JPH0433326B2 - - Google Patents

Info

Publication number
JPH0433326B2
JPH0433326B2 JP13949787A JP13949787A JPH0433326B2 JP H0433326 B2 JPH0433326 B2 JP H0433326B2 JP 13949787 A JP13949787 A JP 13949787A JP 13949787 A JP13949787 A JP 13949787A JP H0433326 B2 JPH0433326 B2 JP H0433326B2
Authority
JP
Japan
Prior art keywords
water
trench
sheet
construction
wall
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Expired
Application number
JP13949787A
Other languages
Japanese (ja)
Other versions
JPS63304821A (en
Inventor
Nobuyuki Matsui
Shozo Konno
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Kajima Corp
Original Assignee
Kajima Corp
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Kajima Corp filed Critical Kajima Corp
Priority to JP13949787A priority Critical patent/JPS63304821A/en
Priority to US07/196,617 priority patent/US4909674A/en
Publication of JPS63304821A publication Critical patent/JPS63304821A/en
Priority to US07/460,044 priority patent/US5022792A/en
Publication of JPH0433326B2 publication Critical patent/JPH0433326B2/ja
Granted legal-status Critical Current

Links

Landscapes

  • Bulkheads Adapted To Foundation Construction (AREA)

Description

【発明の詳細な説明】 〔産業上の利用分野〕 この発明は地中連続遮水壁工法に関するもので
ある。
[Detailed Description of the Invention] [Industrial Application Field] This invention relates to an underground continuous impermeable wall construction method.

〔この発明が解決すべき問題点〕[Problems to be solved by this invention]

地下構造物を施工中の地下水の湧水を防ぎ、或
いはダム工事における地下水の止水等を目的とし
て地中連続壁を構築するか、シートパネルを打設
してジヨイント部に注入を行う等の工法が採用さ
れている。
In order to prevent groundwater from springing up during construction of underground structures or to stop groundwater during dam construction, it is necessary to construct an underground continuous wall, or to pour sheet panels into joints. construction method has been adopted.

これら従来の工法を止水のみを目的として構築
する場合、以下のような問題点がある。
When using these conventional construction methods for the sole purpose of water stopping, there are the following problems.

イ 地中連続壁は必要以上の壁厚を施工するのが
通常であり、施工が不必要に大がかりとなると
ともに余分なコンクリートを大量に使用して施
工費が高価である。
B. Underground continuous walls are usually built with a wall thickness greater than necessary, making the construction unnecessarily large-scale and using a large amount of excess concrete, resulting in high construction costs.

ロ シートパイルを打設してジヨイント部に注入
を行う工法も同じく施工が大がかりであり、材
料費が高価である。
The method of driving sheet piles and injecting into the joints also requires extensive construction and is expensive in material cost.

ハ 地中連続壁において施工費を安価にするため
に壁厚を薄く造ることも考えられるが、狭巾の
溝を掘削し得る機械もなく、例え狭巾の溝が掘
れたとしてもコンクリートの流動性が損なわれ
て均質な地中壁は完成できない。
C. It is possible to make the wall thickness thinner in order to reduce construction costs for underground continuous walls, but there are no machines that can excavate narrow trenches, and even if a narrow trench can be dug, the flow of concrete A homogeneous underground wall cannot be completed due to the loss of properties.

ニ また止水の確実性及び信頼性の点で見れば、
コンクリート壁は地震時のクラツクが止水性を
損なわせ、プレキヤストコンクリートパネルや
シートパイルを使用した工法ではジヨイント部
に夾雑物、ベントナイト等を挟み込み充分な止
水性能を得ることができなかつた。
D. Also, from the point of view of water stoppage certainty and reliability,
Cracks during earthquakes impair the water-stopping properties of concrete walls, and construction methods using precast concrete panels or sheet piles were unable to obtain sufficient water-stopping performance due to contaminants, bentonite, etc. being trapped in the joints.

この発明は、施工が容易であつて施工費が安価
となり、且つ止水の確実性、信頼性の高い遮水壁
を構築可能な地中連続遮水壁工法を提供すること
を目的とする。
An object of the present invention is to provide an underground continuous impermeable wall construction method that is easy to construct, has low construction cost, and can construct an impermeable wall that is highly reliable and reliable in stopping water.

〔問題点を解決するための手段〕[Means for solving problems]

この発明にかかる地中連続遮水壁工法は、複数
本の鋼製の支柱間に張設した遮水シートを使用す
るものである。
The continuous underground impermeable wall construction method according to the present invention uses a impermeable sheet stretched between a plurality of steel supports.

地盤に溝を掘削する。この溝内に上記遮水シー
トを配設し、溝を巾方向左右に仕切るようにす
る。溝内に硬化材を注入して泥水固化、或いは溝
内にソイルモルタルを充填し遮水壁を構築する。
Dig a trench in the ground. The above-mentioned water-blocking sheet is disposed within this groove so as to partition the groove into left and right sides in the width direction. A hardening material is injected into the groove to solidify the muddy water, or a water-blocking wall is constructed by filling the groove with soil mortar.

溝掘削、遮水シート配設、泥水固化という簡易
な施工によつて構築でき、施工費を安価にするこ
とができる。
It can be constructed by simple construction such as trench excavation, installation of water-shielding sheets, and solidification of muddy water, and construction costs can be reduced.

地震によつてクラツクが生ずる等があつても遮
水シートによつて止水性が損なわれることがな
い。
Even if cracks occur due to an earthquake, the water-stopping properties of the water-blocking sheet will not be impaired.

〔実施例〕〔Example〕

以下、図に示す一実施例に基づきこの発明を詳
細に説明する。
Hereinafter, the present invention will be explained in detail based on an embodiment shown in the drawings.

(1) 溝掘削 地盤に溝1を掘削する。溝1の巾は大きくな
くともよく、その分施工が大がかりとならな
い。溝1の掘削にはオーガ等を使用し、溝1内
には安定液として泥水2を充填する。また溝壁
が強固な場合は泥水2を使用せずともよい。
(1) Trench excavation Dig trench 1 in the ground. The width of the groove 1 does not need to be large, so the construction does not require a large scale. An auger or the like is used to excavate the groove 1, and the groove 1 is filled with muddy water 2 as a stabilizing liquid. Further, if the groove wall is strong, the muddy water 2 may not be used.

(2) 遮水シート 遮水シート3はポリエチレンシート等が採用
でき、鋼製の複数本の支柱4に張設する。
(2) Water-shielding sheet The water-shielding sheet 3 can be made of polyethylene sheet, etc., and is stretched over multiple steel supports 4.

支柱4としてはH型鋼等が採用できる。支柱
4は一枚の遮水シート3の左右いずれか一端近
くに固着してある。遮水シート3の左右端には
全長にフアスナー5,5が取付けてある。また
遮水シート3の支柱4近くにはポケツト状のパ
ツカー6が縫込んである。以上のような複数本
の遮水シート3がフアスナー5,5によつて連
続的に繋いである。
As the support 4, H-type steel or the like can be used. The support column 4 is fixed near one end of one of the right and left ends of one sheet of water-shielding sheet 3. Fasteners 5, 5 are attached to the left and right ends of the water-shielding sheet 3 over the entire length. Further, a pocket-shaped packer 6 is sewn into the water-shielding sheet 3 near the pillar 4. A plurality of water-shielding sheets 3 as described above are continuously connected by fasteners 5, 5.

(3) 遮水シートの配設(第1図) 遮水シート3を折畳んだままで支柱4ととも
に溝1内に降下する。掘削した溝1の長さに応
じて所要枚数の遮水シート3を張出して、溝1
を巾方向に仕切るよう配設する。
(3) Arranging the water-shielding sheet (Fig. 1) With the water-shielding sheet 3 folded, lower it into the groove 1 together with the pillar 4. Depending on the length of the trench 1 that has been excavated, the required number of water-blocking sheets 3 are stretched out, and the trench 1 is
Arranged so that it is partitioned in the width direction.

また第2図に示すように遮水シート3をフア
スナー5,5によつて更に継ぎ足す。
Further, as shown in FIG. 2, the water-blocking sheet 3 is further joined with fasteners 5, 5.

(4) 泥水固化 配設した遮水シート3のパツカー6内にエア
若しくは水を注入して、溝1を仕切る。このパ
ツカー6によつて仕切られた溝1内に硬化材を
注入して泥水2を固化する。硬化材としてはモ
ルタル、コンクリート等が使用できる。泥水2
が固化して遮水シート3を内側に挟んだ遮水壁
が完成する。
(4) Solidification of muddy water Air or water is injected into the tanker 6 of the installed water-blocking sheet 3 to partition the groove 1. A hardening material is injected into the groove 1 partitioned by the packer 6 to solidify the muddy water 2. Mortar, concrete, etc. can be used as the hardening material. muddy water 2
solidifies, and a water-shielding wall with the water-shielding sheet 3 sandwiched inside is completed.

その後溝1掘削を進めるとともに遮水シート
3を随時溝1内に配設し、泥水固化によつて遮
水壁を続けて構築する。また泥水を使用しない
場合には、溝内にソイルモルタルを充填しても
よい。
Thereafter, as the trench 1 is excavated, a water-blocking sheet 3 is placed in the trench 1 as needed, and a water-blocking wall is successively constructed by solidifying the muddy water. In addition, if muddy water is not used, soil mortar may be filled in the groove.

〔発明の効果〕〔Effect of the invention〕

この発明は以上のような鋼製を有し、以下のよ
うな効果を得ることができる。
This invention has the above-mentioned steel construction, and can obtain the following effects.

イ 溝を掘削し、遮水シートを配設し、泥水を固
化、或いはソイルモルタルを充填するだけであ
るため、施工は容易となり、大がかりな施工は
不要で施工費は安価となる。
(b) Construction is easy, as it only involves digging a trench, installing a water-blocking sheet, solidifying muddy water, or filling it with soil mortar, and there is no need for large-scale construction, resulting in low construction costs.

ロ 完成した遮水壁は内側に遮水シートを挟み込
むために、地震等によるクラツクが発生しても
止水が損なわれることがなく、確実性、信頼性
が高くなる。
(b) Since the completed water-shielding wall has a water-shielding sheet sandwiched inside, water-stopping will not be impaired even if cracks occur due to earthquakes, etc., and reliability and reliability will be high.

ハ 泥水を固化、或いはソイルモルタルを充填し
て構築するため、地中壁全体を均一な地中壁と
することができる。また例え強度の低下する部
分が生じても上記のように遮水シートによつて
止水性は確保される。
C) Because the wall is constructed by solidifying muddy water or filling it with soil mortar, the entire underground wall can be made into a uniform underground wall. Furthermore, even if there is a portion where the strength is reduced, water-stopping properties are ensured by the water-blocking sheet as described above.

ニ 鋼製の支柱によつて遮水シートを支えるた
め、シートがたわむ恐れがないとともに支柱に
よつて遮水壁が補強される。
D. Since the water-shielding sheet is supported by steel columns, there is no risk of the sheet bending, and the water-shielding wall is reinforced by the columns.

【図面の簡単な説明】[Brief explanation of drawings]

第1図〜第3図はこの発明にかかる地中連続遮
水壁工法の一実施例の施工順序を示すもので
()は平面図、()は縦断面図である。 1……溝、2……泥水、3……遮水シート、4
……支柱、5……フアスナー、6……パツカー。
1 to 3 show the construction order of one embodiment of the underground continuous impermeable wall construction method according to the present invention, in which () is a plan view and () is a longitudinal sectional view. 1...Gutter, 2...Muddy water, 3...Waterproof sheet, 4
...Strut, 5...Fassner, 6...Patzker.

Claims (1)

【特許請求の範囲】[Claims] 1 地盤に溝を掘削し、複数本の鋼製の支柱間に
張設した遮水シートを溝内に降下し、溝を巾方向
左右に仕切るよう溝内に配設し、溝内に硬化材を
注入して泥水固化、或いは溝内にソイルモルタル
を充填し遮水壁を構築することを特徴とする地中
連続遮水壁工法。
1 A trench is excavated in the ground, a water-blocking sheet stretched between multiple steel supports is lowered into the trench, and a hardened material is placed inside the trench to divide the trench into left and right sides in the width direction. An underground continuous impermeable wall construction method characterized by injecting soil to solidify mud, or by filling a trench with soil mortar to construct an impermeable wall.
JP13949787A 1987-05-28 1987-06-03 Construction work of underground continuous cut-off wall Granted JPS63304821A (en)

Priority Applications (3)

Application Number Priority Date Filing Date Title
JP13949787A JPS63304821A (en) 1987-06-03 1987-06-03 Construction work of underground continuous cut-off wall
US07/196,617 US4909674A (en) 1987-05-28 1988-05-19 Underground continuous impervious wall and method for installing same
US07/460,044 US5022792A (en) 1987-05-28 1990-01-02 Undergrond continuous impervious wall and method for installing same

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
JP13949787A JPS63304821A (en) 1987-06-03 1987-06-03 Construction work of underground continuous cut-off wall

Publications (2)

Publication Number Publication Date
JPS63304821A JPS63304821A (en) 1988-12-13
JPH0433326B2 true JPH0433326B2 (en) 1992-06-02

Family

ID=15246651

Family Applications (1)

Application Number Title Priority Date Filing Date
JP13949787A Granted JPS63304821A (en) 1987-05-28 1987-06-03 Construction work of underground continuous cut-off wall

Country Status (1)

Country Link
JP (1) JPS63304821A (en)

Families Citing this family (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPH05163720A (en) * 1991-12-18 1993-06-29 Fusao Sakano Underground wall and construction of continuous underground wall
JPH06341140A (en) * 1993-02-04 1994-12-13 Fusao Sakano Construction method by which column-wall holes are bored within approximate line by 10-700mm from boundary by intermittent work and continuous wall, connection wall, butt-joint wall, superposed wall, and cut-off wall are erected by use of the hole, and these walls
JPH06341141A (en) * 1993-02-17 1994-12-13 Fusao Sakano Construction method of underground earth retaining wall by bored holes excavated in the ground within line separated from boundary by 500mm, and various walls like joint wall, connection wall, butt-joint wall, continuousline wall, superposed wall, cut-off wall by use the method

Also Published As

Publication number Publication date
JPS63304821A (en) 1988-12-13

Similar Documents

Publication Publication Date Title
CA1185441A (en) Process of forming a continuous wall in the ground
JP4485006B2 (en) Construction method for underground structures
JPH0433326B2 (en)
JPH09158174A (en) Water stopping mechanism and method between case bodies of underground continuous wall
JPS5936058B2 (en) How to construct a structure using underground continuous walls
JP2565452B2 (en) Construction method of self-supporting retaining wall
JPS5944431A (en) Construction of basement
JPH01190819A (en) Method for constructing under-ground continuous impervious wall
JP3098458B2 (en) Construction method of multi-functional underground diaphragm wall
JP2693028B2 (en) Construction method of human hole in middle of pipeline
JPS6043495B2 (en) How to build a retaining wall
JPH01235715A (en) Underground continuous impermeable wall method
JP2576902B2 (en) Construction methods and buildings in landfills
JPH0310200Y2 (en)
JP3240394B2 (en) Construction method of impermeable wall
JPH0786229B2 (en) Impermeable wall using impermeable sheet, construction method thereof, and impermeable sheet used for impermeable wall
JP2556415B2 (en) Construction method of self-supporting retaining wall
JPH086326B2 (en) Reinforced soil retaining wall
JPS6262206B2 (en)
JPH0351843B2 (en)
JPS63522A (en) Underground continuous wall
JPH01163315A (en) Continuous underground wall construction
JPS63297625A (en) Underground continuous cut-off wall construction work
JPH0538125Y2 (en)
JP2524579B2 (en) Reinforcement method of existing retaining wall under water surface