992-12-17 Horizontal joining method of precast concrete earthquake resisting wall with steel beam

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
JP33710792A JPH06185139A (en) 1992-12-17 1992-12-17 Horizontal joining method of precast concrete earthquake resisting wall with steel beam

Publications (1)

Publication Number Publication Date
JPH06185139A true JPH06185139A (en) 1994-07-05

Family

ID=18305504

Family Applications (1)

Application Number Title Priority Date Filing Date
JP33710792A Pending JPH06185139A (en) 1992-12-17 1992-12-17 Horizontal joining method of precast concrete earthquake resisting wall with steel beam

Country Status (1)

Country Link
JP (1) JPH06185139A (en)

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN103397719A (en) * 2013-08-06 2013-11-20 郑勤民 Column-wall conjoined shear wall with hollow cavity
CN115726496A (en) * 2022-11-15 2023-03-03 海南大学 Anti-seismic superposed shear wall structure and construction method thereof

Cited By (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN103397719A (en) * 2013-08-06 2013-11-20 郑勤民 Column-wall conjoined shear wall with hollow cavity
CN103397719B (en) * 2013-08-06 2015-09-09 郑勤民 Post, wall disjunctor cavity shear wall
CN115726496A (en) * 2022-11-15 2023-03-03 海南大学 Anti-seismic superposed shear wall structure and construction method thereof
CN115726496B (en) * 2022-11-15 2023-08-11 海南大学 Anti-seismic superimposed shear wall structure and construction method thereof

Similar Documents

Publication Publication Date Title
JPH03244725A (en) Junction portion for pole and beam
JPH02136444A (en) Construction of composite structure consisting of precast reinforced concrete column and steel structural beam
JP2000170285A (en) Connecting method for steel sheet concrete structural wall and junction structure
JP3050136B2 (en) Connection structure between reinforced concrete columns and steel beams with large diameters only in the column reinforcement around the panel zone
JPH07252891A (en) Junction structure of steel member and concrete member
JPH06185139A (en) Horizontal joining method of precast concrete earthquake resisting wall with steel beam
JP2007291636A (en) Mixed-structure beam
JPH06248722A (en) Joining method for precast reinforcement concrete earthquake resisting wall and steel frame beam
JP3804174B2 (en) Seismic retrofitting method for existing buildings with square frame structure
JPH06185138A (en) Horizontal joining method of precast concrete earthquake resisting wall with steel beam
JP2972962B2 (en) Connection structure
JPH06185136A (en) Horizontal joining method for precast concrete earthquake resisting wall with steel beam
JP3250760B2 (en) Joining method of precast concrete column with beam bracket and precast concrete shear wall with steel beam
JPH06185135A (en) Precast earthquake resisting wall of complex structure
JP3169887B2 (en) Column base structure of steel pipe column and its construction method
JP2001107373A (en) Joint structure of steel column base with foundation concrete
JP2716510B2 (en) Column and beam joining method
JPH11117392A (en) Joint between steel pipe structure column or filling type steel pipe concrete structure column and src structure beam
JP3156014B2 (en) Precast reinforced concrete frame with end steel joints
JPH0932311A (en) Reinforcement structure of existing building
JPH05112985A (en) Joint structure of steel column legs
JPH0450324Y2 (en)
JPH07113260A (en) Method for connecting column and beam
JP2003307035A (en) Base isolation reinforcement
JP2674439B2 (en) Column / beam joint structure