JPH032488A - Anchoring work - Google Patents

Anchoring work

Info

Publication number
JPH032488A
JPH032488A JP13555589A JP13555589A JPH032488A JP H032488 A JPH032488 A JP H032488A JP 13555589 A JP13555589 A JP 13555589A JP 13555589 A JP13555589 A JP 13555589A JP H032488 A JPH032488 A JP H032488A
Authority
JP
Japan
Prior art keywords
tip
attached
construction
drilling
back hoe
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
JP13555589A
Other languages
Japanese (ja)
Inventor
Akira Suzuki
昭 鈴木
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
TONE CHIKA GIJUTSU KK
Original Assignee
TONE CHIKA GIJUTSU KK
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by TONE CHIKA GIJUTSU KK filed Critical TONE CHIKA GIJUTSU KK
Priority to JP13555589A priority Critical patent/JPH032488A/en
Publication of JPH032488A publication Critical patent/JPH032488A/en
Pending legal-status Critical Current

Links

Landscapes

  • Earth Drilling (AREA)

Abstract

PURPOSE:To curtail the construction cost and the period of the construction by a method in which a back hoe is set below steep-sloped ground, and the ground is excavated by a drill hammer attached to the tip of the back hoe. CONSTITUTION:A working tool is removed from the tip of a heavy construction machine such as a back hoe 50 or a power crane, and a drill hammer 52 is attached to the tip. A working platform 60 is also attached to the hammer 52 as needed. The back hoe is set on the lower part of steep slope 54 or wall, and the higher places are excavated by extending an arm 56 to form a pit 58. From the platform 60, attendent operations such as anchor insertion, cement paste injection, etc., are made. Since the needs for great-scale scaffold construction work can be eliminated, the constructing period can be gently shoetened and economical effect can thus be greatly raised.

Description

【発明の詳細な説明】 〔産業上の利用分野〕 本発明はアンカー施工方法に係り、特に削孔作業空間の
確保が困難な急斜面や掘削壁面の土留め工事やよう壁工
事などに対して好適なアンカー施工方法に関する。
[Detailed Description of the Invention] [Field of Industrial Application] The present invention relates to an anchor construction method, and is particularly suitable for steep slopes where it is difficult to secure a drilling work space, earth retaining work on excavated walls, wall construction, etc. Regarding anchor construction methods.

〔従来の技術〕[Conventional technology]

一般にアンカー工法は、地盤を削孔してアンカ一体を挿
入し、セメントペースト等を注入して施工する。
Generally, the anchor construction method involves drilling a hole in the ground, inserting the anchor, and then injecting cement paste or the like.

従来は、急斜面や掘削壁面の土留め、あるいは斜面安定
工、地ζり抑止上などにアンカーを施工する場合、第2
図に示すように、根切り底を」↓盤として削孔機を据付
け、根切りの進行に従って、順次掘削壁面に削孔を行う
か、削孔面に対面して作業用の足場又は構台などを仮設
し、その」ユに削孔機を据付けるのが通常であった。図
中の符けは、2が土留め材、4は根切り底又は仮設足場
、6は削孔機、8は削孔ハンマ、lOは動力設備である
Conventionally, when constructing anchors for earth retaining on steep slopes or excavated walls, slope stabilization works, and ground erosion prevention, the second
As shown in the figure, install a hole-drilling machine with the root cutting bottom as a ↓ board, and as the root cutting progresses, drill holes sequentially on the excavation wall surface, or use a scaffold or gantry for work facing the drilling surface. It was common practice to temporarily construct a hole and install a drilling machine in the hole. In the figure, 2 is the earth retaining material, 4 is the cutting bottom or temporary scaffolding, 6 is the hole drilling machine, 8 is the drilling hammer, and 1O is the power equipment.

〔発明が解決しようとする課題〕[Problem to be solved by the invention]

しかしながら、削孔面の前面に作業空間を確保するのが
困難なときや、地辷り抑止工事のように勾配のある急な
斜面上での施工の場合には、大がかりな足場が必要とな
るという問題点があった。
However, when it is difficult to secure a working space in front of the drilling surface, or when construction is to be carried out on a steep slope, such as when performing landslide prevention work, large-scale scaffolding is required. There was a problem.

また、そのため斜面に樹木などが生い茂っているときは
、広範囲の伐採によって地山の強度が弱められ、更には
樹木伐採による環境上の問題もあった。
In addition, when the slopes are overgrown with trees, the strength of the ground is weakened by extensive felling, and the felling of trees also poses environmental problems.

本願発明者らは、既にバックホーの先端に削孔ハンマを
取付け、崖下などの下方の急斜面、あるいは掘削壁面に
対する削孔に顕著な効果をもたらしてきた。(特願平1
−29182号参照)。
The inventors of the present application have already attached a drilling hammer to the tip of a backhoe, and have achieved remarkable results in drilling holes on steep slopes below, such as under cliffs, or on excavated walls. (Special application Hei 1
-29182).

この発明の目的は上記問題点に鑑みなされたもので、高
位置にある削孔面の前面に削孔のための足場や構台を配
設する必要のないアンカー施工方法を提供することであ
る。
The object of the present invention has been made in view of the above-mentioned problems, and is to provide an anchor construction method that does not require providing a scaffold or pedestal for drilling holes in front of a drilling surface located at a high position.

〔課題を解決するための手段〕[Means to solve the problem]

上記の目的を達成するために本発明のアンカー施工方法
は、急斜面又は掘削壁面等の土留め工事におけるアンカ
ー施工方法において、前記急斜面又は掘削壁面の下方に
バックホーを位置せしめ、該バックホーの先端に取付け
た削孔ハンマによって該バックホーより上方の急斜面又
は掘削壁面に削孔することを特徴とするものである。
In order to achieve the above object, the anchor construction method of the present invention is an anchor construction method for earth retaining work on a steep slope or an excavated wall, in which a backhoe is positioned below the steep slope or excavated wall, and the anchor is attached to the tip of the backhoe. This method is characterized in that a hole is drilled on a steep slope or excavation wall above the backhoe using a hole-drilling hammer.

また、前記削孔ハンマは作業台を仮設することもできる
Further, the drilling hammer can also be used as a temporary workbench.

〔作用〕[Effect]

上記構成によれば、急斜面や掘削壁面の下方の地盤上な
どにバックホーを配置し、その先端に削孔ハンマを取付
けて急斜面や掘削壁面を削孔することができるので、削
孔面の前面に重機を配置するための大がかりな足場等を
設けることなく、高い位置の削孔が可能となる。
According to the above configuration, the backhoe can be placed on the ground below the steep slope or the excavation wall surface, and a drilling hammer can be attached to the tip of the backhoe to drill a hole on the steep slope or the excavation wall surface. It is possible to drill holes at high positions without having to install large-scale scaffolding for placing heavy machinery.

そのために経済的であり、大1jに工期の短縮を図るこ
とができる。
Therefore, it is economical and the construction period can be significantly shortened.

〔実施例〕〔Example〕

以下1本発明の一実施例を図面に基づいて説明する。 An embodiment of the present invention will be described below based on the drawings.

第1図に示すように、バックホー50の先端のクラムシ
ェル(図示せず)を取外して削孔ハンマ52を取付けた
ものを、急斜面54の下方に配置して斜面54の削孔を
行う。
As shown in FIG. 1, a backhoe 50 with a clamshell (not shown) at the tip thereof removed and a drilling hammer 52 attached thereto is placed below a steep slope 54 to drill holes in the slope 54.

バックホー50のアーム56を延ばすことによって、斜
面54の高い位置であっても削孔58をすることができ
る。
By extending the arm 56 of the backhoe 50, the hole 58 can be drilled even at a high position on the slope 54.

図の例では、削孔ハンマ52に作業台60を設けである
。こうすることによって削孔後も、アンカ一体の挿入、
セメントペーストの注入等の作業を容易に行うことがで
きる。
In the illustrated example, the drilling hammer 52 is provided with a workbench 60. By doing this, even after drilling, the anchor can be inserted as a single piece,
Operations such as cement paste injection can be performed easily.

また、本実施例では急斜面に施工する場合について説明
しているが、垂直な掘削壁面の高い位置は勿論のこと、
勾配45度以下の緩斜面についても、同様に施工するこ
とができる−1 また、本実施例のように、バックホーを用いることによ
って容易に施工することができるが、バックホーに限定
されるものではなく、他の動力クレーン等の重機を用い
ることによっても同様の効果を奏することができる。
In addition, although this example describes the case of construction on a steep slope, it goes without saying that construction is performed at a high position on a vertical excavation wall.
It can be constructed in the same way on gentle slopes with a slope of 45 degrees or less. Similar effects can also be achieved by using other heavy equipment such as power cranes.

本実施例によれば、アンカーエのための仮設工事を大巾
に省略することができ、しかもなおアンカー自体の精度
・品質は従来の方法によるものと全く変わらない。
According to this embodiment, temporary construction work for the anchorage can be largely omitted, and the accuracy and quality of the anchor itself are no different from those of conventional methods.

〔発明の効果〕〔Effect of the invention〕

上述のとおり1本発明によれば、急斜面等の高い位置に
アンカーの施工をするに当り、アンカー施工部の下方に
重機を配置することによって、がなりの仮設工事が省略
され、そのため工期が大目1に短縮され、極めて大きい
経済的効果を奏することができる。
As mentioned above, according to the present invention, when constructing an anchor at a high position such as a steep slope, by placing heavy equipment below the anchor construction part, temporary construction work is omitted, and the construction period is therefore increased. It can be shortened to 1 second, and can have an extremely large economical effect.

【図面の簡単な説明】[Brief explanation of drawings]

第1図は本発明の一実施例を示す説明図、第2図は従来
例を示す説明図である。 50・・・バックホー 52・・・削孔ハンマ、54・
・・急斜面、56・・・アーム、58・・・削孔、60
・・・作業台。
FIG. 1 is an explanatory diagram showing one embodiment of the present invention, and FIG. 2 is an explanatory diagram showing a conventional example. 50...Backhoe 52...Drilling hammer, 54.
... Steep slope, 56... Arm, 58... Drilling, 60
···Workbench.

Claims (1)

【特許請求の範囲】 1、急斜面又は掘削壁面等の土留め工事におけるアンカ
ー施工方法において、前記急斜面又は掘削壁面の下方に
バックホーを位置せしめ、該バックホーの先端に取付け
た削孔ハンマによって該バックホーより上方の急斜面又
は掘削壁面に削孔することを特徴とするアンカー施工方
法。 2、請求項1記載の方法において、前記削孔ハンマに作
業台を取付けることを特徴とするアンカー施工方法。
[Claims] 1. In an anchor construction method for earth retaining work on a steep slope or an excavated wall surface, a backhoe is positioned below the steep slope or excavated wall surface, and a drilling hammer attached to the tip of the backhoe is used to remove the anchor from the backhoe. An anchor construction method characterized by drilling a hole in an upper steep slope or an excavated wall. 2. An anchor construction method according to claim 1, characterized in that a workbench is attached to the drilling hammer.
JP13555589A 1989-05-29 1989-05-29 Anchoring work Pending JPH032488A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
JP13555589A JPH032488A (en) 1989-05-29 1989-05-29 Anchoring work

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
JP13555589A JPH032488A (en) 1989-05-29 1989-05-29 Anchoring work

Publications (1)

Publication Number Publication Date
JPH032488A true JPH032488A (en) 1991-01-08

Family

ID=15154540

Family Applications (1)

Application Number Title Priority Date Filing Date
JP13555589A Pending JPH032488A (en) 1989-05-29 1989-05-29 Anchoring work

Country Status (1)

Country Link
JP (1) JPH032488A (en)

Citations (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPS6133113U (en) * 1984-07-31 1986-02-28 株式会社 光合金製作所 Pressure reducing valve for low tanks in cold regions

Patent Citations (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPS6133113U (en) * 1984-07-31 1986-02-28 株式会社 光合金製作所 Pressure reducing valve for low tanks in cold regions

Similar Documents

Publication Publication Date Title
JPH032488A (en) Anchoring work
JP2794069B2 (en) Anchor construction method
CN108643184A (en) Rock drilling construction method is abolished in artificial digging pile
JP2004218378A (en) Removing method for existing pile
JPS6434383A (en) Construction method for erecting support for backnet and foundation block
JP2612497B2 (en) Drilling method for large diameter underground holes
JPS5771926A (en) Treatment of extra-banking concrete at head of pile driven at site
CN212405120U (en) Bored concrete pile of construction is executed to underground reinforced concrete structure department
JP3158227B2 (en) Underground building construction method
JPS5938425A (en) Cutting work of slope
JP2004278250A (en) Method for positioning concrete pile
JP3692451B2 (en) Shield method
RU2049857C1 (en) Method for formation of foundation of chimney stack
JPS61155519A (en) Settlement work of caisson
JP2586459Y2 (en) Drilling equipment
JPH0518969B2 (en)
JPS62215720A (en) Driving work of steel tube
JPS5585731A (en) Method and apparatus for burying pile
JPS6229625A (en) Settling construction for open caisson
KR20210081717A (en) Device for vibration hammer
JPS58222211A (en) Pile driving work using platform and temporary pier
RU23905U1 (en) SHOCK DRILL
JPS6272817A (en) Construction of retaining wall concurrently serving as sheathing
JP2000073366A (en) Ground anchor removing method
JPH07119471B2 (en) Board blister prevention method using an earth anchor