JPH04237732A - Constructing method for partial precast pillar with core reinforcement bar - Google Patents

Constructing method for partial precast pillar with core reinforcement bar

Info

Publication number
JPH04237732A
JPH04237732A JP594491A JP594491A JPH04237732A JP H04237732 A JPH04237732 A JP H04237732A JP 594491 A JP594491 A JP 594491A JP 594491 A JP594491 A JP 594491A JP H04237732 A JPH04237732 A JP H04237732A
Authority
JP
Japan
Prior art keywords
column
concrete
core
core reinforcing
precast
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
JP594491A
Other languages
Japanese (ja)
Inventor
Toshio Fujiwara
敏夫 藤原
Masaru Teraoka
勝 寺岡
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Fujita Corp
Original Assignee
Fujita Corp
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Fujita Corp filed Critical Fujita Corp
Priority to JP594491A priority Critical patent/JPH04237732A/en
Publication of JPH04237732A publication Critical patent/JPH04237732A/en
Pending legal-status Critical Current

Links

Landscapes

  • Rod-Shaped Construction Members (AREA)

Abstract

PURPOSE:To enhance the effectiveness in execution of works and simplify the procedure in constructing pillars in the substratum part of a multi-storey building of ferro-concrete, wherein the substratum part includes a core steel reinforcement. CONSTITUTION:A precast pillar material A of ferro-concrete having built-in core steel reinforcement 2 is placed in a specified position, wherein a sleeve joint 1 is mounted at the pillar leg. After this pillar material A is joined with the core steel reinforcement 4 of the substratum part through the sleeve joint 1, concrete 8 is placed till the bottom of beam.

Description

【発明の詳細な説明】[Detailed description of the invention]

【0001】0001

【産業上の利用分野】本発明は高層鉄筋コンクリート(
以下RCと称す)建物の下層階の施工に適用される芯鉄
筋を有する部分プレキヤスト柱工法に係るものである。
[Industrial Application Field] The present invention applies to high-rise reinforced concrete (
(hereinafter referred to as RC) relates to a partial precast column construction method with core reinforcing bars that is applied to the construction of the lower floors of buildings.

【0002】0002

【従来の技術】高層RC建物の下層階に適用される柱は
通常の建物の柱にくらべて施工が複雑となる。図6乃至
図9は従来の柱部分の現場施工工程を示し、柱主筋a及
び芯鉄筋bを下層部の鉄筋Cと溶接w接合し、芯フープ
筋dが梁下端まで配筋し、フープ筋eを梁下端まで配筋
し、柱部分の型枠fを設置して梁下端までコンクリート
を打設する。(図6及び図7参照)先組工法の場合、柱
主筋a及びフープ筋eと、芯鉄筋b及び芯フープ筋dを
それぞれ先組し、先組した鉄筋gをクレーンによって所
定の位置に配置し、下層部の鉄筋Cと溶接w接合し、柱
部分の型枠fを設置して梁下端までコンクリートを打設
する。(図7参照)かくして梁下端までコンクリートを
打設したのち、梁接合部及びスラブ筋を配筋してコンク
リートを打設する。(図8参照)図中hは梁、iはスラ
ブである。
BACKGROUND OF THE INVENTION Columns applied to the lower floors of high-rise RC buildings are more complex to construct than columns of ordinary buildings. Figures 6 to 9 show the conventional on-site construction process for column parts, in which the main column reinforcement a and the core reinforcement b are welded together with the lower reinforcing reinforcement C, the core hoop reinforcement d is arranged up to the lower end of the beam, and the hoop reinforcement Reinforce e to the bottom end of the beam, install formwork f for the column, and pour concrete up to the bottom end of the beam. (Refer to Figures 6 and 7) In the case of pre-assembled construction method, main column reinforcement a and hoop reinforcement e, core reinforcing bar b and core hoop reinforcement d are respectively pre-assembled, and the pre-assembled reinforcing bar g is placed in a predetermined position by a crane. Then, it is welded to the reinforcing steel C on the lower layer, and the formwork f for the column part is installed, and concrete is poured to the bottom end of the beam. (See Figure 7) After concrete is poured to the bottom end of the beam, reinforcement is placed at the beam joint and slab reinforcement, and concrete is poured. (See FIG. 8) In the figure, h is a beam and i is a slab.

【0003】図10乃至図13は従来のプレキヤスト柱
の施工工程を示し、柱主筋a及び芯鉄筋bにおける下端
部にスリーブジヨイントjを有する柱プレキヤスト柱k
を所定の位置に設置し、スリーブジヨイント部に下層部
の鉄筋cを挿入して、グラウトモルタルを注入し、プレ
キヤスト柱kの主筋aと下層部の鉄筋cとを接合し、前
記の場合と同様に梁との接合部及びスラブ筋の配筋とコ
ンクリートの打設を行なう。
FIGS. 10 to 13 show the construction process of a conventional precast column.
is installed in a predetermined position, the lower reinforcing bar c is inserted into the sleeve joint, grout mortar is injected, and the main reinforcing bar a of the precast column k and the lower reinforcing bar c are joined. Similarly, the joints with the beams and slab reinforcement are placed and concrete is placed.

【0004】0004

【発明が解決しようとする課題】しかしながら前記図6
乃至図9に示す現場配筋の場合、高層RC建物では従来
のRC建物にくらべて太径の鉄筋が使用され、フープ筋
が密に配筋されるので、鉄筋の配筋、組立に時間を要し
、また鉄筋が密に配筋されるため、コンクリートの打設
が困難になる。
[Problem to be solved by the invention] However, the above-mentioned FIG.
In the case of on-site reinforcement shown in Figures 9 to 9, high-rise RC buildings use reinforcing bars with a larger diameter than conventional RC buildings, and the hoop reinforcement is densely arranged, so it takes less time to arrange and assemble the reinforcing bars. Also, because the reinforcing bars are densely arranged, concrete placement becomes difficult.

【0005】また図10乃至図13に示すプレキヤスト
柱の場合、主筋の内側に芯鉄筋が配置されるため、芯鉄
筋柱脚部のスリーブに対するグラウト注入が困難であり
、またその注入状況の確認が困難である。本発明は前記
従来技術の有する問題点に鑑みて提案されたもので、そ
の目的とする処は、施工性が向上され、省力化されると
ともに、構造的に信頼性の高い芯鉄筋を有する高層建物
における下層部のRC柱の構築方法を提供する点にある
Furthermore, in the case of the precast columns shown in FIGS. 10 to 13, since the core reinforcing bars are placed inside the main reinforcement, it is difficult to inject grout into the sleeves of the core reinforcing bar column legs, and it is difficult to confirm the grouting status. Have difficulty. The present invention has been proposed in view of the problems of the prior art, and aims to improve construction efficiency, save labor, and provide a high-rise building with core reinforcing bars that are structurally highly reliable. The object of the present invention is to provide a method for constructing RC columns in the lower part of a building.

【0006】[0006]

【課題を解決するための手段】前記の目的を達成するた
め、本発明に係る芯鉄筋を有する部分プレキヤスト柱工
法によれば、高層鉄筋コンクリート構造の下層階におけ
る芯鉄筋を有する鉄筋コンクリート柱の構築方法におい
て、柱脚、端部にスリーブジヨイントが装着された芯鉄
筋を内蔵したプレキヤスト鉄筋コンクリート柱材を所定
位置に建込み、前記スリーブジヨイントを介して前記芯
鉄筋を下階部芯鉄筋と接合したのち、梁下端部まで柱コ
ンクリートを打設するものである。
[Means for Solving the Problems] In order to achieve the above object, according to the partial precast column construction method with core reinforcement according to the present invention, a method for constructing a reinforced concrete column with core reinforcement on the lower floor of a high-rise reinforced concrete structure is provided. After erecting a precast reinforced concrete column containing a core reinforcing bar with a sleeve joint attached to the column base and end in a predetermined position, and connecting the core reinforcing bar to the lower floor core reinforcing bar via the sleeve joint, , column concrete is poured up to the bottom end of the beam.

【0007】[0007]

【作用】本発明によれば前記したように、柱脚端部にス
リーブジヨイントが装着された芯鉄筋を内蔵したプレキ
ヤストRC柱材を現場に搬入し、所定の位置に配置して
前記スリーブジヨイントを介して下層部の鉄筋と接合す
ることによって、現場における鉄筋工事が減少し、また
現場におけるコンクリート打設量が節減され施工性が向
上する。
[Operation] According to the present invention, as described above, a precast RC column material containing a built-in core reinforcing bar with a sleeve joint attached to the end of the column base is delivered to the site, placed at a predetermined position, and then the sleeve joint By connecting to the reinforcing bars in the lower layer through the ints, reinforcing steel work on site is reduced, and the amount of concrete placed on site is also reduced, improving workability.

【0008】また芯鉄筋部分と現場打設部分を異種類、
及び異種強度のコンクリートを使い分けることができ、
圧縮靭性に優れた柱部材を構成しうるものである。
[0008] Also, the core reinforcing bar part and the on-site cast part are of different types.
and can use concrete of different strengths,
It is possible to construct a column member with excellent compressive toughness.

【0009】[0009]

【実施例】AはプレキヤストRC柱材で、柱脚端部にス
リーブジヨイント1が装着された芯鉄筋2及び芯フープ
筋3が内蔵されている。而して前記プレキヤストRC柱
材Aを図1に示す如く所定位置に設置して、スリーブジ
ヨイント1に下層部芯鉄筋4を挿入し、グラウトモルタ
ルを注入して同芯鉄筋4と前記柱材Aの芯鉄筋2とを接
合する。
[Embodiment] A is a precast RC column material, and a core reinforcing bar 2 and a core hoop bar 3 with a sleeve joint 1 attached to the end of the column base are built-in. Then, the precast RC column material A is installed in a predetermined position as shown in FIG. Join core reinforcing bar 2 of A.

【0010】次いで先組鉄筋5を所定位置に設置し、(
図2参照)先組鉄筋5と下層部の主筋6と溶接接合し(
図3参照)梁下端まで型枠7を組立て、梁下端までコン
クリート8を打設し、しかるのち前記従来工法と同様に
梁、柱梁接合部の施工を行なう。(図4参照)図中9は
フープ筋、10は梁、11はスラブである。
Next, the pre-assembled reinforcing bars 5 are installed at predetermined positions, and (
(See Figure 2) The pre-assembled reinforcing bars 5 and the main reinforcing bars 6 in the lower layer are welded together (
(See FIG. 3) The formwork 7 is assembled up to the lower end of the beam, concrete 8 is poured up to the lower end of the beam, and then the beam-column-beam joint is constructed in the same manner as in the conventional construction method. (See FIG. 4) In the figure, 9 is a hoop reinforcement, 10 is a beam, and 11 is a slab.

【0011】[0011]

【発明の効果】本発明によれば前記したように、柱脚端
部にスリーブジヨイントが装着された芯鉄筋を内蔵した
プレキヤストRC柱材を所定位置に建込み、前記スリー
ブジヨイントを介して前記芯鉄筋を下層階の芯鉄筋と接
合したのち梁下端まで柱コンクリートを打設するように
したので、現場における鉄筋工事が短縮され現場打設コ
ンクリート量が減少し、施工性が向上する。
[Effects of the Invention] According to the present invention, as described above, a precast RC column containing a core reinforcing bar with a sleeve joint attached to the end of the column base is erected at a predetermined position, and After the core reinforcing bars are connected to the core reinforcing bars on the lower floor, column concrete is placed up to the bottom end of the beam, so on-site reinforcing work is shortened, the amount of concrete poured on-site is reduced, and workability is improved.

【0012】また芯鉄筋部分と現場打設部分とを異種類
及び異種強度のコンクリートを使い分けることによって
、圧縮靭性に優れた柱部材を構築できる。更にプレキヤ
ストRC柱材は工場生産のため、コンクリート強度の管
理が容易で、柱脚スリーブジヨイント部のグラウトモル
タル注入状況が明確になる。
Furthermore, by using concrete of different types and strengths for the core reinforcing bar portion and the cast-on-site portion, it is possible to construct a column member with excellent compressive toughness. Furthermore, since precast RC column materials are manufactured in a factory, it is easy to control the concrete strength, and the grout mortar injection situation at the column base sleeve joint is clear.

【図面の簡単な説明】[Brief explanation of the drawing]

【図1】本発明に係る芯鉄筋を有する部分プレキヤスト
柱工法の一実施例の第1工程を示す縦断面図である。
FIG. 1 is a longitudinal cross-sectional view showing the first step of an embodiment of the partially precast column construction method with core reinforcing bars according to the present invention.

【図2】本発明の第2工程を示す縦断面図である。FIG. 2 is a longitudinal sectional view showing the second step of the present invention.

【図3】本発明の第3工程を示す縦断面図である。FIG. 3 is a vertical cross-sectional view showing the third step of the present invention.

【図4】本発明の第4工程を示す縦断面図である。FIG. 4 is a longitudinal sectional view showing the fourth step of the present invention.

【図5】図3の横断平面図である。FIG. 5 is a cross-sectional plan view of FIG. 3;

【図6】従来工法の一例の実施状況を示す縦断面図であ
る。
FIG. 6 is a longitudinal cross-sectional view showing an example of a conventional construction method.

【図7】従来工法の他の例の実施状況を示す縦断面図で
ある。
FIG. 7 is a longitudinal sectional view showing the implementation status of another example of the conventional construction method.

【図8】従来工法によって柱部の配筋が完了した状態を
示す縦断面図である。
FIG. 8 is a longitudinal cross-sectional view showing a state in which reinforcing of a column part has been completed using a conventional construction method.

【図9】図8の横断平面図である。FIG. 9 is a cross-sectional plan view of FIG. 8;

【図10】従来工法の他の例の第1の工程を示す縦断面
図である。
FIG. 10 is a longitudinal sectional view showing the first step of another example of the conventional construction method.

【図11】前記従来工法の第2の工程を示す縦断面図で
ある。
FIG. 11 is a longitudinal sectional view showing the second step of the conventional construction method.

【図12】前記従来工法の第3の工程を示す縦断面図で
ある。
FIG. 12 is a longitudinal sectional view showing the third step of the conventional construction method.

【図13】図12の横断平面図である。FIG. 13 is a cross-sectional plan view of FIG. 12;

【符号の説明】[Explanation of symbols]

A    プレキヤストRC柱材 1    スリーブジヨイント 2    芯鉄筋 4    下層部芯鉄筋 8    コンクリート A Precast RC pillar material 1 Sleeve joint 2 Core reinforcing bar 4 Lower core reinforcing bar 8 Concrete

Claims (1)

【特許請求の範囲】[Claims] 【請求項1】  高層鉄筋コンクリート構造の下層階に
おける芯鉄筋を有する鉄筋コンクリート柱の構築方法に
おいて、柱脚、端部にスリーブジヨイントが装着された
芯鉄筋を内蔵したプレキヤスト鉄筋コンクリート柱材を
所定位置に建込み、前記スリーブジヨイントを介して前
記芯鉄筋を下階部芯鉄筋と接合したのち、梁下端部まで
柱コンクリートを打設することを特徴とする芯鉄筋を有
する部分プレキヤスト柱工法。
Claim 1. A method for constructing a reinforced concrete column having a core reinforcing bar on the lower floor of a high-rise reinforced concrete structure, in which a precast reinforced concrete column material having a built-in core reinforcing bar with a sleeve joint attached to the column foot and end is constructed in a predetermined position. A partial precast column construction method with core reinforcing bars, characterized in that after the core reinforcing bars are joined to the lower floor core reinforcing bars via the sleeve joints, column concrete is poured up to the lower end of the beam.
JP594491A 1991-01-22 1991-01-22 Constructing method for partial precast pillar with core reinforcement bar Pending JPH04237732A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
JP594491A JPH04237732A (en) 1991-01-22 1991-01-22 Constructing method for partial precast pillar with core reinforcement bar

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
JP594491A JPH04237732A (en) 1991-01-22 1991-01-22 Constructing method for partial precast pillar with core reinforcement bar

Publications (1)

Publication Number Publication Date
JPH04237732A true JPH04237732A (en) 1992-08-26

Family

ID=11625014

Family Applications (1)

Application Number Title Priority Date Filing Date
JP594491A Pending JPH04237732A (en) 1991-01-22 1991-01-22 Constructing method for partial precast pillar with core reinforcement bar

Country Status (1)

Country Link
JP (1) JPH04237732A (en)

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN101914976A (en) * 2010-07-30 2010-12-15 广州市设计院 Distributed steel bar concrete column and manufacturing method thereof
JP2012180671A (en) * 2011-03-01 2012-09-20 Toda Constr Co Ltd Aseismatic reinforcing structure of column or leg

Citations (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPS5312113A (en) * 1976-07-19 1978-02-03 Nippon Telegraph & Telephone Method of construction of rahmen structure
JPS6311499A (en) * 1986-07-01 1988-01-18 日本飛行機株式会社 Altitude controller for body to be towed

Patent Citations (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPS5312113A (en) * 1976-07-19 1978-02-03 Nippon Telegraph & Telephone Method of construction of rahmen structure
JPS6311499A (en) * 1986-07-01 1988-01-18 日本飛行機株式会社 Altitude controller for body to be towed

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN101914976A (en) * 2010-07-30 2010-12-15 广州市设计院 Distributed steel bar concrete column and manufacturing method thereof
JP2012180671A (en) * 2011-03-01 2012-09-20 Toda Constr Co Ltd Aseismatic reinforcing structure of column or leg

Similar Documents

Publication Publication Date Title
JP3160748B2 (en) Precast structural member composed of reinforced concrete columns and steel beams, and method of constructing structure using the same
JPH0518003A (en) Joining method of steel pipe concrete column and half-precast reinforced concrete column
JPH09209451A (en) Joint construction of up and down columns with beam and joint method
JP3424842B2 (en) Joining method of steel reinforced concrete columns in precast method
JPH04237732A (en) Constructing method for partial precast pillar with core reinforcement bar
JP3586121B2 (en) Mixed structure of reinforced concrete column and steel beam and its construction method
JPH04237731A (en) Constructing method for rc pillar with core reinforcement bar
JPH0732706Y2 (en) Reinforcement structure of precast reinforced concrete columns and crossed steel frames for joining steel beams
JPH0598653A (en) Steel pipe concrete pillar in underground inverter construction method
JPH05156654A (en) Top-down construction method
JPH1150538A (en) Building and method for constructing the same
JPH06316964A (en) Method for constructing joint of precast reinforced concrete column and beam
JPH08144425A (en) Prefabricated member of mixed structure and construction method of mixed structure
JPH0781307B2 (en) How to build a skyscraper
JP2005002585A (en) Capital member and rcft pole construction method using the same
JPH0452815B2 (en)
JP3094198B2 (en) Precast reinforced concrete member and method of constructing structure using the same
JPH01214641A (en) Construction of steel-pipe precast concrete pole
JPH01287336A (en) Steel frame reinforced concrete lamination construction
JP3039260B2 (en) Building method using PC members
JPH0447737B2 (en)
JP2554535B2 (en) Steel beam / reinforced concrete column composite construction method
JPH02274938A (en) Combining method for src column
JPH0533388A (en) Joining section of precast reinforced concrete construction
JPH02282538A (en) Construction method of reinforced concrete-made building frame