JPH0561232U - Steel column base structure - Google Patents

Steel column base structure

Info

Publication number
JPH0561232U
JPH0561232U JP6686592U JP6686592U JPH0561232U JP H0561232 U JPH0561232 U JP H0561232U JP 6686592 U JP6686592 U JP 6686592U JP 6686592 U JP6686592 U JP 6686592U JP H0561232 U JPH0561232 U JP H0561232U
Authority
JP
Japan
Prior art keywords
column
anchor bolt
column base
bolt
anchor
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
JP6686592U
Other languages
Japanese (ja)
Inventor
春三 菊川
Original Assignee
川崎製鉄株式会社
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by 川崎製鉄株式会社 filed Critical 川崎製鉄株式会社
Priority to JP6686592U priority Critical patent/JPH0561232U/en
Publication of JPH0561232U publication Critical patent/JPH0561232U/en
Pending legal-status Critical Current

Links

Landscapes

  • Foundations (AREA)

Abstract

(57)【要約】 【目的】 アンカーボルトの寸法誤差を吸収し、柱脚金
物の曲げ耐力を向上させる。 【構成】 鋼製柱1の下端部に取り付けた柱脚金物2
を、アンカーボルト4によって基礎コンクリートに結合
してなる柱脚構造であって、アンカーボルト4はその全
長のうち上部の柱脚金物2のボルト孔21を貫通する部
分、すなわち上部アンカーボルト42と下部アンカーボル
ト41とを連結スリーブ43により結合してなり、上部アン
カーボルト42は高力ボルト、下部アンカーボルト41はね
じ鉄筋により構成される。
(57) [Summary] [Purpose] To absorb the dimensional error of anchor bolts and improve the bending resistance of column pedestals. [Structure] Column base metal fitting 2 attached to the lower end of the steel column 1.
Is a column base structure formed by connecting the anchor bolts 4 to the foundation concrete, and the anchor bolts 4 have a portion of their entire length that penetrates the bolt holes 21 of the upper column base metal fitting 2, that is, the upper anchor bolt 42 and the lower portion. The anchor bolt 41 and the anchor bolt 41 are connected by a connecting sleeve 43. The upper anchor bolt 42 is a high-strength bolt, and the lower anchor bolt 41 is a screw reinforcing bar.

Description

【考案の詳細な説明】[Detailed description of the device]

【0001】[0001]

【産業上の利用分野】[Industrial applications]

本考案は、鋼構造もしくは鉄骨鉄筋コンクリート構造の建築物における鋼製柱 (その周囲にコンクリートその他の被覆をしたものや、合成構造のものも含む) の柱脚構造に関する。 The present invention relates to a column base structure of a steel column (including those having a concrete or other coating around it, or a composite structure) in a building having a steel structure or a steel reinforced concrete structure.

【0002】[0002]

【従来の技術】[Prior Art]

通常、鋼構造もしくは鉄骨鉄筋コンクリート構造の建築物における鋼製柱は、 その下端部に取り付けた柱脚金物と称する金物とアンカーボルトを介して地中梁 あるいは基礎コンクリートに固定される。図4は、特開平2-256741号公報におい て従来の技術として示されている典型的な柱脚構造の一例で、鋼製柱1の下端部 に柱脚金物2を溶接し、アンカーボルト4により基礎コンクリート3と緊結する もので、レベル調整モルタル5上に柱1を立設してアンカーボルト4を締付けた 後、柱脚金物2下部全面にわたり充填モルタル6が打設される。 Usually, a steel column in a building of steel structure or steel reinforced concrete structure is fixed to an underground beam or foundation concrete through a metal fixture called a column pedestal attached to its lower end and anchor bolts. FIG. 4 shows an example of a typical column base structure disclosed in Japanese Patent Laid-Open No. 2-256741 as a conventional technique, in which a column base metal 2 is welded to the lower end of a steel column 1 and an anchor bolt 4 is formed. The pillar 1 is erected on the level adjusting mortar 5, and the pillar 1 is erected on the level adjusting mortar 5 and the anchor bolt 4 is tightened.

【0003】 この構造においては、鋼製柱に作用する曲げモーメントは柱脚金物2の曲げ抵 抗を介してアンカーボルト4の引張力として伝達される。従って、柱脚部と基礎 コンクリートとを強固に固定するためにはアンカーボルト4に充分な太さが必要 である。このアンカーボルト4が挿入される柱脚金物2のボルト孔21は、ボルト 径に隙間分を加えた寸法が必要であるが、柱脚金物2のボルト孔21の孔明け位置 誤差、さらにアンカーボルト4の植え込み位置誤差等をアンカーボルト4とボル ト孔21の隙間で吸収しようとすると一層大きい寸法の孔とせねばならず、柱脚金 物2の曲げ耐力を低下させる結果となる。In this structure, the bending moment acting on the steel column is transmitted as a tensile force of the anchor bolt 4 via the bending resistance of the column base metal member 2. Therefore, the anchor bolt 4 must have a sufficient thickness to firmly fix the column base and the concrete foundation. The bolt hole 21 of the column base metal fitting 2 into which the anchor bolt 4 is inserted needs to have a dimension which is equal to the bolt diameter with a clearance added. However, the hole position error of the bolt hole 21 of the column base metal body 2 and the anchor bolt If the gap between the anchor bolt 4 and the bolt hole 21 is intended to be absorbed in the implantation position error of No. 4 and the like, a hole having a larger size must be formed, resulting in a decrease in bending strength of the column base metal 2.

【0004】 そこで、これらの寸法誤差をボルト孔21の寸法を大きくすることなく吸収する 工夫として、特公昭55-6131 号公報によれば、鋼製柱1のベースプレート22とア ンカーボルト4との中間に図5に示すような柱脚支持装置23を設けている。この 柱脚支持装置23の上板24には柱脚ベースプレート22との結合ボルト26の貫通する 長孔が、また下板25にはアンカーボルト4の貫通する長孔がそれぞれ直交する状 態で穿設されており、この直交する長孔によってあらゆる方向の寸法誤差を吸収 できるようになっている。また、特開昭63-83322号公報によれば、図6に示すよ うに、上面にルーズ孔を設けた接合金具27を用いて、この接合金具27下部のめね じ部をアンカーボルト4にねじ込み結合し、鋼製柱1下部のベースプレートと接 合金具27とを結合する結合ボルト26は接合金具上部のルーズ孔内で固定するよう にして寸法誤差を吸収している。Therefore, as a device for absorbing these dimensional errors without increasing the size of the bolt hole 21, according to Japanese Patent Publication No. 55-6131, an intermediate position between the base plate 22 of the steel column 1 and the anchor bolt 4 is disclosed. Further, a column base supporting device 23 as shown in FIG. 5 is provided. The upper plate 24 of the column base supporting device 23 has a long hole through which the coupling bolt 26 with the column base plate 22 penetrates, and the lower plate 25 has a long hole through which the anchor bolt 4 penetrates in a state orthogonal to each other. It is installed, and the dimensional error in all directions can be absorbed by these orthogonal long holes. Further, according to Japanese Patent Laid-Open No. 63-83322, as shown in FIG. 6, a joint metal fitting 27 having a loose hole on its upper surface is used, and a female part under the joint metal fitting 27 is attached to the anchor bolt 4. A coupling bolt 26, which is screwed to couple the base plate under the steel column 1 and the fitting 27, is fixed in the loose hole in the upper portion of the fitting to absorb the dimensional error.

【0005】 これらの手段によれば、寸法誤差の問題は解決するけれども、使用する柱脚支 持装置23や接合金具27等の補助金物の剛性を高めることが重要であり、補助金物 と柱脚金物との接触面の平行度の精度を満たすことが現実にはきわめて困難であ るという問題点がある。 一方、特公平2-14496 号公報により、アンカーボルトに軸力を導入して柱脚部 に剛性を付与することが提案されている。図7に示すように、アンカーボルト4 は軸部4aと周囲のコンクリート3との付着をなくした不拘束部4bを設けた軸方向 不拘束状態で柱脚金物2を緊結し、柱脚に離間モーメントが存在するようにする ため、このアンカーボルト4に降伏応力度の0.15〜1.2 倍の応力度が発生するよ うに導入張力を付与して緊結している。つまり、アンカーボルト4と基礎コンク リート3との付着の縁を切ることにより、ボルト軸力低下に関する経年劣化の緩 和を図っている。7はアンカーフレームである。ただし、この公報には、いかに して上記の不拘束状態を実現するかの具体的な構成は開示されていない。According to these means, although the problem of dimensional error is solved, it is important to increase the rigidity of the auxiliary metal support such as the column base supporting device 23 and the joint fitting 27 to be used. In reality, it is extremely difficult to satisfy the accuracy of the parallelism of the contact surface with the metal object. On the other hand, Japanese Patent Publication No. 2-14496 proposes to introduce axial force into the anchor bolt to give rigidity to the column base. As shown in FIG. 7, the anchor bolt 4 is tightly connected to the column base metal fitting 2 in the axially unconstrained state in which the unconstrained portion 4b which eliminates adhesion between the shaft portion 4a and the surrounding concrete 3 is provided, and is separated from the column base. In order to allow the moment to exist, the anchor bolt 4 is tightly connected by applying an introduction tension so that a stress of 0.15 to 1.2 times the yield stress is generated. In other words, by cutting off the edge of adhesion between the anchor bolt 4 and the basic concrete 3, it is attempted to mitigate aging deterioration related to the decrease in bolt axial force. Reference numeral 7 is an anchor frame. However, this publication does not disclose a specific configuration of how to realize the above-mentioned unconstrained state.

【0006】 この方法によると、アンカーボルトは強度的性能を十分に発揮し、柱脚に発生 する曲げモーメントに対しても良好な性能を確保でき、耐震製の低下を防止でき るけれども、さきの各例で見られたようなアンカーボルト4の寸法誤差の吸収に 関しては何ら解決がなされていない。According to this method, the anchor bolt exerts sufficient strength performance, can secure good performance against bending moments generated in the column base, and can prevent deterioration of seismic resistance. No solution has been made to the absorption of the dimensional error of the anchor bolt 4 as seen in each example.

【0007】[0007]

【考案が解決しようとする課題】[Problems to be solved by the device]

本考案は、上記の諸問題を解消し、柱脚金物の曲げ耐力を低下させないでしか も寸法誤差を吸収できる鋼製柱の柱脚構造を提供することを目的とする。 An object of the present invention is to solve the above problems and to provide a column base structure of a steel column that can absorb a dimensional error without reducing the bending strength of the column base metal.

【0008】[0008]

【課題を解決するための手段】[Means for Solving the Problems]

本考案の第1ないし第3の柱脚構造は、鋼製柱の下端部に取り付けた柱脚金物 を、アンカーボルトによって基礎コンクリートに結合してなる柱脚構造であって 、前記アンカーボルトの全長のうち少なくとも上部の柱脚金物のボルト孔を貫通 する部分が高力ボルトで構成されていることを特徴とする。 1st thru | or 3rd column base structure of this invention is a column base structure which connects the column base metal thing attached to the lower end part of a steel column to basic concrete with an anchor bolt, Comprising: The said anchor bolt full length At least a portion of the upper column pedestal that penetrates the bolt hole is made of high-strength bolts.

【0009】 また、本考案の第4ないし第5の柱脚構造は、鋼製柱の下端部に取り付けた柱 脚金物をアンカーボルトによって基礎コンクリートに結合してなる柱脚構造であ って、前記アンカーボルトが貫通する管状の支柱を相互に連結してなるアンカー フレームを前記基礎コンクリート内に埋設させて構成したことを特徴とする。The fourth to fifth column base structures of the present invention are column base structures in which a column base metal fitting attached to a lower end portion of a steel column is connected to basic concrete by anchor bolts. An anchor frame, which is formed by connecting tubular columns through which the anchor bolt penetrates, is embedded in the basic concrete.

【0010】[0010]

【作 用】[Work]

本考案の第1ないし第3の柱脚構造によれば、アンカーボルトの全長のうち少 なくとも上部の柱脚金物のボルト孔を貫通する部分が高力ボルトで構成されてい ることにより、柱脚金物のボルト孔を従来よりも小径となるので、柱脚金物の曲 げ耐力を向上させることができる。また、柱脚金物の締付けに高力ボルトを使用 することにより、締付け力の管理が容易となり、柱脚の固定度の信頼性も向上す る。 According to the first to third column base structures of the present invention, since at least a portion of the entire length of the anchor bolt that penetrates the bolt hole of the upper column base metal member is formed of high-strength bolts, Since the bolt hole of the leg metal has a smaller diameter than the conventional one, the bending resistance of the column metal can be improved. Also, the use of high-strength bolts for tightening the column base metal makes it easier to control the tightening force and improves the reliability of the degree of fixing the column base.

【0011】 また、本考案の第4ないし第5の柱脚構造によれば、アンカーボルトが貫通す る管状の支柱を相互に連結してなるアンカーフレームを前記基礎コンクリート内 に埋設させ、この支柱内にアンカーボルトを貫通させ、支柱下部の支圧板と地上 の柱脚金物とでアンカーボルトを締付けるようにしたから、吸収できるアンカー ボルトの寸法誤差がきわめて大きくなり、柱脚の固定度の信頼製が向上するとと もに、施工能率が向上する。According to the fourth to fifth column base structures of the present invention, an anchor frame formed by interconnecting tubular columns through which anchor bolts penetrate is embedded in the foundation concrete, and the columns are formed. Since the anchor bolts are pierced inside and the anchor bolts are tightened between the bearing plate at the bottom of the column and the column base metal fittings on the ground, the dimensional error of the anchor bolts that can be absorbed becomes extremely large, and the column base's fixing degree is made reliable. And the construction efficiency is improved.

【0012】[0012]

【実施例】 実施例1 図1に本考案の第1の実施例である柱脚構造を示す。さきの図4と共通する部 品については同じ符号を使用している。図4と異なるのはアンカーボルト4の関 係である。本実施例においては、基礎コンクリート3中に埋設された下部アンカ ーボルト41は、連結スリーブ43を介して上部アンカーボルト42と連結されている 。下部アンカーボルト41は、異形棒鋼の一種であるねじ鉄筋をそのままアンカー ボルトとして使用している。上部アンカーボルト42は引張強度80〜100kgf/mm2 程度の高力ボルトである。下部アンカーボルト41の径を50mm前後とすると、上部 アンカーボルトの径は24mm以下とすることが可能であり、さきに説明した寸法誤 差吸収に要する隙間を 6mmとしても、柱脚金物のボルト孔21は30mmあればよいこ とになり、従来のアンカーボルト径50mmに対するボルト孔56mmと比較してボルト 孔が大幅に小径化される。Embodiment 1 FIG. 1 shows a column base structure which is a first embodiment of the present invention. The same reference numerals are used for the same parts as those in FIG. 4 above. What is different from FIG. 4 is the relationship of the anchor bolt 4. In this embodiment, the lower anchor bolt 41 embedded in the foundation concrete 3 is connected to the upper anchor bolt 42 via the connecting sleeve 43. As the lower anchor bolt 41, a screw rebar, which is a type of deformed steel bar, is directly used as an anchor bolt. The upper anchor bolt 42 is a high strength bolt having a tensile strength of about 80 to 100 kgf / mm 2 . If the diameter of the lower anchor bolt 41 is around 50 mm, the diameter of the upper anchor bolt can be 24 mm or less, and even if the gap required to absorb the dimensional error described above is 6 mm, the bolt hole of the column base metal It is sufficient for 21 to be 30 mm, and the diameter of the bolt hole is significantly smaller than the conventional bolt diameter of 50 mm and bolt hole of 56 mm.

【0013】 連結スリーブ43は、異形棒鋼の接続に使用するねじジョイントと類似のもので 、この実施例では下部アンカーボルト41がねじ鉄筋であるから、これに対応する めねじ部を有し、上部アンカーボルト42側にはこの高力ボルトに対応するめねじ 部を加工してある。上下アンカーボルト41、42と連結スリーブ43との締結を確実 にするため、連結スリーブ43の上下にはそれぞれ下部ロックナット44、上部ロッ クナット45を使用する。下部アンカーボルト41がねじ鉄筋以外の通常の異形棒鋼 である場合には、異形棒鋼の接続に一般的に使用される連結スリーブを下部アン カーボルト41に予め圧着により取り付けておけばよい。The connecting sleeve 43 is similar to a threaded joint used for connecting deformed steel bars, and in this embodiment, since the lower anchor bolt 41 is a threaded reinforcing bar, it has a female thread portion corresponding to this, A female thread corresponding to this high strength bolt is machined on the side of the anchor bolt 42. In order to secure the fastening between the upper and lower anchor bolts 41, 42 and the connecting sleeve 43, a lower lock nut 44 and an upper lock nut 45 are used above and below the connecting sleeve 43, respectively. When the lower anchor bolt 41 is a normal deformed steel bar other than the screw rebar, a connecting sleeve generally used for connecting the deformed steel bar may be attached to the lower anchor bolt 41 by crimping in advance.

【0014】 本実施例におけるアンカーボルトは、全長のうち少なくとも上部の柱脚金物の ボルト孔を貫通する部分が高力ボルトで構成されていることが必要であって、下 部については上記実施例のようにねじ鉄筋あるいは通常の異形棒鋼でよいが、全 長が高力ボルトであっても差し支えはない。この場合は前記実施例のような連結 スリーブが不要であるのは、いうまでもない。In the anchor bolt in this embodiment, at least a portion of the entire length that penetrates the bolt hole of the upper column pedestal must be made of a high-strength bolt, and the lower portion has the above-mentioned embodiment. As mentioned above, screw rebar or ordinary deformed steel bar may be used, but there is no problem even if the entire length is a high strength bolt. In this case, needless to say, the connecting sleeve as in the above embodiment is unnecessary.

【0015】 また、図1においては、柱脚金物2の底辺の厚みをほぼ均一としているけれど も、図2に示すように鋼製柱1との継手部へ向かって底辺の厚みを増してやると 、柱脚金物2の曲げ耐力がいっそう向上するので好ましい。このような場合は柱 脚金物を鋳造もしくは鍛造で製造する必要がある。 本実施例の柱脚構造による柱部分の架設は、以下の手順により行う。 1)下部アンカーボルト41をアンカーフレーム等により位置決めして、基礎コン クリート3を打設する。 2)レベル調整モルタル5を設置し、その上面高さを所定値に調整する。 3)下部アンカーボルト41の頂部に連結スリーブ43および上部アンカーボルト41 を接続し、締め付ける。 4)予め柱脚金物2を溶接により取り付けた鋼製柱1をレベル調整モルタル5上 に建て込む。 5)基礎コンクリート3と柱脚金物2との間に充填モルタル6を打設する。 6)上部アンカーナット46を締付ける。Further, in FIG. 1, although the thickness of the bottom of the column base metal 2 is made substantially uniform, if the thickness of the bottom is increased toward the joint with the steel column 1 as shown in FIG. This is preferable because the bending resistance of the column base metal 2 is further improved. In such cases, it is necessary to manufacture the column base metal by casting or forging. The erection of the column portion by the column base structure of the present embodiment is performed by the following procedure. 1) Position the lower anchor bolt 41 with an anchor frame, etc., and drive the foundation concrete 3. 2) Install the level adjustment mortar 5 and adjust the height of the upper surface to a predetermined value. 3) Connect the connecting sleeve 43 and the upper anchor bolt 41 to the top of the lower anchor bolt 41 and tighten them. 4) Build the steel column 1 with the column base 2 attached by welding in advance on the level adjustment mortar 5. 5) A filling mortar 6 is placed between the foundation concrete 3 and the column base metal 2. 6) Tighten the upper anchor nut 46.

【0016】 これにより、柱脚金物2と基礎コンクリート3とは完全に一体化され、鋼構造 建築における高力ボルト接合と同等の力学的挙動の発現が期待できる。すなわち 、柱脚金物2は高力ボルトを通して基礎コンクリート3と緊結されることにより 、このボルトが降伏して柱脚金物2と基礎コンクリート3とが離間しない限り、 柱脚部分の曲げ剛性は完全剛に近い状態が保持されるのである。As a result, the column base metal 2 and the foundation concrete 3 are completely integrated, and it is expected that the mechanical behavior equivalent to that of the high-strength bolted joint in steel structure construction is exhibited. That is, the column base metal fitting 2 is tightly bonded to the foundation concrete 3 through a high-strength bolt, so that the bending rigidity of the column base portion is completely rigid unless the bolt yields and the column base metal fitting 2 and the basic concrete 3 are separated from each other. The state close to is maintained.

【0017】 実施例2 本考案の第2の実施例を図3により説明する。図3(a)はその柱脚部分の縦 断面図である。これまでの図と共通する部品については同じ符号を使用する。鋼 製柱1は柱脚金物2に溶接接合されている。柱脚金物2は、アンカーボルト4に より基礎コンクリート3と緊結されているが、図4と異なるところは、アンカー ボルト4が直接基礎コンクリート3内に埋設されているのではなく、アンカーフ レーム7を介して結合されている点であり、アンカーフレーム7は、管状材より なる支柱71、この上下に固定されている支圧板72、72' ならびに図示しないが各 アンカーボルト毎の支柱71を連結して一体化する梁状材より構成される。また、 支圧板72、72' と上下ナット42、44の中間には座金73、73' が挿入される。Second Embodiment A second embodiment of the present invention will be described with reference to FIG. FIG. 3A is a longitudinal sectional view of the column base portion. The same reference numerals are used for the parts that are common to the above figures. The steel column 1 is welded to the column base metal piece 2. The column pedestal 2 is tightly connected to the foundation concrete 3 by the anchor bolts 4, but the difference from FIG. 4 is that the anchor bolts 4 are not directly embedded in the foundation concrete 3 but the anchor frame 7 is attached. The anchor frame 7 is formed by connecting the pillar 71 made of a tubular material, the pressure plates 72 and 72 'fixed above and below, and the pillar 71 for each anchor bolt (not shown). It is composed of integrated beam-shaped members. Further, washers 73, 73 'are inserted between the pressure bearing plates 72, 72' and the upper and lower nuts 42, 44.

【0018】 本実施例における施工手順はつぎのとおりである。 1)アンカーボルト4の予定位置にアンカーフレーム7を設置する。アンカーボ ルト4はアンカーフレーム7の支柱71内にセットしておく。 2)アンカーフレーム7の周囲に基礎コンクリート3を打設する。このとき、図 3に示すように、基礎コンクリート3の上面が上部支圧板72' よりも高くならな いことが必要である。 3)レベル調整ブロック5に柱脚金物2を載置して鋼製柱1を設置し、アンカー ボルト4の仮締めを行う。 4)レベル調整、センタリング調整等の建入れ直しを行う。このとき、各アンカ ーボルト4はアンカーフレーム7の上下支圧板72、72' の孔径とアンカーボルト 4の外径との隙間の範囲で水平方向に移動可能である。 5)レベル調整、センタリング調整等の建入れ直しを完了したら、基礎コンクリ ート3と柱脚金物2との間に無収縮の充填モルタル6を打設する。このとき、充 填モルタル6がアンカーフレーム7の支柱71内に流入しないようにしてモルタル 量を節約するためには、上部座金73' の孔径がアンカーボルト4の外径にほぼ等 しいことが望ましい。The construction procedure in this embodiment is as follows. 1) Install the anchor frame 7 at the expected position of the anchor bolt 4. The anchor bolt 4 is set in the column 71 of the anchor frame 7. 2) Pour the foundation concrete 3 around the anchor frame 7. At this time, as shown in FIG. 3, it is necessary that the upper surface of the foundation concrete 3 is not higher than the upper bearing plate 72 '. 3) Place the column pedestal 2 on the level adjustment block 5, install the steel column 1, and temporarily tighten the anchor bolt 4. 4) Rebuild the building such as level adjustment and centering adjustment. At this time, each anchor bolt 4 is movable in the horizontal direction within the range of the gap between the hole diameter of the upper and lower bearing plates 72, 72 'of the anchor frame 7 and the outer diameter of the anchor bolt 4. 5) After reassembling such as level adjustment and centering adjustment, a non-shrinkable filling mortar 6 is placed between the basic concrete 3 and the column base metal 2. At this time, in order to prevent the filled mortar 6 from flowing into the columns 71 of the anchor frame 7 and save the amount of mortar, it is desirable that the hole diameter of the upper washer 73 'be substantially equal to the outer diameter of the anchor bolt 4. ..

【0019】 このように、本実施例においては、アンカーボルト4の寸法誤差はアンカーフ レーム7の上下支圧板72、72' の孔径とアンカーボルト4の外径との隙間の範囲 で水平方向に移動可能であり、上下支圧板72、72' の孔径は支柱71の内径を限度 に大きくすることができるが、脚部の耐力の面からは特に下部支圧板72の孔径は あまり大きくないほうが有利であり、アンカーボルト4の外径の2倍程度が一応 の限度と考えられる。この場合、アンカーボルト4の許容寸法誤差は片側でボル ト径の1/2であり、従来の柱脚金物のボルト孔による許容誤差等と比較すると きわめて大きい誤差を吸収できることがわかる。As described above, in this embodiment, the dimensional error of the anchor bolt 4 moves horizontally within the range of the gap between the hole diameters of the upper and lower bearing plates 72, 72 ′ of the anchor frame 7 and the outer diameter of the anchor bolt 4. The hole diameter of the upper and lower bearing plates 72, 72 'can be increased up to the inner diameter of the support column 71, but from the standpoint of the yield strength of the legs, it is advantageous that the hole diameter of the lower bearing plate 72 is not too large. Yes, it is considered that the limit is about twice the outer diameter of the anchor bolt 4. In this case, the allowable dimensional error of the anchor bolt 4 is ½ of the bolt diameter on one side, and it can be understood that an extremely large error can be absorbed as compared with the allowable error due to the bolt holes of the conventional column pedestal.

【0020】 また、アンカーフレーム7の支柱71の外表面に突起を設けたり、高力ボルトの 摩擦継手に要求されているような粗面とすることにより、アンカーフレーム7と 基礎コンクリート3との付着効果を高めることができ、より強固な脚部構造が実 現する。 さらに、図3(b)に示したように、下部支圧板72の外表面ならびに下部座金 73の接触部を球面とすれば、アンカーボルト4に偏芯力が作用しないため、脚部 の力学的性状が安定するので好ましい。Further, by providing a protrusion on the outer surface of the pillar 71 of the anchor frame 7 or by providing a rough surface as required for a friction joint of a high-strength bolt, adhesion between the anchor frame 7 and the foundation concrete 3 is achieved. The effect can be enhanced and a stronger leg structure is realized. Further, as shown in FIG. 3B, if the outer surface of the lower bearing plate 72 and the contact portion of the lower washer 73 are spherical surfaces, the eccentric force does not act on the anchor bolt 4, so that the mechanical force of the leg portion is reduced. It is preferable because the properties are stable.

【0021】[0021]

【考案の効果】[Effect of the device]

本考案の第1ないし第3の柱脚構造によれば、吸収する寸法誤差は同等として 、柱脚金物のボルト孔が従来よりも小径となるので、柱脚金物の曲げ耐力が向上 する。また、柱脚金物の締付けに高力ボルトを使用することにより、締付け力の 管理が容易となり、柱脚の固定度の信頼性も向上する。 According to the first to third column base structures of the present invention, the dimensional errors to be absorbed are the same, but the bolt holes of the column base metal product have a smaller diameter than the conventional one, so that the bending resistance of the column base metal product is improved. Also, by using high-strength bolts to tighten the column pedestal, the tightening force can be easily controlled, and the reliability of the fixation of the column pedestal can be improved.

【0022】 また、本考案の第4ないし第5の柱脚構造によれば、吸収する寸法誤差がきわ めて大きくなり、柱脚の固定度の信頼性が向上するとともに、施工能率が向上す るというすぐれた効果がある。Further, according to the fourth to fifth column base structures of the present invention, the dimensional error to be absorbed becomes extremely large, the reliability of the column base fixation is improved, and the construction efficiency is improved. It has the excellent effect of

【図面の簡単な説明】[Brief description of drawings]

【図1】本考案の実施例の構成を示す断面図である。FIG. 1 is a sectional view showing the configuration of an embodiment of the present invention.

【図2】本考案に用いられる柱脚金物の一実施例の断面
図である。
FIG. 2 is a cross-sectional view of an embodiment of a column pedestal used in the present invention.

【図3】本考案の他の実施例の構成を示す断面図であ
る。
FIG. 3 is a sectional view showing the configuration of another embodiment of the present invention.

【図4】鋼製柱の柱脚構造の従来例を示す断面図であ
る。
FIG. 4 is a sectional view showing a conventional example of a column base structure of a steel column.

【図5】鋼製柱の柱脚構造の他の従来例を示す断面図で
ある。
FIG. 5 is a sectional view showing another conventional example of a column base structure of a steel column.

【図6】鋼製柱の柱脚構造のさらに他の従来例を示す断
面図である。
FIG. 6 is a sectional view showing still another conventional example of a column base structure of a steel column.

【図7】鋼製柱の柱脚構造のさらに他の従来例を示す断
面図である。
FIG. 7 is a sectional view showing still another conventional example of a column base structure of a steel column.

【符号の説明】[Explanation of symbols]

1 鋼製柱 2 柱脚金物 21 ボルト孔 3 基礎コンクリート 4 アンカーボルト 41 下部アンカーボルト 42 上部アンカーボルト 43 連結スリーブ 5 レベル調整モルタル 6 充填モルタル 7 アンカーフレーム 71 支柱 72、72' 支圧板 73、73' 座金 1 Steel Column 2 Column Base Metal 21 Bolt Hole 3 Foundation Concrete 4 Anchor Bolt 41 Lower Anchor Bolt 42 Upper Anchor Bolt 43 Connecting Sleeve 5 Level Adjustment Mortar 6 Filling Mortar 7 Anchor Frame 71 Strut 72, 72 'Bearing Plate 73, 73' Washer

Claims (5)

【実用新案登録請求の範囲】[Scope of utility model registration request] 【請求項1】 鋼製柱の下端部に取り付けた柱脚金物を
アンカーボルトによって基礎コンクリートに結合してな
る柱脚構造であって、前記アンカーボルトの全長のうち
少なくとも上部の柱脚金物のボルト孔を貫通する部分が
高力ボルトで構成されていることを特徴とする鋼製柱の
柱脚構造。
1. A column pedestal structure in which a column pedestal attached to a lower end of a steel column is connected to a foundation concrete by an anchor bolt, and at least an upper part of the column pedestal of the anchor bolt is bolted. The column base structure of the steel column, characterized in that the portion penetrating the hole is composed of high strength bolts.
【請求項2】 鋼製柱の下端部に取り付けた柱脚金物を
アンカーボルトによって基礎コンクリートに結合してな
る柱脚構造であって、前記アンカーボルトの全長のうち
上部の柱脚金物のボルト孔を貫通する部分が高力ボルト
よりなり、異形棒鋼よりなる下部アンカーボルトと連結
スリーブにより結合して構成されていることを特徴とす
る鋼製柱の柱脚構造。
2. A column base structure in which a column base metal fitting attached to a lower end portion of a steel column is connected to a foundation concrete by an anchor bolt, and a bolt hole of the upper column base metalwork of the entire length of the anchor bolt. A column base structure of a steel column, characterized in that a portion penetrating through is made of a high-strength bolt, and is constituted by connecting a lower anchor bolt made of deformed steel bar and a connecting sleeve.
【請求項3】 鋼製柱の下端部に取り付けた柱脚金物を
アンカーボルトによって基礎コンクリートに結合してな
る柱脚構造であって、前記アンカーボルトの全長のうち
少なくとも上部の柱脚金物のボルト孔を貫通する部分が
高力ボルトで構成されているとともに、前記柱脚金物の
底辺の厚みを、ボルト孔の内側から柱との接続部へ向か
ってほぼ一定の勾配により増大させたことを特徴とする
鋼製柱の柱脚構造。
3. A column pedestal structure in which a column pedestal attached to a lower end portion of a steel column is connected to a foundation concrete by an anchor bolt, wherein at least an upper column pedestal of the anchor bolt in the entire length thereof. The portion penetrating the hole is composed of high-strength bolts, and the thickness of the bottom side of the pillar base metal is increased by a substantially constant gradient from the inside of the bolt hole toward the connection portion with the pillar. Column base structure of steel columns.
【請求項4】 鋼製柱の下端部に取り付けた柱脚金物を
アンカーボルトによって基礎コンクリートに結合してな
る柱脚構造であって、前記アンカーボルトが貫通する管
状の支柱を相互に連結してなるアンカーフレームを前記
基礎コンクリート内に埋設させて構成したことを特徴と
する鋼製柱の柱脚構造。
4. A column base structure in which a column base metal fitting attached to a lower end of a steel column is connected to a foundation concrete by an anchor bolt, and tubular columns through which the anchor bolt penetrates are connected to each other. A column base structure of a steel column, wherein the anchor frame is embedded in the basic concrete.
【請求項5】 アンカーフレームの支柱の外表面に突起
を設けるなどの付着効果を増大させる手段を施した請求
項4記載の鋼製柱の柱脚構造。
5. The column base structure for a steel column according to claim 4, wherein a means for increasing the adhesion effect is provided such as providing a protrusion on the outer surface of the column of the anchor frame.
JP6686592U 1991-11-22 1992-09-25 Steel column base structure Pending JPH0561232U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
JP6686592U JPH0561232U (en) 1991-11-22 1992-09-25 Steel column base structure

Applications Claiming Priority (3)

Application Number Priority Date Filing Date Title
JP9614491 1991-11-22
JP3-96144 1991-11-22
JP6686592U JPH0561232U (en) 1991-11-22 1992-09-25 Steel column base structure

Publications (1)

Publication Number Publication Date
JPH0561232U true JPH0561232U (en) 1993-08-13

Family

ID=26408067

Family Applications (1)

Application Number Title Priority Date Filing Date
JP6686592U Pending JPH0561232U (en) 1991-11-22 1992-09-25 Steel column base structure

Country Status (1)

Country Link
JP (1) JPH0561232U (en)

Cited By (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP2003049487A (en) * 2001-08-06 2003-02-21 Sumitomo Constr Co Ltd Connection structure between steel member and concrete member
JP2013044204A (en) * 2011-08-25 2013-03-04 Asahi Kasei Construction Materials Co Ltd Construction method of rising block
JP2013241729A (en) * 2012-05-17 2013-12-05 Okabe Co Ltd Junction structure of concrete and steel frame
JP2018104945A (en) * 2016-12-26 2018-07-05 センクシア株式会社 Column base structure
JP2021123863A (en) * 2020-01-31 2021-08-30 大和ハウス工業株式会社 Vertical installation tool for anchor bolt and vertical installation method for anchor bolt

Cited By (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP2003049487A (en) * 2001-08-06 2003-02-21 Sumitomo Constr Co Ltd Connection structure between steel member and concrete member
JP2013044204A (en) * 2011-08-25 2013-03-04 Asahi Kasei Construction Materials Co Ltd Construction method of rising block
JP2013241729A (en) * 2012-05-17 2013-12-05 Okabe Co Ltd Junction structure of concrete and steel frame
JP2018104945A (en) * 2016-12-26 2018-07-05 センクシア株式会社 Column base structure
JP2021123863A (en) * 2020-01-31 2021-08-30 大和ハウス工業株式会社 Vertical installation tool for anchor bolt and vertical installation method for anchor bolt

Similar Documents

Publication Publication Date Title
JP5123378B2 (en) Seismic joint device
KR101602595B1 (en) Foundation anchor for industrial-scale machines
JP6948754B2 (en) Column base joint structure
JPH0561232U (en) Steel column base structure
JP6447777B2 (en) Column beam connection structure and steel reinforced concrete column
JP2973812B2 (en) Joint structure between steel members and concrete members
US20230110886A1 (en) Ductile anchor attachment (daa) mechanism, fuse plate system, and modified jacket
JPH10121576A (en) Fixing structure of pedestal
JP2000096834A (en) Reinforcing structure of concrete member
JP3129685B2 (en) Column / beam joint structure
US11499331B2 (en) Ductile anchor attachment (DAA) mechanism
JP3290636B2 (en) Joint structure between steel column base and foundation concrete
JP6587111B2 (en) Braces and brace mounting structure
JP3129682B2 (en) Open section column and beam joining device
JP2007205162A (en) Method of reinforcing opening of steel frame girder
JP6474575B2 (en) Brace seismic reinforcement structure and seismic reinforcement method for existing buildings
JPH09317004A (en) Steel frame column base
JP3189953B2 (en) Joint structure between steel column and foundation concrete
JPS6158620B2 (en)
JPH1025808A (en) Steel column base anchoring structure
JP3871549B2 (en) Hole down position adjustment hardware
JPH09296457A (en) Anchorage structure of anchoring material in steel frame column base
KR20000041006A (en) Steel frame structure prepared with end plate
JP2022192021A (en) Column-beam joint structure
JP2021161631A (en) Joint structure for woody shaft member