JPH0514318U - Draining structure such as balcony - Google Patents

Draining structure such as balcony

Info

Publication number
JPH0514318U
JPH0514318U JP7066891U JP7066891U JPH0514318U JP H0514318 U JPH0514318 U JP H0514318U JP 7066891 U JP7066891 U JP 7066891U JP 7066891 U JP7066891 U JP 7066891U JP H0514318 U JPH0514318 U JP H0514318U
Authority
JP
Japan
Prior art keywords
draining
longitudinal direction
balcony
wall
mounting member
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Granted
Application number
JP7066891U
Other languages
Japanese (ja)
Other versions
JP2561112Y2 (en
Inventor
実 勝相田
Original Assignee
文化シヤツター株式会社
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by 文化シヤツター株式会社 filed Critical 文化シヤツター株式会社
Priority to JP1991070668U priority Critical patent/JP2561112Y2/en
Publication of JPH0514318U publication Critical patent/JPH0514318U/en
Application granted granted Critical
Publication of JP2561112Y2 publication Critical patent/JP2561112Y2/en
Anticipated expiration legal-status Critical
Expired - Fee Related legal-status Critical Current

Links

Landscapes

  • Building Environments (AREA)

Abstract

(57)【要約】 【目的】 現場施工に際して、バルコニ−などの壁部を
構成する段階で、その取付け作業が簡単で、完成後の見
栄えも良く、また、壁部底面と一体の水平度が得られ
て、完全な水切り効果を発揮できるバルコニ−などの水
切り構造を提供しようとするものである。 【構成】 バルコニ−などの壁部底面の水切り構造にお
いて、下面に長手方向に沿って開口部1C−1が連続し
て形成されてなる長手方向に連続する形状のビーム材よ
りなる取り付け部材1Cと、上部に突条部2Aを有し下
部の少なくとも一側には水切り縁部2Bが突設されてな
る長手方向に連続する形状のビーム材よりなる水切り部
材2と、を具備し、前記取り付け部材1Cは、前記壁部
の底面にその長手方向に沿って連続して固定され、前記
水切り部材2は、その突条部2Aが前記取り付け部材1
Cの開口部1C−1に挿入されるとともにその水切り縁
部2Bの上面が前記取り付け部材1C及び壁部の底面に
当接された状態で、前記壁部の底面にその長手方向に沿
って連続して固定されていることを特徴とするバルコニ
−などの水切り構造。
(57) [Abstract] [Purpose] At the time of construction on site, at the stage of constructing a wall such as a balcony, the installation work is easy, it looks good after completion, and the levelness of the bottom of the wall is integral. The present invention is intended to provide a draining structure such as a balcony that can achieve a complete draining effect. In a draining structure of a bottom surface of a wall such as a balcony, a mounting member 1C made of a beam material having a continuous shape in the longitudinal direction, in which an opening 1C-1 is continuously formed in the lower surface along the longitudinal direction, And a draining member 2 made of a beam material having a shape continuous in the longitudinal direction and having a protruding portion 2A on the upper portion and a draining edge portion 2B protruding on at least one side of the lower portion, the mounting member 1C is continuously fixed to the bottom surface of the wall portion along the longitudinal direction thereof, and the draining member 2 has a ridge portion 2A of the mounting member 1
While being inserted into the opening 1C-1 of C and the upper surface of the draining edge portion 2B being in contact with the attachment member 1C and the bottom surface of the wall portion, the bottom surface of the wall portion is continuously formed along the longitudinal direction thereof. A drainage structure such as a balcony, which is characterized by being fixed.

Description

【考案の詳細な説明】[Detailed description of the device]

【0001】[0001]

【産業上の利用分野】[Industrial applications]

本考案は、プレハブ方式で、建て物躯体に対して装着するバルコニ−などの水 切り構造に関するものである。 The present invention relates to a prefabricated drainage structure such as a balcony to be attached to a building frame.

【0002】[0002]

【従来の技術】[Prior Art]

一般に知られているプレハブ方式のバルコニ−などは、建て物躯体の所定個所 に先付け金具を取付け、これに寸法合せをするようにして、現場で骨組みを構成 し、これに外壁仕上げをし、その時、現場で下場見切りを形造り、また、その後 、アルミ材よりなる笠木などのプレハブ部材の取付けを行なって、全体が構成さ れている。このような施工では、外壁仕上げの段階で、バルコニ−などの周壁部 の下縁に水切り用の段差を形成したり、あるいは、上記周壁部のコ−ナ−支柱間 にアングル部材などを架け渡し、打付けて、水切り用に採用している。 Generally known prefabricated balconies, etc. are equipped with pre-installed metal fittings at predetermined locations on the building frame, and the dimensions are adjusted to construct a frame on site and finish the outer wall at that time. The entire construction is completed by forming the unlisted parting line on site and then installing prefabricated members such as a headstock made of aluminum. In such construction, at the stage of finishing the outer wall, a step for draining water is formed on the lower edge of the peripheral wall part such as a balcony, or an angle member is bridged between the corner and column of the peripheral wall part. It is used for draining by tapping.

【0003】[0003]

【考案が解決しようとする課題】[Problems to be solved by the device]

しかしながら、このように、バルコニ−などの周壁部を構成した後で、水切り 構造を構成するのでは、水切り構造の形成、あるいは、取付けの際の作業性が悪 く、しかも、取付けの際のねじ頭などが外部に露呈していて、見栄えが悪く、機 能的にも、完全な水切りが困難である。 However, if the draining structure is formed after the peripheral wall such as the balcony is formed in this way, the workability at the time of forming or mounting the draining structure is poor, and the screw at the time of mounting is not required. The head etc. is exposed to the outside, it looks bad and it is difficult to completely drain water functionally.

【0004】[0004]

【考案の目的】[The purpose of the device]

本考案は上記事情に基いてなされたもので、現場施工に際して、バルコニ−な どの壁部を構成する段階で、その取付け作業が簡単で、完成後の見栄えも良く、 また、壁部底面と一体の水平度が得られて、完全な水切り効果を発揮できるバル コニ−などの水切り構造を提供しようとするものである。 The present invention was made based on the above circumstances, and at the stage of constructing a wall part such as a balcony at the time of site construction, its installation work is easy, it looks good after completion, and it is integrated with the bottom surface of the wall part. It is intended to provide a drainage structure such as a balcony that can achieve the perfect level of drainage and achieve a complete drainage effect.

【0005】[0005]

【課題を解決するための手段】[Means for Solving the Problems]

このため、本考案では、図示の実施例にも明らかにしているように、バルコニ −などの壁部底面の水切り構造において、 下面に長手方向に沿って開口部(1C−1)が連続して形成されてなる長手方向 に連続する形状のビーム材よりなる取り付け部材(1C)と、 上部に突条部(2A)を有し下部の少なくとも一側には水切り縁部(2B)が突 設されてなる長手方向に連続する形状のビーム材よりなる水切り部材(2)と、 を具備し、 前記取り付け部材(1C)は、前記壁部の底面にその長手方向に沿って連続して 固定され、前記水切り部材(2)は、その突条部(2A)が前記取り付け部材( 1C)の開口部(1C−1)に挿入されるとともにその水切り縁部(2B)の上 面が前記取り付け部材(1C)及び壁部の底面に当接された状態で、前記壁部の 底面にその長手方向に沿って連続して固定されていることを特徴としている。 Therefore, in the present invention, as is clear from the illustrated embodiment, in the draining structure of the bottom surface of the wall such as the balcony, the opening (1C-1) is continuously formed on the lower surface along the longitudinal direction. An attachment member (1C) formed of a beam material having a continuous shape in the longitudinal direction is formed, and a projection portion (2A) is provided on the upper portion, and a draining edge portion (2B) is provided on at least one side of the lower portion. A draining member (2) made of a beam material having a shape continuous in the longitudinal direction, and the mounting member (1C) is fixed to the bottom surface of the wall portion continuously along the longitudinal direction, In the draining member (2), the ridge (2A) is inserted into the opening (1C-1) of the mounting member (1C), and the upper surface of the draining edge (2B) is the mounting member (2B). 1C) and the bottom of the wall In this state, it is characterized in that it is continuously fixed to the bottom surface of the wall portion along the longitudinal direction thereof.

【0006】[0006]

【作用】[Action]

上記の構造によれば、水切り部材(2)は、壁部の底面にその長手方向に沿っ て連続して固定されたビーム材より成る取り付け部材(1C)の連続開口部(1 C−1)に、上部の突条部(2A)を挿入するようにして固定するので、その取 付け作業が容易に行なえ、また、水切り部材(2)の水切り縁部(2B)が、取 り付け部材(1C)及び壁部の底面に当接された状態で、前記壁部の底面にその 長手方向に沿って連続して固定されているので、壁部底面と一体の水平度が得ら れると共に完全な水切り効果を発揮できることになる。 According to the above structure, the draining member (2) has the continuous opening portion (1 C-1) of the mounting member (1 C) made of the beam material continuously fixed to the bottom surface of the wall portion along the longitudinal direction thereof. Since the upper protruding portion (2A) is fixed by inserting it, the mounting work can be easily performed, and the draining edge portion (2B) of the draining member (2) is fixed to the mounting member (2B). 1C) and the bottom surface of the wall portion, they are continuously fixed to the bottom surface of the wall portion along the longitudinal direction thereof, so that a levelness integral with the bottom surface of the wall portion can be obtained and perfect You will be able to exert a great draining effect.

【0007】[0007]

【実施例】【Example】

以下、本考案の水切り構造を、図示のバルコニ−の施工の実施例に基いて具体 的に説明する。図において、符号A1 、A2 、A3 は、Cチャンネル断面の軽量 形鋼を素材とした骨組み部材1A、1B、1D及び同様の骨組み部材より成る取 り付け部材1Cよりなる骨組みユニットである。この取り付け部材1Cの下面に は、開口部1C−1が連続して形成されている。上記骨組み部材1Aは上記骨組 みユニットの側面縦枠部を構成し、上記骨組み部材1Bは上記骨組みユニットの 上場の枠部を構成し、上記骨組み部材としての取り付け部材1Cは同じく下場の 枠部を構成し、更に、上記骨組み部材1Dは中間の縦桟部を構成する。なお、要 すれば、上記骨組みユニットの内側に筋交い1Eを備えてもよい。このような長 方形の骨組みユニットA1 、A2 、A3 、を、例えば、上下二段に組合わせて、 また、互いに直交して組合わせて、ボルト・ナットの結合手段を用いて一つのバ ルコニ−の骨組みAを構成するのである。この骨組みAは、ボルト・ナットの取 付手段によって、建て物躯体に対して取付けられる(図示せず)。 Hereinafter, the draining structure of the present invention will be specifically described based on an embodiment of the construction of the balcony shown in the drawings. In the figure, reference numerals A1, A2 and A3 are skeleton units composed of skeleton members 1A, 1B and 1D made of lightweight steel having a C-channel cross section and an attachment member 1C made of the same skeleton members. An opening 1C-1 is continuously formed on the lower surface of the mounting member 1C. The skeleton member 1A constitutes a side surface vertical frame portion of the skeleton unit, the skeleton member 1B constitutes a listed frame portion of the skeleton unit, and the mounting member 1C as the skeleton member also constitutes a listed frame portion. Further, the frame member 1D constitutes an intermediate vertical rail portion. If necessary, a brace 1E may be provided inside the skeleton unit. Such rectangular skeleton units A1, A2, A3 are combined, for example, in two stages, upper and lower, and also orthogonally mutually, and one balcony is formed by using bolt and nut coupling means. The skeleton A is constructed. The skeleton A is attached to the building body by bolt and nut attachment means (not shown).

【0008】 このようにして構成された骨組みA(図1参照)に対しては、次に、下場見切 り部材Bが取付けられる。この実施例では、図5及び図6に詳細に示すように、 上記下場見切り部材Bは、アルミ製の引き抜き部材より成る水切り部材2で構成 されている。この、水切り部材2は、略凸形の中空ビ−ム材よりなり、上部の突 条部2Aと下部両側の水切り縁部2Bを有し、この上部の突条部2Aが、上下に 組み付けられた骨組みユニットA1 、A2 の内、下側の骨組みユニットA2 の骨 組み部材としての取り付け部材1Cの開口部1C−1内及び各骨組みユニットA 3 の下側の骨組み部材としての取り付け部材1Cの開口部1C−1内に挿入され 、この挿入状態で互いに重合される突条部2Aの上板と取り付け部材1Cの中間 板とを、ボルト・ナットの結合手段3で連結することにより、骨組みAに組み付 けられる。この場合、上記水切り部材2の水切り縁部2Bは、取り付け部材1C 及び壁部の底面に当接された状態で少なくともバルコニ−の周壁部の外側に向け て張り出すように設けられている。 尚、上記水切り部材2は、略逆T形の非中空形状としてもよく、また、下部の一 側にのみ水切り縁部2Bを設けた略L形としてもさしつかえない。[0008] Next, the undercut parting member B is attached to the skeleton A (see FIG. 1) thus configured. In this embodiment, as shown in detail in FIG. 5 and FIG. 6, the undercut parting member B is composed of a draining member 2 made of an aluminum drawing member. The draining member 2 is made of a substantially convex hollow beam material and has an upper protruding portion 2A and lower draining edge portions 2B. The upper protruding portions 2A are assembled vertically. Of the skeletal units A1 and A2, the opening of the mounting member 1C as a skeletal member of the lower skeletal unit A2 and the opening of the mounting member 1C as a lower skeletal member of each skeletal unit A3. By connecting the upper plate of the ridge portion 2A and the intermediate plate of the mounting member 1C which are inserted into the portion 1C-1 and overlap each other in this inserted state by the bolt / nut coupling means 3, the skeleton A is connected. It can be assembled. In this case, the draining edge portion 2B of the draining member 2 is provided so as to project toward at least the outer side of the peripheral wall portion of the balcony while being in contact with the mounting member 1C and the bottom surface of the wall portion. The draining member 2 may be a substantially inverted T-shaped non-hollow shape, or may be a substantially L-shaped one in which the draining edge portion 2B is provided only on one side of the lower portion.

【0009】 次に、上記下場見切り部材B(水切り部材2)に載せるようにして、上記骨組 みAの内外周壁部に合板などの下地パネルCをねじ結合具4で取付ける(図2お よび図5、6参照)。その後、上記骨組みAの正面部の内側下部および建て物躯 体の正面下部(開口部下場)にそれぞれ、先付け根太掛け部材5を取付け、その 間に根太6を架設して、これに簀の子7を載せ、バルコニ−の床部Dを構成する 。Next, the base panel C such as plywood is attached to the inner and outer peripheral wall portions of the skeleton A by the screw connector 4 so as to be placed on the lower parting parting member B (draining member 2) (FIG. 2 and FIG. 2). 5 and 6). Then, the front joist hanging members 5 are attached to the inside lower part of the front part of the skeleton A and the lower part of the front part of the building frame (opening area listing), respectively, and the joists 6 are installed between them, and the sash 7 is attached to this. And place the floor D of the balcony.

【0010】 また、上記骨組みAの上縁には、上記下地パネルCを覆うようにして、笠木E が、ねじの結合具8で取付けられる(図3および図5参照)。この実施例では、 上記笠木Eは、その笠木部材9の内側に、上記骨組みAの上縁に載せられる笠木 ブラケット10を備えており、また、上記笠木部材9の上に支柱部材11を介し て手摺り部材12を装備している。Further, a headstock E 1 is attached to the upper edge of the frame A so as to cover the base panel C with a screw connector 8 (see FIGS. 3 and 5). In this embodiment, the headstock E is provided with a headstock bracket 10 mounted on the upper edge of the frame A inside the headboard member 9, and also on the headboard member 9 via a column member 11. The handrail member 12 is equipped.

【0011】 そして、最後に、上記下地パネルCの表面に仕上げ壁面Fを設けるのである。 なお、仕上げ壁面を、コンクリ−ト、漆喰などの材料で構成する場合には、通常 のように、下地パネルCの表面にラスを張設して、コンクリ−ト、漆喰などの保 持を確実にするとよい。Finally, a finishing wall surface F is provided on the surface of the base panel C. When the finished wall surface is made of concrete, plaster, etc., a lath is stretched over the surface of the base panel C as usual to ensure that concrete, plaster, etc. are retained. It is good to set.

【0012】 このような施工手順でバルコニ−を構成にすることで、バルコニ−の骨組みの 段階で、水切り部材としての下場見切り部材を、骨組み部材に取付けられるから 、取付け精度が高く、また、ねじ取付け位置などを気にすることなく、取付け作 業ができ、作業がしやすい。また、その後の仕上げ段階で、寸法や位置のずれが なく、ねじ取付け部などが外部から見えず、見栄えが良くなる。また、このよう に、水切り構造を構成することは、本格建築で見られるような完全な水切り構造 に匹敵し、プレハブ構造でありながら、完全な水切り構造として満足できる。 上記、本考案に係るバルコニ−などの水切り構造は、その他、例えばビル建造 物の開口上面の垂れ壁底面の水切り構造としても用いる事が出来る。By constructing the balcony by such a construction procedure, since the unsealed parting member as the draining member can be attached to the frame member at the stage of the frame of the balcony, the installation accuracy is high and the screw is used. The installation work can be done without worrying about the installation position and the work is easy. Also, in the subsequent finishing stage, there is no deviation in size or position, and the screw mounting part, etc. are not visible from the outside, and the appearance is improved. In addition, constructing the drainage structure in this way is comparable to the complete drainage structure seen in full-scale construction, and is satisfactory as a complete drainage structure even though it is a prefabricated structure. The above-described drainage structure such as a balcony according to the present invention can also be used as a drainage structure on the bottom surface of the hanging wall on the upper surface of the opening of a building construction, for example.

【0013】[0013]

【考案の効果】[Effect of the device]

本考案は、以上詳述したように、バルコニ−などの壁部下面を構成する水切り 構造において、水切り部材(2)を長手方向に沿って連続するビ−ム材により構 成すると共に、壁部の底面にその長手方向に沿って連続して固定されたビーム材 より成る取り付け部材(1C)の連続開口部(1C−1)に、水切り部材(2) の上部の突条部(2A)を挿入するようにして固定するので、その取付け作業が 容易に行なえ、また、水切り部材(2)の水切り縁部(2B)が、取り付け部材 (1C)及び壁部の底面に当接された状態で、前記壁部の底面にその長手方向に 沿って連続して固定されているので、壁部底面と一体の水平度が得られると共に 完全な水切り効果を発揮できることになる。 As described in detail above, the present invention provides a draining structure that constitutes the lower surface of a wall such as a balcony, in which the draining member (2) is made of a beam material that is continuous in the longitudinal direction, and At the continuous opening (1C-1) of the mounting member (1C) made of a beam material continuously fixed to the bottom surface of the drainage member (2), the protrusion (2A) above the draining member (2) is attached. Since it is fixed by inserting it, the mounting work can be easily performed, and the draining edge (2B) of the draining member (2) is in contact with the mounting member (1C) and the bottom surface of the wall. Since it is continuously fixed to the bottom surface of the wall portion along the longitudinal direction thereof, it is possible to obtain the levelness integral with the bottom surface of the wall portion and to achieve a complete draining effect.

【図面の簡単な説明】[Brief description of drawings]

【図1】本考案の構造を適用したバルコニ−を、施工順
序に従って説明するための骨組みの概略構成図である。
FIG. 1 is a schematic configuration diagram of a skeleton for explaining a balcony to which a structure of the present invention is applied according to a construction order.

【図2】同じく、下地パネル取付けの概略構成図であ
る。
FIG. 2 is likewise a schematic configuration diagram of mounting a base panel.

【図3】同じく、笠木取付けの概略構成図である。[Fig. 3] Similarly, it is a schematic configuration diagram of mounting a headboard.

【図4】同じく、仕上げ壁面の施工の概略構成図であ
る。
FIG. 4 is likewise a schematic configuration diagram of construction of a finished wall surface.

【図5】本考案の要部を示す縦断側面図である。FIG. 5 is a vertical sectional side view showing an essential part of the present invention.

【図6】本考案の要部を示す拡大縦断側面図である。FIG. 6 is an enlarged vertical side view showing the main part of the present invention.

【符号の説明】[Explanation of symbols]

A 骨組み、 A1 、A2 、A3 骨組みユニッ
ト、 B 下場見切り部材、 C 下地パネ
ル、 D 床部、 E 笠木、 F仕上げ壁面、
1A、1B、1D 骨組み部材、1C 取り付け
部材、 2 水切り部材、 2A 突条部、
2B 水切り縁部、3 結合手段、 4 結合
具、 5先付け根太掛け部材、 6根太、 7 簀
の子、 8 結合具、 9 笠木部材、 10笠
木ブラケット、 11 支柱、 12 手摺り部
A skeleton, A1, A2, A3 skeleton unit, B unlisted parting member, C base panel, D floor, E heading, F finished wall,
1A, 1B, 1D frame members, 1C mounting members, 2 draining members, 2A ridges,
2B draining edge part, 3 connecting means, 4 connecting tool, 5 tip joist hanging member, 6 joist, 7 cage child, 8 connecting tool, 9 head board member, 10 head board bracket, 11 props, 12 handrail member

Claims (1)

【実用新案登録請求の範囲】[Scope of utility model registration request] 【請求項1】 バルコニ−などの壁部底面の水切り構造
において、 下面に長手方向に沿って開口部(1C−1)が連続して
形成されてなる長手方向に連続する形状のビーム材より
なる取り付け部材(1C)と、 上部に突条部(2A)を有し下部の少なくとも一側には
水切り縁部(2B)が突設されてなる長手方向に連続す
る形状のビーム材よりなる水切り部材(2)と、 を具備し、 前記取り付け部材(1C)は、前記壁部の底面にその長
手方向に沿って連続して固定され、前記水切り部材
(2)は、その突条部(2A)が前記取り付け部材(1
C)の開口部(1C−1)に挿入されるとともにその水
切り縁部(2B)の上面が前記取り付け部材(1C)及
び壁部の底面に当接された状態で、前記壁部の底面にそ
の長手方向に沿って連続して固定されていることを特徴
とするバルコニ−などの水切り構造。
1. A drainage structure for a bottom surface of a wall such as a balcony, comprising a beam material having a continuous shape in the longitudinal direction, in which an opening (1C-1) is continuously formed on the lower surface along the longitudinal direction. A draining member composed of a mounting member (1C) and a beam member having a continuous shape in the longitudinal direction, which has a protruding portion (2A) on the upper portion and a draining edge portion (2B) protruding on at least one side of the lower portion (2) and, the mounting member (1C) is continuously fixed to the bottom surface of the wall portion along the longitudinal direction thereof, and the draining member (2) has its ridge portion (2A). Is the attachment member (1
C) is inserted into the opening (1C-1) and the top surface of the draining edge (2B) is in contact with the attachment member (1C) and the bottom surface of the wall portion. A draining structure such as a balcony, which is continuously fixed along its longitudinal direction.
JP1991070668U 1991-08-09 1991-08-09 Drainage structure such as balcony Expired - Fee Related JP2561112Y2 (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
JP1991070668U JP2561112Y2 (en) 1991-08-09 1991-08-09 Drainage structure such as balcony

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
JP1991070668U JP2561112Y2 (en) 1991-08-09 1991-08-09 Drainage structure such as balcony

Publications (2)

Publication Number Publication Date
JPH0514318U true JPH0514318U (en) 1993-02-23
JP2561112Y2 JP2561112Y2 (en) 1998-01-28

Family

ID=13438280

Family Applications (1)

Application Number Title Priority Date Filing Date
JP1991070668U Expired - Fee Related JP2561112Y2 (en) 1991-08-09 1991-08-09 Drainage structure such as balcony

Country Status (1)

Country Link
JP (1) JP2561112Y2 (en)

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP2012149417A (en) * 2011-01-18 2012-08-09 Sekisui House Ltd Ventilation structure of hanging wall at building outer wall part

Families Citing this family (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP4625821B2 (en) * 2007-03-15 2011-02-02 ミサワホーム株式会社 Balcony floor support structure

Citations (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPS5732402U (en) * 1980-07-31 1982-02-20

Patent Citations (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPS5732402U (en) * 1980-07-31 1982-02-20

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP2012149417A (en) * 2011-01-18 2012-08-09 Sekisui House Ltd Ventilation structure of hanging wall at building outer wall part

Also Published As

Publication number Publication date
JP2561112Y2 (en) 1998-01-28

Similar Documents

Publication Publication Date Title
JPH0514318U (en) Draining structure such as balcony
JP2556409Y2 (en) Attachment structure such as Kasagi
JPH0126838Y2 (en)
JP2002201714A (en) Unit building
JP2806276B2 (en) Sleeve wall balcony and construction method
JPH1072927A (en) Decorative structure for corner column
JP2003232075A (en) House having extended eaves
JPH0340976Y2 (en)
JPS6349443Y2 (en)
JP3284566B2 (en) Balcony and its assembly method
JP2763058B2 (en) Railing wall support structure
JP2618559B2 (en) Joint structure of unit with handrail wall
JPH0726487Y2 (en) Eave ceiling mounting structure
JP2001065049A (en) Roof balcony unit
JP2517183B2 (en) Building outer structure
JPH067145Y2 (en) Wall panels
JPH10331250A (en) Structure of balcony and corridor, and floor board therefor
JPH01116158A (en) Method of rebuilding existing building, roof of which is remodelled previously
JPH042266Y2 (en)
JP3154791B2 (en) Structure and method for mounting decorative panel on roof structure
JPH0520803Y2 (en)
JP2705866B2 (en) Construction method of roof structure
JPH09195374A (en) Accessory building
JPH03275863A (en) Wooden building
JPH0377901B2 (en)

Legal Events

Date Code Title Description
LAPS Cancellation because of no payment of annual fees