JPH0449334A - Construction method of underground skeleton - Google Patents

Construction method of underground skeleton

Info

Publication number
JPH0449334A
JPH0449334A JP2157482A JP15748290A JPH0449334A JP H0449334 A JPH0449334 A JP H0449334A JP 2157482 A JP2157482 A JP 2157482A JP 15748290 A JP15748290 A JP 15748290A JP H0449334 A JPH0449334 A JP H0449334A
Authority
JP
Japan
Prior art keywords
columns
underground
ground
column
construct
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
JP2157482A
Other languages
Japanese (ja)
Inventor
Koichi Nagase
公一 長瀬
Masahide Nishikawa
西川 正英
Yoshiaki Nagataki
慶明 長瀧
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Taisei Corp
Original Assignee
Taisei Corp
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Taisei Corp filed Critical Taisei Corp
Priority to JP2157482A priority Critical patent/JPH0449334A/en
Publication of JPH0449334A publication Critical patent/JPH0449334A/en
Pending legal-status Critical Current

Links

Landscapes

  • Underground Structures, Protecting, Testing And Restoring Foundations (AREA)

Abstract

PURPOSE:To make it possible to construct an underground skeleton with high reliability by repeating the progress of work to join PC girder member between side columns and middle columns after beams, side columns with underground walls and middle columns are inserted into excavated holes bored in positions of the side columns and middle columns. CONSTITUTION:Excavated holes 2 and 3 are respectively bored in positions of side columns and middle columns of a building from a cutting bottom of the ground 1 to a bearing ground. After beams 4, the side columns A with underground walls 5 and PC middle columns B are inserted each of the excavated holes 2 and 3, girder members C are joined between adjacent PC side column A and PC middle column B and between adjacent PC middle columns B to construct the upper part of an underground skeleton. After that, while utilizing underground walls 5 provided to the PC side columns 5 as a landslide protection wall and utilizing the PC girder members C as braces, the ground 1 is excavated to construct the lower part of the underground skeleton, and the progress of work is repeated. According to the constitution, the execution of the work of the underground skeleton and the work of piles can be carried out at a time.

Description

【発明の詳細な説明】 (産業上の利用分野) 本発明は建造物の地下躯体の構築方法に係るものである
DETAILED DESCRIPTION OF THE INVENTION (Industrial Field of Application) The present invention relates to a method of constructing an underground framework for a building.

(従来の技術) 従来この種の工法においては、地下躯体部分まで根伐り
したのち、杭部分を支持層まで掘削してコンクリートを
打設するか、既成のPC杭を支持層まで貫入して杭を構
築し、しかるのち捨コンクリドを打設してレベル墨出し
を行ない、型枠を組み、地中梁、柱、壁等のコンクリー
トを打設して地下製体を構築していた。
(Conventional technology) Conventionally, in this type of construction method, after cutting down to the underground structure, the pile area is excavated to the supporting layer and concrete is poured, or existing PC piles are penetrated to the supporting layer and piled. After that, concrete was poured, the level was marked, formwork was erected, concrete was poured for underground beams, columns, walls, etc., and the underground structure was constructed.

(発明が解決しようとする課B) しかしながら前記の方法においては、地下躯体底部まで
掘削しなくてはならず、また場所打ち抗の場合、杭躯体
部分を掘削してコンクリートを打設するため、コンクリ
ートが硬化するまで時間がかかっていた。
(Problem B to be solved by the invention) However, in the above method, it is necessary to excavate to the bottom of the underground structure, and in the case of cast-in-place, the pile structure part is excavated and concrete is poured. It took a long time for the concrete to harden.

またレヘル、墨出し等を行なうため、捨コンクリートを
打設しなくてはならず、型枠組立、解体、排出等に手間
がかかる。
In addition, in order to perform leveling, marking, etc., it is necessary to pour waste concrete, which requires time and effort in assembling, dismantling, and discharging formwork.

更に抗コンクリートも水が多い掘削場所においてはコン
クリートが分離し易く、品nが低下し易い。
Furthermore, in excavation sites where there is a lot of water, the concrete tends to separate and the quality of the concrete tends to deteriorate.

本発明は前記従来技術の有する問題点に鑑みて提案され
たもので、その目的とする処は、施工性が向上され、工
期が短縮され、施工の省力化が図られ、しかも構造的G
コ信転性のある地下躯体の構築方法を提供する点にある
The present invention has been proposed in view of the problems of the prior art, and its objectives are to improve workability, shorten the construction period, save labor in construction, and improve structural efficiency.
The purpose of the present invention is to provide a method for constructing an underground structure with reliability.

(課題を解決するための手段) 前記の目的を達成するため、本発明に係る地下躯体の構
築方法によれば、根伐り底地盤より建物の側柱及び中柱
位置を掘削し、同各掘削孔に夫々梁、地中壁付きのPC
側柱及びPC中柱を支持層まで挿入したのち、前記側柱
及び中柱間にPCc梁部材を接合し、次いで地盤を掘削
し、前記同様に前記側柱及び中柱間にPCc梁部材を接
合し、以下前記工程を反覆するものである。
(Means for Solving the Problems) In order to achieve the above-mentioned object, according to the method for constructing an underground framework according to the present invention, the positions of the side columns and middle columns of the building are excavated from the root cutting bottom ground, and each excavation PC with beams and underground walls in each hole
After inserting the side columns and the PC center column up to the support layer, connect the PCc beam member between the side column and the center column, then excavate the ground, and insert the PCc beam member between the side column and the center column in the same manner as above. Then, the above steps are repeated.

(作用) 本発明によれば前記したように、根伐り底地盤より建物
の側柱及び中柱位置を掘削し、同各掘削孔に梁、地中壁
付きのPC側柱及びPC中柱を支持層まで挿入し、上部
地下躯体の柱、杭を先行して施工し、前記側柱及び中柱
間にPCc梁部材を接合し、地下躯体上部を構築する。
(Function) According to the present invention, as described above, the positions of the side pillars and middle pillars of the building are excavated from the ground at the bottom of the cutting, and the beams, the PC side pillars with underground walls, and the PC middle pillars are installed in each excavated hole. The supporting layer is inserted, the columns and piles of the upper underground framework are constructed in advance, and the PCc beam members are joined between the side columns and middle columns to construct the upper part of the underground framework.

更に前記側柱に付設された地中壁を山留壁とし、同側柱
及び前記中柱間に接合されたPC大梁部材を切梁として
利用して、地盤を掘削して、同掘削部におけるPC側柱
及びPCc柱間にPC大梁部材を連結して下部の地下躯
体を構築し、以下前記同様の工程を反覆して地下躯体を
構築するとともに、前記PC側柱及び中柱に地下製体の
柱と杭とを兼用せしめるものである。
Furthermore, the ground is excavated using the underground wall attached to the side pillar as a retaining wall, and the PC girder members connected between the side pillar and the middle pillar as a strut, and the Connect the PC girder members between the PC side pillars and the PCc pillars to construct the lower underground framework, and then repeat the same process as above to construct the underground framework, and attach the underground framework to the PC side pillars and middle pillars. It is used as both a pillar and a stake.

(実施例) 以下本発明を図示の実施例について説明する。(Example) The present invention will be described below with reference to the illustrated embodiments.

地盤(1)を所定深さまで根伐りし、同相伐り底より側
柱位置及び中柱位置に支持地盤まで掘削し、各掘削孔(
2)(3)に夫々、梁(4)、地中壁(5)付きPC側
側柱法びPCc柱+81を挿入したのち、相隣るPC側
側柱法PC中柱(B1間及び相隣るPC中柱(a間にP
C大梁部材(0を接合する。
The ground (1) is cut down to a predetermined depth, and excavations are made from the bottom of the cutting to the supporting ground at the side pillar positions and middle pillar positions, and each excavation hole (
2) After inserting the beam (4), the PC side column with the underground wall (5) and the PCc column +81 into (3), insert the PC side column with the adjacent PC side column and the PC middle column (between B1 and the phase Adjacent PC middle pillar (P between a)
C girder member (join 0.

第2図はPC中柱+BlとPCc梁部材(0との接合部
を示し、PC中柱filにおけるPC大梁部材(Qの接
合部には上下−双の水平鞘管(6)が埋設されている。
Figure 2 shows the joint between the PC middle pillar +Bl and the PCc beam member (0), and the PC middle pillar fil has two horizontal sheath pipes (6) buried in the joint of the PC main beam member (Q). There is.

同各鞘管(6)にはPC中柱(印の建込み時に泥水が進
入しないように苦を嵌装しておく。またPC中柱(aの
前記接合部にはコツター(7)が設けられている。
Each of the sheath pipes (6) is fitted with a PC middle pillar (to prevent muddy water from entering during the construction of the mark). Also, a socket (7) is installed at the joint part of the PC middle pillar (a). It is being

而して接合作業に陳じては前記PC中柱(81の鞘管(
6)にラップ鉄筋(8)を横貫しておき、相隣るPC中
柱fB1間、または同PC中柱fBlとPC側柱(2)
との間にPCc梁部材(0を吊込み、同PC大梁部材C
+の端部より突出した梁鉄筋(9)を前記ランプ鉄筋(
8)と重合せしめ、PC中柱filとPCc梁部材(Q
との間に接合コンクリート(10)を打設して、PC中
柱filとPC大梁部材(C1とを接合する。
In terms of the joining work, the PC middle pillar (81 sheath pipe)
6), pass through the lap reinforcing bars (8) laterally, and connect them between the adjacent PC center columns fB1, or between the same PC center columns fBl and the PC side columns (2).
Suspend the PCc beam member (0) between the PCc beam member C
The beam reinforcing bar (9) protruding from the + end is connected to the ramp reinforcing bar (
8), and overlap the PC middle column fil and PCc beam member (Q
Joining concrete (10) is poured between the two to join the PC center column fil and the PC main beam member (C1).

図中(11)は型枠である。In the figure (11) is the formwork.

第3図はPC側柱(2)とPC大梁部材(Oとの接合部
を示し、同PC側柱因に埋設された一端部がPC側柱^
の外周面に開口した鞘管(12)の他端部を、アンカー
鉄筋(13)を介してPC側柱囚に定着されたアンカー
金物(14)に定着し、同アンカー金物(14ンの雌ね
し孔に一端部を螺着されたねじ付きラップ鉄筋(15)
の他端部を前記PC側側柱法り突出せしめ、同う。
Figure 3 shows the joint between the PC side column (2) and the PC girder member (O), and one end buried in the PC side column is the PC side column ^
The other end of the sheath pipe (12), which is open on the outer peripheral surface of Threaded lap reinforcing bar with one end screwed into a tapped hole (15)
The other end is made to protrude from the side pillar on the PC side, and the same is true.

ブ鉄筋(15)とPC大梁部材fclの端面より突出し
た梁鉄筋(9)とを重合せしめ、同PC大梁部材(C1
と前記PC側柱(2)とを接合コンクリートを介して結
合するものである。
The beam reinforcing bars (15) and the beam reinforcing bars (9) protruding from the end face of the PC girder member fcl are overlapped, and the PC girder member (C1
and the PC side pillar (2) are connected via joint concrete.

図中(16)は接合コンクリート打設用型枠である。In the figure (16) is a formwork for pouring concrete.

かくして梁、地中壁付きPC側側柱法PC中柱(B1間
、及びPC中柱(a同志をPCc梁部材(0で接合した
のち前記梁(4)、地中壁(5)を山留壁とし、前記各
PCc梁部材(0を切梁として利用し、前記根伐り底よ
り更に一定深度掘削して、前記同様にしてPC側柱t”
y及びPC中柱(BJをPC大梁部材(Qで連結し、以
下前記同様の工程を反覆して地下躯体を構築する。
In this way, the beam, PC side column with underground wall PC middle column (between B1 and PC middle column (a) are connected with PCc beam member (0), and then the beam (4) and underground wall (5) are connected to the mountain. Using each PCc beam member (0 as a strut), excavate to a certain depth from the bottom of the cutting, and install PC side pillars t'' in the same manner as above.
y and the PC center column (BJ) are connected by the PC girder member (Q), and the same steps as above are repeated to construct the underground framework.

なおPCc梁部材(0の代りに鉄骨大梁を使用してもよ
い。
Note that a steel girder may be used instead of the PCc beam member (0).

(発明の効果) 本発明によれば前記したように、根伐り底の地盤より建
物の側柱及び中柱位置に設けた掘削孔に、梁、地中壁付
きのPC側柱及びPC中柱を支持層まで挿入して、地下
躯体の柱、抗及び地中壁を施工し、前記PC側柱及びP
Cc柱間にPC大梁部材を接合することによって地下躯
体の梁を施工するとともに、同梁を切梁、前記PC側柱
の地中壁、梁を山留壁として爾後の地盤の掘削作業が安
全に行なわれるようにしたのもであり、同地盤の掘削に
伴って前記PC側柱及びPCc柱間にPCc梁部材を接
合して地下1体の下部梁を施工し、以下前記同様の工程
を反覆して地下躯体を構築するものである。
(Effects of the Invention) According to the present invention, as described above, beams, PC side columns with underground walls, and PC center columns are installed in the excavated holes made from the ground at the bottom of the cutting at the positions of the side columns and middle columns of the building. are inserted up to the supporting layer, and the pillars, shafts and underground walls of the underground framework are constructed, and the PC side pillars and P
By joining the PC girder members between the Cc columns, we can construct the beams of the underground framework, use the beams as cut beams, use the underground walls of the PC side columns, and use the beams as retaining walls to make subsequent ground excavation work safer. With the excavation of the same ground, PCc beam members were joined between the PC side columns and PCc columns to construct one underground lower beam, and the same process as described above was then carried out. The underground structure is constructed by repeating the process.

このように本発明によれば支持層まで貫入された前記P
C側柱及びPC中柱を杭として利用することlこよって
、地下躯体及び杭の施工が同時に行なわれ、従来の工法
に比して省力化され、工期が短縮され、また工場生産に
よる20部材によって地下躯体を構築するので、現場打
ちコンクリートによる施工に比して施工が簡単で、部材
に強度上のばらつきがなく、構造的に信較性の高い地下
躯体を構築することができる。
As described above, according to the present invention, the P
By using the C side pillars and the PC middle pillars as piles, the underground framework and piles can be constructed at the same time, saving labor and shortening the construction period compared to conventional construction methods. Since the underground framework is constructed using concrete, it is easier to construct than using cast-in-place concrete, there is no variation in the strength of the members, and it is possible to construct an underground framework with high structural reliability.

【図面の簡単な説明】[Brief explanation of drawings]

第1図は本発明に係る地下製体の構築方法の一実施例の
実施状況を示す斜視図、第2図及び第3図は夫々PC中
柱とPC大梁部材の接合部並にPC側柱とPC大梁部材
の接合部を示す継断面図である。 (2)・・・梁、地中壁付きPC側柱、 (&・−・P
C中柱、(0・・・PC大梁部材、      (1)
・・・地盤、(2) (3)・・・掘削孔、     
  (4)・・・梁、(5)・・・地中壁。
Fig. 1 is a perspective view showing the implementation status of one embodiment of the method for constructing an underground body according to the present invention, and Figs. 2 and 3 show the joint between the PC center column and the PC girder member, and the PC side column, respectively. FIG. 3 is a joint cross-sectional view showing the joint portion of the main beam member and the PC girder member. (2)... Beam, PC side pillar with underground wall, (&...P
C center column, (0...PC girder member, (1)
...Ground, (2) (3)...Drilling hole,
(4)...beam, (5)...underground wall.

Claims (1)

【特許請求の範囲】[Claims] 根伐り底地盤より建物の側柱及び中柱位置を掘削し、同
各掘削孔に夫々梁、地中壁付きのPC側柱及びPC中柱
を支持層まで挿入したのち、前記側柱及び中柱間にPC
大梁部材を接合し、次いで地盤を掘削し、前記同様に前
記側柱及び中柱間にPC大梁部材を接合し、以下前記工
程を反覆することを特徴とする地下躯体の構築方法。
Excavate the positions of the side columns and middle pillars of the building from the ground at the bottom of the cutting, and insert the beams, PC side columns with underground walls, and PC middle pillars into the respective excavated holes up to the supporting layer. PC for Hashirama
A method for constructing an underground framework, characterized by joining girder members, then excavating the ground, joining PC girder members between the side columns and middle columns in the same manner as described above, and repeating the above steps.
JP2157482A 1990-06-18 1990-06-18 Construction method of underground skeleton Pending JPH0449334A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
JP2157482A JPH0449334A (en) 1990-06-18 1990-06-18 Construction method of underground skeleton

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
JP2157482A JPH0449334A (en) 1990-06-18 1990-06-18 Construction method of underground skeleton

Publications (1)

Publication Number Publication Date
JPH0449334A true JPH0449334A (en) 1992-02-18

Family

ID=15650649

Family Applications (1)

Application Number Title Priority Date Filing Date
JP2157482A Pending JPH0449334A (en) 1990-06-18 1990-06-18 Construction method of underground skeleton

Country Status (1)

Country Link
JP (1) JPH0449334A (en)

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPH06228979A (en) * 1993-02-05 1994-08-16 Nippon Concrete Ind Co Ltd Inverted lining method for building-construction

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPH06228979A (en) * 1993-02-05 1994-08-16 Nippon Concrete Ind Co Ltd Inverted lining method for building-construction

Similar Documents

Publication Publication Date Title
KR100634726B1 (en) Form system for construction of underground slab and method for constructing underground slab and breast wall using the same
JP4881555B2 (en) Construction method of underground structure
KR20050098338A (en) Structure of steel pipe applied to steel pipe roof construction method for building underground structure, and steel pipe roof structure therefor using the same, and steel roof construction method thereof
JPS62288269A (en) Method for extending underground stair of building
JP7275844B2 (en) WALL-LIKE STRUCTURE AND METHOD OF CONSTRUCTING WALL-LIKE STRUCTURE
JPS63280153A (en) Underground inverted lining method
JPH0449334A (en) Construction method of underground skeleton
JP3133598B2 (en) Construction method of small and medium-sized building with basement floor
JPH0754364A (en) Construction method of basement floor
CN216193926U (en) Construction site trestle structure
JPH073777A (en) Method for constructing self-supporting land slide protection wall
KR102670462B1 (en) Permanent beam bonding structure that is joined to the core part during reverse rudder construction, permanent beam installation method using this and removal method of temporary members for joining
KR102392517B1 (en) Top-down method using by double beam system
CN215888268U (en) Utilize slant steel of steel stand biography power to trade and prop system
JPH04185816A (en) Construction of beam in underground wall
JPS6286242A (en) Reverse casting consttructin method
JP2003293363A (en) Method for constructing earth retaining wall
JP4031284B2 (en) Construction method for underground structures
JPH03147926A (en) construction method for basement
JPH02132226A (en) Method for constructing retaining wall
JPH0734449A (en) Self standing type landslide protection wall construction method
JPS6217233A (en) Foundation base column
JPH0748847A (en) Steel frame column base section structure for building with underground floor and underground skeleton construction method
JPH04360908A (en) Construction of underground continuous wall and formwork therefor
JP3061934B2 (en) Retaining wall construction method