Erection method for steel framed construction of low-rise building

Info

Publication number
JPH04333775A
JPH04333775A JP13058191A JP13058191A JPH04333775A JP H04333775 A JPH04333775 A JP H04333775A JP 13058191 A JP13058191 A JP 13058191A JP 13058191 A JP13058191 A JP 13058191A JP H04333775 A JPH04333775 A JP H04333775A
Authority
JP
Japan
Prior art keywords
steel frame
work
floor
steel
column
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Granted
Application number
JP13058191A
Other languages
Japanese (ja)
Other versions
JP2690822B2 (en
Inventor
Masaaki Kikuchi
菊地 正明
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Fujita Corp
Original Assignee
Fujita Corp
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Fujita Corp filed Critical Fujita Corp
Priority to JP3130581A priority Critical patent/JP2690822B2/en
Publication of JPH04333775A publication Critical patent/JPH04333775A/en
Application granted granted Critical
Publication of JP2690822B2 publication Critical patent/JP2690822B2/en
Anticipated expiration legal-status Critical
Expired - Fee Related legal-status Critical Current

Links

Landscapes

  • Conveying And Assembling Of Building Elements In Situ (AREA)

Abstract

PURPOSE:To make it possible to assemble the whole steel frame construction on the ground by eliminating high-place work in erection of steel-frame construc tion to promote safety of work, to execute painting work or horizontal work such as ceiling ground work, etc., together with the assembly of steel frame construction on the ground simultaneously and to reduce a construction period. CONSTITUTION:Steel frame columns 1 for a portion of one floor are so formed that they can be folded with hinges 2, and steel frame construction from the lowest floor to the highest floor is assembled on the ground in a folding state. The upper parts of the steel frame columns for the highest floor are suspended with cranes 10 through jigs 11, and erection is completed by extending the steel frame columns 1 linearly to fix.

Description

【発明の詳細な説明】[Detailed description of the invention]

【0001】0001

【産業上の利用分野】本発明は、低層建築物の鉄骨造建
方工法に関し、特に柱を蝶番で連結することにより折り
たたみ可能に形成し、低層鉄骨造の全てを折りたたんだ
状態に地組で行い、その後に最上階を吊り上げて鉄骨の
建方を行うようにしたものである。
[Industrial Application Field] The present invention relates to a method of constructing a steel frame structure for a low-rise building, and in particular, the present invention relates to a method of constructing a steel frame structure for a low-rise building. After that, the top floor was lifted and the steel frame was erected.

【0002】0002

【従来の技術】従来、低層建築物の鉄骨造の建方を行う
場合、ベースプレートを付けた2〜3層分の鉄骨柱を一
本づつ単独にしてワンブロックを建て、大梁をかけて隣
の鉄骨柱を建て、大梁をかける作業を繰り返し行うこと
により所要階の鉄骨造にしている。さらに建入りを直し
、大梁の継手をボルト又は溶接により仕上げて行くよう
にしている。これら作業のうち高所での作業は吊り作業
床から行う必要があり、そこからの墜落等を防止するた
め、安全ネットやガイドロープ等の張込み等を仮設する
必要がある。また主鉄骨柱や大梁の組立て完了後に、小
梁がけ、ボルト本締めをし、その後、デッキプレート等
の敷込みを下層より上層へと進めて鉄骨建方を完了する
。そして塗装工事、天井工事等を行うためには、鉄骨工
事とは別個の仮設足場を設けて、その上で作業を行って
いる。
[Prior Art] Conventionally, when constructing a steel frame structure for a low-rise building, one block was built using two or three layers of steel columns each with a base plate attached, and a girder was attached to the adjacent block. By repeatedly erecting steel columns and installing girders, a steel frame structure with the required floors was achieved. Furthermore, the construction work has been corrected and the girder joints are being finished by bolting or welding. Among these operations, work at high places must be performed from a suspended work floor, and to prevent falls from there, it is necessary to temporarily install safety nets, guide ropes, etc. After the main steel columns and girders are assembled, the small beams are installed and bolts are tightened, and deck plates, etc. are then laid from the lower to the upper floors to complete the steel frame erection. In order to carry out painting work, ceiling work, etc., temporary scaffolding is set up separately from the steel frame work, and work is carried out on it.

【0003】0003

【発明が解決しようとする課題】前記従来の鉄骨造の建
方では、危険な高所作業を伴うため、とび職等の専門職
でないと作業が不可能であり、また安全対策の仮設材が
各作業ごとに必要であり、作業工数が多くなって鉄骨建
方完了までにかなりの時間を要してしまう。さらに鉄骨
工事の完了後に、塗装工事や天井下地等の水平工事をし
なければならず、工期が長びいてしまう。また鉄骨造の
継手部分の検査も、鉄骨造の高い位置まで上がって確認
しなければならないので、検査に手間取るという問題も
あった。そこで本発明は、鉄骨造の建方において高所作
業をなくすことにより高所専門職以外の作業員でも建方
作業を可能とし、安全に鉄骨地組をできるようにすると
ともに、塗装工事、屋根葺工事、天井下地工事等の水平
工事を鉄骨の地組状態で行えるようにして、安全仮設用
資材の節約と鉄骨建方時の災害の発生を低減することを
目的とする。
[Problems to be Solved by the Invention] The above-mentioned conventional construction of steel structures involves dangerous work at high places, so only professionals such as jumpers can perform the work, and temporary materials are required for safety measures. This is necessary for each task, which increases the number of man-hours and takes a considerable amount of time to complete the erection of the steel frame. Furthermore, after the steel frame work is completed, horizontal work such as painting and ceiling foundation work must be done, which lengthens the construction period. Furthermore, when inspecting joints in steel structures, it is necessary to go up to a high position on the steel structure, which causes the problem of time-consuming inspections. Therefore, the present invention eliminates work at heights when constructing steel structures, thereby making it possible for workers other than those working in high places to carry out erection work, enabling safe steel frame assembly, and also allowing for painting work, roofing work, etc. The purpose of this project is to enable horizontal work such as roofing work and ceiling foundation work to be carried out while the steel frame is assembled, thereby saving materials for safe temporary construction and reducing the occurrence of disasters during steel frame construction.

【0004】0004

【課題を解決するための手段】本発明は低層建築物の鉄
骨造の建方に際し上記目的を達成したものであり、一層
分の柱鉄骨を柱脚近くと大梁下端付近の2カ所で蝶番に
より折りたたみ可能に形成して、最下階から最上階まで
の鉄骨造を折りたたんだ状態に地組で行うようにした。 そして最上階の上部を吊り枠治具を介してクレーンで吊
り上げて折りたたみみ状態の柱鉄骨を全て直線状に伸ば
すとともに、各柱鉄骨の接合部分を溶接やボルトで固定
することにより鉄骨造の建方を完了する。なお、各階の
鉄骨の組立てに伴い、各階のデッキプレートを順次敷込
むとともに、塗装工事や天井工事等の水平作業をも行う
ようにしてもよい。
[Means for Solving the Problems] The present invention has achieved the above object when constructing a steel frame structure for a low-rise building, and the steel columns for one story are hinged at two locations, near the column base and near the bottom end of the girder. It was designed to be foldable, and the steel structure from the bottom floor to the top floor was assembled into a folded state. Then, the upper part of the top floor is lifted by a crane using a hanging frame jig, and all the collapsed column steel frames are stretched in a straight line, and the joints of each column steel frame are fixed with welding or bolts to complete the construction of the steel structure. Complete the process. Incidentally, along with the assembly of the steel frame for each floor, the deck plates for each floor may be sequentially laid, and horizontal work such as painting work and ceiling work may also be performed.

【0005】[0005]

【作用】上記の低層建築物の鉄骨造建方工法では、鉄骨
柱を折りたたみ可能に形成しているので、低層建築物の
下階から最上階まで全てを折りたたんだ状態に地組で行
うことができ、高所専門職でなくても、安全対策の仮設
資材をほとんど設けない状態で安全に全体を組立てて建
てることができる。
[Operation] In the steel frame construction method for low-rise buildings mentioned above, the steel columns are formed so that they can be folded, so it is possible to assemble the entire structure from the bottom floor to the top floor of the low-rise building in a folded state. Even if you are not an expert on heights, you can safely assemble and build the entire structure with almost no temporary materials required for safety measures.

【0006】[0006]

【実施例】本発明の実施例を図1〜4により説明する。 低層建築物の鉄骨造に使用する一層分の柱鉄骨1は、柱
脚近くと大梁下端付近の2カ所でそれぞれ蝶番2により
折りたたみ可能に形成したものを使用する。なお、柱鉄
骨1への蝶番2の取付けは、柱鉄骨1の断面形状の違い
により図3の3つの態様に示すように取付けられる。初
めに複数の柱鉄骨1の下端を所定位置に固定するため、
複数のベースプレート3を所定の据え付け位置にそれぞ
れ正確にセットする。
[Embodiment] An embodiment of the present invention will be explained with reference to FIGS. 1 to 4. A single-story column steel frame 1 used for the steel frame construction of a low-rise building is formed so as to be foldable with hinges 2 at two locations, near the column base and near the bottom end of the girder. The hinge 2 is attached to the column steel frame 1 in three ways as shown in FIG. 3 depending on the cross-sectional shape of the column steel frame 1. First, in order to fix the lower ends of the plurality of column steel frames 1 in a predetermined position,
A plurality of base plates 3 are each accurately set at a predetermined installation position.

【0007】次いで蝶番2で折りたたまれた状態の鉄骨
柱1の下端を各ベースプレート3の位置にセットする。 この場合、床上にウマ4とジャッキ5を使用して、折り
たたまれた柱鉄骨1の各部分が水平状と鉛直状になるよ
うにレベル調整して据え付ける。この後、据え付けた各
柱鉄骨1の間に大梁6をセットするとともに、小梁7を
もセットする。さらに水平通し等を調整して梁のボルト
締めを行い、かつ柱鉄骨1の下端をベースプレート3に
溶接して固定する。この後、各柱鉄骨1の間の梁上にデ
ッキプレート8等を敷込んで緊結し、同時に塗装工事、
天井下地工事、設備工事等の水平作業を行い、最下階の
作業を完了する。
[0007] Next, the lower end of the steel column 1 in the folded state with the hinge 2 is set at the position of each base plate 3. In this case, using a horse 4 and a jack 5, the folded column steel frame 1 is level-adjusted and installed so that each part is horizontal and vertical. After this, the large beams 6 are set between the installed steel columns 1, and the small beams 7 are also set. Furthermore, the horizontal passage etc. are adjusted and the bolts of the beam are tightened, and the lower end of the column steel frame 1 is welded and fixed to the base plate 3. After this, deck plates 8 etc. are laid on the beams between each column steel frame 1 and tied together, and at the same time painting work is carried out.
Perform horizontal work such as ceiling foundation work and equipment work, and complete work on the lowest floor.

【0008】次に、前記最下階に相当する鉄骨組の上に
、同様に折りたたみ可能に形成した柱鉄骨1を使用して
中層階の鉄骨を折りたたんだ状態に組立てる。この場合
、中層階の柱鉄骨1の下端を、最下階の柱鉄骨1の上端
に蝶番2を介して取付け、またウマ4やジャッキ5等を
使用して柱鉄骨1の各部分が水平状と鉛直状になるよう
にする。さらに大梁6、小梁7も最下階と同様に組立て
た後、デッキプレート8等を敷き込んで緊結し、さらに
塗装工事、天井下地工事等の水平作業を進める。
[0008] Next, on the steel frame corresponding to the lowest floor, the steel frame for the middle floor is assembled in a folded state using the column steel frame 1 which is also formed to be foldable. In this case, the lower end of the column steel frame 1 on the middle floor is attached to the upper end of the column steel frame 1 on the lowest floor via the hinge 2, and each part of the column steel frame 1 is adjusted horizontally using a horse 4, a jack 5, etc. and make it vertical. Furthermore, after assembling the large beams 6 and small beams 7 in the same manner as for the lowest floor, deck plates 8 and the like are laid and tied together, and horizontal work such as painting and ceiling foundation work is proceeded.

【0009】中層階の鉄骨の組立てが完了した後、最上
階の鉄骨の組立ても中層階と同様に折りたたんだ状態に
行う。そして、最上階の組立てた鉄骨の上に折版等の屋
根材9を葺く。以上の最下階から最上階までの鉄骨の組
立て及び水平作業は全て地組される。なお、全ての柱鉄
骨1は折りたたんだ状態にあるので、その組立て状態で
の各階の高さは1500〜2000mmであり、高所作
業となることがないので安全仮設資材をほとんど使用す
ることなく安全に作業することができる。
After the assembly of the steel frame for the middle floor is completed, the steel frame for the top floor is also assembled in a folded state in the same way as for the middle floor. Then, a roofing material 9 such as a folded plate is placed on the assembled steel frame on the top floor. All of the above steel frame assembly and horizontal work from the bottom floor to the top floor will be carried out on the ground. In addition, since all the column steel frames 1 are in a folded state, the height of each floor in the assembled state is 1500 to 2000 mm, and there is no need to work at heights, so safety can be achieved without using much temporary construction materials. be able to work on it.

【0010】上記のように組上がった鉄骨造の建方を行
うためには、図4に示すようにクレーン10により吊り
上げて行ない、その場合、鉄骨造の重量によりクレーン
の吊り上げ能力と台数を調整する。すなわち、最上階の
柱鉄骨1の上部に吊り枠治具11を取付け、クレーン1
0により吊り枠治具11を吊り上げることにより、最上
階の折りたたまれた柱鉄骨1を直線状に伸びた状態にす
る。なお柱鉄骨1を直線状に伸ばすときに、内部に位置
する部分を横方向に引っ張り出すようにするのが望まし
い。また吊り上げ治具11は、鉄骨造を水平状態を保っ
て吊り上げられるように、例えば水平枠11aとその上
部水平棒11bとをワイヤー11cで連結した構成にな
っている。そして直線状に伸ばした各柱鉄骨1の折り曲
げ接続部に、ブレースを当てて仮ボルトにより固定する
。次いで中層階、最下階の順に吊り上げて、各柱鉄骨1
の接続部をブレースと仮ボルトを使用して固定するとと
もに、各柱鉄骨1の接合部の溶接を行なうことにより鉄
骨造の建方を完了する。なお、低層建築物の平面建て坪
が大きい場合は、鉄骨造の吊り上げを部分ごとに行なう
ことも可能である。
In order to erect the steel structure assembled as described above, it is lifted by a crane 10 as shown in FIG. 4. In this case, the lifting capacity and number of cranes are adjusted depending on the weight of the steel structure. do. That is, the hanging frame jig 11 is attached to the top of the column steel frame 1 on the top floor, and the crane 1 is
By lifting the hanging frame jig 11 using 0, the folded column steel frame 1 on the top floor is made to extend linearly. Note that when extending the column steel frame 1 in a straight line, it is desirable to pull out the inner portion laterally. Further, the lifting jig 11 has a structure in which, for example, a horizontal frame 11a and its upper horizontal bar 11b are connected by a wire 11c so that the steel frame structure can be lifted while maintaining a horizontal state. Then, braces are applied to the bent joints of each straightly stretched column steel frame 1 and fixed with temporary bolts. Next, lift the middle floor and the bottom floor in that order, and attach 1 steel frame to each column.
The erection of the steel structure is completed by fixing the joints using braces and temporary bolts, and welding the joints of each column steel frame 1. If the floor plan of a low-rise building is large, it is also possible to lift the steel frame section by section.

【0011】[0011]

【発明の効果】本発明の低層建築物の鉄骨造建方工法に
よれば、柱鉄骨を折りたたんだ状態で下階から最上階ま
でを地組することができるので、高所作業になることが
なく、専門職でなくとも安全に作業でき、安全仮設用資
材が少なくて済み、鉄骨建方時の墜落災害を少なくする
ことができる。また塗装工事や天井下地工事等の水平部
分の工事を、鉄骨造の組立て作業と平行して行なえると
ともに、高所作業となることがないので、安全対策が楽
になる。さらに鉄骨造の継手部分の検査も鉄骨造を吊り
上げる前に行なえるので、検査が簡単である。
[Effects of the Invention] According to the steel frame construction method for low-rise buildings of the present invention, it is possible to assemble the ground from the bottom floor to the top floor with the column steel frames folded, so there is no need to work at heights. This means that even non-professionals can work safely, less materials are required for safety temporary construction, and the risk of falling during steel frame erection can be reduced. In addition, horizontal work such as painting work and ceiling foundation work can be carried out in parallel with the steel structure assembly work, and safety measures are made easier because the work does not have to be carried out at heights. Furthermore, the inspection of the joints of the steel structure can be carried out before the steel structure is lifted, making the inspection easy.

【図面の簡単な説明】[Brief explanation of drawings]

【図1】本発明の鉄骨造建方工法を示す正面図である。FIG. 1 is a front view showing the steel frame construction method of the present invention.

【図2】本発明の鉄骨造建方工法を示す部分拡大図であ
る。
FIG. 2 is a partially enlarged view showing the steel frame construction method of the present invention.

【図3】柱鉄骨への蝶番の取付け状態を示す3つの態様
である。
FIG. 3 shows three aspects of how the hinge is attached to the steel column.

【図4】本発明の鉄骨造建方工法により折りたたみ状態
の鉄骨造を吊り上げる状態の斜視図である。
FIG. 4 is a perspective view of a folded steel structure being lifted up using the steel structure construction method of the present invention.

【符号の説明】[Explanation of symbols]

1  柱鉄骨 2  蝶番 8  デッキプレート 9  屋根材 10  クレーン 11  吊り枠治具 1 Column steel frame 2 Hinge 8 Deck plate 9 Roofing material 10 Crane 11 Hanging frame jig

Claims (2)

【特許請求の範囲】[Claims] 【請求項1】  低層建築物の鉄骨造の建方に際し、一
層分の柱鉄骨を柱脚近くと大梁下端付近の2カ所で蝶番
により折りたたみ可能に形成して、最下層の柱鉄骨の下
部を所定の据え付け位置にセットし、最下層の折りたた
んだ状態の柱鉄骨に梁鉄骨を組立てた後、蝶番により折
りたたんだ柱鉄骨と梁鉄骨とで順次上層階を組立てて最
上階までの鉄骨造を地組で行い、その後、最上階の上部
を吊り枠治具を介してクレーンで吊り上げて、折りたた
んだ状態の柱鉄骨を直線状に伸ばすとともに、各柱鉄骨
の接合部分を溶接やボルトにより固定することを特徴と
する低層建築物の鉄骨造建方工法。
[Claim 1] When constructing a steel frame structure for a low-rise building, the column steel frame for one layer is formed so that it can be folded with hinges in two places, near the column base and near the bottom end of the girder, so that the lower part of the column steel frame on the lowest floor is foldable. After setting the steel frame at the specified installation position and assembling the beam steel frame to the folded column steel frame on the lowest floor, the upper floors are sequentially assembled using the folded column steel frame and beam steel frame using hinges, and the steel structure up to the top floor is placed on the ground. After that, the upper part of the top floor is lifted by a crane using a hanging frame jig, the collapsed column steel frames are stretched in a straight line, and the joints of each column steel frame are fixed by welding or bolts. A steel frame construction method for low-rise buildings characterized by:
【請求項2】  各階の鉄骨の組立てに伴い、各階のデ
ッキプレートを順次敷込むとともに、塗装工事や天井工
事等の水平作業をも行うようにした請求項1に記載の低
層建築物の鉄骨造建方工法。
Claim 2: The steel frame construction of a low-rise building according to claim 1, wherein deck plates for each floor are sequentially laid as the steel frames for each floor are assembled, and horizontal work such as painting work and ceiling work is also performed. Construction method.
JP3130581A 1991-05-02 1991-05-02 Steel construction method for low-rise buildings Expired - Fee Related JP2690822B2 (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
JP3130581A JP2690822B2 (en) 1991-05-02 1991-05-02 Steel construction method for low-rise buildings

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
JP3130581A JP2690822B2 (en) 1991-05-02 1991-05-02 Steel construction method for low-rise buildings

Publications (2)

Publication Number Publication Date
JPH04333775A true JPH04333775A (en) 1992-11-20
JP2690822B2 JP2690822B2 (en) 1997-12-17

Family

ID=15037642

Family Applications (1)

Application Number Title Priority Date Filing Date
JP3130581A Expired - Fee Related JP2690822B2 (en) 1991-05-02 1991-05-02 Steel construction method for low-rise buildings

Country Status (1)

Country Link
JP (1) JP2690822B2 (en)

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN103696577A (en) * 2013-12-16 2014-04-02 上海建工五建集团有限公司 Overhead steel-beam stress platform and construction method thereof

Citations (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPS5659944A (en) * 1979-10-22 1981-05-23 Taiyo Kk Assembly of building frame
JPS5659943A (en) * 1979-10-22 1981-05-23 Taiyo Kk Assembly of building frame
JPS6062370A (en) * 1983-09-17 1985-04-10 清水建設株式会社 Pillar and beam iron skeletal
JPS63280135A (en) * 1987-05-12 1988-11-17 清水建設株式会社 Rotary assembling construction method for reinforcement beam

Patent Citations (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPS5659944A (en) * 1979-10-22 1981-05-23 Taiyo Kk Assembly of building frame
JPS5659943A (en) * 1979-10-22 1981-05-23 Taiyo Kk Assembly of building frame
JPS6062370A (en) * 1983-09-17 1985-04-10 清水建設株式会社 Pillar and beam iron skeletal
JPS63280135A (en) * 1987-05-12 1988-11-17 清水建設株式会社 Rotary assembling construction method for reinforcement beam

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN103696577A (en) * 2013-12-16 2014-04-02 上海建工五建集团有限公司 Overhead steel-beam stress platform and construction method thereof

Also Published As

Publication number Publication date
JP2690822B2 (en) 1997-12-17

Similar Documents

Publication Publication Date Title
JP2928948B2 (en) Construction method of large span roof
US12012745B2 (en) System and apparatus for securing a floorplate to a structure
US20050066609A1 (en) Preassembled roof and floor deck panel system
JP6712501B2 (en) High-rise building demolition system and demolition method
JPH07292986A (en) Device and method for constructing long-span roof
JP2018199933A (en) Structure body and construction method of structure constructed on top of tower-like building
JPH06323503A (en) Assembling method for large size suspension type boiler
JPH04333775A (en) Erection method for steel framed construction of low-rise building
JP3061560B2 (en) Tent warehouse and its construction method
JPH05133016A (en) Peripheral supporting self-rising type building engineering method
JP2021116153A (en) Supporting platform for tower crane and climbing method using the same
US3435583A (en) Method of forming buildings
RU2808791C1 (en) Multifunctional lifting system
RU2758824C1 (en) Device for restoring the design position of the outer wall panel of the attic of a large-panel building
JP3187618B2 (en) How to assemble beam reinforcement
CN115162823B (en) Assembling method of pinnacle steel member
JP2004270377A (en) Column-beam preassembled reinforcement body, and preassembled reinforcement method using the same
JP3100574B2 (en) Suspended scaffold and its erection method
JPH0513862Y2 (en)
JP2022177571A (en) Construction method of structure
JPH0339538A (en) Construction work of wooden building
RU2651558C2 (en) Method of establishing walls of the shield (panel) building
SU1110884A1 (en) Suspended scaffolding
JP3364426B2 (en) How to build pillars
JPH0447072A (en) Construction method for multistory building and its device

Legal Events

Date Code Title Description
LAPS Cancellation because of no payment of annual fees