JP7126111B2 - Offshore work equipment and its manufacturing method - Google Patents

Offshore work equipment and its manufacturing method Download PDF

Info

Publication number
JP7126111B2
JP7126111B2 JP2020506597A JP2020506597A JP7126111B2 JP 7126111 B2 JP7126111 B2 JP 7126111B2 JP 2020506597 A JP2020506597 A JP 2020506597A JP 2020506597 A JP2020506597 A JP 2020506597A JP 7126111 B2 JP7126111 B2 JP 7126111B2
Authority
JP
Japan
Prior art keywords
deck
offshore
main deck
equipment
offshore work
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Active
Application number
JP2020506597A
Other languages
Japanese (ja)
Other versions
JPWO2019177010A1 (en
Inventor
桂資 枝光
成樹 吉田
訓 大野
正人 川上
哲也 安田
結花 北小路
高典 山口
啓彰 前田
健一 久保
浩三 石田
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
YOSHIDA GUMI CO., LTD.
Japan Drilling Co Ltd
Japan Marine United Corp
Original Assignee
YOSHIDA GUMI CO., LTD.
Japan Drilling Co Ltd
Japan Marine United Corp
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by YOSHIDA GUMI CO., LTD., Japan Drilling Co Ltd, Japan Marine United Corp filed Critical YOSHIDA GUMI CO., LTD.
Publication of JPWO2019177010A1 publication Critical patent/JPWO2019177010A1/en
Priority to JP2022119402A priority Critical patent/JP7464658B2/en
Application granted granted Critical
Publication of JP7126111B2 publication Critical patent/JP7126111B2/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Images

Classifications

    • BPERFORMING OPERATIONS; TRANSPORTING
    • B63SHIPS OR OTHER WATERBORNE VESSELS; RELATED EQUIPMENT
    • B63BSHIPS OR OTHER WATERBORNE VESSELS; EQUIPMENT FOR SHIPPING 
    • B63B35/00Vessels or similar floating structures specially adapted for specific purposes and not otherwise provided for
    • B63B35/44Floating buildings, stores, drilling platforms, or workshops, e.g. carrying water-oil separating devices
    • BPERFORMING OPERATIONS; TRANSPORTING
    • B63SHIPS OR OTHER WATERBORNE VESSELS; RELATED EQUIPMENT
    • B63BSHIPS OR OTHER WATERBORNE VESSELS; EQUIPMENT FOR SHIPPING 
    • B63B11/00Interior subdivision of hulls
    • B63B11/02Arrangement of bulkheads, e.g. defining cargo spaces
    • BPERFORMING OPERATIONS; TRANSPORTING
    • B63SHIPS OR OTHER WATERBORNE VESSELS; RELATED EQUIPMENT
    • B63BSHIPS OR OTHER WATERBORNE VESSELS; EQUIPMENT FOR SHIPPING 
    • B63B27/00Arrangement of ship-based loading or unloading equipment for cargo or passengers
    • B63B27/10Arrangement of ship-based loading or unloading equipment for cargo or passengers of cranes
    • BPERFORMING OPERATIONS; TRANSPORTING
    • B63SHIPS OR OTHER WATERBORNE VESSELS; RELATED EQUIPMENT
    • B63BSHIPS OR OTHER WATERBORNE VESSELS; EQUIPMENT FOR SHIPPING 
    • B63B3/00Hulls characterised by their structure or component parts
    • B63B3/14Hull parts
    • B63B3/48Decks
    • BPERFORMING OPERATIONS; TRANSPORTING
    • B63SHIPS OR OTHER WATERBORNE VESSELS; RELATED EQUIPMENT
    • B63BSHIPS OR OTHER WATERBORNE VESSELS; EQUIPMENT FOR SHIPPING 
    • B63B35/00Vessels or similar floating structures specially adapted for specific purposes and not otherwise provided for
    • B63B35/003Vessels or similar floating structures specially adapted for specific purposes and not otherwise provided for for transporting very large loads, e.g. offshore structure modules
    • BPERFORMING OPERATIONS; TRANSPORTING
    • B63SHIPS OR OTHER WATERBORNE VESSELS; RELATED EQUIPMENT
    • B63BSHIPS OR OTHER WATERBORNE VESSELS; EQUIPMENT FOR SHIPPING 
    • B63B77/00Transporting or installing offshore structures on site using buoyancy forces, e.g. using semi-submersible barges, ballasting the structure or transporting of oil-and-gas platforms
    • B63B77/10Transporting or installing offshore structures on site using buoyancy forces, e.g. using semi-submersible barges, ballasting the structure or transporting of oil-and-gas platforms specially adapted for electric power plants, e.g. wind turbines or tidal turbine generators
    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02BHYDRAULIC ENGINEERING
    • E02B17/00Artificial islands mounted on piles or like supports, e.g. platforms on raisable legs or offshore constructions; Construction methods therefor
    • FMECHANICAL ENGINEERING; LIGHTING; HEATING; WEAPONS; BLASTING
    • F03MACHINES OR ENGINES FOR LIQUIDS; WIND, SPRING, OR WEIGHT MOTORS; PRODUCING MECHANICAL POWER OR A REACTIVE PROPULSIVE THRUST, NOT OTHERWISE PROVIDED FOR
    • F03DWIND MOTORS
    • F03D13/00Assembly, mounting or commissioning of wind motors; Arrangements specially adapted for transporting wind motor components
    • F03D13/10Assembly of wind motors; Arrangements for erecting wind motors
    • F03D13/126Offshore
    • FMECHANICAL ENGINEERING; LIGHTING; HEATING; WEAPONS; BLASTING
    • F03MACHINES OR ENGINES FOR LIQUIDS; WIND, SPRING, OR WEIGHT MOTORS; PRODUCING MECHANICAL POWER OR A REACTIVE PROPULSIVE THRUST, NOT OTHERWISE PROVIDED FOR
    • F03DWIND MOTORS
    • F03D13/00Assembly, mounting or commissioning of wind motors; Arrangements specially adapted for transporting wind motor components
    • F03D13/20Arrangements for mounting or supporting wind motors; Masts or towers for wind motors
    • F03D13/25Arrangements for mounting or supporting wind motors; Masts or towers for wind motors specially adapted for offshore installation
    • FMECHANICAL ENGINEERING; LIGHTING; HEATING; WEAPONS; BLASTING
    • F05INDEXING SCHEMES RELATING TO ENGINES OR PUMPS IN VARIOUS SUBCLASSES OF CLASSES F01-F04
    • F05BINDEXING SCHEME RELATING TO WIND, SPRING, WEIGHT, INERTIA OR LIKE MOTORS, TO MACHINES OR ENGINES FOR LIQUIDS COVERED BY SUBCLASSES F03B, F03D AND F03G
    • F05B2230/00Manufacture
    • F05B2230/60Assembly methods
    • F05B2230/61Assembly methods using auxiliary equipment for lifting or holding
    • F05B2230/6102Assembly methods using auxiliary equipment for lifting or holding carried on a floating platform
    • FMECHANICAL ENGINEERING; LIGHTING; HEATING; WEAPONS; BLASTING
    • F05INDEXING SCHEMES RELATING TO ENGINES OR PUMPS IN VARIOUS SUBCLASSES OF CLASSES F01-F04
    • F05BINDEXING SCHEME RELATING TO WIND, SPRING, WEIGHT, INERTIA OR LIKE MOTORS, TO MACHINES OR ENGINES FOR LIQUIDS COVERED BY SUBCLASSES F03B, F03D AND F03G
    • F05B2240/00Components
    • F05B2240/90Mounting on supporting structures or systems
    • F05B2240/95Mounting on supporting structures or systems offshore
    • YGENERAL TAGGING OF NEW TECHNOLOGICAL DEVELOPMENTS; GENERAL TAGGING OF CROSS-SECTIONAL TECHNOLOGIES SPANNING OVER SEVERAL SECTIONS OF THE IPC; TECHNICAL SUBJECTS COVERED BY FORMER USPC CROSS-REFERENCE ART COLLECTIONS [XRACs] AND DIGESTS
    • Y02TECHNOLOGIES OR APPLICATIONS FOR MITIGATION OR ADAPTATION AGAINST CLIMATE CHANGE
    • Y02EREDUCTION OF GREENHOUSE GAS [GHG] EMISSIONS, RELATED TO ENERGY GENERATION, TRANSMISSION OR DISTRIBUTION
    • Y02E10/00Energy generation through renewable energy sources
    • Y02E10/70Wind energy
    • Y02E10/727Offshore wind turbines

Landscapes

  • Engineering & Computer Science (AREA)
  • Mechanical Engineering (AREA)
  • Combustion & Propulsion (AREA)
  • Chemical & Material Sciences (AREA)
  • Ocean & Marine Engineering (AREA)
  • General Engineering & Computer Science (AREA)
  • Civil Engineering (AREA)
  • Structural Engineering (AREA)
  • Sustainable Development (AREA)
  • Sustainable Energy (AREA)
  • Life Sciences & Earth Sciences (AREA)
  • Architecture (AREA)
  • Transportation (AREA)
  • Wind Motors (AREA)
  • Water Supply & Treatment (AREA)
  • Jib Cranes (AREA)
  • Golf Clubs (AREA)
  • Materials For Medical Uses (AREA)
  • Earth Drilling (AREA)

Description

本発明は、洋上風力発電設備等の洋上設備の建設に用いることのできる洋上作業設備およびその製造方法に関する。 TECHNICAL FIELD The present invention relates to offshore working equipment that can be used for constructing offshore equipment such as offshore wind power generation equipment, and a manufacturing method thereof.

自然エネルギー有効活用の観点から、洋上風力発電が注目されている。 From the viewpoint of effective utilization of natural energy, offshore wind power generation is attracting attention.

洋上風力発電設備の建設には、自己昇降式作業台船(SEP)といった洋上作業設備が用いられることが多い。自己昇降式作業台船は、通常、複数の脚柱と、これら脚柱に昇降自在に支持されたデッキとを有する(特許文献1、特許文献2)。デッキには作業用のクレーンが搭載され、このクレーンを用いて洋上風力発電設備の組み立てが行われる。また、デッキは、洋上風力発電設備の各種部品の荷役スペースなどとして利用することもできる。 Offshore work equipment such as a self-elevating work barge (SEP) is often used for the construction of offshore wind power generation facilities. A self-elevating work barge usually has a plurality of pedestals and a deck supported by these pedestals so that they can be raised and lowered (Patent Document 1, Patent Document 2). A work crane is mounted on the deck, and offshore wind power generation equipment is assembled using this crane. The deck can also be used as a cargo handling space for various parts of the offshore wind power generation facility.

特許文献1:特開2015-37925号公報
特許文献2:特開2016-215937号公報
Patent Document 1: JP-A-2015-37925 Patent Document 2: JP-A-2016-215937

近年、洋上風力発電設備として、例えば6MW以上の大出力の洋上風力発電設備が開発されており、それに伴って、洋上風力発電設備のサイズ自体が大型化するとともに、着床式に加えて浮体式設備が開発・実用化される流れとなっている。前述したとおり、洋上作業設備のデッキは、作業用のクレーンが搭載され、また各種部品の荷役スペースなどとしても利用される。よって、大型の洋上風力発電設備を施工するためには、より大型のデッキを有する洋上作業設備が必要となる。また、浮体式風力設備を施工するためには、水深が90mを越える海域でも安定して作業できる洋上作業設備が必要となる。 In recent years, as offshore wind power generation equipment, for example, offshore wind power generation equipment with a large output of 6 MW or more has been developed. Equipment is being developed and commercialized. As mentioned above, the deck of the offshore work equipment is equipped with a working crane and is also used as a cargo handling space for various parts. Therefore, in order to construct a large offshore wind power generation facility, offshore work equipment having a larger deck is required. In addition, in order to construct floating wind turbines, it is necessary to have offshore work equipment that can stably work even in areas where the water depth exceeds 90m.

水深が90mを越える海域での洋上施工には、既存の自己昇降式作業台船で使用できるものがないため、通常は大型浮体式クレーンを使用するが、波による影響を受けやすく、作業待機期間が発生するなど作業効率低下が生じやすい。一方、大型のデッキを有する洋上作業設備は、港湾から洋上設備の建設現場である海域までの曳航速度の低下を招く。曳航速度の低下は、洋上設備の工期の長期化の原因となる。 For offshore construction in areas where the water depth exceeds 90m, there is no existing self-elevating work barge that can be used, so a large floating crane is usually used, but it is easily affected by waves and has a waiting period for work. It is easy to cause a decrease in work efficiency, such as the occurrence of On the other hand, the offshore work equipment having a large deck causes a reduction in the towing speed from the harbor to the sea area where the offshore equipment is to be constructed. Decrease in towing speed causes the construction period of offshore facilities to be prolonged.

そこで本発明は、深海域でも安定した作業が可能であり、かつ、作業効率を向上させ得る洋上作業設備およびその製造方法を提供することを目的の一つとする。 SUMMARY OF THE INVENTION Accordingly, it is an object of the present invention to provide an offshore work facility and a method of manufacturing the same that enable stable work even in deep sea areas and improve work efficiency.

本発明の洋上作業設備は、
3本以上の脚柱と、
浮体構造物として構成され、前記脚柱に対して昇降可能に支持されたデッキと、
前記デッキに搭載されたクレーンと、
を有し、
前記デッキは、前記脚柱が配置されるメインデッキ部と、前記メインデッキ部から張り出して形成された張り出し部と、を有する洋上作業設備であって、
前記洋上作業設備は、前記メインデッキ部および前記脚柱を有する既存のジャッキアップ式掘削リグに前記張り出し部および前記クレーンを付加することによって構成され、
前記張り出し部は、前記既存のジャッキアップ式掘削リグに搭載されている船上掘削設備のためのカンチレバーの支持構造を利用して、前記メインデッキ部に付加され、
前記クレーンは前記張り出し部に搭載されている。
The offshore work equipment of the present invention is
three or more pedestals;
a deck configured as a floating structure and supported so as to be able to ascend and descend with respect to the pedestal;
a crane mounted on the deck;
has
The deck is an offshore work facility having a main deck portion on which the pedestal is arranged and an overhang portion formed by projecting from the main deck portion,
The offshore work equipment is constructed by adding the overhang and the crane to an existing jack-up drilling rig having the main deck and the pedestals;
the overhang is added to the main deck using a cantilever support structure for shipboard drilling equipment on board the existing jack-up drilling rig;
The crane is mounted on the overhang.

本発明の洋上作業設備の製造方法は、
3本以上の脚柱、前記脚柱が配置され、前記脚柱に対して昇降可能に支持されたメインデッキ部、前記メインデッキ部に支持構造を介して支持されたカンチレバーおよび前記カンチレバーに配置された掘削設備を有するジャッキアップ式掘削リグを用意すること、
前記ジャッキアップ式掘削リグから、前記カンチレバーおよび前記掘削設備を撤去すること、
前記メインデッキ部から張り出して形成された張り出し部を、前記支持構造を利用して前記メインデッキ部に付加すること、および
前記張り出し部にクレーンを搭載する設置することを含む。
The manufacturing method of the offshore work equipment of the present invention comprises:
three or more pedestals, a main deck portion on which the pedestals are arranged and supported so as to be able to move up and down with respect to the pedestals, a cantilever supported by the main deck portion via a support structure, and a cantilever arranged on the cantilever providing a jack-up drilling rig with drilling equipment;
removing the cantilever and the drilling equipment from the jack-up drilling rig;
Adding an overhang formed from the main deck to the main deck using the support structure, and installing a crane on the overhang.

本発明によれば、深海域であっても安定かつ効率的に作業可能な洋上作業設備を提供することができる。また、本発明の洋上作業設備の製造方法によれば、上記洋上作業設備を短期間かつ低コストで製造することができる。 ADVANTAGE OF THE INVENTION According to this invention, the offshore working equipment which can operate stably and efficiently even in a deep-sea area can be provided. Moreover, according to the manufacturing method of the offshore work equipment of the present invention, the offshore work equipment can be manufactured in a short period of time and at low cost.

本発明の一実施形態による洋上作業設備の概略側面図である。1 is a schematic side view of an offshore work facility according to one embodiment of the present invention; FIG. 図1に示す洋上作業設備の概略平面図である。FIG. 2 is a schematic plan view of the offshore working equipment shown in FIG. 1; 図2に示す洋上作業設備において、デッキの内部構造を示す図である。3 is a diagram showing the internal structure of a deck in the offshore work equipment shown in FIG. 2. FIG. 脚柱で囲まれる領域内にクレーンを配置した場合のクレーンの作業範囲を説明する図である。FIG. 4 is a diagram illustrating the working range of a crane when the crane is placed within an area surrounded by pedestals; デッキを複層構造とした本発明の他の形態による洋上作業設備の概略側面図である。FIG. 4 is a schematic side view of an offshore work facility according to another embodiment of the present invention having a multi-layered deck; 図1に示す洋上作業設備の利用形態の一例を説明する図である。FIG. 2 is a diagram illustrating an example of a usage pattern of the offshore work equipment shown in FIG. 1;

図1~図3を参照すると、脚柱10と、脚柱10に支持されたデッキ20と、デッキ20に搭載されたクレーン30とを有する、本発明の一実施形態による洋上作業設備1が示されている。この洋上作業設備1は、例えば洋上風力発電設備などの洋上設備の建設に用いることができる。デッキ20は浮体構造体として構成されており、洋上作業設備1を用いた洋上設備の建設に際し、洋上作業設備1は、タグボートなどの曳航用船舶によって洋上設備の建設現場である海域まで曳航される。 1-3, a offshore work facility 1 according to one embodiment of the present invention is shown having a pedestal 10, a deck 20 supported by the pedestal 10, and a crane 30 mounted on the deck 20. It is This offshore work facility 1 can be used for constructing offshore facilities such as offshore wind power generation facilities. The deck 20 is configured as a floating structure, and when constructing the offshore facility using the offshore work facility 1, the offshore work facility 1 is towed by a towing vessel such as a tugboat to the sea area where the offshore facility is to be constructed. .

脚柱10は、この洋上作業設備1による洋上での作業中に、デッキ20を海面よりも上方で支持するものである。したがって、脚柱10は、下端部を海底に着底させた状態で、デッキ20を海面よりも上方で支持できる長さを有している。洋上作業設備1は、デッキ20を安定して支持するために3本以上の脚柱10を有している。脚柱10の構造は、脚柱10が上記の機能を果たすことができる限り任意であってよく、例えば、洋上作業設備1の一種である自己昇降式作業台船あるいはジャッキアップ式掘削リグに用いられる脚柱の構造など、公知の構造を採用することができる。脚柱10の長さは特に限定されないが、例えば、90mを超える海域での施工時でも脚柱10を着底させて波による影響を受けず安定して施工を行うことができる長さを有することが好ましい。また、脚柱10の断面形状も、特に限定されず、円形や多角形など任意の形状であってよい。 The pedestal 10 supports the deck 20 above the sea surface during work on the sea by the offshore work equipment 1 . Therefore, the pedestal 10 has a length that allows the deck 20 to be supported above the sea surface with the lower end of the pedestal 10 resting on the sea floor. The offshore work equipment 1 has three or more pedestals 10 for stably supporting the deck 20 . The structure of the pedestal 10 may be arbitrary as long as the pedestal 10 can perform the above functions. A known structure such as a structure of a pedestal can be adopted. The length of the pedestal 10 is not particularly limited, but it has a length that allows the pedestal 10 to land on the bottom even during construction in a sea area exceeding 90 m and to stably perform construction without being affected by waves. is preferred. Also, the cross-sectional shape of the pedestal 10 is not particularly limited, and may be any shape such as circular or polygonal.

デッキ20は、昇降機構(不図示)によって脚柱10に対して昇降自在に支持される。昇降機構としては、ラックアンドピニオン機構など任意の機構を用いることができる。洋上作業設備1の曳航時には、この昇降機構を動作させ、脚柱10が着底しないように脚柱10をデッキ20に対して上昇させる。デッキ20は浮体構造体として構成されているので、脚柱10を上昇させることによって洋上作業設備1が海面上に浮かび、この状態で洋上作業設備1を曳航することができる。 The deck 20 is supported so as to be vertically movable with respect to the pedestal 10 by a lifting mechanism (not shown). Any mechanism such as a rack and pinion mechanism can be used as the lifting mechanism. When the offshore work equipment 1 is towed, the elevating mechanism is operated to raise the pedestal 10 relative to the deck 20 so that the pedestal 10 does not reach the bottom. Since the deck 20 is configured as a floating structure, the offshore work equipment 1 floats on the sea surface by raising the pedestal 10, and in this state the offshore work equipment 1 can be towed.

デッキ20は、天壁20a、底壁20bおよび外周壁20cを有し、これによってデッキ20は閉じた内部空間が形成された浮体構造体として構成されている。図2Aに示すように、デッキ20の内部空間は、強度部材である少なくとも1つの隔壁20dによって複数の区画に分けられ、これによって、デッキ20の上面を作業スペースおよび建設する洋上設備の部品搭載用スペースとして利用するのに十分な機械的強度を確保している。 The deck 20 has a ceiling wall 20a, a bottom wall 20b, and an outer peripheral wall 20c, whereby the deck 20 is configured as a floating structure having a closed internal space. As shown in FIG. 2A, the interior space of the deck 20 is divided into a plurality of compartments by at least one bulkhead 20d, which is a strength member, so that the upper surface of the deck 20 is used as a work space and for mounting parts of the offshore facility to be constructed. It has sufficient mechanical strength to be used as a space.

図2に示すように、デッキ20は、メインデッキ部21、第1張り出し部22および第2張り出し部23を有している。図示した形態では、デッキ20は2つの第1張り出し部22および2つの第2張り出し部23を有しているが、第1張り出し部22の数および第2張り出し部23の数は任意であってよい。これらメインデッキ部21、第1張り出し部22および第2張り出し部23のうち、メインデッキ部21は上方から見て最も大きな面積を有する部分であり、脚柱10は、メインデッキ部21の外縁部に配置されている。よって、メインデッキ部21の上面の大部分を、作業スペースおよび建設する洋上設備の部品搭載用スペースとして利用することができる。洋上設備が洋上風力発電設備である場合、デッキ20は、例えば、洋上風力発電設備1基分の部品を搭載できるスペースを有することが好ましい。メインデッキ部21の平面形状は任意であってよい。 As shown in FIG. 2, the deck 20 has a main deck portion 21, a first projecting portion 22 and a second projecting portion . In the illustrated form, the deck 20 has two first lugs 22 and two second lugs 23, although the number of first lugs 22 and the number of second lugs 23 are arbitrary. good. Of the main deck portion 21, the first overhanging portion 22 and the second overhanging portion 23, the main deck portion 21 has the largest area when viewed from above. are placed in Therefore, most of the upper surface of the main deck section 21 can be used as a work space and a space for mounting parts of the offshore facility to be constructed. If the offshore facility is an offshore wind power generation facility, the deck 20 preferably has a space capable of mounting components for one offshore wind power generation facility, for example. The planar shape of the main deck portion 21 may be arbitrary.

第1張り出し部22は、上から見て、隣り合う2本の脚柱10を結ぶ辺に対してメインデッキ部21から凸状に張り出した形状とすることができる。また、第1張り出し部22の上面は、メインデッキ部21の上面と同一平面上にあるように構成することが好ましい。これにより、デッキ20の上面の作業スペースおよび部品搭載用スペースを実質的に拡大することができる。 The first projecting portion 22 can have a shape projecting from the main deck portion 21 with respect to the side connecting two adjacent pedestals 10 when viewed from above. In addition, it is preferable that the upper surface of the first projecting portion 22 and the upper surface of the main deck portion 21 are on the same plane. As a result, the work space and component mounting space on the upper surface of the deck 20 can be substantially enlarged.

第1張り出し部22にはクレーン30が搭載される。クレーン30は固定式であってもよいし、クローラ式であってもよい。ただし、作業は第1張り出し部22上で移動を伴わずに行うことが多いため、実質的には固定式のクレーン30で十分である。また、固定式のクレーン30は、クローラ式のクレーンと比べて、デッキ20上での占有面積も少なく、デッキ20上により大きいスペースを確保できるという点からも有利である。 A crane 30 is mounted on the first projecting portion 22 . The crane 30 may be of a stationary type or of a crawler type. However, since the work is often performed on the first projecting portion 22 without movement, the stationary crane 30 is substantially sufficient. The fixed type crane 30 is also advantageous in that it occupies a smaller area on the deck 20 than a crawler type crane and can secure a larger space on the deck 20 .

第1張り出し部22にクレーン30を搭載することで、クレーン30は、デッキ20を支持するすべての脚柱10(本形態では3本の脚柱10)で囲まれる領域の外側に位置することになる。 By mounting the crane 30 on the first overhang 22, the crane 30 is positioned outside the area surrounded by all the pedestals 10 (three pedestals 10 in this embodiment) that support the deck 20. Become.

このように、クレーン30を第1張り出し部22に搭載し、脚柱20で囲まれる領域の外側に位置させることで、図2に示すように、クレーン30の作業範囲θ1(クレーン30の旋回中心Oを中心とした回転範囲)を、180°を超える範囲まで拡大することができる。これに対し、図3に示すようにメインデッキ部21上にクレーン30を搭載した場合、通常、脚柱10はメインデッキ部21の隅部に配置されることから、クレーン30は、2本の脚柱10に挟まれた領域に位置することになる。そのため、クレーン30の作業範囲θ2は、180°未満となる。クレーン30の作業範囲が拡大することによって、クレーン30による作業の自由度を向上させることができる。 In this way, by mounting the crane 30 on the first overhang 22 and positioning it outside the area surrounded by the pedestal 20, as shown in FIG. range of rotation about O) can be extended to over 180°. On the other hand, when the crane 30 is mounted on the main deck portion 21 as shown in FIG. It will be located in the area sandwiched between the pedestals 10 . Therefore, the working range θ2 of the crane 30 is less than 180°. By expanding the work range of the crane 30, the degree of freedom of work by the crane 30 can be improved.

なお、デッキ20全体が浮体構造体として構成されていれば、第1張り出し部22自身は浮体構造体として構成されていてもよいし浮体構造体として構成されていなくてもよい。第1張り出し部22が浮体構造体として構成される場合、第1張り出し部22は、メインデッキ21と同様、第1張り出し部22に内部空間を形成する天壁、底壁および外周壁を有することができる。第1張り出し部22は、必要に応じてさらに隔壁を有していてもよい。 If the entire deck 20 is configured as a floating structure, the first projecting portion 22 itself may or may not be configured as a floating structure. When the first overhanging portion 22 is configured as a floating body structure, the first overhanging portion 22 should have a top wall, a bottom wall, and an outer peripheral wall that form an internal space in the first overhanging portion 22, like the main deck 21. can be done. The first overhanging portion 22 may further have a partition as necessary.

第2張り出し部22は、第1張り出し部22とは異なる位置にて、メインデッキ部21の幅員を超えない形状でメインデッキ21から張り出して形成されている。第2張り出し部22も第1張り出し部21と同様、上から見て、隣り合う2本の脚柱10を結ぶ辺に対してメインデッキ部21から凸状に張り出した形状とすることができる。また、第2張り出し部22は、浮体構造体として構成されている。したがって、第2張り出し部22は、メインデッキ部21と同様、第2張り出し部23に内部空間を形成する天壁、底壁および外周壁を有することができる。第2張り出し部23は、必要に応じて隔壁をさらに有していてもよい。 The second projecting portion 22 is formed to project from the main deck 21 at a position different from that of the first projecting portion 22 in a shape that does not exceed the width of the main deck portion 21 . As with the first projecting portion 21, the second projecting portion 22 can also have a shape projecting from the main deck portion 21 with respect to the side connecting two adjacent pedestals 10 when viewed from above. Also, the second projecting portion 22 is configured as a floating structure. Therefore, like the main deck portion 21, the second overhanging portion 22 can have a top wall, a bottom wall, and an outer peripheral wall that form an internal space in the second overhanging portion 23. As shown in FIG. The second projecting portion 23 may further have a partition wall as necessary.

メインデッキ部21に第2張り出し部23を付加することによって、デッキ20上のスペースが拡大され、それと同時に、洋上作業設備1の曳航中の安定性を向上させることができる。また、第2張り出し部23がメインデッキ部21の幅員を超えない形状であるので、曳航時に抵抗が大きくなることが抑制される。これにより、曳航速度の低下が抑制されるなど洋上作業設備1を効率よく曳航することができる。曳航時の抵抗をより抑制するためには、洋上作業設備1が図2Aに示す白抜き矢印方向に曳航されるように構成されるとき、第2張り出し部23を、メインデッキ部21と第2張り出し部23とを組み合わせた形状が、船首側から船尾側へ向かって幅が広がる船形となるような形状とすることが好ましい。 By adding the second overhang 23 to the main deck section 21, the space above the deck 20 is increased while at the same time improving the stability of the offshore work equipment 1 during towing. Further, since the second projecting portion 23 has a shape that does not exceed the width of the main deck portion 21, an increase in resistance during towing is suppressed. As a result, the offshore work equipment 1 can be towed efficiently, such as by suppressing a decrease in towing speed. In order to further suppress the resistance during towing, when the offshore work equipment 1 is configured to be towed in the direction of the white arrow shown in FIG. It is preferable that the shape combined with the overhanging portion 23 is a ship shape that widens from the bow side toward the stern side.

以上、デッキ20が単層構造である場合について説明したが、デッキ20は複層構造であってもよい。図4に、複層のデッキを有する洋上作業設備の概略側面図を示す。なお、図4に示す洋上作業設備についての以下の説明おいて、これまで説明した洋上作業設備と同様の構成については図1等と同じ符号を付し、それらの説明は省略する。 Although the case where the deck 20 has a single-layer structure has been described above, the deck 20 may have a multi-layer structure. FIG. 4 shows a schematic side view of an offshore work facility having multiple decks. In the following description of the offshore work equipment shown in FIG. 4, the same reference numerals as in FIG. 1 etc. are assigned to the same configurations as those of the offshore work equipment described so far, and the description thereof is omitted.

図4に示す洋上作業設備1では、デッキ20は、天壁20aの上方に天壁20aと間隔をあけて配置された第2天壁120aと、第2天壁120aを天壁20aと間隔をあけて支持する第2外周壁120cおよび第2隔壁(不図示)とを有し、これによってデッキ20は2層構造とされる。これら天壁20a、第2天壁120a、第2外周壁120cおよび第2隔壁によって、天壁20aの上方に配置された構造は、複数の区画に分けられた内部空間が形成された浮体構造体として構成される。よって、天壁20a上に第2天壁120a、第2外周壁120cおよび第2隔壁といった構造物を付加しても、デッキ20は、洋上作業設備を曳航できるようにするのに必要な浮力が確保される。 In the offshore work equipment 1 shown in FIG. 4, the deck 20 includes a second ceiling wall 120a arranged above the ceiling wall 20a with a gap from the ceiling wall 20a, and the second ceiling wall 120a with a gap from the ceiling wall 20a. It has a second peripheral wall 120c and a second partition wall (not shown) which are spaced and supported, whereby the deck 20 has a two-layer structure. The structure arranged above the ceiling wall 20a by the ceiling wall 20a, the second ceiling wall 120a, the second outer peripheral wall 120c, and the second partition is a floating structure in which an internal space divided into a plurality of sections is formed. configured as Therefore, even if the structures such as the second ceiling wall 120a, the second outer peripheral wall 120c and the second bulkhead are added on the ceiling wall 20a, the deck 20 still has the buoyancy necessary to allow the offshore work equipment to be towed. Secured.

第2天壁120aおよび第2外周壁120cは、メインデッキ部21(図2参照)、第1張り出し部22(図2参照)および第2張り出し部(図2参照)のうち少なくともメインデッキ部21に対応する位置に配置することができる。すなわち、デッキ20全体が2層構造とされる必要はない。ただし、デッキ20の上面を有効に利用できるようにするためには、メインデッキ部21、第1張り出し部22および第2張り出し部23のすべての領域が2層構造となるように第2天板120aおよび第2外周壁120cを配置することが好ましい。 The second ceiling wall 120a and the second outer peripheral wall 120c are at least the main deck portion 21 out of the main deck portion 21 (see FIG. 2), the first overhanging portion 22 (see FIG. 2), and the second overhanging portion (see FIG. 2). can be placed at a position corresponding to That is, the entire deck 20 does not need to have a two-layer structure. However, in order to make effective use of the upper surface of the deck 20, the second top plate must be installed so that all areas of the main deck portion 21, the first overhanging portion 22, and the second overhanging portion 23 have a two-layer structure. 120a and a second outer peripheral wall 120c are preferably provided.

このようにデッキ20を2層構造とすることで、デッキ20の機械的強度を向上させることができ、デッキ20上により重量物を搭載することができるようになる。その結果、洋上設備建設の施工ヤードから建設現場である海域までの部品の運搬に際して、より多くの、あるいはより重量のある部品の運搬に洋上作業設備を利用することができる。ここではデッキ20を2層構造とした場合について説明したが、デッキ20を3層以上で構成することもできる。 By forming the deck 20 into a two-layer structure in this manner, the mechanical strength of the deck 20 can be improved, and a heavier object can be mounted on the deck 20 . As a result, when transporting parts from a construction yard for construction of offshore equipment to the sea area where the construction site is, the offshore work equipment can be used to transport more or heavier parts. Although the case where the deck 20 has a two-layer structure has been described here, the deck 20 can also be configured with three or more layers.

次に、本形態の洋上作業設備1を用いた洋上設備の建設方法について、洋上設備が洋上風力発電設備である場合を例に挙げて説明する。 Next, a method for constructing an offshore facility using the offshore work facility 1 of the present embodiment will be described by taking as an example a case where the offshore facility is an offshore wind power generation facility.

まず、建設用の施工ヤードから建設現場である海域まで、洋上風力発電設備の風車部材など各種部品および洋上作業設備1を移動させる。洋上作業設備1の移動は、脚部10をデッキ20に対して上昇させ、デッキ20が海面上に浮かんた状態で洋上作業設備1を曳航用船舶で曳航することによって行う。この際、デッキ20上に、洋上風力発電設備の部品を搭載する。デッキ20が、洋上風力発電設備1基分の部品を搭載できるスペースを有し、かつ機械的強度を有していれば、洋上風力発電設備の部品の移動には、部品運搬用の船舶は必要ない。 First, various parts such as windmill members of the offshore wind power generation facility and offshore work equipment 1 are moved from the construction yard to the sea area where the construction site is located. The offshore work equipment 1 is moved by raising the legs 10 with respect to the deck 20 and towing the offshore work equipment 1 with a towing vessel while the deck 20 is floating on the sea surface. At this time, the components of the offshore wind power generation equipment are mounted on the deck 20 . If the deck 20 has a space for mounting the parts for one offshore wind power generation facility and has mechanical strength, a ship for transporting parts is necessary to move the parts of the offshore wind power generation facility. do not have.

洋上風力発電設備の部品および洋上作業設備1の移動が完了したら、洋上作業設備1の脚柱10をデッキ20に対して降下させ、脚柱10を海底に着底させる。このとき、図1に示すように、デッキ20が海面から離れて上方に位置するまで脚柱10を降下させる。これにより、海象条件の影響を受けずに洋上風力発電設備を建設することができる。 After completing the movement of the components of the offshore wind power generation facility and the offshore work equipment 1, the pedestal 10 of the offshore work equipment 1 is lowered with respect to the deck 20 so that the pedestal 10 touches the seabed. At this time, as shown in FIG. 1, the pedestal 10 is lowered until the deck 20 is above the sea surface. As a result, offshore wind power generation facilities can be constructed without being affected by sea conditions.

脚柱10を海底に着底させた後、デッキ20上の部品をクレーン30で吊り下げ、クレーン30による洋上風力発電設備の組み立てを行う。クレーン30は第1張り出し部22に搭載されており、クレーン30の作業範囲がより拡大されるので、スムーズな組み立てが可能である。 After landing the pedestal 10 on the seabed, the parts on the deck 20 are suspended by the crane 30, and the offshore wind power generation equipment is assembled by the crane 30. - 特許庁Since the crane 30 is mounted on the first projecting portion 22 and the working range of the crane 30 is further expanded, smooth assembly is possible.

洋上風力発電設備の組み立て後、再び脚柱10をデッキ20に対して上昇させ、曳航用船舶によって洋上作業設備1を施工ヤードに帰還させる。 After assembling the offshore wind power generation equipment, the pedestal 10 is raised again with respect to the deck 20, and the offshore work equipment 1 is returned to the construction yard by a towing vessel.

複数の洋上作業設備1を接続して、洋上設備の部品の荷役や組み立てのための、洋上設備建設用施工ヤードとして利用することもできる。図5に、複数の洋上作業設備1を利用した施工ヤードの平面図を示す。 A plurality of offshore work facilities 1 can be connected and used as a construction yard for construction of offshore facilities for cargo handling and assembly of parts of offshore facilities. FIG. 5 shows a plan view of a construction yard using a plurality of offshore work facilities 1. As shown in FIG.

図5に示す施工ヤードは、デッキ20上で洋上設備の部品の荷役や組み立て行うことができるように、3基の洋上作業設備1を接続したものである。クレーン30が第1張り出し部22に搭載されているので、より広いデッキスペースを確保できる。また、クレーン30が互い違いに位置するように洋上作業設備1を配置することで、同時に複数のクレーン30を動作させた場合であっても互いに干渉することが抑制される。 The construction yard shown in FIG. 5 connects three offshore work facilities 1 so that parts of offshore facilities can be handled and assembled on a deck 20 . Since the crane 30 is mounted on the first projecting portion 22, a wider deck space can be secured. Further, by arranging the offshore work equipment 1 so that the cranes 30 are staggered, mutual interference is suppressed even when a plurality of cranes 30 are operated at the same time.

施工ヤードは、プロジェクトごとに設置することができる。洋上作業設備1を施工ヤードとして利用することで、ヤード作業が終了したら、そのまま洋上作業設備1を洋上設備の建設海域に移動させ、洋上設備の建設を行うことができる。施工ヤードは、恒久設備として使用することもできる。このように、洋上作業設備1を施工ヤードとして利用することにより、洋上設備用の港湾設備の代用となり、施工ヤードを低コストでかつ短期に設置することができる。 A construction yard can be set up for each project. By using the offshore work equipment 1 as a construction yard, when the yard work is completed, the offshore work equipment 1 can be moved to the construction sea area of the offshore equipment, and the offshore equipment can be constructed. Construction yards can also be used as permanent installations. By using the offshore work equipment 1 as a construction yard in this way, it can be used as a substitute for harbor equipment for offshore equipment, and a construction yard can be installed at low cost in a short period of time.

以上、本発明について代表的な実施形態を例に挙げて説明した。本発明による洋上作業設備1は、メインデッキ部21および脚柱10を有する、自己昇降式作業台船あるいはジャッキアップ式掘削リグといった既存の洋上作業設備に対し、第1張り出し部21およびクレーン30を付加し、また必要に応じてさらに第2張り出し部23を付加することによって構成することができる。「既存の洋上作業設備」とは、その洋上作業設備の目的とする機能を有するように既に組み立てられて存在している洋上作業設備の意味であり、本形態による洋上作業設備1は、そのような洋上作業設備を改造して構成することができる。 The present invention has been described above with reference to typical embodiments. The offshore work equipment 1 according to the present invention is an existing offshore work equipment such as a self-elevating work barge or a jack-up drilling rig, which has a main deck portion 21 and a pedestal 10, by replacing the first overhang portion 21 and the crane 30. It can be configured by adding a second projecting portion 23 as necessary. "Existing offshore work equipment" means offshore work equipment that has already been assembled so as to have the intended function of the offshore work equipment, and the offshore work equipment 1 according to this embodiment is such a work equipment. It can be configured by modifying the offshore work equipment.

一般に、自己昇降式作業台船およびジャッキアップ式掘削リグ等の従来の洋上作業設備は、自己昇降式の脚柱、および脚柱に対して昇降可能に支持されたプラットフォーム(上述した本形態の洋上作業設備1におけるメインデッキ部21に相当する)を有する。 In general, conventional offshore work equipment such as self-elevating work barges and jack-up drilling rigs are equipped with self-elevating pedestals and platforms that are supported so as to be able to go up and down on the pedestals. corresponding to the main deck portion 21 in the work equipment 1).

そこで、既存の洋上作業設備を利用(改造)して本発明による洋上作業設備を構成することで、既存の洋上作業設備の構造の脚柱およびプラットフォームを利用してそれぞれ脚柱10およびメインデッキ部21を構成することができる。それにより、より簡便にかつ短い工期で洋上作業設備を得ることができ、結果的に、洋上作業設備の大幅なコストダウンが達成される。特に、既存のジャッキアップ式掘削リグを利用して洋上作業設備1を構成することにより、水深が90mを超える海域での洋上施工時に脚柱を着底させることにより波による影響を受けず安定して施工を行うことのできる洋上作業設備をより簡便にかつ短い工期で得ることができる。 Therefore, by utilizing (modifying) the existing offshore work equipment to configure the offshore work equipment according to the present invention, the pedestal and the platform of the structure of the existing offshore work equipment are used, respectively, and the pedestal 10 and the main deck section 21 can be configured. As a result, the offshore work equipment can be obtained more easily and in a shorter construction period, and as a result, a significant cost reduction of the offshore work equipment is achieved. In particular, by configuring the offshore work equipment 1 using an existing jack-up type drilling rig, it is stable without being affected by waves by allowing the pedestals to reach the bottom during offshore construction in water depths exceeding 90m. It is possible to obtain an offshore work facility that can be constructed in a simple manner and in a short construction period.

また、ジャッキアップ式掘削リグは、洋上で着底した状態で石油や天然ガスの掘削作業を行えるよう、船上掘削設備を有している。船上掘削設備は、プラットフォーム上に設置されたカンチレバーに搭載されている。ただし、カンチレバーは駆動機構によってプラットフォーム上を移動し、プラットフォームから乗り出した位置で掘削作業をする。そのような、駆動機構および船上掘削設備も含めたカンチレバー全体の荷重を支持するため、プラットフォームは、必要な強度を有する隔壁等の強度部材を支持構造として内部に持っている。 In addition, the jack-up drilling rig has on-board drilling equipment so that the drilling operation for oil and natural gas can be performed while the drilling rig is grounded on the sea. The shipboard drilling equipment is mounted on a cantilever installed on the platform. However, the cantilever is moved on the platform by a driving mechanism, and performs excavation work at a position where it leans out from the platform. In order to support the entire cantilever load, including the drive mechanism and onboard drilling equipment, the platform has internal strength members, such as bulkheads, having the necessary strength as support structures.

本形態はこの点に着目し、第1張り出し部22を構成するに際して、既存のジャッキアップ式掘削リグが有しているカンチレバーの支持構造を利用している。すなわち、第1張り出し部22は、カンチレバーの支持構造によって支持されて、メインデッキ部21から張り出している。ここで、「カンチレバーの支持構造」とは、上述した、駆動機構および船上掘削設備も含めたカンチレバー全体の荷重を支持するためにプラットフォームが有している支持構造であり、具体的には、カンチレバー全体を支持するのに必要な強度を有する強度部材、例えば隔壁である。このように、ジャッキアップ式掘削リグに元々存在している支持構造を利用することで、例えば洋上風力発電設備のナセルなどの重量構造物を楊重可能なクレーン30を搭載するのに十分な機械的強度を有する第1張り出し部22を、新たに強度部材を追加することなく、元々存在している強度部材に合わせてより簡単に追加することができる。結果的に、洋上作業設備の大幅なコストダウンが達成される。 Focusing on this point, the present embodiment utilizes a cantilever support structure of an existing jack-up type excavation rig when constructing the first projecting portion 22 . That is, the first protruding portion 22 protrudes from the main deck portion 21 while being supported by the cantilever support structure. Here, the "support structure of the cantilever" is a support structure that the platform has for supporting the load of the entire cantilever including the driving mechanism and the onboard drilling equipment described above. A strength member, such as a partition wall, having the strength necessary to support the whole. Thus, by utilizing the support structure originally present in the jack-up drilling rig, there is sufficient machinery to mount the crane 30 capable of lifting a heavy structure such as the nacelle of an offshore wind farm. The first protruding portion 22 having a sufficient strength can be added more easily according to the originally existing strength members without adding a new strength member. As a result, a significant cost reduction of offshore work equipment is achieved.

なお、上述のようにジャッキアップ式掘削リグのカンチレバーの支持構造を利用して第1張り出し部22を構成する場合、ジャッキアップ式掘削リグのカンチレバーおよび船上掘削設備が撤去されて、カンチレバーの支持構造上に第1張り出し部22が構成され、その上にクレーン30が搭載される。したがって、洋上作業設備1は、もはや掘削リグとしては機能しない。 When the first overhang portion 22 is configured using the cantilever support structure of the jack-up drilling rig as described above, the cantilever and the onboard drilling equipment of the jack-up drilling rig are removed and the cantilever support structure is used. A first projecting portion 22 is configured on top, and a crane 30 is mounted thereon. Therefore, the offshore work facility 1 no longer functions as a drilling rig.

また、デッキ20の機械的強度を向上させるためにデッキ20を複層構造とする場合、既存の天壁をより高い機械的強度を有する天壁と交換することが一般的に考えられる。しかし、通常、天壁の下面には電気配線や給排水管などさまざまな構造物が取り付けられている。したがって、天壁を交換する場合はこれらの構造物も一緒に交換する必要がある。そこで、図4に示したように、天壁20aをそのまま残してその上方に第2天壁120aを配置するようにしたことで、既存の電気配線および給排水管などを活用することができ、その結果、洋上作業設備1の建造工期を短縮するとともに、建造コストの上昇を抑制することができる。 Further, when the deck 20 has a multi-layer structure in order to improve the mechanical strength of the deck 20, it is generally considered to replace the existing ceiling wall with a ceiling wall having higher mechanical strength. However, various structures such as electrical wiring and water supply and drainage pipes are usually attached to the underside of the ceiling wall. Therefore, when replacing the ceiling wall, it is necessary to replace these structures together. Therefore, as shown in FIG. 4, by leaving the ceiling wall 20a as it is and placing the second ceiling wall 120a above it, it is possible to utilize the existing electrical wiring and water supply and drainage pipes. As a result, it is possible to shorten the construction period of the offshore work equipment 1 and suppress the increase in construction cost.

1 洋上作業設備
10 脚柱
20 デッキ
20a 天壁
20b 底壁
20c 外周壁
20d 隔壁
21 メインデッキ部
22 第1張り出し部
23 第2張り出し部
30 クレーン
120a 第2天壁
120c 第2外周壁
1 offshore work equipment 10 pedestal 20 deck 20a ceiling wall 20b bottom wall 20c outer peripheral wall 20d bulkhead 21 main deck portion 22 first overhanging portion 23 second overhanging portion 30 crane 120a second ceiling wall 120c second outer peripheral wall

Claims (7)

3本以上の脚柱と、 浮体構造物として構成され、前記脚柱に対して昇降可能に支持されたデッキと、前記デッキに搭載されたクレーンと、を有し、前記デッキは、前記脚柱が配置されるメインデッキ部を有する洋上作業設備であって、
前記脚と前記メインデッキ部とを有し、掘削設備および前記掘削設備を搭載するためのカンチレバーが撤去されたジャッキアップ式掘削リグと、
前記メインデッキ部から張り出して前記メインデッキ部に付加された張り出し部と、
を有し、
前記デッキは、前記脚柱が配置されるメインデッキ部と、前記張り出し部と、を有し、
前記クレーンは前記張り出し部に搭載され、かつ、
前記張り出し部は、前記カンチレバーの支持構造を利用して、前記張り出し部の上面が前記メインデッキ部の上面と同一平面上にあるように前記メインデッキ部に付加されている洋上作業設備。
a deck configured as a floating structure and supported so as to be able to move up and down with respect to the pedestals; and a crane mounted on the deck, wherein the deck comprises the pedestals. An offshore work facility having a main deck on which
a jack-up drilling rig having the pedestal and the main deck portion, from which drilling equipment and a cantilever for mounting the drilling equipment have been removed;
a projecting portion projecting from the main deck portion and added to the main deck portion;
has
The deck has a main deck section on which the pedestal is arranged and the overhang section,
the crane is mounted on the overhang, and
The offshore work facility, wherein the overhang is attached to the main deck so that the upper surface of the overhang is flush with the upper surface of the main deck using the support structure of the cantilever.
前記デッキは、浮体構造体として構成された第2張り出し部をさらに有する請求項1に記載の洋上作業設備。 2. The offshore work equipment of claim 1, wherein said deck further comprises a second overhang configured as a floating structure. 前記第2張り出し部は、前記メインデッキ部の幅員を超えない形状で前記メインデッキ部から張り出して形成されている請求項2に記載の洋上作業設備。 3. The offshore work facility according to claim 2, wherein the second overhanging portion is formed so as to overhang from the main deck portion in a shape that does not exceed the width of the main deck portion. 前記第2張り出し部は、前記メインデッキ部と組み合わせた形状が、船首側から船尾側へ向かう方向に幅が広がる船形となるような形状で前記メインデッキ部から張り出して形成されている請求項2または3に記載の洋上作業設備。 2. The second protruding portion is formed to protrude from the main deck portion in such a shape that the shape combined with the main deck portion forms a ship shape that widens in the direction from the bow side to the stern side. Or the offshore work facility according to 3. 前記デッキは、天壁、底壁、外周壁および隔壁を有し、前記天壁、前記底壁および前記外周壁によって前記デッキに内部空間が形成され、前記隔壁によって前記内部空間が複数の区画に分けられる請求項1から4のいずれか一項に記載の洋上作業設備。 The deck has a top wall, a bottom wall, an outer peripheral wall, and a partition wall. An internal space is formed in the deck by the top wall, the bottom wall, and the outer peripheral wall, and the internal space is divided into a plurality of sections by the partition walls. 5. Offshore work equipment according to any one of claims 1 to 4, which is divided. 前記天壁の上方に配置された第2天壁と、前記第2天壁を前記天壁と間隔をあけて支持する第2外周壁および第2隔壁とをさらに有する請求項5に記載の洋上作業設備。 6. The ocean according to claim 5, further comprising: a second ceiling wall arranged above the ceiling wall; and a second outer peripheral wall and a second partition supporting the second ceiling wall with a space between the ceiling wall and the ceiling wall. work equipment. 洋上作業設備の製造方法であって、
3本以上の脚柱、前記脚柱が配置され、前記脚柱に対して昇降可能に支持されたメインデッキ部、前記メインデッキ部に支持構造を介して支持されたカンチレバーおよび前記カンチレバーに配置された掘削設備を有するジャッキアップ式掘削リグを用意すること、
前記ジャッキアップ式掘削リグから、前記カンチレバーおよび前記掘削設備を撤去すること、
前記メインデッキ部から張り出して形成された張り出し部を、前記支持構造を利用して前記メインデッキ部に付加すること、および
前記張り出し部にクレーンを搭載することを含む、洋上作業設備の製造方法。
A method for manufacturing offshore work equipment,
three or more pedestals, a main deck portion on which the pedestals are arranged and supported so as to be able to move up and down with respect to the pedestals, a cantilever supported by the main deck portion via a support structure, and a cantilever arranged on the cantilever providing a jack-up drilling rig with drilling equipment;
removing the cantilever and the drilling equipment from the jack-up drilling rig;
A method of manufacturing offshore work equipment, comprising: attaching an overhang formed from the main deck to the main deck using the support structure; and mounting a crane on the overhang.
JP2020506597A 2018-03-14 2019-03-13 Offshore work equipment and its manufacturing method Active JP7126111B2 (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
JP2022119402A JP7464658B2 (en) 2018-03-14 2022-07-27 Offshore work equipment and manufacturing method thereof

Applications Claiming Priority (3)

Application Number Priority Date Filing Date Title
JP2018046848 2018-03-14
JP2018046848 2018-03-14
PCT/JP2019/010235 WO2019177010A1 (en) 2018-03-14 2019-03-13 Offshore working facility and construction method thereof

Related Child Applications (1)

Application Number Title Priority Date Filing Date
JP2022119402A Division JP7464658B2 (en) 2018-03-14 2022-07-27 Offshore work equipment and manufacturing method thereof

Publications (2)

Publication Number Publication Date
JPWO2019177010A1 JPWO2019177010A1 (en) 2021-03-11
JP7126111B2 true JP7126111B2 (en) 2022-08-26

Family

ID=67907176

Family Applications (2)

Application Number Title Priority Date Filing Date
JP2020506597A Active JP7126111B2 (en) 2018-03-14 2019-03-13 Offshore work equipment and its manufacturing method
JP2022119402A Active JP7464658B2 (en) 2018-03-14 2022-07-27 Offshore work equipment and manufacturing method thereof

Family Applications After (1)

Application Number Title Priority Date Filing Date
JP2022119402A Active JP7464658B2 (en) 2018-03-14 2022-07-27 Offshore work equipment and manufacturing method thereof

Country Status (6)

Country Link
JP (2) JP7126111B2 (en)
KR (2) KR102449636B1 (en)
CN (1) CN112119006B (en)
SG (1) SG11202009003XA (en)
TW (1) TWI745662B (en)
WO (1) WO2019177010A1 (en)

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
US11518977B2 (en) 2014-01-31 2022-12-06 AgBiome, Inc. Modified biological control agents and their uses
JP7464658B2 (en) 2018-03-14 2024-04-09 株式会社 吉田組 Offshore work equipment and manufacturing method thereof

Citations (7)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP2004001750A (en) 2003-06-25 2004-01-08 Penta Ocean Constr Co Ltd Special working ship and execution method for offshore structure
JP2009511347A (en) 2005-10-14 2009-03-19 ナショナル ユニバーシティ オブ シンガポール Pontoon type floating structure
US20100186653A1 (en) 2009-01-29 2010-07-29 Friede & Goldman, Ltd. Extended-deck jack-up
WO2010085970A1 (en) 2009-01-27 2010-08-05 Statoil Asa Mobile offshore platform
WO2012144952A1 (en) 2011-04-19 2012-10-26 Primepoint Pte Ltd A multi-functional jack up system for decommissioning an offshore platform
CN104554625A (en) 2013-10-11 2015-04-29 烟台中集来福士海洋工程有限公司 Revolving crane ship renovation method based on unmanned barge and crane barge
CN106347595A (en) 2016-09-30 2017-01-25 南通中远船务工程有限公司 Cylinder type maritime work platform

Family Cites Families (10)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
WO2013133694A1 (en) * 2012-03-06 2013-09-12 Itrec B.V. An offshore system comprising a rig and a cantilever
JP2015037925A (en) 2013-07-18 2015-02-26 半蔵 門脇 Self-elevating working barge
KR20150093392A (en) * 2014-02-07 2015-08-18 대우조선해양 주식회사 Derrick module and drilling unit with the same
KR20150107257A (en) * 2014-03-13 2015-09-23 대우조선해양 주식회사 Telescopic Type Retractable Leg For Jack Up Rig
KR20160035738A (en) * 2014-09-24 2016-04-01 삼성중공업 주식회사 Floating structure
KR102154142B1 (en) * 2014-10-24 2020-09-09 대우조선해양 주식회사 Cantilever structure of the self-elevationg drilling rig possible ragng expansion
JP2016215937A (en) 2015-05-25 2016-12-22 鹿島建設株式会社 Self-elevation type work bench device
KR20160150431A (en) * 2015-06-22 2016-12-30 권순일 Semi-submersible platform with a built-in wind and ocean current and tidal power generation equipment
CN106005293A (en) * 2016-06-13 2016-10-12 太重(天津)滨海重型机械有限公司 Notch cantilevered type self elevating type drilling platform
SG11202009003XA (en) 2018-03-14 2020-10-29 Yoshida Gumi Co Ltd Offshore work equipment and method for constructing thereof

Patent Citations (7)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP2004001750A (en) 2003-06-25 2004-01-08 Penta Ocean Constr Co Ltd Special working ship and execution method for offshore structure
JP2009511347A (en) 2005-10-14 2009-03-19 ナショナル ユニバーシティ オブ シンガポール Pontoon type floating structure
WO2010085970A1 (en) 2009-01-27 2010-08-05 Statoil Asa Mobile offshore platform
US20100186653A1 (en) 2009-01-29 2010-07-29 Friede & Goldman, Ltd. Extended-deck jack-up
WO2012144952A1 (en) 2011-04-19 2012-10-26 Primepoint Pte Ltd A multi-functional jack up system for decommissioning an offshore platform
CN104554625A (en) 2013-10-11 2015-04-29 烟台中集来福士海洋工程有限公司 Revolving crane ship renovation method based on unmanned barge and crane barge
CN106347595A (en) 2016-09-30 2017-01-25 南通中远船务工程有限公司 Cylinder type maritime work platform

Non-Patent Citations (3)

* Cited by examiner, † Cited by third party
Title
"R-550D Jack-up Drilling Rig",米国,ZENTECH INCORPORATED,2014年04月29日,zentech-usa.com/wp-content/uploads/2014/09/Zentech-Jackup-Rig-Design-R-550D.pdf
"R-550D",中国,TSC Group,2017年10月27日,http://www.t-s-c.com/products-services/rig-integrated-solutions/jack-up-rig-solutions-1/case-studies-1/
河内紀雄,"カンチレバー型ジャッキアップバージ第六白竜の構想について",石油技術協会誌,日本,石油技術協会,1978年,43巻 5号,p.308-316,DOI: 10.3720/japt.43.308,ISSN 1881-4131(online),0370-9868(print)

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
US11518977B2 (en) 2014-01-31 2022-12-06 AgBiome, Inc. Modified biological control agents and their uses
JP7464658B2 (en) 2018-03-14 2024-04-09 株式会社 吉田組 Offshore work equipment and manufacturing method thereof

Also Published As

Publication number Publication date
KR20200128723A (en) 2020-11-16
WO2019177010A1 (en) 2019-09-19
SG11202009003XA (en) 2020-10-29
CN112119006A (en) 2020-12-22
JP2022160521A (en) 2022-10-19
JPWO2019177010A1 (en) 2021-03-11
TWI745662B (en) 2021-11-11
KR102449636B1 (en) 2022-09-29
CN112119006B (en) 2023-03-24
TW201938453A (en) 2019-10-01
JP7464658B2 (en) 2024-04-09
KR102607972B1 (en) 2023-11-29
KR20220133334A (en) 2022-10-04

Similar Documents

Publication Publication Date Title
JP7464658B2 (en) Offshore work equipment and manufacturing method thereof
KR101201959B1 (en) Extensible semi-submersible platform
US8025020B2 (en) Auxiliary float of floating structure and method for remodeling floating structure
JP5189050B2 (en) Connecting self-elevating work platform ship and installation method of wind power generation facilities in the open ocean
KR101865164B1 (en) Separable type offshore structures installation vessels and method of operating the same
KR101422227B1 (en) Floating structure
WO2017058098A1 (en) A mobile docking apparatus and method of operating thereof
CA2892028C (en) Structure-supported jackup system
KR20140035658A (en) Leg system for offshore vessel
KR20200057537A (en) Floating vessel for wind turbine installation, wind turbine installation system including same and wind turbine installation method
KR101814623B1 (en) Floating structure and method for installing offshore wind turbines using the same
KR20130143363A (en) Floating structure
KR102071010B1 (en) construction method of Semi-submissible type platform
KR101947670B1 (en) Floating structure
JPS61222892A (en) Semisubmersible type floating structure and construction method thereof
KR101616826B1 (en) Floating structure comprising mooring device
DK3255211T3 (en) Jack-bridge structure
KR20130065024A (en) Floating dock and manufacturing method for shorestructure using the same
KR101690966B1 (en) Method for installing leg of marine structure
WO2023167816A1 (en) Method of assembling floating offshore wind vessels using a mobile offshore assembly facility
KR20170030200A (en) Offshore structure installation vessel
KR101845426B1 (en) Floating structure
KR20240010995A (en) Floating structure
KR20240004955A (en) Systems and methods for rack structures for transport vessels configured for use with offshore self-elevating vessels
KR20160050701A (en) Method for manufacturing jack-up platform

Legal Events

Date Code Title Description
A621 Written request for application examination

Free format text: JAPANESE INTERMEDIATE CODE: A621

Effective date: 20200911

A131 Notification of reasons for refusal

Free format text: JAPANESE INTERMEDIATE CODE: A131

Effective date: 20211109

A521 Request for written amendment filed

Free format text: JAPANESE INTERMEDIATE CODE: A523

Effective date: 20211227

A131 Notification of reasons for refusal

Free format text: JAPANESE INTERMEDIATE CODE: A131

Effective date: 20220301

A521 Request for written amendment filed

Free format text: JAPANESE INTERMEDIATE CODE: A523

Effective date: 20220325

TRDD Decision of grant or rejection written
A01 Written decision to grant a patent or to grant a registration (utility model)

Free format text: JAPANESE INTERMEDIATE CODE: A01

Effective date: 20220628

A61 First payment of annual fees (during grant procedure)

Free format text: JAPANESE INTERMEDIATE CODE: A61

Effective date: 20220728

R150 Certificate of patent or registration of utility model

Ref document number: 7126111

Country of ref document: JP

Free format text: JAPANESE INTERMEDIATE CODE: R150

S111 Request for change of ownership or part of ownership

Free format text: JAPANESE INTERMEDIATE CODE: R313117

R350 Written notification of registration of transfer

Free format text: JAPANESE INTERMEDIATE CODE: R350