JPH0497010A - Measurement of void water pressure in ground by concurrent formation of multistage seal layer - Google Patents

Measurement of void water pressure in ground by concurrent formation of multistage seal layer

Info

Publication number
JPH0497010A
JPH0497010A JP2215515A JP21551590A JPH0497010A JP H0497010 A JPH0497010 A JP H0497010A JP 2215515 A JP2215515 A JP 2215515A JP 21551590 A JP21551590 A JP 21551590A JP H0497010 A JPH0497010 A JP H0497010A
Authority
JP
Japan
Prior art keywords
water pressure
sealing material
pipe
granular solid
material layer
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Granted
Application number
JP2215515A
Other languages
Japanese (ja)
Other versions
JPH0753970B2 (en
Inventor
Norihisa Matsumoto
松本 徳久
Yoshikazu Yamaguchi
嘉一 山口
Yoshihiko Umeda
梅田 美彦
Toshikazu Miyauchi
宮内 鋭弌
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Minister for Public Works for State of New South Wales
JDC Corp
National Research and Development Agency Public Works Research Institute
Original Assignee
Minister for Public Works for State of New South Wales
JDC Corp
Public Works Research Institute Ministry of Construction
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Minister for Public Works for State of New South Wales, JDC Corp, Public Works Research Institute Ministry of Construction filed Critical Minister for Public Works for State of New South Wales
Priority to JP2215515A priority Critical patent/JPH0753970B2/en
Publication of JPH0497010A publication Critical patent/JPH0497010A/en
Publication of JPH0753970B2 publication Critical patent/JPH0753970B2/en
Anticipated expiration legal-status Critical
Expired - Fee Related legal-status Critical Current

Links

Landscapes

  • Investigation Of Foundation Soil And Reinforcement Of Foundation Soil By Compacting Or Drainage (AREA)

Abstract

PURPOSE:To form seal layers concurrently on solid granule layers laminated in a multistage form by a method in which water conveyance ports are formed in mutually divided sections of a long tube, water pressure meters and a vertical leading short tube are provided, and a sealant is injected through the vertical leading short tube from the outside. CONSTITUTION:Water conveyance ports 5 are formed in the divided sections of a long tube 1f, the upper and lower parts of the ports 5 are closed with stoppers, and water pressure meters 1a, 1b, and 1c are set in it. A vertical leading short tube 7 is set near the ports 5 to form a water pressure measuring tube 1. The tube 1 is inserted into a bored hole H, and a sealant-injecting pipe 2 is inserted into the hole H. Solid granule layers 8a, 8b, 8c, and 8d are laminated through the pipe 2 and a sealant is concurrently injected to the laminate layers. The constructing period can thus be greatly shortened and void water pressure can be measured efficiently.

Description

【発明の詳細な説明】 (産業上の利用分野) 本発明は、地盤の状況を判断するのに必要とされている
地下水圧の分布を知るため、当該地盤の各種深さにおけ
る夫々の水圧(間隙水圧)を測定する方法に関する。
DETAILED DESCRIPTION OF THE INVENTION (Industrial Application Field) In order to know the distribution of groundwater pressure required to judge the ground condition, the present invention is based on the water pressure ( pore water pressure).

(従来の技術) ダムの基礎や切土斜面の安定、地滑りの防止等の調査に
おいては、地盤の強度や変形に関する性質を理解する事
、及び地下の間隙水圧の分布とその経時変化を知る事は
、極めて重要である。
(Conventional technology) In investigating the stability of dam foundations and cut slopes, prevention of landslides, etc., it is necessary to understand the properties related to the strength and deformation of the ground, and to know the distribution of underground pore water pressure and its changes over time. is extremely important.

深い地盤内の間隙水圧の分布とその経時変化を測定する
ため、従来は1、深さが異なる多数のボーリング孔を削
孔し、該ボーリング孔の各々に間隙水圧計を設置して間
隙水圧の測定を行っていた。
In order to measure the distribution of pore water pressure in deep ground and its change over time, the conventional method was to drill a number of boreholes with different depths, install a pore water pressure gauge in each of the boreholes, and measure the pore water pressure. I was taking measurements.

しかし、この方法では、多数のボーリング孔の削孔や、
その各々に間隙水圧計を設置すること等に多大な時間お
よび経費を必要とするという欠点がある。
However, this method requires drilling a large number of boreholes,
The drawback is that it requires a great deal of time and expense to install a pore water pressure gauge in each of them.

そこで、と記の難点を解消するため、既に第3図に示さ
れているような測定方法も実施されている。
Therefore, in order to solve the above-mentioned difficulties, a measuring method as shown in FIG. 3 has already been implemented.

上記の方法は、地盤Aに削孔したボーリング孔d内にあ
って、砂などによるフィルター材層すと1モルタルやセ
メントミルク等によるシール材層Cとを交互に、各複数
層だけ積層すると共に。
In the above method, a filter material layer made of sand or the like and a sealing material layer C made of mortar, cement milk, etc. are alternately laminated in a borehole d drilled in the ground A. .

上記フィルター材層す中である所定位置に水圧計dを夫
々埋設し、これらの水圧計dのリード線eを、上記のフ
ィルター材層b、シール材層Cを介して地上側へ導出し
、当該リード線eを図示しない計測器に接続することで
、当該計測器によって所定深さに配置された各水圧計d
の測定値を知るようにしたものである。
Water pressure gauges d are buried at predetermined positions in the filter material layer, and the lead wires e of these water pressure gauges d are guided to the ground side via the filter material layer b and the sealing material layer C, By connecting the lead wire e to a measuring device (not shown), each water pressure gauge d placed at a predetermined depth by the measuring device
It is designed to know the measured value of.

従って、この方法によれば、多数のボーリング孔を削孔
したり、その各々に間隙水圧計を設置する等の必要がな
くなり、時間および軽費が節約される。
Therefore, according to this method, there is no need to drill a large number of boreholes or install a pore water pressure gauge in each of them, thereby saving time and cost.

(発明が解決しようとする課題) しかし、上記の従来技術においては、フィルター材層す
およびシール材層Cをボーリング孔aへ交互に落し込み
ながら水圧計dを埋設していくので、フィルター材層す
およびシール材層Cの充填深度を正確に求めることが不
可部であり、従って水圧計dの埋設深度を正確に決定す
る事ができない、という問題がある。
(Problem to be Solved by the Invention) However, in the above-mentioned prior art, since the water pressure gauge d is buried while the filter material layer and the sealing material layer C are alternately dropped into the borehole a, the filter material layer Therefore, there is a problem in that it is impossible to accurately determine the filling depth of the water pressure gauge d and the filling depth of the sealing material layer C, and therefore, the buried depth of the water pressure gauge d cannot be determined accurately.

また、ボーリング孔a内の地盤における割れ目等にシー
ル材層Cを形成するためのシール材が浸透してしまうと
、その充填量が不足してしまい、この結果シール材層C
が所定の深度まで充填されなくなってしまうことになる
Furthermore, if the sealing material for forming the sealing material layer C penetrates into cracks in the ground within the borehole a, the amount of filling will be insufficient, and as a result, the sealing material layer C will be insufficient.
will not be filled to a predetermined depth.

さらに、各フィルター材層すに埋設された水圧計dのリ
ード線eが所謂「水みち」となり、この結果上記各層す
におけるシール材層による遮断状態が破れて、間隙水(
地下水)が漏出してしまうので 各層の間隙水圧を正確
に測定することが出来なくなる。
Furthermore, the lead wire e of the water pressure gauge d buried in each filter material layer becomes a so-called "water path", and as a result, the isolation state by the seal material layer in each layer is broken, and pore water (
(groundwater) leaks out, making it impossible to accurately measure pore water pressure in each layer.

これに加えて、フィルター材層すやシール材層Cの埋設
時(充填時)或いは埋設深度の確認作業の際に、水圧計
d及びそのリート線を損傷するという問題がある。
In addition to this, there is a problem that the water pressure gauge d and its Riet wire may be damaged when burying (filling) the filter material layer or the sealing material layer C or when confirming the embedding depth.

本願は、上記従来法の難点に鑑み検討されたもので、本
願に係る多段シール材層の同時形成による地盤内の間隙
水圧測定方法によるときは、予め所定の位置に水圧測定
が可能なるよう複数の水圧計か夫々分離された独立の状
態で内蔵されている水圧測定管を用意しておき、これを
、地盤の所定箇所にあって削孔したボーリング孔に挿入
することにより、所要複数の水圧計につき、その位置(
深さ)決めを極めて正確に行い得るようにして、要求さ
れた深さにおける間隙水圧の測定を可能とするだけでな
く、上記ボーリング孔に供与されるフィルター材とシー
ル材の充填深度と上記水圧計の埋設深度とを正確に求め
る事ができるようにして、従来技術の欠点を解消し、ざ
らに、L記水圧計のり−ト線は水圧測定管内を通して導
出されるようにすることで、当該リート線の損傷をなく
しその耐久性をも良好にするのはもちろん、前記の如く
リード線か水みちとなるようなことを完全に解消してし
まうことを、第1の目的としている。
The present application was studied in view of the drawbacks of the conventional method described above, and when using the method of measuring pore water pressure in the ground by simultaneous formation of multi-stage sealing material layers according to the present application, multiple By preparing water pressure measuring pipes that are built into separate and independent water pressure gauges, and inserting them into boreholes drilled at predetermined locations in the ground, it is possible to measure multiple water pressures as required. per meter, its position (
Depth) can be very accurately determined, making it possible not only to measure the pore water pressure at the required depth, but also to determine the filling depth of the filter material and sealing material applied to the borehole and the water pressure. By making it possible to accurately determine the depth at which the water pressure gauge is buried, the drawbacks of the prior art are overcome, and more specifically, by making it possible to derive the gauge line L through the water pressure measuring pipe, The first objective is not only to eliminate damage to the lead wire and improve its durability, but also to completely eliminate the problem of the lead wire becoming a water channel as described above.

さらに、本発明にあって重要である第2の目的は、上記
したシール材によるシール材層を、単に合成樹脂材の供
給により形成することなく、予め供与しておいた礫など
による粒状固形材層に、合成樹脂材を注入することで形
成するようにし、これにより、使用する合成樹脂材の量
を低減することで、当該合成樹脂材が硬化時に放出する
熱量を可及的に少なくし、当該硬化時の温度上昇による
水圧計やそのリート線の機能損傷といったトラブルの発
生を阻止すると共に、この種の測定を安価に行い得るよ
うにするだけでなく、その作業時間をも大幅に短縮しよ
うとすることにある。
Furthermore, the second objective of the present invention is to form the sealing material layer using the above-mentioned sealing material by not simply supplying a synthetic resin material, but by using a granular solid material such as gravel provided in advance. The layer is formed by injecting a synthetic resin material, thereby reducing the amount of synthetic resin material used and minimizing the amount of heat released by the synthetic resin material during curing. In addition to preventing troubles such as functional damage to the water pressure gauge and its Riet wire due to temperature rise during curing, it will not only be possible to perform this type of measurement at a low cost, but it will also significantly shorten the work time. It is to do so.

そして1本発明における第3の目的は、上記のボーリン
グ孔に挿入した水圧測定管に複数個の緩装連通端管を付
設しておくと共に、シール材注入用バイブをも同上ボー
リング孔に挿入しておき、予め当該ボーリング孔内の適
所に砂などによるファイルター材層と、砂礫等による粒
状固形材層を形成した上で、上記シール材注入用パイプ
から合成樹脂によるシール材を圧送することで、何段に
も形成された各粒状固形材層内へ一度にシール材を供給
可能となし、これにより、当該間隙水圧の測定を容易に
して効率よく、短時間に行い得るようにしようとするこ
とである。
A third object of the present invention is to attach a plurality of loosely connected end pipes to the water pressure measuring pipe inserted into the borehole, and also insert a sealing material injection vibrator into the borehole. A filter material layer made of sand or the like and a granular solid material layer made of gravel or the like are formed in advance at appropriate locations in the borehole, and then a synthetic resin sealant is pumped through the sealant injection pipe. , it is possible to supply a sealing material into each layer of granular solid material formed in multiple stages at once, thereby making it possible to easily measure the pore water pressure, efficiently, and in a short time. That's true.

(課題を解決するための手段) 本願は上記の目的を達成するため、地盤の所要箇所に削
設したボーリング孔中には、長尺管体の互いに区分され
た箇所に夫々の導水口を開口すると共に、各水圧計が内
蔵され、かつ、これら水圧計のリード線が当該長尺管体
内より導出され、かつ、所要複数個の寝装連通短管を付
設してなる水圧測定管と、上下配置にて所要数個の供給
口が開成されたシール材注入用パイプとを挿入した後、
上記ボーリング孔内にあって、砂などによるフィルター
材層は、前記導水口を被装し、かつ上記寝装連通短管が
貫通する箇所に形成し、その他の箇所には、前記シール
材注入用パイプの各注入口が開口するよう砂礫等による
とき粒状固形材層を形成することにより、上記寝装連通
短管の上下端口を夫々上下の当該粒状固形層に開口させ
、その後、前記のシール材注入用パイプを介して合成樹
脂によるシール材を圧送することにより、当該シール材
を前記の各供給口から夫々の粒状固形層へ注入させてシ
ール材層を形成し、上記リード線を接続した地上側にお
ける計測器によって、各深度における前記各水圧計の測
定値が測知されるようにしたことを特徴とする多段シー
ル材層の同時形成による地盤内の間隙水圧測定方法を提
供しようとするものである。
(Means for Solving the Problems) In order to achieve the above object, the present application has water inlets opened at mutually separated parts of the long pipe body in boreholes drilled at required locations in the ground. At the same time, each water pressure gauge is built in, and the lead wires of these water pressure gauges are led out from the long pipe, and a water pressure measuring pipe is provided with a plurality of required bedding communication short pipes, and the upper and lower pipes are connected to each other. After inserting the sealant injection pipe with the required number of supply ports opened,
A filter material layer made of sand or the like is formed in the borehole at a location that covers the water inlet and is penetrated by the bedding communication short pipe, and a layer of filter material made of sand or the like is formed in the other locations for injecting the sealing material. By forming a layer of granular solid material using sand and gravel so that each injection port of the pipe opens, the upper and lower end ports of the bedding communicating short pipe are opened to the upper and lower granular solid layers, respectively, and then the sealing material is By force-feeding a synthetic resin sealing material through an injection pipe, the sealing material is injected from each supply port into each granular solid layer to form a sealing material layer. To provide a method for measuring pore water pressure in the ground by simultaneously forming multi-stage sealing material layers, characterized in that the measured values of each of the water pressure gauges at each depth are measured by a measuring device on the side. It is.

(作   用) 本発明に係る地盤内の間隙水圧測定方法によるときは、
水圧測定管の所定位置に、予め所要複数個の水圧計が隔
離状態で内蔵されているから、これを所定深さのボーリ
ング孔に挿入立置することで、各水圧計の地盤内におけ
る深さが正確に特定され、これにより要求通りの地下位
置における間隙水圧を測定できることとなる。
(Function) When using the method for measuring pore water pressure in the ground according to the present invention,
A plurality of water pressure gauges are pre-installed in isolation at predetermined positions in the water pressure measurement pipe, so by inserting and standing them in a borehole at a predetermined depth, the depth of each water pressure gauge in the ground can be adjusted. is accurately identified, which makes it possible to measure the pore water pressure at the required underground location.

また、水位測定管をボーリング孔に挿入するだけで 水
位計のり一ト線は水位測定管内から地上側へ導出される
こととなるので、当該リード線はボーリング孔内にあっ
て、その後流されるフィルター材層、シール材層とは全
く無関係となるから、これらによって損傷を受けること
も同上諸材中に水みちを形成することもない。
In addition, just by inserting the water level measuring pipe into the borehole, the water level gauge lead wire will be led out from inside the water level measuring pipe to the ground side, so the lead wire will be inside the borehole and the filter that will be flowed afterwards. Since it is completely unrelated to the material layer and the sealing material layer, it will not be damaged by them and will not form water channels in the materials mentioned above.

次に、フィルター層が水圧測定管の導水口と寝装連通短
管とに臨装して積層され、当該縦装連通短管の上下端口
が1粒状固形材層に開口されるようになるが 当該フィ
ルター材層を形成するための位置決めに際しても、上記
導入口、寝装連通短管の位置は特定されているので、ボ
ーリング孔内におけるフィルター材層や粒状固形材層の
深さを、スケールを用いたり、音、光などを用いて測長
することで、導入口から外れてしまったり、寝装連通短
管との相対関係位置が符合しなくなったりすることなく
、正確な位置に上記フィルター材層と粒状固形材層を形
成することかでさる。
Next, a filter layer is stacked on the water inlet of the water pressure measurement pipe and the bedding communication short pipe, and the upper and lower end ports of the vertical communication short pipe are opened to one granular solid material layer. When determining the position for forming the filter material layer, the positions of the inlet and bedding communication short pipe are specified, so the depth of the filter material layer and granular solid material layer in the borehole is determined by adjusting the scale. By measuring the length of the filter material using sound, light, etc., the filter material can be placed in the correct position without coming off the inlet or with the relative position of the bedding communication short pipe not matching. It is possible to form a layer and a layer of granular solid material.

さらに、シール材層の形成に際し、粒状固形材層内へ合
成樹脂材を注入することで、これが粒状固形材間や粒状
固形材とボーリング孔の内壁との間隙に浸入して、これ
らの空隙部が充填され、これ番こより透水係数の小さな
上水箇所を形成できるだけでなく、上記空隙部だけに合
成樹脂材を供給すればよいから、硬化時における発熱量
は少なくなり、合成樹脂材だけの場合には110℃まで
昇温したものを、25℃程度までに抑制することができ
、水圧計やリード線への熱的影響を無視することが可能
となる。
Furthermore, when forming the sealing material layer, by injecting the synthetic resin material into the granular solid material layer, this material infiltrates between the granular solid materials and into the gaps between the granular solid materials and the inner wall of the borehole, causing these voids to become injected into the granular solid material layer. Not only is this possible to form a water supply area with a smaller hydraulic permeability than this, but also because the synthetic resin material only needs to be supplied to the void, the amount of heat generated during curing is reduced, and when using only synthetic resin material. In this case, the temperature increased to 110°C, but it can be suppressed to about 25°C, making it possible to ignore the thermal influence on the water pressure gauge and lead wires.

しかも、本発明では予めボーリング孔内に挿入されたシ
ール材注入用パイプには、適所に供給口が開設されてい
るから、当該シール材注入用パイプにより圧送される合
成樹脂材としてのシール材は、−度に多段である各粒状
固形材層内に注入されることとなり、この際各粒状固形
材層は縦装連通短管により連通状態となっていることか
ら、シール材の注入に際し粒状固形材層の排気も支障な
く行われ、かつ、当該縦装連通短管を介して、一方の粒
状固形材層から他の粒状固形材層へシール材が流入し得
るので、注入未完な空所が残置されることなく、しかも
短時間に合成樹脂たるシール材の注入が容易に完了され
ることとなる。
Furthermore, in the present invention, the sealing material injection pipe inserted into the borehole in advance has a supply port at an appropriate location, so that the sealing material as a synthetic resin material that is pumped through the sealing material injection pipe is The granular solid material is injected into each multi-stage granular solid material layer at the same time, and at this time, each granular solid material layer is in a state of communication through a vertically connected short pipe. The material layer can be evacuated without any problem, and the sealing material can flow from one granular solid material layer to the other granular solid material layer via the vertically connected short pipe, so that there are no gaps where the injection has not been completed. Injection of the sealing material, which is a synthetic resin, can be easily completed in a short time without leaving any residue behind.

(実 施 例) 以下、本発明につき第1図と第2図を参照して、その1
実施例についてこれを説明する。
(Example) Hereinafter, with reference to FIGS. 1 and 2, part 1 of the present invention will be described.
This will be explained with reference to an example.

当該地盤内の間隙水圧測定方法の実施に際しては、第1
図(a)に示すように、先ず、測定の対象となる地盤G
にボーリング孔Hを削孔し、別途用意した水圧測定管1
とシール材注入用パイプ2とを、ボーリング孔H内にあ
って前者は中央部内に、後者はその傍側に挿入して、こ
れを前者では孔底箇所H°に立置し、後者では孔底筒所
H゛から離して緩装するのである。
When implementing the pore water pressure measurement method in the ground, the first
As shown in Figure (a), first, the ground G to be measured
A bore hole H was drilled in the water pressure measuring pipe 1 prepared separately.
and sealing material injection pipe 2 are inserted into the borehole H, the former in the center and the latter on the side. It is loosely mounted away from the bottom tube place H.

ここで、水圧測定管lには複数の水圧計1a、lb。Here, the water pressure measuring tube l includes a plurality of water pressure gauges 1a and lb.

1cが所定位置に内蔵されていることから、上記のボー
リング孔Hの深さと水圧測定管1の長さからして、夫々
の水圧計1a、lb、lcの深度を所要位置に決するこ
とができる。
1c is built in at a predetermined position, the depth of each water pressure gauge 1a, lb, lc can be determined at the desired position based on the depth of the borehole H and the length of the water pressure measuring pipe 1. .

これらの水圧計の個数は、間隙水圧を測定すべき深度の
段数に対応しており、図示の実施例では3段の深度で間
隙水圧を測定するようになっていて、図中符号3は上記
水圧計1a、1b、Icの地上側4まで導出されたリー
ド線を示している。
The number of these water pressure gauges corresponds to the number of depth stages at which the pore water pressure is to be measured, and in the illustrated embodiment, the pore water pressure is measured at three depth stages, and the reference numeral 3 in the figure corresponds to the number of depth stages at which the pore water pressure is to be measured. Lead wires led to the ground side 4 of the water pressure gauges 1a, 1b, and Ic are shown.

ここで、上記の水圧測定管lは第2図の拡大断面図で示
すように、水圧計1a、lb、lcを内蔵した水圧計内
蔵管1dと、これに螺着連結される延長用管体1eとか
らなる長尺管体1fを具備し、上記水圧計内蔵管1dに
は、水圧測定部位に導水口5が穿孔され、上端にポーラ
スストーン等の透水性材料6を備えた水圧計1a、lb
、lcにより当該部位の水圧を測定し得る構成となって
いる・ またこの水圧計内蔵管ld内の上下部にはエポキシ樹脂
等による開栓部■が充填されているため延長用管体1e
の内部への水の浸入は防止され、リード線3を常時乾燥
した状態に保持することができさらに、上記の水圧測定
管lには、その導水口5における傍側に、寝装連通短管
7が所要複数個だけ付設されている。
Here, as shown in the enlarged cross-sectional view of FIG. 2, the water pressure measuring tube 1 is comprised of a built-in water pressure gauge tube 1d that has built-in water pressure gauges 1a, lb, and lc, and an extension tube that is screwed and connected to the built-in water pressure gauge tube 1d. 1e, the water pressure gauge built-in pipe 1d is provided with a water inlet 5 at the water pressure measurement site, and a water pressure gauge 1a equipped with a water permeable material 6 such as porous stone at the upper end; lb
, lc is configured to measure the water pressure at the relevant location. In addition, the upper and lower parts of this water pressure gauge built-in pipe ld are filled with openings ■ made of epoxy resin, etc., so that the extension pipe 1e
Water is prevented from entering the inside of the pipe, and the lead wire 3 can be kept dry at all times.Furthermore, the water pressure measuring pipe l has a bedding communication short pipe on the side of the water inlet 5. 7 are attached as many as required.

次に、前掲シール材注入用バイブ2には、その下端に供
給口2aが開口されているだけでなく、上下配置にて所
要の供給口2b、2c、2dが穿設されており、これら
の供給口2a、2b、2c、2dは第1図(a)に示さ
れている如く、各導水口5の中間に配置されるように、
その開口位置が特定されており、従って、ボーリング孔
Hに挿入した場合、当該供給口2a、2b、2c、2d
の位置を正確に把握することができる。
Next, the above-mentioned sealing material injection vibrator 2 not only has a supply port 2a opened at its lower end, but also has required supply ports 2b, 2c, and 2d in an upper and lower arrangement. As shown in FIG. 1(a), the supply ports 2a, 2b, 2c, and 2d are arranged in the middle of each water inlet 5.
Its opening position is specified, and therefore, when inserted into the borehole H, the corresponding supply ports 2a, 2b, 2c, 2d
The location can be accurately determined.

本発明では次工程として第1図(b)に示す如く4上記
ボーリング孔H内に、先ず別途用意した粒状固形材を投
入することで、孔底箇所H′土に粒状固形材R8aを形
成するが、この際当該粒状固形材層8a内にシール材注
入用バイブ2の下端部が埋入された状態となるようにし
、かつその上表面8a’ は、前記した最下位の導水口
5よりも下位にして、これまた最下位の寝装連通短管7
における下端ロアaと同一か高い位置となるようにする
のであり、このことは、別途用意した適宜の測長手段に
よって測知することにより可能となる。
In the present invention, as the next step, as shown in FIG. 1(b), a separately prepared granular solid material is first introduced into the bore hole H to form a granular solid material R8a in the soil at the bottom of the hole H'. However, at this time, the lower end of the sealing material injection vibe 2 is buried in the granular solid material layer 8a, and the upper surface 8a' is lower than the lowermost water inlet 5. Lower down, this is also the lowest bedding communication short pipe 7
This is made possible by measuring the length using a separately prepared appropriate length measuring means.

ここで、上記の粒状固形材としては、後述する合成樹脂
によるシール材を粒状固形材層8a内へ注入する際、そ
の浸透性をよくすることから、比重が1.3以北であり
、粒径が1嘗■〜5■畷程度のものが望ましく、素材と
しては砂礫、ガラスピーズ鉄球などを使用することがで
きる。
Here, the above-mentioned granular solid material has a specific gravity of 1.3 or higher, and has a specific gravity of 1.3 or higher, in order to improve the permeability when a sealing material made of synthetic resin, which will be described later, is injected into the granular solid material layer 8a. It is desirable to have a diameter of about 1 inch to 5 inches, and materials such as sand and gravel, glass beads, etc. can be used.

次に、所要深度まで形成した上記粒状固形材層8aの上
表面8a’ にフィルター材層9dを積層するのであり
、その層厚は第1図(b)に示す如く、前記最下段の導
水口5の下位から上位までに達し、これにより当該フィ
ルター材層9aを通して進入した間隙水が、上記導水口
5から当該水圧計1aに達するように施すのであり、こ
の際フィルター材としては標準砂を用いることができ、
もちろん、この場合もフィルター材層9aの上表面9a
“につy、その深度を測定し、導水口5の既定深度と比
較して、その適否を確認することとなる。
Next, a filter material layer 9d is laminated on the upper surface 8a' of the granular solid material layer 8a formed to a required depth, and the thickness of the filter material layer 9d is as shown in FIG. 1(b). 5, so that the interstitial water that has entered through the filter material layer 9a reaches the water pressure gauge 1a from the water inlet 5. At this time, standard sand is used as the filter material. It is possible,
Of course, in this case as well, the upper surface 9a of the filter material layer 9a
Then, the depth will be measured and compared with the predetermined depth of the water inlet 5 to confirm its suitability.

さらに、この際上記フィルター材層9aの上表面9a’
は、前記縦装連通短管7の上端ロアbと同一レベルか、
それよりも高い位置となるように設定される。
Furthermore, at this time, the upper surface 9a' of the filter material layer 9a is
Is it at the same level as the upper end lower b of the vertically installed short pipe 7?
It is set to a higher position than that.

このようにして形成されたフィルター材層8aの上表面
9a’上には、次の粒状固形材R8bを積層するのであ
り、さらに、その上表面8b′には、次段のフィルター
材層材9bを積み上げていくのであり、このようにして
粒状固形材層8a、8b、8c、8dとフィルター材層
9a、9b、9cを交互に、所定複数段だけ積み上げて
行くのであり、この際、粒状固形材層8a、8b、8c
の上表面8a’ 、8b’ 、8c’ とフィルター材
層9a、9bJcの上表面9a’ 、9b’ 、9c’
 と、導水口5、縦装連通短管7、下端ロアa、上端ロ
アbとの相対位置関係は何れも、前記と同じように設定
して行くこととなる。
On the upper surface 9a' of the filter material layer 8a formed in this way, the next granular solid material R8b is laminated, and furthermore, on the upper surface 8b', the next filter material layer material 9b is laminated. In this way, the granular solid material layers 8a, 8b, 8c, 8d and the filter material layers 9a, 9b, 9c are alternately stacked in a predetermined number of stages. Material layers 8a, 8b, 8c
Upper surfaces 8a', 8b', 8c' and upper surfaces 9a', 9b', 9c' of filter material layers 9a, 9bJc
The relative positional relationship between the water inlet 5, the vertical communication short pipe 7, the lower end a, and the lower end b are all set in the same manner as described above.

ここで、地上側4にあって用意した図示しない注入ポン
プを稼動することで、エポキシ樹脂等の合成樹脂による
シール材をシール材注入用パイプ2により供与し、これ
により5当該シール材を最下段の粒状固形材層8aには
最下段の供給口2aから、その上段における粒状固形材
層8bへは供給口2bから、そして順次粒状固形材層8
c、8dへは、夫々供給口2c、2dから一度に供給す
るのである。
Here, by operating an injection pump (not shown) prepared on the ground side 4, a sealing material made of synthetic resin such as epoxy resin is supplied through the sealing material injection pipe 2. The granular solid material layer 8a is supplied from the supply port 2a at the lowest stage, the granular solid material layer 8b at the upper stage is supplied from the supply port 2b, and then the granular solid material layer 8
C and 8d are supplied at once from supply ports 2c and 2d, respectively.

かくシテ、各粒状固形材M8a、8b、8c、8dにお
ける粒状固形材の相互間隙や、これとボーリング孔Hの
周側壁間である空隙部にシール材を浸透させることで、
第1図(C)に示す如く、同時に各シール材層10a、
10b、10c、10dを形成するのである。
By infiltrating the sealing material into the mutual gaps between the granular solid materials M8a, 8b, 8c, and 8d, and the gap between this and the peripheral side wall of the borehole H,
As shown in FIG. 1(C), each sealing material layer 10a,
10b, 10c, and 10d.

この際、上記エポキシ樹脂としては、その浸透性をよく
するため粘度は3000C:P以下とするのが望ましく
、特に1ooocp程度とするのが望ましい。
At this time, the epoxy resin preferably has a viscosity of 3000 C:P or less, particularly about 1 ooocp, in order to improve its permeability.

ここで、上記エポキシ樹脂等のシール材注入に際しては
、その主剤と硬化剤とを夫々のポンプにより所容量完遂
り出し、これらを混合器にて混合した後、シール材注入
用パイプ2により住込するのがよい。
When injecting the sealing material such as the epoxy resin, the main resin and curing agent are pumped to the required amount using respective pumps, mixed in a mixer, and then poured into the housing via the sealing material injection pipe 2. It is better to do so.

また、上記のシール材層10a、lOb、10c、10
dを形成するに際し、合成樹脂の硬化時にあって、前掲
の如く熱を放出することとなるが、今このシール材層を
全部エポキシ樹脂によって形成した場合には、硬化時に
あって、 110℃にまで達するのに反し1本発明によ
るときは25℃程度の上昇に抑制することができた。
Further, the above sealing material layers 10a, lOb, 10c, 10
When forming d, heat is emitted as mentioned above during the curing of the synthetic resin, but if this sealing material layer is entirely made of epoxy resin, it will emit heat at 110°C during curing. However, according to the present invention, the temperature increase could be suppressed to about 25°C.

本発明では前記の如く縦装連通短管7が水圧測定管lに
付設されているので、上記のシール材が各粒状固形材層
8a、8b、8c、8dに注入された際、当該層内の空
気が各縦装連通短管7を介して排気され得るから、シー
ル材の注入が円滑に行われると共に、先行して満杯とな
った粒状固形材層から、まだ満杯に至っていない粒状固
形材層へ、当該寝装連通短管を介してシール材が流入さ
れることとなるので、極めて迅速にして円滑にシール材
が全粒状固形材層8a、8b、8c、8dに注入される
こととなる。
In the present invention, as described above, the vertically connected short pipe 7 is attached to the water pressure measuring pipe 1, so when the above-mentioned sealing material is injected into each of the granular solid material layers 8a, 8b, 8c, and 8d, the inside of the layer is Since the air can be exhausted through each vertically connected short pipe 7, the sealing material can be injected smoothly, and the granular solid material layer that has not yet become full can be removed from the granular solid material layer that has previously become full. Since the sealing material is flowed into the layer through the bedding communication short pipe, the sealing material can be injected into all the granular solid material layers 8a, 8b, 8c, and 8d extremely quickly and smoothly. Become.

このような作業が終れば、本実施例では上、中下の三段
にフィルター材層9a、9b、9cが形成され、夫々に
おける間隙水圧が、夫々の各水圧計1a、Ib。
When such work is completed, in this embodiment, the filter material layers 9a, 9b, and 9c are formed in three stages, upper, middle, and lower, and the pore water pressure in each layer is determined by the respective water pressure gauges 1a, Ib.

1Cにより測定され、図示しない地上側の計測器により
、その測定値を知ることができる。
1C, and the measured value can be known by a measuring device on the ground side (not shown).

尚、ここで実際上シール材注入用パイプ2は細いもので
あるから、シール材の硬化が進行しないうちに、これを
ボーリング孔Hから引き抜いてしまうこともできるが、
もちろん、当該シール材注入用パイプ2を引き抜くこと
なく、そのまま放置してシール材を硬化させてしまうよ
うにしてもよい。
Incidentally, since the sealant injection pipe 2 is actually thin, it is possible to pull it out from the borehole H before the sealant hardens.
Of course, the sealing material injection pipe 2 may be left alone to harden the sealing material without being pulled out.

(発明の効果) 本発明は以上のようにして実施できるものであるから、
水圧測定管をボーリング孔に挿入することで極めて精度
の高い深度における水圧を測定することができ、その測
定結果に高い信頼性を与えることが可能となり、水圧計
のリード線を損傷したり、当該リード線が水みちを形成
してしまうこともない。
(Effect of the invention) Since the present invention can be implemented as described above,
By inserting a water pressure measurement tube into a borehole, it is possible to measure water pressure at extremely high depths with high precision, and the measurement results are highly reliable. The lead wire does not form a water path.

これに加えて、シール材層の形成を粒状固形材層への合
成樹脂材注入手段により行うようにしたので、高価な合
成樹脂材の使用量が削減されて安価になるだけでなく1
合成樹脂材の硬化時に発生する熱量を抑制でき、これに
より当該発熱昇温により、水圧計やリード線が損傷され
るといった問題を解消し得ることとなり、信頼性の高い
測定を行うことができる。
In addition, since the sealing material layer is formed by means of injecting a synthetic resin material into the granular solid material layer, the amount of expensive synthetic resin material used is reduced, which not only makes it cheaper;
The amount of heat generated during curing of the synthetic resin material can be suppressed, thereby solving the problem of damage to the water pressure gauge and lead wires due to the heat generation and temperature rise, making it possible to perform highly reliable measurements.

さらに、本発明によるときは、多段に形成の粒状固形材
層に対し、順次シール材を注入して、各シール材層を形
成していくのではなく、予め多段に積層した粒状固形材
層に対して、−度にシール材を供給するようにし、しか
も、この際、皺襞連通短管により、各段の粒状固形材層
を連通状態に保持するようにしたので、円滑にして迅速
に、しかも充分なシール材が各粒状固形材層に注入され
るから、多段の各粒状固形材層に対し、順次シール材を
注入し、下段のシール材層がシール材の硬化により形成
されるのを長時間(1段につき1日程度を要す。)待っ
てから、次の粒状固形材層へシール材注入を行うといっ
た方法に比し、大幅にその施工時間を短縮することがで
き、能率的な間隙水圧の測定を行うことがでSる。
Furthermore, according to the present invention, instead of sequentially injecting sealing material into the granular solid material layers formed in multiple stages to form each sealing material layer, the granular solid material layers laminated in multiple stages are On the other hand, the sealing material is supplied every second time, and at this time, the granular solid material layers at each stage are maintained in a communicating state by means of the wrinkle communication short tube, so that the sealing material can be supplied smoothly and quickly. Since sufficient sealing material is injected into each granular solid material layer, the sealing material is injected into each of the multi-stage granular solid material layers one after another, and the lower sealing material layer is formed by curing of the sealing material for a long time. Compared to the method of injecting sealant into the next layer of granular solid material after waiting for a period of time (about one day per layer), the construction time can be significantly shortened, making it more efficient. Pore water pressure can be measured.

【図面の簡単な説明】[Brief explanation of the drawing]

第1図(a)(b) (c) (d)は、本発明に係る
地盤内の間隙水圧測定方法の一実施例による工程順を示
した縦断正面説明図、第2図は同上方法の実施に用いら
れる水圧測定管の一例を示す部分縦断正面図、第3図は
従来の地盤的間隙水圧の測定方法を示した地盤要部の縦
断面正面説明図である。 1・・・・・・水圧測定管 la、lb、lc・・・・・・・・・・水圧計1f・・
・・・・長尺管体 2・・・・・・シール材注入用パイプ 2a、2b、2c、2d ””供給口 3 ・・・・・・リード線 4・・・・・・地上側 5・・・・・・導水口 ア・・・・・・皺襞連通短管 7a・・・・・・下端口 アb・・・・・・上端口 8a、8b、8c、8d・・・・・・粒状固形材層Sa
、9b、9c・・・・・・・・・・フィルター材層10
a、job、loc・・・・・・シール材層G・・・・
・・地盤 H・・・・・・ボーリング孔 第1図 (al (b) (C) 代理人 弁理士 斎 藤 義 雄 第 図 第 図
Figures 1 (a), (b), (c), and (d) are longitudinal cross-sectional front explanatory diagrams showing the process order according to an embodiment of the method for measuring pore water pressure in the ground according to the present invention, and Figure 2 is a diagram showing the process sequence of an embodiment of the method for measuring pore water pressure in the ground according to the present invention. FIG. 3 is a partial longitudinal sectional front view showing an example of a water pressure measuring pipe used in practice, and FIG. 3 is an explanatory longitudinal sectional front view of the main part of the ground showing a conventional method for measuring pore water pressure in the ground. 1...Water pressure measuring tubes la, lb, lc...Water pressure gauge 1f...
...Long tube body 2 ...Seal material injection pipes 2a, 2b, 2c, 2d "" Supply port 3 ...Lead wire 4 ...Ground side 5 ...Water inlet a...Wrinkled communication short pipe 7a...Lower end port ab...Top end port 8a, 8b, 8c, 8d...・Granular solid material layer Sa
, 9b, 9c...Filter material layer 10
a, job, loc...Seal material layer G...
・・・Ground H・・・Borehole Diagram 1 (al (b) (C) Agent Patent Attorney Yoshio Saito Diagram

Claims (1)

【特許請求の範囲】[Claims] 地盤の所要箇所に削設したボーリング孔中には、長尺管
体の互いに区分された箇所に夫々の導水口を開口すると
共に、各水圧計が内蔵され、かつ、これら水圧計のリー
ド線が当該長尺管体内より導出され、かつ、所要複数個
の縦装連通短管を付設してなる水圧測定管と、上下配置
にて所要数個の供給口が開成されたシール材注入用パイ
プとを挿入した後、上記ボーリング孔内にあって、砂な
どによるフィルター材層は、前記導水口を被装し、かつ
上記縦装連通短管が貫通する箇所に形成し、その他の箇
所には、前記シール材注入用パイプの各注入口が開口す
るよう砂礫等によるとき粒状固形材層を形成することに
より、上記縦装連通短管の上下端口を夫々上下の当該粒
状固形層に開口させ、その後、前記のシール材注入用パ
イプを介して合成樹脂によるシール材を圧送することに
より、当該シール材を前記の各供給口から夫々の粒状固
形層へ注入させてシール材層を形成し、上記リード線を
接続した地上側における計測器によって、各深度におけ
る前記各水圧計の測定値が測知されるようにしたことを
特徴とする多段シール材層の同時形成による地盤内の間
隙水圧測定方法。
In the boreholes drilled at required locations in the ground, water inlets are opened at separate locations on the long pipe body, and each water pressure gauge is built in, and the lead wires of these water pressure gauges are connected. A water pressure measuring pipe led out from the long pipe body and provided with a required plurality of vertically connected short communication pipes, and a sealing material injection pipe having a required number of supply ports arranged vertically. After inserting the filter material in the borehole, a layer of filter material made of sand or the like is formed at a location that covers the water inlet and is penetrated by the vertical communication short pipe, and at other locations, By forming a granular solid material layer using sand and gravel etc. so that each injection port of the sealing material injection pipe opens, the upper and lower end ports of the vertical connecting short pipe are opened to the upper and lower granular solid layers, respectively, and then By force-feeding a synthetic resin sealing material through the sealing material injection pipe, the sealing material is injected from each supply port into each granular solid layer to form a sealing material layer. A method for measuring pore water pressure in the ground by simultaneous formation of multi-stage sealing material layers, characterized in that the measured values of each of the water pressure gauges at each depth are measured by a measuring device on the ground side connected to a line.
JP2215515A 1990-08-15 1990-08-15 Pore water pressure measurement method in ground by simultaneous formation of multi-stage sealing material layers Expired - Fee Related JPH0753970B2 (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
JP2215515A JPH0753970B2 (en) 1990-08-15 1990-08-15 Pore water pressure measurement method in ground by simultaneous formation of multi-stage sealing material layers

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
JP2215515A JPH0753970B2 (en) 1990-08-15 1990-08-15 Pore water pressure measurement method in ground by simultaneous formation of multi-stage sealing material layers

Publications (2)

Publication Number Publication Date
JPH0497010A true JPH0497010A (en) 1992-03-30
JPH0753970B2 JPH0753970B2 (en) 1995-06-07

Family

ID=16673693

Family Applications (1)

Application Number Title Priority Date Filing Date
JP2215515A Expired - Fee Related JPH0753970B2 (en) 1990-08-15 1990-08-15 Pore water pressure measurement method in ground by simultaneous formation of multi-stage sealing material layers

Country Status (1)

Country Link
JP (1) JPH0753970B2 (en)

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
US5909846A (en) * 1994-09-28 1999-06-08 Tetra Laval Holdings & Finance S.A. Nozzle plate for filling liquid

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
US5909846A (en) * 1994-09-28 1999-06-08 Tetra Laval Holdings & Finance S.A. Nozzle plate for filling liquid

Also Published As

Publication number Publication date
JPH0753970B2 (en) 1995-06-07

Similar Documents

Publication Publication Date Title
CN104329076B (en) A kind of deviational survey hole osmotic pressure counter device and installation method
US7389815B2 (en) Methods for reverse-circulation cementing in subterranean formations
AU2012323825B2 (en) Formation pressure sensing system
CN105908744B (en) Pore pressure counter-force construction method
CN106320354B (en) The Seepage method on solution cavity development stratum under coating
CN110185844A (en) Shallow earthing pipe-jacking with large diameter construction method
CN204252103U (en) A kind of deviational survey hole osmometer device
JP6433069B2 (en) Ground buried board and method of using the same
CN112900430B (en) Cast-in-place pile casing in karst area and construction method of cast-in-place pile
JPH0497010A (en) Measurement of void water pressure in ground by concurrent formation of multistage seal layer
CN110644492B (en) Comprehensive grouting construction method for steep dip angle wide-crack stratum
CN111335368B (en) Method for installing inclinometer pipe
CN110500119A (en) A kind of waterproof consolidation structure construction method for passing through Debris Flow Deposition body tunnel
CN105887904A (en) Construction method for filling dissolving cavity in outer side of deep foundation pit in karst area
JP2594171B2 (en) A method for measuring pore water pressure in the ground by forming a sealing material layer on the water blocking material layer
CN207828946U (en) A kind of solution cavity waits for the drilling arrangement of reinforcing area
CN116735378B (en) Device and method for testing along-drilling follow pipe pile side grouting shear model
JPH0721279B2 (en) Method of measuring pore water pressure in the ground by forming a special sealing material layer
CN218027625U (en) Outer-pouring backfill rotary-digging pile hole pile casing structure
CN114810048B (en) Pressure control commutator, in-situ stress measurement equipment and in-situ stress measurement method
JP2626456B2 (en) Rock permeability test equipment
Kronberg KBS-3H Preparations, assembly and installation of the Multi Purpose Test
JP7264793B2 (en) Well repair method
JPH0753969B2 (en) Pore water pressure measurement method in the ground
JPH03279510A (en) Measuring of gap water pressure in the ground and its device

Legal Events

Date Code Title Description
R250 Receipt of annual fees

Free format text: JAPANESE INTERMEDIATE CODE: R250

R250 Receipt of annual fees

Free format text: JAPANESE INTERMEDIATE CODE: R250

LAPS Cancellation because of no payment of annual fees