JPH0413326Y2 - - Google Patents

Info

Publication number
JPH0413326Y2
JPH0413326Y2 JP16478686U JP16478686U JPH0413326Y2 JP H0413326 Y2 JPH0413326 Y2 JP H0413326Y2 JP 16478686 U JP16478686 U JP 16478686U JP 16478686 U JP16478686 U JP 16478686U JP H0413326 Y2 JPH0413326 Y2 JP H0413326Y2
Authority
JP
Japan
Prior art keywords
net
distance
gondola
wire
prevention mechanism
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Expired
Application number
JP16478686U
Other languages
Japanese (ja)
Other versions
JPS6371358U (en
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed filed Critical
Priority to JP16478686U priority Critical patent/JPH0413326Y2/ja
Publication of JPS6371358U publication Critical patent/JPS6371358U/ja
Application granted granted Critical
Publication of JPH0413326Y2 publication Critical patent/JPH0413326Y2/ja
Expired legal-status Critical Current

Links

Landscapes

  • Movable Scaffolding (AREA)

Description

【考案の詳細な説明】 〔産業上の利用分野〕 本考案は、建築物の外壁等工事の際、工事、斫
り屑、ペンキ等の落下と飛散を防止し、隣家や下
を通行する車両や通行人に被害(以下、飛散公害
と称す)を与えるのを防止する養生ネツト(以
下、ネツトと称す)の展開自在装置に関するもの
で、ネツトを張る構造を簡単にすると共に、少な
いネツトの面積で、最大限に飛散公害を防止で
き、又、工事作業終了時ネツトをコンパクトに自
動的に折畳めることを可能にしたものである。
[Detailed description of the invention] [Industrial application field] This invention prevents construction debris, paint, etc. from falling and scattering during construction work on the exterior walls of buildings, and prevents construction work, scraps, paint, etc. from falling and scattering. This relates to a device that can deploy a curing net (hereinafter referred to as a net) that prevents damage (hereinafter referred to as a scattering pollution) to people and passersby.It simplifies the structure for installing the net and reduces the area of the net. This makes it possible to prevent scattering pollution to the maximum extent possible, and also makes it possible to automatically fold the net into a compact size at the end of construction work.

〔従来技術と問題点〕[Conventional technology and problems]

従来、例えばビル等の建築物の外壁の工事をす
る場合、第5図に示すように、飛散公害防止のた
め、ネツトAを屋上から地上まで、外壁全面に張
り、その内側でゴンドラBを昇降させて工事を行
なつていた。
Conventionally, when constructing the outer wall of a building such as a building, as shown in Figure 5, in order to prevent scattering pollution, Net A was stretched over the entire outer wall from the rooftop to the ground, and Gondola B was raised and lowered inside it. Construction work was being carried out.

ところが、この張り方であると、ネツト張付用
柱1を必要とし構造が複雑であること、ネツトの
張付け、取外しに人手と時間を有すること、風の
影響を受けネツトや柱1が外れるおそれがあるこ
と、ネツトの使用量が大であること、建物の1階
の出入及び交通の妨げになること等、種々の問題
点を有していた。
However, this tensioning method requires poles 1 for attaching the net, making the structure complicated, requiring manpower and time to attach and remove the net, and there is a risk that the net or the poles 1 may come off due to the influence of wind. There were various problems, such as the large amount of internet used, and the fact that it obstructed access to the first floor of the building and traffic.

該問題点を解決したネツトの張り方として、第
6図、第7図(第6図に右側面)に示すように、
建物Cの屋上を移動するゴンドラ吊下台車Dに、
ワイヤEを介して吊下げたゴンドラBの上部に枠
組2を取付け、該枠組2にネツトAを張つたもの
がある(図中、MはワイヤEを巻上げるモータで
ある)。
As shown in Figures 6 and 7 (right side in Figure 6), a method of tensioning the net that solves this problem is as follows.
On the gondola hanging trolley D moving on the roof of the building C,
There is one in which a framework 2 is attached to the upper part of a gondola B suspended via a wire E, and a net A is stretched over the framework 2 (in the figure, M is a motor for hoisting the wire E).

しかし、この張り方であると、枠組2の縦材3
の強度を考慮すると、高さ2乃至3mが限度であ
り、斫り屑やペンキの飛散防止が不完全であるこ
と、ゴンドラBが最上端まで上昇すると、想像線
で示すように、枠組2の横材4がゴンドラ吊下台
車Dに衝突し、枠組2に損傷を与えること、工事
終了後ネツトを折畳むことができないこと等の
種々の問題点を有していた。
However, with this tensioning method, the vertical members 3 of frame 2
Considering the strength of the frame, the maximum height is 2 to 3 meters, and it is incomplete to prevent the scattering of scraps and paint. There have been various problems such as the cross member 4 colliding with the gondola hanging cart D and damaging the frame 2, and the net being unable to be folded after construction is completed.

〔目的〕〔the purpose〕

本考案は、以上の問題点を解決すべく、簡単な
構造でネツトを張り、飛散公害を確実に防止する
と共に、工事終了後ネツトを自動的に折畳めるこ
とが可能な養生ネツトの展開自在装置を提供する
ことを目的とする。
In order to solve the above-mentioned problems, the present invention is a device for deploying a curing net that has a simple structure, reliably prevents scattering pollution, and can automatically fold the net after construction is completed. The purpose is to provide

〔問題点を解決するための手段〕[Means for solving problems]

本考案の養生ネツトの展開自在装置は、昇降体
を側壁に添つて昇降させる索条に、所定の摺動抵
抗を有して摺動可能に設けられて、且つ前記側壁
に面した部分を開放して前記昇降体を囲むように
養生ネツトを吊下げたネツト吊下体と、前記昇降
体と前記ネツト吊下体との間に設けられ、該両者
の離間距離を規制する距離規制索と、前記昇降体
が最上位置に上昇したとき、前記ネツト吊下体の
上昇を阻止する上昇阻止機構と、前記昇降体が最
上位置から下降するとき、前記ネツト吊下体に係
止し該ネツト吊下体の下降を阻止すると共に、該
係止を昇降体がネツト吊下体より所定距離離間し
たとき前記距離規制手段の該ネツト吊下体の牽引
により解除する下降阻止機構とで構成し、前記の
問題点を解決した。
The deployable device for the curing net of the present invention is slidably provided with a predetermined sliding resistance on the cable that raises and lowers the elevating body along the side wall, and the part facing the side wall is opened. a net suspension body in which a curing net is suspended so as to surround the elevating body; a distance regulating cable provided between the elevating body and the net suspending body to regulate the separation distance between the two; a rise prevention mechanism that prevents the net hanging body from rising when the body rises to the highest position; and a rise prevention mechanism that locks to the net hanging body and prevents the net hanging body from lowering when the elevating body descends from the highest position. In addition, the above problem is solved by comprising a lowering prevention mechanism that releases the lock by pulling the net hanging body by the distance regulating means when the elevating body is separated from the net hanging body by a predetermined distance.

〔作用〕[Effect]

上記のように構成したことにより、昇降体が最
上位置から下降するとき、当初はネツト吊下体の
下降が下降阻止機構により阻止され、索条はネツ
ト吊下体を摺動して昇降体と共に下降する。それ
に伴つてネツトが展開する。
With the above configuration, when the lifting body descends from the highest position, the lowering of the net hanging body is initially prevented by the descent prevention mechanism, and the cables slide on the net hanging body and descend together with the lifting body. . Net will expand accordingly.

昇降体がネツト吊下体から所定の距離離間した
位置まで下降すると、距離規制手段によつてネツ
ト吊下体は牽引され、前記下降阻止機構の前記阻
止が解除される。
When the elevating body descends to a position separated by a predetermined distance from the net suspension body, the net suspension body is pulled by the distance regulating means, and the inhibition of the descent prevention mechanism is released.

その後は、昇降体とネツト吊下体は所定距離離
間した状態でネツトを展開したまま昇降をする。
Thereafter, the elevating body and the net hanging body move up and down while the net is unfolded, with a predetermined distance between them.

作業終了後、昇降体が最上位置まで上昇する
と、ネツト吊下体は上昇阻止機構により上昇を阻
止されるが、索条はネツト吊下体に対して摺動上
昇し、昇降体を引き上げる。それと共にネツトと
距離規制索とが自然に折畳まれる。
After the work is completed, when the elevating body rises to the highest position, the net suspension body is prevented from rising by the rise prevention mechanism, but the cables slide upward relative to the net suspension body and pull up the elevating body. At the same time, the net and the distance control cable are naturally folded.

〔実施例〕〔Example〕

以下、本考案の実施例を図面を用いて説明す
る。
Embodiments of the present invention will be described below with reference to the drawings.

第1図は本考案の側面図、第2図は第1図の
−断面矢視図である。
FIG. 1 is a side view of the present invention, and FIG. 2 is a cross-sectional view taken along the arrow - in FIG.

第1図中の、建物Cの屋上に移動自在に設けら
れたゴンドラ吊下台車Dからは、モータMにより
巻取られるワイヤEが滑車10を介して垂らされ
ている。ワイヤEの下端にはゴンドラBが吊下げ
られている。ワイヤEには所定の摺動抵抗でこの
ワイヤEに沿つて摺動可能なワイヤ押え機構12
が取付けられている。このワイヤ押え機構12に
はネツト吊下枠11が取り付けられている。
In FIG. 1, a wire E wound by a motor M is suspended via a pulley 10 from a gondola suspension cart D which is movably provided on the roof of a building C. A gondola B is suspended from the lower end of the wire E. The wire E has a wire holding mechanism 12 that can slide along the wire E with a predetermined sliding resistance.
is installed. A net hanging frame 11 is attached to this wire holding mechanism 12.

ワイヤ押え機構12は、ネツト吊下枠11に取
付けられたワイヤ受板13と、ワイヤEを間に挟
んでワイヤ受板13と対向して配されたワイヤ押
え板16を有している。ワイヤ押え板16は、ワ
イヤ受板13にねじ込まれた複数の締付ねじ15
は摺動自在に支持されている。締付ねじ15には
スプリング14が装着され、ワイヤ押え板16を
ワイヤ受板13の方向に付勢して、ワイヤEとの
間に適当な摺動抵抗を与えている。締付けネジ5
のねじ込み量を調節することにより、ワイヤEに
対するワイヤ押え板16の押え力が変化し、摺動
抵抗の調整を行える。
The wire holding mechanism 12 includes a wire receiving plate 13 attached to the net hanging frame 11, and a wire holding plate 16 disposed opposite to the wire receiving plate 13 with the wire E interposed therebetween. The wire holding plate 16 has a plurality of tightening screws 15 screwed into the wire receiving plate 13.
is slidably supported. A spring 14 is attached to the tightening screw 15, and urges the wire holding plate 16 toward the wire receiving plate 13 to provide an appropriate sliding resistance between the wire holding plate 16 and the wire E. Tightening screw 5
By adjusting the amount of screwing in, the holding force of the wire holding plate 16 against the wire E changes, and the sliding resistance can be adjusted.

該ネツト吊下枠11には、後述する下降阻止機
構が係合するフレームベロ17が設けてある。
The net suspension frame 11 is provided with a frame tongue 17 that engages with a lowering prevention mechanism, which will be described later.

以上の、ネツト吊下枠11、ワイヤ押え機構1
2、フレームベロ17によつてネツト吊下体18
が構成されている。
The above net hanging frame 11 and wire holding mechanism 1
2. Net hanging body 18 by frame tongue 17
is configured.

さらにネツト吊下枠11には、建物Cの外壁
Caに面した部分を開放して前記ゴンドラBを包
囲するネツトAが吊下げてある。ネツトAの下端
はネツトA自身が風によつて流されないように、
ゴンドラAの下端に設けたネツト受け19に固着
してある。
Furthermore, the outer wall of building C is attached to the net suspension frame 11.
A net A that surrounds the gondola B is suspended with its portion facing Ca open. The lower end of net A is set so that net A itself will not be blown away by the wind.
It is fixed to a net receiver 19 provided at the lower end of the gondola A.

ネツト受け19と、前記ゴンドラBとの間に
は、ネツトEの長さ(例えば10m)を規制するた
めの距離規制索(ワイヤ)20が複数本設けてあ
る。
A plurality of distance regulating cables (wires) 20 are provided between the net receiver 19 and the gondola B to regulate the length of the net E (for example, 10 m).

尚、ネツトAの長さは該距離規制索20より多
少長くなつていおり、ネツトAが強く張らないよ
うにしている。
Note that the length of the net A is somewhat longer than the distance regulating cable 20, so that the net A is not stretched too tightly.

ゴンドラ吊下台車Dの下側には、下降阻止機構
21を備えた支持板22が固着してある。
A support plate 22 provided with a descent prevention mechanism 21 is fixed to the lower side of the gondola suspension truck D.

該下降阻止機構21は、支持板22に第1の軸
23を介して回転自在に設けたウエイトアーム2
4と、該支持板22に立設され、ウエイトアーム
24の時計方向の回転を阻止する第1の規制ピン
25と、該ウエイトアーム24の右端に設けたウ
エイト26と、ウエイトアーム24の左端に第2
の軸27を介して回転自在に設けたロツク片28
と、ウエイトアーム24に立設され、ロツク片2
8の反時計方向への回動を規制する第2の規制ピ
ン29とで構成されている。
The descent prevention mechanism 21 includes a weight arm 2 rotatably provided on a support plate 22 via a first shaft 23.
4, a first regulating pin 25 erected on the support plate 22 to prevent clockwise rotation of the weight arm 24, a weight 26 provided on the right end of the weight arm 24, and a first regulating pin 25 provided on the left end of the weight arm 24. Second
A lock piece 28 rotatably provided via a shaft 27 of
and the lock piece 2 is installed upright on the weight arm 24.
8 and a second regulating pin 29 for regulating the counterclockwise rotation.

前記ウエイト26の位置は、ウエイトアーム2
4に複数穿設したウエイト調整孔30によつて、
可変できる。
The position of the weight 26 is based on the weight arm 2.
By the weight adjustment holes 30 drilled in plural numbers in 4,
Can be changed.

前記支持板22の下面、前記ネツト吊下枠11
と対向した位置にはネツト吊下枠11の上昇阻止
板31が設けてある。
The lower surface of the support plate 22, the net suspension frame 11
A rise prevention plate 31 for the net suspension frame 11 is provided at a position opposite to the net suspension frame 11.

次に以上の構成の動作について説明する。 Next, the operation of the above configuration will be explained.

先ず、第1図に示すように、ネツト吊下枠11
が上昇阻止板31に当接している状態から、モー
タMを回転してワイヤEを送り出すと、ゴンドラ
Bは自重により下降を開始する。
First, as shown in FIG.
When the motor M is rotated and the wire E is sent out from the state in which the gondola B is in contact with the rise prevention plate 31, the gondola B starts descending due to its own weight.

それと同時にネツト吊下枠11も下降するが、
下降後直ちにネツト吊下枠11に設けたフレーム
ベロ17が図中点線の様に、下降阻止機構21の
ロツク片28の先端に係合する。
At the same time, the net suspension frame 11 also descends,
Immediately after being lowered, the frame tongue 17 provided on the net suspension frame 11 engages with the tip of the locking piece 28 of the lowering prevention mechanism 21, as shown by the dotted line in the figure.

ワイヤ押え機構12のワイヤEに対する摺動抵
抗より、下降阻止機構21のウエイト26による
係止力の方が大きくなるように締付けねじ15を
調節しておけば、ネツト吊下枠11の下降は阻止
され、ゴンドラBのみを下降する。そして、ゴン
ドラBの下降に伴つて、ネツトAの距離規制索2
0とが展開していく。
If the tightening screw 15 is adjusted so that the locking force exerted by the weight 26 of the descent prevention mechanism 21 is greater than the sliding resistance of the wire holding mechanism 12 against the wire E, the descent of the net hanging frame 11 can be prevented. Then, only gondola B descends. Then, as gondola B descends, net A's distance control cable 2
0 develops.

ゴンドラBが所定距離下降し、距離規制索20
がぴんと張ると、ゴンドラBの自重により下降阻
止機構21がネツト吊下枠11に対する係止を解
除する方法に作動していく。
Gondola B descends a predetermined distance, and the distance regulating rope 20
When the gondola B becomes taut, the weight of the gondola B causes the descent prevention mechanism 21 to operate in a manner that releases the net suspension frame 11.

即ち、第3図に示すように、距離規制索20に
より、ネツト吊下枠11と、ゴンドラBとが所定
距離保持された状態で、ネツト吊下枠11はワイ
ヤEと共に下降し、ウエイトアーム24は第1の
軸23を中心として反時計方向に回動する。これ
によりロツク片28はフレームベロ17から外
れ、ウエイトアーム24はウエイト26の重みに
より時計方向に回転し、元の位置に復元する(第
3図中想像線)。これによりネツト吊下体11は、
ネツトAを完全に展開した状態でゴンドラBと共
に、ワイヤEにより昇降し作業を行うことが出来
る。
That is, as shown in FIG. 3, with the distance regulating rope 20 holding the net suspension frame 11 and the gondola B at a predetermined distance, the net suspension frame 11 descends together with the wire E, and the weight arm 24 rotates counterclockwise around the first shaft 23. As a result, the lock piece 28 comes off the frame tongue 17, and the weight arm 24 rotates clockwise due to the weight of the weight 26, returning to its original position (imaginary line in FIG. 3). As a result, the net hanging body 11 is
When net A is fully expanded, work can be carried out by raising and lowering it together with gondola B using wire E.

次に、作業終了後、ゴンドラBを最上位置まで
引き上げるべく、モータMでワイヤEを巻上げる
と、ゴンドラBと、ネツト吊下枠11はゴンドラ
吊下台車Dに接近していく。そして、フレームベ
ロ17は、ロツク片28に当接すると、このロツ
ク片28を第2の軸27を中心として容易に押し
上げ反時計方向に回動させ(第4図)、下降阻止
機構21を通過する。ロツク片28は該通過後、
自重(若しくはばね)により復元する。
Next, after the work is completed, the wire E is wound up by the motor M in order to raise the gondola B to the highest position, and the gondola B and the net suspension frame 11 approach the gondola suspension cart D. When the frame tongue 17 comes into contact with the lock piece 28, it easily pushes up the lock piece 28 around the second shaft 27 and rotates it counterclockwise (FIG. 4), allowing it to pass through the lowering prevention mechanism 21. do. After the lock piece 28 passes through the
It is restored by its own weight (or spring).

その後、ネツト吊下枠11は、上昇阻止板31
に当接して上昇が阻止される。
After that, the net suspension frame 11 is moved by the rise prevention plate 31.
It touches and is prevented from rising.

ワイヤEをさらに巻上げると、ネツト吊下枠1
1のワイヤ押え機構12摺動して、ネツトAと、
距離規制索20は折畳まれて、ネツト受け19の
内側に自然に収納される。
When wire E is further wound up, net suspension frame 1
The wire holding mechanism 12 of 1 slides and connects to the net A.
The distance regulating cable 20 is folded and naturally stored inside the net receiver 19.

これにより、全体の高さが第1図のようにちぢ
められた状態にもどる。
As a result, the overall height returns to the reduced state as shown in FIG.

以上のように本考案の実施例によると、ネツト
を、従来の柱や枠組を使用せず、索条に設けたネ
ツト吊下枠に単に吊下げただけであるから、構造
が簡単になると共に、地上を通行する人や車両の
往来の妨げになることがない。又、ネツトを工事
に必要な長さだけ張ることができ、飛散公害を確
実に防止できる。
As described above, according to the embodiment of the present invention, the net is simply suspended from the net suspension frame provided on the cable without using conventional pillars or frameworks, which simplifies the structure and , will not obstruct the traffic of people or vehicles passing on the ground. In addition, the net can be stretched as long as necessary for the construction work, and scattering pollution can be reliably prevented.

さらに、ネツトを自動的に折畳めるので、あら
ためて、ネツトの収容作業をすることが不要とな
る。
Furthermore, since the net can be automatically folded, there is no need to carry out the work of storing the net again.

尚、以上の説明では、建物に養生ネツトの展開
自在装置を適用した実施例であるが崖等の工事に
おいても適用できる。
In the above description, the deployable device for the curing net is applied to a building, but it can also be applied to construction work on a cliff or the like.

なお、下降阻止機構にワイヤ押え機構の摺動抵
抗に抗するために重りを用いたが、ウエイトアー
ムとゴンドラ吊下台車との間にスプリングを張架
しても同一の目的を達成することができる。
Although a weight was used in the descent prevention mechanism to resist the sliding resistance of the wire holding mechanism, the same purpose could also be achieved by tensioning a spring between the weight arm and the gondola suspension car. can.

また、養生ネツトが丈夫な場合には、この養生
ネツトに距離規制手段を兼用させれば、前記実施
例で示したような距離規制索20は不要となる。
Further, if the curing net is strong and the curing net also serves as the distance regulating means, the distance regulating cable 20 as shown in the above embodiment becomes unnecessary.

〔考案の効果〕[Effect of idea]

以上のように、本考案の養生ネツトの展開装置
はネツトを索条に取付けたネツト吊下体に吊下げ
たので、ネツトを張る構造が簡単になると共に、
地上を通行する人や車両の往来の妨げになること
がない。又、ネツトを工事に必要な長さだけ張る
ことができ、飛散公害を確実に防止できる。
As described above, in the curing net deployment device of the present invention, the net is suspended from the net hanging body attached to the cables, so the structure for tensioning the net is simplified, and
It does not obstruct the traffic of people or vehicles passing on the ground. In addition, the net can be stretched as long as necessary for the construction work, and scattering pollution can be reliably prevented.

又、ネツト吊下体を索条に対し摺動自在にした
ので、昇降体が最上昇位置に上昇すると、ネツト
が自動的に折畳められるので工事終了後あらため
て、ネツトの収容作業をすることが不要となる。
In addition, since the net hanging body is made to be able to slide freely on the cable, the net is automatically folded when the elevating body rises to the highest position, making it possible to store the net again after construction is completed. No longer needed.

【図面の簡単な説明】[Brief explanation of the drawing]

第1図乃至第4図は本考案の実施例で、第1図
は側面図で第2図のI−I断面矢視図、第2図は
第1図の−断面斜視図、第3図はネツトが展
開した状態の説明図、第4図はゴンドラが上昇し
て行く説明図、第5図、第6図は従来例、第7図
は第6図の右側図である。 A……養生ネツト、B……ゴンドラ、C……建
物、E……ワイヤ、M……モータ、1……柱、2
……枠組、3……縦材、4……横材、11……ネ
ツト吊下枠、12……ワイヤ押え機構、18……
ネツト吊下体、20……距離規制索、21……下
降阻止機構、24……ウエイトアーム、26……
ウエイト、28……ロツク片、31……上昇阻止
板。
Figures 1 to 4 show embodiments of the present invention, where Figure 1 is a side view, Figure 2 is a cross-sectional view taken along line I-I in Figure 2, Figure 2 is a perspective view of Figure 1, and Figure 3 is a cross-sectional perspective view of Figure 1. 4 is an explanatory diagram of the net in an expanded state, FIG. 4 is an explanatory diagram of the gondola going up, FIGS. 5 and 6 are conventional examples, and FIG. 7 is a right side view of FIG. 6. A...Cure net, B...Gondola, C...Building, E...Wire, M...Motor, 1...Column, 2
...Framework, 3...Vertical member, 4...Horizontal member, 11...Net suspension frame, 12...Wire presser mechanism, 18...
Net hanging body, 20... Distance regulating cable, 21... Lowering prevention mechanism, 24... Weight arm, 26...
Weight, 28...lock piece, 31...rise prevention plate.

Claims (1)

【実用新案登録請求の範囲】 昇降体を側壁に添つて昇降させる索条に、所定
の摺動抵抗を有して摺動可能に設けられ、且つ前
記側壁に面した部分を展開して前記昇降体を囲む
ように養生ネツトを吊下げたネツト吊下体と、 前記昇降体と前記ネツト吊下体との間に設けら
れ、該両者の離間距離を規制する距離規制手段
と、 前記昇降体が最上位置に上昇したとき、前記ネ
ツト吊下体の上昇を阻止する上昇阻止機構と、 前記昇降体が最上位置から下降するとき、前記
ネツト吊下体に係止し該ネツト吊下体の下降を阻
止すると共に、該係止を昇降体がネツト吊下体よ
り所定距離離間したとき前記距離規制手段の該ネ
ツト吊下体の牽引により解除する下降阻止機構
と、 を有して構成したことを特徴とする養生ネツトの
展開自在装置。
[Claims for Utility Model Registration] A cable for raising and lowering an elevating body along a side wall is slidably provided with a predetermined sliding resistance, and the part facing the side wall is expanded to raise and lower the elevating body. a net suspension body in which a curing net is suspended so as to surround the body; a distance regulating means provided between the elevating body and the net suspending body to regulate a distance between the two; and a distance regulating means for regulating the distance between the two; a rise prevention mechanism that prevents the net hanging body from rising when the lifting body rises from the uppermost position; A freely deployable curing net characterized by comprising: a lowering prevention mechanism that releases the lock by pulling the net hanging body of the distance regulating means when the lifting body moves a predetermined distance from the net hanging body. Device.
JP16478686U 1986-10-27 1986-10-27 Expired JPH0413326Y2 (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
JP16478686U JPH0413326Y2 (en) 1986-10-27 1986-10-27

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
JP16478686U JPH0413326Y2 (en) 1986-10-27 1986-10-27

Publications (2)

Publication Number Publication Date
JPS6371358U JPS6371358U (en) 1988-05-13
JPH0413326Y2 true JPH0413326Y2 (en) 1992-03-27

Family

ID=31094225

Family Applications (1)

Application Number Title Priority Date Filing Date
JP16478686U Expired JPH0413326Y2 (en) 1986-10-27 1986-10-27

Country Status (1)

Country Link
JP (1) JPH0413326Y2 (en)

Families Citing this family (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
KR20020040396A (en) * 2000-11-24 2002-05-30 하라다 마모루 Gondola with a wall corner covering for wall face work

Also Published As

Publication number Publication date
JPS6371358U (en) 1988-05-13

Similar Documents

Publication Publication Date Title
US8579081B2 (en) Remote controlled overhead ladder system
US4167224A (en) Escape chute
US8151940B2 (en) Evacuation systems and methods
KR101033695B1 (en) Flag hoisting unit
JPH0413326Y2 (en)
JP3052246B2 (en) Fall prevention device for wall work
KR102338446B1 (en) A Top-down evacuation ladder to prevent the shaking of the folding ladder
CN211722707U (en) Door opening device
JP3091889B2 (en) Ladder mounting structure for evacuation device
JP2987321B2 (en) Seat opening and closing mechanism in a temporary tent
CN215974711U (en) Well lid opening tool for underground operation
JP2998068B2 (en) lift device
JP3994648B2 (en) Elevator apparatus and installation method thereof
JP2907707B2 (en) heliport
CN114232963B (en) Steel construction building wall mounting platform
JPS5929735Y2 (en) Building evacuation device
JP3053143B2 (en) Building shed for building construction with lift-up device
JP2553545Y2 (en) Simple crane of a building construction work shed
JP2562091B2 (en) External curing method and external curing device in construction work
JPH1144095A (en) Automatic lift for construction, self-lifting type curing net and self-lifting type exterior scaffold
JPH05222834A (en) Ascending or descending continuous suspended scaffolding for multistoried building
JP3044575B2 (en) Anti-swing device for suspended loads
JPH0727943Y2 (en) Evacuation device
JP4167377B2 (en) Rainfall installation method for unit housing, tent
JP2001140473A (en) Curing apparatus