JPH047520Y2 - - Google Patents

Info

Publication number
JPH047520Y2
JPH047520Y2 JP3894687U JP3894687U JPH047520Y2 JP H047520 Y2 JPH047520 Y2 JP H047520Y2 JP 3894687 U JP3894687 U JP 3894687U JP 3894687 U JP3894687 U JP 3894687U JP H047520 Y2 JPH047520 Y2 JP H047520Y2
Authority
JP
Japan
Prior art keywords
scrap
bucket
waste gas
preheating
lid
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Expired
Application number
JP3894687U
Other languages
Japanese (ja)
Other versions
JPS63147699U (en
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed filed Critical
Priority to JP3894687U priority Critical patent/JPH047520Y2/ja
Publication of JPS63147699U publication Critical patent/JPS63147699U/ja
Application granted granted Critical
Publication of JPH047520Y2 publication Critical patent/JPH047520Y2/ja
Expired legal-status Critical Current

Links

Landscapes

  • Furnace Details (AREA)

Description

【考案の詳細な説明】 (産業上の利用分野) 本考案は、電気炉の廃ガスが有する残余熱を利
用して電気炉へ装入する原料のスクラツプを予熱
しようとするスクラツプ予熱装置の改良に関する
ものである。
[Detailed description of the invention] (Field of industrial application) The present invention is an improvement of a scrap preheating device that uses the residual heat of the waste gas of the electric furnace to preheat the raw material scrap to be charged into the electric furnace. It is related to.

(従来の技術・考案が解決しようとする問題点) 電気製鋼の場合、原料としてスクラツプが大量
に使用されている。スクラツプが原料装入用バケ
ツトに予め入れられて、電気炉の炉蓋を取つて、
炉中に装入される。しかし、電気製鋼における溶
解時間の短縮、スクラツプに付着した雪や水の除
去により、炉内爆発および鋼浴中の水素増加の防
止を図るほか、特に炉の廃ガス熱を利用する場
合、電力コストの低減を図るため、バケツト内で
スクラツプの予熱が行われている。
(Problems to be solved by conventional techniques and ideas) In the case of electric steel manufacturing, a large amount of scrap is used as a raw material. Scrap is placed in the raw material charging bucket in advance, and the lid of the electric furnace is removed.
Charged into the furnace. However, by shortening the melting time in electric steelmaking and removing snow and water adhering to scrap, it is possible to prevent explosions in the furnace and increase in hydrogen in the steel bath. In order to reduce this, the scrap is preheated in the bucket.

このスクラツプ予熱のための方法が、種々開発
されている。
Various methods for this scrap preheating have been developed.

スクラツプ予熱方法としては、炉内の補助燃焼
法と、バケツト内スクラツプを燃料で予熱する方
法、又は廃ガスで予熱する方法等がある。
Scrap preheating methods include an auxiliary combustion method in a furnace, a method of preheating scrap in a bucket with fuel, or a method of preheating with waste gas.

これらの各方法専用、又は汎用のスクラツプ予
熱装置が開発され、使用されている。
Scrap preheating devices dedicated to each of these methods or general-purpose scrap preheating devices have been developed and used.

従来のスクラツプ予熱装置の1つを第2図に示
す。以下にこの第2図に基づいて従来装置の構造
を説明する。
One conventional scrap preheating device is shown in FIG. The structure of the conventional device will be explained below based on FIG. 2.

1は予熱室であつて、内部にバケツト2を装入
して据え置くことができる容量のものである。3
は、該予熱室1の天井に当たる部分を構成するも
ので、バケツト2を予熱室1内に装入・取り出し
を行うため取外しができる蓋である。
Reference numeral 1 denotes a preheating chamber, which has a capacity such that a bucket 2 can be placed therein. 3
The lid constitutes the part corresponding to the ceiling of the preheating chamber 1 and is removable for loading and unloading the bucket 2 into the preheating chamber 1.

4は、電気炉(図示せず)の廃ガスを予熱室1
内に誘導する廃ガス管であつて、蓋3の中央の穴
5に密閉固定され、先端には、予熱室1内に置か
れたバケツト2の上部に覆い被さるようにフード
6が設けられている。
4, the waste gas from the electric furnace (not shown) is transferred to the preheating chamber 1.
It is a waste gas pipe that guides the inside of the exhaust gas pipe, and is hermetically fixed in a hole 5 in the center of the lid 3, and a hood 6 is provided at the tip so as to cover the top of the bucket 2 placed in the preheating chamber 1. There is.

又、該廃ガス管4は、前記蓋3と共にクレーン
(図示せず)等で取外し除去できる(図示せず)。
81は遮蔽用蛇腹であつて、蓋3の内側から予熱
室1内に置かれたバケツト2の上端まで降下可能
に構成されている。9は、前記蓋3の端部と予熱
室1の側壁間から廃ガスGが洩れないように設け
られた水封機構である。
Further, the waste gas pipe 4 can be removed together with the lid 3 using a crane (not shown) or the like (not shown).
Reference numeral 81 is a shielding bellows, which is configured to be able to descend from the inside of the lid 3 to the upper end of the bucket 2 placed in the preheating chamber 1. Reference numeral 9 denotes a water seal mechanism provided to prevent waste gas G from leaking between the end of the lid 3 and the side wall of the preheating chamber 1.

10は、排気ガス煙道であつて、予熱室1から
集塵機11へ排気ガスを誘導するものである。1
2は、集塵機11内に設けられた瀘布であつて、
集塵機能を有するものである。
10 is an exhaust gas flue that guides exhaust gas from the preheating chamber 1 to the dust collector 11. 1
2 is a filter cloth provided in the dust collector 11,
It has a dust collection function.

以下に従来装置の作用効果を説明する。 The effects of the conventional device will be explained below.

予め蓋3がクレーン等(図示せず)で除去され
ている予熱室1内に、スクラツプSを装入したバ
ケツト2がクレーンで装入される。次いで、蓋3
がクレーン等で予熱室1に被せられる。これと同
時に蓋3は水封機構9で水封されると共に、蓋3
の下に設けられている遮蔽用蛇腹81が蓋3とバ
ケツト2との間を遮蔽する。
A bucket 2 loaded with scraps S is charged by a crane into a preheating chamber 1 from which the lid 3 has been previously removed by a crane or the like (not shown). Next, lid 3
is placed over the preheating chamber 1 using a crane or the like. At the same time, the lid 3 is water-sealed by the water-sealing mechanism 9, and the lid 3 is
A shielding bellows 81 provided below shields between the lid 3 and the bucket bag 2.

この状態となつた後、電気炉(図示せず)から
廃ガスGが送られる。送られた廃ガスGは、バケ
ツト2内のスクラツプSの間隙を通過し、集塵機
11の吸引力によりバケツト2の底部間隙より予
熱室1内に出て、排気ガス煙道10・瀘布12を
経由して大気中へ排出される。
After reaching this state, waste gas G is sent from an electric furnace (not shown). The sent waste gas G passes through the gap between the scraps S in the bucket 2, exits into the preheating chamber 1 through the bottom gap of the bucket 2 due to the suction force of the dust collector 11, and flows through the exhaust gas flue 10 and filter 12. and is emitted into the atmosphere.

この廃ガスGの通過によつて、スクラツプSに
付着していた雪や水が除去されて、炉内爆発なら
びに鋼浴中の水素増加の防止を図るほか、廃ガス
Gの熱を利用して、スクラツプSを予熱するの
で、製鋼電力コストの低減が図れるし、電気製鋼
における溶解時間を短縮することができる。
As this waste gas G passes through, snow and water adhering to the scrap S are removed, preventing an explosion inside the furnace and an increase in hydrogen in the steel bath. Since the scrap S is preheated, the steelmaking power cost can be reduced and the melting time in electric steelmaking can be shortened.

しかし、上記従来装置では、予熱時の固定式の
蛇腹81による密閉度が高過ぎて、スクラツプS
から発生した油煙が、バケツト2から予熱室1・
排気ガス煙道10を通つて、集塵機11にまで達
することがあり、そのため集塵機11の瀘布12
に油が付着して、集塵効率が低下するほか、該瀘
布12を高頻度で取り替えなければならないし、
排気ガスが高熱のため、煙道10内及び瀘布12
に付着している油が発火して、集塵機11に火災
が発生し、この復旧工事が必要であるほか、電気
炉がその間休止させられる危険があつた。
However, in the above conventional device, the degree of sealing by the fixed bellows 81 during preheating is too high, and the scrap S
The oil smoke generated from the bucket 2 and the preheating chamber 1.
The exhaust gas may reach the dust collector 11 through the flue 10, so that the filter cloth 12 of the dust collector 11
In addition to reducing dust collection efficiency due to oil adhering to the filter, the filter cloth 12 must be replaced frequently.
Due to the high temperature of the exhaust gas, the inside of the flue 10 and the filter 12
The oil adhering to the dust collector 11 ignited, causing a fire in the dust collector 11, which required restoration work, and there was a risk that the electric furnace would be shut down for a while.

(考案が解決しようとする問題点) 本考案は、上記諸欠点を解決するために種々検
討の結果、なされたものであつて、その要旨とす
るところは、電気炉の廃ガス管の端がスクラツプ
バケツトに近接し、両者間を密閉するシール装置
が設けられたスクラツプ予熱装置において、前記
シール装置を稼動式となし、バケツトと廃ガス管
との間の遮蔽量を調整可能としたことを特徴とす
るものである。
(Problems to be solved by the invention) The present invention was developed as a result of various studies to solve the above-mentioned drawbacks, and its gist is that the end of the waste gas pipe of the electric furnace In the scrap preheating device, which is equipped with a sealing device that is close to the scrap bucket and seals the gap between the two, the sealing device is made movable so that the amount of shielding between the bucket and the waste gas pipe can be adjusted. It is characterized by this.

(作用・効果) バケツトに装入されているスクラツプは、その
生成過程が異なることによつて、油分の量に差が
ある。従つて、予熱によつて、発生する油煙の濃
度にも差がある。又、スクラツプ予熱に利用する
廃ガスの温度・予熱時間等によつても油煙の濃度
に差が生じる。従つて、発生する油煙の量・濃度
にもバラツキがある。
(Function/Effect) The amount of oil contained in the scraps charged in the bucket differs due to the different generation processes. Therefore, there is a difference in the concentration of the oil smoke generated depending on the preheating. Furthermore, the concentration of oil smoke varies depending on the temperature of the waste gas used for scrap preheating, the preheating time, etc. Therefore, there are variations in the amount and concentration of oil smoke generated.

本考案は、上述の構成よりなるため、シール装
置を稼動してバケツトと廃ガス管との間隙を調整
して、バケツト内に送り込まれる廃ガスの量を調
整して、スクラツプを予熱する温度をコントロー
ルすることによつて、予熱によつてスクラツプか
ら発生する油煙の量・濃度を一定にし、もつて油
煙の集塵機にまで達することを防止し、強いて
は、集塵機の瀘布に油が付着する量を減少せしめ
て集塵効率が低下するのを防止し、従つて瀘布の
取り替え頻度を減少することができる。
Since the present invention has the above-mentioned configuration, the sealing device is operated to adjust the gap between the bucket and the waste gas pipe, adjust the amount of waste gas sent into the bucket, and adjust the temperature at which the scrap is preheated. By controlling the amount and concentration of oil smoke generated from the scrap through preheating, it is possible to prevent the oil smoke from reaching the dust collector, and ultimately to reduce the amount of oil that adheres to the filter cloth of the dust collector. This can prevent the dust collection efficiency from decreasing and therefore reduce the frequency of replacing the filter cloth.

又、集塵機に火災が発生することもなく、その
復旧工事の人工・費用も不要となり、又、火災・
復旧による電気炉の休止も防止できる。そのほ
か、スクラツプ予熱の効果(水分を除去して炉内
爆発を防止し、鋼浴中の水素増加を防止する。
In addition, fires do not occur in the dust collector, and there is no need for personnel or expenses for restoration work.
It also prevents the electric furnace from being shut down due to restoration. In addition, the effects of scrap preheating (remove moisture to prevent explosions in the furnace and prevent hydrogen from increasing in the steel bath).

又、廃ガス熱利用により電力コスト低減、溶解
時間短縮等の効果)も有する。
In addition, it also has the effect of reducing electricity costs and shortening melting time by utilizing waste gas heat.

(実施例) 本考案の1実施例をその図面(第1図)に基づ
いて説明する。
(Example) An example of the present invention will be described based on the drawing (FIG. 1).

第1図は、本考案の要旨説明用に、従来装置の
1つ(第2図)において違つた部分(本考案の要
部)を拡大した説明用図である。従つて、第2図
と違う点について説明する。
FIG. 1 is an enlarged explanatory view of a different part (main part of the present invention) of one of the conventional devices (FIG. 2) for explaining the gist of the present invention. Therefore, the differences from FIG. 2 will be explained.

7は、基台72から予熱室1上空へ突出された
アーム71に設けられた昇降装置である。8は廃
ガス管4(その先端フード6)とバケツト2との
間隙を遮蔽するシール装置であつて、封水・砂等
による密閉機能である。本実施例では、水封であ
る。
Reference numeral 7 denotes a lifting device provided on an arm 71 that projects from a base 72 into the air above the preheating chamber 1 . 8 is a sealing device for shielding the gap between the waste gas pipe 4 (its tip hood 6) and the bucket 2, and has a sealing function using water sealing, sand, etc. In this embodiment, it is a water seal.

82は封水85を入れるケーシングであり、前
記昇降装置7によつて蓋3の貫通孔51を通して
巻き上げられるチエン73で昇降調整可能であ
る。31は蓋3の下面に下方に向かつて突出した
遮蔽板であつて、前記ケーシング82内の封水8
5内に下端が浸漬された状態にあり、廃ガス管4
(フード6)とバケツト2との隙間を遮蔽するこ
とができる。
Reference numeral 82 denotes a casing in which a water seal 85 is placed, and can be raised and lowered by a chain 73 that is rolled up through the through hole 51 of the lid 3 by the lifting device 7. Reference numeral 31 denotes a shielding plate that protrudes downward from the lower surface of the lid 3, and is a shielding plate that prevents water sealing 8 in the casing 82.
The lower end is immersed in the waste gas pipe 4.
(The hood 6) and the bucket 2 can be shielded from each other.

又、昇降装置7を駆動してチエン73を巻き上
げ、巻戻すことによつて、ケーシング82が昇降
し、最下死点はケーシング82がバケツト2の上
端に密着する点であり、ここまで降下したままに
してあると完全にシールすることができる。又、
巻上げたときケーシング82の上端に取り付けら
れているストツパー84が蓋3の下面に当接して
停止できるようになつている。又シール装置8は
途中の任意な位置で停止できる。
In addition, by driving the lifting device 7 to wind up and unwind the chain 73, the casing 82 is raised and lowered, and the lowest dead center is the point where the casing 82 comes into close contact with the upper end of the bucket 2, and the casing 82 has descended to this point. If left as is, it can be completely sealed. or,
When the lid 3 is rolled up, a stopper 84 attached to the upper end of the casing 82 comes into contact with the lower surface of the lid 3 and can be stopped. Further, the sealing device 8 can be stopped at any position along the way.

次に上記実施例の作用効果を説明する。 Next, the effects of the above embodiment will be explained.

スクラツプSの装入されたバケツト2が、クレ
ーン(図示せず)で、予め蓋3が除去された予熱
室1内に装入され置かれる。次いで、蓋3が予熱
室1に被せられる。次いで、昇降装置7が作動し
て、ケーシング82が降下され、バケツト2の上
端に密着される。
The bucket 2 loaded with the scraps S is loaded and placed into the preheating chamber 1 from which the lid 3 has been previously removed by a crane (not shown). Then, the lid 3 is placed over the preheating chamber 1. Next, the lifting device 7 is operated, and the casing 82 is lowered and brought into close contact with the upper end of the bucket bag 2.

この状態になつた予熱室1は、電気炉(図示せ
ず)から廃ガスGが廃ガス管4・フード6を経由
して、バケツト2とフード6との間がシール装置
8で遮蔽されている空間を通つてバケツト2内の
スクラツプSに当り、スクラツプSの間隙を通つ
て、スクラツプSを加熱し、これによりスクラツ
プSに付着している雪や水は蒸発されて、集塵機
11の吸引力で吸引されバケツト2の底部の間隙
から予熱室1・排気ガス煙道10を経由して集塵
機11を通つて大気中に排気される。
In the preheating chamber 1 in this state, the waste gas G from the electric furnace (not shown) passes through the waste gas pipe 4 and the hood 6, and the space between the bucket 2 and the hood 6 is shielded by the sealing device 8. The scrap S in the bucket 2 is heated through the space in which the scrap S is heated, and the snow and water adhering to the scrap S are evaporated, and the suction force of the dust collector 11 is heated. The gas is sucked in through the gap at the bottom of the bucket 2, passes through the preheating chamber 1 and the exhaust gas flue 10, passes through the dust collector 11, and is exhausted into the atmosphere.

そのため、スクラツプSから製鋼された鋼浴中
の水素の増加を防止して電気炉内爆発を防止する
ことができる。又、高熱の廃ガスGがスクラツプ
Sに当ることによりスクラツプSに付着していた
油分が燃焼して油煙となり同じく排気ガス煙道1
0から集塵機11を通つて大気中に排気される。
Therefore, it is possible to prevent an increase in hydrogen in the steel bath produced from the scrap S, thereby preventing an explosion in the electric furnace. Also, when the high-temperature waste gas G hits the scrap S, the oil adhering to the scrap S burns and becomes oil smoke, which also flows into the exhaust gas flue 1.
0 to the atmosphere through a dust collector 11.

この場合、排気ガス量を監視していて、スクラ
ツプSから発生する油煙が濃い場合は、昇降装置
7を稼動させて、シール装置8を上昇させて、バ
ケツト2との間から廃ガスGを予熱室1に一部直
接排出させて、スクラツプSの昇温強いては油煙
量を調整する。
In this case, if the amount of exhaust gas is monitored and the oil smoke generated from the scrap S is thick, the elevating device 7 is operated, the sealing device 8 is raised, and the waste gas G is preheated from between it and the bucket 2. A portion of the oil is directly discharged into the chamber 1 to adjust the temperature rise of the scrap S and the amount of oil smoke.

このように、スクラツプSを予熱する温度をコ
ントロールすることによつて、油煙量を一定にし
もつて油煙が集塵機11にまで達することを防止
し、瀘布12に油が付着する量を減少せしめて、
集塵効率の低下を防止し、瀘布の取替え頻度を減
少させることができる。又、集塵機11に火災も
発生することがなくなり、その復旧の工事人工・
費用も不要となり、又、これに関連した電気炉の
休止も防止できる。
In this way, by controlling the temperature at which the scrap S is preheated, the amount of oil smoke can be kept constant, the oil smoke can be prevented from reaching the dust collector 11, and the amount of oil adhering to the filter cloth 12 can be reduced. ,
It is possible to prevent a decrease in dust collection efficiency and reduce the frequency of replacing the filter cloth. In addition, fires no longer occur in the dust collector 11, and the restoration work requires manual labor and maintenance.
This eliminates costs and also prevents the electric furnace from being shut down in connection with this.

このほか、本来廃ガス利用によるスクラツプ予
熱によつて、製鋼電力コストの低減も、溶解時間
の短縮も図れ、製鋼の生産性向上に役立つ。
In addition, by preheating the scrap using waste gas, it is possible to reduce steelmaking power costs and shorten melting time, which helps improve steelmaking productivity.

【図面の簡単な説明】[Brief explanation of the drawing]

第1図は本考案の要旨を説明するために必要な
1実施例の要部拡大説明図、第2図は従来装置の
1実施例の説明用図である。 1……予熱室、2……バケツト、3……蓋、4
……廃ガス管、6……フード、7……昇降装置、
8……シール装置、9……水封機構、10……排
気ガス煙道、11……集塵機、12……瀘布、G
……廃ガス、S……スクラツプ。
FIG. 1 is an enlarged explanatory view of a main part of an embodiment necessary for explaining the gist of the present invention, and FIG. 2 is an explanatory diagram of an embodiment of a conventional device. 1... Preheating chamber, 2... Bucket, 3... Lid, 4
...waste gas pipe, 6...hood, 7...lifting device,
8... Sealing device, 9... Water sealing mechanism, 10... Exhaust gas flue, 11... Dust collector, 12... Filter, G
...waste gas, S...scrap.

Claims (1)

【実用新案登録請求の範囲】[Scope of utility model registration request] 電気炉の廃ガス管の端がスクラツプバケツトに
近接し、両者間を密閉するシール装置が設けられ
たスクラツプ予熱装置において、前記シール装置
を稼動式となし、バケツトと廃ガス管との間の遮
蔽量を調整可能としたことを特徴とするスクラツ
プ予熱装置の稼動式シール装置。
In a scrap preheating device in which the end of the waste gas pipe of an electric furnace is close to the scrap bucket and is equipped with a sealing device that seals the gap between the two, the sealing device is operated and the end of the waste gas pipe is close to the scrap bucket. A movable sealing device for a scrap preheating device, characterized in that the amount of shielding between the scraps can be adjusted.
JP3894687U 1987-03-17 1987-03-17 Expired JPH047520Y2 (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
JP3894687U JPH047520Y2 (en) 1987-03-17 1987-03-17

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
JP3894687U JPH047520Y2 (en) 1987-03-17 1987-03-17

Publications (2)

Publication Number Publication Date
JPS63147699U JPS63147699U (en) 1988-09-29
JPH047520Y2 true JPH047520Y2 (en) 1992-02-27

Family

ID=30851659

Family Applications (1)

Application Number Title Priority Date Filing Date
JP3894687U Expired JPH047520Y2 (en) 1987-03-17 1987-03-17

Country Status (1)

Country Link
JP (1) JPH047520Y2 (en)

Also Published As

Publication number Publication date
JPS63147699U (en) 1988-09-29

Similar Documents

Publication Publication Date Title
CN1052729A (en) Hazardous waste incinerator in the belt material
US4506370A (en) Arc furnace installation with shroud
US4033846A (en) Apparatus for gas collection in aluminum smelting furnaces
KR850001479Y1 (en) Apparatus for preheating a steel scrap
JPH047520Y2 (en)
US4005252A (en) Apparatus for gas collection in open electric smelting furnaces
JP2004361003A (en) Dust collector to be used for steelmaking electric furnace in charging scrap
CA1052844A (en) Apparatus for gas collection in aluminum smelting furnaces
USRE31266E (en) Apparatus for gas collection in aluminum smelting furnaces
GB1424316A (en) Dust and gas-tight apparatus for charging lifting the door of and closing a charging opening of a coke oven battery
JPS6056963B2 (en) Melting treatment method and melting furnace for municipal waste incineration ash, sewage sludge, etc.
CN206786725U (en) A kind of industrial incinerator with automatic charging function
JPS6136159Y2 (en)
CN218530147U (en) Dust overflow dust removal device for coke tank cover on top of dry quenching furnace
RU2743943C1 (en) Method for sealing bath casing of ore recovery furnace with rotating bath and device for its implementation
CN212720926U (en) A separable ring suction dust removal cigarette cover for intermediate frequency furnace
JPS631188Y2 (en)
JPS58691Y2 (en) Batch furnace lid sealing device
JPS6023296Y2 (en) Charging device for coke dry fire extinguishing equipment
JP3278077B2 (en) Coke production method
JPH027861Y2 (en)
JPH0333964B2 (en)
JPS624875Y2 (en)
CS211353B2 (en) Facility for catching the furnace gases particularly tapping gases from electric melting furnaces
CN206973562U (en) A kind of fixed hermetically sealed solid waste burning device