JPH03206291A - Shield excavator - Google Patents

Shield excavator

Info

Publication number
JPH03206291A
JPH03206291A JP1344109A JP34410989A JPH03206291A JP H03206291 A JPH03206291 A JP H03206291A JP 1344109 A JP1344109 A JP 1344109A JP 34410989 A JP34410989 A JP 34410989A JP H03206291 A JPH03206291 A JP H03206291A
Authority
JP
Japan
Prior art keywords
front frame
segment
frame
existing
excavation
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Granted
Application number
JP1344109A
Other languages
Japanese (ja)
Other versions
JP2712686B2 (en
Inventor
Ryusaburo Otsuka
隆三郎 大塚
Shigeo Fujii
茂男 藤井
Masaaki Ura
浦 雅明
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
IHI Corp
Original Assignee
IHI Corp
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by IHI Corp filed Critical IHI Corp
Priority to JP1344109A priority Critical patent/JP2712686B2/en
Publication of JPH03206291A publication Critical patent/JPH03206291A/en
Application granted granted Critical
Publication of JP2712686B2 publication Critical patent/JP2712686B2/en
Anticipated expiration legal-status Critical
Expired - Fee Related legal-status Critical Current

Links

Landscapes

  • Excavating Of Shafts Or Tunnels (AREA)
  • Lining And Supports For Tunnels (AREA)

Abstract

PURPOSE:To increase the size of a tunnel as existing equipment is jointly used by forming a pushing front frame and a rear frame following the front frame, and sealing a gap between new and existing segments with a seal part. CONSTITUTION:A shield excavator comprising a front frame 23 having a cutter 22 for excavating the outer periphery of an existing segment 21 of a jointly using shield tunnel, a rear frame 24 to alternately push excavation in a manner to be overlapped therewith, and seal parts 25 and 26 mounted to the frames 23 and 24, respectively, is concentrically to the segment 21. In excavation, through expansion of a seal part 26 of a rear frame 24 in a waiting stop state, underground water and sludge from the facing side are shut off and excavation is effected by a given length. Thereafter, through expansion of a seal part 25 of a fixing front frame 23, cutoff is effected, through alternate repetition, a gap between the segment 21 and a new segment is sealed, and a tunnel the size of which is increased is built.

Description

【発明の詳細な説明】 [産業上の利用分野] 本発明は、トンネルを掘削すると共にセグメントを順次
組み立てて覆工するシールド掘進機に関する. [従来の技術] シールド工法によりトンネル掘削を行うシールド掘進機
のうち、泥水の還流により切羽の安定と掘削土砂の排出
を行うものとして、泥水式シールド掘進機が知られてい
る. 第7図に示すように、従来この種のシールド掘進機は、
回転して地盤を掘削するカッタ1と、カッタ1を回転自
在に支持すると共に隔壁2で切羽から隔てられたシール
ドフレーム3と、セグメント4を組み立てるエレクタ5
とにより主として梢或され、泥水を切羽に供給・循環さ
せるための送泥管6及び排泥管7が備えられている.そ
してシールドジャッキ8による推力と、シールドフレー
ム3に設けられた駆動用モータ9による回転力とで、所
定の孔径のトンネルを掘進すると共に、セグメント4の
幅だけ堀進する度ごとにセグメント4を組み立てること
で、順次シールドするようになっている. またこの他、シールドフレーム3の後端部には、掘進す
るシールドフレーム3とセグメント4との間を止水する
ためのテールシール10が設けられ、さらに地山とセグ
メント4との間を充填するための裏込め注入装置(図示
せず)が設けられている.[発明が解決しようとする課
題] ところで近来にあっては、地中の利用率が高まり、特に
都市地盤においては上下水道、地下鉄、電線のための埋
設管等々の地中構造物が密集して設けられている.この
ため、ケーブルの増設などの要求があっても、これに対
応すべくトンネルを新規梢築することは極めて困難な状
況にある。
DETAILED DESCRIPTION OF THE INVENTION [Industrial Field of Application] The present invention relates to a shield excavator that excavates a tunnel and sequentially assembles segments to line the tunnel. [Conventional technology] Among the shield excavators that excavate tunnels using the shield method, the mud water type shield excavator is known as one that stabilizes the face and discharges excavated soil by circulating mud water. As shown in Fig. 7, conventionally, this type of shield excavator is
A cutter 1 that rotates to excavate the ground, a shield frame 3 that rotatably supports the cutter 1 and is separated from the face by a bulkhead 2, and an erector 5 that assembles the segments 4.
A mud pipe 6 and a mud drainage pipe 7 are provided to supply and circulate mud water to the face. Then, using the thrust from the shield jack 8 and the rotational force from the drive motor 9 provided on the shield frame 3, a tunnel of a predetermined hole diameter is dug, and each segment 4 is assembled each time the width of the segment 4 is dug. This allows them to be shielded in sequence. In addition, a tail seal 10 is provided at the rear end of the shield frame 3 to stop water between the shield frame 3 and the segments 4 that are being dug, and to fill the space between the ground and the segments 4. A backfill injection device (not shown) is provided for this purpose. [Problem to be solved by the invention] In recent years, the utilization rate of underground has increased, and underground structures such as underground pipes for water supply, sewage, subway, and electric wires have become densely packed, especially in urban areas. It is provided. For this reason, even if there is a demand for additional cables, it is extremely difficult to construct new tunnels to accommodate this demand.

従って、地中スペースを有効に利用するために、既存の
埋設管(トンネル)を拡径することが考えられる,この
場合、既存の埋設管を取り壊しつつ掘進することは、工
事期間中に既存設備の供用を中断することとなるので、
供用と並行して堀進することが望ましい。
Therefore, in order to make effective use of underground space, it is conceivable to expand the diameter of existing buried pipes (tunnels). As this will result in the suspension of service,
It is desirable to proceed with excavation in parallel with the opening.

しかしながら、既存のトンネルに影響を与えず、供用し
たまま掘進するシールド掘進機は、従来なかった。
However, there has never been a shield tunneling machine that excavates existing tunnels while leaving them in service without affecting them.

また、単に掘進機を中空筒体状に変形して、既存埋設管
の周囲を掘進するように楕或しても、機械本体と既存埋
設管との隙間に入り込んでくる地下水(泥水)に対処で
きないと、シールド内での作業が困難となるばかりか、
既存埋設管内に漏水して供用中のケーブル等に悪影響を
及ぼすことにもなる. そこで本発明は、上記事情に鑑み、既存トンネルを拡径
でき、しかもその供用に影響を与えることのないシール
ド掘進機を提供すべく創案されたものである. [課題を解決するための手段] 本発明は、既存埋設管に沿ってその外周を掘削するカッ
タを有した前部フレームと、この前部フレームに重合さ
れその掘進と交互に推進される後部フレームと、上記両
フレームにそれぞれ設けられその待機停止中に既存埋設
管との隙間を封止するシール部とを備えたものである. [作 用] 上記桐戒によって、前部フレームは、カッタの回転によ
り既存埋設管の外周にトンネルを掘削する. tIk部
フレームは、この掘進に追従する。シール部は、他方の
フレームが堀進或いは推進しているときに停止中のフレ
ームと既存埋設管との間を止水し、地下水及び泥水の進
入を阻む.[実總例] 以下、本発明の実施例を、添付図面に従って説明する。
In addition, even if you simply transform the excavator into a hollow cylindrical shape and dig around the existing buried pipe, you can deal with groundwater (muddy water) that gets into the gap between the machine body and the existing buried pipe. Failing to do so will not only make it difficult to work inside the shield, but also
Water may leak into existing buried pipes and have a negative impact on cables, etc. that are in service. In view of the above circumstances, the present invention was devised to provide a shield tunneling machine that can expand the diameter of an existing tunnel without affecting its service. [Means for Solving the Problems] The present invention includes a front frame having a cutter for excavating the outer periphery of an existing buried pipe, and a rear frame superimposed on the front frame and propelled alternately with the excavation. and a seal portion provided on each of the above-mentioned frames to seal the gap with the existing buried pipe while the frame is on standby. [Operation] According to the above-mentioned paulownia, the front frame excavates a tunnel around the outer periphery of the existing buried pipe by rotating the cutter. The tIk part frame follows this excavation. The seal part shuts off water between the stationary frame and the existing buried pipe when the other frame is digging or moving, and prevents groundwater and mud from entering. [Examples] Examples of the present invention will be described below with reference to the accompanying drawings.

第1図は、本発明に係るシールド掘進機の一実施例を示
したものであり、従来と同様の横或には同一符号を付し
、その説明を省略する。
FIG. 1 shows an embodiment of a shield tunneling machine according to the present invention, and the same horizontal or same reference numerals as those in the prior art are used, and the explanation thereof will be omitted.

このシールド掘進機は、既存埋設管たる既設セグメント
2lの外周を掘削するカツタ22を有した前部フレーム
23と、この前部フレーム23に活動可能に重合された
後部フレーム24と、これらフレーム23.24にそれ
ぞれ設けられたシール部25.26とにより主として構
成され、機械全体が略中空筒体状に形或されている。
This shield excavator includes a front frame 23 having a cutter 22 for excavating the outer periphery of an existing segment 2l, which is an existing buried pipe, a rear frame 24 operatively superposed on the front frame 23, and a rear frame 24 that is movably superposed on the front frame 23. 24 and sealing portions 25 and 26 provided respectively, and the entire machine is shaped into a substantially hollow cylindrical shape.

カッタ22は、第3図にも示すように、ドーナツ状に形
成されたカッターフレーム27と、その前端面となる円
環板28に適宜配設されたカツタビット29とで成り、
円環板28の内径は、既設セグメント21の外径よりも
わずかに大きく形成されている.また円環板28の最も
軸心側に位置されたカッタビット30は、既存セグメン
ト21の外壁に分布する裏込め注入材(モルタル)mを
も切削できるように形成されている. 第2図に示すように、前部フレーム23は、カッタ22
の外径に略等しい外殻3lと、切羽からその後方を遮断
する隔壁32と、既設セグメント21を囲繞するように
形成された内殻33とを有し、これらを適宜縦横に骨組
みしてm戒されている. 一方力ッタ22には、この前部フレーム231PIに後
方へ延出された中間リング34が連結され、この延出l
it側に、軸ブロック35が取り付けられている6そし
て外殻31と内殻33との間に、この軸ブロック35を
適宜軸受けするための軸受部36が形成されている.さ
らに、軸ブロック35の後方端部にはラック37が形成
されており、これと噛合する出力端38を有した駆動用
モータ39が、内殻33と外殻3lとの間に固定支持さ
れている.即ち、中間リング34を介して、カッタ22
が駆動用モータ39により回転駆動されるようになって
いる。
As shown in FIG. 3, the cutter 22 consists of a donut-shaped cutter frame 27 and a cutter bit 29 appropriately disposed on an annular plate 28 serving as the front end surface of the cutter frame 27.
The inner diameter of the annular plate 28 is slightly larger than the outer diameter of the existing segment 21. Further, the cutter bit 30 located closest to the axis of the annular plate 28 is formed so as to be able to cut even the backfilling material (mortar) m distributed on the outer wall of the existing segment 21. As shown in FIG. 2, the front frame 23 is connected to the cutter 22
It has an outer shell 3l approximately equal to the outer diameter of the face, a partition wall 32 that blocks the rear part from the face, and an inner shell 33 formed to surround the existing segment 21, and these are appropriately framed vertically and horizontally to form a m It is admonished. On the other hand, an intermediate ring 34 extending rearward from this front frame 231PI is connected to the forceter 22, and this extending l
On the IT side, a shaft block 35 is attached 6, and a bearing portion 36 is formed between the outer shell 31 and the inner shell 33 to properly support the shaft block 35. Further, a rack 37 is formed at the rear end of the shaft block 35, and a drive motor 39 having an output end 38 that meshes with the rack 37 is fixedly supported between the inner shell 33 and the outer shell 3l. There is. That is, via the intermediate ring 34, the cutter 22
is rotated by a drive motor 39.

この中間リング34には、隔壁32の前方において泥水
を撹拌するための攬拌翼40が取り付けられていると共
に、中間リング34と、隔壁32、軸受部36及び内殻
33との間にはそれぞれシールブロック41,42.4
3が設けられ、前部フレーム23に泥水等が浸入しない
ようになっている。また内殻33の軸受部36の内方に
相当する位置には、既設セグメント2lに沿って前部フ
レーム23を案内するためのガイドローラ44が回転自
在に取り付けられている. 第1図に示したように、後部フレーム24は、前部フレ
ーム23の外殻31と略同径の外殻45と、前部フレー
ム23の内殻31よりも俺かに大きい径で成る内殻46
とを有して形成されていると共に、この外殻45の前半
部分かfeJ径されて、前部フレーム23の後半部分に
挿入される形になっている。またこれら外殻31.45
同士及び内殻33.46同士の間には、摺動可能で且つ
機密を保持するように形成されたシール部材47が設け
られている. そしてこの後部フレーム24の前半部分に、所定の推進
力を得るための掘進ジャッキ48と保持ジャッキ49と
が固定されている. 堀進ジャッキ48は、その進退ロッド50の先端が前部
フレーム23に当接するようになっており、伸長したと
きに、フレーム23.24同士が離反するようになって
いる.即ち、後部フレーム24に反力をとることで、掘
進のための推力を得るようになっている.また保持ジャ
ッキ49は、その進退ロッド51の先端が、組み立てら
れたセグメント4の前端面に当接するようになっており
、伸長したときに後部フレーム24が前進するようにな
っている。
A stirring blade 40 for stirring muddy water is attached to the intermediate ring 34 in front of the partition wall 32, and there are spaces between the intermediate ring 34, the partition wall 32, the bearing section 36, and the inner shell 33, respectively. Seal block 41, 42.4
3 is provided to prevent muddy water etc. from entering the front frame 23. Further, a guide roller 44 for guiding the front frame 23 along the existing segment 2l is rotatably attached to a position corresponding to the inside of the bearing part 36 of the inner shell 33. As shown in FIG. 1, the rear frame 24 includes an outer shell 45 having approximately the same diameter as the outer shell 31 of the front frame 23, and an inner shell 45 having a diameter slightly larger than that of the inner shell 31 of the front frame 23. shell 46
The first half of the outer shell 45 has a diameter of feJ and is inserted into the second half of the front frame 23. Also, these outer shells are 31.45
A sealing member 47 is provided between the inner shells 33, 46 and the inner shells 33, 46, which is slidable and configured to maintain airtightness. A digging jack 48 and a holding jack 49 for obtaining a predetermined propulsive force are fixed to the front half of the rear frame 24. The tip of the advancing/retracting rod 50 of the digging jack 48 comes into contact with the front frame 23, and when the jack 48 is extended, the frames 23 and 24 are separated from each other. That is, by applying a reaction force to the rear frame 24, thrust for digging is obtained. Further, the holding jack 49 is configured such that the tip of its advancing/retracting rod 51 comes into contact with the front end surface of the assembled segment 4, so that when the holding jack 49 is extended, the rear frame 24 moves forward.

これらジャッキ48.49は、第4図に示したように、
周方向に交互に配置されている。そしてその作動は、掘
進工程において交互に行われるようになっており、掘進
ジャッキ48によって前部フレーム23が前進するとき
には後部フレーム24は停止し、所定長の掘進がなされ
たときに、後部フレーム24が保持ジャッキ49の伸長
で前部フレーム231l11へと引き付けられるように
なっている.従って、両フレーム23.24の前進は交
互に行われることになる。
These jacks 48, 49, as shown in Figure 4,
They are arranged alternately in the circumferential direction. The operation is performed alternately during the excavation process; when the front frame 23 is advanced by the excavation jack 48, the rear frame 24 is stopped, and when a predetermined length of excavation has been made, the rear frame 24 is stopped. is drawn to the front frame 231l11 by extension of the holding jack 49. The forward movement of both frames 23, 24 therefore takes place alternately.

そして本発明の特長となるシール部25.26は、両フ
レーム23.24の内殻33.46に設けられ、既設セ
グメント21との隙間Sを封止するようになっている. 第5図に示すように、このシール部25.26は、内殻
33.46に形威された複数の環状凹部50と、これら
環状凹部50に保持されたタイヤ状のチューブ5lとで
成る。チューブ51の外周端には鍔52が形成されて、
これが内殻33.46にボルト止めされていると共に、
チューブ51内に流体(空気)を注入するための注入孔
53が形吠されている、そしてその注入圧〈量)を調節
することで、内殻33.46から膨出したチューブ51
の内開端面が、カッタ22によって切り残された裏込め
注入材mの凹凸状の外表面に接着、或いは離間するよう
になっている。従ってこれらシール部25.26は、実
際には、変化する裏込め注入材mとの間隙S0を封止し
ていることになる. またこれら環状凹部50の間には、チューブ51同士の
間に充填材(グリース)gを注入するためのノズル54
が設けられている. このほか前部フレーム23には、第1図に示したように
、径方向に仲縮するサポートジャッキ55が支持されて
おり、後部フレーム24が前進して前部フレーム231
1!lに引き付けられる際に、既設セグメント2lに当
接することで、前部フレーム23が動かないように固定
できるようになっている. また、カッタ22には任意に余掘りを行うための公知の
オーバー力ツタ56が取り付けられていると共に、フレ
ーム23.24内には送泥管57及び排泥管58が適宜
延長されて設けられている。
The seal portions 25, 26, which are a feature of the present invention, are provided on the inner shells 33, 46 of both frames 23, 24, and are designed to seal the gap S with the existing segment 21. As shown in FIG. 5, this seal 25, 26 consists of a plurality of annular recesses 50 formed in the inner shell 33, 46 and a tire-shaped tube 5l held in these annular recesses 50. A collar 52 is formed at the outer peripheral end of the tube 51,
This is bolted to the inner shell 33.46 and
An injection hole 53 for injecting fluid (air) into the tube 51 is formed, and by adjusting the injection pressure (amount), the tube 51 bulges out from the inner shell 33.46.
The inner open end surface of the cutter 22 is attached to or separated from the uneven outer surface of the backfill injection material m left uncut by the cutter 22. Therefore, these seal portions 25, 26 actually seal the gap S0 between the changing backfill injection material m. Further, between these annular recesses 50, there is a nozzle 54 for injecting filler (grease) g between the tubes 51.
is provided. In addition, as shown in FIG. 1, the front frame 23 supports a support jack 55 that is compressed in the radial direction.
1! 1, it comes into contact with the existing segment 2l, thereby fixing the front frame 23 so that it does not move. Further, a well-known over-force vine 56 is attached to the cutter 22 for optionally over-digging, and a mud feeding pipe 57 and a mud draining pipe 58 are provided in the frames 23 and 24 with appropriate extensions. ing.

さらに後部フレーム24には、新規なセクメン1・62
を組み立てるためのエレクタ59が設けられ、このエレ
クタ59を適宜作動させるためのエレク夕昇降ジャッキ
60とエレクタ摺動ジャッ−1r61とが備えられてい
る. 次に本実施例の作用を説明する。
Furthermore, the rear frame 24 has a new Sekmen 1 and 62.
An erector 59 is provided for assembling the erector 59, and an erector lifting jack 60 and an erector sliding jack 1r61 are provided for operating the erector 59 appropriately. Next, the operation of this embodiment will be explained.

ケーブル等が配設されて供用されているシールドトンネ
ルを利用して、これを拡径するに際して、まず前部フレ
ーム23及び後部フレーム24を、その発進立坑(図示
せず)において既設セグメント21に同心状にセットす
る。
When expanding the diameter of a shield tunnel in use with cables etc. installed, first the front frame 23 and the rear frame 24 are installed concentrically with the existing segment 21 in the starting shaft (not shown). set in shape.

そして、後部フレーム24を固定しておき、送泥管57
及び排泥管58によって泥水を循環させつつ、駆動用モ
ータ39及び掘進ジャッキ48を作動させることで、カ
ッタ22の所定の回転及び推進力をもってa設セグメン
ト2lの外周を掘進する. この掘進の際、後部フレーム24は待機停止された状態
になっている。そして、そのシール部26において、チ
ューブ5lに流体を注入してこれを適宜膨張させること
で、既設セグメント21の周囲に分布している切り残さ
れた裏込め注入材mに圧接させ、切羽開からカツタ22
及び?lv部フレーム23と既設セグメント21との隙
間Sを通って後方に浸入してくる地下水及び泥水を遮断
する. 所定の長さだけ掘進した後、前部フレーム23をサポー
トジャッキ55によって、その位置で固定させると共に
、そのシール部25においてチューブ51を膨張させる
ことで止水を行う.そして後部シール部26のチューブ
圧を除去して既設セグメント21側から離間させた後、
掘進ジャッキ48を短縮、保持ジャッキ49を伸長させ
ることで、後部フレーム24を前進させて、前部フレー
ム23内に挿入し重ね合わせる.そしてエレクタ59に
よって、掘進した分の新設セグメント62の組み立てを
行う. セグメント62の組み立て終了後、後部フレーム24は
このセグメント62に反力をとることで保持ジャッキ5
5により保持され、以降、カッタ22及び前部フレーム
23による掘進、後部フレーム24の追従、セグメント
62の組み立てが繰り返されて、既設セグメント2lの
外周に、断面が同心円状の拡径されたトンネルが楕築さ
れる.このように、掘進する前部フレーム23とこれに
追従する後部フレーム24とを形成し、それぞれのシー
ル部25.26によって、既設セグメント21との隙間
Sを封止するようにしたので、既存のトンネルに影響を
与えることなく、拡径したシールドトンネルを構築する
ことができる。
Then, the rear frame 24 is fixed, and the mud feeding pipe 57 is
By operating the drive motor 39 and excavation jack 48 while circulating mud water through the mud drain pipe 58, the cutter 22 excavates around the outer periphery of the a-setting segment 2l with a predetermined rotation and propulsive force. During this digging, the rear frame 24 is in a standby state. Then, in the sealing part 26, by injecting fluid into the tube 5l and expanding it appropriately, it is brought into pressure contact with the uncut backfill injection material m distributed around the existing segment 21, and from the opening of the face. Katsuta 22
as well as? Blocks groundwater and muddy water from entering the rear through the gap S between the lv frame 23 and the existing segment 21. After digging a predetermined length, the front frame 23 is fixed at that position by a support jack 55, and the tube 51 is expanded at the seal portion 25 to stop water. After removing the tube pressure from the rear seal portion 26 and separating it from the existing segment 21 side,
By shortening the digging jack 48 and extending the holding jack 49, the rear frame 24 is advanced, inserted into the front frame 23, and overlapped. Then, the erecta 59 assembles the newly constructed segment 62 corresponding to the excavated portion. After assembling the segment 62, the rear frame 24 applies a reaction force to the segment 62, thereby lifting the holding jack 5.
Thereafter, the excavation by the cutter 22 and the front frame 23, the following by the rear frame 24, and the assembly of the segments 62 are repeated, and an enlarged diameter tunnel with a concentric cross section is formed around the outer periphery of the existing segment 2l. It is built oval. In this way, the front frame 23 that excavates and the rear frame 24 that follows it are formed, and the gaps S between them and the existing segments 21 are sealed by the respective seal parts 25 and 26. It is possible to construct a shield tunnel with an expanded diameter without affecting the tunnel.

即ち、a設管内の施設を供用させたまま、これと並行し
て堀進作業ができ、ケーブルの増設などの規模拡張工事
を行うに際し、その工期短縮に貢献できる, そして、両フレーム23.24を交互に前進させて、停
止している方のシール部25.26を作動するようにし
たので、既設セグメント21周囲の凹凸がある注入材m
層表面に対して確実にシールでき、地下水(泥水)の浸
入を防止して、シールド内での作業環境保全が図れると
共に、既存トンネル内への漏水を未然に防ぐ。
In other words, excavation work can be carried out in parallel while the facilities in the pipe a are kept in service, contributing to shortening the construction period when carrying out scale expansion work such as adding cables. Since the seal portions 25 and 26 that are stopped are activated by advancing them alternately, the injection material m that has irregularities around the existing segment 21 can be moved forward.
It can reliably seal against the surface of the layer, preventing underground water (muddy water) from entering, preserving the working environment within the shield, and preventing water leakage into existing tunnels.

なお、シール部25.26の楕戊としては、上記実施例
に限るものではなく、例えば第6図に示すように構成し
てもよい。
Note that the oval shape of the seal portions 25 and 26 is not limited to the above embodiment, and may be configured as shown in FIG. 6, for example.

このシール部71は、内殻33.46の端部に取り付け
られた鍵状の延長板72と、その内開(既設セグメント
21側)に設けられた前記実施例と同様のチューブ73
及びチューブ保持体74と、内殻33.46及びチュー
ブ保持体74とを連結する弾性板75とでllI戒され
ている.チューブ保持体74には、環状凹部76が形成
されてチューブ73を保持するようになっていると共に
、延長板71の鍵状の先端部の内壁に対して径方向に摺
動自在に形成されている.そして保持体74と延長板7
1との間に区画された密閉室には所定圧の流体nが充填
され、弾性板75の弾性力と相俟って、保持体74を常
時内側に適宜押し付けるようになっている. 従って、このチューブ73は、フレーム23.24の相
対的な位置とは無関係に、既設セグメント21(注入材
m)に嵌め合わされる形になり、掘進めフレがあっても
、常に接着するものである.言い換えると、チューブ7
3の膨張は必要最少限のものでよく、シール部の操作管
理上、或いは部材の耐久性からみて極めて実際的である
.なお、この新設トンネルを供用するに際しては、既設
セグメントをそのまま残しても、或いは掘進完了後に壊
して拡径トンネルとして利用してもどちらでもよく、汎
用性のあるトンネルとして利用できるものである。
This sealing portion 71 consists of a key-shaped extension plate 72 attached to the end of the inner shell 33.46, and a tube 73 similar to that of the previous embodiment provided at the inner opening (on the existing segment 21 side).
And the tube holder 74 and the elastic plate 75 connecting the inner shell 33.46 and the tube holder 74 are held together. The tube holder 74 is formed with an annular recess 76 for holding the tube 73, and is also formed to be slidable in the radial direction on the inner wall of the key-shaped tip of the extension plate 71. There is. And the holding body 74 and the extension plate 7
1 is filled with a fluid n at a predetermined pressure, and in combination with the elastic force of the elastic plate 75, the holding body 74 is pressed inward at all times. Therefore, this tube 73 is fitted into the existing segment 21 (injected material m) regardless of the relative position of the frames 23 and 24, and is always bonded even if there is deflection during digging. be. In other words, tube 7
The expansion in step 3 is the minimum necessary amount, and is extremely practical from the viewpoint of operational management of the seal section and durability of the parts. When putting this new tunnel into service, it can be used as a versatile tunnel, either by leaving the existing segments as they are or by destroying them after excavation is complete and using them as an expanded tunnel.

[発明の効果] 以上要するに本発明によれば、次のような優れた効果を
発揮する. 既存埋設管に沿ってその外周を掘削するカッタを有した
前部フレームと、これに重合されその掘進と交互に推進
される後部フレームと、両フレームにそれぞれ設けられ
その待機停止中に既存埋設管との隙間を封止するシール
部とを備えたので、既存設備を供用させた.tまトンネ
ルを拡径できると共に、既存埋設管と掘進機との間を確
実に止水して作業環境保全及び既存埋設管内への漏水防
止ができる。
[Effects of the Invention] In summary, according to the present invention, the following excellent effects are achieved. A front frame has a cutter that excavates the outer periphery of the existing buried pipe, a rear frame that overlaps with this and is propelled alternately with the excavation, and a rear frame that is installed on both frames and excavates the existing buried pipe while it is in standby. Since it is equipped with a seal part that seals the gap between the In addition to expanding the diameter of the tunnel, it is possible to reliably shut off water between the existing buried pipe and the excavator, thereby preserving the working environment and preventing water leakage into the existing buried pipe.

【図面の簡単な説明】[Brief explanation of drawings]

第1図は本発明に係るシールド掘進機の側断面図、第2
図は第1図中の■部拡大図、第3図は第1図中の厘一■
線矢視断面図、第4図は第1図中のIV−rV線矢視断
面図、第5図は第1図のシール部の拡大図、第6図はシ
ール部の他の実施例を示した側断面図、第7図は従来の
シールド掘進機を示した側断面図である.
FIG. 1 is a side sectional view of a shield tunneling machine according to the present invention, and FIG.
The figure is an enlarged view of part ■ in Figure 1, and Figure 3 is an enlarged view of part ■ in Figure 1.
4 is a sectional view taken along the line IV-rV in FIG. 1, FIG. 5 is an enlarged view of the seal portion in FIG. 1, and FIG. 6 shows another example of the seal portion. The side sectional view shown in FIG. 7 is a side sectional view showing a conventional shield tunneling machine.

Claims (1)

【特許請求の範囲】[Claims] 1、既存埋設管に沿ってその外周を掘削するカッタを有
した前部フレームと、該前部フレームに重合されその掘
進と交互に推進される後部フレームと、上記両フレーム
にそれぞれ設けられその待機停止中に上記既存埋設管と
の隙間を封止するシール部とを備えたことを特徴とする
シールド掘進機。
1. A front frame with a cutter that excavates the outer circumference of an existing buried pipe, a rear frame that overlaps with the front frame and is propelled alternately with the excavation, and a standby frame that is installed on each of the above frames. A shield excavator characterized by comprising a seal part that seals a gap with the existing buried pipe while the shield excavator is stopped.
JP1344109A 1989-12-29 1989-12-29 Shield machine Expired - Fee Related JP2712686B2 (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
JP1344109A JP2712686B2 (en) 1989-12-29 1989-12-29 Shield machine

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
JP1344109A JP2712686B2 (en) 1989-12-29 1989-12-29 Shield machine

Publications (2)

Publication Number Publication Date
JPH03206291A true JPH03206291A (en) 1991-09-09
JP2712686B2 JP2712686B2 (en) 1998-02-16

Family

ID=18366710

Family Applications (1)

Application Number Title Priority Date Filing Date
JP1344109A Expired - Fee Related JP2712686B2 (en) 1989-12-29 1989-12-29 Shield machine

Country Status (1)

Country Link
JP (1) JP2712686B2 (en)

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP2009001960A (en) * 2007-06-19 2009-01-08 Mitsubishi Heavy Industries Tunneling Machinery & Geotechnology Co Ltd Tunnel excavator, gear for transmitting rotation torque used in tunnel excavator, and positioning method for gear for transmitting rotation torque

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP2009001960A (en) * 2007-06-19 2009-01-08 Mitsubishi Heavy Industries Tunneling Machinery & Geotechnology Co Ltd Tunnel excavator, gear for transmitting rotation torque used in tunnel excavator, and positioning method for gear for transmitting rotation torque
JP4648364B2 (en) * 2007-06-19 2011-03-09 三菱重工メカトロシステムズ株式会社 Rotational torque transmission gear used in tunnel excavator and positioning method of rotational torque transmission gear

Also Published As

Publication number Publication date
JP2712686B2 (en) 1998-02-16

Similar Documents

Publication Publication Date Title
JP2017166189A (en) Construction method of large cross-section underground space, and outer shell shield starting base
JPH03206291A (en) Shield excavator
JP3471457B2 (en) Shielding machine for tunneling of different diameter
JP3559089B2 (en) Magnifying shield drilling rig
JPH0244996B2 (en)
JP2712685B2 (en) Shield machine
JP3733796B2 (en) Shield device and shield method
JPH0468188A (en) Execution method of tunnel widening section
JPH02140394A (en) Annular double excavating device
JP4299233B2 (en) Shield machine
JPS6349034B2 (en)
JP3636320B2 (en) Diverging type propulsion machine
JP3347810B2 (en) Shield tunnel widening method and equipment
JP2585365B2 (en) Shield method
JP2876338B2 (en) Shield backfill device
JP2735871B2 (en) Hollow body drilling method and drilling equipment
JP2006194003A (en) Shielding machine
JPH11294069A (en) Underground junction type shield boring machine
JP2712685C (en)
JPH01203593A (en) Shield excavator
JP3487645B2 (en) Underground joining structure and underground joining method of different diameter shield machine
JPH0224997B2 (en)
JPH10131662A (en) Method for taking out shield excavator out of arrival pit mouth
JPS63217098A (en) Method and device for constructing underground shell body
JPH0588357B2 (en)

Legal Events

Date Code Title Description
FPAY Renewal fee payment (event date is renewal date of database)

Free format text: PAYMENT UNTIL: 20071031

Year of fee payment: 10

S531 Written request for registration of change of domicile

Free format text: JAPANESE INTERMEDIATE CODE: R313531

S533 Written request for registration of change of name

Free format text: JAPANESE INTERMEDIATE CODE: R313533

FPAY Renewal fee payment (event date is renewal date of database)

Free format text: PAYMENT UNTIL: 20071031

Year of fee payment: 10

R350 Written notification of registration of transfer

Free format text: JAPANESE INTERMEDIATE CODE: R350

FPAY Renewal fee payment (event date is renewal date of database)

Free format text: PAYMENT UNTIL: 20071031

Year of fee payment: 10

FPAY Renewal fee payment (event date is renewal date of database)

Free format text: PAYMENT UNTIL: 20081031

Year of fee payment: 11

LAPS Cancellation because of no payment of annual fees