JP7502886B2 - Building Construction Method - Google Patents

Building Construction Method Download PDF

Info

Publication number
JP7502886B2
JP7502886B2 JP2020068945A JP2020068945A JP7502886B2 JP 7502886 B2 JP7502886 B2 JP 7502886B2 JP 2020068945 A JP2020068945 A JP 2020068945A JP 2020068945 A JP2020068945 A JP 2020068945A JP 7502886 B2 JP7502886 B2 JP 7502886B2
Authority
JP
Japan
Prior art keywords
construction
section
building
floor
constructing
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Active
Application number
JP2020068945A
Other languages
Japanese (ja)
Other versions
JP2021165479A (en
Inventor
茂臣 深沢
智行 宮▲崎▼
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Takenaka Corp
Original Assignee
Takenaka Corp
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Takenaka Corp filed Critical Takenaka Corp
Priority to JP2020068945A priority Critical patent/JP7502886B2/en
Publication of JP2021165479A publication Critical patent/JP2021165479A/en
Application granted granted Critical
Publication of JP7502886B2 publication Critical patent/JP7502886B2/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Images

Landscapes

  • Conveying And Assembling Of Building Elements In Situ (AREA)

Description

本発明は、建物の施工方法に関する。 The present invention relates to a building construction method.

従来、建物を複数の工区に分割して施工するための技術の一つとして、2つの工区に2つの躯体のフレーム部を先行して施工し、これら2つのフレーム部同士の間に別途設けたレール体を介して他の躯体の屋根部を掛け渡し、その後屋根部の下で他の躯体の残り部分を施工する技術が提案されている(例えば、特許文献1参照)。 One technique proposed for dividing a building into multiple work sections for construction is to first construct the frame parts of two structures in two work sections, then suspend the roof part of the other structure between these two frame parts via a rail body separately installed, and then construct the remaining part of the other structure underneath the roof part (see, for example, Patent Document 1).

特開平09-273311号公報Japanese Patent Application Laid-Open No. 09-273311

しかしながら、上記従来の技術においては、上述したように、他の躯体の屋根部を設置する際にレール体を別途設ける必要があるので、建物が比較的大きい場合には、レール体の設置数が増えることでレール体の製造コスト及び設置作業の手間が増大してしまうおそれがあることから、施工性の観点からは改善の余地があった。 However, as mentioned above, in the above conventional technology, a rail body needs to be installed separately when installing the roof part of another structure. Therefore, in the case of a relatively large building, there is a risk that the manufacturing costs and the labor required for installation will increase as the number of rail bodies installed increases, and there is therefore room for improvement in terms of workability.

本発明は、上記に鑑みてなされたものであって、建物の施工性を高めることが可能となる、建物の施工方法を提供することを目的とする。 The present invention has been made in consideration of the above, and aims to provide a building construction method that can improve the ease of construction of buildings.

上述した課題を解決し、目的を達成するために、請求項1に記載の建物の施工方法は、建物を複数の工区に分割して施工するための施工方法であって、第1の工区において、前記建物を構成する第1の躯体を施工する第1施工工程と、前記第1施工工程の後又は途中に、前記第1の工区に隣接する第2の工区において、前記建物を構成する第2の躯体における少なくとも屋根部を含む一部分の水平力を前記第1の躯体に直接支持させながら、当該一部分を施工する第2先行施工工程と、前記第2先行施工工程の後に、前記第2の躯体における他の一部分の水平力を前記第1の躯体に直接支持させながら、当該他の一部分を施工する第2後行施工工程と、を含み、前記第2先行施工工程においては、前記第2の躯体の前記一部分に含まれる梁部を当該一部分に含まれる柱部に対して仮固定し、且つ前記第1の躯体に含まれる梁部又は柱部に対して仮固定し、前記第2後行施工工程においては、前記第2の躯体の前記一部分に含まれる梁部を当該一部分に含まれる柱部に対して本固定し、且つ前記第1の躯体に含まれる梁部又は柱部に対して本固定する。 In order to solve the above-mentioned problems and achieve the object, the construction method of a building described in claim 1 is a construction method for dividing a building into a plurality of work sections and constructing the divided building, the construction method comprising: a first construction step of constructing a first structure constituting the building in a first work section; a second advance construction step of constructing a second structure constituting the building in a second work section adjacent to the first work section after or during the first construction step, while directly supporting a horizontal force of at least a roof portion of the second structure constituting the building on the first structure; and a second advance construction step of constructing the second structure constituting the building in a second work section adjacent to the first work section after the second advance construction step. and a second subsequent construction process in which the horizontal force of another part of the first structure is directly supported by the first structure while the other part is constructed , wherein in the second prior construction process, a beam portion included in the part of the second structure is temporarily fixed to a column portion included in the part, and is also temporarily fixed to a beam portion or a column portion included in the first structure, and in the second subsequent construction process, a beam portion included in the part of the second structure is permanently fixed to a column portion included in the part, and is also permanently fixed to a beam portion or a column portion included in the first structure.

請求項2に記載の建物の施工方法は、建物を複数の工区に分割して施工するための施工方法であって、第1の工区において、前記建物を構成する第1の躯体を施工する第1施工工程と、前記第1施工工程の後又は途中に、前記第1の工区に隣接する第2の工区において、前記建物を構成する第2の躯体における少なくとも屋根部を含む一部分の水平力を前記第1の躯体に直接支持させながら、当該一部分を施工する第2先行施工工程と、前記第2先行施工工程の後に、前記第2の躯体における他の一部分の水平力を前記第1の躯体に直接支持させながら、当該他の一部分を施工する第2後行施工工程と、を含み、前記複数の工区のうち、車両が前記建物内を出入りするための通行設備と隣接する工区を最先に施工する。 The construction method of a building described in claim 2 is a construction method for dividing a building into a plurality of work sections and constructing the same, comprising: a first construction step of constructing a first structure constituting the building in a first work section; a second advance construction step of constructing a portion of the second structure constituting the building, including at least a roof portion, in a second work section adjacent to the first work section after or during the first construction step, while having the first structure directly support the horizontal force of the portion; and a second following construction step of constructing another portion of the second structure while having the first structure directly support the horizontal force of the other portion, wherein of the plurality of work sections, a work section adjacent to a passage facility for vehicles to enter and exit the building is constructed first.

請求項3に記載の建物の施工方法は、請求項1又は2に記載の建物の施工方法において、前記第2先行施工工程時において、前記第1の躯体は、当該第1の躯体の水平力及び前記第2の躯体の水平力を支持可能に構成されていると共に、当該第1の躯体の鉛直力を支持可能に構成されており、前記第2の躯体における前記一部分は、当該一部分の水平力を支持不能に構成されていると共に、当該一部分の鉛直力を支持可能に構成されている。
請求項4に記載の建物の施工方法は、請求項1から3のいずれか一項に記載の建物の施工方法において、前記第2先行施工工程の前に、前記第1の躯体を補強するための補強材を当該第1の躯体に設ける補強工程を含む。
The building construction method described in claim 3 is the building construction method described in claim 1 or 2, wherein, during the second preliminary construction step, the first structure is configured to be able to support the horizontal force of the first structure and the horizontal force of the second structure, and is configured to be able to support the vertical force of the first structure, and the portion of the second structure is configured to be unable to support the horizontal force of the portion, and is configured to be able to support the vertical force of the portion.
The building construction method described in claim 4 is a building construction method described in any one of claims 1 to 3, which includes a reinforcing step of providing a reinforcing material for reinforcing the first structure to the first structure prior to the second advance construction step.

請求項1に記載の建物の施工方法によれば、第1の工区において、第1の躯体を施工する第1施工工程と、第1施工工程の後又は途中に、第1の工区に隣接する第2の工区において、第2の躯体における少なくとも屋根部を含む一部分の水平力を第1の躯体に直接支持させながら、当該一部分を施工する第2先行施工工程と、第2先行施工工程の後に、第2の躯体における他の一部分の水平力を第1の躯体に直接支持させながら、当該他の一部分を施工する第2後行施工工程と、を含むので、第1の躯体を施工した後に第2の躯体を施工する際に、第2の躯体の水平力を一方の躯体に直接支持でき、仮設部材を設ける必要がないことから、建物の施工性を高めることができる。また、第2の躯体における屋根部を含む一部分を先行施工することで、全天候において第2の躯体における他の一部分を施工でき、建物の施工性を一層高めることができる。 According to the building construction method described in claim 1, the method includes a first construction step of constructing a first structure in a first construction area, a second advance construction step of constructing at least a portion of the second structure, including the roof, in a second construction area adjacent to the first construction area after or during the first construction step, while the horizontal force of the portion is directly supported by the first structure, and a second follow-up construction step of constructing another portion of the second structure while the horizontal force of the other portion is directly supported by the first structure after the second advance construction step. Therefore, when constructing the second structure after constructing the first structure, the horizontal force of the second structure can be directly supported by one of the structures, and there is no need to provide temporary members, thereby improving the constructability of the building. In addition, by constructing a portion of the second structure, including the roof, in advance, the other portion of the second structure can be constructed in all weather conditions, further improving the constructability of the building.

請求項2に記載の建物の施工方法によれば、第1の工区において、第1の躯体を施工する第1施工工程と、第1施工工程の後又は途中に、第1の工区に隣接する第2の工区において、第2の躯体における少なくとも屋根部を含む一部分の水平力を第1の躯体に直接支持させながら、当該一部分を施工する第2先行施工工程と、第2先行施工工程の後に、第2の躯体における他の一部分の水平力を第1の躯体に直接支持させながら、当該他の一部分を施工する第2後行施工工程と、を含むので、第1の躯体を施工した後に第2の躯体を施工する際に、第2の躯体の水平力を一方の躯体に直接支持でき、仮設部材を設ける必要がないことから、建物の施工性を高めることができる。また、第2の躯体における屋根部を含む一部分を先行施工することで、全天候において第2の躯体における他の一部分を施工でき、建物の施工性を一層高めることができる。 According to the construction method of the building described in claim 2, the method includes a first construction step of constructing the first structure in the first construction area, a second preceding construction step of constructing at least a part of the second structure including the roof portion in the second construction area adjacent to the first construction area after or during the first construction step while the horizontal force of the part is directly supported by the first structure, and a second following construction step of constructing another part of the second structure while the horizontal force of the other part is directly supported by the first structure after the second preceding construction step, so that when the second structure is constructed after the first structure is constructed, the horizontal force of the second structure can be directly supported by one of the structures, and there is no need to provide temporary members, thereby improving the constructability of the building. In addition, by constructing a part of the second structure including the roof portion in advance, the other part of the second structure can be constructed in all weather conditions, which further improves the constructability of the building.

請求項3に記載の建物の施工方法によれば、第2先行施工工程時において、第1の躯体は、当該第1の躯体の水平力及び第2の躯体の水平力を支持可能に構成されていると共に、当該第1の躯体の鉛直力を支持可能に構成されており、第2の躯体における一部分は、当該一部分の水平力を支持不能に構成されていると共に、当該一部分の鉛直力を支持可能に構成されているので、第2の躯体の一部分を施工する際に、第1の躯体が第2の躯体の一部分の水平力を確実に支持でき、第2の躯体の一部分を安定して施工することができる。また、第2の躯体の一部分の強度を過大に設定することを回避でき、第2の躯体の一部分の製造性を維持できる。
請求項4に記載の建物の施工方法によれば、第2先行施工工程の前に、第1の躯体を補強するための補強材を当該第1の躯体に設ける補強工程を含むので、第1の躯体を補強することができ、第2の躯体を施工する際に第2の躯体を安定して支持できる。
According to the construction method of the building described in claim 3, during the second preceding construction step, the first skeleton is configured to be able to support the horizontal force of the first skeleton and the horizontal force of the second skeleton, and is configured to be able to support the vertical force of the first skeleton, and a portion of the second skeleton is configured to be unable to support the horizontal force of the portion, and is configured to be able to support the vertical force of the portion, so that when constructing the portion of the second skeleton, the first skeleton can reliably support the horizontal force of the portion of the second skeleton, and the portion of the second skeleton can be stably constructed. Also, it is possible to avoid setting the strength of the portion of the second skeleton to be excessive, and the manufacturability of the portion of the second skeleton can be maintained.
According to the building construction method described in claim 4, a reinforcement process is included in which reinforcing material is provided on the first structure prior to the second preliminary construction process, so that the first structure can be reinforced and the second structure can be stably supported when being constructed.

本発明の実施の形態に係る建物の概要を示す図であり、(a)は平面図、(b)は正面図である。1A and 1B are diagrams showing an overview of a building according to an embodiment of the present invention, in which FIG. 第1工区施工工程を示す図であり、(a)は平面図、(b)は正面図である。1A and 1B are diagrams showing the construction process of the first construction section, where (a) is a plan view and (b) is a front view. 第2工区施工工程を示す図であり、(a)は平面図、(b)は正面図である。13A and 13B are diagrams showing the construction process of the second construction section, where (a) is a plan view and (b) is a front view. 第2工区第4工区間施工工程を示す図であり、(a)は平面図、(b)は正面図である。A diagram showing the construction process of the fourth section of the second section, where (a) is a plan view and (b) is a front view. 第3工区第4工区間施工工程を示す図であり、(a)は平面図、(b)は正面図である。A diagram showing the construction process of the fourth section of the third section, where (a) is a plan view and (b) is a front view. 第4工区施工工程を示す図であり、(a)は平面図、(b)は正面図である。13A and 13B are diagrams showing the construction process of the fourth construction section, where (a) is a plan view and (b) is a front view.

以下に添付図面を参照して、この発明に係る建物の施工方法の実施の形態を詳細に説明する。まず、〔I〕実施の形態の基本的概念を説明した後、〔II〕実施の形態の具体的内容について説明し、最後に、〔III〕実施の形態に対する変形例について説明する。ただし、実施の形態によって本発明が限定されるものではない。 The following describes in detail an embodiment of the building construction method according to the present invention with reference to the attached drawings. First, [I] the basic concept of the embodiment is explained, then [II] the specific content of the embodiment is explained, and finally, [III] modified examples of the embodiment are explained. However, the present invention is not limited to the embodiment.

〔I〕実施の形態の基本的概念
最初に、実施の形態の基本的概念について説明する。実施の形態は、概略的に、建物を複数の工区に分割して施工するための施工方法に関する。
[I] Basic Concept of the Embodiment First, the basic concept of the embodiment will be described. The embodiment generally relates to a construction method for dividing a building into a plurality of work sections and constructing the divided sections.

ここで、「建物」の具体的な構造や種類は任意であり、例えば、物流施設、商業施設、工場施設、アパートやマンションの如き集合住宅、オフィスビル等の建物等を含む概念であるが、実施の形態では、物流施設として説明する。また、「工区」とは、建物が施工される現場の領域を区分けした領域を意味する。 The specific structure and type of the "building" is arbitrary, and the concept includes, for example, logistics facilities, commercial facilities, factory facilities, apartment complexes such as apartments and condominiums, office buildings, and other buildings, but in the embodiment, it will be described as a logistics facility. Also, the "construction area" refers to an area divided into sections of the site where the building is constructed.

〔II〕実施の形態の具体的内容
次に、実施の形態の具体的内容について説明する。
[II] Specific Contents of the Embodiment Next, specific contents of the embodiment will be described.

(構成)
最初に、実施の形態に係る施工方法が適用される建物の構成について説明する。図1は、本発明の実施の形態に係る建物の概要を示す図であり、(a)は平面図、(b)は正面図である。ここで、図1のX方向を建物の左右方向(-X方向を建物の左方向、+X方向を建物の右方向)、図2のY方向を建物の前後方向(+Y方向を建物の前方向、-Y方向を建物の後方向)、図1のZ方向を建物の上下方向(+Z方向を建物の上方向、-Z方向を建物の下方向)と称する。なお、図1から後述する図6においては、後述する床部22が施工されている階層21をハッチングで示し、後述する床部22が施工されていない階層21をハッチングで示さないものする。
(composition)
First, the structure of a building to which the construction method according to the embodiment is applied will be described. FIG. 1 is a diagram showing an outline of a building according to the embodiment of the present invention, in which (a) is a plan view and (b) is a front view. Here, the X direction in FIG. 1 is referred to as the left-right direction of the building (-X direction is the left direction of the building, and +X direction is the right direction of the building), the Y direction in FIG. 2 is referred to as the front-rear direction of the building (+Y direction is the front direction of the building, and -Y direction is the rear direction of the building), and the Z direction in FIG. 1 is referred to as the up-down direction of the building (+Z direction is the up direction of the building, and -Z direction is the down direction of the building). In FIG. 1 to FIG. 6 described later, the story 21 on which the floor section 22 described later is constructed is shown by hatching, and the story 21 on which the floor section 22 described later is not constructed is shown by not hatching.

建物1は、図1に示すように、所定の敷地内において、車両が建物1内を出入りするための通行設備10(例えば、ランプウェイ等)に隣接して設けられ、複数の躯体20及び補強材30を備えている。 As shown in FIG. 1, the building 1 is located within a specified site, adjacent to a passage facility 10 (e.g., a rampway, etc.) that allows vehicles to enter and exit the building 1, and is equipped with multiple frameworks 20 and reinforcing members 30.

ここで、実施の形態では、図1に示すように、敷地における建物1が施工される施工領域2は、通行設備10と隣接する第1工区2aと、第1工区2aよりも右側に位置する第2工区2bと、第2工区2bよりも右側に位置する第3工区2cと、及び第3工区2cよりも右側に位置する第4工区2dとに区分け(分割)されている。 In this embodiment, as shown in FIG. 1, the construction area 2 on the site where the building 1 is constructed is divided (segmented) into a first construction area 2a adjacent to the access facility 10, a second construction area 2b located to the right of the first construction area 2a, a third construction area 2c located to the right of the second construction area 2b, and a fourth construction area 2d located to the right of the third construction area 2c.

また、第1工区2a、第2工区2b、第3工区2c、及び第4工区2dの各々は、最も後側に位置するA工区3aと、A工区3aよりも前側に位置するB工区3bと、B工区3bよりも前側に位置するC工区3cと、C工区3cよりも前側に位置するD工区3dと、D工区3dよりも前側に位置するE工区3eとにさらに区分けされている。 In addition, each of the first work section 2a, the second work section 2b, the third work section 2c, and the fourth work section 2d is further divided into a work section A 3a located at the rearmost position, a work section B 3b located forward of the work section A 3a, a work section C 3c located forward of the work section B 3b, a work section D 3d located forward of the work section C 3c, and a work section E 3e located forward of the work section D 3d.

なお、以下では、必要に応じて、複数の躯体20のうち、第1工区2aの躯体20aを「第1躯体20a」と称し、第2工区2bの躯体20bを「第2躯体20b」と称し、第3工区2cの躯体20cを「第3躯体20c」と称し、第4工区2dの躯体20dを「第4躯体20d」と称する。 In the following, where necessary, of the multiple structures 20, the structure 20a in the first work area 2a will be referred to as the "first structure 20a", the structure 20b in the second work area 2b will be referred to as the "second structure 20b", the structure 20c in the third work area 2c will be referred to as the "third structure 20c", and the structure 20d in the fourth work area 2d will be referred to as the "fourth structure 20d".

(構成-躯体)
複数の躯体20の各々は、複数の階層21からなるものであり、床部22、屋根部23、柱部24、梁部25、及び壁部26をそれぞれ備えている。なお、以下では、必要に応じて、複数の階層21のうち、地上に位置する最下層の階層21aを「第1階層21a」と称し、第1階層21aより上側の階層21bを「第2階層21b」と称し、第2階層21bより上側の階層21cを「第3階層21c」と称し、第3階層21cより上側の階層21dを「第4階層21d」と称する。
(Structure - Structure)
Each of the multiple frameworks 20 is made up of multiple stories 21, and includes a floor section 22, a roof section 23, columns 24, beams 25, and walls 26. In the following, as necessary, the lowest story 21a located on the ground among the multiple stories 21 will be referred to as the "first story 21a", the story 21b above the first story 21a will be referred to as the "second story 21b", the story 21c above the second story 21b will be referred to as the "third story 21c", and the story 21d above the third story 21c will be referred to as the "fourth story 21d".

床部22は、建物1の階層21を区分けするための部材であり、例えば公知のコンクリート製の床材(一例として、フェローデッキを含むRC製の床材)等で構成されており、相互に間隔を隔てて上下方向に向けて複数並設されている。なお、以下では、必要に応じて、床部22のうち、第1階層21aの床部22aを「第1床部22a」と称し、第2階層21bの床部22bを「第2床部22b」と称し、第3階層21cの床部22cを「第3床部22c」と称し、第4階層21dの床部22dを「第4床部22d」と称する。 The floors 22 are members for dividing the stories 21 of the building 1, and are made of, for example, known concrete flooring materials (one example is a reinforced concrete flooring material including a ferrodeck), and are arranged in a row in the vertical direction at intervals from each other. In the following, as necessary, the floor 22a of the first story 21a will be referred to as the "first floor 22a", the floor 22b of the second story 21b will be referred to as the "second floor 22b", the floor 22c of the third story 21c will be referred to as the "third floor 22c", and the floor 22d of the fourth story 21d will be referred to as the "fourth floor 22d".

屋根部23は、建物1の最上方に位置する部材であり、例えば公知の鋼製(一例として、スチール製、ステンレス製)の屋根材等で構成されており、最上階(第4階層21d)の上端において複数並設されている。 The roof section 23 is a member located at the top of the building 1 and is made of, for example, a known steel roofing material (for example, steel or stainless steel), and multiple roof sections are arranged side by side at the top end of the top floor (fourth floor 21d).

柱部24は、床部22又は屋根部23を支持する部材であり、例えば公知のコンクリート製の柱材(一例として、RC製のPC柱材)等で構成されており、床部22同士の相互間又は屋根部23と床部22との相互間に複数設けられ、当該床部22、当該屋根部23、又は地表に対して固定具等によって固定されていると共に、当該床部22と柱部24との相互間の隙間にグラウト材を充填することにより固定されている。なお、以下では、必要に応じて、柱部24のうち、第1階層21aの柱部24aを「第1柱部24a」と称し、第2階層21bの柱部24bを「第2柱部24b」と称し、第3階層21cの柱部24cを「第3柱部24c」と称し、第4階層21dの柱部24dを「第4柱部24d」と称する。 The pillars 24 are members that support the floor 22 or roof 23, and are made of, for example, known concrete pillars (RC PC pillars, for example). A plurality of pillars 24 are provided between the floors 22 or between the roofs 23 and floors 22, and are fixed to the floors 22, the roofs 23, or the ground surface by fasteners, and are fixed by filling the gaps between the floors 22 and the pillars 24 with grout. In the following, as necessary, the pillars 24a of the first story 21a will be referred to as the "first pillar 24a", the pillars 24b of the second story 21b will be referred to as the "second pillar 24b", the pillars 24c of the third story 21c will be referred to as the "third pillar 24c", and the pillars 24d of the fourth story 21d will be referred to as the "fourth pillar 24d".

梁部25は、床部22又は屋根部23を支持する部材であり、例えば公知の鋼製の梁材等で構成されており、床部22の下面又は屋根部23の下面と当接するように複数設けられ、当該床部22又は当該屋根部23に対して固定具等によって固定されている。なお、以下では、必要に応じて、梁部25のうち、第1階層21aの梁部25aを「第1梁部25a」と称し、第2階層21bの梁部25bを「第2梁部25b」と称し、第3階層21cの梁部25cを「第3梁部25c」と称し、第4階層21dの梁部25dを「第4梁部25d」と称する。 The beams 25 are members that support the floor 22 or roof 23, and are made of, for example, known steel beams, etc., and are provided in multiple numbers so as to abut against the underside of the floor 22 or the underside of the roof 23, and are fixed to the floor 22 or roof 23 by fasteners or the like. In the following, as necessary, the beams 25a of the first story 21a will be referred to as the "first beam 25a", the beams 25b of the second story 21b will be referred to as the "second beam 25b", the beams 25c of the third story 21c will be referred to as the "third beam 25c", and the beams 25d of the fourth story 21d will be referred to as the "fourth beam 25d".

壁部26は、各階層21の内部空間を仕切るための壁であり、例えば公知の壁材等で構成されており、床部22同士の相互間に複数設けられ、床部22、屋根部23、柱部24、又は梁部25に対して固定具又は嵌合構造等によって固定されている。なお、以下では、必要に応じて、壁部26のうち、第1階層21aの壁部26aを「第1壁部26a」と称し、第2階層21bの壁部26bを「第2壁部26b」と称し、第3階層21cの壁部26cを「第3壁部26c」と称し、第4階層21dの壁部26dを「第4壁部26d」と称する。 The walls 26 are walls for dividing the internal space of each story 21, and are made of, for example, known wall materials, and are provided between the floors 22, and are fixed to the floors 22, the roofs 23, the columns 24, or the beams 25 by fasteners or fitting structures, etc. In the following, as necessary, the wall 26a of the first story 21a will be referred to as the "first wall 26a", the wall 26b of the second story 21b will be referred to as the "second wall 26b", the wall 26c of the third story 21c will be referred to as the "third wall 26c", and the wall 26d of the fourth story 21d will be referred to as the "fourth wall 26d".

(構成-補強材)
補強材30は、躯体20を補強するための部材である。この補強材30は、例えば公知の建物用補強材(一例として、建物用ブレース材)を用いて構成され、図1に示すように、複数の躯体20の少なくとも1つ以上に設けられている。具体的には、第2躯体20b、第3躯体20c、及び第4躯体20dの各々におけるB工区3b及びC工区3cの部分の隣接する階層21のうち、少なくとも1組以上の隣接する階層21の床部22同士の相互間にわたって配置され、当該床部22に対して固定具等によって接続されている。
(Structure - Reinforcement)
The reinforcing material 30 is a member for reinforcing the skeleton 20. The reinforcing material 30 is formed, for example, using a known building reinforcing material (one example is a building brace material), and is provided in at least one of the multiple skeletons 20 as shown in Fig. 1. Specifically, the reinforcing material 30 is disposed between the floor portions 22 of at least one pair of adjacent stories 21 among the adjacent stories 21 in the B work area 3b and the C work area 3c in each of the second skeleton 20b, the third skeleton 20c, and the fourth skeleton 20d, and is connected to the floor portions 22 by a fastener or the like.

(建物の施工方法)
次に、建物1の施工方法について説明する。図2は、第1工区施工工程を示す図であり、(a)は平面図、(b)は正面図である。図3は、第2工区施工工程を示す図であり、(a)は平面図、(b)は正面図である。図4は、第2工区第4工区間施工工程を示す図であり、(a)は平面図、(b)は正面図である。図5は、第3工区第4工区間施工工程を示す図であり、(a)は平面図、(b)は正面図である。図6は、第4工区施工工程を示す図であり、(a)は平面図、(b)は正面図である。
(Building construction method)
Next, the construction method of the building 1 will be described. Figure 2 is a diagram showing the construction process of the first work section, (a) being a plan view and (b) being a front view. Figure 3 is a diagram showing the construction process of the second work section, (a) being a plan view and (b) being a front view. Figure 4 is a diagram showing the construction process of the fourth work section of the second work section, (a) being a plan view and (b) being a front view. Figure 5 is a diagram showing the construction process of the fourth work section of the third work section, (a) being a plan view and (b) being a front view. Figure 6 is a diagram showing the construction process of the fourth work section, (a) being a plan view and (b) being a front view.

この建物1の施工方法は、建物1を複数の工区に分割して施工するための方法であり、実施の形態では、図2から図6に示すように、第1工区施工工程、第2工区施工工程、第2工区第4工区間施工工程、第3工区第4工区間施工工程、第4工区施工工程、及び仕上工程を含んでいる。 This construction method for building 1 is a method for dividing building 1 into multiple work sections and constructing it. In the embodiment, as shown in Figures 2 to 6, it includes a first work section construction process, a second work section construction process, a second work section fourth work section construction process, a third work section fourth work section construction process, a fourth work section construction process, and a finishing process.

(建物の施工方法-第1工区施工工程)
最初に、第1工区施工工程について説明する。第1工区施工工程は、通行設備10の設置後(あるいは、通行設備10の設置前又は設置の途中に)、第1工区2aにおいて第1躯体20aを施工する工程である。
(Building construction method - First section construction process)
First, the first construction section construction process will be described. The first construction section construction process is a process of constructing the first structure 20a in the first construction section 2a after the passage facility 10 is installed (or before or during the installation of the passage facility 10).

実施の形態では、図2に示すように、公知の施工手法(例えば、積層工法)及び図示しない建設重機(例えば、クレーン等)を用いて、第1躯体20aを第1階層21aから第4階層21dの順に施工する(すなわち、最下方の階層21から最上方の階層21に至るように順次施工する)。 In the embodiment, as shown in FIG. 2, the first structure 20a is constructed in the order of the first story 21a to the fourth story 21d (i.e., construction is performed sequentially from the lowest story 21 to the highest story 21) using a known construction method (e.g., a layered construction method) and heavy construction equipment (e.g., a crane, etc.) not shown.

(建物の施工方法-第1工区施工工程-第1階層について)
具体的には、第1躯体20aの第1階層21aの施工については、まず、第1躯体20aの第1床部22a用の型枠(例えば、フェローデッキ等を含む型枠)を地表に設置し、当該型枠にコンクリートを流し込んで打設した後、当該コンクリートを所定期間固化させることにより、第1床部22aを当該地表に設置する。そして、第1柱部24aを第1床部22aに対して本固定した後に、第1梁部25a及び第1壁部26aを第1床部22a又は第1柱部24aに対して本固定する。
(Building construction method - 1st section construction process - 1st floor)
Specifically, in the construction of the first story 21a of the first skeleton 20a, first, a formwork (e.g., a formwork including a fello deck, etc.) for the first floor 22a of the first skeleton 20a is installed on the ground surface, concrete is poured into the formwork, and the concrete is allowed to harden for a predetermined period of time to install the first floor 22a on the ground surface. Then, after the first column 24a is permanently fixed to the first floor 22a, the first beam 25a and the first wall 26a are permanently fixed to the first floor 22a or the first column 24a.

ここで、「本固定」とは、部材を固定対象から取り外れないように強固に固定することを意味し、例えば、ボルトを用いて本固定する場合には、ボルトのトルクが閾値以上となるように締め付けること等が該当する。一方、「仮固定」とは、部材を固定対象から容易に取り外すことができるものの、振動等の外力によっては固定対象から脱落しない程度に固定することを意味し、例えば、ボルトを用いて仮固定する場合には、ボルトのトルクが閾値未満となるように締め付けること等が該当する。 Here, "permanent fixation" means that a member is firmly fixed so that it cannot be removed from the object to be fixed; for example, in the case of permanent fixation using a bolt, this corresponds to tightening the bolt so that the torque of the bolt is equal to or greater than a threshold value. On the other hand, "temporary fixation" means that a member can be easily removed from the object to be fixed, but is fixed to such an extent that it will not fall off the object due to external forces such as vibration; for example, in the case of temporary fixation using a bolt, this corresponds to tightening the bolt torque so that it is less than a threshold value.

(建物の施工方法-第1工区施工工程-第2階層について)
また、第1躯体20aの第2階層21bの施工については、まず、第1躯体20aの第2床部22b用の型枠を第1柱部24a及び第1梁部25aの上部に設置し、当該型枠にコンクリートを流し込んで打設した後、当該コンクリートを所定期間固化させることにより、第2床部22bを第1柱部24a及び第1梁部25aに設置する。そして、第2柱部24bを第2床部22bに対して本固定した後に、第2梁部25b及び第2壁部26bを第2床部22b又は第2柱部24bに対して本固定する。
(Building construction method - 1st section construction process - 2nd floor)
Regarding the construction of the second story 21b of the first skeleton 20a, first, a form for the second floor 22b of the first skeleton 20a is placed on the top of the first column 24a and the first beam 25a, concrete is poured into the form, and the concrete is allowed to harden for a predetermined period of time to install the second floor 22b on the first column 24a and the first beam 25a. Then, after the second column 24b is permanently fixed to the second floor 22b, the second beam 25b and the second wall 26b are permanently fixed to the second floor 22b or the second column 24b.

(建物の施工方法-第1工区施工工程-第3階層について)
また、第1躯体20aの第3階層21cの施工については、上述した第1躯体20aの第2階層21bの施工と略同様に施工する。
(Building construction method - 1st section construction process - 3rd floor)
The construction of the third story 21c of the first structure 20a is carried out in substantially the same manner as the construction of the second story 21b of the first structure 20a described above.

(建物の施工方法-第1工区施工工程-第4階層について)
また、第1躯体20aの第4階層21dの施工については、上述した第1躯体20aの第2階層21bの施工と略同様に施工した後に、屋根部23を第4梁部25d又は第4柱部24dに対して本固定する。
(Building construction method - 1st section construction process - 4th floor)
In addition, the construction of the fourth story 21d of the first structure 20a is carried out in substantially the same manner as the construction of the second story 21b of the first structure 20a described above, and then the roof section 23 is finally fixed to the fourth beam section 25d or the fourth column section 24d.

なお、各階層21の壁部26の設置方法については任意であるが、実施の形態では、設置すべき数よりも少ない数だけ設置することにより、第2工区施工工程以降の工程の作業性を確保している。ただし、これに限らず、例えば、設置すべき数のすべてを設置してもよい(なお、他の工程(ただし、仕上工程を除く)の壁部26の設置方法についても略同様とする)。 The method of installing the walls 26 on each floor 21 is arbitrary, but in the embodiment, fewer walls than the number that should be installed are installed to ensure the workability of the second construction section and subsequent processes. However, this is not limited to this, and for example, all of the walls that should be installed may be installed (note that the method of installing the walls 26 in other processes (excluding the finishing process) is approximately the same).

このような第1工区施工工程により、最先に施工される工区が、端側に位置する第1工区2aであるので、中央側に位置する第2工区2b又は第3工区2cである場合に比べて、効率的な建物1の施工計画(例えば、部材の運搬計画、作業員の配置計画等)を立案しやすくなる。 With this first section construction process, the section to be constructed first is the first section 2a located at the end, which makes it easier to devise an efficient construction plan for the building 1 (for example, a plan for transporting components, a plan for deploying workers, etc.) compared to when the second section 2b or the third section 2c are located in the center.

(建物の施工方法-第2工区施工工程)
次に、第2工区施工工程について説明する。第2工区施工工程は、第1工区施工工程の後に、第2工区2bにおいて第2躯体20bの一部分(具体的には、第2躯体20bにおけるA工区3aからE工区3eの一部分)を施工する工程である。
(Building construction method - Second section construction process)
Next, the second construction section construction process will be described. The second construction section construction process is a process of constructing a part of the second structure 20b (specifically, a part of the A construction section 3a to the E construction section 3e in the second structure 20b) in the second construction section 2b after the first construction section construction process.

ここで、「躯体20の一部分」とは、実施の形態では、躯体20の部分のうち少なくとも屋根部23を含む部分であり、具体的には、床部22を除く部分(例えば、屋根部23、柱部24、梁部25等)が該当する。また、「躯体20の他の一部分」とは、実施の形態では、躯体20の部分のうち、躯体20の一部分以外の部分であり、具体的には、少なくとも床部22を含む部分(例えば、床部22、壁部26等)が該当する。 Here, in the embodiment, "a part of the structure 20" refers to a part of the structure 20 that includes at least the roof portion 23, and specifically refers to a part excluding the floor portion 22 (e.g., the roof portion 23, the columns 24, the beams 25, etc.). In addition, in the embodiment, "another part of the structure 20" refers to a part of the structure 20 other than the part of the structure 20, and specifically refers to a part that includes at least the floor portion 22 (e.g., the floor portion 22, the wall portion 26, etc.).

実施の形態では、図3に示すように、公知の施工手法(例えば、屏風建て工法)及び建設重機を用いて、第2躯体20bの一部分の水平力を第1躯体20aに直接支持させながら、当該一部分を施工する。また、第2躯体20bの一部分を第1階層21aから第4階層21dの順に施工する。 In the embodiment, as shown in FIG. 3, a known construction method (e.g., folding screen construction method) and heavy construction equipment are used to construct a portion of the second structure 20b while the horizontal force of that portion is directly supported by the first structure 20a. In addition, the portions of the second structure 20b are constructed in the order of the first story 21a to the fourth story 21d.

(建物の施工方法-第2工区施工工程-第1階層について)
具体的には、まず、第2躯体20bの一部分における第1階層21aを施工する。より具体的には、第2躯体20bの第1柱部24aを地表に対して本固定する。また、第2躯体20bの第1梁部25aを第2躯体20bの第1柱部24aに対して仮固定し、且つ第1躯体20aの第1梁部25a又は第1柱部24aに対して仮固定する。
(Building construction method - Second section construction process - First floor)
Specifically, first, the first story 21a in a part of the second structure 20b is constructed. More specifically, the first column 24a of the second structure 20b is permanently fixed to the ground surface. In addition, the first beam 25a of the second structure 20b is provisionally fixed to the first column 24a of the second structure 20b, and is provisionally fixed to the first beam 25a or the first column 24a of the first structure 20a.

ここで、第2躯体20bの第1梁部25aを仮固定する理由については、このタイミングで第2躯体20bの第1梁部25aを本固定しようとすると、第2躯体20bの第1柱部24a等の付近に仮設部材を設置する必要が生じるものの、第1梁部25aを仮固定する際には仮設部材の設置は必ずしも必要ではないので、仮設部材を設置する作業を省略することが可能になるからである(なお、その他の梁部25を仮固定する理由についても、略同様とする)。なお、「仮設部材」とは、作業者が安全に作業を行うために躯体20又はその周辺に仮設される部材であり、例えば、仮設足場(例えば、トピック、コラム、水平ネット)、仮設機材等が該当する。 Here, the reason for temporarily fixing the first beam 25a of the second structure 20b is that if the first beam 25a of the second structure 20b is to be permanently fixed at this time, it will be necessary to install temporary members near the first column 24a of the second structure 20b, etc., but since the installation of temporary members is not necessarily required when temporarily fixing the first beam 25a, it is possible to omit the work of installing temporary members (note that the same applies to the reasons for temporarily fixing the other beams 25). Note that "temporary members" are members that are temporarily installed on or around the structure 20 to allow workers to work safely, and include, for example, temporary scaffolding (e.g., topics, columns, horizontal nets), temporary equipment, etc.

(建物の施工方法-第2工区施工工程-第2階層について)
次に、第2躯体20bの一部分における第2階層21bを施工する。より具体的には、第2躯体20bの第2柱部24bを第2躯体20bの第1柱部24aに対して本固定した後に、第2躯体20bの第2梁部25bを第2躯体20bの第2柱部24bに対して仮固定し、且つ第1躯体20aの第2梁部25b又は第2柱部24bに対して仮固定する。
(Building construction method - Second section construction process - Second floor)
Next, the second story 21b in a part of the second skeleton 20b is constructed. More specifically, after the second column portion 24b of the second skeleton 20b is permanently fixed to the first column portion 24a of the second skeleton 20b, the second beam portion 25b of the second skeleton 20b is provisionally fixed to the second column portion 24b of the second skeleton 20b, and is provisionally fixed to the second beam portion 25b or the second column portion 24b of the first skeleton 20a.

(建物の施工方法-第2工区施工工程-第3階層について)
次いで、第2躯体20bの一部分における第3階層21cを施工し、より具体的には、上述した第2躯体20bの一部分における第2階層21bの施工と略同様に施工する。
(Building construction method - Second section construction process - Third floor)
Next, the third story 21c in a portion of the second structure 20b is constructed, more specifically, in substantially the same manner as the second story 21b in a portion of the second structure 20b described above.

(建物の施工方法-第2工区施工工程-第4階層について)
続いて、第2躯体20bの一部分における第4階層21dを施工し、より具体的には、上述した第2躯体20bの一部分における第2階層21bの施工と略同様に施工した後に、第2躯体20bの屋根部23を第2躯体20bの第4梁部25d又は第4柱部24dに対して本固定する。
(Building construction method - Second section construction process - Fourth floor)
Next, the fourth level 21d in a part of the second structure 20b is constructed, more specifically, in substantially the same manner as the construction of the second level 21b in a part of the second structure 20b described above, and then the roof portion 23 of the second structure 20b is finally fixed to the fourth beam portion 25d or the fourth column portion 24d of the second structure 20b.

(建物の施工方法-第2工区施工工程-その他について)
また、第2工区施工工程時における第1躯体20aと第2躯体20bの一部分との具体的な構成については任意であるが、実施の形態では、第1躯体20aは、当該第1躯体20aの水平力及び第2躯体20bの水平力を支持可能に構成されていると共に、当該第1躯体20aの鉛直力を支持可能に構成されており、第2躯体20bの一部分は、当該一部分の水平力を支持不能に構成されていると共に、当該一部分の鉛直力を支持可能に構成されている(なお、後述する第2工区第4工区間施工工程における第2躯体20bと第3躯体20cの一部分との具体的な構成、後述する第2工区第4工区間施工工程における第3躯体20cの一部分と第4躯体20dのD工区3dの一部分との具体的な構成、並びに、後述する第3工区第4工区間施工工程における第3躯体20c及び第4躯体20dのD工区3dの部分と第4躯体20dのD工区3d以外の工区の一部分との具体的な構成についても、略同様とする)。
(Building construction method - Second section construction process - Others)
In addition, the specific configuration of the first structure 20a and a portion of the second structure 20b during the second construction section construction process is arbitrary, but in the embodiment, the first structure 20a is configured to be able to support the horizontal force of the first structure 20a and the horizontal force of the second structure 20b, and is configured to be able to support the vertical force of the first structure 20a, and a portion of the second structure 20b is configured not to be able to support the horizontal force of the portion, and is configured to be able to support the vertical force of the portion (e.g. The same applies to the specific configurations of the second structure 20b and a portion of the third structure 20c in the construction process of the fourth work section of the second work section described below, the specific configurations of the portion of the third structure 20c and a portion of section D 3d of the fourth structure 20d in the construction process of the fourth work section of the second work section described below, and the specific configurations of the third structure 20c and portions of section D 3d of the fourth structure 20d and portions of work sections other than section D 3d of the fourth structure 20d in the construction process of the fourth work section of the third work section described below).

具体的には、第1躯体20aについては、設計上第1躯体20aに作用し得る第1躯体20aの水平力、第2躯体20bの水平力、及び第1躯体20aの鉛直力に耐えられるように、第1躯体20aの各種部材(具体的には、床部22、屋根部23、柱部24、梁部25、及び壁部26)の形状、大きさ(具体的には、左右方向の長さ、前後方向の長さ、上下方向の長さ)、及び材質を設定している。また、第2躯体20bの一部分については、設計上第2躯体20bに作用し得る第2躯体20bの鉛直力のみに耐えられるように、第2躯体20bの一部分の各種部材(具体的には、屋根部23、柱部24、及び梁部25)の形状、大きさ、及び材質を設定している。 Specifically, the shapes, sizes (specifically, the left-right length, the front-back length, and the up-down length) and materials of the various members of the first body 20a (specifically, the floor 22, the roof 23, the columns 24, the beams 25, and the walls 26) are set so that the first body 20a can withstand the horizontal force of the first body 20a, the horizontal force of the second body 20b, and the vertical force of the first body 20a, which may act on the first body 20a in terms of design. In addition, the shapes, sizes and materials of the various members of a portion of the second body 20b (specifically, the roof 23, the columns 24, and the beams 25) are set so that the portion of the second body 20b can withstand only the vertical force of the second body 20b, which may act on the second body 20b in terms of design.

これにより、第2躯体20bの一部分を施工する際に、第1躯体20aが第2躯体20bの一部分の水平力を確実に支持でき、第2躯体20bの一部分を安定して施工することができる。また、第2躯体20bの一部分の強度を過大に設定することを回避でき、第2躯体20bの一部分の製造性を維持できる。 As a result, when constructing a portion of the second structure 20b, the first structure 20a can reliably support the horizontal force of the portion of the second structure 20b, and the portion of the second structure 20b can be stably constructed. In addition, it is possible to avoid setting the strength of the portion of the second structure 20b excessively, and the manufacturability of the portion of the second structure 20b can be maintained.

また、第2工区施工工程のその他の作業内容については任意であるが、実施の形態では、図3に示すように、補強材30を第2躯体20bに設ける補強工程をさらに含んでいる(なお、第2工区第4工区間施工工程、及び第3工区第4工区間施工工程についても略同様とする)。 The other work content of the second section construction process is optional, but in the embodiment, as shown in FIG. 3, it further includes a reinforcing process of providing reinforcing material 30 to the second structure 20b (note that the same applies to the second section, fourth section construction process and the third section, fourth section construction process).

具体的には、上述した作業の終了後又は途中に、第2躯体20bのB工区3b及びD工区3dにおける少なくとも1つ以上の階層21に一対の補強材30を設けて、当該部分の床部22及び隣接する床部22に対して固定具等によって本固定する。 Specifically, after or during the above-mentioned work, a pair of reinforcing members 30 are provided on at least one or more stories 21 in the B section 3b and the D section 3d of the second structure 20b, and are permanently fixed to the floor section 22 of that section and the adjacent floor section 22 by means of fasteners or the like.

これにより、第2躯体20bを補強することができ、第3躯体20cを施工する際に第3躯体20cを安定して支持できる。 This allows the second structure 20b to be reinforced, and the third structure 20c can be stably supported when it is constructed.

このような第2工区施工工程により、第2躯体20bの一部分を施工する際に第2躯体20bの一部分の水平力を第1躯体20aに直接支持でき、仮設部材を設ける必要がないことから、第2躯体20bの一部分の施工性を高めることができる。また、第2躯体20bの一部分を先行施工することで、全天候において第2躯体20bの他の一部分を施工でき、第2躯体20bの施工性を高めやすくなる。特に、第2躯体20bの床部22がコンクリート製であるので、全天候において当該床部22のコンクリート打設を行うことができ、雨等による当該床部22の施工遅延を回避できる。 By carrying out this second section construction process, when constructing a portion of the second structure 20b, the horizontal force of the portion of the second structure 20b can be directly supported by the first structure 20a, and there is no need to provide temporary members, which improves the workability of the portion of the second structure 20b. Furthermore, by constructing a portion of the second structure 20b in advance, the other portion of the second structure 20b can be constructed in all weather conditions, which makes it easier to improve the workability of the second structure 20b. In particular, since the floor 22 of the second structure 20b is made of concrete, concrete can be poured for the floor 22 in all weather conditions, which avoids delays in the construction of the floor 22 due to rain, etc.

なお、第2工区施工工程の施工時においては、第1躯体20aは、特許請求の範囲における「第1の躯体」に対応し、第2躯体20bは、特許請求の範囲における「第2の躯体」に対応する。また、第1工区施工工程は、特許請求の範囲における「第1施工工程」に対応し、第2工区施工工程は、特許請求の範囲における「第2先行施工工程」(具体的には、第1施工工程の後に行われる「第2先行施工工程」)に対応する。 During the construction of the second section construction process, the first structure 20a corresponds to the "first structure" in the claims, and the second structure 20b corresponds to the "second structure" in the claims. The first section construction process corresponds to the "first construction process" in the claims, and the second section construction process corresponds to the "second advance construction process" in the claims (specifically, the "second advance construction process" carried out after the first construction process).

(建物の施工方法-第2工区第4工区間施工工程)
次に、第2工区第4工区間施工工程について説明する。第2工区第4工区間施工工程は、第2工区施工工程の後に、第2工区2bから第4工区間において第2躯体20bの他の一部分(具体的には、第2躯体20bのA工区3aからE工区3eの他の一部分)、第3躯体20cの一部分(具体的には、第3躯体20cのA工区3aからE工区3eの一部分)、及び第4躯体20dの一部分(具体的には、第4躯体20dのD工区3dの一部分)を施工する工程である。
(Building construction method - Construction process for the 2nd and 4th sections)
Next, the construction process of the fourth section of the second section will be described. The construction process of the fourth section of the second section is a process of constructing another part of the second skeleton 20b (specifically, another part of the A section 3a to the E section 3e of the second skeleton 20b), a part of the third skeleton 20c (specifically, a part of the A section 3a to the E section 3e of the third skeleton 20c), and a part of the fourth skeleton 20d (specifically, a part of the D section 3d of the fourth skeleton 20d) in the second section 2b to the fourth section after the construction process of the second section.

実施の形態では、図4に示すように、公知の施工手法(例えば、屏風建て工法)及び建設重機を用いて、第2躯体20bの他の一部分の水平力を第1躯体20aに直接支持させながら、当該他の一部分を施工すると共に、第3躯体20cの一部分の水平力を第2躯体20bに直接支持させ、且つ第4躯体20dの一部分の水平力を第3躯体20cに直接支持させながら、これら一部分を施工する。また、第2躯体20bの他の一部分、第3躯体20cの一部分、及び第4躯体20dの一部分を第1階層21aから第4階層21dの順に施工する。 In the embodiment, as shown in FIG. 4, a known construction method (e.g., folding screen construction method) and heavy construction equipment are used to construct another part of the second structure 20b while the horizontal force of that other part is directly supported by the first structure 20a, and to construct a part of the third structure 20c while the horizontal force of that part is directly supported by the second structure 20b and a part of the fourth structure 20d while the horizontal force of that part is directly supported by the third structure 20c. In addition, the other part of the second structure 20b, a part of the third structure 20c, and a part of the fourth structure 20d are constructed in the order of the first story 21a to the fourth story 21d.

ここで、第2工区第4工区間施工工程において、第4躯体20dのD工区3dの一部分を施工する理由は、第4躯体20dのD工区3dの一部分を先行施工することにより、図5(a)に示すように、第4躯体20dのD工区3d以外の工区の部分を施工する際に、第4躯体20dのD工区3d以外の工区の部分の水平力を第3躯体20c及び第4躯体20dのD工区3dの部分に支持させるためである。特に、第3躯体20cに第4躯体20dのD工区3d以外の工区の部分の左右方向の水平力を支持させ、第4躯体20dのD工区3dの部分に第4躯体20dのD工区3d以外の工区の部分の左右方向とは異なる方向の水平力(図5では、前後方向の水平力)を支持させることで、第4躯体20dのD工区3d以外の工区の部分の施工時の安定性を高めることが可能となる。 Here, the reason for constructing a portion of section D 3d of the fourth structure 20d in the construction process of the fourth section of the second structure is that by constructing a portion of section D 3d of the fourth structure 20d in advance, as shown in Figure 5 (a), when constructing sections other than section D 3d of the fourth structure 20d, the horizontal force of the sections other than section D 3d of the fourth structure 20d can be supported by the third structure 20c and the section D 3d of the fourth structure 20d. In particular, by having the third structure 20c support the horizontal force in the left-right direction of the sections of the fourth structure 20d other than section D 3d, and having section D 3d of the fourth structure 20d support a horizontal force in a direction different from the left-right direction of the sections of the fourth structure 20d other than section D 3d (in FIG. 5, a horizontal force in the front-back direction), it is possible to increase the stability of the sections of the fourth structure 20d other than section D 3d during construction.

(建物の施工方法-第2工区第4工区間施工工程-第1階層について)
具体的には、まず、第2躯体20bの他の一部分における第1階層21aを施工すると共に、第3躯体20cの一部分及び第4躯体20dのD工区3dの一部分の各々における第1階層21aを施工する。
(Building construction method - Construction process for the 2nd section, 4th section - 1st floor)
Specifically, first, the first level 21a in another part of the second structure 20b is constructed, and then the first level 21a in each of a part of the third structure 20c and a part of the D section 3d of the fourth structure 20d is constructed.

より具体的には、第2躯体20bの上記第1階層21aの施工については、まず、第2躯体20bの第1床部22a用の型枠を地表に設置し、当該型枠にコンクリートを流し込んで打設した後、当該コンクリートを所定期間固化させることにより、第2躯体20bの第1床部22aを地表に設置すると共に、第1躯体20aの第1床部22aと連結する。その後、第2躯体20bの第1梁部25aを第2躯体20bの第1柱部24aに対して本固定し、且つ第1躯体20aの第1梁部25a又は第1柱部24aに対して本固定する。また、第2躯体20bの第1壁部26aを第2躯体20bの第1柱部24aに対して本固定する。 More specifically, in the construction of the first floor 21a of the second structure 20b, first, a form for the first floor 22a of the second structure 20b is installed on the ground surface, concrete is poured into the form, and the concrete is allowed to harden for a predetermined period of time, thereby installing the first floor 22a of the second structure 20b on the ground surface and connecting it to the first floor 22a of the first structure 20a. After that, the first beam 25a of the second structure 20b is fixed to the first column 24a of the second structure 20b, and is also fixed to the first beam 25a or the first column 24a of the first structure 20a. In addition, the first wall 26a of the second structure 20b is fixed to the first column 24a of the second structure 20b.

また、第3躯体20cにおける上記第1階層21aの施工については、第3躯体20cの第1柱部24aを地表に対して本固定した後に、第3躯体20cの第1梁部25aを第3躯体20cの第1柱部24aに対して仮固定し、且つ第2躯体20bの第1梁部25a又は第1柱部24aに対して仮固定する。 In addition, for the construction of the first floor 21a of the third structure 20c, the first column 24a of the third structure 20c is permanently fixed to the ground surface, and then the first beam 25a of the third structure 20c is provisionally fixed to the first column 24a of the third structure 20c, and provisionally fixed to the first beam 25a or the first column 24a of the second structure 20b.

また、第4躯体20dにおける上記第1階層21aの施工については、上述した第3躯体20cにおける上記第1階層21aの施工と略同様に施工する。 The construction of the first floor 21a of the fourth structure 20d is carried out in substantially the same manner as the construction of the first floor 21a of the third structure 20c described above.

(建物の施工方法-第2工区第4工区間施工工程-第2階層について)
次に、第2躯体20bの他の一部分における第2階層21bを施工すると共に、第3躯体20cの一部分及び第4躯体20dのD工区3dの一部分の各々における第2階層21bを施工する。
(Building construction method - Construction process for the 2nd section, 4th section - 2nd floor)
Next, the second level 21b in another part of the second structure 20b is constructed, and the second level 21b in each of a part of the third structure 20c and a part of the D section 3d of the fourth structure 20d is constructed.

より具体的には、第2躯体20bの上記第2階層21bの施工については、第2躯体20bの第2床部22b用の型枠を第2躯体20bの第1柱部24a及び第1梁部25aの上部に設置し、当該型枠にコンクリートを流し込んで打設した後、当該コンクリートを所定期間固化させることにより、第2躯体20bの第2床部22bを第2躯体20bの第1柱部24a及び第1梁部25aに設置すると共に、第1躯体20aの第2床部22bと連結する。その後、第2躯体20bの第2梁部25bを第2躯体20bの第2柱部24bに対して本固定し、且つ第1躯体20aの第2梁部25b又は第2柱部24bに対して本固定する。また、第2躯体20bの第2壁部26bを第2躯体20bの第2柱部24bに対して本固定する。 More specifically, for the construction of the second floor 21b of the second structure 20b, a form for the second floor 22b of the second structure 20b is installed on the first column 24a and the first beam 25a of the second structure 20b, concrete is poured into the form, and the concrete is allowed to solidify for a predetermined period of time, thereby installing the second floor 22b of the second structure 20b on the first column 24a and the first beam 25a of the second structure 20b and connecting it to the second floor 22b of the first structure 20a. After that, the second beam 25b of the second structure 20b is fixed to the second column 24b of the second structure 20b, and is fixed to the second beam 25b or the second column 24b of the first structure 20a. In addition, the second wall portion 26b of the second body 20b is permanently fixed to the second column portion 24b of the second body 20b.

また、第3躯体20cの上記第2階層21bの施工については、第3躯体20cの第2柱部24bを第3躯体20cの第1柱部24aに対して本固定した後に、第3躯体20cの第2梁部25bを第3躯体20cの第2柱部24bに対して仮固定し、且つ第2躯体20bの第2梁部25b又は第2柱部24bに対して仮固定する。 In addition, for the construction of the second floor 21b of the third structure 20c, the second column 24b of the third structure 20c is permanently fixed to the first column 24a of the third structure 20c, and then the second beam 25b of the third structure 20c is provisionally fixed to the second column 24b of the third structure 20c, and is provisionally fixed to the second beam 25b or the second column 24b of the second structure 20b.

また、第4躯体20dの上記第2階層21bの施工については、上述した第3躯体20cにおける上記第2階層21bの施工と略同様に施工する。 The construction of the second floor 21b of the fourth structure 20d is carried out in substantially the same manner as the construction of the second floor 21b of the third structure 20c described above.

(建物の施工方法-第2工区第4工区間施工工程-第3階層について)
次に、第2躯体20bの他の一部分における第3階層21cを施工すると共に、第3躯体20cの一部分及び第4躯体20dのD工区3dの一部分の各々における第3階層21cを施工する。
(Building construction method - Construction process for the 2nd section, 4th section - 3rd floor)
Next, the third level 21c in another part of the second structure 20b is constructed, and the third level 21c in each of a part of the third structure 20c and a part of the D section 3d of the fourth structure 20d is constructed.

より具体的には、第2躯体20bの上記第3階層21cの施工については、上述した第2躯体20bの上記第2階層21bの施工と略同様に施工する。 More specifically, the construction of the third level 21c of the second structure 20b is carried out in substantially the same manner as the construction of the second level 21b of the second structure 20b described above.

また、第3躯体20cの上記第3階層21cの施工については、上述した第3躯体20cの上記第2階層21bの施工と略同様に施工する。 The construction of the third floor 21c of the third structure 20c is carried out in substantially the same manner as the construction of the second floor 21b of the third structure 20c described above.

また、第4躯体20dの上記第3階層21cの施工については、上述した第3躯体20cにおける上記第3階層21cの施工と略同様に施工する。 The construction of the third floor 21c of the fourth structure 20d is carried out in substantially the same manner as the construction of the third floor 21c of the third structure 20c described above.

(建物の施工方法-第2工区第4工区間施工工程-第4階層について)
続いて、第2躯体20bの他の一部分における第4階層21dを施工すると共に、第3躯体20cの一部分及び第4躯体20dのD工区3dの一部分の各々における第4階層21dを施工する。
(Building construction method - Construction process for the 2nd section, 4th section - 4th floor)
Next, the fourth level 21d in another part of the second structure 20b is constructed, and the fourth level 21d in each of a part of the third structure 20c and a part of the D section 3d of the fourth structure 20d is constructed.

より具体的には、第2躯体20bの上記第4階層21dの施工については、上述した第2躯体20bの上記第2階層21bの施工と略同様に施工する。 More specifically, the construction of the fourth floor 21d of the second structure 20b is carried out in substantially the same manner as the construction of the second floor 21b of the second structure 20b described above.

また、第3躯体20cの上記第4階層21dの施工については、上述した第3躯体20cの上記第2階層21bの施工と略同様に施工した後に、第3躯体20cの屋根部23を第3躯体20cの第4梁部25d又は第4柱部24dに対して本固定する。 The construction of the fourth floor 21d of the third structure 20c is carried out in a manner substantially similar to that of the second floor 21b of the third structure 20c described above, and then the roof portion 23 of the third structure 20c is finally fixed to the fourth beam portion 25d or the fourth column portion 24d of the third structure 20c.

また、第4躯体20dの上記第4階層21dの施工については、上述した第3躯体20cにおける上記第4階層21dの施工と略同様に施工する。 The construction of the fourth floor 21d of the fourth structure 20d is carried out in substantially the same manner as the construction of the fourth floor 21d of the third structure 20c described above.

このような第2工区第4工区間施工工程により、第2躯体20bの他の一部分を施工する際に第2躯体20bの他の一部分の水平力を第1躯体20aに直接支持でき、仮設部材を設ける必要がないことから、第2躯体20bの他の一部分の施工性を高めることができる。また、第3躯体20cの一部分及び第4躯体20dのD工区3dの一部分を先行施工することで、全天候において第3躯体20cの他の一部分及び第4躯体20dのD工区3dの他の一部分を施工でき、第3躯体20c及び第4躯体20dの施工性を高めやすくなる。特に、第3躯体20c及び第4躯体20dのD工区3dの床部22がコンクリート製であるので、全天候において当該床部22のコンクリート打設を行うことができ、雨等による当該床部22の施工遅延を回避できる。 By carrying out the construction process for the fourth section of the second section, when constructing the other part of the second structure 20b, the horizontal force of the other part of the second structure 20b can be directly supported by the first structure 20a, and there is no need to provide temporary members, so that the workability of the other part of the second structure 20b can be improved. In addition, by constructing a part of the third structure 20c and a part of the D section 3d of the fourth structure 20d in advance, the other part of the third structure 20c and the other part of the D section 3d of the fourth structure 20d can be constructed in all weather conditions, which makes it easier to improve the workability of the third structure 20c and the fourth structure 20d. In particular, since the floors 22 of the D section 3d of the third structure 20c and the fourth structure 20d are made of concrete, concrete can be poured in the floors 22 in all weather conditions, and delays in the construction of the floors 22 due to rain, etc. can be avoided.

なお、第2工区第4工区間施工工程における第2躯体20bの施工時においては、第1躯体20aは、特許請求の範囲における「第1の躯体」に対応し、第2躯体20bは、特許請求の範囲における「第2の躯体」に対応する。また、第2工区第4工区間施工工程のうち第2躯体20bの他の一部分を施工する工程は、特許請求の範囲における「第2後行施工工程」に対応する。 In addition, during the construction of the second structure 20b in the construction process of the fourth section of the second work area, the first structure 20a corresponds to the "first structure" in the claims, and the second structure 20b corresponds to the "second structure" in the claims. Also, the process of constructing another part of the second structure 20b in the construction process of the fourth section of the second work area corresponds to the "second subsequent construction process" in the claims.

また、第2工区第4工区間施工工程における第3躯体20cの施工時においては、第2躯体20bは、特許請求の範囲における「第1の躯体」に対応し、第3躯体20cは、特許請求の範囲における「第2の躯体」に対応する。また、第2工区施工工程及び第2工区第4工区間施工工程のうち第2躯体20bの他の一部分を施工する工程は、特許請求の範囲における「第1施工工程」に対応し、第2工区第4工区間施工工程のうち第3躯体20cの一部分を施工する工程は、特許請求の範囲における「第2先行施工工程」(具体的には、第1施工工程の途中に行われる「第2先行施工工程」)に対応する。 In addition, during the construction of the third structure 20c in the construction process of the fourth section of the second work area, the second structure 20b corresponds to the "first structure" in the claims, and the third structure 20c corresponds to the "second structure" in the claims. In addition, the process of constructing another part of the second structure 20b in the construction process of the second work area and the construction process of the fourth section of the second work area corresponds to the "first construction process" in the claims, and the process of constructing a part of the third structure 20c in the construction process of the fourth section of the second work area corresponds to the "second advance construction process" in the claims (specifically, the "second advance construction process" carried out in the middle of the first construction process).

また、第2工区第4工区間施工工程における第4躯体20dの施工時においては、第3躯体20cは、特許請求の範囲における「第1の躯体」に対応し、第4躯体20dは、特許請求の範囲における「第2の躯体」に対応する。また、第2工区第4工区間施工工程のうち第3躯体20cの一部分を施工する工程は、特許請求の範囲における「第1施工工程」に対応し、第2工区第4工区間施工工程のうち第4躯体20dのD工区3dの一部分を施工する工程は、特許請求の範囲における「第2先行施工工程」(具体的には、第1施工工程の途中に行われる「第2先行施工工程」)に対応する。 In addition, during the construction of the fourth structure 20d in the construction process of the fourth section of the second work area, the third structure 20c corresponds to the "first structure" in the claims, and the fourth structure 20d corresponds to the "second structure" in the claims. In addition, the process of constructing a portion of the third structure 20c in the construction process of the fourth section of the second work area corresponds to the "first construction process" in the claims, and the process of constructing a portion of section D 3d of the fourth structure 20d in the construction process of the fourth section of the second work area corresponds to the "second advance construction process" in the claims (specifically, the "second advance construction process" carried out in the middle of the first construction process).

(建物の施工方法-第3工区第4工区間施工工程)
次に、第3工区第4工区間施工工程について説明する。第3工区第4工区間施工工程は、第2工区第4工区間施工工程の後に、第3工区2cから第4工区2d間において第3躯体20cの他の一部分(具体的には、第3躯体20cのA工区3aからE工区3eの他の一部分)、第4躯体20dのD工区3dの他の一部分、及び第4躯体20dのD工区3d以外の工区(具体的には、A工区3a、B工区3b、C工区3c、E工区3e)の一部分を施工する工程である。
(Building construction method - construction process for the 3rd and 4th sections)
Next, the construction process of the fourth section of the third section will be described. The fourth section of the third section is a process of constructing another part of the third skeleton 20c (specifically, another part of the A section 3a to the E section 3e of the third skeleton 20c) between the third section 2c and the fourth section 2d, another part of the D section 3d of the fourth skeleton 20d, and a part of the sections other than the D section 3d of the fourth skeleton 20d (specifically, the A section 3a, the B section 3b, the C section 3c, and the E section 3e) after the second section fourth section construction process.

実施の形態では、図5に示すように、公知の施工手法(例えば、屏風建て工法)及び建設重機を用いて、第3躯体20cの他の一部分の水平力を第2躯体20bに直接支持させ、且つ第4躯体20dのD工区3dの他の一部分の水平力を第3躯体20cに直接支持させながら、これら他の一部分を施工すると共に、第4躯体20dのD工区3d以外の工区の一部分の水平力を第3躯体20c及び第4躯体20dのD工区3dの部分に直接支持させながら、当該一部分を施工する。また、第3躯体20cの他の一部分、第4躯体20dのD工区3dの他の一部分、及び第4躯体20dのD工区3d以外の工区の一部分を第1階層21aから第4階層21dの順に施工する。 In the embodiment, as shown in FIG. 5, using a known construction method (e.g., folding screen construction method) and heavy construction equipment, the horizontal force of another part of the third structure 20c is directly supported by the second structure 20b, and the horizontal force of another part of the D section 3d of the fourth structure 20d is directly supported by the third structure 20c while these other parts are constructed, and the horizontal force of a part of the section other than the D section 3d of the fourth structure 20d is directly supported by the third structure 20c and the D section 3d of the fourth structure 20d while the part is constructed. In addition, the other part of the third structure 20c, the other part of the D section 3d of the fourth structure 20d, and the part of the section other than the D section 3d of the fourth structure 20d are constructed in the order from the first floor 21a to the fourth floor 21d.

(建物の施工方法-第3工区第4工区間施工工程-第1階層について)
具体的には、まず、第3躯体20cの他の一部分及び第4躯体20dのD工区3dの他の一部分の各々における第1階層21aを施工すると共に、第4躯体20dのD工区3d以外の工区の一部分における第1階層21aを施工する。
(Building construction method - 3rd section, 4th section construction process - 1st floor)
Specifically, first, the first level 21a is constructed in each of other parts of the third structure 20c and other parts of section D 3d of the fourth structure 20d, and the first level 21a is constructed in parts of sections other than section D 3d of the fourth structure 20d.

より具体的には、第3躯体20cの上記第1階層21aの施工については、まず、第3躯体20cの第1床部22a用の型枠を地表に設置し、当該型枠にコンクリートを流し込んで打設した後、当該コンクリートを所定期間固化させることにより、第3躯体20cの第1床部22aを地表に設置すると共に、第2躯体20bの第1床部22aと連結する。その後、第3躯体20cの第1梁部25aを第3躯体20cの第1柱部24aに対して本固定し、且つ第2躯体20bの第1梁部25a又は第1柱部24aに対して本固定する。また、第3躯体20cの第1壁部26aを第3躯体20cの第1柱部24aに対して本固定する。 More specifically, in the construction of the first floor 21a of the third structure 20c, first, a form for the first floor 22a of the third structure 20c is installed on the ground surface, concrete is poured into the form, and the concrete is allowed to harden for a predetermined period of time, thereby installing the first floor 22a of the third structure 20c on the ground surface and connecting it to the first floor 22a of the second structure 20b. After that, the first beam 25a of the third structure 20c is fixed to the first column 24a of the third structure 20c, and is also fixed to the first beam 25a or the first column 24a of the second structure 20b. In addition, the first wall 26a of the third structure 20c is fixed to the first column 24a of the third structure 20c.

また、第4躯体20dのD工区3dにおける上記第1階層21aの施工については、上述した第3躯体20cの上記第1階層21aの施工と略同様に施工する。 The construction of the first floor 21a in the D section 3d of the fourth structure 20d will be carried out in substantially the same manner as the construction of the first floor 21a of the third structure 20c described above.

また、第4躯体20dのD工区3d以外の工区における上記第1階層21aの施工については、第4躯体20dの第1柱部24aを地表に対して本固定した後に、第4躯体20dの第1梁部25aを第4躯体20dの第1柱部24aに対して仮固定し、且つ第3躯体20cの第1梁部25a又は第1柱部24aに対して仮固定する。さらに、第4躯体20dのC工区3c及びE工区3eの各々の第1梁部25aを第4躯体20dのD工区3dの第1梁部25a又は第1柱部24aに対して仮固定する。 In addition, for the construction of the first floor 21a in sections other than section D 3d of the fourth structure 20d, after the first column 24a of the fourth structure 20d is permanently fixed to the ground surface, the first beam 25a of the fourth structure 20d is provisionally fixed to the first column 24a of the fourth structure 20d, and provisionally fixed to the first beam 25a or first column 24a of the third structure 20c. Furthermore, the first beam 25a of each of sections C 3c and E 3e of the fourth structure 20d is provisionally fixed to the first beam 25a or first column 24a of section D 3d of the fourth structure 20d.

(建物の施工方法-第3工区第4工区間施工工程-第2階層について)
次に、第3躯体20cの他の一部分及び第4躯体20dのD工区3dの他の一部分の各々における第2階層21bを施工すると共に、第4躯体20dのD工区3d以外の工区の一部分における第2階層21bを施工する。
(Building construction method - 3rd and 4th section construction process - 2nd floor)
Next, the second level 21b is constructed in each of other parts of the third structure 20c and other parts of section D 3d of the fourth structure 20d, and the second level 21b is constructed in parts of sections other than section D 3d of the fourth structure 20d.

より具体的には、第3躯体20cの上記第2階層21bの施工については、まず、第3躯体20cの第2床部22b用の型枠を第3躯体20cの第1柱部24a及び第1梁部25aの上部に設置し、当該型枠にコンクリートを流し込んで打設した後、当該コンクリートを所定期間固化させることにより、第3躯体20cの第2床部22bを第3躯体20cの第1柱部24a及び第1梁部25aに設置すると共に、第2躯体20bの第2床部22bと連結する。その後、第3躯体20cの第2梁部25bを第3躯体20cの第2柱部24bに対して本固定し、且つ第2躯体20bの第2梁部25b又は第2柱部24bに対して本固定する。また、第3躯体20cの第2壁部26bを第3躯体20cの第2柱部24bに対して本固定する。 More specifically, in the construction of the second floor 21b of the third structure 20c, a form for the second floor 22b of the third structure 20c is first installed on the top of the first column 24a and the first beam 25a of the third structure 20c, concrete is poured into the form, and the concrete is allowed to harden for a predetermined period of time, thereby installing the second floor 22b of the third structure 20c on the first column 24a and the first beam 25a of the third structure 20c and connecting it to the second floor 22b of the second structure 20b. After that, the second beam 25b of the third structure 20c is fixed to the second column 24b of the third structure 20c, and is fixed to the second beam 25b or the second column 24b of the second structure 20b. Additionally, the second wall portion 26b of the third body 20c is permanently fixed to the second column portion 24b of the third body 20c.

また、第4躯体20dのD工区3dにおける上記第2階層21bの施工については、上述した第3躯体20cの上記第2階層21bの施工と略同様に施工する。 The construction of the second floor 21b in the D section 3d of the fourth structure 20d will be carried out in substantially the same manner as the construction of the second floor 21b of the third structure 20c described above.

また、第4躯体20dのD工区3d以外の工区における上記第2階層21bの施工については、第4躯体20dの第2柱部24bを第4躯体20dの第1柱部24aに対して本固定した後に、第4躯体20dの第2梁部25bを第4躯体20dの第2柱部24bに対して仮固定し、且つ第3躯体20cの第2梁部25b又は第2柱部24bに対して仮固定する。さらに、第4躯体20dのC工区3c及びE工区3eの各々の第2梁部25bを第4躯体20dのD工区3dの第2梁部25b又は第2柱部24bに対して仮固定する。 In addition, for the construction of the second floor 21b in the sections other than the D section 3d of the fourth structure 20d, the second column 24b of the fourth structure 20d is permanently fixed to the first column 24a of the fourth structure 20d, and then the second beam 25b of the fourth structure 20d is provisionally fixed to the second column 24b of the fourth structure 20d, and is provisionally fixed to the second beam 25b or the second column 24b of the third structure 20c. Furthermore, the second beam 25b of each of the C section 3c and the E section 3e of the fourth structure 20d is provisionally fixed to the second beam 25b or the second column 24b of the D section 3d of the fourth structure 20d.

(建物の施工方法-第3工区第4工区間施工工程-第3階層について)
次に、第3躯体20cの他の一部分及び第4躯体20dのD工区3dの他の一部分の各々における第3階層21cを施工すると共に、第4躯体20dのD工区3d以外の工区の一部分における第3階層21cを施工する。
(Building construction method - 3rd section, 4th section construction process - 3rd floor)
Next, the third level 21c is constructed in each of other parts of the third structure 20c and other parts of section D 3d of the fourth structure 20d, and the third level 21c is constructed in parts of sections other than section D 3d of the fourth structure 20d.

より具体的には、第3躯体20cの上記第3階層21cの施工については、上述した第3躯体20cの上記第2階層21bの施工と略同様に施工する。 More specifically, the construction of the third floor 21c of the third structure 20c is carried out in substantially the same manner as the construction of the second floor 21b of the third structure 20c described above.

また、第4躯体20dのD工区3dにおける上記第3階層21cの施工については、上述した第3躯体20cの上記第3階層21cの施工と略同様に施工する。 The construction of the third floor 21c in the D section 3d of the fourth structure 20d will be carried out in substantially the same manner as the construction of the third floor 21c of the third structure 20c described above.

また、第4躯体20dのD工区3d以外の工区における上記第3階層21cの施工については、上述した第4躯体20dのD工区3d以外の工区における上記第2階層21bの施工と略同様に施工する。 The construction of the third level 21c in the work areas other than the D work area 3d of the fourth structure 20d will be carried out in substantially the same manner as the construction of the second level 21b in the work areas other than the D work area 3d of the fourth structure 20d described above.

(建物の施工方法-第3工区第4工区間施工工程-第4階層について)
続いて、第3躯体20cの他の一部分及び第4躯体20dのD工区3dの他の一部分の各々における第4階層21dを施工すると共に、第4躯体20dのD工区3d以外の工区の一部分における第4階層21dを施工する。
(Building construction method - 3rd section, 4th section construction process - 4th floor)
Next, the fourth level 21d is constructed in each of other parts of the third structure 20c and other parts of section D 3d of the fourth structure 20d, and the fourth level 21d is constructed in parts of sections other than section D 3d of the fourth structure 20d.

より具体的には、第3躯体20cの上記第4階層21dの施工については、上述した第3躯体20cの上記第2階層21bの施工と略同様に施工する。 More specifically, the construction of the fourth floor 21d of the third structure 20c is carried out in substantially the same manner as the construction of the second floor 21b of the third structure 20c described above.

また、第4躯体20dのD工区3dにおける上記第4階層21dの施工については、上述した第3躯体20cの上記第4階層21dの施工と略同様に施工する。 The construction of the fourth floor 21d in the D section 3d of the fourth structure 20d will be carried out in substantially the same manner as the construction of the fourth floor 21d of the third structure 20c described above.

また、第4躯体20dのD工区3d以外の工区における上記第4階層21dの施工については、上述した第4躯体20dのD工区3d以外の工区における上記第2階層21bの施工と略同様に施工した後に、第4躯体20dの屋根部23を第4躯体20dの第4梁部25d又は第4柱部24dに対して本固定する。 In addition, the construction of the fourth floor 21d in the work area other than the D work area 3d of the fourth structure 20d is carried out in substantially the same manner as the construction of the second floor 21b in the work area other than the D work area 3d of the fourth structure 20d described above, and then the roof portion 23 of the fourth structure 20d is finally fixed to the fourth beam portion 25d or the fourth column portion 24d of the fourth structure 20d.

このような第3工区第4工区間施工工程により、第3躯体20cの他の一部分を施工する際に第3躯体20cの他の一部分の水平力を第2躯体20bに直接支持でき、仮設部材を設ける必要がないことから、第3躯体20cの他の一部分の施工性を高めることができる。また、第4躯体20dのD工区3dの他の一部分を施工する際に第4躯体20dのD工区3dの他の一部分の水平力を第3躯体20cに直接支持でき、仮設部材を設ける必要がないことから、第4躯体20dのD工区3dの他の一部分の施工性を高めることができる。また、第4躯体20dのD工区3d以外の工区の一部分を先行施工することで、全天候において第4躯体20dのD工区3d以外の工区の他の一部分を施工でき、第4躯体20dの施工性を高めやすくなる。特に、第4躯体20dのD工区3d以外の工区の床部22がコンクリート製であるので、全天候において当該床部22のコンクリート打設を行うことができ、雨等による当該床部22の施工遅延を回避できる。 By such a construction process of the third section, fourth section, when constructing the other part of the third structure 20c, the horizontal force of the other part of the third structure 20c can be directly supported by the second structure 20b, and there is no need to provide temporary materials, so that the workability of the other part of the third structure 20c can be improved. In addition, when constructing the other part of the D section 3d of the fourth structure 20d, the horizontal force of the other part of the D section 3d of the fourth structure 20d can be directly supported by the third structure 20c, and there is no need to provide temporary materials, so that the workability of the other part of the D section 3d of the fourth structure 20d can be improved. In addition, by constructing a part of the section other than the D section 3d of the fourth structure 20d in advance, the other part of the section other than the D section 3d of the fourth structure 20d can be constructed in all weather conditions, which makes it easier to improve the workability of the fourth structure 20d. In particular, because the floors 22 of the fourth structure 20d in the sections other than section D 3d are made of concrete, concrete can be poured in the floors 22 in all weather conditions, and delays in construction of the floors 22 due to rain, etc. can be avoided.

なお、第3工区第4工区間施工工程における第3躯体20cの施工時においては、第2躯体20bは、特許請求の範囲における「第1の躯体」に対応し、第3躯体20cは、特許請求の範囲における「第2の躯体」に対応する。また、第3工区第4工区間施工工程のうち第3躯体20cの他の一部分を施工する工程は、特許請求の範囲における「第2後行施工工程」に対応する。 In addition, during the construction of the third structure 20c in the construction process of the fourth section of the third work area, the second structure 20b corresponds to the "first structure" in the claims, and the third structure 20c corresponds to the "second structure" in the claims. Also, the process of constructing another part of the third structure 20c in the construction process of the fourth section of the third work area corresponds to the "second subsequent construction process" in the claims.

また、第3工区第4工区間施工工程における第4躯体20dのD工区3dの部分の施工時においては、第3躯体20cは、特許請求の範囲における「第1の躯体」に対応し、第4躯体20dは、特許請求の範囲における「第2の躯体」に対応する。また、第3工区第4工区間施工工程のうち第4躯体20dのD工区3dの他の一部分を施工する工程は、特許請求の範囲における「第2後行施工工程」に対応する。 In addition, during the construction of section D 3d of fourth structure 20d in the construction process of section 4 of section 3, third structure 20c corresponds to the "first structure" in the claims, and fourth structure 20d corresponds to the "second structure" in the claims. In addition, the process of constructing another part of section D 3d of fourth structure 20d in the construction process of section 4 of section 3 corresponds to the "second subsequent construction process" in the claims.

また、第3工区第4工区間施工工程における第4躯体20dのD工区3d以外の工区の部分の施工時においては、第3躯体20c及び第4躯体20dのD工区3dの他の一部分は、特許請求の範囲における「第1の躯体」に対応し、第4躯体20dのD工区3d以外の区分の一部分は、特許請求の範囲における「第2の躯体」に対応する。また、第3工区第4工区間施工工程のうち第3躯体20c及び第4躯体20dのD工区3dの他の一部分を施工する工程は、特許請求の範囲における「第1施工工程」に対応し、第3工区第4工区間施工工程のうち第4躯体20dのD工区3d以外の一部分を施工する工程は、特許請求の範囲における「第2先行施工工程」(具体的には、第1施工工程の途中に行われる「第2先行施工工程」)に対応する。 In addition, during the construction of the portion of the fourth structure 20d other than the D section 3d in the construction process of the third section, the third structure 20c and the other portion of the D section 3d of the fourth structure 20d correspond to the "first structure" in the claims, and the portion of the section other than the D section 3d of the fourth structure 20d corresponds to the "second structure" in the claims. In addition, the process of constructing the third structure 20c and the other portion of the D section 3d of the fourth structure 20d in the construction process of the third section, the fourth section corresponds to the "first construction process" in the claims, and the process of constructing the portion of the fourth structure 20d other than the D section 3d in the construction process of the third section, the fourth section corresponds to the "second advance construction process" in the claims (specifically, the "second advance construction process" carried out during the first construction process).

(建物の施工方法-第4工区施工工程)
次に、第4工区施工工程について説明する。第4工区施工工程は、第3工区第4工区間施工工程の後に、第4工区2dにおいて第4躯体20dの他の一部分(具体的には、第4躯体20dのD工区3d以外の工区の他の一部分)を施工する工程である。
(Building construction method - 4th section construction process)
Next, the fourth section construction process will be described. The fourth section construction process is a process of constructing another part of the fourth structure 20d (specifically, another part of the section other than the D section 3d of the fourth structure 20d) in the fourth section 2d after the third section fourth section construction process.

実施の形態では、図に示すように、公知の施工手法(例えば、屏風建て工法)及び建設重機を用いて、第4躯体20dのD工区3d以外の工区の他の一部分の水平力を第3躯体20c及び第4躯体20dのD工区3dの部分に直接支持させながら、当該他の一部分を施工する。また、第4躯体20dのD工区3d以外の工区を第1階層21aから第4階層21dの順に施工する。 In the embodiment, as shown in the figure, a known construction method (e.g., folding screen construction method) and heavy construction equipment are used to construct another part of the work area other than the D work area 3d of the fourth structure 20d while the horizontal force of that other part is directly supported by the third structure 20c and the D work area 3d of the fourth structure 20d. In addition, the work areas other than the D work area 3d of the fourth structure 20d are constructed in the order from the first floor 21a to the fourth floor 21d.

(建物の施工方法-第4工区施工工程-第1階層について)
具体的には、まず、第4躯体20dのD工区3d以外の工区の他の一部分における第1階層21aを施工する。
(Building construction method - 4th section construction process - 1st floor)
Specifically, first, the first floor 21a in another part of the fourth structure 20d other than the D section 3d is constructed.

より具体的には、まず、第4躯体20dのD工区3d以外の工区における第1床部22a用の型枠を地表に設置し、当該型枠にコンクリートを流し込んで打設した後、当該コンクリートを所定期間固化させることにより、第4躯体20dのD工区3d以外の工区の第1床部22aを地表に設置すると共に、第3躯体20cの第1床部22aと第4躯体20dのD工区3dの第1床部22aと連結する。その後、第4躯体20dのD工区3d以外の工区の第1梁部25aを第4躯体20dのD工区3d以外の工区の第1柱部24aに対して本固定し、且つ第3躯体20cの第1梁部25a又は第1柱部24aに対して本固定する。また、第4躯体20dのC工区3c及びE工区3eの各々の第1梁部25aを第4躯体20dのD工区3dの第1梁部25a又は第1柱部24aに対して本固定する。さらに、第4躯体20dの第1壁部26aを第4躯体20dの第1柱部24aに対して本固定する。 More specifically, first, a form for the first floor 22a of the fourth structure 20d in the section other than the D section 3d is installed on the ground surface, concrete is poured into the form, and the concrete is allowed to harden for a predetermined period of time to install the first floor 22a of the fourth structure 20d in the section other than the D section 3d on the ground surface and connect the first floor 22a of the third structure 20c to the first floor 22a of the D section 3d of the fourth structure 20d. After that, the first beam 25a of the fourth structure 20d in the section other than the D section 3d is fixed to the first column 24a of the fourth structure 20d in the section other than the D section 3d, and is fixed to the first beam 25a or the first column 24a of the third structure 20c. In addition, the first beam portion 25a of each of the C section 3c and the E section 3e of the fourth structure 20d is fixed to the first beam portion 25a or the first column portion 24a of the D section 3d of the fourth structure 20d. Furthermore, the first wall portion 26a of the fourth structure 20d is fixed to the first column portion 24a of the fourth structure 20d.

(建物の施工方法-第4工区施工工程-第2階層について)
次に、第4躯体20dのD工区3d以外の工区の他の一部分における第2階層21bを施工する。
(Building construction method - 4th section construction process - 2nd floor)
Next, the second floor 21b is constructed in another part of the fourth structure 20d other than the D section 3d.

より具体的には、まず、第4躯体20dのD工区3d以外の工区における第2床部22b用の型枠を第4躯体20dの第1柱部24a及び第1梁部25aの上部に設置し、当該型枠にコンクリートを流し込んで打設した後、当該コンクリートを所定期間固化させることにより、第4躯体20dのD工区3d以外の工区の第2床部22bを第4躯体20dの第1柱部24a及び第1梁部25aに設置すると共に、第3躯体20cの第2床部22bと第4躯体20dのD工区3dの第2床部22bと連結する。その後、第4躯体20dのD工区3d以外の工区の第2梁部25bを第4躯体20dのD工区3d以外の工区の第2柱部24bに対して本固定し、且つ第3躯体20cの第2梁部25b又は第2柱部24bに対して本固定する。また、第4躯体20dのC工区3c及びE工区3eの各々の第2梁部25bを第4躯体20dのD工区3dの第2梁部25b又は第2柱部24bに対して本固定する。さらに、第4躯体20dの第2壁部26bを第4躯体20dの第2柱部24bに対して本固定する。 More specifically, first, formwork for the second floor 22b in the work area other than the D work area 3d of the fourth structure 20d is placed on top of the first column 24a and first beam 25a of the fourth structure 20d, and concrete is poured into the formwork and then allowed to harden for a predetermined period of time, thereby placing the second floor 22b in the work area other than the D work area 3d of the fourth structure 20d on the first column 24a and first beam 25a of the fourth structure 20d and connecting the second floor 22b of the third structure 20c to the second floor 22b of the D work area 3d of the fourth structure 20d. Then, the second beams 25b of the fourth structure 20d in the sections other than the D section 3d are fixed to the second columns 24b of the fourth structure 20d in the sections other than the D section 3d, and are fixed to the second beams 25b or the second columns 24b of the third structure 20c. Also, the second beams 25b of the C section 3c and the E section 3e of the fourth structure 20d are fixed to the second beams 25b or the second columns 24b of the D section 3d of the fourth structure 20d. Furthermore, the second wall 26b of the fourth structure 20d is fixed to the second columns 24b of the fourth structure 20d.

(建物の施工方法-第4工区施工工程-第3階層について)
次に、第4躯体20dのD工区3d以外の工区の他の一部分における第3階層21cを施工し、より具体的には、上述した第4躯体20dのD工区3d以外の工区の他の一部分における第2階層21bの施工と略同様に施工する。
(Building construction method - 4th section construction process - 3rd floor)
Next, the third level 21c is constructed in another part of the work area other than the D work area 3d of the fourth structure 20d, and more specifically, in a manner substantially similar to the construction of the second level 21b in another part of the work area other than the D work area 3d of the fourth structure 20d described above.

(建物の施工方法-第4工区施工工程-第4階層について)
続いて、第4躯体20dのD工区3d以外の工区の他の一部分における第4階層21dを施工し、より具体的には、上述した第4躯体20dのD工区3d以外の工区の他の一部分における第2階層21bの施工と略同様に施工する。
(Building construction method - 4th section construction process - 4th floor)
Next, the fourth level 21d is constructed in another part of the work area other than the D work area 3d of the fourth structure 20d, and more specifically, in a manner substantially similar to the construction of the second level 21b in another part of the work area other than the D work area 3d of the fourth structure 20d described above.

このような第4工区施工工程により、第4躯体20dのD工区3d以外の工区の他の一部分を施工する際に第4躯体20dのD工区3d以外の工区の他の一部分の水平力を第3躯体20c及び第4躯体20dのD工区3dの部分に直接支持でき、仮設部材を設ける必要がないことから、第4躯体20dのD工区3d以外の工区の他の一部分の施工性を高めることができる。 By using this construction process for the fourth section, when constructing other parts of the section other than section D 3d of the fourth structure 20d, the horizontal force of the other parts of the section other than section D 3d of the fourth structure 20d can be directly supported by the third structure 20c and the section D 3d of the fourth structure 20d, and there is no need to install temporary members, which improves the workability of the other parts of the section other than section D 3d of the fourth structure 20d.

なお、第4工区施工工程の施工時においては、第3躯体20c及び第4躯体20dのD工区3dの部分は、特許請求の範囲における「第1の躯体」に対応し、第4躯体20dのD工区3d以外の工区の部分は、特許請求の範囲における「第2の躯体」に対応する。また、第4工区施工工程は、特許請求の範囲における「第2後行施工工程」に対応する。 During the construction of the fourth section construction process, the third structure 20c and the D section 3d of the fourth structure 20d correspond to the "first structure" in the claims, and the sections of the fourth structure 20d other than the D section 3d correspond to the "second structure" in the claims. The fourth section construction process corresponds to the "second subsequent construction process" in the claims.

(建物の施工方法-仕上工程)
続いて、仕上工程について説明する。仕上工程は、第4工区施工工程の後に、建物1の仕上げを行う工程である。
(Building construction method - finishing process)
Next, the finishing process will be described. The finishing process is a process for finishing the building 1 after the fourth construction section construction process.

具体的には、第1躯体20aから第4躯体20dにおける残りの部材(例えば、残りの壁部26等)を、対応する床部22、梁部25、柱部24、又は壁部26に対して本固定する。また、第1躯体20aから第4躯体20dにおいて、建物1の外装工事(例えば、壁部26又は屋根部23外面の塗装工事等)及び内装工事(例えば、壁部26又は床部22の内面の塗装工事等)を行う。さらに、各工程で使用した建設重機や機材等を撤去する。これにより、図1に示す建物1を施工することができる。 Specifically, the remaining members (e.g., the remaining wall sections 26, etc.) in the first to fourth frames 20a to 20d are permanently fixed to the corresponding floor sections 22, beam sections 25, columns 24, or walls 26. In addition, in the first to fourth frames 20a to 20d, exterior construction work (e.g., painting the exterior surfaces of the walls 26 or roof section 23, etc.) and interior construction work (e.g., painting the interior surfaces of the walls 26 or floor sections 22, etc.) of the building 1 are carried out. Furthermore, the construction machinery and materials used in each process are removed. This completes the construction of the building 1 shown in FIG. 1.

以上のような建物1の施工方法により、建物1における隣接する2つの躯体20のうち、一方の躯体20を施工した後に他方の躯体20を施工する際に、他方の躯体20の水平力を一方の躯体20に直接支持でき、仮設部材を設ける必要がないことから、建物1の施工性を高めることができる。また、上記他方の躯体20における屋根部23を含む一部分を先行施工することで、全天候において上記他方の躯体20における他の一部分を施工でき、建物1の施工性を一層高めることができる。 By using the above-described construction method for the building 1, when constructing one of the two adjacent frames 20 of the building 1 and then constructing the other frame 20, the horizontal force of the other frame 20 can be directly supported by the one frame 20, and there is no need to install temporary members, thereby improving the constructability of the building 1. In addition, by constructing a portion of the other frame 20, including the roof portion 23, in advance, the other portion of the other frame 20 can be constructed in all weather conditions, further improving the constructability of the building 1.

(実施の形態の効果)
このように実施の形態によれば、第1の工区において、第1の躯体20を施工する第1施工工程と、第1施工工程の後又は途中に、第1の工区に隣接する第2の工区において、第2の躯体20における少なくとも屋根部23を含む一部分の水平力を第1の躯体20に直接支持させながら、当該一部分を施工する第2先行施工工程と、第2先行施工工程の後に、第2の躯体20における他の一部分の水平力を第1の躯体20に直接支持させながら、当該他の一部分を施工する第2後行施工工程と、を含むので、第1の躯体20を施工した後に第2の躯体20を施工する際に、第2の躯体20の水平力を一方の躯体20に直接支持でき、仮設部材を設ける必要がないことから、建物1の施工性を高めることができる。また、第2の躯体20における屋根部23を含む一部分を先行施工することで、全天候において第2の躯体20における他の一部分を施工でき、建物1の施工性を一層高めることができる。
(Effects of the embodiment)
Thus, according to the embodiment, the construction includes a first construction step of constructing the first structure 20 in the first construction area, a second advance construction step of constructing a portion of the second structure 20 including at least the roof portion 23 while the horizontal force of that portion is directly supported by the first structure 20 in a second construction area adjacent to the first construction area after or during the first construction step, and a second subsequent construction step of constructing another portion of the second structure 20 while the horizontal force of that other portion is directly supported by the first structure 20. Therefore, when the second structure 20 is constructed after the first structure 20, the horizontal force of the second structure 20 can be directly supported by one of the structures 20, and there is no need to provide temporary members, thereby improving the constructability of the building 1. Furthermore, by constructing a portion of the second structure 20 including the roof portion 23 in advance, other portions of the second structure 20 can be constructed in all weather conditions, further improving the constructability of the building 1.

また、第2先行施工工程時において、第1の躯体20は、当該第1の躯体20の水平力及び第2の躯体20の水平力を支持可能に構成されていると共に、当該第1の躯体20の鉛直力を支持可能に構成されており、第2の躯体20における一部分は、当該一部分の水平力を支持不能に構成されていると共に、当該一部分の鉛直力を支持可能に構成されているので、第2の躯体20の一部分を施工する際に、第1の躯体20が第2の躯体20の一部分の水平力を確実に支持でき、第2の躯体20の一部分を安定して施工することができる。また、第2の躯体20の一部分の強度を過大に設定することを回避でき、第2の躯体20の一部分の製造性を維持できる。 In addition, during the second advance construction process, the first body 20 is configured to be able to support the horizontal force of the first body 20 and the horizontal force of the second body 20, and is configured to be able to support the vertical force of the first body 20, and a portion of the second body 20 is configured to be unable to support the horizontal force of the portion, but is configured to be able to support the vertical force of the portion. Therefore, when constructing a portion of the second body 20, the first body 20 can reliably support the horizontal force of the portion of the second body 20, and the portion of the second body 20 can be stably constructed. In addition, it is possible to avoid setting the strength of a portion of the second body 20 to be excessive, and the manufacturability of the portion of the second body 20 can be maintained.

また、第2先行施工工程の前に、第1の躯体20を補強するための補強材30を当該第1の躯体20に設ける補強工程を含むので、第1の躯体20を補強することができ、第2の躯体20を施工する際に第2の躯体20を安定して支持できる。 In addition, the method includes a reinforcing step of providing the first structure 20 with reinforcing material 30 prior to the second preliminary construction step, so that the first structure 20 can be reinforced and the second structure 20 can be stably supported when the second structure 20 is constructed.

〔III〕実施の形態に対する変形例
以上、本発明の実施の形態について説明したが、本発明の具体的な構成及び手段は、特許請求の範囲に記載した各発明の技術的思想の範囲内において、任意に改変及び改良することができる。以下、このような変形例について説明する。
[III] Modifications to the embodiment The embodiment of the present invention has been described above, but the specific configuration and means of the present invention can be modified and improved as desired within the scope of the technical ideas of each invention described in the claims. Such modifications will be described below.

(解決しようとする課題や発明の効果について)
まず、発明が解決しようとする課題や発明の効果は、前記した内容に限定されるものではなく、本発明によって、前記に記載されていない課題を解決することや、前記に記載されていない効果を奏することもできる。また、記載されている課題の一部のみを解決することや、記載されている効果の一部のみを奏することがある。
(About the problem to be solved and the effects of the invention)
First, the problems to be solved by the invention and the effects of the invention are not limited to those described above, and the present invention may solve problems not described above or achieve effects not described above. Also, the present invention may solve only some of the problems described or achieve only some of the effects described.

(形状、数値、構造、時系列について)
実施の形態や図面において例示した構成要素に関して、形状、数値、又は複数の構成要素の構造若しくは時系列の相互関係については、本発明の技術的思想の範囲内において、任意に改変及び改良することができる。
(shape, number, structure, time series)
The components illustrated in the embodiments and drawings may be modified and improved as desired within the scope of the technical concept of the present invention with respect to the shape, numerical values, or structure or chronological relationships of multiple components.

(建物について)
上記実施の形態では、床部22が、コンクリート製であると説明したが、これに限らず、例えば、非コンクリート製(一例として、鋼製)であってもよい。
(About the building)
In the above embodiment, the floor portion 22 is described as being made of concrete, but the present invention is not limited to this and may be made of a material other than concrete (for example, steel).

また、上記実施の形態では、建物1が補強材30を備えていると説明したが、これに限らず、例えば、各躯体20の施工時に各躯体20の強度を確保できる場合には、補強材30を省略してもよい。この場合には、建物1の施工方法のうち、第2工区施工工程、第2工区第4工区間施工工程、及び第3工区第4工区間施工工程において行われる補強工程を省略してもよい。 In the above embodiment, the building 1 is described as being equipped with reinforcing material 30, but this is not limiting. For example, if the strength of each structure 20 can be ensured during construction of each structure 20, the reinforcing material 30 may be omitted. In this case, the reinforcing process performed in the second construction section construction process, the second construction section fourth construction process, and the third construction section fourth construction process in the construction method of building 1 may be omitted.

(施工領域について)
上記実施の形態では、施工領域が4つの工区(第1工区2aから第4工区2d)に区分けされていると説明したが、これに限らない。例えば、2つの工区又は3つの工区に区分けされてもよく、あるいは、5つ以上の工区に区分けされてもよい。
(About the construction area)
In the above embodiment, the construction area is divided into four sections (the first section 2a to the fourth section 2d), but this is not limited thereto. For example, the construction area may be divided into two or three sections, or may be divided into five or more sections.

また、上記実施の形態では、第1工区2aから第4工区2dの各々が5つの工区(A工区3aからE工区3e)にさらに区分けされていると説明したが、これに限らない。例えば、5つ未満の工区に区分けされてもよく、あるいは、6つ以上の工区に区分けされてもよい。 In the above embodiment, each of the first work section 2a to the fourth work section 2d is further divided into five work sections (work section A 3a to work section E 3e), but this is not limited to the above. For example, the work sections may be divided into less than five work sections, or into six or more work sections.

(建物の施工方法について)
上記実施の形態では、建物1の施工方法が、仕上工程を含むと説明したが、これに限らず、例えば、仕上工程を省略してもよい。
(About the building construction method)
In the above embodiment, the construction method for the building 1 has been described as including the finishing process, but this is not limiting, and for example, the finishing process may be omitted.

また、上記実施の形態では、建物1の施工方法において最先に施工される工区が、第1工区2aであると説明したが、これに限らず、例えば、第1工区2a以外の工区(例えば、第2工区2bから第4工区2dのいずれか)であってもよい。 In addition, in the above embodiment, it has been explained that the section to be constructed first in the construction method for building 1 is the first section 2a, but this is not limited thereto, and it may be, for example, a section other than the first section 2a (for example, any of the second section 2b to the fourth section 2d).

また、上記実施の形態では、第2工区施工工程が、第1工区施工工程の後に行われると説明したが、これに限らず、例えば、第1工区施工工程の途中に行われもよく、一例として、第1躯体20aの床部22を設置する前に行われてもよい。 In addition, in the above embodiment, it has been described that the second section construction process is carried out after the first section construction process, but this is not limited thereto, and for example, it may be carried out during the first section construction process, or, as one example, it may be carried out before the floor section 22 of the first structure 20a is installed.

また、上記実施の形態では、第2工区施工工程において、第2躯体20bの梁部25を第2躯体20bの柱部24に対して仮固定し、且つ第1躯体20aの梁部25又は柱部24に対して仮固定すると説明したが、これに限らず、例えば、第2躯体20bの梁部25を第2躯体20bの柱部24に対して本固定し、且つ第1躯体20aの梁部25又は柱部24に対して本固定してもよい(なお、第2工区第4工区間施工工程、及び第3工区第4工区間施工工程についても略同様とする)。 In the above embodiment, in the second work section construction process, the beam 25 of the second structure 20b is temporarily fixed to the column 24 of the second structure 20b, and is also temporarily fixed to the beam 25 or column 24 of the first structure 20a. However, this is not limited to the above, and for example, the beam 25 of the second structure 20b may be permanently fixed to the column 24 of the second structure 20b, and is also permanently fixed to the beam 25 or column 24 of the first structure 20a (note that the same applies to the second work section fourth work section construction process and the third work section fourth work section construction process).

また、上記実施の形態では、第2工区第4工区間施工工程において、第4躯体20dのD工区3dの一部分を施工すると説明したが、これに限らず、例えば、第4躯体20dを安定して施工できる場合には、第4躯体20dのD工区3dの一部分を施工することを省略してもよい。この場合には、第3工区第4工区間施工工程において、第4躯体20dのA工区3aからE工区3eの一部分を施工した後に、第4工区施工工程において、第4躯体20dのA工区3aからE工区3eの他の一部分を施工してもよい。 In the above embodiment, it has been described that a portion of section D 3d of the fourth structure 20d is constructed in the construction process of the fourth section of the second structure. However, this is not limited to the above. For example, if the fourth structure 20d can be constructed stably, construction of a portion of section D 3d of the fourth structure 20d may be omitted. In this case, after a portion of sections A 3a to E 3e of the fourth structure 20d is constructed in the construction process of the fourth section of the third structure, another portion of sections A 3a to E 3e of the fourth structure 20d may be constructed in the construction process of the fourth section.

また、上記実施の形態では、第2工区第4工区間施工工程における第3躯体20cの施工時においては、第2躯体20bが、特許請求の範囲における「第1の躯体」に対応すると説明したが、これに限らず、例えば、第1躯体20a及び第2躯体20bは、特許請求の範囲における「第1の躯体」に対応してもよい。この場合には、第1躯体20a及び第2躯体20bは、第2躯体20bの水平力及び第3躯体20cの水平力を支持可能に構成されてもよい(なお、第2工区第4工区間施工工程における第4躯体20dの施工時、及び、第3工区第4工区間施工工程における第4躯体20dのD工区3d以外の工区の一部分の施工時についても略同様とする)。 In the above embodiment, the second structure 20b corresponds to the "first structure" in the claims during the construction of the third structure 20c in the construction process of the fourth section of the second section. However, this is not limited to the above, and for example, the first structure 20a and the second structure 20b may correspond to the "first structure" in the claims. In this case, the first structure 20a and the second structure 20b may be configured to support the horizontal force of the second structure 20b and the horizontal force of the third structure 20c (note that the same applies to the construction of the fourth structure 20d in the construction process of the fourth section of the second section and the construction of a part of the section other than section D 3d of the fourth structure 20d in the construction process of the fourth section of the third section).

(付記)
付記1の建物の施工方法は、建物を複数の工区に分割して施工するための施工方法であって、第1の工区において、前記建物を構成する第1の躯体を施工する第1施工工程と、前記第1施工工程の後又は途中に、前記第1の工区に隣接する第2の工区において、前記建物を構成する第2の躯体における少なくとも屋根部を含む一部分の水平力を前記第1の躯体に直接支持させながら、当該一部分を施工する第2先行施工工程と、前記第2先行施工工程の後に、前記第2の躯体における他の一部分の水平力を前記第1の躯体に直接支持させながら、当該他の一部分を施工する第2後行施工工程と、を含む。
(Additional Note)
The construction method of a building in Appendix 1 is a construction method for dividing a building into a plurality of work sections and constructing the same, and includes a first construction step of constructing a first structure constituting the building in a first work section, a second advance construction step of constructing a second structure constituting the building in a second work section adjacent to the first work section after or during the first construction step, while having the first structure directly support the horizontal force of a portion of the second structure including at least a roof portion, and a second subsequent construction step of constructing another portion of the second structure after the second advance construction step, while having the first structure directly support the horizontal force of the other portion.

付記2の建物の施工方法は、付記1に記載の建物の施工方法において、前記第2先行施工工程時において、前記第1の躯体は、当該第1の躯体の水平力及び前記第2の躯体の水平力を支持可能に構成されていると共に、当該第1の躯体の鉛直力を支持可能に構成されており、前記第2の躯体における前記一部分は、当該一部分の水平力を支持不能に構成されていると共に、当該一部分の鉛直力を支持可能に構成されている。 The building construction method of Appendix 2 is the building construction method described in Appendix 1, in which, during the second advance construction step, the first structure is configured to be able to support the horizontal force of the first structure and the horizontal force of the second structure, and is configured to be able to support the vertical force of the first structure, and the portion of the second structure is configured to be unable to support the horizontal force of the portion, and is configured to be able to support the vertical force of the portion.

付記3の建物の施工方法は、付記1又は2に記載の建物の施工方法において、前記第2先行施工工程の前に、前記第1の躯体を補強するための補強材を当該第1の躯体に設ける補強工程を含む。 The building construction method of Appendix 3 is the building construction method described in Appendix 1 or 2, which includes a reinforcing step of providing a reinforcing material for reinforcing the first structure to the first structure prior to the second advance construction step.

(付記の効果)
付記1に記載の建物の施工方法によれば、第1の工区において、第1の躯体を施工する第1施工工程と、第1施工工程の後又は途中に、第1の工区に隣接する第2の工区において、第2の躯体における少なくとも屋根部を含む一部分の水平力を第1の躯体に直接支持させながら、当該一部分を施工する第2先行施工工程と、第2先行施工工程の後に、第2の躯体における他の一部分の水平力を第1の躯体に直接支持させながら、当該他の一部分を施工する第2後行施工工程と、を含むので、第1の躯体を施工した後に第2の躯体を施工する際に、第2の躯体の水平力を一方の躯体に直接支持でき、仮設部材を設ける必要がないことから、建物の施工性を高めることができる。また、第2の躯体における屋根部を含む一部分を先行施工することで、全天候において第2の躯体における他の一部分を施工でき、建物の施工性を一層高めることができる。
(Effect of supplementary notes)
According to the construction method of the building described in Appendix 1, the method includes a first construction step of constructing the first structure in the first construction area, a second preceding construction step of constructing at least a part of the second structure including the roof portion in the second construction area adjacent to the first construction area after or during the first construction step while the horizontal force of the part is directly supported by the first structure, and a second following construction step of constructing another part of the second structure while the horizontal force of the other part is directly supported by the first structure after the second preceding construction step. Therefore, when constructing the second structure after constructing the first structure, the horizontal force of the second structure can be directly supported by one of the structures, and there is no need to provide temporary members, which improves the constructability of the building. In addition, by constructing a part of the second structure including the roof portion in advance, the other part of the second structure can be constructed in all weather conditions, which further improves the constructability of the building.

付記2に記載の建物の施工方法によれば、第2先行施工工程時において、第1の躯体は、当該第1の躯体の水平力及び第2の躯体の水平力を支持可能に構成されていると共に、当該第1の躯体の鉛直力を支持可能に構成されており、第2の躯体における一部分は、当該一部分の水平力を支持不能に構成されていると共に、当該一部分の鉛直力を支持可能に構成されているので、第2の躯体の一部分を施工する際に、第1の躯体が第2の躯体の一部分の水平力を確実に支持でき、第2の躯体の一部分を安定して施工することができる。また、第2の躯体の一部分の強度を過大に設定することを回避でき、第2の躯体の一部分の製造性を維持できる。 According to the building construction method described in Appendix 2, during the second advance construction process, the first structure is configured to be able to support the horizontal force of the first structure and the horizontal force of the second structure, and is configured to be able to support the vertical force of the first structure, and a portion of the second structure is configured to be unable to support the horizontal force of the portion, but is configured to be able to support the vertical force of the portion. Therefore, when constructing a portion of the second structure, the first structure can reliably support the horizontal force of the portion of the second structure, and the portion of the second structure can be constructed stably. In addition, it is possible to avoid setting the strength of the portion of the second structure to be excessive, and the manufacturability of the portion of the second structure can be maintained.

付記3に記載の建物の施工方法によれば、第2先行施工工程の前に、第1の躯体を補強するための補強材を当該第1の躯体に設ける補強工程を含むので、第1の躯体を補強することができ、第2の躯体を施工する際に第2の躯体を安定して支持できる。 According to the building construction method described in Appendix 3, a reinforcing step is included in which a reinforcing material is provided on the first structure prior to the second advance construction step, so that the first structure can be reinforced and the second structure can be stably supported when the second structure is constructed.

1 建物
2a 第1工区
2b 第2工区
2c 第3工区
2d 第4工区
3a A工区
3b B工区
3c C工区
3d D工区
3e E工区
10 通行設備
20 躯体
20a 第1躯体
20b 第2躯体
20c 第3躯体
20d 第4躯体
21 階層
21a 第1階層
21b 第2階層
21c 第3階層
21d 第4階層
22 床部
22a 第1床部
22b 第2床部
22c 第3床部
22d 第4床部
23 屋根部
24 柱部
24a 第1柱部
24b 第2柱部
24c 第3柱部
24d 第4柱部
25 梁部
25a 第1梁部
25b 第2梁部
25c 第3梁部
25d 第4梁部
26 壁部
26a 第1壁部
26b 第2壁部
26c 第3壁部
26d 第4壁部
30 補強材
LIST OF SYMBOLS 1 Building 2a First work area 2b Second work area 2c Third work area 2d Fourth work area 3a A work area 3b B work area 3c C work area 3d D work area 3e E work area 10 Access facility 20 Structure 20a First structure 20b Second structure 20c Third structure 20d Fourth structure 21 Story 21a First story 21b Second story 21c Third story 21d Fourth story 22 Floor 22a First floor 22b Second floor 22c Third floor 22d Fourth floor 23 Roof 24 Column 24a First column 24b Second column 24c Third column 24d Fourth column 25 Beam 25a First beam 25b Second beam portion 25c Third beam portion 25d Fourth beam portion 26 Wall portion 26a First wall portion 26b Second wall portion 26c Third wall portion 26d Fourth wall portion 30 Reinforcement material

Claims (4)

建物を複数の工区に分割して施工するための施工方法であって、
第1の工区において、前記建物を構成する第1の躯体を施工する第1施工工程と、
前記第1施工工程の後又は途中に、前記第1の工区に隣接する第2の工区において、前記建物を構成する第2の躯体における少なくとも屋根部を含む一部分の水平力を前記第1の躯体に直接支持させながら、当該一部分を施工する第2先行施工工程と、
前記第2先行施工工程の後に、前記第2の躯体における他の一部分の水平力を前記第1の躯体に直接支持させながら、当該他の一部分を施工する第2後行施工工程と、を含み、
前記第2先行施工工程においては、前記第2の躯体の前記一部分に含まれる梁部を当該一部分に含まれる柱部に対して仮固定し、且つ前記第1の躯体に含まれる梁部又は柱部に対して仮固定し、
前記第2後行施工工程においては、前記第2の躯体の前記一部分に含まれる梁部を当該一部分に含まれる柱部に対して本固定し、且つ前記第1の躯体に含まれる梁部又は柱部に対して本固定する、
建物の施工方法。
A construction method for dividing a building into multiple work sections and constructing it,
A first construction step of constructing a first skeleton constituting the building in a first construction section;
A second advance construction process, which is performed after or during the first construction process, in a second construction area adjacent to the first construction area, to construct a portion of a second structure constituting the building, including at least a roof portion, while having the first structure directly support the horizontal force of the portion;
A second subsequent construction step of constructing another part of the second structure while directly supporting the horizontal force of the other part on the first structure after the second preceding construction step ,
In the second advance construction step, a beam portion included in the portion of the second structure is temporarily fixed to a column portion included in the portion, and is temporarily fixed to a beam portion or a column portion included in the first structure;
In the second subsequent construction step, a beam portion included in the portion of the second structure is fixed to a column portion included in the portion, and is fixed to a beam portion or a column portion included in the first structure.
Building construction methods.
建物を複数の工区に分割して施工するための施工方法であって、
第1の工区において、前記建物を構成する第1の躯体を施工する第1施工工程と、
前記第1施工工程の後又は途中に、前記第1の工区に隣接する第2の工区において、前記建物を構成する第2の躯体における少なくとも屋根部を含む一部分の水平力を前記第1の躯体に直接支持させながら、当該一部分を施工する第2先行施工工程と、
前記第2先行施工工程の後に、前記第2の躯体における他の一部分の水平力を前記第1の躯体に直接支持させながら、当該他の一部分を施工する第2後行施工工程と、を含み、
前記複数の工区のうち、車両が前記建物内を出入りするための通行設備と隣接する工区を最先に施工する、
建物の施工方法。
A construction method for dividing a building into multiple work sections and constructing it,
A first construction step of constructing a first skeleton constituting the building in a first construction section;
A second advance construction process, which is performed after or during the first construction process, in a second construction area adjacent to the first construction area, to construct a portion of a second structure constituting the building, including at least a roof portion, while having the first structure directly support the horizontal force of the portion;
A second subsequent construction step of constructing another part of the second structure while directly supporting the horizontal force of the other part on the first structure after the second preceding construction step,
Among the plurality of work sections, a work section adjacent to a passage facility for vehicles to enter and exit the building is constructed first.
Building construction methods.
前記第2先行施工工程時において、
前記第1の躯体は、当該第1の躯体の水平力及び前記第2の躯体の水平力を支持可能に構成されていると共に、当該第1の躯体の鉛直力を支持可能に構成されており、
前記第2の躯体における前記一部分は、当該一部分の水平力を支持不能に構成されていると共に、当該一部分の鉛直力を支持可能に構成されている、
請求項1又は2に記載の建物の施工方法。
During the second advance construction step,
The first body is configured to be able to support a horizontal force of the first body and a horizontal force of the second body, and is configured to be able to support a vertical force of the first body,
The portion of the second body is configured to be unable to support a horizontal force of the portion and to be able to support a vertical force of the portion.
A method for constructing a building according to claim 1 or 2.
前記第2先行施工工程の前に、前記第1の躯体を補強するための補強材を当該第1の躯体に設ける補強工程を含む、A reinforcing step of providing a reinforcing material for reinforcing the first structure to the first structure prior to the second advance construction step,
請求項1から3のいずれか一項に記載の建物の施工方法。A method for constructing a building according to any one of claims 1 to 3.
JP2020068945A 2020-04-07 2020-04-07 Building Construction Method Active JP7502886B2 (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
JP2020068945A JP7502886B2 (en) 2020-04-07 2020-04-07 Building Construction Method

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
JP2020068945A JP7502886B2 (en) 2020-04-07 2020-04-07 Building Construction Method

Publications (2)

Publication Number Publication Date
JP2021165479A JP2021165479A (en) 2021-10-14
JP7502886B2 true JP7502886B2 (en) 2024-06-19

Family

ID=78021756

Family Applications (1)

Application Number Title Priority Date Filing Date
JP2020068945A Active JP7502886B2 (en) 2020-04-07 2020-04-07 Building Construction Method

Country Status (1)

Country Link
JP (1) JP7502886B2 (en)

Citations (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP2001311312A (en) 2000-04-27 2001-11-09 Fudo Kenken Kk Method for constructing building built by pc applied to narrow and small lot
JP2010265596A (en) 2009-05-12 2010-11-25 Takenaka Komuten Co Ltd Construction method for structure
JP2017115495A (en) 2015-12-25 2017-06-29 株式会社竹中工務店 Construction method

Patent Citations (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP2001311312A (en) 2000-04-27 2001-11-09 Fudo Kenken Kk Method for constructing building built by pc applied to narrow and small lot
JP2010265596A (en) 2009-05-12 2010-11-25 Takenaka Komuten Co Ltd Construction method for structure
JP2017115495A (en) 2015-12-25 2017-06-29 株式会社竹中工務店 Construction method

Also Published As

Publication number Publication date
JP2021165479A (en) 2021-10-14

Similar Documents

Publication Publication Date Title
HUT58843A (en) Space-limiting structure
KR101614842B1 (en) frame system of buildings using the pc-column with overhanging beam applicable various span without increase of story-height
KR200414349Y1 (en) Connection structure of precast concrete structure
KR100771144B1 (en) Extension work method by constructing multi-lavers synchronously
US8505599B2 (en) Panelization system and method
JP7502886B2 (en) Building Construction Method
JP3261255B2 (en) Shell roof lift-up method
EA007023B1 (en) Reinforced concrete frame of multistorey building
JPH10159344A (en) Building method of multi-layered structure provided with a plurality of super beam
JP6690150B2 (en) Beam-column structure of plate-like apartment house
JP7051113B2 (en) Building construction method
JPS6314937A (en) Reinforcing bar composite pillar
JP2002167901A (en) Trussed girder and its construction method
CA2639339A1 (en) Method of constructing a multi-storey building using prefabricated modular panels
JP4445366B2 (en) Reinforcement method for tower crane mount
JPH04368528A (en) Frame construction using void beam
JP7377709B2 (en) Floor construction method
JP7053436B2 (en) Work floor and how to use the work floor
JPH0681463A (en) Building method for stair
JP7500408B2 (en) Pre-construction method for interior stairs of buildings
JP7462475B2 (en) How to build a building
KR20220133052A (en) Construction method capable of simultaneous pouring of multi-story walls and slab mortar of a building
JPH07279247A (en) Skeleton of building consisting of concrete core wall and structural steel frame
JP2023022563A (en) Concrete wall construction method
CN118313031A (en) BIM-based construction analysis method and structure for fully assembled concrete frame structure

Legal Events

Date Code Title Description
A621 Written request for application examination

Free format text: JAPANESE INTERMEDIATE CODE: A621

Effective date: 20230330

A977 Report on retrieval

Free format text: JAPANESE INTERMEDIATE CODE: A971007

Effective date: 20231225

A131 Notification of reasons for refusal

Free format text: JAPANESE INTERMEDIATE CODE: A131

Effective date: 20240109

A521 Request for written amendment filed

Free format text: JAPANESE INTERMEDIATE CODE: A523

Effective date: 20240219

TRDD Decision of grant or rejection written
A01 Written decision to grant a patent or to grant a registration (utility model)

Free format text: JAPANESE INTERMEDIATE CODE: A01

Effective date: 20240604

A61 First payment of annual fees (during grant procedure)

Free format text: JAPANESE INTERMEDIATE CODE: A61

Effective date: 20240607

R150 Certificate of patent or registration of utility model

Ref document number: 7502886

Country of ref document: JP

Free format text: JAPANESE INTERMEDIATE CODE: R150