JPH0146652B2 JP2559384A JP2559384A JPH0146652B2 JP H0146652 B2 JPH0146652 B2 JP H0146652B2 JP 2559384 A JP2559384 A JP 2559384A JP 2559384 A JP2559384 A JP 2559384A JP H0146652 B2 JPH0146652 B2 JP H0146652B2
Authority
JP
Japan
Prior art keywords
slope
soil
cloth
concrete
sheet
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Expired
Application number
JP2559384A
Other languages
Japanese (ja)
Other versions
JPS60168820A (en
Inventor
Kyoshi Yamamoto
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
OYO KIKAKU KK
Original Assignee
OYO KIKAKU KK
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by OYO KIKAKU KK filed Critical OYO KIKAKU KK
Priority to JP2559384A priority Critical patent/JPS60168820A/en
Publication of JPS60168820A publication Critical patent/JPS60168820A/en
Publication of JPH0146652B2 publication Critical patent/JPH0146652B2/ja
Granted legal-status Critical Current

Links

Classifications

    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D17/00Excavations; Bordering of excavations; Making embankments
    • E02D17/20Securing of slopes or inclines
    • E02D17/202Securing of slopes or inclines with flexible securing means

Landscapes

  • Engineering & Computer Science (AREA)
  • Mining & Mineral Resources (AREA)
  • Life Sciences & Earth Sciences (AREA)
  • General Life Sciences & Earth Sciences (AREA)
  • Paleontology (AREA)
  • Civil Engineering (AREA)
  • General Engineering & Computer Science (AREA)
  • Structural Engineering (AREA)
  • Pit Excavations, Shoring, Fill Or Stabilisation Of Slopes (AREA)

Description

【発明の詳細な説明】 この発明は、法面の植生基盤形成方法にかかわ
る。
DETAILED DESCRIPTION OF THE INVENTION The present invention relates to a method for forming a vegetation base on a slope.

岩盤など植生基盤の形成し難い法面を緑化する
場合、主として、客土を吹きつける方法、又は、
2枚の布を袋状に形成してその中に、流動化した
土を注入する方法の何れかが用いられてきた。然
し、前者は、吹きつけのコストが高いこと、厚く
吹きつけると脱落し易いこと、後者は、布コスト
が高いこと、注入した土が布によつて遮られ法面
とのなじみが悪いこと、が欠点となつて普及し難
いのが現状である。
When greening slopes where it is difficult to form a vegetation base such as bedrock, the main methods are to spray soil or
One of the methods used has been to form two pieces of cloth into a bag and pour fluidized soil into the bag. However, the former is expensive to spray and tends to fall off when sprayed thickly, while the latter requires high fabric costs, and the injected soil is blocked by the fabric and does not blend well with the slope. The current situation is that this is a drawback and is difficult to popularize.

この発明はこのような従来工法の欠点を改良す
ることを目的とする。この発明の方法は、上記第
二の方法を踏襲し、流動化された土を注入する方
法を用いるが、一枚の布で施工することにより、
従来工法の、コスト並びに法面とのなじみを解決
したものである。以下、この発明の実施例を図面
について詳細に説明する。
The purpose of this invention is to improve the drawbacks of such conventional construction methods. The method of this invention follows the second method described above and uses a method of injecting fluidized soil, but by applying it with a single piece of cloth,
This solves the cost and incompatibility with the slope of conventional construction methods. Hereinafter, embodiments of the present invention will be described in detail with reference to the drawings.

実施例 1 ナイロンキヤンバスなど透水性と可撓性がある
丈夫な布を用いて、法面の長さと略等しい長さの
筒状体1を形成する。ジユウトの粗目の織布な
ど、透水性と可撓性がある、略同じ長さの帯状の
布2の両側縁部に、それぞれ上記筒状体1を縫い
付けて、布型枠3を形成する(第1図参照)。そ
の場合、両側縁には若干の縫い合わせ代4を残し
て置くと都合がよい。この縫い合わせ代には、接
続用の鳩目5を付設しておいてもよい。筒状体
は、充填した時の太さが5〜30cm、帯状の布の巾
は50cm〜2mが一般的である。又、法面の短いと
きには、布型枠3同志何枚かを縫い合わせ代4の
個所で予め接続して広巾の布型枠3を形成してお
いてもよい(第2図参照)。
Example 1 A cylindrical body 1 having a length approximately equal to the length of the slope is formed using a water permeable and flexible strong cloth such as nylon canvas. The above-mentioned cylindrical body 1 is sewn onto both side edges of a band-shaped cloth 2 of approximately the same length, which is water-permeable and flexible, such as a coarse woven cloth, to form a cloth form 3. (See Figure 1). In that case, it is convenient to leave a slight seam allowance 4 on both side edges. A connecting eyelet 5 may be provided in this seam allowance. The cylindrical body generally has a thickness of 5 to 30 cm when filled, and the width of the strip of cloth is generally 50 cm to 2 m. Further, when the slope is short, a wide cloth form 3 may be formed by connecting several pieces of cloth form 3 in advance at seam allowances 4 (see FIG. 2).

このような布型枠3を、筒状体1が法面上で上
下方向となるように、又、筒状体が帯状の布2の
下側になるように法面A上に敷設し、容易に動か
ないように、筒状体をアンカーピン6などを用い
て固定する。布型枠A同志は鳩目5に接続ロープ
7を通して互いに接続しておく。布型枠3の下端
部は基礎コンクリート8を上に打つて封鎖してお
く(第3図参照)。
Such a fabric form 3 is laid on the slope A so that the cylindrical body 1 is vertically on the slope, and the cylindrical body is below the band-shaped cloth 2, The cylindrical body is fixed using an anchor pin 6 or the like so that it does not move easily. The cloth forms A are connected to each other by passing a connecting rope 7 through the eyelet 5. The lower end of the cloth formwork 3 is sealed by pouring foundation concrete 8 on top (see Figure 3).

次いで、コンクリートポンプを用いてコンクリ
ートを筒状体1の中に注入打設する。余剰水はナ
イロンキヤンバスの織目を通して排出され、筒状
体はコンクリート9で充満され縦梁Bが構築され
る。帯状の布2は、筒状の縦梁の上面に張設され
た状態となり、布・法面・両側の縦梁に囲まれた
空間Cが形成される。コンクリート打設に先立つ
て、防錆被覆を施した針金10を、縦梁の上面に
適宜間隔で、先端を差し込んだ状態で付設して置
くと好都合である(第4図参照)。
Next, concrete is injected into the cylindrical body 1 using a concrete pump. Excess water is drained through the weave of the nylon canvas, and the tube is filled with concrete 9 to construct the longitudinal beam B. The band-shaped cloth 2 is stretched over the upper surface of the cylindrical vertical beam, and a space C is formed surrounded by the cloth, the slope, and the vertical beams on both sides. Prior to concrete pouring, it is convenient to attach rust-proof coated wires 10 to the upper surface of the longitudinal beams at appropriate intervals with their tips inserted (see FIG. 4).

次いで、コンクリートがある程度硬化した後、
即ち、少なくとも一両日置いてから、引張強度の
大きい金網11を、帯状の布2の上に横方向に張
設する。金網の上からはワイヤーロープ12で抑
え、縦梁に差し込んだ針金を用いて、ワイヤーロ
ープを固定する。
Then, after the concrete has hardened to some extent,
That is, after leaving it for at least a day or two, a wire mesh 11 having a high tensile strength is stretched across the strip of cloth 2 in the transverse direction. A wire rope 12 is held down from above the wire mesh, and the wire rope is fixed using a wire inserted into a vertical beam.

次いで、上記した空間Cの中に流動化した土を
注入する。余剰水は布の織目を通して排出され、
充分に締まつた土Dが空間に充填されて植生基盤
が形成される。注入する土の中には、堆肥・土壌
改良剤・肥料・緩効性肥料・保水剤・有機物の他
に、植生用種子13を混入しておく(第5図参
照)。
Next, fluidized soil is poured into the space C described above. Excess water is drained through the fabric weave,
The space is filled with sufficiently compacted soil D to form a vegetation base. In addition to compost, soil conditioner, fertilizer, slow-release fertilizer, water retention agent, and organic matter, vegetation seeds 13 are mixed into the soil to be injected (see Figure 5).

実施例 2 鉄筋14、フープ筋15とからなる鉄筋篭16
複数本を、法面A上に上下方向に、所定間隔をお
いて敷設し、適宜アンカーピン5などを用いて固
定し、次いで、該鉄筋篭の上からモルタルあるい
はコンクリートを吹きつけによつて打設し、縦梁
Bを構成する。モルタル類が完全に硬化する前
に、この縦梁に上面を平坦にならし、中央部に溝
17を設けておく(第6図参照)。
Example 2 Reinforcement cage 16 consisting of reinforcing bars 14 and hoop bars 15
A plurality of rods are laid vertically on the slope A at predetermined intervals, fixed using anchor pins 5, etc. as appropriate, and then mortar or concrete is poured over the reinforcing bar cage by spraying. and constitute the longitudinal beam B. Before the mortar is completely hardened, the upper surface of this vertical beam is made flat and a groove 17 is provided in the center (see FIG. 6).

次いで、モルタル類が或る程度硬化した段階
で、広巾の編布からなるシート状物18を、縦梁
相互間上に張設する。シート状物に横方向に補強
用ロープ19が編み込まれている。縦梁の溝17
の個所にシート状物の上からワイヤーロープ12
を当て、アンカーピン5を用いて固定する。シー
ト状物は法面から縦梁の高さの分だけ隔てられる
(第7図参照)。
Next, when the mortar has hardened to some extent, a sheet-like material 18 made of a wide knitted fabric is stretched between the longitudinal beams. A reinforcing rope 19 is woven into the sheet material in the transverse direction. Longitudinal beam groove 17
Place the wire rope 12 on top of the sheet material at
and fix using anchor pin 5. The sheet is separated from the slope by the height of the longitudinal beam (see Figure 7).

次いで、実施例1と同様にシート状物・法面・
両側の縦梁に囲まれた空間Cに土を注入し、植生
基盤を形成する。
Next, in the same manner as in Example 1, sheet-like materials, slopes,
Soil is poured into space C surrounded by the longitudinal beams on both sides to form a vegetation base.

この発明の骨子は、縦梁を法面上に上下方向に
間隔をおいて敷設し、この縦梁相互間にシート状
物を張設して、このシート状物・法面・両側の縦
梁に囲まれた空間に、スラリー状の土を注入する
ことにあるので、上記した二つの実施例に限定さ
れることなく、下記のような方法も可能である。
The gist of this invention is to lay vertical beams on a slope at intervals in the vertical direction, stretch sheet-like materials between the vertical beams, The purpose of this method is to inject soil in the form of slurry into a space surrounded by , so the method is not limited to the two embodiments described above, and the following method is also possible.

〔その他の実施例〕[Other Examples]

(a) ボタ山など酸性の強い土壌に植生する場合に
は、プラスツチツクシート・ゴムシート・アス
フアルト遮水膜などで、法面A上に遮蔽膜20
を形成した上、この発明の方法で植生基盤を形
成する。重い縦梁でもつて、法面を抑え、表面
もシート状物などで保護されるので、厚い客土
層が安定的に形成できる(第8図参照)。
(a) When growing vegetation on highly acidic soil such as a rubbish pile, cover the slope with a shielding film 20, such as a plastic sheet, rubber sheet, or asphalt water-shielding film.
, and then a vegetation base is formed using the method of the present invention. Even with heavy vertical beams, the slope is suppressed, and the surface is also protected by sheets, etc., so a thick layer of soil can be stably formed (see Figure 8).

(b) 実施例1で、布型枠を形成するには、帯状の
布の片側を折り返して袋状に縫製し、これを接
続する方法をとつてもよい(第9図参照)。し
かし、筒状体が充填された後、この上に乗つて
作業する場合があるので、筒状体が並列されて
いる方が、上を歩いたりするには好都合であ
る。
(b) In Embodiment 1, in order to form the cloth form, one side of the strip-like cloth may be folded back and sewn into a bag shape, and then connected (see FIG. 9). However, after the cylindrical bodies are filled, there is a case where the worker steps on the cylindrical bodies to work, so it is more convenient to walk on the cylindrical bodies if they are arranged side by side.

(c) 筒状体と帯状の布とは必ずしも一体に形成さ
れなくとも、筒状体を別個に法面上に敷設し、
コンクリート等を注入・充填してから、広巾の
シート状物を張設する方法でも差し支えない。
(c) Even if the cylindrical body and the band-shaped cloth are not necessarily formed integrally, the cylindrical body may be laid separately on the slope,
It is also possible to pour and fill concrete, etc., and then stretch a wide sheet-like material.

(d) 筒状体の中に、コンクリート・モルタルを注
入する場合、注入に先立つて、鉄筋を配筋する
ことは構造の強度上望ましい。鉄筋コンクリー
トの筒状体を縦梁Bとしてこれに孔をあけ、法
面に深く打ち込んだテンシヨンアンカー21で
引つ張れば、更に安定度が増す(第10図参
照)。コンクリートの縦梁は、法面が長い・勾
配が急・滑り易い地盤など地盤条件の悪い時に
有効である。
(d) When pouring concrete or mortar into a cylindrical body, it is desirable for the strength of the structure to place reinforcing bars before pouring. If a reinforced concrete cylinder is used as the vertical beam B and a hole is drilled in it and tensioned with a tension anchor 21 driven deep into the slope, stability will be further increased (see Figure 10). Concrete vertical beams are effective when ground conditions are poor, such as long slopes, steep slopes, or slippery ground.

(e) 筒状体に注入するのは、コンクリートでなく
土でもよい。この場合、筒状体の部分も植生が
可能である。筒状体並びに空間に注入する土に
は、天然の土の他にも、堆肥・化成肥料・緩効
性肥料・保水剤・土壌改良剤などの内、1種類
または2種類以上を適宜混入してもよい。更に
植生用種子を混入しておいてもよい。
(e) The cylinder may be filled with soil instead of concrete. In this case, the cylindrical body can also be covered with vegetation. In addition to natural soil, one or more of compost, chemical fertilizers, slow-release fertilizers, water retention agents, soil conditioners, etc. may be mixed into the soil injected into the cylindrical body and space. It's okay. Furthermore, seeds for vegetation may be mixed.

(f) 筒状体の中に、砂利・砂・スラグなど重量が
あり、透水係数の高い材料を注入すれば、筒状
体の上に植生が難しいが、上下方向に通ずる透
水管が形成されるので、湧水の多い法面には最
適である。透水管の形成には、不織布を周囲に
巻いた長尺で可撓性のある透水プラスチツク管
22などの暗渠類を、土の注入に先立つて上下
方向に配管しておくのも効果的である(第11
図参照)。
(f) If a heavy material with a high permeability coefficient, such as gravel, sand, or slag, is injected into the cylindrical body, it will be difficult for vegetation to grow on top of the cylindrical body, but a permeable pipe that runs vertically will be formed. Therefore, it is ideal for slopes with a lot of spring water. To form a water permeable pipe, it is also effective to install a long, flexible water permeable plastic pipe 22 wrapped around a nonwoven fabric under conduits in the vertical direction prior to soil injection. (11th
(see figure).

(g) 植生用種子は、実施例のように注入する土
に混入する方法も採用できるが、種子を付設し
た種子シート23を用いることも可能である。
厚い客土層を形成する場合には、種子の無駄を
省く意味からも、種子シートの採用がのぞまし
い。種子シートを用いるには、帯状の布2の裏
面に重ね合わせて付設しておくのがよい(第1
2図参照)。布の表面をネツトで覆う場合には、
種子シートを布の上、ネツトの下に付設するこ
ともできる。
(g) Vegetation seeds may be mixed into the soil to be injected as in the embodiment, but it is also possible to use a seed sheet 23 with seeds attached.
When forming a thick soil layer, it is desirable to use a seed sheet in order to avoid waste of seeds. To use the seed sheet, it is best to attach it to the back side of the strip-shaped cloth 2 (first
(See Figure 2). When covering the surface of cloth with netting,
The seed sheet can also be attached on top of the cloth or under the net.

(h) 実施例においては、帯状の布2の上に金網
及びワイヤーロープでもつて補強してから、土
を注入したが、補強材は省略可能である。
(h) In the example, soil was injected after reinforcing the strip of cloth 2 with wire mesh and wire rope, but the reinforcing material can be omitted.

(i) 筒状体の素材は、その中に何を注入するかに
依つて決定することが望ましい。実施例のよう
にコンクリートの場合は、比較的目の密な布、
土の場合は、粗目で植物の芽が出易い材料を選
定する。
(i) It is desirable to determine the material of the cylindrical body depending on what is to be injected into it. In the case of concrete as in the example, relatively dense cloth,
If using soil, choose a material that is coarse and allows plants to easily sprout.

砂の場合には、不織布を巻いた透水プラスチ
ツク管22が有効である。透水プラスチツク管
二本を並列したものを法面上に上下方向に、間
隔をおいて敷設し、中に砂24を注入・充填し
て砂の柱からなる縦梁を構成する。以下、実施
例2と同様に施工を行う(第13図参照)。
In the case of sand, a water-permeable plastic tube 22 wrapped with non-woven fabric is effective. Two water-permeable plastic pipes arranged in parallel are laid vertically on a slope at intervals, and sand 24 is injected and filled inside to form a vertical beam consisting of a sand column. Thereafter, construction is carried out in the same manner as in Example 2 (see Fig. 13).

(j) 縦梁には法面を上下方向に連続する広巾の
溝に分割する、シート状物を法面から一定間
隔隔てる、注入する土をせき止める、機能が
要求されるので、これらの機能を満足させるこ
とが出来れば、中空の構造であつても差し支え
ない。例えば、ポーラスなコンクリートの管、
耐圧強度がある透水プラスチツク管などを使用
することも可能である。剛性のある材料を用い
る時は、特に法面との空隙に注意が必要であ
る。
(j) Vertical beams are required to have the functions of dividing the slope into wide grooves that are continuous in the vertical direction, separating sheet materials from the slope at a certain distance, and damming up the soil being poured. A hollow structure is acceptable as long as it satisfies the requirements. For example, porous concrete pipes,
It is also possible to use water-permeable plastic pipes that have pressure resistance. When using rigid materials, special attention must be paid to the gap between the slope and the slope.

(k) コンクリート製の縦梁を構成する方法とし
ては、上記二つの実施例に限定されることな
く、コンクリート二次製品の角柱状の法枠部材
25を積み上げる方法でもよい(第14図参
照)。
(k) The method of configuring the concrete vertical beam is not limited to the above two embodiments, and may also be a method of piling up prismatic frame members 25 of secondary concrete products (see Fig. 14). .

又、半筒状のコンクリート製捨て型枠26を
法面上に伏せた状態で設置し、その中に鉄筋篭
16を配筋してコンクリートを打設するような
方法でも差し支えない(第15図参照)。
Alternatively, a half-cylindrical concrete disposable formwork 26 may be installed face down on a slope, and the reinforcing bar baskets 16 may be placed inside the formwork and concrete may be poured (Fig. 15). reference).

〔発明の効果〕〔Effect of the invention〕

この発明は、上記のように構成されているので
次のような効果をもたらす。
Since the present invention is configured as described above, it brings about the following effects.

(1) 法面を覆うシート状物は単層でよいので、必
要材料が大幅に削減でき、又、縫製個所も少な
いので、コスト的に大幅な合理化が可能となつ
た。
(1) Since the sheet-like material covering the slope can be made of a single layer, the required materials can be greatly reduced, and there are fewer sewing parts, so it has become possible to significantly rationalize costs.

(2) 注入された土は直接法面に接するので、法面
へのなじみがよい。
(2) The poured soil is in direct contact with the slope, so it blends well with the slope.

このように、従来工法の持つ二つの根本的欠
点を解決する以外にも、次のような副次的効果
を発揮する。
In this way, in addition to solving the two fundamental drawbacks of the conventional method, it also produces the following secondary effects.

(3) 縦梁が構築されるので、全面が布袋で構成さ
れている従来の方法に比べ、強度・排水性など
独自の機能が発揮できる。特に、上下方向に連
続したコンクリート梁が構築でき、テンシヨン
アンカー等の併用により、植生可能範囲を大幅
に拡大した。
(3) Since vertical beams are constructed, unique functions such as strength and drainage performance can be demonstrated compared to the conventional method where the entire surface is made of cloth bags. In particular, it was possible to construct concrete beams that were continuous in the vertical direction, and by using tension anchors, etc., the possible range of vegetation was greatly expanded.

(4) 必要に応じ、金網・ワイヤーロープなどを用
いて、能率良く且つ有効に補強できる。このた
め、前項のメリツトを更に拡大した。
(4) If necessary, it can be reinforced efficiently and effectively using wire mesh, wire rope, etc. For this reason, the benefits mentioned in the previous section have been further expanded.

(5) シート状物が単層構造なので、種子シートが
使用出来、土全体に種子を混入せざるをえない
従来の工法を合理化できた。
(5) Since the sheet material has a single-layer structure, seed sheets can be used, streamlining the conventional construction method that requires mixing seeds into the entire soil.

【図面の簡単な説明】[Brief explanation of drawings]

第1図・第2図並びに第9図は、布型枠の形成
方法の一例を示す斜視図、第3図〜第5図は実施
例1の施工手順を示す斜視図、第6図並びに第7
図は実施例2の施工手順を示す斜視図、第8図・
第10図並びに第12図は施工状況の一例を示す
側断面図、第11図並びに第13図は同じく平断
面図、第14図並びに第15図は施工状況の一例
を示す斜視図である。 A……法面、B……縦梁、C……空間、D……
土、1……筒状体、2……帯状の布、3……布型
枠、4……縫い合わせ代、5……鳩目、6……ア
ンカーピン、7……接続ロープ、8……基礎コン
クリート、9……コンクリート、10……針金、
11……金網、12……ワイヤーロープ、13…
…植生用種子、14……鉄筋、15……フープ
筋、16……鉄筋篭、17……溝、18……シー
ト状物、19……補強用ロープ、20……遮蔽
膜、21……テンシヨンアンカー、22……透水
プラスチツク管、23……種子シート、24……
砂、25……法枠部材、26……捨て型枠。
FIGS. 1, 2, and 9 are perspective views showing an example of the fabric form forming method, FIGS. 3 to 5 are perspective views showing the construction procedure of Example 1, and FIGS. 7
The figure is a perspective view showing the construction procedure of Example 2.
10 and 12 are side sectional views showing an example of a construction situation, FIGS. 11 and 13 are plan sectional views, and FIGS. 14 and 15 are perspective views showing an example of a construction situation. A...Slope, B...Vertical beam, C...Space, D...
Soil, 1... Cylindrical body, 2... Band-shaped cloth, 3... Fabric formwork, 4... Sewing allowance, 5... Eyelet, 6... Anchor pin, 7... Connection rope, 8... Foundation Concrete, 9...Concrete, 10...Wire,
11...wire mesh, 12...wire rope, 13...
...Vegetation seeds, 14...Reinforcing bars, 15...Hoop bars, 16...Reinforced bar baskets, 17...Grooves, 18...Sheet-like materials, 19...Reinforcing ropes, 20...Shielding membranes, 21... Tension anchor, 22...Water permeable plastic pipe, 23...Seed sheet, 24...
Sand, 25... Law frame members, 26... Discarded formwork.

Claims (1)

【特許請求の範囲】[Claims] 1 縦梁複数本を、間隔をおいて、法面上に上下
方向に構築し、次いで、隣接する縦梁相互間に、
法面との間に縦梁の高さと略等しい隔たりをもつ
て張設された、透水性と可撓性のあるシート状物
並びに法面並びに両側の縦梁で囲まれた空間に、
流動化された土を注入・充填することを特徴とし
た植生基盤形成方法。
1. Construct multiple vertical beams vertically on the slope at intervals, then between adjacent vertical beams,
A water-permeable and flexible sheet-like material is stretched between the slope and the vertical beam at a distance approximately equal to the height of the vertical beam, and in the space surrounded by the slope and the vertical beams on both sides,
A vegetation base formation method characterized by pouring and filling fluidized soil.
JP2559384A 1984-02-14 1984-02-14 Formation of base for greens-planting work Granted JPS60168820A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
JP2559384A JPS60168820A (en) 1984-02-14 1984-02-14 Formation of base for greens-planting work

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
JP2559384A JPS60168820A (en) 1984-02-14 1984-02-14 Formation of base for greens-planting work

Publications (2)

Publication Number Publication Date
JPS60168820A JPS60168820A (en) 1985-09-02
JPH0146652B2 true JPH0146652B2 (en) 1989-10-09

Family

ID=12170201

Family Applications (1)

Application Number Title Priority Date Filing Date
JP2559384A Granted JPS60168820A (en) 1984-02-14 1984-02-14 Formation of base for greens-planting work

Country Status (1)

Country Link
JP (1) JPS60168820A (en)

Also Published As

Publication number Publication date
JPS60168820A (en) 1985-09-02

Similar Documents

Publication Publication Date Title
JP3714885B2 (en) Protection structures for slopes, walls, shores, etc.
SK50582008A3 (en) Vegetation roof, especially inclined and method of her production
JP2002363990A (en) Slope seeding and planting method
JPS61183521A (en) Method of stabilizing vegetation foundation on face of slope
JP3431783B2 (en) Protection structure for slopes and walls
JPH10292380A (en) Slope greening method
JPH0146652B2 (en)
JP4220613B2 (en) Protective greening structure on slopes, walls, shores
JP4024064B2 (en) Revetment structure and revetment method
KR100994740B1 (en) Vegetation net pad constructing on inclined plane or waterside and the method thereof
JP3096424B2 (en) Vegetation infrastructure construction method
JPH10183636A (en) Greening method for bulkhead slope
JPS58189425A (en) Soil board
JP2588097B2 (en) Artificial turf structure and construction method using it
JPH0250255B2 (en)
JPS6351527A (en) Slope stabilization work
JPS60188533A (en) Formation of base for green-planting work
JPS61274017A (en) Stabilization work for vegetation base
JP3807801B2 (en) Slope greening method
JPH0757955B2 (en) Revegetation method on embankment with reinforced structure
CN118087566A (en) Highway side slope reinforcing structure with good anti-scouring effect and reinforcing method
KR20050030428A (en) The net for slope protection, and it's construction method