JPH01131796A - Cut off method of shield tail section in cast-in-place concrete lining construction method - Google Patents

Cut off method of shield tail section in cast-in-place concrete lining construction method

Info

Publication number
JPH01131796A
JPH01131796A JP62288328A JP28832887A JPH01131796A JP H01131796 A JPH01131796 A JP H01131796A JP 62288328 A JP62288328 A JP 62288328A JP 28832887 A JP28832887 A JP 28832887A JP H01131796 A JPH01131796 A JP H01131796A
Authority
JP
Japan
Prior art keywords
concrete
ring
stop ring
water stop
filled
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
JP62288328A
Other languages
Japanese (ja)
Inventor
Hiramasa Aokage
平昌 青景
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Fujita Corp
Original Assignee
Fujita Corp
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Fujita Corp filed Critical Fujita Corp
Priority to JP62288328A priority Critical patent/JPH01131796A/en
Publication of JPH01131796A publication Critical patent/JPH01131796A/en
Pending legal-status Critical Current

Links

Landscapes

  • Lining And Supports For Tunnels (AREA)

Abstract

PURPOSE: To prevent water from leaking by arranging a hollow hard water cut-off ring on the inner circumferential part of a tail plate, and after hardening of concrete pressure-filled in an annular space, pressing-in pressure fluid in the hollow part of the water cut-off ring to expand it. CONSTITUTION: A hollow hard ring 12 formed out of rubber or the like is fitted to the inner circumferential face in the vicinity of the rear end of a tail plate 11 so as to be flush with the face, and the hollow part 12a of the ring 12 is connected to a pressure pipe 13. Next in an excavated tunnel hole A, reinforcements of a concrete part and an annular inner form 16 made of steel are assembled, concrete 17 is filled in between the frame 16, the plate 11, and the front face of an existing concrete, and the concrete 17 is pressurized by a concrete press jack 18. After hardening the concrete 17, pressure fluid is fed to the hollow part 12a, and the ring 12 is expanded to be pressure fitted to the concrete 17. Consequently, water can be surely prevented from leaking.

Description

【発明の詳細な説明】 (産業上の利用分野) 本発明は場所打ちコンクリートライニング工法における
シールドテール部の止水方法に係るものである。
DETAILED DESCRIPTION OF THE INVENTION (Industrial Application Field) The present invention relates to a method for water-stopping a shield tail portion in a cast-in-place concrete lining method.

(従来の技術) 第4図乃至第9図は従来の場所打ちコンクリートライニ
ング工法の工程を示し、シールド掘削機によって掘進さ
れたトンネル穴(A)内に覆工コンクリート部の鉄筋(
1)を配筋するとともに、鋼製の内型枠(2)を組み立
て、同内型枠(2)にコンクリート供給管(3)を取付
けたのち、(第4図参照)同供給管(3)のバルブ(4
)を開いて、シールドテールプレート(5)及び内型枠
(2)並に既設の覆工コンクリートの前面(6)の間に
形成された環状空間にコンクリート(7)を充填し、(
第5図参照)次いで前記コンクリート供給管(3)のバ
ルブ(4)を閉じ、シールド掘削機に装架されたコンク
リートプレスジヤツキ(8)を伸長して、同ジヤツキ先
端のルスリング板(9)を前記環状空間内に挿入し、打
設コンクリート(7)を加圧すると同時に、シールド掘
削機に装架された推進ジヤツキ(図示せず)によって、
前記内型枠(2)に反力をとってシールドテールプレー
ト(5)を前進させ(第6図参照)次いで前記コンクリ
ート(7)が硬化するとコンクリートプレスジヤツキ(
8)を切羽側に後退させ、プレスリング板(9)を前記
環状空間より引出し、コンクリート供給管(3)及びパ
ルプ(4)を撤去し、(第7図参照)かくして構築され
たコンクリート覆工部(6)の前面に、次位のコンクリ
ート覆工部の鉄筋(1)を配筋するとともに内型枠(2
)を組立て、(第8図参照)しかるのち内型枠(2)に
パルプ(4)を具えたコンクリート供給管(3)を取付
けるとともに、コンクリートプレスジヤツキ(8)を伸
長して先端のプレスリング板(9)を前記内型枠(2)
とシールドテールプレート(5)との間の環状空間に挿
入し、(第9図参照ン以下前記の工程を反覆して場所打
ちコンクリートライニングを有するトンネルを構築する
ものである。
(Prior Art) Figures 4 to 9 show the steps of the conventional cast-in-place concrete lining method, in which reinforcing bars of the concrete lining (
1), assemble the steel inner formwork (2), and attach the concrete supply pipe (3) to the inner formwork (2) (see Figure 4). ) valve (4
) is opened, and the annular space formed between the shield tail plate (5), the inner formwork (2), and the front surface (6) of the existing lining concrete is filled with concrete (7).
(See Figure 5) Next, close the valve (4) of the concrete supply pipe (3), extend the concrete press jack (8) mounted on the shield excavator, and remove the rusling plate (9) at the tip of the jack. is inserted into the annular space to pressurize the poured concrete (7), and at the same time, a propulsion jack (not shown) mounted on the shield excavator,
The shield tail plate (5) is advanced by taking the reaction force against the inner formwork (2) (see Figure 6). Then, when the concrete (7) hardens, the concrete press jack (
8) to the face side, pull out the press ring plate (9) from the annular space, remove the concrete supply pipe (3) and pulp (4) (see Figure 7), and remove the concrete lining thus constructed. In front of section (6), the reinforcing bars (1) for the next concrete lining section are arranged, and the inner formwork (2
) (see Figure 8), then attach the concrete supply pipe (3) with pulp (4) to the inner formwork (2), and extend the concrete press jack (8) to press the tip. The ring plate (9) is attached to the inner formwork (2).
and the shield tail plate (5) (see FIG. 9) and repeat the above steps to construct a tunnel with a cast-in-place concrete lining.

(発明が解決しようとする問題点) 前記場所打ちコンクリートライニング工法は他山と内型
枠との間にコンクリートを加圧充填することによって、
テールボイドを発生するこ1となく一次覆工を構築する
工法であるが、地下水圧が作用する場合には、シールド
掘削機のテールプレートと打設覆工コンクリートとの間
隙からの漏水が生起する。
(Problems to be Solved by the Invention) The cast-in-place concrete lining construction method involves filling concrete under pressure between the pile and the inner formwork.
This construction method constructs the primary lining without generating tail voids, but when groundwater pressure acts, water leaks from the gap between the tail plate of the shield excavator and the poured lining concrete.

この際、従来のように、漏水防止を前記テールプレート
と打設コンクリートとの付着強度のみに頼ることは、シ
ールド掘削機の動揺を考えると不十分である。
At this time, relying only on the adhesion strength between the tail plate and the poured concrete to prevent water leakage, as in the past, is insufficient in view of the shaking of the shield excavator.

(問題点を解決するための手段) 本発明はこのような問題点を解決するために提案された
ものであって、シールド掘削機によって掘進されたトン
ネル穴内に組立てた内型枠、及びテールプレート並に既
設の覆工コンクリートの前面の間に形成された環状空間
内にコンクリートを加圧充填するとともに、前記内型枠
に反力をとってシールド掘削機に装架された推進ジヤツ
キによって同堀削機を推進させる場所打ちコンクリート
ライニング工法において、前記テールプレートの内周部
に中空硬質止水リングを配設し、前記環状空間に加圧充
填されたコンクリートが硬化したのち、前記止水リング
の中空部に加圧流体を圧入して同止水リングを膨張させ
、前記コンクリートに圧着することを特徴とする場所打
ちコンクリートライニング工法におけるシールドテール
部の止水方法に係るものである。
(Means for Solving the Problems) The present invention has been proposed to solve these problems, and includes an inner formwork and a tail plate assembled in a tunnel hole excavated by a shield excavator. At the same time, concrete is pressurized and filled into the annular space formed between the front surfaces of the existing concrete lining, and a propulsion jack mounted on a shield excavator takes the reaction force from the inner formwork to excavate the same excavation. In the cast-in-place concrete lining construction method in which a cutting machine is propelled, a hollow hard water stop ring is arranged on the inner periphery of the tail plate, and after the concrete filled under pressure in the annular space has hardened, the water stop ring is The present invention relates to a method for stopping water at a shield tail portion in a cast-in-place concrete lining construction method, which is characterized by injecting pressurized fluid into a hollow portion to expand the water stop ring and press it against the concrete.

(作  用) 本発明は前記したように、シールド掘削機のテールプレ
ートの内周部に中空硬質止水リングが配設されているの
で、同テールプレートと内型枠及び既設の覆工コンクリ
ート部前面の環状空間内に加圧充填されたコンクリート
が硬化したのち、前記止水リングの中空部に圧力流体を
圧入して、同止水リングを膨張させ、前記覆工コンクリ
ート部に圧着することによって、シールドテールプレー
トと打設コンクリートとの間の漏水を防止するものであ
る。
(Function) As described above, in the present invention, a hollow hard water stop ring is provided on the inner circumference of the tail plate of a shield excavator, so that the tail plate, the inner formwork, and the existing concrete lining are connected to each other. After the concrete pressurized and filled into the annular space at the front hardens, pressurized fluid is injected into the hollow part of the water stop ring to expand the water stop ring and press it to the lining concrete part. , to prevent water leakage between the shield tail plate and the poured concrete.

次いで次位の覆工コンクリートを打設する際、前記止水
リングの中空部内を減圧して同止水リングを元の状態に
戻し、コンクリートの前記環状空間内における加圧充填
時に、同コンクリートの流動を阻害しないようにするも
のである。
Next, when pouring the next lining concrete, the pressure inside the hollow part of the water stop ring is reduced to return the water stop ring to its original state, and when the concrete is pressurized and filled in the annular space, the concrete is This is to prevent flow from being obstructed.

(実施例) 以下本発明を図示の実施例について説明する。(Example) The present invention will be described below with reference to the illustrated embodiments.

(11)はシールド掘削機のテールプレートで、その後
端近傍の内周面にゴム等より構成された中空硬質止水リ
ング(12)が、同リング(12)の内周面が前記テー
ルプレート(11)の内周面と同一面状に位置するよう
に取付けられ、前記リング(12)の中空部(12a)
には加圧管(13)の一端部が接続され、同加圧管(1
3)の他端部はシールド掘削機内部に設置された圧力流
体供給源(図示せず)に接続されている。
(11) is a tail plate of a shield excavator, in which a hollow hard water stop ring (12) made of rubber or the like is provided on the inner circumferential surface near the rear end, and the inner circumferential surface of the ring (12) is attached to the tail plate ( The hollow part (12a) of the ring (12) is mounted so as to be flush with the inner peripheral surface of the ring (11)
One end of the pressure pipe (13) is connected to the pressure pipe (13).
3) The other end is connected to a pressure fluid supply source (not shown) installed inside the shield excavator.

なお図示の実施例では、前記止水リング(12)はテー
ルプレート(11)の内周面に設けた環状四部(Ila
)に嵌合され、押えリング板(I4)と固定ポル) (
15)とによって固定されている。
In the illustrated embodiment, the water stop ring (12) has four annular parts (Ila
), and the presser ring plate (I4) and fixed pole) (
15).

図示の実施例は前記したように構成されているので、シ
ールド掘削機によって掘削されたトンネル穴(A)内に
覆工コンクリート部の配筋を行なうとともに環状の鋼製
内型枠(16)を組立て、同内型枠(16)及びテール
プレート(11)並に既設の覆工コンクリート部前面の
間に形成された環状空間にコンクリ−) (17)を充
填し、シールド掘削機に装架されたコンクリートプレス
ジヤツキ(18)の先端のプレスリング板(19)を前
記環状空間内に挿入して打設コンクリート(17)を加
圧充填し、同打設コンクリート(17)が硬化するまで
は前記プレスリング板(19)で止水性を確保する。
Since the illustrated embodiment is constructed as described above, the concrete lining is reinforced in the tunnel hole (A) excavated by the shield excavator, and the annular steel inner formwork (16) is installed. After assembly, the annular space formed between the inner formwork (16), the tail plate (11), and the front of the existing lining concrete section was filled with concrete (17), and mounted on a shield excavator. The press ring plate (19) at the tip of the concrete press jack (18) is inserted into the annular space, and poured concrete (17) is pressurized and filled until the poured concrete (17) hardens. The press ring plate (19) ensures watertightness.

なお前記コンクリート(17)の加圧、充填時は、前記
止水リング(12)の中空部(12a)内が減圧され、
同止水リング(12)がテールプレート(11)の内側
に突出することのないようにして、打設コンクリ−) 
(17)の流動性を阻害しないようにする。
Note that when pressurizing and filling the concrete (17), the pressure inside the hollow part (12a) of the water stop ring (12) is reduced;
The water stop ring (12) should not protrude inside the tail plate (11) when pouring concrete.
(17) Avoid impeding the fluidity of the product.

而して前記コンクリート(17)が硬化したのちは、前
記止水リング(12)の中空部(12a)に加圧管(1
3)を介して圧力エヤ、または圧力水等の圧力流体を供
給し、前記止水リング(12)を膨張させることによっ
て打設コンクリ−) (17)に圧着して止水し、(第
3図参照)地下水圧Pが作用する場合においてもテール
プレート(11)と打設コンクリート(17)との間か
らの漏水を防止するものである。
After the concrete (17) has hardened, the pressure pipe (1) is inserted into the hollow part (12a) of the water stop ring (12).
3) by supplying pressure fluid such as pressurized air or pressurized water to inflate the water stop ring (12) and press it against the poured concrete (17) to stop water. (See figure) This prevents water from leaking between the tail plate (11) and the poured concrete (17) even when groundwater pressure P is applied.

(発明の効果) 本発明によれば前記したように、シールド掘削機のテー
ルプレート内周面に中空硬質止水リングと配設し、同テ
ールプレートと内型枠及び既設の覆工コンクリート部前
面との間に形成された環状空間に加圧充填されたコンク
リートの硬化後、前記止水リングの中空部に加圧流体を
圧入することによって同止水リングを膨張させ、同止水
リングを前記コンクリートに圧着せしめ、前記テールプ
レートとコンクリートとの間を確実に止水し、地下水圧
が作用する場合においても前記テールプレート及び覆工
コンクリート間からの漏水を確実に防止しうるものであ
る。
(Effects of the Invention) According to the present invention, as described above, a hollow hard water stop ring is disposed on the inner peripheral surface of the tail plate of a shield excavator, and the tail plate, the inner formwork, and the front surface of the existing lining concrete part are provided. After the concrete is pressurized and filled into the annular space formed between the water stop ring and the water stop ring, the water stop ring is expanded by injecting pressurized fluid into the hollow part of the water stop ring. It is crimped onto concrete to reliably stop water between the tail plate and the concrete, and to reliably prevent water from leaking between the tail plate and the lining concrete even when underground water pressure is applied.

また前記止水リングの中空部に対する加圧流体による加
圧を解除し、同止水リングを元の状態に戻すことによっ
て、前記コンクリートの加圧充填時における流動を阻害
することなく、同コンクリートの打設が円滑に遂行され
るようにしうるちのである。
In addition, by releasing the pressure applied by the pressurized fluid to the hollow part of the water stop ring and returning the water stop ring to its original state, the flow of the concrete during pressurized filling is not inhibited, and the concrete is This is to ensure that the pouring process is carried out smoothly.

【図面の簡単な説明】[Brief explanation of the drawing]

第1図は本発明に係る場所打ちコンクリートライニング
工法におけるシールドテール部の止水方法の一実施例の
実施状況を示す縦断側面図、第2図及び第3図はその部
分拡大図で、第2図は中空硬貫止水リングの加圧前の状
恋を示し、第3図は同止水リングの加圧中の状態を示す
。第4図乃至第9図は従来の場所打ちコンクリートライ
ニング工法の工程を示す縦断側面図である。 (11)・・・テールプレート (12)・・・中空硬質止水リング (13)・・・加
圧管(16)・・・内型枠     (17)・・・コ
ンクリート代理人 弁理士   岡  本  重  文
外2名 第1図 ρ 第2図
FIG. 1 is a longitudinal side view showing an implementation status of an embodiment of the method for stopping water in the shield tail part in the cast-in-place concrete lining method according to the present invention, FIGS. 2 and 3 are partially enlarged views thereof, and FIG. The figure shows the state of the hollow hard penetrating water stop ring before pressurization, and FIG. 3 shows the state of the same water stop ring during pressurization. 4 to 9 are vertical side views showing the steps of the conventional cast-in-place concrete lining method. (11)...Tail plate (12)...Hollow hard water stop ring (13)...Pressure pipe (16)...Inner formwork (17)...Concrete agent Patent attorney Shige Okamoto Two people outside the text Figure 1 ρ Figure 2

Claims (1)

【特許請求の範囲】[Claims] シールド掘削機によって掘進されたトンネル穴内に組立
てた内型枠、及びテールプレート並に既設の覆工コンク
リートの前面の間に形成された環状空間内にコンクリー
トを加圧充填するとともに、前記内型枠に反力をとって
シールド掘削機に装架された推進ジャッキによつて同堀
削機を推進させる場所打ちコンクリートライニング工法
において、前記テールプレートの内周部に中空硬質止水
リングを配設し、前記環状空間に加圧充填されたコンク
リートが硬化したのち、前記止水リングの中空部に加圧
流体を圧入して同止水リングを膨張させ、前記コンクリ
ートに圧着することを特徴とする場所打ちコンクリート
ライニング工法におけるシールドテール部の止水方法。
Concrete is pressurized and filled into the annular space formed between the inner formwork assembled in the tunnel hole dug by the shield excavator, the tail plate, and the front surface of the existing lining concrete, and the inner formwork is filled with concrete. In the cast-in-place concrete lining construction method, in which the shield excavator is propelled by a propulsion jack mounted on the shield excavator, a hollow hard water stop ring is arranged on the inner periphery of the tail plate. , a place characterized in that after the concrete filled under pressure in the annular space has hardened, pressurized fluid is injected into the hollow part of the water stop ring to expand the water stop ring and press it to the concrete. Water stoppage method for the shield tail part in poured concrete lining construction method.
JP62288328A 1987-11-17 1987-11-17 Cut off method of shield tail section in cast-in-place concrete lining construction method Pending JPH01131796A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
JP62288328A JPH01131796A (en) 1987-11-17 1987-11-17 Cut off method of shield tail section in cast-in-place concrete lining construction method

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
JP62288328A JPH01131796A (en) 1987-11-17 1987-11-17 Cut off method of shield tail section in cast-in-place concrete lining construction method

Publications (1)

Publication Number Publication Date
JPH01131796A true JPH01131796A (en) 1989-05-24

Family

ID=17728760

Family Applications (1)

Application Number Title Priority Date Filing Date
JP62288328A Pending JPH01131796A (en) 1987-11-17 1987-11-17 Cut off method of shield tail section in cast-in-place concrete lining construction method

Country Status (1)

Country Link
JP (1) JPH01131796A (en)

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPH03208999A (en) * 1990-01-12 1991-09-12 Kajima Corp In-situ concrete lining for shield tunnel
JP2007132004A (en) * 2005-11-08 2007-05-31 Mitsubishi Heavy Ind Ltd Tunnel excavator

Citations (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPS63147097A (en) * 1986-12-09 1988-06-20 戸田建設株式会社 Method of concrete lining construction at site of shielding tunnel

Patent Citations (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPS63147097A (en) * 1986-12-09 1988-06-20 戸田建設株式会社 Method of concrete lining construction at site of shielding tunnel

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPH03208999A (en) * 1990-01-12 1991-09-12 Kajima Corp In-situ concrete lining for shield tunnel
JP2007132004A (en) * 2005-11-08 2007-05-31 Mitsubishi Heavy Ind Ltd Tunnel excavator

Similar Documents

Publication Publication Date Title
JP3890528B2 (en) Tunnel construction method
JPH01131796A (en) Cut off method of shield tail section in cast-in-place concrete lining construction method
JP3184456B2 (en) How to receive shield machine into the arrival shaft
JP3769717B2 (en) Tunnel lining method
JP2636139B2 (en) Wellhead sealing device
JP3177908B2 (en) Starting method of shield excavator
JPH08338196A (en) Filling method for backfill material and members for preventing ground collapse and water sealing
JPH02132295A (en) Constructing method for tunnel lining work
JP2976830B2 (en) Joining method of shield excavator and reaching shaft
JP2000257392A (en) Water stopping form and method for constructing tunnel using the same
JP2554885B2 (en) Shield method and shield machine
JPH01271600A (en) Concrete placing for cast-in-place concrete lining construction
JP2527912B2 (en) Shield tunnel lining method
JP2676691B2 (en) Construction method of shield and lining using shield
JPH05118194A (en) Sealing method of lining in cast-in-place lining shield method
JP2634883B2 (en) Construction method of tunnel lining
JPH01174800A (en) Method for constructing concrete covering shield body underground and segment therefor
JPH0686799B2 (en) Construction method for cast-in-place lining shield and pressurizing device therefor
JPH01268997A (en) Axial reinforced joint and reinforced joint method in cast-in-place concrete lining method
JPH01312199A (en) Construction of tunnel linining work
JPS63147097A (en) Method of concrete lining construction at site of shielding tunnel
JPH04277298A (en) Primary segment for shield tunnel and working method thereof
JPH10110588A (en) Ring-shaped cutting edge used in cut-off in constructing underground cylinder
JPH01203598A (en) Construction work of tunnel
JPH0220800A (en) Shield drilling machine